CN201687083U - Suspension type template supporting structure with high-position integrated structure - Google Patents

Suspension type template supporting structure with high-position integrated structure Download PDF

Info

Publication number
CN201687083U
CN201687083U CN2010201443593U CN201020144359U CN201687083U CN 201687083 U CN201687083 U CN 201687083U CN 2010201443593 U CN2010201443593 U CN 2010201443593U CN 201020144359 U CN201020144359 U CN 201020144359U CN 201687083 U CN201687083 U CN 201687083U
Authority
CN
China
Prior art keywords
construction
steel
floor
utility
supporting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
CN2010201443593U
Other languages
Chinese (zh)
Inventor
仓恒芳
刘亚非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Dadi Construction Group Co Ltd
Original Assignee
Nanjing Dadi Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Dadi Construction Group Co Ltd filed Critical Nanjing Dadi Construction Group Co Ltd
Priority to CN2010201443593U priority Critical patent/CN201687083U/en
Application granted granted Critical
Publication of CN201687083U publication Critical patent/CN201687083U/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model relates to a supporting construction method for a suspension type template with a high-position integrated structure, which finishes the supporting construction of the suspension type template by adopting the following working procedures: installing of a box type steel hanging post, installing of a steel beam, profiling of a steel plate, welding of an anti-shearing stud, binding of a reinforcing steel bar mesh sheet and pouring of floor slab concrete. The utility model overcomes the disadvantages of large using quantity of supporting materials, long building construction period, high reinforcing cost, high construction cost, high dead weight, difficult construction and the like when a traditional load-bearing full supporting rack is used to erect an overhead heavy-duty operating platform. Moreover, the utility model makes full use of the load-bearing capability of the main steel beam at a conversion floor to lead a combined floor slab to be adopted as the operating platform for erecting the template supporting rack at the construction stage and as a permanent refuge floor for an ultra-high-rise building at the using stage, thereby ensuring overhead operating safety, saving the construction cost, and increasing the using area. The main steel beam is adopted as a stiff reinforcing bar to participate in work of the steel rib concrete integrated structure, so as to jointly bear gradually-increased structural dead weight and construction load of each floor at the upper part.

Description

High-position conjoined structure suspended type mould board supporting structure
Technical field
The utility model relates to high-position conjoined structure in a kind of highrise building, particularly a kind of high-position conjoined structure suspended type mould board supporting structure.
Background technology
The building that aerial vestibule or conjoined structure are set between the double tower building of high-storey business and office building is more and more, whether the high-altitude disjunctor concrete structure conversion layer formwork bracing system construction technology for these buildings is reasonable, to directly affect safety, quality, duration and the construction cost of engineering, selecting correct shutterings-supported construction technology is the key of this conversion layer structure construction.Before the present utility model, the template braced structures has:
The one, adopt the full hall of traditional load-bearing bracing frame.Take measures after the reinforcing of podium roofing, the full hall formula formwork-support of the about 100m of scaffolding height on roofing, support body is guaranteed stable and is carried out effective drawknot with high building, makes it satisfy the construction requirement of conjoined structure.This scheme is comparatively safe but the backing material consumption is big, take tear open long in time limit, reinforcing expense height, construction cost is big.
The 2nd, set up high-altitude heavy duty operations platform.When two high building main body concrete structure constructions, default embedded part below conjoined structure conversion layer design elevation after this position concrete reaches design strength, utilizes embedded part welding fixed steel support.Six or four formula railway military beams are installed on the shaped steel bearing are formed the heavy construction operating platform, set up the conjoined structure formwork-support again.This construction technology is safe and reliable, but operating platform is from great temporarily, and its cost of making, lease, install and removing is also big, and has certain difficulty of construction.
Because this job practices or technology all are provisional, for the conjoined structure of constructing between two high buildings is provided with, be to need to remove after construction finishes, so engineering time and cost, the time of dismounting and cost and difficulty all are to consider.Obviously, above-mentioned two kinds of job practicess are all undesirable.
Summary of the invention
The purpose of this utility model just is to overcome above-mentioned defective, develops a kind of high-position conjoined structure suspended type mould board supporting structure.
The technical solution of the utility model is:
High-position conjoined structure suspended type mould board supporting structure, its major technique are characterised in that top is the steel girder, and two ends are connected on the high building, and the bottom connects the steel davit, and steel davit bottom connects the steel work refuge story.
Advantage of the present utility model and effect are to make full use of the supporting capacity of conversion layer steel girder self.Conversion layer steel girder is designed to welded H section steel, and the high 2600mm in cross section has sizable supporting capacity through checking, and can utilize its suspension operational platform and the template system of self fully.Design, construction and unit in charge of construction think and can hang one deck steel work composite floor under conversion layer steel girders through repeatedly research.This layer composite floor set up formwork-support in the construction stage as operating platform, at the permanent refuge story of operational phase as super highrise building, both guaranteed work high above the ground safety, saved operating expenses, increased usable floor area for the owner again.
Description of drawings
Fig. 1---the utility model theory structure schematic diagram.
The specific embodiment
As shown in Figure 1:
Steel reinforced concrete disjunctor conversion layer suspended type mould board supporting structure:
Top is steel girder 1, and two ends are connected on the high building, and the bottom connects steel davit 2, and steel davit 2 bottoms connect steel work refuge story 3.
Adopt the stiffness arrangement of reinforcement of welded H section steel, and under conversion layer, hang the operating platform (Fig. 1) of one deck steel work floor support plate as the construction stage as concrete conjoined structure conversion layer girder, secondary beam.Make full use of the enough big supporting capacity of H shaped steel girder self,, independently bear working load such as disjunctor conversion layer self-supporting template and dead load, the following steel work refuge story deadweight of hanging of beam and floor slab formerecting frame in the disjunctor conversion layer construction stage; In the disjunctor conversion layer superstructure construction stage, this steel girder participates in the work of steel reinforced concrete conjoined structure as the stiffness arrangement of reinforcement, bears dead load and working load that its each layer of top increases gradually jointly.

Claims (1)

1. high-position conjoined structure suspended type mould board supporting structure is characterized in that top is the steel girder, and two ends are connected on the high building, and the bottom connects the steel davit, and steel davit bottom connects the steel work refuge story.
CN2010201443593U 2010-03-29 2010-03-29 Suspension type template supporting structure with high-position integrated structure Expired - Lifetime CN201687083U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010201443593U CN201687083U (en) 2010-03-29 2010-03-29 Suspension type template supporting structure with high-position integrated structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010201443593U CN201687083U (en) 2010-03-29 2010-03-29 Suspension type template supporting structure with high-position integrated structure

Publications (1)

Publication Number Publication Date
CN201687083U true CN201687083U (en) 2010-12-29

Family

ID=43375368

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010201443593U Expired - Lifetime CN201687083U (en) 2010-03-29 2010-03-29 Suspension type template supporting structure with high-position integrated structure

Country Status (1)

Country Link
CN (1) CN201687083U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587692A (en) * 2012-01-18 2012-07-18 同济大学建筑设计研究院(集团)有限公司 Hybrid conjoined super high-rise structural system
CN107100367A (en) * 2017-05-22 2017-08-29 中城建设有限责任公司 A kind of construction method of suspension type platform for equipment interlayer
CN107119910A (en) * 2017-05-22 2017-09-01 中城建设有限责任公司 A kind of suspension type platform for equipment interlayer

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102587692A (en) * 2012-01-18 2012-07-18 同济大学建筑设计研究院(集团)有限公司 Hybrid conjoined super high-rise structural system
CN107100367A (en) * 2017-05-22 2017-08-29 中城建设有限责任公司 A kind of construction method of suspension type platform for equipment interlayer
CN107119910A (en) * 2017-05-22 2017-09-01 中城建设有限责任公司 A kind of suspension type platform for equipment interlayer

Similar Documents

Publication Publication Date Title
CN101886468B (en) Construction method of suspension type template support in high-position conjoined structure
CN102444203B (en) High-altitude long-span overhanging corridor type reinforced concrete structure and construction method
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN102535845A (en) Construction method of bearing frame of corridor structure
CN103422434A (en) Corrugated sheet steel composite structure bridge deck system
CN205012666U (en) High altitude steel construction vestibule integrally lift up support structure
CN103452126A (en) Light combined hanging box with recyclable baseplate steels and construction technology thereof
CN103046645A (en) Large span prefabricated monolithic casting structure and construction method
CN105781099A (en) Movable combined type one-sided large template structure and construction method thereof
CN103122691A (en) Tower crane standard knot bearing upper air supporting formwork steel platform structure and construction method
CN216042835U (en) A layering device for a high-rise frame structure with lightweight wall panels
CN106545115B (en) The construction method of assembled steel concrete composite slab
CN201144515Y (en) Steel structure high altitude construction platform
CN201687083U (en) Suspension type template supporting structure with high-position integrated structure
CN114134820A (en) Formwork support and construction method for cast-in-place bridge deck of I-shaped composite beam
CN101761241A (en) Roof suspended type method for pulling out pillars
CN102943439A (en) Method for constructing large-span and self-anchored composite beam suspension bridge girder
CN101403246B (en) Large-tonnage hoisting machine one-storied factory combination column and production method thereof
CN102425123B (en) Combined type protection shed frame and construction method thereof
CN203034799U (en) Tower hoist standard knot bearing overhead support formwork steel platform structure
CN103482493A (en) Internal climbing tower crane
CN210458919U (en) Steel-concrete composite beam and concrete pier connecting structure
CN202831628U (en) Combined type bailey frame load-bearing shelving for pouring large span concrete beam
CN207794317U (en) A kind of New Floor Slab and steel column connecting node
CN216947881U (en) Formwork support of I-shaped composite beam cast-in-situ bridge deck

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CX01 Expiry of patent term
CX01 Expiry of patent term

Granted publication date: 20101229