CN101864842A - 一种核电厂工程的施工方法 - Google Patents

一种核电厂工程的施工方法 Download PDF

Info

Publication number
CN101864842A
CN101864842A CN 201010210437 CN201010210437A CN101864842A CN 101864842 A CN101864842 A CN 101864842A CN 201010210437 CN201010210437 CN 201010210437 CN 201010210437 A CN201010210437 A CN 201010210437A CN 101864842 A CN101864842 A CN 101864842A
Authority
CN
China
Prior art keywords
power plant
nuclear power
installation
room
job practices
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN 201010210437
Other languages
English (en)
Other versions
CN101864842B (zh
Inventor
鲁勤武
柴伟东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
Original Assignee
China General Nuclear Power Corp
China Nuclear Power Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China General Nuclear Power Corp, China Nuclear Power Engineering Co Ltd filed Critical China General Nuclear Power Corp
Priority to CN201010210437XA priority Critical patent/CN101864842B/zh
Publication of CN101864842A publication Critical patent/CN101864842A/zh
Application granted granted Critical
Publication of CN101864842B publication Critical patent/CN101864842B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明公开了一种核电厂工程的施工方法,包括如下步骤:S1.建造厂房构筑物基部区域的所有房间单元的楼板及墙壁;S2.通过吊装设备将安装物引入各个房间单元内;S3.对各个房间单元内的屋顶封顶;S4.封顶后在上层区域厂房土建施工的同时,在各个房间单元内继续进行安装施工;S5.就位安装各个房间内的安装物,并进行装修;S6.调试各个房间单元内的设备;S7.循环此发明的核电厂工程的施工方法的以上六个步骤。本发明提供的核电厂建造方法,将土建工程和机电安装工程的施工模式为并行,不仅大大缩短核电厂工程建造工期,还解决了某些大型设备引入困难以及大型专用起吊设备利用率低的问题,从而提降低设备安装难度,提高安装质量、降低核电厂建造成本。

Description

一种核电厂工程的施工方法
技术领域
本发明涉及施工方法,尤其涉及一种核电厂工程的施工方法。
背景技术
当前核电厂工程的建造过程大体上按时间先后被划分成以下两部分;一是建设厂房的土建工程;二是在厂房内安装机械设备、电气设备以及铺设管路的机电安装工程。
并且任何堆型的核电厂一般由核岛厂房、核辅助厂房、常规岛厂房、电气厂房和BOP厂房组成,由于核电厂特有的安全等方面的要求,特别是核岛厂房、核辅助厂房被建成非常坚实的钢筋混凝土巨大厂房,而且系统多、设备庞大,因此核电厂工程具有土建施工和设备安装施工工程量大、施工质量要求严、施工周期长的特点。
由于大部分核电厂厂房内布置都很紧凑,单个房间内空间也很狭小,大部分安装物都是在厂房建成移交后才进行引入安装,特别是一些重型机械设备和电气设备只能先将其拆卸后搬入厂房的房间内,重新组装完整后再与其它相连的安装物进行对接安装,这样做对器材、电气设备、各种精密机械会造成不良影响,并且耗费大量人力和时间。
而在核电厂建造施工中,需要使用大型专用起重机在特定的施工阶段和时间来引入少量大型设备,由于大型专用起重机的特殊性,使用前要准备供其工作移动范围的起重机专用基础、经过特殊路线的将巨大部件运入到施工现场、将各巨大部件组装成体、起重机的调试等阶段,但是各个大型设备的引入时间间隔很长,期间无法用于其它土建施工物质的搬运,和绝大部分安装物只能通过人力或其他方式搬入房间,使得这些大型专用起重型机械效率得不到充分发挥。
这些问题的存在造成了核电厂建造周期长,内部大型设备运输和安装就位难,而大型起重机又得不到充分利用的主要原因。
发明内容
本发明的发明目的是克服上述已有技术的缺点,提供一种可以实现土建工程与机电安装工程并行施工的核电厂工程的建造施工方法。
本发明核电厂工程的施工方法,包括如下步骤;S1建造厂房构筑物基部区域的所有房间单元的楼板及墙壁;S2通过吊装设备将安装物引入各个房间单元内;S3对各个房间单元内的屋顶封顶;S4封顶后在上层区域厂房土建施工的同时,在各个房间单元内继续进行安装施工;S5就位安装各个房间内的安装物,并进行装修;S6调试各个房间单元内的设备;S7循环此发明的核电厂工程的施工方法的以上六个步骤。
使用本发明的核电站工程建造施工方法,将土建工程和机电安装工程的施工模式变为并行,可大大缩短核电厂工程的建造工期;此施工方法还解决了大型设备引入困难的问题,可以提高大型设备一次引入就位率,降低安装难度,提高安装质量。
附图说明
下面将结合附图及实施例对本发明作进一步说明,附图中;
图1是为本发明核电厂工程的施工方法的步骤流程图;
图2a是为本发明核电厂工程的施工方法步骤S1的示意图;
图2b是为本发明核电厂工程的施工方法步骤S2的示意图;
图2c是为本发明核电厂工程的施工方法步骤S3的示意图;
图2d是为本发明核电厂工程的施工方法步骤S4的示意图;
图2e是为本发明核电厂工程的施工方法步骤S5的示意图;
图2f是为本发明核电厂工程的施工方法步骤S6的示意图;
具体实施方式
下面将结合具体实施例对本发明核电厂工程的施工方法进行详细描述。
本发明所述的土建工程是由厂房基部向上逐层依次建造多层房间,每个房间为一个最小单元,且每个房间由楼板10、墙壁20和屋顶30构成.
机电安装工程是把机器设备、工程物资和器材等搬入各层房间内部,然后安装机器、配管,接通电气,然后再调试各个设备。
如图1所示,为本发明核电厂工程的施工方法的步骤流程图并结合图2a至图2f所示,该施工方法包括以下步骤;
S1建造建造厂房构筑物的所有房间单元的底板10及墙壁20,并在楼板10上设置就位安装引导部件11。
S2通过塔式起重机或履带式起重机等大型起重机将重型设备60、管道器材40引入各个房间单元内,并在吊装的同时将重型管道设备60通过楼板10上的就位安装引导部件11一次性安装就位于楼板10上,随后在各个房间单元内设置脚手架50,所述脚手架50用于方便屋顶30的顶部的安装物项的安装及房间内的装修。
S3对各个房间的屋顶30封顶,并在封顶施工的同时预留贯穿孔洞35;在房间内屋顶30设置多个吊环31,用于管道40的吊装。
S4封顶后在上层区域厂房实施土建工程的同时,在各个房间内继续进行机电安装工程。
具体的,通过穿设于该吊环31的铰链33将各段管道40按照设定线路吊装于房间内;然后通过设置与各个房间内的脚手架50对各个房间内的屋顶30及墙壁20进行装修;随后拆卸脚手架50,将各个房间内的空间腾出来,并在各个房间内进行水、电、气、汽、仪控、通讯、通风等其他设施的安装施工。
S5对房间内的设备60进行定位固定,随后涂防水涂料13,该防水漆涂料13用以防止房间内管道40、设备60因故障漏水而影响到下部房间内的设备的正常运行。
S6将各段管道40用支吊架23定位固定于房间墙壁20,将铰链33拆下,最后调试各个房间内的设备,确定其单元能正常工作。
S7循环此发明的建造方法的以上六个步骤,可完成厂房土建工程与机电安装工程的并行施工。
有益效果;
本发明提供的核电厂建造方法,将土建工程和机电安装工程的施工模式为并行,可大幅度缩短核电厂工程的建造工期,对降低核电厂建造成本,减少现场施工工人劳动量,提高核电厂经济性起到积极的推动作用。此施工方法还解决了某些大型设备引入困难的问题,可以提高某些大型设备一次引入就位率,降低安装难度,提高安装质量。

Claims (12)

1.一种核电厂工程的施工方法,其特征在于,包括如下步骤:
S1建造厂房构筑物基部区域的所有房间单元的楼板及墙壁;
S2通过吊装设备将安装物引入各个房间单元内;
S3对各个房间单元内的屋顶封顶;
S4封顶后在上层区域厂房土建施工的同时,在各个房间单元内继续进行安装施工;
S5就位安装各个房间内的安装物,并进行装修;
S6调试各个房间单元内的设备;
S7循环此发明的核电厂工程的施工方法的以上六个步骤。
2.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S1中还包括在所述楼板或墙壁上的安装物的定位、支撑、固定用预埋板、螺栓、就位安装引导部件。
3.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S2中所述安装物包括各种模块、设备、机器、管道、桥架、托盘、风管、支吊架、钢结构、施工用物资及器材。
4.根据权利要求2所述的核电厂工程的施工方法,其特征在于,在所述步骤S2中所述各种模块、设备、机器引入的同时将其通过墙壁或楼板上的的定位、支撑、固定用螺栓、就位安装引导部件安装就位于墙壁或楼板上。
5.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S2中还有如下步骤,在各个房间单元内设置管道、桥架、托盘、风管、支吊架、钢结构安装和装修用的脚手架。
6.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S3中还有如下步骤,采用钢梁和压型钢板形成屋顶土建施工的支模系统。
7.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S3中还有如下步骤,在封顶施工的同时预留贯穿孔洞,以及在各个房间墙壁和屋顶上设置吊环。
8.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S4中各个房间内的安装施工包括水、电、气、汽、仪控、通讯、通风等设施的安装施工。
9.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S5中还有如下步骤,通过设置于墙壁和屋顶上的吊环和铰链将各管道、桥架、托盘、风管、支吊架、钢结构按照设定线路就位于房间内固定位置。
10.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S5中还有如下步骤,通过设置于各个房间内的脚手架对各个房间内的各管道、桥架、托盘、风管、支吊架、钢结构进行安装,装修屋顶及墙壁。
11.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S5中进行防水处理以防止房间内设备漏水时对其他房间的影响。
12.根据权利要求1所述的核电厂工程的施工方法,其特征在于,在所述步骤S6中还包括需要单元调试设施的调试。
CN201010210437XA 2010-06-28 2010-06-28 一种核电厂工程的施工方法 Active CN101864842B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010210437XA CN101864842B (zh) 2010-06-28 2010-06-28 一种核电厂工程的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010210437XA CN101864842B (zh) 2010-06-28 2010-06-28 一种核电厂工程的施工方法

Publications (2)

Publication Number Publication Date
CN101864842A true CN101864842A (zh) 2010-10-20
CN101864842B CN101864842B (zh) 2012-09-12

Family

ID=42956750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010210437XA Active CN101864842B (zh) 2010-06-28 2010-06-28 一种核电厂工程的施工方法

Country Status (1)

Country Link
CN (1) CN101864842B (zh)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116089A (zh) * 2010-12-31 2011-07-06 青岛建设集团零零一工程有限公司 大跨度型钢梁拔杆整体提升施工方法
CN102182315A (zh) * 2011-03-31 2011-09-14 中广核工程有限公司 一种核电站全天候施工方法及施工装置
CN102251679A (zh) * 2011-05-10 2011-11-23 中广核工程有限公司 施工方法
CN102733614A (zh) * 2012-06-29 2012-10-17 中广核工程有限公司 一种核电厂房间模块的施工方法
CN102881344A (zh) * 2012-09-05 2013-01-16 中国核电工程有限公司 一种核电厂分布式控制系统信号的分配方法
CN103046756A (zh) * 2012-12-29 2013-04-17 陕西省第三建筑工程公司 一种装饰清水砖砌体施工方法
CN103216106A (zh) * 2013-04-24 2013-07-24 启东建筑集团有限公司 电子厂房低温冷库的施工方法
CN103276840A (zh) * 2013-05-22 2013-09-04 中广核工程有限公司 核电厂复合楼板模块及其施工方法
CN103291075A (zh) * 2013-06-27 2013-09-11 中广核工程有限公司 核电厂大型模块制造方法
CN104298792A (zh) * 2013-07-15 2015-01-21 中广核工程有限公司 基于核电站的模块设计方法和系统
CN107419807A (zh) * 2016-05-24 2017-12-01 构法开发株式会社 建筑物的建造方法
CN107975148A (zh) * 2017-10-24 2018-05-01 宋丰伟 主系统设备预引入方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05107381A (ja) * 1991-10-18 1993-04-27 Central Res Inst Of Electric Power Ind 原子力プラントの建設方法
JPH05232280A (ja) * 1992-02-24 1993-09-07 Toshiba Corp 原子力発電所の機器搬入方法
CN1172200A (zh) * 1996-07-11 1998-02-04 株式会社日立制作所 厂的建设方法
CN1195734A (zh) * 1997-03-19 1998-10-14 株式会社日立制作所 工厂的厂房的建设方法和用于该建设的模块构造物

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05107381A (ja) * 1991-10-18 1993-04-27 Central Res Inst Of Electric Power Ind 原子力プラントの建設方法
JPH05232280A (ja) * 1992-02-24 1993-09-07 Toshiba Corp 原子力発電所の機器搬入方法
CN1172200A (zh) * 1996-07-11 1998-02-04 株式会社日立制作所 厂的建设方法
CN1195734A (zh) * 1997-03-19 1998-10-14 株式会社日立制作所 工厂的厂房的建设方法和用于该建设的模块构造物

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102116089B (zh) * 2010-12-31 2015-11-25 青岛博海建设集团有限公司 大跨度型钢梁拔杆整体提升施工方法
CN102116089A (zh) * 2010-12-31 2011-07-06 青岛建设集团零零一工程有限公司 大跨度型钢梁拔杆整体提升施工方法
CN102182315A (zh) * 2011-03-31 2011-09-14 中广核工程有限公司 一种核电站全天候施工方法及施工装置
CN102251679B (zh) * 2011-05-10 2015-04-22 中广核工程有限公司 施工方法
CN102251679A (zh) * 2011-05-10 2011-11-23 中广核工程有限公司 施工方法
CN102733614A (zh) * 2012-06-29 2012-10-17 中广核工程有限公司 一种核电厂房间模块的施工方法
CN102881344A (zh) * 2012-09-05 2013-01-16 中国核电工程有限公司 一种核电厂分布式控制系统信号的分配方法
CN102881344B (zh) * 2012-09-05 2015-06-17 中国核电工程有限公司 一种核电厂分布式控制系统信号的分配方法
CN103046756B (zh) * 2012-12-29 2015-05-13 陕西省第三建筑工程公司 一种装饰清水砖砌体施工方法
CN103046756A (zh) * 2012-12-29 2013-04-17 陕西省第三建筑工程公司 一种装饰清水砖砌体施工方法
CN103216106B (zh) * 2013-04-24 2015-03-18 启东建筑集团有限公司 电子厂房低温冷库的施工方法
CN103216106A (zh) * 2013-04-24 2013-07-24 启东建筑集团有限公司 电子厂房低温冷库的施工方法
CN103276840A (zh) * 2013-05-22 2013-09-04 中广核工程有限公司 核电厂复合楼板模块及其施工方法
CN103276840B (zh) * 2013-05-22 2016-02-24 中广核工程有限公司 核电厂复合楼板模块及其施工方法
CN103291075A (zh) * 2013-06-27 2013-09-11 中广核工程有限公司 核电厂大型模块制造方法
CN103291075B (zh) * 2013-06-27 2016-08-10 中广核工程有限公司 核电厂大型模块制造方法
CN104298792A (zh) * 2013-07-15 2015-01-21 中广核工程有限公司 基于核电站的模块设计方法和系统
CN107419807A (zh) * 2016-05-24 2017-12-01 构法开发株式会社 建筑物的建造方法
CN107975148A (zh) * 2017-10-24 2018-05-01 宋丰伟 主系统设备预引入方法

Also Published As

Publication number Publication date
CN101864842B (zh) 2012-09-12

Similar Documents

Publication Publication Date Title
CN101864842B (zh) 一种核电厂工程的施工方法
CN110407078B (zh) 一种多吊点的闸门节段转体吊装施工方法
CN105544605A (zh) 模块化装配式综合管廊
CN102720432A (zh) 自行式坑道钻孔台车
CN103291075B (zh) 核电厂大型模块制造方法
CN108035568A (zh) 钢结构建筑智能装配工厂
CN103061508A (zh) 一种三角形滑模装置及施工方法
CN103276840B (zh) 核电厂复合楼板模块及其施工方法
CN111042573A (zh) 免除湿作业的增设loft公寓夹层楼板的施工方法及结构
CN102733614B (zh) 一种核电厂房间模块的施工方法
CN202865996U (zh) 一种核电厂房间模块结构
CN201224661Y (zh) 小空间室内大型设备的安装装置
CN101285324A (zh) 一种新型的框架式建筑体及其建造方法
CN109296082A (zh) 一种框架或筒体承重高层模块化建筑半倒装施工结构及施工方法
CN202280073U (zh) 预浇装配式设备基础
CN110282557A (zh) 辅助安装平台和用桥式起重机安装车间内高空管道的方法
CN102704952B (zh) 自行式隧洞灌浆台车
CN105781159A (zh) 一种电厂主厂房钢筋混凝土煤漏斗施工工艺
CN204960324U (zh) 一种悬挂式楼板模板支撑装置
CN204225503U (zh) 大跨度钢桁架高空散装转换梁胎架
CN210194965U (zh) 一种预制混凝土外挂墙板的连接装置
CN102758538A (zh) 一种拉砌组合建筑装配式墙板模车
CN210178020U (zh) 预制舱安装限位结构
Kurakova Use of formwork systems in high-rise construction
CN105370048A (zh) 一种超高超长蒸压轻质加气混凝土板墙体的施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder

Address after: 518023 No. 69 Shennan Middle Road, Shenzhen, Guangdong, Futian District

Co-patentee after: CHINA GENERAL NUCLEAR POWER Corp.

Patentee after: CHINA NUCLEAR POWER ENGINEERING Co.,Ltd.

Address before: 518023 No. 69 Shennan Middle Road, Shenzhen, Guangdong, Futian District

Co-patentee before: CHINA GUANGDONG NUCLEAR POWER GROUP Co.,Ltd.

Patentee before: CHINA NUCLEAR POWER ENGINEERING Co.,Ltd.

CP01 Change in the name or title of a patent holder