CN203361654U - Prefabricated steel frame component - Google Patents
Prefabricated steel frame component Download PDFInfo
- Publication number
- CN203361654U CN203361654U CN 201320442361 CN201320442361U CN203361654U CN 203361654 U CN203361654 U CN 203361654U CN 201320442361 CN201320442361 CN 201320442361 CN 201320442361 U CN201320442361 U CN 201320442361U CN 203361654 U CN203361654 U CN 203361654U
- Authority
- CN
- China
- Prior art keywords
- chord
- truss
- lower chord
- steel frame
- chord member
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses a prefabricated steel frame component. The prefabricated steel frame component comprises a moving truss and a runner support, wherein a main body of the moving truss is a planar truss which comprises an upper chord member, a lower chord member and a connecting rod; the upper chord member and the lower chord member are parallel to each other, and the connecting rod is used for fixedly connecting the upper chord member and the lower chord member integrally; the runner support is mounted on the lower chord member of the planar truss at the end of the moving truss; the planar truss further comprises a reinforcing chord member which is fixed in parallel on the upper chord member and the lower chord member. The prefabricated steel frame component is simple in structure and low in manufacturing cost; by adoption of the prefabricated steel frame component, the problems of long set-up period in construction, short service life, high cost and influences on ground construction and cross operation in an existing steel frame structure are solved.
Description
Technical field
The utility model belongs to construction engineering technical field, and particularly a kind of being applied to assembled the prefabricated units that use as roof beam structure in the constructions such as bridge and road.
Background technology
In recent years along with the development of country to input and the market economy of industrial circle, the building project of large-scale steel structure industrial premises is more and more, most industrial premises have all responded the requirement of country to energy-saving and environmental protection in design, therefore most of roofing all is designed to the form of the middle on-the-spot placing glass silk flosssilk wadding of inside and outside contour plate.And this form just requires roofing construction must divide lower raft construction and upper plate construction, an operating platform need to be arranged in factory building, as first on uncompleted ground, set up full hall support body, Roof system is installed.At first it sets up that the cycle is long, service time is short, and expense is high; Next affects ground construction, and cross-operation is influenced.Also will greatly affect the duration if set up again support body after ground construction completes.
Summary of the invention
In order to solve the problems of the technologies described above, the utility model provides a kind of precasting steel frame member, the steel work main body construction complete and the installation crane girder after, adopt the assembled stable steelframe of the finished product used in bridge construction to carry out the installations of project such as roof inner slab, roofing light fixture as the fitting operation platform of Roof system.
The technical scheme that the utility model is taked is: a kind of precasting steel frame member, comprise mobile truss and runner bearing, the main body of described mobile truss is plane frame, described plane frame comprises upper chord, the lower chord be parallel to each other and the connecting rod that upper chord, lower chord is fixed in to one, described runner bearing is installed on the lower chord of mobile truss end plane truss, described plane frame also comprises that what described reinforcement chord member was parallel is fixed on upper chord and lower chord for strengthening the reinforcement chord member of chord member of truss supporting capacity.
As preferably, the upper chord of each plane frame is two, lower chord is two, be fixed with Connection Block between two upper chords or lower chord, be provided with the chord bolt hole on described Connection Block, described reinforcement chord member uses bolt to be fixed together by chord bolt hole and two upper chords or lower chord, makes support body can carry larger pulling force, pressure and torsion.
As preferably, there is famale connector and the male contact of mutual coupling at the two ends of described upper chord and lower chord, have truss on joint and connect pin-and-hole, have guaranteed simple and easy, the operability of construction.
As preferably, described Connection Block is the steel plate with circular hole, also be provided with a plurality of bolts hole, crossbeam backing plate for connecting rod on described upper chord or lower chord, described crossbeam backing plate is provided with tenon, the position in the plane in order to fixed cross beam, make single plane frame can erect more securely mobile truss.
As preferably, the connecting rod of described plane frame is all made with the I-shaped steel, has strengthened the strength and stiffness of mobile truss body.
In sum, the utlity model has following advantage:
(1) the utility model is simple in structure, and cost of manufacture is low, during construction, sets up on mobile truss body and safeguards railing and windrow platform, in the end of support body, steel wheel is set, and has guaranteed that support body moves freely, thereby reaches effect comprehensive, safe, quick construction;
(2) the utility model is rational in infrastructure, can carry larger pulling force, pressure and torsion, has guaranteed the strength and stability of construction;
(3) the utility model efficiently solves the sequencing problem of Roof system and facility floor construction, the also cross-operation simultaneously of Roof system of both can first having constructed, thus greatly promoted the efficiency of construction of hydropower and the safety of construction.
The accompanying drawing explanation
The schematic diagram that figure l is preferred embodiment of the present utility model;
Fig. 2 is plane frame joint sectional drawing of the present utility model;
Fig. 3 is plane frame joint plan view of the present utility model;
Fig. 4 is the A section schematic diagram of figure l.
Label in accompanying drawing is respectively:
1. plane frame; 2. upper chord;
3. lower chord; 4. connecting rod;
41. vertical connecting rod; 42. oblique connecting rod;
5. runner; 6. Connection Block;
7. chord bolt hole; 8. famale connector;
9. male contact; 10. truss connects pin-and-hole;
11. crossbeam backing plate; 12. tenon;
13. bolt hole; 14. runner bearing.
The specific embodiment
Below in conjunction with accompanying drawing, with embodiment, the utility model is described in further detail.
The part of precasting steel frame member except strengthening chord member that the utility model provides as shown in Figure 1, plane frame 1 is wherein used two upper chords 2 and two lower chords 3 as the basic framework member, and use vertical and oblique connecting rod 4 that upper chord and lower chord are connected to one, between two upper chords and two lower chords, by connector, be welded as a whole, and be provided with Connection Block 6, have chord bolt hole 7 on Connection Block 6, strengthening chord member uses bolt to be fixed together by chord bolt hole 7 and two upper chords 2 or lower chord 3, connection that can be more firm and to bear power stronger.In addition, runner bearing 14 adopts the mode of welding to be installed on the lower chord 3 of mobile truss end plane truss 1.The precasting steel frame member is assemblied to form by single plane frame 1, and plane frame 1 length and width size is generally 3m * 1.5m, when construction, can carry out on-site consolidation according to the size of factory building span.When mounted, the plane frame l of end is with runner 5, and such precasting steel frame member can be put in factory building two across a crane girder top flange, by connection support, tie-rod forms the support of space truss as the spatial operation platform.
The two ends of upper chord 2 and lower chord 3 also have famale connector 8 and the male contact 9 of coupling mutually, have truss on joint and connect pin-and-hole 10, for connecting adjacent two truss.Connection Block 6, for the steel plate with circular hole, also is provided with a plurality of bolts hole 13, crossbeam backing plate 11 on described upper chord 2 or lower chord 3, middle bolt hole l3 is for double or arrange truss more and connect with internode, by the bolt hole 13 at two ends across internode connection use.When many row's truss are done beam or post use, can reinforce with bracing frame the junction surface of upper and lower two joint truss.Crossbeam backing plate 11 is provided with tenon 12, the position in the plane in order to fixed cross beam.
The connecting rod 4 of plane frame 1 is all made with the I-shaped steel, and the vertical connecting rod 4l that connecting rod can be divided into vertical connection upper chord, lower chord reaches and upper chord, the angled oblique connecting rod 42 joined of lower chord.
After completing the splicing of truss, set up the steel pipe operating platform on mobile joist body, the operating platform height need to be determined according to practice of construction.Set up the support of 2 fixed pulleys at the edge of operating platform, according to the material weight of construction handling, determine specification, the size of using fixed pulley, adopt rope made of hemp handling during with fixed pulley.The runner 5 that mobile truss body utilizes runner bearing on end plane truss 1 14 to install, moved, thereby reached the effect of full-scale construction.This support body surrounding is set up guard rail, sets up two higher fulcrums at the two ends of support body, between two fulcrums, hangs cable rope, when the workman constructs on top, safety belt is all hung on this cable rope and moves, thereby effectively avoided the danger of falling from high altitude.When moving this support body, needs enter another across when construction, the scaffold of first dismantling operation platform, and rear recycling mobile crane winches to this support body integral body at the construction space place of another identical span, has realized comprehensively, quick construction.
Above explanation is only to explanation of the present utility model; make those of ordinary skills can accurately implement this programme; but be not to restriction of the present utility model; those skilled in the art can make to the present embodiment the modification that there is no creative contribution as required after reading this manual, all belong to claim protection domain of the present utility model.
Claims (5)
1. a precasting steel frame member, comprise mobile truss and runner bearing, the main body of described mobile truss is plane frame, described plane frame comprises upper chord, the lower chord be parallel to each other and the connecting rod that upper chord, lower chord is fixed in to one, described runner bearing is installed on the lower chord of mobile truss end plane truss, it is characterized in that: described plane frame also comprises the reinforcement chord member, and what described reinforcement chord member was parallel is fixed on upper chord and lower chord.
2. precasting steel frame member according to claim 1, it is characterized in that: the upper chord of described each plane frame is two, lower chord is two, be fixed with Connection Block between two upper chords or lower chord, be provided with the chord bolt hole on described Connection Block, described reinforcement chord member uses bolt to be fixed together by chord bolt hole and two upper chords or lower chord.
3. according to claim l or 2 described precasting steel frame members, it is characterized in that: there is famale connector and the male contact of mutual coupling at the two ends of described upper chord and lower chord, have truss on joint and connect pin-and-hole.
4. precasting steel frame member according to claim 1 and 2, it is characterized in that: described Connection Block is the steel plate with circular hole, also is provided with a plurality of bolts hole, crossbeam backing plate for connecting rod on described upper chord or lower chord, described crossbeam backing plate is provided with tenon.
5. precasting steel frame member according to claim 1 and 2, it is characterized in that: the connecting rod of described plane frame is all made with the I-shaped steel.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320442361 CN203361654U (en) | 2013-07-24 | 2013-07-24 | Prefabricated steel frame component |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320442361 CN203361654U (en) | 2013-07-24 | 2013-07-24 | Prefabricated steel frame component |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203361654U true CN203361654U (en) | 2013-12-25 |
Family
ID=49809440
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201320442361 Expired - Fee Related CN203361654U (en) | 2013-07-24 | 2013-07-24 | Prefabricated steel frame component |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203361654U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108593275A (en) * | 2018-04-29 | 2018-09-28 | 南京林业大学 | A kind of truss loading device |
CN108978477A (en) * | 2018-07-27 | 2018-12-11 | 武汉市盘龙明达建筑有限公司 | A kind of cast-in-situ box girder shuttering supporting body assembly technology |
CN111962374A (en) * | 2020-07-22 | 2020-11-20 | 华南理工大学 | Quickly-installed space truss long-span light steel walking bridge and construction method thereof |
-
2013
- 2013-07-24 CN CN 201320442361 patent/CN203361654U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108593275A (en) * | 2018-04-29 | 2018-09-28 | 南京林业大学 | A kind of truss loading device |
CN108593275B (en) * | 2018-04-29 | 2023-11-24 | 南京林业大学 | Truss loading device |
CN108978477A (en) * | 2018-07-27 | 2018-12-11 | 武汉市盘龙明达建筑有限公司 | A kind of cast-in-situ box girder shuttering supporting body assembly technology |
CN111962374A (en) * | 2020-07-22 | 2020-11-20 | 华南理工大学 | Quickly-installed space truss long-span light steel walking bridge and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104499413B (en) | Modularity punching block concrete combination arch bridge and suspension cable hanging construction method thereof | |
CN201546435U (en) | Bolted stayed cantilever scaffold | |
CN105780925A (en) | Truss-hanging combined system installation construction method | |
CN102261043B (en) | Assembled steel pipe upright post system | |
CN203361654U (en) | Prefabricated steel frame component | |
CN103437283A (en) | Hanging basket truss fast to assemble | |
CN102454292A (en) | Supporting steel frame of high altitude large-span cantilever structure mold frame | |
CN102003078A (en) | Assembling method of net rack | |
CN203461693U (en) | Ultrahigh steel support leg for combined gantry crane with Bailey truss | |
CN211420881U (en) | Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam | |
CN210766431U (en) | Steel arch rib pushing system | |
CN202152442U (en) | Assembling type steel tube-vertical post system | |
CN203334643U (en) | Tower crane standard knot and structural steel combination high-altitude large-span operation frame device | |
CN110700112A (en) | Movable formwork for concrete construction of overhanging wing plate of steel-concrete composite beam and construction method | |
CN101591886A (en) | Composite material truss bridge | |
CN201411926Y (en) | Arc beam hoisting structure | |
CN201952899U (en) | Beam column connecting node of detachable board house | |
CN201447659U (en) | Composite material truss bridge | |
CN214994627U (en) | Space steel structure node | |
CN210420840U (en) | Cantilever light steel pedestrian truss bridge connecting system based on stay cable structure | |
CN209383261U (en) | The prefabricated assembled stair hoisting structure of fast-type | |
CN209685126U (en) | A kind of steel vestibule integrally promotes lifting lug device | |
CN202790959U (en) | Steel pipe truss structure based on aloft lateral support | |
CN201952736U (en) | Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder | |
CN112575948A (en) | Truss string beam and cantilever truss combined roof truss and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20131225 Termination date: 20180724 |