WO2012088653A1 - Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension - Google Patents

Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension Download PDF

Info

Publication number
WO2012088653A1
WO2012088653A1 PCT/CN2010/080305 CN2010080305W WO2012088653A1 WO 2012088653 A1 WO2012088653 A1 WO 2012088653A1 CN 2010080305 W CN2010080305 W CN 2010080305W WO 2012088653 A1 WO2012088653 A1 WO 2012088653A1
Authority
WO
WIPO (PCT)
Prior art keywords
lifting
equipment
mobile
hydraulic
assembling
Prior art date
Application number
PCT/CN2010/080305
Other languages
English (en)
Chinese (zh)
Inventor
赵兴勇
曹岳
董世祎
刘光明
高杰
齐麟
Original Assignee
中国二十冶集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 中国二十冶集团有限公司 filed Critical 中国二十冶集团有限公司
Priority to PCT/CN2010/080305 priority Critical patent/WO2012088653A1/fr
Priority to AU2010366350A priority patent/AU2010366350B2/en
Publication of WO2012088653A1 publication Critical patent/WO2012088653A1/fr

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C5/00Base supporting structures with legs
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C19/00Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries
    • B66C19/02Cranes comprising trolleys or crabs running on fixed or movable bridges or gantries collapsible

Definitions

  • the invention relates to large equipment in place, in particular to a method for seating large industrial and mining equipment.
  • the present invention aims to solve the above problems, and provides a method for lifting a large position of a large industrial and mining equipment.
  • the invention perfectly solves the problem that the large-scale equipment improves the movement and is in place, and the work is stable, and the cost is lower than that of the crane.
  • the present invention is implemented as follows:
  • a method for pre-assembling and lifting a mobile large-scale industrial and mining equipment which comprises:
  • Step one performing main assembly at the manufacturer of the device, and performing equipment foundation and transportation road construction at the installation site of the device;
  • Step 2 transporting the assembled main body of the step 1 to the installation site by using the axle car, and at the same time installing the on-site assembly to lift the mobile positioning device;
  • the lifting mobile positioning device comprises a lifting frame with a lifting device and can be on the track a mobile hydraulic power moving trolley comprising four hydraulic powered trolleys with lifting devices;
  • Step 3 Lifting the main body of the device by using the lifting device, after the axis transport vehicle is withdrawn, the hydraulic power moving trolley enters the lower part of the device through the track, and fixes the main body of the device on the frame of the hydraulic power moving trolley;
  • Step 4 The hydraulic power moving trolley moves the device body to the side of the device base, and lifts the device body through the lifting device. After the lowest point of the device body crosses the foundation, the mobile car enters the basic position, and then the device body is lowered by the lifting device. After the installation accuracy of the main body of the equipment is adjusted, it is installed on the equipment installation saddle.
  • Step 5 Move the mobile trolley out of the equipment installation base position, construct the foundation of the lower part of the equipment body, and complete the final assembly of the equipment.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved into position.
  • the lifting device comprises: four columns and four beams disposed at the top of the column, and the lifting device is erected on the beams on both sides.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved in place.
  • the lifting device has four core-through hydraulic lifting devices, and includes: an independent hydraulic system, a separate core-through hydraulic jack, and an independent wire rope winding.
  • the device and a set of shared PLC remote control boxes.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved.
  • the four beams on the upper part of the lifting frame are provided with mounting brackets, and the hydraulic lifting device is installed at four corners of the mounting bracket.
  • the large-scale industrial and mining equipment pre-assembles and lifts the in-position method
  • the mobile trolley comprises: a supporting column and a vehicle body carrying beam on both sides, and the lifting device is mounted on the supporting columns on both sides.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved in place.
  • the mobile trolley is a hydraulic power mobile trolley, which has four, and includes: a common hydraulic system, four independent hydraulic power motors, and eight balances. Wheel axle support.
  • the large-scale industrial and mining equipment pre-assembles and lifts the mobile seating method
  • the hydraulic power moving trolley further includes an accuracy adjusting device
  • the precision adjusting device comprises: a parallel multi-control hydraulic cylinder precision adjusting device, and a mechanical winch plus Screw adjustment device.
  • the invention adopts the pre-installed equipment main body in the factory, and simultaneously performs basic construction and equipment installation preparation work on the equipment installation site, the equipment body and accessories are transported to the site by the mobile equipment, lifting and unloading the vehicle by using the lifting frame, and the moving vehicle exits, the mobile trolley Move the lifting frame below the load, and then move the lifted device out of the frame. After lifting to the predetermined height, the trolley will be moved into the equipment foundation by the lifting device. After the precision is adjusted, the lifting device will fall back and be installed in place by the lifting device.
  • the invention subverts the previous grinding machine installation process, and can pre-assemble large-scale equipment such as a mill in a pre-assembly site in advance, which not only shortens the installation period, but also reduces the on-site installation strength and greatly reduces the installation cost.
  • the complete system is driven by a hydraulic system, which is stable in operation, high in lifting weight, high in height, and capable of high-precision positioning and adjustment. It is a function not available in other installation methods.
  • the equipment has low requirements on the installation environment, solves the need for the hoisting of large equipment, and has a short impact time on the surrounding construction environment, which better solves the cross-effects with other special installations.
  • Figure 1 is a schematic view of the present invention
  • Figure 2 is a schematic view of the lifting frame
  • Figure 3 is a schematic view of the lifting device
  • Figure 4 is a schematic view of the hydraulic moving trolley.
  • a method for pre-assembling and lifting a mobile in-position of a large-scale industrial and mining equipment includes the following steps: Step 1: Perform main assembly at a manufacturer of the equipment, and perform equipment foundation at the installation site of the equipment. 3. Transportation road construction;
  • Step 2 transporting the assembled device body to the installation site by using the axle car, and at the same time installing the site assembly to improve the mobile positioning device;
  • the lifting mobile seating device includes the lifting frame 1 with the lifting device 11 and a hydraulic power moving trolley 2 moving on the track, comprising four hydraulic powered trolleys, the hydraulic powered mobile trolleys having a positioning lifting device 21;
  • Step 3 Lifting the device body 100 by the lifting device 11 , after the axis transport vehicle is withdrawn, the hydraulic power moving trolley enters the device body 100 through the track, and fixes the device body 100 on the frame of the hydraulic power mobile trolley 2;
  • Step 4 The hydraulic power moving trolley 2 moves the device body 100 to the side of the device base 3, lifts the device body 100 by the lifting device 21, and after the device body 3 passes the device base 3 at the lowest point of the device body, the moving car group 2 enters the basic position. Then, the device body 100 is retracted by the lifting device 21, and the installation accuracy of the device body 100 is adjusted, and then mounted on the device mounting base 3;
  • step 5 the mobile trolley unit 2 is removed from the equipment installation base position, and the foundation of the lower portion of the equipment main body 100 is constructed, and the final assembly of the equipment is completed.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved.
  • the lifting device comprises: four columns 12 and four beams arranged at the top of the column.
  • the lifting device 11 is mounted on the beams 13 on both sides.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved in place.
  • the lifting device 11 includes four core-through hydraulic lifting devices 15, each of which includes: a separate hydraulic system 151, independent core-through The hydraulic jack 152, the independent cable take-up device 153 and a set of shared PLC remote control boxes (not shown).
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved.
  • the four cross members 13 on the upper part of the lifting frame are provided with a mounting frame 16 , and the hydraulic lifting device 15 is mounted at four corners of the mounting frame 16 .
  • the large-scale industrial and mining equipment is pre-assembled and lifted in place.
  • the mobile trolley 2 includes: two side carrying columns 23 and a vehicle body carrying beam 22, and the in-position lifting device 21 is mounted on the two side carrying columns 23.
  • the large-scale industrial and mining equipment is pre-assembled and lifted and moved in place.
  • the mobile trolley is a hydraulic power mobile trolley 24, which has four, and includes: a set of shared hydraulic systems, four independent hydraulic power motors, eight Balanced axle support (not shown in the picture).
  • the hydraulic power moving trolley 2 may further include an accuracy adjusting device including: a parallel multi-controlled hydraulic cylinder precision adjusting device, and a mechanical winch plus screw adjusting device ( None of the figures are shown).

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Leg Units, Guards, And Driving Tracks Of Cranes (AREA)

Abstract

L'invention porte sur un procédé de pré-assemblage, de levage, de déplacement et de mise en place pour un équipement d'usine et de mine de grande dimension, lequel procédé met en œuvre : l'assemblage d'un corps d'équipement (100) dans l'usine de l'équipement, le transport du corps d'équipement assemblé (100) vers un site d'installation, et, en même temps, dans le site d'installation, la construction d'une base d'équipement (3) et d'une route de transport et l'assemblage d'un équipement de levage, de déplacement et de mise en place qui comprend un bâti de levage (1) comportant des accessoires de levage (11), des rails menant à la base d'équipement (3) et une unité de chariot mobile à entraînement hydraulique (2) comportant des accessoires de mise en place et de levage (21) se déplaçant dans les rails ; le levage du corps d'équipement (100) et la fixation de celui-ci à l'unité de chariot mobile à entraînement hydraulique (2) par le bâti de levage (1) ; le déplacement du corps d'équipement (100) vers un côté de la base d'équipement (3) par l'unité de chariot mobile (2), le levage du corps d'équipement (100) dans la position de base et le fait de le faire redescendre par les accessoires de mise en place et de levage (21) ; le réglage et l'installation du corps d'équipement (100) dans la base d'équipement (3) et la finition de l'assemblage final de l'équipement. Le procédé résout les problèmes de levage, de déplacement et de mise en place de l'équipement de grande dimension, à performances de travail stables.
PCT/CN2010/080305 2010-12-27 2010-12-27 Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension WO2012088653A1 (fr)

Priority Applications (2)

Application Number Priority Date Filing Date Title
PCT/CN2010/080305 WO2012088653A1 (fr) 2010-12-27 2010-12-27 Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension
AU2010366350A AU2010366350B2 (en) 2010-12-27 2010-12-27 Pre-assembling, lifting, moving and emplacing method for large factory and mine equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
PCT/CN2010/080305 WO2012088653A1 (fr) 2010-12-27 2010-12-27 Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension

Publications (1)

Publication Number Publication Date
WO2012088653A1 true WO2012088653A1 (fr) 2012-07-05

Family

ID=46382170

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2010/080305 WO2012088653A1 (fr) 2010-12-27 2010-12-27 Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension

Country Status (2)

Country Link
AU (1) AU2010366350B2 (fr)
WO (1) WO2012088653A1 (fr)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108675126A (zh) * 2018-03-30 2018-10-19 南通振华重型装备制造有限公司 一种集装箱堆场智能化设备的支腿门框拼装工艺

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2369991A1 (fr) * 1976-11-09 1978-06-02 Potain Sa Portique telescopable
FR2776280A1 (fr) * 1998-03-19 1999-09-24 Reel Sa Poutre modulaire pour portique et pont, notamment pont roulant et portique et pont muni d'une telle poutre
CN1696043A (zh) * 2005-05-26 2005-11-16 内蒙古自治区第三电力建设工程有限责任公司 钢煤斗吊装就位的施工工艺
CN101152949A (zh) * 2006-09-27 2008-04-02 十一冶建设有限责任公司 超高超大型大吨位行走井架式吊装机具平移方法及其装置
JP2008156015A (ja) * 2006-12-21 2008-07-10 Murata Mach Ltd 移動クレーン
CN201186864Y (zh) * 2007-12-04 2009-01-28 上海宝冶建设有限公司 大型设备安装用自爬式液压顶升装置
CN201224661Y (zh) * 2008-06-06 2009-04-22 陕西化建工程有限责任公司 小空间室内大型设备的安装装置
CN201288033Y (zh) * 2008-08-28 2009-08-12 中国二十冶建设有限公司 八点液压同步顶升设备的控制装置
CN101580211A (zh) * 2009-06-23 2009-11-18 中国电力科学研究院 大型电力设备安装用多功能组合式吊装构架
CN101712444A (zh) * 2009-10-22 2010-05-26 广东力特工程机械有限公司 普通厂房内吊装大型工件方法及其液压顶升设备

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100366525C (zh) * 2005-12-14 2008-02-06 上海振华港口机械(集团)股份有限公司 岸边起重机和堆场起重机间低架桥式小车转接装卸系统
CN101229883A (zh) * 2008-01-24 2008-07-30 上海振华港口机械(集团)股份有限公司 集装箱码头装卸系统

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2369991A1 (fr) * 1976-11-09 1978-06-02 Potain Sa Portique telescopable
FR2776280A1 (fr) * 1998-03-19 1999-09-24 Reel Sa Poutre modulaire pour portique et pont, notamment pont roulant et portique et pont muni d'une telle poutre
CN1696043A (zh) * 2005-05-26 2005-11-16 内蒙古自治区第三电力建设工程有限责任公司 钢煤斗吊装就位的施工工艺
CN101152949A (zh) * 2006-09-27 2008-04-02 十一冶建设有限责任公司 超高超大型大吨位行走井架式吊装机具平移方法及其装置
JP2008156015A (ja) * 2006-12-21 2008-07-10 Murata Mach Ltd 移動クレーン
CN201186864Y (zh) * 2007-12-04 2009-01-28 上海宝冶建设有限公司 大型设备安装用自爬式液压顶升装置
CN201224661Y (zh) * 2008-06-06 2009-04-22 陕西化建工程有限责任公司 小空间室内大型设备的安装装置
CN201288033Y (zh) * 2008-08-28 2009-08-12 中国二十冶建设有限公司 八点液压同步顶升设备的控制装置
CN101580211A (zh) * 2009-06-23 2009-11-18 中国电力科学研究院 大型电力设备安装用多功能组合式吊装构架
CN101712444A (zh) * 2009-10-22 2010-05-26 广东力特工程机械有限公司 普通厂房内吊装大型工件方法及其液压顶升设备

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108675126A (zh) * 2018-03-30 2018-10-19 南通振华重型装备制造有限公司 一种集装箱堆场智能化设备的支腿门框拼装工艺
CN108675126B (zh) * 2018-03-30 2020-06-05 南通振华重型装备制造有限公司 一种集装箱堆场智能化设备的支腿门框拼装工艺

Also Published As

Publication number Publication date
AU2010366350A1 (en) 2013-01-24
AU2010366350B2 (en) 2015-04-09

Similar Documents

Publication Publication Date Title
CN101518784B (zh) 大型轧机牌坊在吊装高度受限下的吊装方法
CN101277049B (zh) 大型电机液压顶升穿芯吊装方法
CN101880006B (zh) 固定式回转起重机用滚装装置及滚装方法
CN105152032A (zh) 封闭环境厂房内桥式起重机的安装方法
CN105312798A (zh) 一种钢结构数控组对中心
KR100867238B1 (ko) 상하 분리가 가능한 전동 이동대차
CN103437563A (zh) 一种用于大型钢结构厂房钢骨架的安装方法
CN110216434B (zh) 一种用于更换大型升船机安全卷筒轴的导向小车装置及方法
CN102049335A (zh) 大型球磨机安装施工方法
CN104291207A (zh) 一种大型电机设备安装专用工具及其使用方法
CN103862251A (zh) 一种受三维空间约束的大型设备的吊装方法及其辅助设备
WO2012088653A1 (fr) Procédé de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension
CN109368519B (zh) 核电站应急柴油发电机的吊运方法
JP6102827B2 (ja) 圧延機の据付方法
WO2012088654A1 (fr) Dispositif de pré-assemblage, de levage, de déplacement et de mise en place pour équipement d'usine et de mine de grande dimension
CN201309796Y (zh) 门式吊装装置
CN203312095U (zh) 全自由度调节刀闸操动机构精准安装平台
CN113697687B (zh) 一种地下多层双t板结构快速吊装方法及其定位卡具
CN102145353A (zh) O成型机安装方法
CN202245924U (zh) 轨道交通机车车辆地坑式构架翻转机
CN112027926A (zh) 一种移动便携装配式钢结构自动吊装工装系统的施工方法
CN112589421A (zh) 一种辊压机用减速机的安装拆卸装置和安装拆卸方法
CN203312096U (zh) 滑轮组驱动、导向套筒导向的刀闸操动机构精准安装平台
CN203312091U (zh) 滑轮组驱动、导向轮导向的刀闸操动机构精准安装平台
KR100877662B1 (ko) 이동대차를 이용한 수평 장애물 승월 방법

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 10861462

Country of ref document: EP

Kind code of ref document: A1

ENP Entry into the national phase

Ref document number: 2010366350

Country of ref document: AU

Date of ref document: 20101227

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 10861462

Country of ref document: EP

Kind code of ref document: A1