WO2019128155A1 - 沉井施工结构及其施工方法 - Google Patents
沉井施工结构及其施工方法 Download PDFInfo
- Publication number
- WO2019128155A1 WO2019128155A1 PCT/CN2018/092434 CN2018092434W WO2019128155A1 WO 2019128155 A1 WO2019128155 A1 WO 2019128155A1 CN 2018092434 W CN2018092434 W CN 2018092434W WO 2019128155 A1 WO2019128155 A1 WO 2019128155A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- steel
- column
- steel pipe
- jack
- sinking
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D7/00—Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
- E02D7/28—Placing of hollow pipes or mould pipes by means arranged inside the piles or pipes
Definitions
- the invention relates to a sinking construction structure and a construction method thereof.
- Sinking is a construction process for building deep foundations and underground structures.
- an open reinforced concrete shaft is first made in the ground or in the foundation pit. After it reaches the specified strength, it is stratified and excavated in the well body. With the reduction of excavation and soil surface, the sinking well body borrows With the help of self-weight or other measures, overcome the frictional resistance and the reaction between the blade and the wall, and continue to sink until the design elevation is in place, and then the back cover.
- the advantage of the sinking construction process is that it can be used in deep underground construction (up to 50 meters) under underground conditions and has less impact on the surrounding environment; it can be constructed in complex areas with geological and hydrological conditions; construction does not require complicated Machine equipment; compared with large excavation, can reduce the amount of earthwork excavated, transported and backfilled.
- Its shortcomings are many construction procedures, high technical requirements, and difficult quality control.
- the correction of the sinking process is one of the keys to the construction of the caisson. If the correction is not timely in the sinking process, the sinking well will be in place. Can't be corrected later.
- the object of the present invention is to provide a sinking construction structure and a construction method thereof, which can solve the problems of low verticality control precision, tilting, easy to cause sinking of the soft soil layer and complicated operation platform setting in the sinking sinking project.
- the present invention provides a sinking construction structure, including:
- a steel pipe column is connected to a top end of each of the pouring piles, and a bottom end of each steel pipe column is connected to a top end of a corresponding pouring pile, and the steel pipe column extends from the foundation pit to be excavated to the ground;
- a pipe joint is connected to the top of each jack
- the sinking well is sleeved outside the space enclosed by the steel pipe column, and the inner wall of the caisson is disposed with a steel bull leg at an interval corresponding to the axial direction of the pipe joint column, and the inner wall of the sinking well is
- the steel pipe columns are adjacent to each other, and the steel bull legs are erected on the pipe joint columns.
- the steel structure platform comprises a platform ring beam and a transverse steel beam, wherein the platform ring beam connects all the steel pipe columns together, and the transverse steel beam is connected to the platform ring beam interior .
- the steel bracing is connected between the lower bottom surface of the steel structure platform and the steel pipe column.
- the steel structure platform is a hollow structure, and the steel structure platform is provided with a crane, and the base pit under the steel structure platform is provided with a grab excavation device.
- the jack is a two-way jack.
- the steel ox leg is an L-shaped structure formed by connecting the first surface and the second surface, the first surface is connected to the inner wall of the caisson, and the second surface is erected on The pipe joint is on the column.
- a horizontal restraining member one end of the horizontal constraining member being perpendicularly connected to the first surface, the horizontal constraining member being perpendicular to the tubular strut, the horizontal constraining member The other end is abutted against the side wall of the pipe section.
- the method further includes:
- a controller coupled to the jack, displacement, and force sensor.
- a construction method for a sinking well comprising:
- a plurality of cast-in-place piles are symmetrically arranged at the bottom of the foundation pit to be excavated, and a steel pipe column is connected at the top end of each of the cast-in-place piles, wherein the bottom end of each steel pipe column is connected with the top end of the corresponding cast-in-place pile, and the steel pipe column is connected
- the foundation pit to be excavated extends to the ground;
- a jack is placed at the top of each steel pipe column
- the steel cattle legs are arranged at intervals corresponding to the axial direction of the pipe joint column on the inner wall of the caisson;
- the sinking hole is sleeved outside the space enclosed by the steel pipe column, and the inner wall of the caisson is adjacent to the steel pipe column, and the steel ox leg is erected on the pipe joint column.
- a plurality of cast-in-place piles are symmetrically arranged at the bottom of the foundation pit to be excavated, and the steel pipe columns are connected at the top end of each of the piles, including:
- the hydraulic sag system is used to control the concrete column into the concrete cage to the second design elevation.
- a steel structure platform connecting all the steel pipe columns including:
- a transverse steel beam is connected inside the platform ring beam.
- the method after installing the steel structure platform connecting all the steel pipe columns, the method includes:
- a steel bracing is connected between the lower bottom surface of the steel structure platform and the steel pipe column.
- a steel structure platform connecting all the steel pipe columns including:
- a grab excavation device is passed through the hollow structure to a foundation pit under the steel structure platform by a crane.
- the jack is a two-way jack.
- the steel bull legs are disposed at intervals along the axial direction of the inner wall of the caisson corresponding to the pipe joints, including:
- An L-shaped steel bullet connected by a first side and a second side;
- Locating the steel ox leg on the pipe section column comprising:
- the second surface is erected on the pipe section column.
- the method before the second surface is mounted on the pipe column, the method further includes:
- the method further includes:
- the other end of the horizontal restraining member is vertically opposed to the side wall of the tubular string.
- the method further includes:
- Displacement and force sensors are placed on each jack;
- the controller obtains the displacement of each pipe joint column through the displacement sensor. If the displacement is inconsistent, the controller controls the jack to adjust the height of the pipe joint column according to the force on the two-way jack collected by the force sensor.
- the present invention provides a one-column (steel pipe column) for the problems of low verticality control precision, tilting, easy to produce a soft soil layer, and complicated operation platform.
- a pile (casting pile) guiding type controlled caisson construction structure the steel column is inserted into the pouring column to form a "one column and one pile" arranged on the inner side of the caisson as a vertical bearing member, and a column is connected with a steel structure platform.
- a pipe joint column is connected through the top of each two-way jack, and the steel cow leg is erected on the pipe joint column as an important guiding member in the sinking process of the sinking hole.
- the steel pipe When the sinking hole is required to sink, the steel pipe can be The soil in the foundation pit in the space enclosed by the column is continuously excavated, and the lowermost steel ox leg A erected on the pipe joint column is removed, and then the sinking well can sink to the steel ox leg A by its own gravity.
- the upper steel ox leg B is erected on the column of the pipe section, and the lowermost steel ox leg erected on the pipe section column can be continuously removed, so that the sinking hole continuously relies on its own gravity drop.
- the height of the pipe joint column of the jack can be adjusted to ensure that the vertical state of the sinking well is always maintained, thereby effectively controlling the verticality during the sinking process. With stability, it is convenient to construct and reduce construction risks and save costs.
- FIG. 1 is a schematic view showing a construction structure of a sinking well according to an embodiment of the present invention
- FIG. 2 is a plan view showing a construction structure of a sinking well according to an embodiment of the present invention
- Figure 3 is a schematic view showing the connection of a steel bull's leg according to an embodiment of the present invention.
- FIG. 4 is a schematic view showing the connection of a pouring pile and a steel pipe column according to an embodiment of the present invention
- FIG. 5 is a schematic view showing a first working condition of a sinking construction method according to an embodiment of the present invention
- FIG. 6 is a schematic view showing a second working condition of a sinking construction method according to an embodiment of the present invention.
- Fig. 7 is a schematic view showing the third working condition of the sinking construction method according to an embodiment of the present invention.
- the present invention provides a sinking construction structure, including:
- a steel pipe column 2 is connected to the top end of each of the pouring piles 1 , and the bottom end of each steel pipe column 2 is connected to the top end of the corresponding pouring pile 1 , and the steel pipe column 2 extends from the foundation pit to be excavated to the ground 3 ;
- each steel pipe column 2 a jack 5 disposed at the top of each steel pipe column 2;
- each steel pipe column 2 and the corresponding jack 5 can be connected to the gasket by anchor bolts;
- each jack 5 is connected with a pipe column 6;
- the pipe post 6 and the corresponding jack 5 may be connected by a flange 13;
- the sinking well 7 is disposed outside the space enclosed by the steel pipe column 2, and the inner wall of the caking well 7 is provided with a steel bull leg 8 at intervals corresponding to the axial direction of the pipe joint column 6.
- the inner wall of the sinkhole 7 is adjacent to the steel pipe column 2, and the steel ox leg 8 is erected on the pipe joint column 6.
- a plurality of screw holes can be drilled in each design elevation of the inner wall of the caisson, and the bolts 12 and the screw holes are matched to facilitate fixing the steel bull legs 8;
- the present invention provides a one-column (steel pipe column) pile (infusion) for the problem that the verticality control precision is low, the inclination, the soft soil layer is easy to produce a sinking, and the operation platform is complicated to set up in the sinking sinking project.
- Pillar-oriented controllable caisson construction structure the steel column is inserted into the perfusion column to form a "one column and one pile" arranged on the inner side of the caisson as a vertical bearing member, and the steel structure platform is used to connect one column and one pile into a whole, which is beneficial to Sinking sinking stability.
- a pipe joint column is connected through the top of each two-way jack, and the steel cow leg is erected on the pipe joint column as an important guiding member in the sinking process of the sinking hole.
- the steel pipe can be The soil in the foundation pit in the space enclosed by the column is continuously excavated, and the lowermost steel ox leg A erected on the pipe joint column is removed, and then the sinking well can sink to the steel ox leg A by its own gravity.
- the upper steel ox leg B is erected on the column of the pipe section, and the lowermost steel ox leg erected on the pipe section column can be continuously removed, so that the sinking hole continuously relies on its own gravity drop.
- the height of the pipe joint column of the jack can be adjusted to ensure that the vertical state of the sinking well is always maintained, thereby effectively controlling the verticality during the sinking process. With stability, it is convenient to construct and reduce construction risks and save costs.
- the steel structure platform includes a platform ring beam and a transverse steel beam, wherein the platform ring beam connects all the steel pipe columns together, the transverse steel A beam is coupled to the interior of the platform ring beam.
- the steel structure platform consists of a platform ring beam and a transverse steel beam, and full strength is used to ensure its strength.
- a steel bracing 11 is connected between a lower bottom surface of the steel structure platform and the steel pipe column to further ensure connection strength.
- the steel structure platform is a hollow structure
- the steel structure platform 4 is provided with a crane 9
- the foundation pit under the steel structure platform is provided with a grip Bucket excavation equipment.
- the steel structure platform 4 can be used as the basis of large-scale equipment, and can be used for loading crane 9, grab earth excavation equipment, hanging construction materials, etc., to facilitate on-site construction, effectively improve work efficiency and construction quality, in order to achieve cost savings, Reduce construction risks and control quality.
- a crane can be erected on a steel structure platform, and then the grab excavation equipment can be hoisted into the foundation pit under the steel structure platform through the hollow space on the steel structure platform for excavation, and then the crane hangs the soil from the foundation pit to the ground. Take it away.
- the jack is a two-way jack to achieve flexible adjustment of the height of the pipe joint column.
- the steel ox leg 8 is an L-shaped structure formed by connecting a first surface and a second surface, the first surface and the sinking surface.
- the inner wall of the well 7 is connected, and the second side is mounted on the pipe column 6.
- a sinking construction structure further includes: a horizontal restraining member 10, one end of which is vertically connected to the first surface, and the horizontal restraining member 10 The other end of the horizontal restraining member abuts against the side wall of the pipe post.
- a controller coupled to the jack, displacement, and force sensor.
- displacement and force sensors can be arranged on the two-way jack 5, the displacement and force of the pipe joint column 6 can be collected, and the controller can be configured to control the multi-jack telescopic form to achieve the purpose of intelligently and accurately controlling the sinking of the sinking hole, and control
- the displacement of each tube section is obtained by the displacement sensor. If the displacement is inconsistent, according to the force on the two-way jack collected by the force sensor, the jack is adjusted to adjust the height of the tube column, and the intelligent precision control is realized.
- the invention also provides another method of sinking construction, including.
- step S1 a plurality of pouring piles 1 are symmetrically arranged at the bottom of the foundation pit to be excavated, and a steel pipe column 2 is connected at the top end of each of the pouring piles 1, wherein the bottom end of each steel pipe column 2 corresponds to The top end of the pouring pile 1 is connected, the steel pipe column 2 extends from the foundation pit to be excavated to the ground 3;
- step S2 the foundation pit is excavated to a designated elevation, and a steel structure platform 4 connecting all the steel pipe columns 2 is installed, and the steel structure platform 4 is perpendicular to the steel pipe column;
- step S3 a jack 5 is placed at the top of each steel pipe column;
- each steel pipe column and the corresponding jack can be connected to the gasket by anchor bolts;
- step S4 at the top of each jack 5 is connected to the pipe section 6;
- the pipe joint 6 and the corresponding jack 5 can be connected by a flange 13;
- step S5 in the inner wall of the caking well 7 in the axial direction corresponding to the position of the pipe column 6 is spaced apart from the steel cattle legs 8;
- step S6 the caisson 7 is sleeved outside the space enclosed by the steel pipe column 2, and the inner wall of the caisson 2 is adjacent to the steel pipe column 2, and the steel is The ox leg 8 is mounted on the pipe column 6 .
- the present invention provides a one-column (steel pipe column) pile (infusion) for the problem that the verticality control precision is low, the inclination, the soft soil layer is easy to produce a sinking, and the operation platform is complicated to set up in the sinking sinking project.
- Pillar-oriented controllable caisson construction structure the steel column is inserted into the perfusion column to form a "one column and one pile" arranged on the inner side of the caisson as a vertical bearing member, and the steel structure platform is used to connect one column and one pile into a whole, which is beneficial to Sinking sinking stability.
- a pipe joint column is connected through the top of each two-way jack, and the steel cow leg is erected on the pipe joint column as an important guiding member in the sinking process of the sinking hole.
- the steel pipe can be The soil in the foundation pit in the space enclosed by the column is continuously excavated, and the lowermost steel ox leg A erected on the pipe joint column is removed, and then the sinking well can sink to the steel ox leg A by its own gravity.
- the upper steel ox leg B is erected on the column of the pipe section, and the lowermost steel ox leg erected on the pipe section column can be continuously removed, so that the sinking hole continuously relies on its own gravity drop.
- the height of the pipe joint column of the jack can be adjusted to ensure that the vertical state of the sinking well is always maintained, thereby effectively controlling the verticality during the sinking process. With stability, it is convenient to construct and reduce construction risks and save costs.
- step S1 a plurality of cast-in-place piles are symmetrically arranged at the bottom of the foundation pit to be excavated, and the steel pipe columns are connected at the top end of each of the piles, including:
- the HDC high-precision hydraulic drooping system is used to control the insertion of the steel pipe column into the concrete cage to the second design elevation.
- step S2 a steel structure platform connecting all the steel pipe columns is installed, including:
- a transverse steel beam is connected inside the platform ring beam.
- the steel structure platform consists of a platform ring beam and a transverse steel beam, and full strength is used to ensure its strength.
- step S2 after installing the steel structure platform connecting all the steel pipe columns, the method includes:
- the steel bracing 11 is connected between the lower bottom surface of the steel structure platform and the steel pipe column to further ensure the joint strength.
- step S2 a steel structure platform connecting all the steel pipe columns is installed, including:
- a grab excavation device is passed through the hollow structure to a foundation pit under the steel structure platform by a crane.
- the steel structure platform can be used as the basis of large-scale equipment, which can be used to load cranes, grab excavation equipment, lifting construction materials, etc., to facilitate on-site construction, effectively improve work efficiency and construction quality, in order to achieve cost savings and reduce construction.
- large-scale equipment which can be used to load cranes, grab excavation equipment, lifting construction materials, etc., to facilitate on-site construction, effectively improve work efficiency and construction quality, in order to achieve cost savings and reduce construction.
- the purpose of risk and quality control For example, a crane can be erected on a steel structure platform, and then the grab excavation equipment can be hoisted into the foundation pit under the steel structure platform through the hollow space on the steel structure platform for excavation, and then the crane hangs the soil from the foundation pit to the ground. Take it away.
- the jack is a two-way jack.
- step S5 the steel bull legs are disposed at intervals corresponding to the axial direction of the pipe joints in the inner wall of the caisson, including:
- An L-shaped structural steel leg 8 joined by a first side and a second side;
- Step S6 the steel cattle legs are erected on the pipe joint column, including:
- the second surface is erected on the pipe column 6 .
- the method further includes:
- the method further includes:
- the other end of the horizontal restraining member 10 is vertically opposed to the side wall of the pipe post 6.
- the method further includes:
- Displacement and force sensors are placed on each jack;
- the controller obtains the displacement of each pipe joint column through the displacement sensor. If the displacement is inconsistent, the controller controls the jack to adjust the height of the pipe joint column according to the force on the two-way jack collected by the force sensor.
- displacement and force sensors can be arranged on the two-way jack, the displacement and force of the pipe joint column can be collected, and the controller can be configured to control the multi-jack telescopic form to achieve the purpose of intelligently and accurately controlling the sinking of the sinking hole, and the controller passes
- the displacement sensor acquires the displacement of each column of the pipe. If the displacement is inconsistent, according to the force on the two-way jack collected by the force sensor, the jack is adjusted to adjust the height of the pipe column, and the intelligent precision control is realized.
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Piles And Underground Anchors (AREA)
- Foundations (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
Claims (17)
- 一种沉井施工结构,其特征在于,包括:在待开挖的基坑底部对称设置的多根灌注桩;每根灌注桩的顶端连接有钢管柱,每根钢管柱的底端与对应的灌注桩的顶端连接,所述钢管柱由所述待开挖的基坑延伸至地面;连接所有钢管柱的钢结构平台,所述钢结构平台与所述钢管柱垂直;设置于每个钢管柱的顶端的千斤顶;每个千斤顶的顶部连接有管节柱;沉井,所述沉井套设于所述钢管柱所围成的空间外,所述沉井的内壁沿轴向对应管节柱的位置间隔设置有钢牛腿,所述沉井的内壁与所述钢管柱相邻,所述钢牛腿架设于所述管节柱上。
- 如权利要求1所述的沉井施工结构,其特征在于,所述钢结构平台包括平台圈梁与横向钢梁,其中,所述平台圈梁将所有钢管柱连接在一起,所述横向钢梁连接于所述平台圈梁内部。
- 如权利要求1所述的沉井施工结构,其特征在于,所述钢结构平台的下底面与所述钢管柱之间连接有钢斜撑。
- 如权利要求1所述的沉井施工结构,其特征在于,所述钢结构平台为镂空结构,所述钢结构平台上设置有吊车,所述钢结构平台下的基坑内设置有抓斗挖土设备。
- 如权利要求1所述的沉井施工结构,其特征在于,所述千斤顶为双向千斤顶。
- 如权利要求1所述的沉井施工结构,其特征在于,所述钢牛腿为由第一面和第二面连接成的L型结构,所述第一面与所述沉井的内壁连接,所述第二面架设于所述管节柱上。
- 如权利要求6所述的沉井施工结构,其特征在于,还包括:水平约束构件,所述水平约束构件的一端与所述第一面垂直连接,所述水平约束构件与所述管节柱垂直,所述水平约束构件的另一端抵在所述管节柱的侧壁上。
- 如权利要求1所述的沉井施工结构,其特征在于,还包括:设置于每个千斤顶上的位移和受力传感器;与所述千斤顶、位移和受力传感器连接的控制器。
- 一种沉井施工方法,其特征在于,包括:在待开挖的基坑底部对称设置多根灌注桩,在每根灌注桩的顶端连接钢管柱,其中,每根钢管柱的底端与对应的灌注桩的顶端连接,所述钢管柱由所述待开挖的基坑延伸至地面;开挖基坑至指定标高,安装连接所有钢管柱的钢结构平台,所述钢结构平台与所述钢管柱垂直;在每个钢管柱的顶端设置千斤顶;在每个千斤顶的顶部连接管节柱;在沉井的内壁沿轴向对应管节柱的位置间隔设置钢牛腿;将所述沉井套设于所述钢管柱所围成的空间外,所述沉井的内壁与所述钢管柱相邻,将所述钢牛腿架设于所述管节柱上。
- 如权利要求9所述的沉井施工方法,其特征在于,在待开挖的基坑底部对称设置多根灌注桩,在每根灌注桩的顶端连接钢管柱,包括:在基坑底部打好桩孔后放入灌注桩的钢筋笼;在所述灌注桩的钢筋笼内灌注混凝土至第一设计标高;采用液压调垂系统控制钢管柱插入钢筋笼中的混凝土至第二设计标高。
- 如权利要求9所述的沉井施工方法,其特征在于,安装连接所有钢管柱的钢结构平台,包括:通过平台圈梁将所有钢管柱连接在一起;在所述平台圈梁内部连接横向钢梁。
- 如权利要求9所述的沉井施工方法,其特征在于,安装连接所有钢管柱的钢结构平台之后,包括:在所述钢结构平台的下底面与所述钢管柱之间连接钢斜撑。
- 如权利要求9所述的沉井施工方法,其特征在于,安装连接所有钢管柱的钢结构平台,包括:安装连接所有钢管柱的镂空结构的钢结构平台;在所述钢结构平台上设置吊车;通过吊车将抓斗挖土设备穿过所述镂空结构至所述钢结构平台下的基坑内。
- 如权利要求9所述的沉井施工方法,其特征在于,所述千斤顶为双向千斤顶。
- 如权利要求9所述的沉井施工方法,其特征在于,在所述沉井的内壁沿轴向对应管节柱的位置间隔设置钢牛腿,包括:由第一面和第二面连接成的L型结构的钢牛腿;将所述第一面与所述沉井的内壁连接;将所述钢牛腿架设于所述管节柱上,包括:将所述第二面架设于所述管节柱上。
- 如权利要求15所述的沉井施工方法,其特征在于,将所述第二面架设于所述管节柱上之前,还包括:将水平约束构件的一端与所述第一面垂直连接;将所述第二面架设于所述管节柱上之后,还包括:将所述水平约束构件的另一端垂直抵在所述管节柱的侧壁上。
- 如权利要求9所述的沉井施工方法,其特征在于,将所述钢牛腿架设于所述管节柱上之后,还包括:在每个千斤顶上设置位移和受力传感器;将所述千斤顶、位移和受力传感器与控制器连接;控制器通过位移传感器获取各管节柱的位移,若位移不一致,控制器根据受力传感器采集的双向千斤顶上的受力,控制千斤顶对管节柱高度进行调节。
Priority Applications (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2020517258A JP6830748B2 (ja) | 2017-12-29 | 2018-06-22 | オープンケーソン施工構造及びその施工方法 |
CH01548/19A CH715226B1 (de) | 2017-12-29 | 2018-06-22 | Offene Senkkastenkonstruktionsstruktur und -Verfahren. |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201711468686.7A CN108086340B (zh) | 2017-12-29 | 2017-12-29 | 沉井施工结构及其施工方法 |
CN201711468686.7 | 2017-12-29 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2019128155A1 true WO2019128155A1 (zh) | 2019-07-04 |
Family
ID=62179868
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2018/092434 WO2019128155A1 (zh) | 2017-12-29 | 2018-06-22 | 沉井施工结构及其施工方法 |
Country Status (4)
Country | Link |
---|---|
JP (1) | JP6830748B2 (zh) |
CN (1) | CN108086340B (zh) |
CH (1) | CH715226B1 (zh) |
WO (1) | WO2019128155A1 (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309130A (zh) * | 2021-07-01 | 2021-08-27 | 中建地下空间有限公司 | 一种沉井可控下沉施工方法 |
CN113585315A (zh) * | 2021-08-26 | 2021-11-02 | 宁波市政工程建设集团股份有限公司 | 一种下沉摩阻力可调节沉井 |
CN115404890A (zh) * | 2022-10-08 | 2022-11-29 | 山东黄河河务局工程建设中心 | 一种沉井的施工方法 |
CN115492144A (zh) * | 2022-09-15 | 2022-12-20 | 中国一冶集团有限公司 | 沙洲区域顶管沉井施工方法 |
CN115538812A (zh) * | 2022-12-01 | 2022-12-30 | 北京市第三建筑工程有限公司 | 一种分段吊装新增柱并增设临时牛腿的托梁插柱改造方法 |
Families Citing this family (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108086340B (zh) * | 2017-12-29 | 2020-02-14 | 上海建工二建集团有限公司 | 沉井施工结构及其施工方法 |
CN108867678B (zh) * | 2018-07-26 | 2024-04-09 | 中建空列(北京)科技有限公司 | 一种空铁沉井系统 |
CN109252533B (zh) * | 2018-09-17 | 2022-01-25 | 中国一冶集团有限公司 | 沉井下沉控制系统及其施工方法 |
CN108999205A (zh) * | 2018-09-28 | 2018-12-14 | 北京首钢建设集团有限公司 | 一种基础开槽护壁使用矩形钢板圈的施工方法 |
CN109826218A (zh) * | 2019-03-25 | 2019-05-31 | 中国十七冶集团有限公司 | 一种沉井终沉阶段液压顶升纠偏系统 |
CN110747876A (zh) * | 2019-09-11 | 2020-02-04 | 中铁上海工程局集团有限公司 | 一种用于沉井施工下沉的辅助装置及其操作方法 |
CN114373286B (zh) * | 2021-11-30 | 2023-12-05 | 成都倍特建筑安装工程有限公司 | 一种基坑位移自动报警装置 |
CN114457993B (zh) * | 2021-12-14 | 2023-07-04 | 深圳中铁二局工程有限公司 | 一种用于沉井施工的整体可移动式操作平台 |
CN115075278B (zh) * | 2022-06-22 | 2023-09-15 | 中交第二航务工程局有限公司 | 一种水中超大沉井台阶渐进式取土下沉施工系统与方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60184127A (ja) * | 1984-03-02 | 1985-09-19 | Nippon Zenisupaipu Kk | プレキヤストコンクリ−ト多層ケ−ソン |
JP2008231810A (ja) * | 2007-03-22 | 2008-10-02 | Ps Mitsubishi Construction Co Ltd | 地下構造物の施工法 |
CN101503879A (zh) * | 2009-03-10 | 2009-08-12 | 中国第一冶金建设有限责任公司 | 防止沉井倾斜的预控方法 |
CN102900090A (zh) * | 2011-07-29 | 2013-01-30 | 邹宗煊 | 一种防涌水防地面下沉不倾斜干作业沉井及其施工方法 |
CN108086340A (zh) * | 2017-12-29 | 2018-05-29 | 上海建工二建集团有限公司 | 沉井施工结构及其施工方法 |
Family Cites Families (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0468123A (ja) * | 1990-07-09 | 1992-03-03 | Shimizu Corp | ケーソン基礎工法 |
JPH06341154A (ja) * | 1993-06-01 | 1994-12-13 | Toda Constr Co Ltd | 地下躯体構築工法 |
JPH08291529A (ja) * | 1995-04-20 | 1996-11-05 | Taisei Corp | 地下階の施工方法 |
JP2003138584A (ja) * | 2001-11-06 | 2003-05-14 | Shimizu Corp | 地下躯体の施工方法 |
CN107100183B (zh) * | 2017-04-19 | 2019-08-16 | 张士普 | 沉井建筑工法 |
CN107142955A (zh) * | 2017-06-12 | 2017-09-08 | 上海市机械施工集团有限公司 | 一种沉井施工方法 |
CN207828995U (zh) * | 2017-12-29 | 2018-09-07 | 上海建工二建集团有限公司 | 沉井施工结构 |
-
2017
- 2017-12-29 CN CN201711468686.7A patent/CN108086340B/zh active Active
-
2018
- 2018-06-22 CH CH01548/19A patent/CH715226B1/de unknown
- 2018-06-22 JP JP2020517258A patent/JP6830748B2/ja active Active
- 2018-06-22 WO PCT/CN2018/092434 patent/WO2019128155A1/zh active Application Filing
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS60184127A (ja) * | 1984-03-02 | 1985-09-19 | Nippon Zenisupaipu Kk | プレキヤストコンクリ−ト多層ケ−ソン |
JP2008231810A (ja) * | 2007-03-22 | 2008-10-02 | Ps Mitsubishi Construction Co Ltd | 地下構造物の施工法 |
CN101503879A (zh) * | 2009-03-10 | 2009-08-12 | 中国第一冶金建设有限责任公司 | 防止沉井倾斜的预控方法 |
CN102900090A (zh) * | 2011-07-29 | 2013-01-30 | 邹宗煊 | 一种防涌水防地面下沉不倾斜干作业沉井及其施工方法 |
CN108086340A (zh) * | 2017-12-29 | 2018-05-29 | 上海建工二建集团有限公司 | 沉井施工结构及其施工方法 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113309130A (zh) * | 2021-07-01 | 2021-08-27 | 中建地下空间有限公司 | 一种沉井可控下沉施工方法 |
CN113309130B (zh) * | 2021-07-01 | 2024-05-24 | 中建地下空间有限公司 | 一种沉井可控下沉施工方法 |
CN113585315A (zh) * | 2021-08-26 | 2021-11-02 | 宁波市政工程建设集团股份有限公司 | 一种下沉摩阻力可调节沉井 |
CN113585315B (zh) * | 2021-08-26 | 2022-10-21 | 宁波市政工程建设集团股份有限公司 | 一种下沉摩阻力可调节沉井 |
CN115492144A (zh) * | 2022-09-15 | 2022-12-20 | 中国一冶集团有限公司 | 沙洲区域顶管沉井施工方法 |
CN115492144B (zh) * | 2022-09-15 | 2023-08-29 | 中国一冶集团有限公司 | 沙洲区域顶管沉井施工方法 |
CN115404890A (zh) * | 2022-10-08 | 2022-11-29 | 山东黄河河务局工程建设中心 | 一种沉井的施工方法 |
CN115538812A (zh) * | 2022-12-01 | 2022-12-30 | 北京市第三建筑工程有限公司 | 一种分段吊装新增柱并增设临时牛腿的托梁插柱改造方法 |
Also Published As
Publication number | Publication date |
---|---|
CH715226B1 (de) | 2021-05-14 |
CN108086340B (zh) | 2020-02-14 |
JP2020522635A (ja) | 2020-07-30 |
CN108086340A (zh) | 2018-05-29 |
JP6830748B2 (ja) | 2021-02-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2019128155A1 (zh) | 沉井施工结构及其施工方法 | |
CN107299643B (zh) | 一种基坑内钢格构柱复合式塔吊基础结构及施工方法 | |
CN101824919B (zh) | 钢管柱在富水软弱地层中深孔水下的安装定位方法 | |
CN105951747B (zh) | 一种逆作法预埋格构柱的施工方法 | |
CN106759477A (zh) | 一种盖挖逆作法钢管柱定位施工方法 | |
CN110206493A (zh) | 一种全套管全回转钻孔灌注桩施工工艺 | |
CN109024651B (zh) | 一种钢管混凝土混合桩基及施工方法 | |
CN111962504A (zh) | 一种盖挖逆作永久钢管柱的施工方法 | |
CN211773659U (zh) | 钢管支撑柱兼做结构柱的固定调垂防上浮装置 | |
CN105672314A (zh) | 一种半逆作法钢管立柱桩施工方法 | |
CN105155602A (zh) | 一种多支点地基加固综合纠倾方法 | |
CN105178368A (zh) | 微型桩桩孔取土建筑物纠倾法 | |
CN107642041A (zh) | 超大直径空心群桩锚碇 | |
CN108755706A (zh) | 可移动基坑内支撑系统及基坑施工方法 | |
CN114673153A (zh) | 复杂地层超长大直径桩基护筒结构的施工方法 | |
CN103485347A (zh) | 一种建筑基坑支护用斜桩及其施工方法 | |
CN207828995U (zh) | 沉井施工结构 | |
CN202969333U (zh) | 钢桁架嵌岩码头结构 | |
CN111962506A (zh) | 一种准直桩结构及施工方法 | |
CN107975040A (zh) | 圆形顶管工作坑深基坑支护技术施工方法 | |
CN107642040A (zh) | 超大直径空心群桩锚碇的施工方法碇 | |
CN209368877U (zh) | 逆作法钢管柱与钢筋笼活动式连接装置 | |
CN206477240U (zh) | 一种用于深水裸岩河床的栈桥桩基 | |
CN105274984A (zh) | 一种双重套管全回转施工立柱桩方法 | |
CN214116620U (zh) | 一种用于永久双钢管柱精确定位的可调节支架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 18896713 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2020517258 Country of ref document: JP Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: 10201900001548 Country of ref document: CH |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 18896713 Country of ref document: EP Kind code of ref document: A1 |