WO2020048102A1 - 一种起重设备 - Google Patents
一种起重设备 Download PDFInfo
- Publication number
- WO2020048102A1 WO2020048102A1 PCT/CN2019/076667 CN2019076667W WO2020048102A1 WO 2020048102 A1 WO2020048102 A1 WO 2020048102A1 CN 2019076667 W CN2019076667 W CN 2019076667W WO 2020048102 A1 WO2020048102 A1 WO 2020048102A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- balance
- trolley
- trolleys
- working condition
- balance beam
- Prior art date
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/36—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
- B66C23/50—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes mounted on railway vehicles, e.g. breakdown cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/18—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes
- B66C23/36—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes specially adapted for use in particular purposes mounted on road or rail vehicles; Manually-movable jib-cranes for use in workshops; Floating cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/60—Derricks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/72—Counterweights or supports for balancing lifting couples
- B66C23/74—Counterweights or supports for balancing lifting couples separate from jib
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/72—Counterweights or supports for balancing lifting couples
- B66C23/78—Supports, e.g. outriggers, for mobile cranes
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C23/00—Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
- B66C23/62—Constructional features or details
- B66C23/84—Slewing gear
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C9/00—Travelling gear incorporated in or fitted to trolleys or cranes
- B66C9/10—Undercarriages or bogies, e.g. end carriages, end bogies
- B66C9/12—Undercarriages or bogies, e.g. end carriages, end bogies with load-distributing means for equalising wheel pressure
Definitions
- the present disclosure relates to the technical field of construction machinery, and in particular, to a lifting device.
- Super-large lifting equipment is a new type of crane, which has the advantages of large lifting weight and large lifting torque, and is often used for the lifting of super-large and over-weight parts.
- the chassis system accounts for about 1/3 of the cost of the whole machine.
- the foundation treatment in the process of lifting oversized and overweight parts is a difficult problem and an irreversible process, which can be solved at a greater cost. The larger the specific ground pressure that the ground needs to withstand It will also cost more.
- the front and rear balance trolleys are arranged in the same way, and the counterweight is fixed on the platform and cannot be moved. Generally, it is increased by increasing the weight of the platform counterweight, strengthening the structure of the whole machine or adjusting the size of the track Load capacity of the whole machine. In this way, the lifting moment of the ring-rail crane is changed by adjusting the distance between the front truck and the counterweight, and the entire conversion process is very complicated.
- the improvement of load carrying capacity can only be achieved by replacing reinforced structural components, increasing the number of counterweights, or adjusting the diameter of the track.
- the load carrying capacity is limited, the cost is large, the parts are not versatile, the utilization rate is not high, and it is subject to transportation conditions Restrictions, structural components can not be strengthened without limit.
- the ground specific pressure is also increased, which puts forward higher requirements for ground treatment.
- the lifting capacity will be wasted in the case of small lifting weights. After all, the frequency of use of super heavy lifting in actual work is not high.
- Embodiments of the present disclosure provide a lifting device that can simultaneously meet the needs of the lifting device under different lifting weights.
- a lifting device including:
- a chassis including a track and a plurality of first balancing trolleys, each of the first balancing trolleys being disposed on the track and located in a front area below the boom assembly;
- each first balancing trolley in the first working condition, includes a first balancing beam and two first trolleys, and the first balancing beam overlaps the two first trolleys; in the second operating condition Next, each first balanced trolley also includes a balanced beam group and a trolley group, the trolley group is located outside the first trolley along the track extension direction, and the balanced beam group is overlapped above the first balanced beam and the trolley group ; The lifting weight of the first working condition does not exceed the preset lifting weight, and the lifting weight of the second working condition exceeds the preset lifting weight.
- the trolley set includes a second trolley
- the balanced beam set includes a second balanced beam
- two ends of the second balanced beam are respectively overlapped above the first balanced beam and the second trolley.
- the second balance beam includes a main load bearing portion and an abutting portion connected to each other, the main load bearing portion is overlapped on the first balance beam, and the abutment portion ranges from an end connected to the main load bearing portion to a free end cross-sectional area. It gradually decreases and inclines downward with respect to the main bearing portion until the free end of the abutting portion contacts the top surface of the second vehicle.
- the trolley set includes at least two second trolleys
- the balance beam set includes at least two second balance beams
- each of the at least two second balance beams overlaps the first balance beam Above the balance beam, at least two second trolleys, and two of the other second flat beams.
- At least two second balance beams include an upper balance beam and a lower balance beam.
- the lower balance beam has the same structure as the first balance beam and will have at least The two second cars overlap each other, and the upper balance beam overlaps the first balance beam and each lower balance beam.
- the lifting device includes a chassis and a boom assembly
- the chassis includes a track and a plurality of first balance trolleys, each first balance trolley is disposed on the track and located in a front area below the boom assembly;
- each first balancing trolley includes a balancing beam and two trolleys arranged along the track extension direction, and the balancing beams overlap the two trolleys; in the second operating condition, each The first balance trolley is provided with a balance beam and a trolley. The added trolley is located outside the original trolley along the track extension direction. At least part of the added balance beam overlaps the added trolley and the original balance beam.
- a balance beam is added for each additional trolley, and the added balance beam overlaps the additional trolley and the lower stage balance beam.
- each first balance trolley under the first working condition, includes a first balance beam and two first trolleys, and the first balance beam overlaps the two first trolleys;
- a second balance beam and a second carriage are added to each of the first balance carriages. The second carriage is located outside the first carriage along the track extension direction, and the second balance beam overlaps the second carriage. Above the car and the first balance beam.
- the added balance beam includes a main load bearing portion and an abutting portion which are connected to each other.
- the main load bearing portion is overlapped on the bottom balance beam, and the abutment portion ranges from an end connected to the main load bearing portion to a free end cross-sectional area. It gradually decreases and inclines downward with respect to the main bearing portion until the free end of the abutting portion contacts the top surface of the increasing trolley.
- the number of trolleys added to each first balanced trolley is an even number.
- the added balancing beams include an upper balancing beam and a lower balancing beam.
- the lower balancing beam has the same structure as the original balancing beam and will be added. They are overlapped one by one, and the upper balance beam is overlapped on each lower balance beam.
- the chassis further includes a plurality of second balance trolleys, each of which is disposed on the track and located in a rear area below the boom assembly.
- the track is a circular track
- the first and second balance trolleys are arranged side by side on the inner ring track and the outer ring track, and the balance trolleys at the corresponding positions on the inner ring track and the outer ring track have the same structure. .
- each second balance trolley under the second working condition, also adds a balance beam and a trolley.
- the additional trolley is located outside the original trolley along the track direction, and the additional balance beam overlaps the Added trolley and bottom balance beam above.
- the chassis further includes a swing platform, and the swing platform includes:
- the front vehicle platform in the first working condition, includes a first beam section and two support platforms, the first beam section is located between the two support platforms, and the longitudinal beam is connected to the first beam section; in the second condition A second beam section is added to both ends of the first beam section, and the second beam section is connected to the supporting platform on the corresponding side.
- the longitudinal beam includes a plurality of mounting sections. Under the first working condition, each mounting section forms a longitudinal beam that is generally parallel to the plane on which the track is located; in the second working condition, the mounting section connected to the front vehicle platform It is inclined with respect to the plane on which the track is located, and the first end connected to the front vehicle platform of the mounting section is higher than the second end connected to the adjacent mounting section.
- the boom assembly includes two masts and two main booms, the bottom ends of the two main booms are respectively connected to a support platform, and the bottom ends of the two masts are respectively connected to a support platform.
- the boom assembly includes two main arms, and the two main arms are correspondingly connected at the top and bottom positions; wherein, in the first working condition, the bottom positions of the two main booms The first connecting rod sections connected to each other; in the second working condition, the first connecting rod sections are added to the bottom positions of the two main arms; or
- the jib assembly includes two jib, the two jib are connected correspondingly at the top and bottom positions; in the first working condition, the bottom position of the two jib is connected by two first connecting rods connected in the length direction In the second working condition, the first connecting rod section is added to the bottom position of the two jib.
- the boom assembly includes two main booms, two masts, and two pullers.
- the bottom end of the mast is hinged on the chassis adjacent to the bottom end of the corresponding main boom, and the top end is connected to the corresponding main boom through the puller. Connected at the top, correspondingly connected between the top and bottom of the two masts;
- the boom assembly includes two main booms and two masts, and the two main booms and / or two masts have a trapezoidal structure from top to bottom under a second working condition.
- the lifting equipment of some embodiments of the present disclosure at least increases the balance beam group and the trolley group in the first balanced trolley under the second working condition to increase the support span of the first balanced trolley.
- the hoisting capacity of the lifting equipment can be configured according to the actual hoisting demand, which can reduce the waste of hoisting capacity when the hoisting weight is small, and can increase the hoisting capacity through the structure when the hoisting weight is heavy, and can also reduce the grounding of the ground. Specific pressure, thereby reducing the difficulty and cost of foundation treatment.
- FIG. 1 is a schematic structural diagram of an embodiment of a lifting device according to the present disclosure
- FIG. 2 is a top view of an embodiment of the lifting equipment of the present disclosure
- 3A and 3B are schematic structural diagrams of a slewing platform in a lifting device of the present disclosure under a first working condition and a second working condition, respectively;
- FIG. 4 is a schematic structural diagram of an embodiment of a swing platform in a lifting device of the present disclosure
- FIG. 5 is a schematic structural diagram of a setting of a balancing trolley of a lifting device of the present disclosure under a first working condition
- FIG. 6 is a schematic structural diagram of the setting of a balancing trolley of the lifting equipment in the second working condition of the present disclosure
- FIG. 7 is an enlarged view of a first balance trolley in FIG. 6;
- FIG. 8 is a force diagram of the first balance trolley in FIG. 7;
- FIG. 9A and FIG. 9B are schematic diagrams of ground areas of a balanced trolley in a first working condition and a second working condition in the present disclosure, respectively;
- FIG. 10A and FIG. 10B are schematic diagrams of a supporting span of a balanced trolley layout in a first working condition and a second working condition in the present disclosure, respectively;
- FIG. 11 is a schematic structural diagram of a chassis in a lifting device of the present disclosure.
- FIGS. 12A and 12B are schematic structural diagrams of a mast in a lifting device in a first working condition and a second working condition, respectively;
- FIGS. 13A and 13B are schematic structural diagrams of a main boom in a lifting device of the present disclosure under a first working condition and a second working condition, respectively;
- FIG. 14 is a schematic structural diagram of a lifting device of the present disclosure under a first working condition
- FIG. 15 is a schematic structural diagram of a lifting device of the present disclosure under a second working condition.
- first and second appearing in the present disclosure are merely for convenience of description, to distinguish different component parts having the same name, and do not indicate a sequential or primary-secondary relationship.
- the improvement of the carrying capacity of the entire vehicle will also increase the specific pressure on the ground, and even increase the area occupied by the entire machine.
- the requirements for the bearing capacity of the foundation and the site's adaptation conditions will be greatly increased. Difficulty in handling foundations and entire volumes. After all, the second working condition is a minority in comparison. Under normal lifting conditions, the lifting equipment is in a wasteful state of lifting capacity, causing the equipment to be expensive to use.
- the current front and rear balance trolleys in the lifting equipment use the same arrangement, but in the actual lifting process, due to the role of the front load, the first balance trolley in the front bears much more force than the rear.
- the second balance trolley the uneven load of the two balance trolleys causes the ground specific pressure under the two balance trolleys to be different, and the ground specific pressure under the first balance trolley is also much larger than the second balance trolley.
- the ground must be processed according to the ground specific pressure under the first balanced trolley, which increases the cost and difficulty of foundation treatment.
- the present disclosure provides a lifting device.
- the lifting device includes a chassis and a boom assembly, and the boom assembly is integrally disposed on the chassis.
- the boom assembly includes a main boom 5, a mast 4, and a pulling member 7.
- the main boom 5 is a main boom part of a front end of a lifting device, and an “A” type or parallel double-truss boom structure can be adopted; the mast 4 It is set at an angle with the main boom 5 and its function is to change the working range of the boom and improve the lifting performance.
- the bottom end of the mast 4 is hinged to the chassis, and the bottom end is located near the bottom end of the main arm 5.
- the top end is connected to the top end of the main arm 5 through a pulling member 7 and is also connected to the chassis through a mast bracket 8 or a suspension pull plate.
- Platform weights 9 in the rear area are connected.
- the pulling member 7 may be a pulling plate, a rope, or a truss.
- the mast bracket 8 may provide a pulling force for the mast 4 or support the mast 4.
- a luffing pulley group 6 is provided at a position where the pulling member 7 is connected to the mast 4, and the expansion and contraction of the wire rope can be controlled by the pulley group to pull the main arm 5 to rotate along the lower hinge point through the pulling member 7 to realize the crane luffing.
- the chassis includes a track, a slewing platform 1, a plurality of first balance trolleys 2 and a plurality of second balance trolleys 2 ′ provided on the track, and each of the first balance trolleys 2 is located below the boom assembly.
- each second balance trolley 2 ' is located in the rear area below the boom assembly.
- the track can be in a circular ring shape.
- the bottom of the balancing trolley is a wheel structure. The wheels are pressed on the annular track.
- the whole machine controls the driving motor on the balancing trolley through a hydraulic system to drive the wheels of the balancing trolley to rotate on the annular track. turn around.
- the slewing platform 1 is overlapped on each of the first and second balance trolleys 2 and 2 ', and the entire boom assembly can be disposed on the slewing platform 1.
- the main boom 5, the mast 4, the platform counterweight 9, Both the hoisting system 3 and the power system 10 can be provided on the slewing platform 1.
- the power system 10 provides power for the lifting equipment, and the platform counterweight 9 is used to maintain the stability of the entire vehicle.
- each of the first balance trolleys 2 includes a balance beam and two trolleys arranged along the track extension direction.
- the balance beam is overlapped on the two trolleys, and the second balance trolley
- the vehicle 2 ′ can adopt the same structure as the first balanced trolley 2, and the rotary platform 1 is overlapped on each balanced beam.
- the slewing platform 1 is used to connect the first balance trolley 2 and the second balance trolley 2 'on the lifting equipment, and can be used to install a boom assembly, a power unit 10, a platform counterweight 9, and a control room frame.
- the hoisting weight of the first working condition does not exceed the preset hoisting weight, and the hoisting working condition is a small weight.
- the preset lifting weight can be set according to the lifting capacity of different cranes.
- a balance beam group and a trolley group are added to each of the first balanced trolleys 2.
- the added trolley group is located at the outer side of the original trolley along the track direction.
- the balance beam overlaps the added trolley and the original balance beam, and the rotary platform 1 overlaps the top balance beam.
- the at least partially increased balance beam can be directly overlapped on the added trolley, or the partially increased balance beam can be indirectly overlapped on the added trolley.
- the lifting weight of the second working condition exceeds the preset lifting weight, which is an overweight lifting working condition.
- the load of the first balance trolley 2 is much greater than that of the second balance trolley 2 '.
- the first balance trolley 2 is off the ground.
- the increase of grounding pressure is greater than that of the structure.
- the structure can be increased by the first balance trolley 2 providing a supporting point for the slewing platform 1, which effectively increases Grounding area, without changing the chassis system, can increase the load capacity of the whole machine and reduce the ground specific pressure, thereby reducing the difficulty and cost of ground treatment.
- the ground specific pressure refers to the vertical load on a unit area of an object in contact with the ground.
- the balance trolley can realize the walking action on the circular track, and adopts multi-level balance beam to realize the equalizing force.
- Multiple vehicles are arranged on the same track, which can make full use of the chassis, increase the contact area, effectively reduce the ground specific pressure, simple foundation treatment, and can greatly reduce operating costs.
- the solution of this embodiment of the present disclosure can configure the lifting capacity of the lifting equipment according to the actual lifting requirements when the lifting equipment is assembled, which can both When the lifting weight is small, the waste of lifting capacity is reduced, and the lifting capacity can be increased by the structure when the weight is heavy, and the ground pressure of the ground can be reduced, thereby reducing the difficulty and cost of foundation treatment.
- This kind of lifting equipment can realize multiple uses of one machine, and the load capacity of the whole machine can be improved by adding a few components on the basis of the existing ring-rail crane equipment.
- the number of added trolleys for each first balanced trolley 2 is an even number.
- the added balancing beams include an upper balancing beam and a lower balancing beam.
- the balance beam has the same structure and overlaps the additional trolleys.
- a lower-level balance beam needs to be added, and the upper-level balance beam is overlapped on each lower-level balance beam.
- the number of trolleys is increased to two.
- Two lower balancing beams are used to span the two trolleys.
- the upper balancing beams are used to span the two lower balancing beams at the bottom to ensure that four The trolleys are evenly stressed.
- a balance beam needs to be added accordingly.
- the added balance beam overlaps the additional trolley and the lower stage balance beam.
- One end of the balancing beam is directly attached to the added trolley.
- each first balanced trolley 2 includes a first balanced beam 22 and two first trolleys 21.
- the first balanced beam 22 Overlap the two first cars 21.
- the structure of the two first trolleys 21 is the same.
- the first trolley 21 may adopt a trapezoidal structure, and the bottom is provided with a guide wheel that moves along the track.
- the first balance beam 22 may be designed as an inverted trapezoidal structure. The tops of the two first trolleys 21 are fitted into the space between the two first trolleys 21 to improve the support stability and overall rigidity of the balanced trolleys.
- each of the first balanced trolleys 2 maintains the structural configuration under the first working condition, and the added trolley group includes a second trolley 23,
- the two additional sets of balance include a second balance beam 24, the second carriage 23 is located outside the first carriage 21 along the track extension direction, and the two ends of the second balance beam 24 overlap the second carriage 23 and the first Above a balance beam 22.
- This embodiment adopts a form in which two-stage balance beams are superposed in the height direction.
- the structure is simple, and a single first balance trolley 2 can be moved outward to the supporting point of the slewing platform 1, and two pairs of first balance trolleys are added.
- the supporting distance of the slewing platform 1 effectively increases the ground area and reduces the ground specific pressure, thereby reducing the difficulty and cost of ground treatment.
- the second balance beam 24 includes a main load bearing portion 241 and an abutting portion 242 connected to each other.
- the main load bearing portion 241 is overlapped on the bottom balance beam, and the abutting portion 242 is connected with the main load.
- the cross-sectional area from one end to the free end of the bearing portion 241 gradually decreases, and is inclined downward with respect to the main bearing portion 241 until the free end of the abutting portion 242 contacts the top surface of the increased balance trolley.
- the first balance trolley 2 can form a stable supporting structure while saving weight.
- the main bearing portion 241 of the second balance beam 24 is overlapped on the first balance beam 22.
- One end of the abutting portion 242 is connected to the main bearing portion 241 and the other end is in contact with the top surface of the second trolley 23.
- the top of the second balance beam 24 is provided with a mounting interface, which can realize the connection between the swing platform 1 and the first balance trolley 2.
- the two first trolleys 21 collectively provide support for the first balance beam 22, and the first and second trolleys 22 and 23 collectively provide support for the second balance beam 24.
- the slewing platform 1 is set on the second balance beam 24 of the first balance trolley 2 so that the lifting weight is shared by the three trolleys, which not only increases the support span, but also Reduce the force of each trolley when working, and ensure that the forces of three trolleys are uniform, thereby reducing the size of the structural parts, the specifications of supporting parts and the transportation parameters of the balanced trolley.
- the front end of the turning platform 1 is straddled on two first balanced trolleys 2 and the rear end is straddled on two second balanced trolleys 2 ′, which can ensure that the left and right two sets of balanced trolleys are stressed. Uniform and stable work.
- the supporting span between the two first balanced trolleys 2 is L1; in the second working condition, referring to FIG. 10B, by increasing the platform
- the support span between the vehicle and the balance beam and the two first balance trolleys 2 is L2, and L2> L1.
- the trolley set includes at least two second trolleys 23, the balance beam set includes at least two second balance beams 24, and each second balance beam 24 of the at least two second balance beams 24 It is overlapped above any two of the first balance beam 22, the at least two second trolleys 23, and the other second flat beams 24.
- This embodiment can further increase the load carrying capacity of the crane in the second working condition.
- This setting method can adopt the following two types of structures, which will be given separately below.
- the second trolley 23 is an even number.
- At least two second balance beams 24 include an upper balance beam and a lower balance beam.
- the lower balance beam has the same structure as the first balance beam 22 and has at least two
- the second trolley 23 is overlapped one by one, and the upper balance beam is overlapped on the first balance beam 22 and each lower balance beam.
- a lower balance beam needs to be added.
- This embodiment can reduce the height of the first balanced trolley 2 after the expanded structure, reduce the influence on the original crane structure, and make the structure symmetrical and stable, and can also make full use of the original balanced beam structural components.
- a second balance beam 24 is required for each additional second vehicle 23, for each additional second vehicle 23, a second balance beam 24 is required. One end of the second balance beam 24 is directly connected to the second vehicle 23, and the other end is overlapped. Above the lower-stage balance beam, the lower-stage balance beam may be the first balance beam 22 or the second balance beam 24. This structure can flexibly increase the number of the second vehicles 23, so as to gradually increase the chassis support strength according to the requirements of the lifting weight.
- the chassis includes a subgrade box 30, which is laid on the ground and has a ring plate structure with a large area, which can reduce the pressure of the lifting equipment on the ground.
- the track is a circular track, which is laid on the subgrade box, and the balance trolley can rotate along it.
- the first balance trolley 2 and the second balance trolley 2 ′ are arranged side by side on the inner ring track 31 and the outer ring track 32, and the first balance of the corresponding positions on the inner ring track 31 and the outer ring track 32
- the structure of the trolley 2 is the same, and the structure of the second balanced trolley 2 'at the corresponding position on the inner ring track 31 and the outer ring track 32 is the same.
- two sets of first balance trolleys 2 are spaced in the front area of the track, and each group of first balance trolleys 2 includes two correspondingly arranged first and second balance trolleys on the inner ring track 31 and the outer ring track 32.
- each first balanced trolley 2 is added with a balanced beam group and a trolley group, including three trolleys and two balanced beams.
- two sets of second balance trolleys 2 ′ are spaced apart, and each set of second balance trolleys 2 ′ includes two second balance trolleys correspondingly provided on the inner ring track 31 and the outer ring track 32.
- the first balance beam 22 overlaps the two first trolleys 21 at the bottom of each of the second balanced trolleys 2 ′.
- the first balance trolley 2 and the second balance trolley 2 act on the inner and outer ring tracks, and the number of the first and second balance trolleys is differentiated according to the force to reduce a single balance trolley.
- the load on the first and second balance trolleys is uniform, and the contact area with the ground is increased to reduce the ground specific pressure.
- each second balance trolley 2 ' also adds a balance beam group and a trolley group, and the added trolley group is located outside the original trolley along the track direction.
- the balance beam overlaps the added trolley and the bottom balance beam. If the hoisting weight is large, this embodiment can increase the span of the first balancing trolley 2 and the second balancing trolley 2 'to support the slewing platform 1 at the same time, thereby further increasing the grounding area and reducing the ground specific pressure on the ground. , Thereby reducing the difficulty and cost of foundation treatment, so that the crane can obtain greater lifting capacity.
- each second balance trolley 2 ′ includes a first balance beam 22 and two first trolleys 21, and the first balance beam 22 overlaps the two first trolleys 21.
- each second balanced trolley 2 ' also includes a balanced beam group and a trolley group, the trolley group is located outside the first trolley 21 along the track extension direction, and the balanced beam group overlaps with The first balance beam 22 and the top of the trolley.
- the structures of the first balance trolley 2 given above are all applicable to the second balance trolley 2 '.
- the chassis further includes a slewing platform 1, which includes a front vehicle platform 12, a rear vehicle platform 11, and two longitudinal beams 13.
- the rear vehicle platform 11 is supported on a plurality of second balanced trolleys 2 '
- the front vehicle platform 12 is supported on a plurality of first balanced trolleys 2
- two longitudinal beams 13 are connected side by side to the front vehicle platform 12 and the rear vehicle platform. Between 11.
- the front vehicle platform 12 includes a first beam section 121 and two support platforms 122, and the first beam section 121 is located between the two support platforms 122.
- Two support beams 122 are provided with two first beam sections 121 spaced apart from each other along the length direction of the slewing platform 1.
- the two beams 13 are connected to the first beam section 121 on the inner side.
- the supporting platform 122 is provided with a mounting interface 123 for mounting the boom assembly.
- the mounting interface 123 may be a lug plate.
- the bottom ends of the two main arms 5 are respectively hinged on the lug plates of a support base 122 and the bottom ends of the two masts 4 They are also connected to the ear plates of a support base 122 respectively.
- a second beam section 124 is added to both ends of the first beam section 121, and the second beam section 124 is connected to the supporting platform 122 on the corresponding side. It is equivalent to increasing the distance between the two supporting platforms 122, thereby increasing the supporting span of the front vehicle platform 12 so as to match the increase in the supporting point span of the first balanced trolley 2 at the bottom.
- the front-car platform 12 of the special-shaped slewing platform 1 is installed on the top of the second balance beam 24, which can ensure that the three trolleys in the same first balance trolley 2 are uniformly stressed.
- the length of the second beam section 124 is shorter than the length of the first beam section 121, so that the lifting capacity can be increased in small steps, so as to flexibly increase the structural rigidity of the component according to the actual lifting demand, so as not to cause waste of the lifting capacity.
- the lifting capacity of the lifting equipment can be configured according to the requirements of the actual lifting weight.
- the lifting weight is small, the supporting span of the boom platform of the swing platform 1 and the front vehicle platform 12 can be reduced, and the platform and the balance beam are not added.
- the matching of the first balanced trolley 2 can reduce the waste of lifting capacity. It can also increase the lifting capacity through the structure during heavy lifting, and increase the supporting span of the boom platform of the front platform 12 of the swing platform 1 to match the first balance trolley 2 with the increase of the trolley and the balance beam. At the same time of lifting capacity, it can also reduce the specific pressure of grounding on the ground, thereby reducing the difficulty and cost of ground treatment.
- the side member 13 includes a plurality of mounting sections.
- the top height also changes. It is the same, so each mounting section is connected in sequence along its own length direction, forming a longitudinal beam 13 that is parallel to the plane where the track is located as a whole.
- the installation section connected to the front vehicle platform 12 is inclined relative to the plane on which the track is located, and the first end of the installation section connected to the front vehicle platform 12 is higher than the second end connected to the adjacent installation section.
- the longitudinal beam 13 adopts a multi-segment split structure, which can meet the requirements of different transformation forms.
- the hoisting system 3 and the power system 10 can be overlapped and disposed on the two longitudinal beams 13 and can be disposed on different installation sections.
- the rear vehicle platform 11 includes two parallel beams 111.
- the two beams 111 are connected by two longitudinal beams 112.
- One mounting interface 113 is provided on each of the two longitudinal beams 112.
- the platform counterweight 9 can be set on the rear platform 11.
- the mounting interface 113 on the rear vehicle platform 11 may be a lug, one end of the mast bracket 8 is hinged to the top of the mast 4, and the other end is hinged to the lug of the rear vehicle platform 11.
- first beam sections 121 (D1) are spaced apart along the length direction of the turning platform 1.
- the distance between the two supporting platforms 122 is L1.
- second working condition as shown in FIG. 3B, between the two support stands 122 of the front vehicle platform 12, two sets of beam sections are provided at intervals along the length direction of the turning platform 1, and each group of beam sections includes sequential connections.
- the second beam section 124 (D2), the first beam section 121 (D1), and the second beam section 124 (D2) are separated by a distance L2. Since the second beam section 124 is added, L2> L1, which is equivalent to increasing the support span of the front vehicle platform 12 under the second working condition through the structure.
- the side member 13 includes the mounting sections C1, C2, C3, and C4 connected in order along the length direction from the rear vehicle platform 11 to the front vehicle platform 12, and the side member 13 The plane is parallel to the orbit.
- the side member 13 includes the mounting sections C1, C2, C3, and C5 connected in sequence along the length direction from the rear vehicle platform 11 to the front vehicle platform. It can be seen that the mounting section C5 is arranged obliquely.
- the crossbeam and longitudinal beam 13 of the lifting equipment slewing platform 1 of the present disclosure both adopt a modular design, a multi-segment split structure, and have an interface for upgrading from a small span to a large span, which can realize the rotation from a small span platform to a large span Conversion of platform 1.
- the boom assembly includes two main arms 5, and the two main arms 5 are correspondingly connected at the top and bottom positions.
- the positions of the bottoms of the two main arms 5 are connected by two first connecting rod segments 51 connected in the length direction; in the second working condition, as shown in FIG. 13B, the two A first connecting rod segment 51 is added to the position of the bottom of each main arm 5. Specifically, it may be increased between the two first connecting rod segments 51 or between the first connecting rod segment 51 and the main arm 5.
- the bottoms of the two main booms 5 are connected by two first connecting rod segments 51. They are E1 and E2 respectively, and the bottom width between the two main arms 5 is L1.
- the bottoms of the two main arms 5 are connected by three first connecting rod segments 51, E3 is added between E1 and E2, and the bottom width between the two main arms 5 Is L2, and L2> L1.
- the bottom width between the two main arms 5 is larger than the top width, so that the two main arms 5 have a trapezoidal structure from the top to the bottom, which is conducive to increasing the overall rigidity of the main arms 5.
- the jib assembly includes two jibs, the jib is an extended arm of the main jib 5, and the two jibs are correspondingly connected at the top and bottom positions; in the first working condition, the bottoms of the two jibs The positions are connected by two first connecting rod segments 51 connected along the length direction; in the second working condition, the first connecting rod segments 51 are added to the positions of the bottoms of the two jib arms.
- the boom assembly includes two main booms 5, two masts 4, and two pullers 7, the bottom ends of the masts 4 are adjacent to the bottom ends of the corresponding main booms 5 on the chassis Hinged, the top end is connected to the top end of the corresponding main arm 5 through a pulling member 7, and the top and bottom of the two masts 4 are correspondingly connected.
- the first working condition as shown in FIG. 12A
- the position at the bottom of the mast 4 is connected by two second connecting rod segments 41 connected in the length direction;
- the second working condition as shown in FIG. 12B, it is located on the mast 4
- a second connecting rod segment 41 is added between the two second connecting rod segments 41 at the bottom. Specifically, it may be increased between the two second connecting rod segments 41 or between the second connecting rod segment 41 and the main arm 4.
- the bottoms of the two masts 4 are connected by two second connecting rod segments 41, respectively. D1 and D2, the bottom width between the two masts 4 is L1, and a rectangular structure is formed between the two masts 4.
- the bottoms of the two masts 4 are connected by three second connecting rod segments 41, D3 is added between D1 and D2, and the bottom width between the two masts 4 is L2.
- the bottom width between the two masts 4 is greater than the top width, so that the two masts 4 have a trapezoidal structure from the top to the bottom, which is beneficial to increasing the overall rigidity of the masts 4.
- the chassis is provided with a first balance trolley 2 and a second balance trolley 2 ′, which respectively correspond to the front balance trolley and The rear balance trolley, so that the hoisting equipment can get on the car to realize the whole rotation.
- the improvements of the present disclosure are also applicable to semi-circular rail lifting equipment. Only the first balancing trolley 2 is provided in the chassis. Corresponding to the front balancing trolley in the usual sense, the lifting equipment can only be loaded onto the vehicle. The center point of the counterweight is used as the center of rotation, and the part of the track is rotated in the circumferential direction.
- the entire vehicle is transformed based on the same ring track, the transformation method is simple, and the cost is low; during the transformation process, only the components need to be re-assembled and assembled, and the component universality is high; multiple vehicles are arranged in the same Equipped with a balance trolley, the component utilization rate is high.
- it can reduce the design difficulty of the balance trolley, reduce the structural size of the balance trolley, reduce the stress during work, reduce the size of supporting parts and transportation parameters, and achieve "small structure and large load. Ability.
- the following theoretical analysis will be performed:
- F is the vertical force of the entire vehicle
- S is the actual ground area, that is, the ground area of the balanced trolley
- the grounding area of multiple vehicles is S2> S1. Therefore, with the same hoisting capacity and the same vertical force of the vehicle, P2 ⁇ P1, the configuration of multiple vehicles can greatly reduce the ground specific pressure on the ground.
- I x 8I dg + 2A 2 A dg + 2B 2 A dg
- Ix is the moment of inertia of the plane of rotation (in the plane of revolution, the boom is used as a fixed mechanical model for one end to analyze);
- Iy is the moment of inertia of the plane of amplitude (in the plane of amplitude, the boom is simply supported at both ends)
- Mechanical model for analysis Idg is the moment of inertia of a single main chord;
- B is the width dimension of the section of the single boom;
- H is the height dimension of the section of the single boom;
- A is the center distance of the two arms (that is, Figures 12A, 12B, 13A and 13B; Lg;
- Adg is the cross-sectional area of a single main chord.
- the load capacity of very large lifting equipment can be improved by adding a few components, which can effectively reduce the ground specific pressure of the vehicle to the ground without changing the chassis system.
- it can greatly reduce the difficulty and cost of handling the foundation of the hoisting site. It can realize the functions of multiple functions of one machine, which broadens the scope of use.
- the conventional model and the extended model use the same track. The component utilization rate is high, the cost is low, and the overall machine footprint is not increased.
- the conventional model and the extended model are the same. Equipped with a balanced trolley, the component utilization rate is high. At the same time, it can reduce the design difficulty of the balanced trolley, reduce the structural size of the balanced trolley, and achieve the purpose of "small structure" and large carrying capacity.
- the lifting capacity of the lifting equipment can be configured according to demand, and the lifting capacity of the whole machine can be fully utilized. It can meet the operating economics of the "car”, and at the same time has structural interfaces and methods to improve the carrying capacity, which can improve the carrying capacity and meet the lifting of individual oversized and heavy parts.
- the super-large lifting equipment uses the same set of balanced trolleys and the same set of chassis to reduce the structural size of the balanced trolley and the chassis, reduce the stress during work, reduce the size of supporting parts and transportation parameters, and achieve "small structure and large "Bearing capacity", the cost of the entire machine to achieve the function of improving the carrying capacity is low.
- Different super-large lifting equipment can be assembled according to the actual hoisting conditions, site and other conditions, which reduces the requirements of the vehicle on the external environment (such as the hoisting site), improves the vehicle utilization rate, and makes the project more applicable. wide.
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Jib Cranes (AREA)
Abstract
Description
Claims (14)
- 一种起重设备,包括:臂架组件;和底盘,所述底盘包括轨道和多个第一平衡台车(2),各个所述第一平衡台车(2)设在所述轨道上且位于臂架组件下方的前部区域;其中,在第一工况下,每个所述第一平衡台车(2)中包括第一平衡梁(22)和两个第一台车(21),所述第一平衡梁(22)搭接在所述两个第一台车(21)上方;在第二工况下,每个所述第一平衡台车(2)还包括平衡梁组和台车组,所述台车组位于所述第一台车(21)沿所述轨道延伸方向的外侧,所述平衡梁组搭接在所述第一平衡梁(22)和所述台车组的上方;第一工况的吊重量不超过预设吊装重量,第二工况的吊重量超过预设吊装重量。
- 根据权利要求1所述的起重设备,其中,所述台车组包括一个第二台车(23),平衡梁组包括一个第二平衡梁(24),所述第二平衡梁(24)的两端分别搭接在所述第一平衡梁(22)和所述第二台车(23)上方。
- 根据权利要求2所述的起重设备,其中,所述第二平衡梁(24)包括相互连接的主承载部(241)和抵接部(242),所述主承载部(241)搭接在所述第一平衡梁(22)上,所述抵接部(242)从与主承载部(241)连接的一端至自由端截面积逐渐减小,且相对于所述主承载部(241)向下倾斜,直至所述抵接部(242)的自由端与所述第二台车(23)的顶面接触。
- 根据权利要求1所述的起重设备,其中,所述台车组包括至少两个第二台车(23),平衡梁组包括至少两个第二平衡梁(24),所述至少两个第二平衡梁(24)中的每个第二平衡梁(24)搭接在第一平衡梁(22)、至少两个第二台车(23)和其它第二平横梁(24)中的两个的上方。
- 根据权利要求4所述的起重设备,其中,所述第二台车(23)为偶数个,所述至少两个第二平衡梁(24)包括上级平衡梁和下级平衡梁,所述下级平衡梁与所述第一平衡梁(22)结构相同且将所述至少两个第二台车(23)两两搭接,所述上级平衡梁搭接在所述第一平衡梁(22)和各个下级平衡梁上。
- 根据权利要求1所述的起重设备,其中,所述底盘还包括多个第二平衡台车(2’),各个所述第二平衡台车(2’)设在所述轨道上且位于臂架组件下方的后部 区域。
- 根据权利要求6所述的起重设备,其中,所述轨道为环形轨道且包括:内环轨道(31)和外环轨道(32),所述第一平衡台车(2)和第二平衡台车(2’)均在所述内环轨道(31)和外环轨道(32)上并排设置,所述内环轨道(31)和外环轨道(32)上相应位置的所述第一平衡台车(2)结构相同,所述内环轨道(31)和外环轨道(32)上相应位置的所述第二平衡台车(2’)结构相同。
- 根据权利要求6所述的起重设备,其中,在第一工况下,每个所述第二平衡台车(2’)中包括所述第一平衡梁(22)和两个第一台车(21),所述第一平衡梁(22)搭接在所述两个第一台车(21)上方;在第二工况下,每个所述第二平衡台车(2’)还包括平衡梁组和台车组,所述台车组位于所述第一台车(21)沿所述轨道延伸方向的外侧,所述平衡梁组搭接在所述第一平衡梁(22)和所述台车组的上方。
- 根据权利要求6所述的起重设备,其中,所述底盘还包括回转平台(1),所述回转平台(1)包括:前车平台(12),支撑于各个所述第一平衡台车(2)上;后车平台(11),支撑于各个所述第二平衡台车(2’)上;和纵梁(13),连接于所述前车平台(12)与后车平台(11)之间;其中,在第一工况下,所述前车平台(12)包括第一横梁段(121)和两个支撑台(122),所述第一横梁段(121)位于两个所述支撑台(122)之间,所述纵梁(13)与所述第一横梁段(121)连接;在第二工况下,所述第一横梁段(121)的两端增加第二横梁段(124),所述第二横梁段(124)与相应侧的所述支撑台(122)连接。
- 根据权利要求9所述的起重设备,其中,所述纵梁(13)包括多个安装段,在第一工况下,各个所述安装段形成整体与轨道所在平面平行的纵梁(13);在第二工况下,与所述前车平台(12)连接的所述安装段相对于轨道所在平面倾斜设置,且所述安装段与所述前车平台(12)连接的第一端高于与相邻安装段连接的第二端。
- 根据权利要求9所述的起重设备,其中,所述臂架组件包括两个桅杆(4)和两个主臂(5),两个所述主臂(5)的底端分别连接在一个所述支撑台(122)上,所述两个桅杆(4)的底端分别连接在一个所述支撑台(122)上。
- 根据权利要求1所述的起重设备,其中,所述臂架组件包括两个主臂(5),两个所述主臂(5)在顶部与底部的位置对应连接;其中,在第一工况下,两个所述主臂(5)的底部位置通过两个沿长度方向相连的第一连接杆段(51)连接;在第二 工况下,两个所述主臂(5)的底部位置增加第一连接杆段(51);或者所述臂架组件包括两个副臂,两个所述副臂在顶部与底部的位置对应连接;其中,在第一工况下,两个所述副臂的底部位置通过两个沿长度方向相连的第一连接杆段(51)连接;在第二工况下,两个所述副臂的底部位置增加第一连接杆段(51)。
- 根据权利要求1所述的起重设备,其中,所述臂架组件包括两个主臂(5)、两个桅杆(4)和两个牵拉件(7),所述桅杆(4)的底端在所述底盘上邻近相应主臂(5)的底端铰接,顶端通过所述牵拉件(7)与相应所述主臂(5)的顶端连接,两个所述桅杆(4)的顶部与底部之间对应连接;其中,在第一工况下,位于所述桅杆(4)的底部位置设有两个所述第二连接杆段(41);在第二工况下,位于所述桅杆(4)底部的两个所述第二连接杆段(41)之间增加第二连接杆段(41)。
- 根据权利要求1所述的起重设备,其中,所述臂架组件包括两个主臂(5)和两个桅杆(4),两个所述主臂(5)和/或两个所述桅杆(4)在第二工况下从顶部至底部呈梯形结构。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
GB2102004.5A GB2590831B (en) | 2018-09-05 | 2019-03-01 | Hoisting apparatus |
RU2021108671A RU2761006C1 (ru) | 2018-09-05 | 2019-03-01 | Грузоподъемное устройство |
ZA2021/02235A ZA202102235B (en) | 2018-09-05 | 2021-04-01 | Hoisting apparatus |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201811029799.1A CN108946515B (zh) | 2018-09-05 | 2018-09-05 | 一种起重设备 |
CN201811029799.1 | 2018-09-05 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2020048102A1 true WO2020048102A1 (zh) | 2020-03-12 |
Family
ID=64475195
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2019/076667 WO2020048102A1 (zh) | 2018-09-05 | 2019-03-01 | 一种起重设备 |
Country Status (5)
Country | Link |
---|---|
CN (1) | CN108946515B (zh) |
GB (1) | GB2590831B (zh) |
RU (1) | RU2761006C1 (zh) |
WO (1) | WO2020048102A1 (zh) |
ZA (1) | ZA202102235B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114408735A (zh) * | 2022-01-07 | 2022-04-29 | 国网新源控股有限公司 | 一种可旋转多用式水车室起重检修平台 |
CN115977129A (zh) * | 2023-01-13 | 2023-04-18 | 中国十九冶集团有限公司 | 一种装配式圆形沉井装置及安装方法 |
CN117550500A (zh) * | 2024-01-10 | 2024-02-13 | 天津同丰信息技术有限公司 | 一种货物运输用车臂架工作安全保护装置 |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108946515B (zh) * | 2018-09-05 | 2024-05-17 | 徐工集团工程机械股份有限公司 | 一种起重设备 |
CN113460594B (zh) * | 2020-03-30 | 2023-03-21 | 南京宝地梅山产城发展有限公司 | 一种带回转辅助支撑的料机 |
CN111847285B (zh) * | 2020-08-13 | 2023-06-02 | 合肥工业大学 | 一种适用于柔索并联起重机器人的稳定调节机构及调节方法 |
CN113023564A (zh) * | 2021-03-29 | 2021-06-25 | 中核能源科技有限公司 | 环形吊车 |
CN112960574B (zh) * | 2021-04-28 | 2023-10-24 | 徐工集团工程机械股份有限公司建设机械分公司 | 起重机平衡重的托架和起重机 |
CN112978593A (zh) * | 2021-04-28 | 2021-06-18 | 徐工集团工程机械股份有限公司建设机械分公司 | 轨道底盘组件及轨道式起重机 |
CN113184697B (zh) * | 2021-04-28 | 2024-11-19 | 徐工集团工程机械股份有限公司建设机械分公司 | 轨道行走组件及环轨起重机 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4394911A (en) * | 1980-04-08 | 1983-07-26 | Fmc Corporation | Heavy duty crane |
US6516961B1 (en) * | 1998-03-26 | 2003-02-11 | Atecs Mannesmann Ag | Ringlift crane |
CN202609838U (zh) * | 2012-05-07 | 2012-12-19 | 徐工集团工程机械股份有限公司 | 组合式台车及履带起重机 |
CN108083140A (zh) * | 2017-09-18 | 2018-05-29 | 太原重型机械集团工程技术研发有限公司 | 环轨直轨两用起重机 |
CN108328483A (zh) * | 2018-03-29 | 2018-07-27 | 徐工集团工程机械股份有限公司 | 一种带门架的超大型起重设备 |
CN108328487A (zh) * | 2018-04-11 | 2018-07-27 | 徐工集团工程机械股份有限公司 | 一种具有变形功能的双轨道超大型起重设备 |
CN108946515A (zh) * | 2018-09-05 | 2018-12-07 | 徐工集团工程机械股份有限公司 | 一种起重设备 |
Family Cites Families (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1207988A1 (ru) * | 1984-04-11 | 1986-01-30 | Донецкий Филиал Института "Автомэнергостройпроект" | Ходова часть крана |
CN204625000U (zh) * | 2015-01-07 | 2015-09-09 | 河南省矿山起重机有限公司 | 一种台车装置及使用该台车装置的门式起重机 |
CN108455467A (zh) * | 2018-04-11 | 2018-08-28 | 徐工集团工程机械股份有限公司 | 一种具有变形功能的多轨道超大型起重设备 |
CN208883351U (zh) * | 2018-09-05 | 2019-05-21 | 徐工集团工程机械股份有限公司 | 一种起重设备 |
-
2018
- 2018-09-05 CN CN201811029799.1A patent/CN108946515B/zh active Active
-
2019
- 2019-03-01 WO PCT/CN2019/076667 patent/WO2020048102A1/zh active Application Filing
- 2019-03-01 GB GB2102004.5A patent/GB2590831B/en active Active
- 2019-03-01 RU RU2021108671A patent/RU2761006C1/ru active
-
2021
- 2021-04-01 ZA ZA2021/02235A patent/ZA202102235B/en unknown
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4394911A (en) * | 1980-04-08 | 1983-07-26 | Fmc Corporation | Heavy duty crane |
US6516961B1 (en) * | 1998-03-26 | 2003-02-11 | Atecs Mannesmann Ag | Ringlift crane |
CN202609838U (zh) * | 2012-05-07 | 2012-12-19 | 徐工集团工程机械股份有限公司 | 组合式台车及履带起重机 |
CN108083140A (zh) * | 2017-09-18 | 2018-05-29 | 太原重型机械集团工程技术研发有限公司 | 环轨直轨两用起重机 |
CN108328483A (zh) * | 2018-03-29 | 2018-07-27 | 徐工集团工程机械股份有限公司 | 一种带门架的超大型起重设备 |
CN108328487A (zh) * | 2018-04-11 | 2018-07-27 | 徐工集团工程机械股份有限公司 | 一种具有变形功能的双轨道超大型起重设备 |
CN108946515A (zh) * | 2018-09-05 | 2018-12-07 | 徐工集团工程机械股份有限公司 | 一种起重设备 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114408735A (zh) * | 2022-01-07 | 2022-04-29 | 国网新源控股有限公司 | 一种可旋转多用式水车室起重检修平台 |
CN115977129A (zh) * | 2023-01-13 | 2023-04-18 | 中国十九冶集团有限公司 | 一种装配式圆形沉井装置及安装方法 |
CN117550500A (zh) * | 2024-01-10 | 2024-02-13 | 天津同丰信息技术有限公司 | 一种货物运输用车臂架工作安全保护装置 |
CN117550500B (zh) * | 2024-01-10 | 2024-03-19 | 天津同丰信息技术有限公司 | 一种货物运输用车臂架工作安全保护装置 |
Also Published As
Publication number | Publication date |
---|---|
GB2590831A (en) | 2021-07-07 |
GB202102004D0 (en) | 2021-03-31 |
GB2590831B (en) | 2022-06-29 |
ZA202102235B (en) | 2022-10-26 |
RU2761006C1 (ru) | 2021-12-02 |
CN108946515B (zh) | 2024-05-17 |
CN108946515A (zh) | 2018-12-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2020048102A1 (zh) | 一种起重设备 | |
CN201580914U (zh) | 单梁无轨组合龙门吊 | |
CN103848360B (zh) | 一种安装有可移动式平衡重系统的组塔塔式起重机 | |
CN102190255B (zh) | 一种起重机 | |
CN105110213A (zh) | 起重物自重配重平衡机构的起重机和起重机改造方案 | |
CN108328487B (zh) | 一种具有变形功能的双轨道超大型起重设备 | |
CN103832933B (zh) | 一种带有副臂的组塔塔式起重机 | |
CN203728443U (zh) | 一种具有主副臂结构的组塔塔式起重机 | |
CN102556861B (zh) | 一种用于起重机的配重拉板装置及起重机 | |
CN208883351U (zh) | 一种起重设备 | |
CN101955133B (zh) | 一种移动式起重机 | |
CN115676616A (zh) | 轨道转场装置、环轨起重机、转场系统及转场方法 | |
CN108275584B (zh) | 一种具有多功能的直轨超大型起重设备 | |
CN201338910Y (zh) | 简易移动式行车 | |
CN118978094A (zh) | 一种通过多吊车配合式风电施工方法 | |
CN102826447A (zh) | 一种桁架臂起重机及其下车结构、转点方法 | |
CN201999659U (zh) | 一种加强型臂架及设有该臂架的起重机 | |
CN112645224A (zh) | 一种塔式起重机 | |
CN107010545A (zh) | 一种用于柴油机的起吊装置 | |
CN108455467A (zh) | 一种具有变形功能的多轨道超大型起重设备 | |
CN202449768U (zh) | 一种用于起重机的配重拉板装置及起重机 | |
CN108328483A (zh) | 一种带门架的超大型起重设备 | |
CN203159081U (zh) | 一种桁架臂起重机及其下车结构 | |
CN221876424U (zh) | 一种适用于狭小空间作业的臂架系统 | |
CN214692982U (zh) | 一种起重机械的三方位预应力体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 19857026 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 202102004 Country of ref document: GB Kind code of ref document: A Free format text: PCT FILING DATE = 20190301 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 19857026 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 521421379 Country of ref document: SA |