CN101457514B - 一种斜拉桥的施工方法 - Google Patents

一种斜拉桥的施工方法 Download PDF

Info

Publication number
CN101457514B
CN101457514B CN2008102206588A CN200810220658A CN101457514B CN 101457514 B CN101457514 B CN 101457514B CN 2008102206588 A CN2008102206588 A CN 2008102206588A CN 200810220658 A CN200810220658 A CN 200810220658A CN 101457514 B CN101457514 B CN 101457514B
Authority
CN
China
Prior art keywords
construction
king
girder
tower column
tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2008102206588A
Other languages
English (en)
Other versions
CN101457514A (zh
Inventor
许建得
李钦
赵资钦
刘联伟
钟显奇
邵孟新
陈锦云
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foundation Design Group Co Ltd Of Guangdong Province
Guangdong Construction Engineering Group Co Ltd
Original Assignee
GUANGDONG PROV FOUNDATION ENGINEERING Co
Guangdong Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG PROV FOUNDATION ENGINEERING Co, Guangdong Construction Engineering Group Co Ltd filed Critical GUANGDONG PROV FOUNDATION ENGINEERING Co
Priority to CN2008102206588A priority Critical patent/CN101457514B/zh
Publication of CN101457514A publication Critical patent/CN101457514A/zh
Application granted granted Critical
Publication of CN101457514B publication Critical patent/CN101457514B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种斜拉桥的施工方法,包括以下步骤:首先施工主塔柱的非挂索区的结构,并在该主塔柱的非挂索区结构施工的同时,进行主梁的0#块结构的施工;接着进行主塔柱的挂索区结构和主梁的同步施工,即主塔柱的挂索区结构沿竖向分节增高施工的同时,主梁对应地向两侧逐块施工,并进行斜拉索的逐根挂设和张拉,直至主塔完成,主梁合拢。本发明由于采用主塔柱分节段施工,在主塔柱完成一定的节段并满足可挂斜拉索的施工条件后,就进行挂索和主梁的施工,同时主塔柱也继续向上分节段进行施工,这样可使主塔柱和主梁同步施工,达到“塔梁并举”,以有效地减少施工工期,保障施工期间的塔柱结构安全。

Description

一种斜拉桥的施工方法
技术领域
本发明涉及建筑工程技术领域,特别是涉及斜拉桥的施工技术。
背景技术
斜拉桥梁常规施工方法是采用先塔后梁的施工方法,即先完成主塔柱直至封顶,然后浇筑主梁。随着斜拉桥的规模增大,跨度增长和主塔高度增高,这种常规施工方法的施工工期往往很长,并且要针对主塔采取专门的减振及防裂等措施,造成施工成本较大。
发明内容
本发明的目的是针对上述问题的存在,提供一种有效缩短施工工期和在不采取其它专门措施的条件下保护主塔柱的斜拉桥的施工方法。
本发明的目的是通过以下技术方案实现的:
一种斜拉桥的施工方法,包括以下步骤:
(1)、首先施工主塔柱的非挂索区的结构,并在该主塔柱的非挂索区结构施工的同时,进行主梁的0#块结构的施工;
(2)、接着进行主塔柱的挂索区结构和主梁的同步施工,即主塔柱的挂索区结构沿竖向分节增高施工的同时,主梁对应地向两侧逐块施工,并进行斜拉索的逐根挂设和张拉,直至主塔完成,主梁合拢。
本发明由于采用主塔柱分节段施工,在主塔柱完成一定的节段并满足可挂斜拉索的施工条件后,就进行挂索和主梁的施工,同时主塔柱也继续向上分节段进行施工,这样可使主塔柱和主梁同步施工,达到“塔梁并举”,以有效地减少施工工期。另一方面,由于“塔梁并举”,从而达到减小裸塔的高度和增加塔柱封顶后的结构刚度和重量,从而有效地减弱塔柱的风振响应,在不需要增加减振设备的情况下就可防止主塔混凝土结构的开裂,保障施工期间的塔柱结构安全。
以下结合附图详细说明本发明的实现。
附图说明
图1为本发明主塔非挂索区及主梁0#块施工完成后的示意图;
图2为本发明主塔挂索区分节及主梁分块逐段施工的示意图;
图3为本发明主塔挂索区及主梁施工完成后的示意图。
具体实施方式
本发明所述的斜拉桥的施工方法,包括以下步骤:
1、在施工完桥桩基3和桩承台4后,首先施工主塔柱的非挂索区结构11,在该主塔柱的非挂索区结构11施工的同时,进行主梁0#块结构21的施工。其中主塔柱的非挂索区结构11施工可以采用滑模、爬模或组合模板分节段完成,而主梁0#块结构21可以采用支架模板现浇完成。
2、接着进行主塔柱的挂索区结构12和主梁22的同步施工。即主塔柱的挂索区结构21沿竖向分节段增高施工的同时,主梁22对应地向两侧逐块施工,并进行斜拉索的逐根挂设和张拉,直至主塔完成,主梁合拢。其中,各根斜拉索挂设和张拉前,先对固定其一端的主塔柱索区结构的对应分节和固定其另一端的主梁的对应块进行各项设计参数的测量和监控,确保各设计参数已达到设计要求。
同时,在整个施工的过程中,应对主塔柱、主梁的截面尺寸、平面位置、轴线位置、垂直度偏差、预埋件的制作和安装精度、索力等进行实时监测和测量,并将监测和测量数据反馈于施工过程。而在全部施工过程中可减少甚至取消主塔柱的防风、抗裂措施的采取。

Claims (1)

1.一种斜拉桥的施工方法,其特征在于包括以下步骤:
(1)、在施工完桥桩基(3)和桩承台(4)后,首先施工主塔柱的非挂索区的结构,并在该主塔柱的非挂索区结构施工的同时,进行主梁的0#块结构的施工,其中主塔柱的非挂索区结构(11)施工采用滑模、爬模或组合模板分节段完成,而主梁0#块结构(21)采用支架模板现浇完成;
(2)、接着进行主塔柱的挂索区结构和主梁的同步施工,即主塔柱的挂索区结构沿竖向分节增高施工的同时,主梁对应地向两侧逐块施工,并进行斜拉索的逐根挂设和张拉,直至主塔完成,主梁合拢,其中各根斜拉索挂设和张拉前,先对固定其一端的主塔柱索区结构的对应分节和固定其另一端的主梁的对应块进行各项设计参数的测量和监控,确保各设计参数已达到设计要求,此时各设计参数的测量和监控包括对主塔柱、主梁、斜拉索的截面尺寸、平面位置、轴线位置、垂直度偏差、预埋件的制作和安装精度、索力进行施工测量和监控,并将监测的数据反馈于施工过程中。 
CN2008102206588A 2008-12-31 2008-12-31 一种斜拉桥的施工方法 Expired - Fee Related CN101457514B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2008102206588A CN101457514B (zh) 2008-12-31 2008-12-31 一种斜拉桥的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2008102206588A CN101457514B (zh) 2008-12-31 2008-12-31 一种斜拉桥的施工方法

Publications (2)

Publication Number Publication Date
CN101457514A CN101457514A (zh) 2009-06-17
CN101457514B true CN101457514B (zh) 2011-11-23

Family

ID=40768618

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2008102206588A Expired - Fee Related CN101457514B (zh) 2008-12-31 2008-12-31 一种斜拉桥的施工方法

Country Status (1)

Country Link
CN (1) CN101457514B (zh)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100969005B1 (ko) * 2009-11-06 2010-07-09 동아대학교 산학협력단 가설케이블을 이용한 무장력 사재케이블 상태의 사장교 시공방법 및 이를 위한 가설케이블
CN102251478B (zh) * 2011-04-27 2013-05-08 中铁港航局集团第二工程有限公司 斜拉桥塔梁同步施工测量控制方法
CN102296525B (zh) * 2011-05-31 2013-09-11 中铁大桥勘测设计院有限公司 支座体系混合式结合梁斜拉桥及其施工方法
CN102286930A (zh) * 2011-09-09 2011-12-21 中铁五局集团建筑工程有限责任公司 一种斜拉桥施工方法
CN102535348B (zh) * 2012-03-14 2013-10-30 天津市市政工程设计研究院 一种铰塔斜拉桥斜拉索的张拉方法
CN103741601B (zh) * 2013-06-28 2017-02-01 中交第三航务工程局有限公司 一种塔、梁以及索同步成桥工艺
CN103741606B (zh) * 2013-12-31 2016-10-05 中铁大桥局集团有限公司 软牵引设备快速换索的施工方法
CN104294747B (zh) * 2014-09-23 2016-05-18 同济大学 一种双塔混合梁斜拉桥体系及其施工方法
CN104532743B (zh) * 2014-12-29 2016-09-28 中交公路规划设计院有限公司 塔梁固结机构和相应的斜拉桥及其建造方法
CN104652282B (zh) * 2015-01-06 2016-06-29 中交第二航务工程局有限公司 用于组合梁斜拉桥翼缘施工的移动支架及其使用方法
CN104900136B (zh) * 2015-05-29 2018-02-27 长沙理工大学 一种试验用斜拉桥及安装方法
CN106758841B (zh) * 2016-12-29 2018-07-31 中交第三航务工程局有限公司 一种双塔双索面矮塔斜拉桥的整体施工工艺
CN106948267B (zh) * 2017-04-13 2019-05-14 中铁四局集团市政工程有限公司 一种牌坊门楼式桥梁索塔塔柱同步施工方法
CN106906751B (zh) * 2017-04-25 2019-01-11 中铁四局集团有限公司 特大斜拉桥主塔弧形段竖向预应力施工方法
CN109371852A (zh) * 2018-10-26 2019-02-22 中铁武汉勘察设计研究院有限公司 一种跨铁路站场的高架桥施工方法
CN110184915B (zh) * 2019-04-30 2020-11-27 安徽省公路桥梁工程有限公司 斜拉桥现浇塔柱及其施工方法
CN110629678A (zh) * 2019-10-23 2019-12-31 中国电建集团成都勘测设计研究院有限公司 斜拉桥的拉索辅助支架

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
傅科奇.绥芬河转体施工斜拉桥施工控制的研究.东北林业大学硕士学位论文.2006,10-13. *
孙全胜,孙永存.斜拉桥塔梁同步施工与控制技术的研究.公路.2007,(04),88-91. *
徐强,杨威,蒋敏杰.绥芬河斜拉桥塔梁同步施工控制技术的研究.城市道桥与防洪.2007,(11),76-79. *

Also Published As

Publication number Publication date
CN101457514A (zh) 2009-06-17

Similar Documents

Publication Publication Date Title
CN101457514B (zh) 一种斜拉桥的施工方法
CN104088467B (zh) 一种大悬臂钢桁架结构高空施工变形监测方法
CN102535343A (zh) 钢桁梁斜拉桥主塔墩顶钢梁架设方法
CN102121234A (zh) 一种双塔五跨钢桁梁斜拉桥的快速施工方法
CN104265002A (zh) 一种连续桁架柱顶铰接结构的提升架设计应用方法
CN102493471A (zh) 结构地脚锚栓悬空安装施工工艺方法
CN102864934A (zh) 一种背栓式干挂石材幕墙施工方法
CN104100090A (zh) 一种大悬臂钢桁架结构高空综合施工方法
CN109853964A (zh) 一种用于钢结构钢筋混凝土混合结构的施工方法
CN102286930A (zh) 一种斜拉桥施工方法
CN105347142A (zh) 一种施工升降机安装在地下室顶板上的穿板安装方法
CN202000265U (zh) 桥梁高墩混凝土施工模板
CN102635070B (zh) 斜拉桥钢塔互拉式竖向转体施工方法
CN103726445B (zh) 一种塔梁固结斜拉桥0#块支架现浇与挂篮悬浇相结合的施工方法
CN102877412A (zh) 钢塔整体竖立式预拼装方法
CN104453228A (zh) 一种大跨度超大截面钢板墙梁施工方法
CN107761580A (zh) 一种桥梁旧墩柱改造施工方案
CN204475182U (zh) 一种铁路桥墩墩顶吊篮的安装工装
CN103046743A (zh) 一种超高层转换层型钢混凝土大梁吊挂式模板支撑体系及施工方法
CN103132461B (zh) 用于钢桁架梁桥悬臂施工的柔性托架装置
CN101994294A (zh) 公路工程三角轻型挂篮悬臂浇筑施工
KR101399679B1 (ko) 대규모 구조물의 성능 기반 구조 해석 방법
CN103321449B (zh) 框架结构加层建筑物的处理方法
KR101381449B1 (ko) 초고층 건물의 시공 중 골조 변위 해석방법
CN204139634U (zh) 一种快捷式洞口安全封闭结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: GUANGDONG FOUNDATION ENGINEERING GROUP CO., LTD.

Free format text: FORMER NAME: GUANGDONG PROV. FOUNDATION ENGINEERING CO.

CP01 Change in the name or title of a patent holder

Address after: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Patentee after: Foundation Design Group Co., Ltd of Guangdong Province

Patentee after: Guangdong Construction Engineering Group Co., Ltd.

Address before: 19-20, No. 510620, Tianhe Road, 99 Tianhe Road, Guangdong, Guangzhou

Patentee before: Guangdong Prov. Foundation Engineering Co.

Patentee before: Guangdong Construction Engineering Group Co., Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20111123

Termination date: 20171231