CN201411926Y CN2009203042142U CN200920304214U CN201411926Y CN 201411926 Y CN201411926 Y CN 201411926Y CN 2009203042142 U CN2009203042142 U CN 2009203042142U CN 200920304214 U CN200920304214 U CN 200920304214U CN 201411926 Y CN201411926 Y CN 201411926Y
Authority
CN
China
Prior art keywords
factory building
arc beam
arc
lifting
workshop
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2009203042142U
Other languages
Chinese (zh)
Inventor
胡伟山
曾祥勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 19th Metallurgical Corp
Original Assignee
MCC Shijiu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by MCC Shijiu Construction Co Ltd filed Critical MCC Shijiu Construction Co Ltd
Priority to CN2009203042142U priority Critical patent/CN201411926Y/en
Application granted granted Critical
Publication of CN201411926Y publication Critical patent/CN201411926Y/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses an arc beam hoisting structure which is used for dismounting and mounting the large-scale crane in the old workshop. The hoisting structure is locate in the workshop. The workshop includes multiple pairs of workshop roof trusses which are arranged at intervals and supported by the workshop upright column, wherein at least a pair of workshop upright columns are mounted with the arc beam in a mode of simple strut-beams; and the arc beam is provided with a hanger. Compared with the hoisting device of a tower crane, the hoisting structure formed by the arc beam or its combined structure adapts to local conditions, saves the cost and operation time, has high safety and small operation area. The process of constructing the arc beam hoisting structure does not influence the normal production in other areas, therefore, the arc beam hoisting structure has strong practicability and pertinence and is especially suitable as the hoisting structure for dismounting and mounting the large-scale hoisting device in the old workshop.

Description

Arc beam lifting structure
Technical field
The utility model relates to a kind of lifting structure that large-scale crane in the old factory building is carried out dismounting, especially a kind of arc beam lifting structure.
Background technology
At present, domestic when in new factory building, the large-scale bridge type crane gear being installed, mainly be to utilize large-tonnage mobile job crane tool or tower crane lifting to put in place.Large-scale bridge type crane gear in the old factory building is dismantled, when installing, also mainly considered to utilize large-tonnage mobile job crane tool or tower crane lifting to put in place.But, when effects limit such as place, produced on-site situations mobile job crane tool or tower crane march into the arena or when using, directly lift with regard to unrenewable mobile job crane tool or tower crane, at this moment, can only realize dismounting and installation with other lifting structure to large-scale bridge type crane gear in the old factory building.Common in this case lifting structure is exactly: the house roof truss that utilizes old factory building is as spandrel girder, and equipped suitable suspender carries out lifting operation.Yet, for large-tonnage overhead traveling crane equipment, its deadweight is bigger, generally reach 30~40 tons even bigger, this moment, above-mentioned structure just seemed powerless, at this moment, generally be selected near the mode that heavy tower crane is set the factory building, but this kind mode engineering time is long, the construction cost height, and can interfere ordinary production operation in the factory building.
The utility model content
For overcome existing lifting structure can not the compliance factory building in the deficiency of large-scale crane dismounting, technical problem to be solved in the utility model provides a kind of arc beam lifting structure that can be used in large-scale crane dismounting in the old factory building.
The technical scheme that its technical problem that solves the utility model adopts is: arc beam lifting structure, described lifting structure is positioned at factory building, factory building comprises by many factory building roof trusses to the factory building upright supports that is provided with along factory building longitudinal separation, wherein with the simply supported beam form arc beam is installed at least one pair of factory building column, the arc beam is provided with suspender.
The beneficial effects of the utility model are: form lifting structure with arc beam or its combining structure, with tower crane be set compare as crane gear, suit measures to local conditions, it is good to provide cost savings with activity duration, safety, simultaneously, the operation area is little, does not influence the ordinary production operation in other each district in the factory building in constructing arc beam lifting structure process of the present utility model, have very strong practicality and specific aim, be particularly suitable for dismounting, installation lifting structure as large-scale lifting appliance in the old factory building.
Description of drawings
Fig. 1 is a schematic diagram of the present utility model.
Be labeled as among the figure, factory building roof truss 1, factory building column 2, arc beam 3, auxilliary beam 4, lifting longeron 5, suspender 6, large-scale crane 7, intercolumniation support 8, factory building are reinforced column 9.
The specific embodiment
Below in conjunction with drawings and Examples the utility model is further specified.
As shown in Figure 1, arc beam lifting structure of the present utility model, described lifting structure is positioned at factory building, factory building comprises the factory building roof truss 1 that the factory building column 2 that is provided with along factory building longitudinal separation is supported by many, wherein with the simply supported beam form arc beam 3 is installed at least one pair of factory building column 2, arc beam 3 is provided with suspender 6.Each is meant at the same laterally two relative factory building columns 2 of factory building of striding factory building column 2.
Utilize the arc beam of making separately as the lifting spandrel girder, utilize factory building roof truss 1 as the lifting spandrel girder, its supporting power increases greatly, the lifting capacity that allows is big, simultaneously, adopt arc beam form can obtain higher sling height, thereby arc beam lifting structure of the present utility model can be used for the dismounting or the installation of large-scale lifting appliance in the factory building, its lifting capacity is all bigger when generally needing to use this structure, and therefore described arc beam is generally selected the structural shape of box-girder.In case of necessity, if lifting capacity is very big, also the factory building column of reply support arc beam is reinforced, to guarantee safety.
When the bigger lifting capacity of needs, during higher lifting height, can further select to have the lifting structure of two arc beams 3, the adjacent two pairs of factory building columns 2 of this appropriate to the occasion selection support two arc beams 3, a pair of auxilliary beam 4 is set on two arc beams 3, to assisting the lifting longeron 5 that suspender 6 is installed is set on the beam 4 at this, promptly adopt the multi-layer combined type lifting structure that comprises arc beam 3, at this moment, it is unfavorable for load and the auxilliary beam material of waste if select 2 on non-conterminous two pairs of factory building columns, system becomes bad scheme, and described suspender 6 is complementary with the weight of equipment to be lifted, and considers certain safety factor.
At this moment, can also reinforce column 9, reinforce column 9 by factory building column 2 and factory building and come together support arc beam 3, to guarantee safety at the described every factory building column 2 adjacent factory buildings that are provided with.
In the said structure, in described two pairs of factory building columns 2, the intercolumniation that can be provided with truss-like along factory building longitudinally between two factory building columns 2 in case of necessity supports 8, to reinforce whole lifting structure, ensures safety.
In the said structure, described lifting longeron 5 should be arranged on the midpoint of auxilliary beam 4, and is stressed more even.
In the said structure, described arc beam 3 is considered the stressed less of factory building roof truss if deadweight is bigger, can adopt the method that assembly unit is shaped behind the sectional making to make arc beam 3.
For this reason, can be erected with arc beam assembly platform on described factory building roof truss 1, the handled easily personnel are spliced each section arc beam, and described assembly platform can adopt checkered plates or plank, bamboo clappers etc. to build, and assembly platform should be provided with the security protection facility.
For this reason, arc beam lifting structure can be set on described factory building roof truss 1, arc beam lifting structure can adopt hoisting machine to cooperate realization liftings such as assembly pulley, is used for assembly unit arc beam 3.
Embodiment:
Weigh in the old factory building to certain large enterprise and use arc beam lifting structure of the present utility model when 46 tons large-scale crane is dismantled with installation exercise.Its key operation process comprises: treat that the crane gear relevant parameter is (long, wide, sling height, weight etc.) appraise and decide → job site mapping (determine select for use factory building column) → the on-site hoisting ability appraises and decides → makeshift device design → construction suspender prepares → in case of necessity the factory building roof truss reinforce → be provided with factory building column suspension centre → be provided with in case of necessity factory building and reinforce column → be provided with the in case of necessity intercolumniation between adjacent two pairs of factory building columns and support → arc beam lifting structure → setting up arc beam assembly platform → arc beam sectional making on the factory building roof truss and lifting are being set on the factory building roof truss put in place → assembly unit of each section arc beam connects → building auxilliary beam assembly platform → the be provided with auxilliary beam of auxilliary beam suspension centre → lifting and is being connected → lifts to lift by crane longeron and be connected with auxilliary beam → lifting by crane with the arc beam and be provided with on the longeron that hoisting sling → lifting need be dismantled or the large-scale crane of installation on the arc beam.
To those skilled in the art, as long as above-mentioned structure has been arranged, the structure design of arc beam, auxilliary beam, lifting longeron, hoisting sling selection and lifting safety checking computations all are conventional.

Claims (7)

1. arc beam lifting structure, it is characterized in that: described lifting structure is positioned at factory building, factory building comprises the factory building roof truss (1) that the factory building column (2) that is provided with along factory building longitudinal separation is supported by many, wherein at least one pair of factory building column (2) is gone up and with the simply supported beam form arc beam (3) is installed, and arc beam (3) is provided with suspender (6).
2. arc beam lifting structure as claimed in claim 1, it is characterized in that: described factory building column (2) comprises adjacent two couple, two arc beams (3) are separately positioned on these two pairs of factory building columns (2), two arc beams (3) are provided with a pair of auxilliary beam (4), this is provided with lifting longeron (5) to auxilliary beam (4), on lifting longeron (5) suspender (6) is installed.
3. arc beam lifting structure as claimed in claim 2 is characterized in that: the adjacent factory building that is provided with of described every factory building column (2) is reinforced column (9), and factory building column (2) and factory building are reinforced column (9) together support arc beam (3).
4. as claim 2 or 3 described arc beam lifting structures, it is characterized in that: in described two pairs of factory building columns (2), the intercolumniation that respectively is provided with truss-like along factory building longitudinally between two factory building columns (2) supports (8).
5. as claim 2 or 3 described arc beam lifting structures, it is characterized in that: described lifting longeron (5) is arranged on the midpoint of auxilliary beam (4).
6. as claim 1,2 or 3 described arc beam lifting structures, it is characterized in that: assembly unit is shaped behind described arc beam (3) sectional making.
7. arc beam lifting structure as claimed in claim 5 is characterized in that: be erected with arc beam assembly platform on the described factory building roof truss (1).
CN2009203042142U 2009-06-10 2009-06-10 Arc beam hoisting structure Expired - Lifetime CN201411926Y (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009203042142U CN201411926Y (en) 2009-06-10 2009-06-10 Arc beam hoisting structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009203042142U CN201411926Y (en) 2009-06-10 2009-06-10 Arc beam hoisting structure

Publications (1)

Publication Number Publication Date
CN201411926Y true CN201411926Y (en) 2010-02-24

Family

ID=41713813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009203042142U Expired - Lifetime CN201411926Y (en) 2009-06-10 2009-06-10 Arc beam hoisting structure

Country Status (1)

Country Link
CN (1) CN201411926Y (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383613A (en) * 2011-11-11 2012-03-21 天津电力工程监理有限公司 Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN104018680A (en) * 2014-06-17 2014-09-03 中国建筑第二工程局有限公司 Lifting method for large-span solid-web arc beam
CN105926959A (en) * 2016-05-06 2016-09-07 浙江精工钢结构集团有限公司 All-weather truss splicing bed-jig

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383613A (en) * 2011-11-11 2012-03-21 天津电力工程监理有限公司 Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN102383613B (en) * 2011-11-11 2014-09-17 天津电力工程监理有限公司 Hoisting construction method for steel roof truss of main power house of power plant and special hoisting device
CN104018680A (en) * 2014-06-17 2014-09-03 中国建筑第二工程局有限公司 Lifting method for large-span solid-web arc beam
CN105926959A (en) * 2016-05-06 2016-09-07 浙江精工钢结构集团有限公司 All-weather truss splicing bed-jig

Similar Documents

Publication Publication Date Title
CN102535845A (en) Construction method of bearing frame of corridor structure
CN101892736B (en) High altitude moving hanging basket construction method
CN203296361U (en) Long-span steel structure cross assembling hoisting platform
CN103452126A (en) Light combined hanging box with recyclable baseplate steels and construction technology thereof
CN105484502A (en) Combination installation method for steel structure roofing purlins and support bars of industrial factory building
CN104929364A (en) Auxiliary construction method for longspan cantilever entire laminated Vierendeel truss structure
CN201144515Y (en) Steel structure high altitude construction platform
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN201411926Y (en) Arc beam hoisting structure
CN102261043B (en) Assembled steel pipe upright post system
CN106759909B (en) Bearing structure system and its construction method are hung up under one kind
CN201458583U (en) Liftable and detachable lifting platform
CN202658590U (en) Integral assembled drilling platform
CN206562827U (en) A kind of modularization steel-frame structure for tower equipment
CN203213637U (en) Roadbed box for walking on floor of larger crawler crane
CN203361654U (en) Prefabricated steel frame component
CN204126297U (en) A kind of temporary support of steel truss roof
CN216190654U (en) Line-straight-down type station room finite space large-span steel structure lifting tool
CN102465601B (en) Method for installing main body frame steel structure of benzene hydrogenation project
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN201756401U (en) Snap for lifting
CN201687083U (en) Suspension type template supporting structure with high-position integrated structure
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN207749859U (en) A kind of trestle support system for structure floor operation in Large-scale Hoisting equipment
CN203961239U (en) High-altitude overhanging awning construction operation platform

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: CHINA 19TH METALLURGICAL CORPORATION

Free format text: FORMER OWNER: MCC SHIJIU CONSTRUCTION CO., LTD.

Effective date: 20110317

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 617000 MCC SHIJIU CONSTRUCTION CO., LTD., NO. 350, RENMIN STREET, PANZHIHUA CITY, SICHUAN PROVINCE TO: 617000 NO. 350, RENMIN STREET, EAST DISTRICT, PANZHIHUA CITY, SICHUAN PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20110317

Address after: 617000 Panzhihua, Sichuan, East Street, No. 350

Patentee after: China 19th Metallurgical Corporation

Address before: 617000, Sichuan province Panzhihua City People's Street No. 350 MCC Long Construction Co., Ltd.

Patentee before: MCC Shijiu Construction Co., Ltd.

EE01 Entry into force of recordation of patent licensing contract

Assignee: China 19th Metallurgical Corp. (Fangchenggang) Equipment Structure Co., Ltd.

Assignor: China 19th Metallurgical Corporation

Contract record no.: 2011510000072

Denomination of utility model: Arc beam hoisting structure

Granted publication date: 20100224

License type: Exclusive License

Record date: 20110530

CX01 Expiry of patent term
CX01 Expiry of patent term