BR112012028669A2 - método para controlar o gerenciamento da formação de tambores, e, planta para produção de pneus - Google Patents
método para controlar o gerenciamento da formação de tambores, e, planta para produção de pneusInfo
- Publication number
- BR112012028669A2 BR112012028669A2 BR112012028669A BR112012028669A BR112012028669A2 BR 112012028669 A2 BR112012028669 A2 BR 112012028669A2 BR 112012028669 A BR112012028669 A BR 112012028669A BR 112012028669 A BR112012028669 A BR 112012028669A BR 112012028669 A2 BR112012028669 A2 BR 112012028669A2
- Authority
- BR
- Brazil
- Prior art keywords
- time
- workstations
- production plant
- equal
- tire production
- Prior art date
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/06—Pneumatic tyres or parts thereof (e.g. produced by casting, moulding, compression moulding, injection moulding, centrifugal casting)
- B29D30/08—Building tyres
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/005—General arrangement or lay-out of plants for the processing of tyres or parts thereof
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/0016—Handling tyres or parts thereof, e.g. supplying, storing, conveying
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/06—Pneumatic tyres or parts thereof (e.g. produced by casting, moulding, compression moulding, injection moulding, centrifugal casting)
- B29D30/08—Building tyres
- B29D30/20—Building tyres by the flat-tyre method, i.e. building on cylindrical drums
- B29D30/24—Drums
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/005—General arrangement or lay-out of plants for the processing of tyres or parts thereof
- B29D2030/0055—Optimization of the cycle times of the tyre manufacturing process, e.g. adaptation of the tyre building process to the vulcanization process
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/06—Pneumatic tyres or parts thereof (e.g. produced by casting, moulding, compression moulding, injection moulding, centrifugal casting)
- B29D30/08—Building tyres
- B29D30/10—Building tyres on round cores, i.e. the shape of the core is approximately identical with the shape of the completed tyre
- B29D2030/105—Building tyres on round cores, i.e. the shape of the core is approximately identical with the shape of the completed tyre the cores being movable
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/06—Pneumatic tyres or parts thereof (e.g. produced by casting, moulding, compression moulding, injection moulding, centrifugal casting)
- B29D30/08—Building tyres
- B29D30/20—Building tyres by the flat-tyre method, i.e. building on cylindrical drums
- B29D2030/202—Building tyres by the flat-tyre method, i.e. building on cylindrical drums the building drums being movable, i.e. not permanently connected to a fixed frame
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B29—WORKING OF PLASTICS; WORKING OF SUBSTANCES IN A PLASTIC STATE IN GENERAL
- B29D—PRODUCING PARTICULAR ARTICLES FROM PLASTICS OR FROM SUBSTANCES IN A PLASTIC STATE
- B29D30/00—Producing pneumatic or solid tyres or parts thereof
- B29D30/06—Pneumatic tyres or parts thereof (e.g. produced by casting, moulding, compression moulding, injection moulding, centrifugal casting)
- B29D30/08—Building tyres
- B29D30/20—Building tyres by the flat-tyre method, i.e. building on cylindrical drums
- B29D2030/206—A plurality of building drums being mounted on a fixture or supporting device, e.g. turret or turntable
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Tyre Moulding (AREA)
Abstract
método para controlar o gerenciamento da formação de tambores, e, planta para produção de pneus. a presente invenção diz respeito a um método para controlar o gerenciamento de tambores de formação na construção de pneus para rodas de veículos, e a uma planta para produção de pneus para rodas de veículos. a plantacompreende pelo menos uma linha de construção (12, 14) incluindo oelo menos um conjunto (17,35,44) de "m" estações de trabalho (17a, 17b;35a, 35b; 44a, 44b), cada qual adaptada para formar pelo menos uma porção de um componente de pneu (2); dispositivos para alimentar e capturar "n" tambores em formação (13, 15), cada um de uma vez, para a, e a partir da linha de construção (12, 14); cada intervalo de tempo igual a um ciclo de tempo (tc); dispositivos de tranferência (31;37,38,39,41,42;45,47,48) para, respectivamente, levar em direção a, e, afastar "m" tambores de formação distintos (13; 15), para as, e a partir das "m" estações de trabalho distintas (17a, 17b; 35a, 35b; 33a, 44b) do mencionado conjunto (17,35,44); sendo que cada uma das mencionadas "m" estações de trabalho (17a, 17b; 35a,35b; 44a, 44b), respectivamente, recebeeliberaumtambordeformação (13,15),a cada intervalo de tempo igual a um múltiplo "m" do mencionado ciclo de tempo (tc); sendo que "m" é maior do que, ou igual a 2, e "n" é maior do que, ou igual a "m".
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
ITMI20100967 | 2010-05-28 | ||
US35154310P | 2010-06-04 | 2010-06-04 | |
PCT/IB2011/051969 WO2011148283A1 (en) | 2010-05-28 | 2011-05-04 | Method of controlling the management of forming drums in building tyres for vehicle wheels and plant for production of tyres for vehicle wheels |
Publications (2)
Publication Number | Publication Date |
---|---|
BR112012028669A2 true BR112012028669A2 (pt) | 2016-08-16 |
BR112012028669B1 BR112012028669B1 (pt) | 2020-04-22 |
Family
ID=43432018
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
BR112012028669A BR112012028669B1 (pt) | 2010-05-28 | 2011-05-04 | método para controlar o gerenciamento da formação de tambores, e, planta para produção de pneus |
Country Status (7)
Country | Link |
---|---|
US (1) | US20130078058A1 (pt) |
EP (1) | EP2576195B1 (pt) |
JP (1) | JP5907953B2 (pt) |
KR (1) | KR101812137B1 (pt) |
CN (1) | CN102892574B (pt) |
BR (1) | BR112012028669B1 (pt) |
WO (1) | WO2011148283A1 (pt) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP2925511B3 (en) * | 2012-11-30 | 2018-12-12 | Pirelli Tyre S.p.A. | Method and plant for building tyres |
ITMI20122194A1 (it) * | 2012-12-20 | 2014-06-21 | Pirelli | Metodo ed impianto per confezionare pneumatici |
ITMI20122214A1 (it) * | 2012-12-21 | 2014-06-22 | Pirelli | Metodo e impianto per confezionare pneumatici per ruote di veicoli |
CN107073852B (zh) * | 2014-12-15 | 2019-03-29 | 倍耐力轮胎股份公司 | 用于管理胎体结构构建线的方法、用于构建轮胎胎体结构的工艺和设备 |
US11584100B2 (en) | 2015-09-30 | 2023-02-21 | Pirelli Tyre S.P.A. | Method and apparatus for controlling the feed of semifinished products in a tyre building process |
EP3990270B1 (en) * | 2019-06-26 | 2023-08-02 | Pirelli Tyre S.p.A. | Method for building tyres |
CN116600978B (zh) * | 2020-12-17 | 2024-05-14 | 倍耐力轮胎股份公司 | 用于管理用于构建车辆车轮用轮胎的过程的方法和构建线 |
Family Cites Families (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4088524A (en) * | 1976-04-14 | 1978-05-09 | Taylor Don A | Method and apparatus for continuously applying tread material to tire casings and curing the same |
US4092090A (en) * | 1977-05-18 | 1978-05-30 | Nrm Corporation | Tire curing system |
JP3124560B2 (ja) * | 1990-12-28 | 2001-01-15 | 株式会社ブリヂストン | プライ部材の成型方法 |
JP3187954B2 (ja) * | 1992-07-21 | 2001-07-16 | 三菱重工業株式会社 | タイヤ成形システム |
JP2969034B2 (ja) * | 1993-06-18 | 1999-11-02 | 東京エレクトロン株式会社 | 搬送方法および搬送装置 |
JPH11288995A (ja) * | 1998-04-04 | 1999-10-19 | Tokyo Electron Ltd | 搬送システム及び処理装置 |
KR100319891B1 (ko) * | 1999-06-29 | 2002-01-10 | 윤종용 | 웨이퍼용 열처리 방법 |
ES2249310T3 (es) * | 1999-12-01 | 2006-04-01 | Pirelli Pneumatici S.P.A. | Instalacion para la produccion de neumaticos de tipos diferentes de manera simultanea. |
JP5159013B2 (ja) * | 2000-05-26 | 2013-03-06 | ピレリ・タイヤ・ソチエタ・ペル・アツィオーニ | 異なるタイプのタイヤを同時に製造するためのプラント |
EP1584439B1 (en) * | 2002-11-25 | 2007-09-12 | Bridgestone Corporation | Vulcanized tire size allocating method, tire manufacturing method, and vulcanizing process setting method |
US7089076B2 (en) * | 2003-05-16 | 2006-08-08 | Fsi International, Inc. | Scheduling multi-robot processing systems |
US20040238102A1 (en) * | 2003-05-30 | 2004-12-02 | Jean-Claude Girard | Method for manufacturing tires on a flexible manufacturing system |
US7195047B2 (en) * | 2003-12-11 | 2007-03-27 | The Goodyear Tire And Rubber Company | Tire manufacturing module and method of manufacturing tires |
JP2006297778A (ja) * | 2005-04-21 | 2006-11-02 | Bridgestone Corp | タイヤの製造方法、および、それに用いるタイヤ製造システム |
US7644829B2 (en) * | 2006-08-07 | 2010-01-12 | Plastipak Packaging, Inc. | Plastic container including a grip feature |
CN101522403B (zh) * | 2006-10-12 | 2012-08-29 | 倍耐力轮胎股份公司 | 充气轮胎的制造工艺及相关的构建生产线和组装设备 |
JP4904173B2 (ja) * | 2007-01-31 | 2012-03-28 | 昭和アルミニウム缶株式会社 | 複数品種の缶体の製造方法および缶体の分別装置 |
KR101427355B1 (ko) * | 2007-09-27 | 2014-08-07 | 피렐리 타이어 소시에떼 퍼 아찌오니 | 차륜용 타이어 제조방법 및 장치 |
US8535465B2 (en) | 2007-11-30 | 2013-09-17 | Pirelli Tyre S.P.A. | Process and apparatus for manufacturing tyres for vehicle wheels |
EP2291282B1 (en) | 2008-06-27 | 2013-02-27 | Pirelli Tyre S.P.A. | Process and plant for building tyres for vehicle wheels |
-
2011
- 2011-05-04 KR KR1020127029566A patent/KR101812137B1/ko active IP Right Grant
- 2011-05-04 CN CN201180023754.3A patent/CN102892574B/zh active Active
- 2011-05-04 WO PCT/IB2011/051969 patent/WO2011148283A1/en active Application Filing
- 2011-05-04 EP EP11724460.8A patent/EP2576195B1/en active Active
- 2011-05-04 BR BR112012028669A patent/BR112012028669B1/pt active IP Right Grant
- 2011-05-04 US US13/700,350 patent/US20130078058A1/en not_active Abandoned
- 2011-05-04 JP JP2013511760A patent/JP5907953B2/ja active Active
Also Published As
Publication number | Publication date |
---|---|
KR20130092973A (ko) | 2013-08-21 |
BR112012028669B1 (pt) | 2020-04-22 |
CN102892574B (zh) | 2015-12-16 |
JP5907953B2 (ja) | 2016-04-26 |
WO2011148283A1 (en) | 2011-12-01 |
EP2576195B1 (en) | 2015-07-15 |
KR101812137B1 (ko) | 2017-12-26 |
US20130078058A1 (en) | 2013-03-28 |
CN102892574A (zh) | 2013-01-23 |
EP2576195A1 (en) | 2013-04-10 |
JP2013530067A (ja) | 2013-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
BR112012028669A2 (pt) | método para controlar o gerenciamento da formação de tambores, e, planta para produção de pneus | |
BR112019000718A2 (pt) | processo para a produção de geopolímero ou compósito de geopolímero | |
BR112017004046A2 (pt) | processo de produção de butadieno e hidrogênio, a partir de etanol em duas etapas reacionais de baixo consumo em água e em energia | |
BR112014014062A2 (pt) | produção de 1,3-dienos por conversão enzimática de 3- hidroxialc-4-enoatos e/ou 3-fosfonoxialc-4-enoatos | |
GB2495362B (en) | Decode-time computer instruction optimization | |
BR112014031425A2 (pt) | microrganismo recombinante para produção fermentativa de metionina | |
BR112013033176A2 (pt) | método para produzir uma modificação direcionada em um gene de fertilidade masculina, planta, molécula de ácido nucleio isolada, construto de expressão | |
BR112013019811A2 (pt) | processo para a produção de butadieno e organismo microbiano que não ocorre naturalmente. | |
BR112012015490A2 (pt) | adoçantes e processo para a sua produção | |
BR112012022506A2 (pt) | preparação de metionina ou selenometionina a partir de homosserina através de um intermediário de lactona. | |
CR20190057A (es) | PROCEDIMIENTO DE PREPARACIÓN DE 5-FLUORO-1H-PIRAZOLOPIRIDINAS SUSTITUIDAS (Divisional 2014-0237) | |
BR112015005353A2 (pt) | cordão de reforço para produtos elastômeros, em particular para pneu de veículo, e pneu de veículo | |
BR112014015123A2 (pt) | processo para a produção de um ou mais alcenos ou compostos aromáticos | |
BR112012011961A2 (pt) | processo para produzir cloretos de ácido 5-flúor-1-alquil-3-fluoralquil-1h-pirazol-4-carboxílico | |
BR112015005081A8 (pt) | Método para produzir um polissacarídeo capsular tendo um sorotipo de pneumococo | |
BR112013019589A2 (pt) | processo para produzir aromáticos a partir de uma corrente de alimentação de hidrocarboneto. | |
BR112012020824A2 (pt) | processo para produção de corpos moldados revestidos. | |
BR112013026660A2 (pt) | métodos ou processos para produção de depsipeptídeos macrocíclicos e intermediários | |
BR112012015166A2 (pt) | "processo, instalação, e, método para construção de diferentes tipos de pneus crus para rodas de veículos". | |
BR112016009324A2 (pt) | Microrganismo, e, método de produção de l-lisina | |
BR112017001177A2 (pt) | processo para a purificação de poliovírus a partir de culturas celulares | |
WO2012178163A3 (en) | Optimal network configuration repair | |
MX2014006944A (es) | Metodo, proceso y planta para controlar la fabricacion de llantas para ruedas de vehiculo. | |
BR112015014335A2 (pt) | (6r,10r)-6,10,14-trimetilpentadecan-2-ona preparada a partir de 6,10-dimetilundec-5-en-2-ona ou 6,10-dimetilundeca-5,9-dien-2-ona | |
FR3014097B1 (fr) | Procede de production de 1,3-butadiene a partir d'une charge comprenant de l'ethanol |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
B06F | Objections, documents and/or translations needed after an examination request according [chapter 6.6 patent gazette] | ||
B06U | Preliminary requirement: requests with searches performed by other patent offices: procedure suspended [chapter 6.21 patent gazette] | ||
B09A | Decision: intention to grant [chapter 9.1 patent gazette] | ||
B16A | Patent or certificate of addition of invention granted [chapter 16.1 patent gazette] |
Free format text: PRAZO DE VALIDADE: 20 (VINTE) ANOS CONTADOS A PARTIR DE 04/05/2011, OBSERVADAS AS CONDICOES LEGAIS. |