CN102286930A - 一种斜拉桥施工方法 - Google Patents

一种斜拉桥施工方法 Download PDF

Info

Publication number
CN102286930A
CN102286930A CN2011102666757A CN201110266675A CN102286930A CN 102286930 A CN102286930 A CN 102286930A CN 2011102666757 A CN2011102666757 A CN 2011102666757A CN 201110266675 A CN201110266675 A CN 201110266675A CN 102286930 A CN102286930 A CN 102286930A
Authority
CN
China
Prior art keywords
construction
cable
tower
girder
stayed bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011102666757A
Other languages
English (en)
Inventor
陈玉发
朱长城
苟祖宽
王学明
杨俊�
颜旭旺
陈中超
邓少林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Original Assignee
Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd filed Critical Construction Engineering Co Ltd of China Railway No 5 Engineering Group Co Ltd
Priority to CN2011102666757A priority Critical patent/CN102286930A/zh
Publication of CN102286930A publication Critical patent/CN102286930A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种塔梁同时、独立施工的斜拉桥施工方法。在完成斜拉桥的下部结构(4)施工后,同时进行上部的主塔(1)和主梁(2)施工,充分利用整个施工的工作面,主塔(1)采用双斜钢拱塔原位悬臂拼装方法的施工技术,不影响主梁(2)的施工;主梁(2)采用支架法施工,施工荷载全由支架(5)承担;主塔(1)和主梁(2)施工完成后,施工斜拉索(3)。本发明成功解决了斜拉桥主塔和主梁同时施工的技术问题,充分利用了施工工作面,节约了施工工期,产生较好的经济效益。本发明适用于各种宜用支架法施工的斜拉桥。

Description

一种斜拉桥施工方法
技术领域
本发明涉及一种斜拉桥施工方法。
背景技术
以往的斜拉桥施工中,一般是在下部结构施工完成后,进行主塔的施工,待主塔施工完成后采用挂篮悬浇法或移动支架法,分段进行主梁施工,每施工完一段主梁就挂一组斜拉索,如此反复,直至主梁合龙。对于传统的施工方法,主塔完工后才能开始主梁施工,主梁施工需要分段张拉体内预应力和张挂斜拉索,并由斜拉索承担部分梁体施工荷载,因此主塔和主梁在施工过程中相互影响、相互制约,施工工期过长,施工成本较高。
发明内容
本发明要解决的技术问题:提供一种斜拉桥施工方法,以克服现有技术存在的施工工期过长、成本较高等不足。
为了解决所述的技术问题,本发明采取以下技术方案:在斜拉桥施工中,下部结构施工完成后,充分利用施工工作面,同时进行上部结构的主塔施工和主梁施工,主塔施工和主梁施工互不干涉;当主塔和主梁施工完成后,进行斜拉索施工;主塔采用双斜钢拱塔原位悬臂拼装方法施工,主梁采用支架法施工,梁体施工荷载由主梁下面的支架承担。
采用塔梁同时施工的方法,在完成斜拉桥的下部结构施工后,同时进行上部的主塔和主梁施工,充分利用整个施工的工作面,主塔采用双斜钢拱塔原位悬臂拼装方法的施工技术,不影响主梁的施工;主梁采用支架法施工,施工荷载由支架承担;主塔和主梁施工完成后,施工斜拉索。
主塔和主梁施工不需要斜拉索承担结构荷载或施工荷载,主梁自重由支架承担,主梁施工不受体内预应力张拉和斜拉索施工的制约,主塔和主梁施工相互不影响、不受制约,分别作为一个独立的单位工程进行施工,充分、合理地利用了施工工作面。
主梁支架的设计考虑桥位区水文、地质等情况并结合施工现场实际,采用墩梁式支架结合满堂支架施工。
施工前采用有限元分析软件建立施工各阶段模型,计算和验算各施工阶段的应力、位移和变形,提供数据指导施工。
本发明解决了斜拉桥主塔和主梁同时、独立施工的技术问题,充分利用了整个施工工作面,节约了施工工期,产生较好的经济效益。
附图说明
图1为一种斜拉桥的示意图。
具体实施方式
本发明的实施例:采用塔梁同时施工的方法,在完成斜拉桥的下部结构4施工后,同时进行上部的主塔1和主梁2施工,充分利用整个施工的工作面,主塔1采用无支架施工技术,不影响主梁2的施工;主梁1采用支架法施工,施工荷载全由支架5承担;主塔1和主梁2施工完成后,施工斜拉索3。
主塔1和主梁2施工不需要斜拉索3承担结构荷载或施工荷载,主梁2自重由支架承担,主梁2施工不受体内预应力张拉和斜拉索3施工的制约,主塔1和主梁2施工相互不影响、不制约,分别作为一个独立的单位工程进行施工,充分、合理地利用了施工工作面。

Claims (2)

1.一种斜拉桥施工方法,其特征在于:在斜拉桥施工中,下部结构(4)施工完成后,同时进行上部结构的主塔(1)施工和主梁(2)施工;当主塔(1)和主梁(2)施工完成后,进行斜拉索(3)施工;主塔(1)采用双斜钢拱塔原位悬臂拼装方法的施工技术,主梁(2)采用支架法施工,梁体施工荷载由主梁(2)下面的支架(5)承担。
2.根据权利要求1所述的斜拉桥施工方法,其特征在于:主梁(2)采用支架法施工是指采用墩梁式支架结合满堂支架施工。
CN2011102666757A 2011-09-09 2011-09-09 一种斜拉桥施工方法 Pending CN102286930A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011102666757A CN102286930A (zh) 2011-09-09 2011-09-09 一种斜拉桥施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011102666757A CN102286930A (zh) 2011-09-09 2011-09-09 一种斜拉桥施工方法

Publications (1)

Publication Number Publication Date
CN102286930A true CN102286930A (zh) 2011-12-21

Family

ID=45333660

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011102666757A Pending CN102286930A (zh) 2011-09-09 2011-09-09 一种斜拉桥施工方法

Country Status (1)

Country Link
CN (1) CN102286930A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669224A (zh) * 2013-12-26 2014-03-26 中铁上海工程局有限公司 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工方法及钢管支架
CN105926448A (zh) * 2016-05-03 2016-09-07 中交第三航务工程局有限公司 一种曲线独塔双索面的斜拉桥主塔的施工方法
CN106948267A (zh) * 2017-04-13 2017-07-14 中铁四局集团市政工程有限公司 一种牌坊门楼式桥梁索塔塔柱同步施工方法
CN110629678A (zh) * 2019-10-23 2019-12-31 中国电建集团成都勘测设计研究院有限公司 斜拉桥的拉索辅助支架
CN113430932A (zh) * 2021-07-16 2021-09-24 中交投资南京有限公司 超大跨径人行景观曲线形斜拉桥的组合桥塔及施工方法
CN113774811A (zh) * 2021-10-28 2021-12-10 江西省长大桥隧研究设计院有限公司 一种组合梁斜拉桥上部结构建造方法
CN114197315A (zh) * 2021-12-27 2022-03-18 上海市机械施工集团有限公司 一种由空间索面组合体系斜拉的螺旋双曲结构的施工方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446075A (zh) * 2008-12-30 2009-06-03 江苏沪宁钢机股份有限公司 一种双斜拱塔同步竖转提升施工工法
CN101457514A (zh) * 2008-12-31 2009-06-17 广东省基础工程公司 一种斜拉桥的施工方法
CN101799276A (zh) * 2010-02-26 2010-08-11 中铁大桥局股份有限公司 斜拉桥塔梁同步施工时塔柱及索道管的测量控制方法
KR100993865B1 (ko) * 2009-09-08 2010-11-11 (주)티이솔루션 제진장치를 이용한 사장교 가설 방법
CN201915332U (zh) * 2010-12-14 2011-08-03 中铁大桥局集团第二工程有限公司 悬浇连续梁桥0号块与下部结构同步快捷施工装置

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446075A (zh) * 2008-12-30 2009-06-03 江苏沪宁钢机股份有限公司 一种双斜拱塔同步竖转提升施工工法
CN101457514A (zh) * 2008-12-31 2009-06-17 广东省基础工程公司 一种斜拉桥的施工方法
KR100993865B1 (ko) * 2009-09-08 2010-11-11 (주)티이솔루션 제진장치를 이용한 사장교 가설 방법
CN101799276A (zh) * 2010-02-26 2010-08-11 中铁大桥局股份有限公司 斜拉桥塔梁同步施工时塔柱及索道管的测量控制方法
CN201915332U (zh) * 2010-12-14 2011-08-03 中铁大桥局集团第二工程有限公司 悬浇连续梁桥0号块与下部结构同步快捷施工装置

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103669224A (zh) * 2013-12-26 2014-03-26 中铁上海工程局有限公司 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工方法及钢管支架
CN105926448A (zh) * 2016-05-03 2016-09-07 中交第三航务工程局有限公司 一种曲线独塔双索面的斜拉桥主塔的施工方法
CN105926448B (zh) * 2016-05-03 2017-05-31 中交第三航务工程局有限公司 一种曲线独塔双索面的斜拉桥主塔的施工方法
CN106948267A (zh) * 2017-04-13 2017-07-14 中铁四局集团市政工程有限公司 一种牌坊门楼式桥梁索塔塔柱同步施工方法
CN106948267B (zh) * 2017-04-13 2019-05-14 中铁四局集团市政工程有限公司 一种牌坊门楼式桥梁索塔塔柱同步施工方法
CN110629678A (zh) * 2019-10-23 2019-12-31 中国电建集团成都勘测设计研究院有限公司 斜拉桥的拉索辅助支架
CN113430932A (zh) * 2021-07-16 2021-09-24 中交投资南京有限公司 超大跨径人行景观曲线形斜拉桥的组合桥塔及施工方法
CN113774811A (zh) * 2021-10-28 2021-12-10 江西省长大桥隧研究设计院有限公司 一种组合梁斜拉桥上部结构建造方法
CN114197315A (zh) * 2021-12-27 2022-03-18 上海市机械施工集团有限公司 一种由空间索面组合体系斜拉的螺旋双曲结构的施工方法
CN114197315B (zh) * 2021-12-27 2024-04-26 上海市机械施工集团有限公司 一种由空间索面组合体系斜拉的螺旋双曲结构的施工方法

Similar Documents

Publication Publication Date Title
CN102535343B (zh) 钢桁梁斜拉桥主塔墩顶钢梁架设方法
CN102286930A (zh) 一种斜拉桥施工方法
CN102352604B (zh) 一种钢桁梁桁片单元和钢桁梁结构及其安装方法
CN102121234B (zh) 一种双塔五跨钢桁梁斜拉桥的快速施工方法
CN103669226B (zh) 一种跨江预应力混凝土连续梁桥箱梁0#块支架施工方法
CN102535348B (zh) 一种铰塔斜拉桥斜拉索的张拉方法
CN101775775B (zh) 一种具有自抗裂功能的组合桥梁及其施工方法
CN104775364B (zh) 斜拉桥索塔塔柱钢筋的安装方法
CN202202577U (zh) 预应力托梁拆柱结构
CN101748682A (zh) 采用波形钢腹板的钢-混凝土叠合板组合梁及其施工方法
CN102373671A (zh) 钢桁梁柔性拱桥带拱顶推施工方法
CN103866698B (zh) 对称悬拼桥梁支座端假悬拼施工方法
CN102605717A (zh) 墩顶纵向支撑膺架法
CN207244447U (zh) 一种钢混组合桥梁移动挂篮
CN104594201B (zh) 一种利用单侧墩旁托架架设墩顶钢梁的方法
CN102493353B (zh) 桥梁施工中大型设备的起吊方法及墩顶提升吊架
CN204570446U (zh) 一种预制拼装t型简支梁
CN203613467U (zh) 斜置拱塔双索面预应力混凝土斜拉桥中拱塔施工中的钢管支架
CN203583674U (zh) 一种装配式混凝土抗震梁柱框架
CN104775363B (zh) 上塔柱钢筋节段的组拼方法
CN102493363B (zh) 连续梁0号块快速施工方法
CN104047223A (zh) 轻型组合结构桥梁及其施工方法
CN203530864U (zh) 大跨度混凝土连续梁桥边跨合拢装置
CN115162697B (zh) 一种异形柱施做用工字钢悬挑平台及施做方法
CN206279454U (zh) 活动式组合贝雷架平台、可移动式组合贝雷架搭设平台

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20111221