WO2012039049A1 - 無停電電源装置及び電子計算機システム - Google Patents
無停電電源装置及び電子計算機システム Download PDFInfo
- Publication number
- WO2012039049A1 WO2012039049A1 PCT/JP2010/066492 JP2010066492W WO2012039049A1 WO 2012039049 A1 WO2012039049 A1 WO 2012039049A1 JP 2010066492 W JP2010066492 W JP 2010066492W WO 2012039049 A1 WO2012039049 A1 WO 2012039049A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- power
- power supply
- circuit
- electronic computer
- time
- Prior art date
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F1/00—Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
- G06F1/26—Power supply means, e.g. regulation thereof
- G06F1/30—Means for acting in the event of power-supply failure or interruption, e.g. power-supply fluctuations
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F1/00—Details not covered by groups G06F3/00 - G06F13/00 and G06F21/00
- G06F1/26—Power supply means, e.g. regulation thereof
- G06F1/263—Arrangements for using multiple switchable power supplies, e.g. battery and AC
Definitions
- the present invention relates to an uninterruptible power supply and an electronic computer system.
- UPS uninterruptible power supply
- An uninterruptible power supply includes a storage battery (battery) as a backup power supply. For this reason, at the time of a power failure, it can switch to the power supply by a storage battery, and can supply power to a computer.
- the computer saves the data, performs application termination processing, and stops the OS (Operating System).
- the UPS Operating System
- the UPS setting time is set to a longer time with a margin.
- the time required to shut down a computer system generally varies with the passage of system operation time. Conventionally, the fluctuation of the time required for shutdown which increases with the passage of operation time has been relatively small. For this reason, the computer system could be shut down safely within the set time set once.
- the shutdown time of the computer software may be longer than expected. Even if the shutdown time is longer than expected, the UPS will turn off the output voltage after the set time has elapsed. If the shutdown time is shortened, the computer system will be powered off while the computer system is operating, causing abnormal May be shut down.
- UPS generally uses a lead battery for backup.
- Lead batteries have the characteristic that the capacity to store power decreases over time. This life characteristic is such that the capacity at the end of life is about half of the initial capacity.
- the set time at the time of shutdown is lengthened, if the battery is backed up due to a power failure, the power supply to the computer system stops before the set time depending on the storage capacity of the battery. For this reason, similarly, when the shutdown time of the computer software is longer than expected, the computer system may be powered off while the computer system is operating, resulting in an abnormal shutdown.
- An object of the present invention is to provide an uninterruptible power supply and an electronic computer system that prevent the power source from being cut off before the shutdown of the electronic computer system is completed.
- the disclosed uninterruptible power supply includes a main power supply circuit that supplies power to an electronic computer, a backup power supply circuit that supplies power to the electronic computer instead of the main power supply circuit in the event of a power failure, An output power detection circuit for detecting output power supplied to the electronic computer, and in response to a power-off instruction from the electronic computer, the power supply to the electronic computer is cut off after a set time has elapsed, and the output power detection circuit Monitor the detected output power, measure the time until the power-off processing of the computer is completed, and based on the measurement time, abnormal power-off of the computer due to the power supply being cut off at the set time And a control circuit that warns the end of processing.
- another uninterruptible power supply apparatus includes a main power supply circuit that supplies power to an electronic computer, and a backup power supply that supplies power to the electronic computer instead of the main power supply circuit in the event of a power failure A circuit, an output power detection circuit for detecting output power to be supplied to the electronic computer, and in response to a power-off instruction from the electronic computer, the power supply to the electronic computer is cut off after a lapse of a set time, and the output Monitor the output power detected by the power detection circuit, measure the time until the power-off processing of the computer is completed, extend the set time based on the measurement time, and disconnect the power supply A control circuit.
- the disclosed electronic computer system includes an uninterruptible power supply circuit that supplies power to the electronic computer, and the electronic computer that performs power-off processing after transmitting a power-off instruction to the uninterruptible power supply circuit
- the uninterruptible power supply circuit is a main power supply circuit, a backup power supply circuit that supplies power to the electronic computer instead of the main power supply circuit in the event of a power failure, an output power detection circuit that detects output power supplied to the electronic computer,
- the power supply to the computer is cut off after a set time has elapsed, the output power detected by the output power detection circuit is monitored, and the power-off process of the computer The time until the completion of the computer is measured, and based on the measured time, the abnormal power-off processing of the computer due to the power supply being cut off according to the set time.
- a control circuit to warn of the termination.
- another electronic computer system disclosed includes an uninterruptible power supply circuit that supplies power to the electronic computer, and the electronic computer that performs a power-off process after transmitting a power-off instruction to the uninterruptible power supply circuit.
- the uninterruptible power supply circuit includes a main power supply circuit, a backup power supply circuit that supplies power to the electronic computer instead of the main power supply circuit in the event of a power failure, and an output power detection circuit that detects output power supplied to the electronic computer And cutting off the power supply to the electronic computer after a set time has elapsed in response to a power-off instruction from the electronic computer, monitoring the output power detected by the output power detection circuit, and turning off the electronic computer A control circuit for measuring a time until the completion of the processing, extending the set time based on the measurement time, and cutting off the power supply.
- the uninterruptible power supply circuit is provided with a control circuit that measures the time until the output power detection circuit and the power-off processing of the computer are completed. Based on the measurement time until the power-off processing is completed, a warning is issued or the power is disconnected. Since the set time is extended, it is possible to prevent in advance an abnormal shutdown due to the power source of the electronic computer system being cut off while the electronic computer system is operating.
- FIG. 1 is a block diagram of a computer system according to an embodiment.
- FIG. 2 is a block diagram of the server of FIG. 1 and 2 show a server system as a computer system.
- UPS uninterruptible power supply circuit
- the UPS 1 is connected to a commercial power source by a power plug 10.
- the plug PG of the power cable 70 of the server 2 is connected to the outlet CS of the UPS 1.
- the server 2 receives power supply from the UPS 1.
- the server 2 is connected to the UPS 1 via the control interface line 72.
- the server 2 executes the UPS management software 60 and transmits and receives control signals via the UPS 1 and the control interface line 72.
- As the control interface line 72 for example, an RS232C standard interface can be used. However, other standard interfaces may be used.
- the UPS 1 includes a main power supply circuit 11, a backup battery circuit 12, a power failure detection circuit 13, a changeover switch 14, and a power cut-off switch 15.
- the UPS 1 includes an output power detection circuit 16, a control circuit 17, a memory 18, and a display unit 19.
- the main power supply circuit 11 is a circuit that stably outputs the commercial power supply from the plug 10.
- the main power supply circuit 11 converts alternating current into direct current, converts the converted direct current into alternating current, and outputs alternating current 100 volts (V) from which noise and the like are removed.
- the backup battery circuit 12 has a rechargeable battery.
- the backup battery circuit 12 supplies AC power from the battery during a power failure.
- the backup battery circuit 12 charges the battery with power from a commercial power source when the amount of charge of the battery is not sufficient.
- the power failure detection circuit 13 detects a commercial power failure. This power failure includes a case where the plug of the UPS 1 is disconnected and the input of the commercial power is cut off. When a power failure is detected, the power failure detection circuit 13 switches the changeover switch 14 from the output of the main power supply circuit 11 (a side in FIG. 1) to the output of the backup battery circuit 12 (b side in FIG. 1). The output power detection circuit 16 detects AC power (AC 100 volts) output from the changeover switch 14 to the output outlet CS.
- AC power AC 100 volts
- the control circuit 17 receives the power failure detection signal from the power failure detection circuit 13, and notifies the UPS management software 60 of the server 2 of the power failure via the control interface line 72.
- the control circuit 17 receives the detection power of the output power detection circuit 16 and detects the shutdown of the server 2. When detecting the shutdown of the server 2, the control circuit 17 turns off the switch 15 and stops the power supply to the server 2.
- control circuit 17 turns off the switch 15 after the time set from the start instruction in response to the shutdown start instruction from the UPS management software 60 of the server 2 via the control interface line 72 and supplies power to the server 2. To stop.
- the set time is set from the UPS 1 main body or the server 2.
- the control circuit 17 has an arithmetic processing unit (MPU: Micro Processing Unit).
- the memory 18 holds the set time and the shutdown time measured by the control circuit 17 as will be described later.
- the display unit 19 is controlled by the control circuit 17 and displays the operation state of the UPS and an abnormal state described later.
- the display unit 19 includes a display lamp such as an LED (Light Emitting Diode).
- the server 2 includes a power control circuit 24, one or more CPU chips 2A, 2B, a storage unit 26, a bridge circuit 27, a memory 28, a crossbar switch (or switch) 4, and a plurality of input / outputs.
- Units (IOU: Input Output Units) 3A, 3B,... 3N and an external port 30 are included.
- Each of the CPU chips 2A and 2B includes CPUs (Central Processing Units) 20A and 20B and cache memories 22A and 22B.
- IOUs Input / output units
- IO devices such as LAN (Local Area Network) devices and storage devices.
- the storage device 5 is connected to the IOU 3A.
- the storage device 5 is composed of a large capacity storage circuit.
- the storage device 5 is, for example, a database device.
- the storage device 5 has, for example, a RAID (Redundancy Array Independent Disk).
- the CPUs 20A and 20B of the CPU chips 2A and 2B are connected to the cache memories 22A and 22B and to the bridge circuit 27, respectively.
- the CPUs 20A and 20B execute a desired application program and perform business processing based on the operation of the OS.
- the CPUs 20A and 20B are connected to the main memory 28 and the internal storage unit 26 via the bridge circuit 27.
- the main memory 27 stores various programs, parameters, and data.
- the aforementioned UPS management software 60 is expanded in the main memory 28.
- the internal storage unit 26 is composed of a nonvolatile storage unit such as a hard disk drive (HDD).
- the internal storage unit 26 stores various programs, parameters, and data.
- the external port 30 is connected to the control circuit 17 of the UPS 1 in FIG.
- the external port 30 is connected to the CPU chips 2A and 2B via the bridge circuit 27.
- the CPUs 20A and 20B communicate commands and data with the IOUs 3A to 3N via the bridge circuit 27 and the crossbar switch (or switch) 4.
- the bridge circuit 27 performs a bridge function for connecting the CPUs 20A and 20B, the storage unit 26, the main memory 28, the external port 30, and the crossbar switch (or switch) 4.
- the power supply control circuit 24 is supplied with AC power (AC 100 volts) from the UPS 1 via the power cable 70.
- the power supply control circuit 24 includes an AC (alternating current) / DC (direct current) converter and a plurality of DC / DC converters. Then, the power supply control circuit 24 converts AC power (AC 100 volts) from the UPS 1 into DC power having a necessary capacity (current value).
- the power supply control circuit 24 supplies DC power to the CPU chips 2A and 2B via the power supply lines L3 and L4.
- the power supply control circuit 24 supplies DC power to the storage unit 26 and the main memory 28 via the power supply lines L2 and L5. Further, the power supply control circuit 24 supplies DC power to the external storage device 5, the switch 4, and the IOUs 3A to 3N via the power supply lines L1 and L6.
- the CPU chips 2 A and 2 B, the storage unit 26, the bridge circuit 27, the main memory 28, the switch 4, the IOUs 3 A to 3 N, and the storage device 5 receive DC power from the power supply control circuit 24. Then, the CPUs 20A and 20B execute the firmware program and the application program using the cache memories 22A and 22B, the main memory 28, the storage unit 26, and the storage device 5 under the control of the OS. The CPUs 20A and 20B execute UPS management software (application program) 60 to manage the UPS 1.
- UPS management software application program
- the control circuit 17 of the UPS 1 measures the time from the stop instruction time from the OS of the server 2 until the server 2 is turned off, and stores the information in the memory 18. To accumulate. Further, the control circuit 17 statistically processes the data accumulated in the memory 18 in monitoring the shutdown time, and calculates an average value and a standard deviation required for the shutdown. Then, the control circuit 17 determines abnormality from the calculation result and the measurement time. For example, the control circuit 17 determines that there is an abnormality when the measurement time becomes (average value + standard deviation ⁇ 3) or more. Further, if the shutdown is not completed even after the set time has elapsed, the control circuit 17 extends the backup time corresponding to the battery capacity.
- FIG. 3 is an explanatory diagram of power disconnection processing between the uninterruptible power supply circuit and the server.
- FIG. 4 is a time chart of power disconnection processing of the uninterruptible power supply circuit.
- the UPS 1 has a UPS output outlet CS for supplying power to the server.
- the plug PG of the power cable 70 of the server 2 is connected to the output outlet CS.
- power is supplied from the UPS 1 to the server 2.
- control interface line 72 is provided to connect the UPS management software 60 operating on the server 2 and the control circuit 17 of the UPS 1 for communication.
- the UPS management software 60 receives a power failure notification from the UPS 1 via the control interface line 72.
- a command such as a shutdown start instruction is communicated from the UPS management software 60 of the server 1 to the UPS 1 via the control interface line 72.
- the UPS management software 60 When the UPS management software 60 receives the notification of the power failure, it notifies the OS of the server 2 of the power failure. The OS starts the shutdown process. The UPS management software 60 transmits a shutdown start instruction to the UPS 1 in response to the start of the OS shutdown process. When the UPS management software 60 receives a shutdown start (business end) instruction from an operator of the server 2 or by OS schedule management, the UPS management software 60 transmits a shutdown start instruction to the UPS 1.
- the data and setting information of the main memory 60 used by the application program and the firmware program are stored in the storage unit 26 and the storage device 5. Then, the OS finishes the application program and firmware program. Further, the OS stores the OS setting information or the like in the storage unit 26 or the storage device 5 and terminates the OS.
- FIG. 3 and 4 show an example of the shutdown operation sequence when a UPS 1 power failure is detected.
- the operation is the same as that in FIG.
- FIG. 4 when a power failure occurs at the UPS input (AC power supply), the power failure detection circuit 13 of the UPS 1 detects the power failure, switches the changeover switch 14 to the battery 12, and notifies the control circuit 17 of the power failure detection.
- the control circuit 17 is set with a set time until the power is turned off in FIG.
- the control circuit 17 of the UPS 1 notifies the UPS management software 60 of the server 2 of the power failure through the control interface line 72.
- the UPS management software 60 recognizes the power failure notification, the OS starts the shutdown process. After the OS starts the shutdown process, the UPS management software 60 cannot perform UPS control by communication. Therefore, the UPS management software 60 sets the time set for the UPS 1 before starting the shutdown process via the control interface line 72. After that, an instruction is issued with a command to stop the UPS output. This set time is usually set with a sufficient time so that the shutdown is completed within that time.
- the shutdown time of the server 2 may change depending on the number of times the server 2 is operated or the usage of the server 2 is changed. For example, if the server 2 is a database server, the time required for shutdown tends to increase due to an increase in database information. That is, the current shutdown time # 2 is longer than the previous shutdown time # 1.
- the shutdown process does not end within the set time, and the power output from the UPS 1 is cut off during the shutdown process, and the server 2 may end abnormally.
- the control circuit 17 of the UPS 1 monitors the shutdown time every time and issues a prior warning if the shutdown time becomes longer than usual. For example, if the control circuit 17 determines that the current shutdown time # 2 is longer than the previous shutdown time # 1, it issues a warning that the shutdown time has been extended. With this advance warning, it is possible to prevent abnormal operation of the server 2 in advance.
- the control circuit 17 monitors the output power from the UPS 1 (during backup) of the output power detection circuit 16 from the time of power failure detection.
- the control circuit 17 detects from the output power that the server shutdown has been completed and the power supply has been cut off, and monitors the time required for the server 2 to shut down.
- the control circuit 17 stores the measured time in the memory 18 for later processing.
- the control circuit 17 displays an abnormality on the display unit 19 of the UPS 1. For example, the control circuit 17 controls the display unit 19 so that the lamp is lit when an abnormality is detected.
- the control circuit 17 stores the abnormality in the memory 18. Then, at the next startup of the server 2 (for example, a power-on instruction), the control circuit 17 notifies the UPS management software 60 of the server 2 of the abnormality through the control interface line 72.
- the UPS management software 60 issues a warning. This makes it easy for the operator to recognize an abnormality even in an unattended environment.
- the control circuit 17 calculates the average and standard deviation of the measured shutdown time on the assumption that the distribution of the shutdown time becomes a normal distribution (Gaussian distribution), and determines the abnormality of the shutdown time based on the average and standard deviation of the shutdown time. to decide. Thereby, a measurement error can be avoided and an unnecessary abnormality alarm can be prevented.
- the shutdown may not be completed when the set time has elapsed.
- a shutdown time longer than the set time may be required as in the shutdown time # 3 in FIG.
- the control circuit 17 compares the measurement time with the set time, and controls the switch 15 to extend the shutdown time if the shutdown does not occur after the set time.
- the shutdown time tends to become longer due to the increase in data volume.
- a system that can be shut down normally can be provided by the UPS prior warning process or the time extension process in the disclosed form. For this reason, it is possible to prevent data destruction due to an abnormal shutdown.
- the capacity of the battery can be minimized.
- the operator can take countermeasures such as replacing the battery or replacing the uninterruptible power supply with a larger capacity.
- FIG. 5 is a power disconnection processing flowchart according to the first embodiment.
- FIG. 6 is an explanatory diagram of time information recording processing according to the first embodiment.
- FIG. 7 is an explanatory diagram of the distribution of the shutdown time according to the first embodiment. The process of FIG. 5 is executed by the control circuit 17 of FIG. Hereinafter, the process of FIG. 5 will be described with reference to FIGS. 6 and 7.
- the control circuit 17 starts measuring the shutdown time in response to a power failure detection or a shutdown start notification from the server 2.
- the output power detection circuit 16 of the UPS 1 converts the current output from the switch 15 to the outlet CS into power, and detects the output power. When no current flows to the server 2, the output power of the output power detection circuit 16 becomes almost zero.
- the control circuit 17 measures the shutdown time until the output power of the output power detection circuit 16 becomes almost zero from the power failure detection or the shutdown start notification from the server 2. Then, the control circuit 17 records the measured shutdown time in the measurement time area 18 ⁇ / b> A of the memory 18. As shown in FIG. 6, the measurement time area 18 ⁇ / b> A of the memory 18 holds the shutdown time measured by the control circuit 17 every time the server 2 is powered off.
- FIG. 6 shows an example in which the shutdown time for each power-off is managed by the sample number.
- the control circuit 17 determines whether the number of samples stored in the measurement time area 18A of the memory 18 is, for example, 100 samples or more. When the control circuit 17 determines that the number of samples stored in the measurement time area 18A of the memory 18 is not 100 samples or more, the process is terminated. That is, the control circuit 17 turns off the switch 15 after the set time (see FIG. 4) has elapsed, and stops the power supply to the server 2.
- the reference number of 100 samples is an example, and at least two samples are necessary for the above-described abnormality determination. However, if the number of samples is small, accurate determination cannot be made. For this reason, considering the measurement error and the variation in the shutdown time of the server 2, the number of samples is 3 or more, and about 100 samples are desirable.
- control circuit 17 determines that the number of samples stored in the measurement time area 18A of the memory 18 is 100 samples or more, the average value of the duration (data) accumulated in the measurement time area 18A of the memory 18 Calculate Further, the control circuit 17 calculates the standard deviation of the duration (data) accumulated in the measurement time area 18A of the memory 18.
- the control circuit 17 determines the normality of the shutdown time using the calculated average value and standard deviation. Specifically, the control circuit 17 compares whether the currently measured shutdown time is longer than (average value + standard deviation ⁇ 3). As shown in FIG. 6, the distribution of the shutdown time measured by the server 2 under the same operating conditions (data amount, processing capacity, etc.) is a normal distribution (Gaussian distribution). FIG. 6 shows the measured shutdown time (seconds) on the horizontal axis and the number of samples (number of cases) on the vertical axis. In the example of FIG. 6, the variation in the shutdown time under the same operating condition shows a normal distribution, the average value of the shutdown time is 180 seconds, and the standard deviation is about 25 seconds.
- the control circuit 17 determines that there is an abnormality and performs an abnormality process. In the case of an abnormality, the control circuit 17 records the error in the memory 18 as an abnormality, and turns on an abnormality LED (Light Emitting Diode) of the display unit 19. That is, the warning is given so that the operator can understand the abnormal state. In the unattended environment, even if displayed on the UPS 1, it is not recognized by the operator. Therefore, the control circuit 17 notifies the UPS management software 60 of an abnormality at the next system startup via the control interface line 72. By issuing a warning from the UPS management software 60 at the next startup, the operator can easily recognize.
- an abnormality LED Light Emitting Diode
- the shutdown time may change due to changes in the system operation mode.
- the operation mode may be changed from a database server to a file server.
- the UPS management software 60 clears the data stored in the measurement time area 18A of the memory 18 so as not to issue an unnecessary warning when such an operation mode is changed. Thereby, it is possible to prevent an unnecessary warning from being issued when there is an operation change that greatly changes the shutdown time.
- a normal shutdown can be realized by detecting that the server 2 has not been shut down even if the time set in such a case has elapsed and extending the time to disconnect.
- an abnormal shutdown may occur if the extended time becomes longer.
- FIG. 8 is a processing flow diagram of the second embodiment.
- the control circuit 17 of the UPS 1 determines whether it is the output off time when the set time has elapsed from the shutdown start instruction notified from the UPS management program 60.
- control circuit 17 determines whether the output off time is reached, it determines whether the server 2 is shut down. That is, the control circuit 17 determines whether or not the detected power of the output power detection circuit 16 is substantially zero, and determines whether or not the server 2 has completed shutdown.
- control circuit 17 determines that the server 2 has not completed the shutdown, the control circuit 17 extends the time to turn off regardless of the set time.
- the control circuit 17 determines that an abnormality has occurred and performs an abnormality process. In the case of an abnormality, the control circuit 17 records the error in the memory 18 as an abnormality, and turns on an abnormality LED (Light Emitting Diode) of the display unit 19. That is, the warning is given so that the operator can understand the abnormal state. In the unattended environment, even if displayed on the UPS 1, it is not recognized by the operator. Therefore, the control circuit 17 notifies the UPS management software 60 of an abnormality at the next system startup via the control interface line 72. By issuing a warning from the UPS management software 60 at the next startup, the operator can easily recognize.
- an abnormality LED Light Emitting Diode
- FIG. 9 is a process flow diagram of the third embodiment. In the figure, the same components as those shown in FIG.
- the control circuit 17 of the UPS 1 determines whether it is the output off time when the set time has elapsed from the shutdown start instruction notified from the UPS management program 60.
- control circuit 17 determines whether the output off time is reached, it determines whether the server 2 is shut down. That is, the control circuit 17 determines whether the detected power of the output power detection circuit 16 is substantially zero, and determines whether the server 2 has completed shutdown.
- the control circuit 17 determines that an abnormality has occurred and performs an abnormality process. In the case of an abnormality, the control circuit 17 records the error in the memory 18 as an abnormality, and turns on an abnormality LED (Light Emitting Diode) of the display unit 19. That is, the warning is given so that the operator can understand the abnormal state. In the unattended environment, even if displayed on the UPS 1, it is not recognized by the operator. Therefore, the control circuit 17 notifies the UPS management software 60 of an abnormality at the next system startup via the control interface line 72. By issuing a warning from the UPS management software 60 at the next startup, the operator can easily recognize.
- an abnormality LED Light Emitting Diode
- the control circuit 17 measures the shutdown time until the output power of the output power detection circuit 16 becomes almost zero from the power failure detection or the shutdown start notification from the server 2. When the control circuit 17 determines that the server 2 has completed the shutdown, the control circuit 17 records the measured shutdown time in the measurement time area 18 ⁇ / b> A of the memory 18.
- the control circuit 17 determines whether the number of samples stored in the measurement time area 18A of the memory 18 is, for example, 100 samples or more. When the control circuit 17 determines that the number of samples stored in the measurement time area 18A of the memory 18 is not 100 samples or more, the process is terminated. That is, the control circuit 17 turns off the switch 15 after the set time (see FIG. 4) has elapsed, and stops the power supply to the server 2.
- the control circuit 17 determines the normality of the shutdown time using the calculated average value and standard deviation. Specifically, the control circuit 17 compares whether the currently measured shutdown time is longer than (average value + standard deviation ⁇ 3). If the currently measured shutdown time is not longer than (average value + standard deviation ⁇ 3), the control circuit 17 determines that the operation is normal and ends the process.
- the control circuit 17 determines that an abnormality has occurred and performs an abnormality process. In the case of an abnormality, the control circuit 17 records the error in the memory 18 as an abnormality, and turns on an abnormality LED (Light Emitting Diode) of the display unit 19. That is, the warning is given so that the operator can understand the abnormal state. In the unattended environment, even if displayed on the UPS 1, it is not recognized by the operator. Therefore, the control circuit 17 notifies the UPS management software 60 of an abnormality at the next system startup via the control interface line 72. By issuing a warning from the UPS management software 60 at the next startup, the operator can easily recognize.
- an abnormality LED Light Emitting Diode
- the server 2 can be prevented from abnormally shutting down and a stable power-off process can be realized.
- the backup power source is not limited to a battery, and a generator or the like can be used.
- the uninterruptible power supply circuit is provided with a control circuit that measures the time until the output power detection circuit and the power-off processing of the computer are completed. Based on the measurement time until the power-off processing is completed, a warning is issued or the power is disconnected. Since the set time is extended, it is possible to prevent in advance an abnormal shutdown due to the power source of the electronic computer system being cut off while the electronic computer system is operating.
- UPS Uninterruptible power circuit
- Computer Main power supply 12 Backup power supply 13 Power failure detection circuit 14 Changeover switch 15 Switch 16 Output power detection circuit 17 Control circuit 18 Memory 19 Display unit 60 UPS management software
Landscapes
- Engineering & Computer Science (AREA)
- Theoretical Computer Science (AREA)
- Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Power Engineering (AREA)
- Power Sources (AREA)
- Stand-By Power Supply Arrangements (AREA)
Abstract
主電源(11)とバックアップ電源(12)とを有する無停電電源回路(1)に、出力電力検出回路(16)と電子計算機(2)の電源切断処理の完了までの時間を計測する制御回路(17)とを設ける。制御回路(17)が、電源切断処理の完了までの計測時間に基づき、警告を発し、又は電源切断までの設定時間を延長する。このため、電子計算機システムが動作中に電子計算機システムの電源が切断され、異常なシャットダウンとなることを防止できる。
Description
本発明は、無停電電源装置及び電子計算機システムに関する。
コンピュータが正常に稼働するためには、コンピュータに安定した電力を供給する必要がある。コンピュータに安定した電力を供給するため、無停電電源装置(UPS:Un-interruptible Power Supply)が利用されている。無停電電源装置(以下、UPSという)は、バックアップ電源である蓄電池(バッテリー)を備えている。このため、停電時には、蓄電池による電源供給に切り替え、コンピュータに電源を供給できる。
コンピュータが電源供給を必要としない場合には、UPSからコンピュータへの電力供給を切断することは、省電力化の観点で有効である。このため、コンピュータ側からUPSへ電源切断を指示する方法が提案されている。例えば、電源切断に際し、コンピュータのソフトウェアがUPSに対して、何分か後に、UPS出力を切断するようにコマンドを発行する。UPSは、設定された時間が経過すると、無条件で電源出力を切断する。
この設定時間内において、コンピュータは、データを退避し、アプリケーションの終了処理を行い、OS(Operating System)を停止する。即ち、OSが停止した後は、UPSの制御ができないため、UPSの設定時間は余裕を持った長めの時間を設定していた。
コンピュータシステムのシャットダウンに要する時間は、一般的にシステムの運用時間の経過とともに変動する。従来、運用時間の経過とともに増大するシャットダウンに要する時間の変動は比較的小さかった。このため、一回設定した設定時間でコンピュータシステムを安全にシャットダウンできた。
しかしながら、例えば、データベースを保持しているコンピュータにおいては、データの容量が増加するにしたがって、データベースを正常に終了させるための時間は増加する傾向がある。このため、コンピュータのソフトウェアのシャットダウン時間が予想より延びる可能性がある。シャットダウン時間が予想より伸びた場合でも、UPSは設定された時間が経過すると出力電圧をオフするため、シャットダウンの設定時間を短くすると、コンピュータシステムが動作中にコンピュータシステムの電源が切断され、異常なシャットダウンとなる場合がある。
又、バッテリーは充電できるが、時間の経過とともに、電力を蓄積する能力が低下する。例えば、UPSは、一般的には鉛バッテリーをバックアップ用に使用している。鉛バッテリーは時間の経過とともに電力を蓄積できる容量が減少するという特性を持っている。この寿命特性は、初期の容量に対して、寿命末期の容量が約半分となるような特性である。
シャットダウン時の設定時間を長くすると、もし停電によりバッテリーでバックアップしていた場合に、バッテリーの蓄電容量によっては、設定時間前にコンピュータシステムへの電力の供給が停止する。このため、同様に、コンピュータのソフトウェアのシャットダウン時間が予想より延びた場合には、コンピュータシステムが動作中にコンピュータシステムの電源が切断され、異常なシャットダウンとなる場合がある。
本発明の目的は、電子計算機システムのシャットダウン完了前に電源が切断されることを防止する無停電電源装置及び電子計算機システムを提供することにある。
この目的の達成のため、開示の無停電電源装置は、電子計算機に電力を供給する主電源回路と、停電時に前記主電源回路に代わりに前記電子計算機に電力を供給するバックアップ電源回路と、前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間による前記電力供給の切断による前記電子計算機の異常な前記電源切断処理の終了を警告する制御回路とを有する。
又、この目的の達成のため、開示の他の無停電電源装置は、電子計算機に電力を供給する主電源回路と、停電時に前記主電源回路に代わりに前記電子計算機に電力を供給するバックアップ電源回路と、前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間した時間を延長して、前記電力供給を切断する制御回路とを有する。
更に、開示の電子計算機システムは、電子計算機に電力を供給する無停電電源回路と、前記無停電電源回路に電源切断指示を送信した後、電源切断処理を行う前記電子計算機とを有し、前記無停電電源回路は、主電源回路と、停電時に前記主電源回路に代わりに前記電子計算機に電力を供給するバックアップ電源回路と、前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、 前記電子計算機からの前記電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間による前記電力供給の切断による前記電子計算機の異常な前記電源切断処理の終了を警告する制御回路とを有する。
更に、開示の他の電子計算機システムは、電子計算機に電力を供給する無停電電源回路と、前記無停電電源回路に電源切断指示を送信した後、電源切断処理を行う前記電子計算機とを有し、前記無停電電源回路は、主電源回路と、停電時に前記主電源回路に代わりに前記電子計算機に電力を供給するバックアップ電源回路と、前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定した時間を延長して、前記電力供給を切断する制御回路とを有する。
無停電電源回路に出力電力検出回路と電子計算機の電源切断処理の完了までの時間を計測する制御回路を設け、電源切断処理の完了までの計測時間に基づき、警告を発し、又は電源切断までの設定時間を延長するため、電子計算機システムが動作中に電子計算機システムの電源が切断され、異常なシャットダウンとなることを事前に防止できる。
以下、実施の形態の例を、コンピュータシステム、無停電電源回路の電力切断処理、無停電電源回路の電力切断処理の第1の実施の形態、電力切断処理の第2の実施の形態、電力切断処理の第3の実施の形態、他の実施の形態の順で説明するが、開示のコンピュータシステム、無停電電源回路は、この実施の形態に限られない。
(コンピュータシステム)
図1は実施の形態のコンピュータシステムのブロック図である。図2は図1のサーバのブロック図である。図1及び図2は、コンピュータシステムとして、サーバシステムを示す。図1に示すように、無停電電源回路(以下、UPSという)1はサーバ2に電力を供給する。UPS1は電源プラグ10により商用電源に接続する。UPS1のコンセントCSにサーバ2の電力ケーブル70のプラグPGを接続する。これにより、サーバ2は、UPS1から電力の供給を受ける。
図1は実施の形態のコンピュータシステムのブロック図である。図2は図1のサーバのブロック図である。図1及び図2は、コンピュータシステムとして、サーバシステムを示す。図1に示すように、無停電電源回路(以下、UPSという)1はサーバ2に電力を供給する。UPS1は電源プラグ10により商用電源に接続する。UPS1のコンセントCSにサーバ2の電力ケーブル70のプラグPGを接続する。これにより、サーバ2は、UPS1から電力の供給を受ける。
又、サーバ2はUPS1と制御インタフェース線72で接続する。サーバ2はUPS管理ソフトウェア60を実行し、UPS1と制御インタフェース線72を介し制御信号を送受信する。制御インターフェース線72としては、例えば、RS232C規格のインタフェースを使用できる。しかしながら、他の規格のインタフェースを利用しても良い。
UPS1は、主電源回路11とバックアップバッテリー回路12と停電検出回路13と切り替えスイッチ14と電源切断スイッチ15とを有する。又、UPS1は、出力電力検出回路16と制御回路17とメモリ18と表示ユニット19とを有する。
プラグ10からの商用電源(交流AC)は、主電源回路11とバックアップバッテリー回路12と停電検出回路13とに供給される。主電源回路11は、プラグ10からの商用電源を安定に出力する回路である。例えば、主電源回路11は、交流を直流に変換し、変換した直流を交流に変換し、ノイズ等を除去した交流100ボルト(V)を出力する。
バックアップバッテリー回路12は、充電可能なバッテリーを有する。バックアップバッテリー回路12は、停電時にバッテリーから交流電力を供給する。又、バックアップバッテリー回路12は、バッテリーの充電量が十分でない場合に、商用電源からの電力でバッテリーを充電する。
停電検出回路13は商用電源の停電を検出する。この停電は、UPS1のプラグ10が抜けて、商用電源の入力が切断された場合を含む。停電検出回路13は、停電を検出すると、切り替えスイッチ14を主電源回路11の出力(図1のa側)からバックアップバッテリー回路12の出力(図1のb側)に切り替える。出力電力検出回路16は、切り替えスイッチ14から出力コンセントCSに出力される交流電力(AC100ボルト)の電力を検出する。
制御回路17は、停電検出回路13の停電検出信号を受け、制御インタフェース線72を介しサーバ2のUPS管理ソフトウェア60に停電を通知する。又、制御回路17は出力電力検出回路16の検出電力を受け、サーバ2のシャットダウンを検出する。制御回路17は、サーバ2のシャットダウンを検出した場合、スイッチ15をオフし、サーバ2への電源供給を停止する。
更に、制御回路17は制御インタフェース線72を介しサーバ2のUPS管理ソフトウェア60からのシャットダウン開始指示に応じて、開始指示から設定された時間経過後、スイッチ15をオフし、サーバ2への電源供給を停止する。設定時間は、UPS1本体又はサーバ2から設定される。例えば、制御回路17は演算処理ユニット(MPU:Micro Processing Unit)を有する。
メモリ18は後述するように、設定時間や制御回路17が測定したシャットダウン時間を保持する。表示ユニット19は、制御回路17により制御され、UPSの運転状態や後述する異常状態を表示する。表示ユニット19は、例えば、LED(Light Emitting Diode)等の表示ランプを有する。
図2に示すように、サーバ2は、電源制御回路24と単数又は複数のCPUチップ2A、2Bとストレージユニット26とブリッジ回路27とメモリ28とクロスバースイッチ(又はスイッチ)4と複数の入出力ユニット(IOU:Input Output Unit)3A,3B,・・・3Nと外部ポート30とを有する。
CPUチップ2A,2Bの各々は、CPU(Central Processing Unit)20A,20Bとキャッシュメモリ22A,22Bとを有する。入出力ユニット(以下、IOUという)3A~3Nは、LAN(Local Area Network)デバイス、ストレージデバイス等のIOデバイスに接続する。この実施の形態では、ストレージデバイス5がIOU3Aに接続する。ストレージデバイス5は、大容量の記憶回路で構成される。ストレージデバイス5は、例えば、データベースデバイスである。ストレージデバイス5は、例えば、RAID(Redundancy Array Independent Disk)を有する。
CPUチップ2A、2BのCPU20A,20Bの各々がキャッシュメモリ22A,22Bに接続し、且つブリッジ回路27に接続する。CPU20A,20Bは、OSの動作の元に、所望のアプリケーションプログラムを実行し、業務処理を行う。
又、CPU20A,20Bは、ブリッジ回路27を介しメインメモリ28と内部ストレージユニット26に接続する。メインメモリ27は種々のプログラム及びパラメータ、データを格納する。前述のUPS管理ソフトウェア60はメインメモリ28に展開される。内部ストレージユニット26はハードデイスクドライブ(HDD)等の不揮発性記憶ユニットで構成される。内部ストレージユニット26は種々のプログラム及びパラメータ、データを格納する。
外部ポート30は、図1のUPS1の制御回路17に制御インタフェース線72を介し接続する。又、外部ポート30は、ブリッジ回路27を介しCPUチップ2A,2Bに接続する。CPU20A、20Bは、ブリッジ回路27、クロスバースイッチ(又はスイッチ)4を介し、IOU3A~3Nと、コマンド、データの通信を行う。ブリッジ回路27は、CPU20A,20B、ストレージユニット26、メインメモリ28、外部ポート30、クロスバースイッチ(又はスイッチ)4との接続を行うブリッジ機能を果たす。
電源制御回路24は、UPS1から交流電力(AC100ボルト)を電源ケーブル70を介し供給される。電源制御回路24は、AC(交流)/DC(直流)コンバータと複数のDC/DCコンバータを有する。そして、電源制御回路24は、UPS1から交流電力(AC100ボルト)を必要な容量(電流値)の直流電力に変換する。
電源制御回路24は、電源ラインL3,L4を介しCPUチップ2A,2Bに直流電力を供給する。又、電源制御回路24は、電源ラインL2,L5を介しストレージユニット26、メインメモリ28に直流電力を供給する。更に、電源制御回路24は、電源ラインL1,L6を介し外部ストレージデバイス5、スイッチ4、IOU3A~3Nに直流電力を供給する。
このサーバシステム2は、CPUチップ2A,2B、ストレージユニット26、ブリッジ回路27、メインメモリ28、スイッチ4、IOU3A~3N,ストレージデバイス5が電源制御回路24から直流電力を受ける。そして、CPU20A,20Bは、OSの制御の元に、ファームウェアプログラム及びアプリケーションプログラムを、キャッシュメモリ22A,22B、メインメモリ28、ストレージユニット26、ストレージデバイス5を使用して、実行する。CPU20A,20BはUPS管理ソフトウェア(アプリケーションプログラム)60を実行し、UPS1を管理する。
図1に戻り、UPS1の制御回路17は、シャットダウンに要する時間を監視するために、サーバ2のOSからの停止指示時刻からサーバ2が電源オフするまでの時刻を計測し、その情報をメモリ18に蓄積する。又、制御回路17は、シャットダウン時間の監視において、メモリ18に蓄積したデータを統計的に処理して、シャットダウンに要する平均値と標準偏差を計算する。そして、制御回路17は、計算結果と測定時間とから異常を判定する。例えば、制御回路17は、測定時間が(平均値+標準偏差×3)以上になると異常と判断する。更に、制御回路17は、設定された時間が経過しても、シャットダウンが終了していない場合は、バッテリーの容量が持つ時間分のバックアップ時間を延長する。
(無停電電源回路の電力切断処理)
図3は無停電電源回路とサーバとの電力切断処理の説明図である。図4は無停電電源回路の電力切断処理のタイムチャート図である。図3に示すように、UPS1はサーバに電力を供給するためのUPS出力コンセントCSを持つ。サーバ2の電源ケーブル70のプラグPGが、出力コンセントCSに接続される。これにより、UPS1からサーバ2に電力が供給される。
図3は無停電電源回路とサーバとの電力切断処理の説明図である。図4は無停電電源回路の電力切断処理のタイムチャート図である。図3に示すように、UPS1はサーバに電力を供給するためのUPS出力コンセントCSを持つ。サーバ2の電源ケーブル70のプラグPGが、出力コンセントCSに接続される。これにより、UPS1からサーバ2に電力が供給される。
また、制御インタフェース線72はサーバ2で動作するUPS管理ソフトウェア60とUPS1の制御回路17とを接続し、通信するために設けられる。UPS管理ソフトウェア60は、制御インタフェース線72を経由して、UPS1から停電の通知を受ける。又、サーバ1のUPS管理ソフトウェア60から制御インタフェース線72を介しUPS1へシャットダウン開始指示などのコマンドを通信する。
UPS管理ソフトウェア60は、停電の通知を受けると、サーバ2のOSに停電通知を伝える。OSはシャットダウン処理を開始する。UPS管理ソフトウェア60はOSのシャットダウン処理開始に応じて、UPS1へシャットダウン開始指示を送信する。又、UPS管理ソフトウェア60はサーバ2のオペレータから又はOSのスケジュール管理により、シャットダウン開始(業務終了)指示を受けると、UPS1にシャットダウン開始指示を送信する。
OSのシャットダウン処理は、アプリケーションプログラムやファームウェアプログラムが使用していたメインメモリ60のデータ、設定情報をストレージユニット26やストレージデバイス5に格納する。そして、OSはアプリケーションプログラムやファームウェアプログラムを終了処理する。更に、OSはOSの設定情報等をストレージユニット26やストレージデバイス5に格納し、OSを終了する。
図3及び図4はUPS1の停電検出時のシャットダウンの動作シーケンスを例に示してある。しかしながら、サーバ2のオペレータから又はOSのスケジュール管理により、シャットダウンを開始する場合も、図4の動作と同様である。図4に示すように、UPS入力(AC電源)に停電が発生すると、UPS1の停電検出回路13が停電を検出し、切り替えスイッチ14をバッテリー12に切り替え、制御回路17に停電検出を通知する。尚、制御回路17には、図4の電源断までの設定時間が設定されている。
UPS1の制御回路17は制御インタフェース線72を通してサーバ2のUPS管理ソフトウェア60に停電を通知する。UPS管理ソフトウェア60は停電通知を認識すると、OSがシャットダウン処理を開始する。OSがシャットダウン処理を開始した後は、UPS管理ソフトウェア60から通信によるUPS制御ができなくなるため、UPS管理ソフトウェア60は制御インタフェース線72を介し、シャットダウン処理開始前にUPS1に対して、設定された時間の後に、UPS出力を停止するようにコマンドで指示を発行する。この設定された時間は、その時間内にシャットダウンが完了するように、通常は余裕を持った時間を設定する。
サーバ2のシャットダウン時間は、サーバ2の稼働回数やサーバ2の用途の変更により、変化する場合がある。例えば、サーバ2がデータベースサーバであれば、データベースの情報が増加することにより、シャットダウンに要する時間が長くなる傾向にある。即ち、以前のシャットダウン時間#1に対し、今回のシャットダウン時間#2が長くなる。
このようにシャットダウン時間が長くなると、設定時間内にシャットダウン処理が終了せずに、シャットダウン処理の途中でUPS1からの電源出力が切断され、サーバ2が異常な終了となるおそれがある。
開示の第1の形態では、UPS1の制御回路17が毎回のシャットダウンの時間を監視し、通常よりシャットダウンの時間が長くなれば事前警告を発する。例えば、制御回路17が以前のシャットダウン時間#1に対し、今回のシャットダウン時間#2が長いと判断すると、シャットダウンの時間が延びた旨の警告を発する。この事前警告により、サーバ2の異常な動作を事前に防ぐことが可能となる。
図1において、制御回路17は、停電検出時から、出力電力検出回路16の(バックアップ時の)UPS1からの出力電力を監視する。そして、制御回路17は、出力電力からサーバのシャットダウンが終了し、電源が切断されたことを検出するとともに、サーバ2のシャットダウンに要する時間を監視する。制御回路17は、計測した時間は、後で処理するためにメモリ18に格納しておく。
制御回路17は、シャットダウン時間が以前より延びた場合には、UPS1の表示ユニット19に異常を表示する。例えば、制御回路17は、異常を検出した場合に、ランプ点灯するように表示ユニット19を制御する。
例えば、データセンターの設備のように、サーバ2が無人の環境に置かれた場合には、UPS1の表示ユニット19に異常表示されていても、操作者に認識されないおそれがある。このため、制御回路17は、異常であることをメモリ18に記憶しておく。そして、サーバ2の次回の起動時(例えば、電源投入指示)に、制御回路17は制御インタフェース線72を通してサーバ2のUPS管理ソフトウェア60に異常を通知する。UPS管理ソフトウェア60は警告を発する。これにより、無人環境でも、操作者に異常の認識が容易となる。
制御回路17は、シャットダウン時間の分布が正規分布(ガウス分布)となるという前提で、計測したシャットダウン時間の平均と標準偏差を計算し、シャットダウン時間の平均と標準偏差を基準にシャットダウン時間の異常を判断する。これにより、計測誤差を回避でき、無用な異常警報を防止できる。
又、設定時間が経過した時点で、シャットダウンが終了していない場合がある。即ち、図4のシャットダウン時間#3のように、設定時間以上のシャットダウン時間を要する場合がある。開示の第2の実施の形態は、制御回路17が、計測時間と設定時間を比較し、設定時間を過ぎてもシャットダウンしない場合には、シャットダウンの時間を延長するようにスイッチ15を制御する。
サーバのシステムを運用する時間が長くなると、データ量の増加によりシャットダウン時間が長くなる傾向がある。開示の形態のUPSの事前警告処理又は時間延長処理により、正常にシャットダウンできるシステムを提供することができる。このため、異常なシャットダウンに起因するデータの破壊などを防止できる。また、余分なバックアップ時間のための余分なバッテリー容量を持つ必要がなくなるため、バッテリーの容量を最小化できる。
尚、警告があった場合には、操作者は、バッテリーの交換や無停電電源をより大容量なものに交換する等の対応策をとることができる。
(無停電電源回路の電力切断処理の第1の実施の形態)
図5は第1の実施の形態の電力切断処理フロー図である。図6は第1の実施の形態の時間情報記録処理の説明図である。図7は第1の実施の形態のシャットダウン時間の分布の説明図である。図5の処理は図1の制御回路17が実行する。以下、図6、図7を参照して、図5の処理を説明する。
図5は第1の実施の形態の電力切断処理フロー図である。図6は第1の実施の形態の時間情報記録処理の説明図である。図7は第1の実施の形態のシャットダウン時間の分布の説明図である。図5の処理は図1の制御回路17が実行する。以下、図6、図7を参照して、図5の処理を説明する。
(S10)制御回路17は、停電検出又はサーバ2からのシャットダウン開始通知に応じて、シャットダウン時間の計測を開始する。UPS1の出力電力検出回路16は、スイッチ15からコンセントCSへ出力する電流を電力に変換し、出力電力を検出する。サーバ2へ電流が流れなくなると、出力電力検出回路16の出力電力がほぼ零になる。制御回路17は、停電検出又はサーバ2からのシャットダウン開始通知から、出力電力検出回路16の出力電力がほぼ零になるまでのシャットダウン時間を計測する。そして、制御回路17は計測したシャットダウン時間をメモリ18の計測時間領域18Aに記録する。図6に示すように、メモリ18の計測時間領域18Aはサーバ2の電源切断毎に、制御回路17が計測したシャットダウン時間を保持する。図6では、電源切断毎のシャットダウン時間をサンプル番号で管理する例を示す。
(S12)制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、例えば、100サンプル以上であるかを判定する。制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、100サンプル以上でないと判定すると、処理を終了する。即ち、制御回路17は、設定時間(図4参照)経過後、スイッチ15をオフし、サーバ2への電力供給を停止する。ここで、基準数を100サンプルとしたのは、例示であり、前述の異常判定には、少なくとも2サンプル必要である。しかしながら、サンプル数が少ないと、正確な判定が行えない。このため、計測誤差やサーバ2のシャットダウン時間のばらつきを考慮すると、3サンプル数以上であり、100サンプル程度が望ましい。
(S14)制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、100サンプル以上であると判定した場合、メモリ18の計測時間領域18Aに蓄積した継続時間(データ)の平均値を計算する。更に、制御回路17は、メモリ18の計測時間領域18Aに蓄積した継続時間(データ)の標準偏差を計算する。
(S16)制御回路17は、計算した平均値と標準偏差を用いて、シャットダウン時間の正常性を判断する。具体的には、制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長いかを比較する。図6に示すように、サーバ2が同一の稼働条件(データ量、処理能力等)で計測したシャットダウン時間の分布は正規分布(ガウス分布)を示す。尚、図6は横軸に計測したシャットダウン時間(秒)を、縦軸にサンプル数(件数)を示す。図6の例では、同一の稼働条件でのシャットダウン時間のばらつきは正規分布を示し、シャットダウン時間の平均値は180秒であり、標準偏差は約25秒であることを示す。このことから、(平均値+標準偏差×3)程度を基準として、今回測定したシャットダウン時間が長いかを比較することが、異常判定に有効である。例えば、図6の例では、180+25×3=255(秒)を基準とすると、同一稼働条件の全ての場合のシャットダウン時間のばらつきをカバーできるため、異常判定を正確にできる。制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長くない場合には、正常と判定し、処理を終了する。
(S18)一方、制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長い場合は、異常と判定し、異常処理を行う。異常の場合は、制御回路17は、異常として、メモリ18にエラーを記録し、表示ユニット19の異常LED(Light Emitting Diode)を点灯する。即ち、異常状態を操作者にわかるようにして警告する。また、無人の環境ではUPS1に表示されていても操作者に認識されないため、制御回路17は、制御インタフェース線72を通して次回のシステム起動時にUPS管理ソフトウェア60に異常を通知する。次回起動時に、UPS管理ソフトウェア60から警告を発することにより、操作者に認識が容易となる。
又、システムの運用形態が変更になったことにより、シャットダウン時間が変化する場合がある。例えば、データベースサーバをファイルサーバに運用形態を変更する場合がある。このような運用形態の変更があった場合に、不要な警告を出さないために、UPS管理ソフトウェア60が、メモリ18の計測時間領域18Aに蓄積されたデータをクリアする。これにより、シャットダウン時間が大きく変わるような運用変更があった場合に、不要な警告を出すことを防止することができる。
(電源切断処理の第2の実施の形態)
次に、図4で説明した設定された時間よりシャットダウンの時間が延長される場合(シャットダウン時間#3)の実施の形態の処理を説明する。図4において、シャットダウンの時間が#3の場合は、従来の技術ではシャットダウンの途中でUPS出力が停止するために、サーバ2の電源が突然切れてしまい、異常なシャットダウン(ダーティシャットダウン)となる。
次に、図4で説明した設定された時間よりシャットダウンの時間が延長される場合(シャットダウン時間#3)の実施の形態の処理を説明する。図4において、シャットダウンの時間が#3の場合は、従来の技術ではシャットダウンの途中でUPS出力が停止するために、サーバ2の電源が突然切れてしまい、異常なシャットダウン(ダーティシャットダウン)となる。
本実施の形態では、このような場合に設定された時間が経過しても、サーバ2がシャットダウンしていないことを検出して、切断する時間を延長することにより、正常なシャットダウンを実現できる。ただし、UPS1のバッテリー容量により、バックアップできる時間には限りがあるため、延長時間が長くなった場合には、異常シャットダウンとなる場合がある。
図8は第2の実施の形態の処理フロー図である。
(S20)UPS1の制御回路17は、UPS管理プログラム60から通知されたシャットダウン開始指示から設定された時間経過した出力オフ時刻になっているかを判定する。
(S22)制御回路17は、出力オフ時刻になったと判定した場合に、サーバ2がシャットダウンしているかどうかを判断する。即ち、制御回路17は、出力電力検出回路16の検出電力がほぼ零であるかを判定し、サーバ2がシャットダウンを完了しているか否かを判定する。
(S24)制御回路17は、サーバ2がシャットダウンを完了していると判定した場合は、UPSからの出力をオフして処理を終了する。これは正常な場合の処理である。
(S26)制御回路17は、サーバ2がシャットダウンを完了していないと判定した場合は、設定時間にかかわらず、オフする時間を延長する。
(S28)制御回路17は、時間を延長した場合は、異常と判定し、異常処理を行う。異常の場合は、制御回路17は、異常として、メモリ18にエラーを記録し、表示ユニット19の異常LED(Light Emitting Diode)を点灯する。即ち、異常状態を操作者にわかるようにして警告する。また、無人の環境ではUPS1に表示されていても操作者に認識されないため、制御回路17は、制御インタフェース線72を通して次回のシステム起動時にUPS管理ソフトウェア60に異常を通知する。次回起動時に、UPS管理ソフトウェア60から警告を発することにより、操作者に認識が容易となる。
(電源切断処理の第3の実施の形態)
次に、第1の実施の形態と第2の実施の形態とを組み合わせた第3の実施の形態を説明する。図9は第3の実施の形態の処理フロー図である。図中、図8で示したものと同一のものは、同一に記号を付す。
次に、第1の実施の形態と第2の実施の形態とを組み合わせた第3の実施の形態を説明する。図9は第3の実施の形態の処理フロー図である。図中、図8で示したものと同一のものは、同一に記号を付す。
(S20)UPS1の制御回路17は、UPS管理プログラム60から通知されたシャットダウン開始指示から設定された時間経過した出力オフ時刻になっているかを判定する。
(S22)制御回路17は、出力オフ時刻になったと判定した場合に、サーバ2がシャットダウンしているかどうかを判断する。即ち、制御回路17は、出力電力検出回路16の検出電力がほぼ零であるかを判定し、サーバ2がシャットダウンを完了している否かを判定する。
(S26)制御回路17は、サーバ2がシャットダウンを完了していないと判定した場合は、設定時間にかかわらず、オフする時間を延長する。このため、シャットダウンが完了するまで、UPS1からの出力をオフしないため、サーバ2が異常なシャットダウンとなることを防ぐことが可能となる。
(S28)制御回路17は、時間を延長した場合は、異常と判定し、異常処理を行う。異常の場合は、制御回路17は、異常として、メモリ18にエラーを記録し、表示ユニット19の異常LED(Light Emitting Diode)を点灯する。即ち、異常状態を操作者にわかるようにして警告する。また、無人の環境ではUPS1に表示されていても操作者に認識されないため、制御回路17は、制御インタフェース線72を通して次回のシステム起動時にUPS管理ソフトウェア60に異常を通知する。次回起動時に、UPS管理ソフトウェア60から警告を発することにより、操作者に認識が容易となる。
(S30)制御回路17は、停電検出又はサーバ2からのシャットダウン開始通知から、出力電力検出回路16の出力電力がほぼ零になるまでのシャットダウン時間を計測している。制御回路17は、サーバ2がシャットダウンを完了していると判定した場合は、制御回路17は計測したシャットダウン時間をメモリ18の計測時間領域18Aに記録する。
(S32)制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、例えば、100サンプル以上であるかを判定する。制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、100サンプル以上でないと判定すると、処理を終了する。即ち、制御回路17は、設定時間(図4参照)経過後、スイッチ15をオフし、サーバ2への電力供給を停止する。
(S34)制御回路17は、メモリ18の計測時間領域18Aに格納したサンプル数が、100サンプル以上であると判定した場合、メモリ18の計測時間領域18Aに蓄積した継続時間(データ)の平均値を計算する。更に、制御回路17は、メモリ18の計測時間領域18Aに蓄積した継続時間(データ)の標準偏差を計算する。
(S36)制御回路17は、計算した平均値と標準偏差を用いて、シャットダウン時間の正常性を判断する。具体的には、制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長いかを比較する。制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長くない場合には、正常と判定し、処理を終了する。
(S38)一方、制御回路17は、今回測定したシャットダウン時間が(平均値+標準偏差×3)より長い場合は、異常と判定し、異常処理を行う。異常の場合は、制御回路17は、異常として、メモリ18にエラーを記録し、表示ユニット19の異常LED(Light Emitting Diode)を点灯する。即ち、異常状態を操作者にわかるようにして警告する。また、無人の環境ではUPS1に表示されていても操作者に認識されないため、制御回路17は、制御インタフェース線72を通して次回のシステム起動時にUPS管理ソフトウェア60に異常を通知する。次回起動時に、UPS管理ソフトウェア60から警告を発することにより、操作者に認識が容易となる。
このように、事前警告処理と時間延長処理を組み合わせることにより、サーバ2のシャットダウンの異常終了を防止でき、安定な電源切断処理を実現できる。
(他の実施の形態)
前述の実施の形態では、サーバが1台の例で説明したが、複数台のサーバにも適用できる。又、バックアップ電源はバッテリーに限らず、発電機等も使用できる。
前述の実施の形態では、サーバが1台の例で説明したが、複数台のサーバにも適用できる。又、バックアップ電源はバッテリーに限らず、発電機等も使用できる。
以上、本発明を実施の形態により説明したが、本発明の趣旨の範囲内において、本発明は、種々の変形が可能であり、本発明の範囲からこれらを排除するものではない。
無停電電源回路に出力電力検出回路と電子計算機の電源切断処理の完了までの時間を計測する制御回路を設け、電源切断処理の完了までの計測時間に基づき、警告を発し、又は電源切断までの設定時間を延長するため、電子計算機システムが動作中に電子計算機システムの電源が切断され、異常なシャットダウンとなることを事前に防止できる。
1 無停電電源回路(UPS)
2 電子計算機
11 主電源
12 バックアップ電源
13 停電検出回路
14 切り替えスイッチ
15 スイッチ
16 出力電力検出回路
17 制御回路
18 メモリ
19 表示ユニット
60 UPS管理ソフトウェア
2 電子計算機
11 主電源
12 バックアップ電源
13 停電検出回路
14 切り替えスイッチ
15 スイッチ
16 出力電力検出回路
17 制御回路
18 メモリ
19 表示ユニット
60 UPS管理ソフトウェア
Claims (14)
- 電子計算機に電力を供給する主電源回路と、
停電時に前記主電源回路の代わりに前記電子計算機に電力を供給するバックアップ電源回路と、
前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、
前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間による前記電力供給の切断による前記電子計算機の異常な前記電源切断処理の終了を警告する制御回路とを有する
ことを特徴とする無停電電源回路。 - 電子計算機に電力を供給する主電源回路と、
停電時に前記主電源回路の代わりに前記電子計算機に電力を供給するバックアップ電源回路と、
前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、
前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間した時間を延長して、前記電力供給を切断する制御回路とを有する
ことを特徴とする無停電電源回路。 - 請求項1の無停電電源回路であって、
前記計測時間を計測毎に記憶する記憶部を更に有し、
前記制御回路は、前記記憶部の複数の計測時間を統計的に処理し、処理結果の統計値と前記計測した計測時間とを比較して、前記異常な前記電源切断処理の終了を警告するか否か判定する
ことを特徴とする無停電電源回路。 - 請求項3の無停電電源回路であって、
前記制御回路は、前記記憶部の複数の計測時間から平均値と標準偏差値を計算し、前記平均値と前記標準偏差値とを比較して、前記異常な前記電源切断処理の終了を警告するか否か判定する
ことを特徴とする無停電電源回路。 - 請求項4の無停電電源回路であって、
前記制御回路は、前記計測時間が(平均値+標準偏差値×3)以上であるかを判定し、前記計測時間が(平均値+標準偏差値×3)以上であると判定した場合に、前記異常な前記電源切断処理の終了を警告する
ことを特徴とする無停電電源回路。 - 請求項3の無停電電源回路であって、
前記制御回路は、前記記憶部に格納された前記計測時間の数が所定数以上である場合に、前記記憶部の複数の計測時間を統計的に処理し、処理結果の統計値と前記計測した計測時間とを比較し、前記計測時間の数が所定数以下である場合には、前記警告のための処理を実行しない
ことを特徴とする無停電電源回路。 - 請求項2の無停電電源回路であって、
前記制御回路は、前記設定した時間を延長して、前記電力供給を切断するとともに、異常な前記電源切断処理の終了を警告する
ことを特徴とする無停電電源回路。 - 電子計算機に電力を供給する無停電電源装置と、
前記無停電電源装置に電源切断指示を送信した後、電源切断処理を行う前記電子計算機とを有し、
前記無停電電源装置は、
主電源回路と、
停電時に前記主電源回路の代わりに前記電子計算機に電力を供給するバックアップ電源回路と、
前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、
前記電子計算機からの前記電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間による前記電力供給の切断による前記電子計算機の異常な前記電源切断処理の終了を警告する制御回路とを有する
ことを特徴とする電子計算機システム。 - 電子計算機に電力を供給する無停電電源装置と、
前記無停電電源装置に電源切断指示を送信した後、電源切断処理を行う前記電子計算機とを有し、
前記無停電電源装置は、
主電源回路と、
停電時に前記主電源回路の代わりに前記電子計算機に電力を供給するバックアップ電源回路と、
前記電子計算機へ供給する出力電力を検出する出力電力検出回路と、
前記電子計算機からの電源切断指示に応じて、設定時間経過後に前記電子計算機への電力供給を切断するとともに、前記出力電力検出回路が検出した出力電力を監視し、前記電子計算機の電源切断処理の完了までの時間を計測し、前記計測時間に基づいて、前記設定時間した時間を延長して、前記電力供給を切断する制御回路とを有する
ことを特徴とする電子計算機システム。 - 請求項8の電子計算機システムであって、
前記無停電電源装置は、前記計測時間を計測毎に記憶する記憶部を更に有し、
前記制御回路は、前記記憶部の複数の計測時間を統計的に処理し、処理結果の統計値と前記計測した計測時間とを比較して、前記異常な前記電源切断処理の終了を警告するか否か判定する
ことを特徴とする電子計算機システム。 - 請求項10の電子計算機システムであって、
前記制御回路は、前記記憶部の複数の計測時間から平均値と標準偏差値を計算し、前記平均値と前記標準偏差値とを比較して、前記異常な前記電源切断処理の終了を警告するか否か判定する
ことを特徴とする電子計算機システム。 - 請求項11の電子計算機システムであって、
前記制御回路は、前記計測時間が(平均値+標準偏差値×3)以上であるかを判定し、前記計測時間が(平均値+標準偏差値×3)以上であると判定した場合に、前記異常な前記電源切断処理の終了を警告する
ことを特徴とする電子計算機システム。 - 請求項10の電子計算機システムであって、
前記制御回路は、前記記憶部に格納された前記計測時間の数が所定数以上である場合に、前記記憶部の複数の計測時間を統計的に処理し、処理結果の統計値と前記計測した計測時間とを比較し、前記計測時間の数が所定数以下である場合には、前記警告のための処理を実行しない
ことを特徴とする電子計算機システム。 - 請求項9の電子計算機システムであって、
前記制御回路は、前記設定した時間を延長して、前記電力供給を切断するとともに、異常な前記電源切断処理の終了を警告する
ことを特徴とする電子計算機システム。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2012534865A JP5556894B2 (ja) | 2010-09-24 | 2010-09-24 | 無停電電源装置及び電子計算機システム |
PCT/JP2010/066492 WO2012039049A1 (ja) | 2010-09-24 | 2010-09-24 | 無停電電源装置及び電子計算機システム |
US13/803,409 US9116682B2 (en) | 2010-09-24 | 2013-03-14 | Uninterruptible power supply device with alerts abnormal end of power-off processing of a computer system |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/JP2010/066492 WO2012039049A1 (ja) | 2010-09-24 | 2010-09-24 | 無停電電源装置及び電子計算機システム |
Related Child Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US13/803,409 Continuation US9116682B2 (en) | 2010-09-24 | 2013-03-14 | Uninterruptible power supply device with alerts abnormal end of power-off processing of a computer system |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2012039049A1 true WO2012039049A1 (ja) | 2012-03-29 |
Family
ID=45873563
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2010/066492 WO2012039049A1 (ja) | 2010-09-24 | 2010-09-24 | 無停電電源装置及び電子計算機システム |
Country Status (3)
Country | Link |
---|---|
US (1) | US9116682B2 (ja) |
JP (1) | JP5556894B2 (ja) |
WO (1) | WO2012039049A1 (ja) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103713721A (zh) * | 2012-10-04 | 2014-04-09 | 纬创资通股份有限公司 | 不断电系统及其电源控制系统 |
JP6020707B2 (ja) * | 2013-03-18 | 2016-11-02 | 富士通株式会社 | 情報処理装置、情報処理装置の停止方法、及び情報処理装置の停止プログラム |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US9965365B2 (en) * | 2013-12-31 | 2018-05-08 | Lite-On, Inc. | Power supply failover system and method |
US9698614B2 (en) | 2015-11-20 | 2017-07-04 | International Business Machines Corporation | Adjusting an extended power line disruption time and end-of-life used for at least one battery backup unit in a system |
US9772942B2 (en) * | 2015-12-09 | 2017-09-26 | Lenovo Enterprise Solutions (Singapore) PTE., LTD. | Committing transaction without first flushing processor cache to non-volatile memory when connected to UPS |
US10409349B2 (en) * | 2016-02-19 | 2019-09-10 | Microsoft Technology Licensing, Llc | Remediating power loss at a server |
EP3477427A1 (en) * | 2017-10-30 | 2019-05-01 | Thomson Licensing | Early detection of power supply failure combined with premature switching to a backup power supply |
US10955892B2 (en) | 2018-09-17 | 2021-03-23 | Advanced Micro Devices, Inc. | Transition into and out of a partially-off power state |
US11822403B1 (en) * | 2022-06-14 | 2023-11-21 | Schneider Electric It Corporation | Systems and methods for intelligent UPS shutdown sequencing in virtualization environments |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63251845A (ja) * | 1987-04-08 | 1988-10-19 | Hitachi Ltd | プログラム異常検出装置 |
JP2000316239A (ja) * | 1999-04-28 | 2000-11-14 | Nec Corp | 無停電電源装置および無停電電源装置の給電制御方法 |
JP2007272756A (ja) * | 2006-03-31 | 2007-10-18 | Toshiba Corp | 無停電電源装置および電源管理方法 |
JP2009183044A (ja) * | 2008-01-30 | 2009-08-13 | Fuji Electric Systems Co Ltd | 電源管理装置および無停電電源装置 |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5315161A (en) * | 1990-09-27 | 1994-05-24 | Ncr Corporation | Power failure detection and shut down timer |
JPH06161610A (ja) | 1992-09-08 | 1994-06-10 | Toshiba Corp | コンピュータ設備 |
JPH08263134A (ja) * | 1995-03-27 | 1996-10-11 | Oki Electric Ind Co Ltd | プロセス制御装置の異常検出方法およびプロセス制御装置 |
US5923099A (en) * | 1997-09-30 | 1999-07-13 | Lam Research Corporation | Intelligent backup power controller |
US6274949B1 (en) * | 1999-01-18 | 2001-08-14 | Hewlett-Packard Company | Back-up power accessory for a computer |
JP4258112B2 (ja) * | 2000-07-27 | 2009-04-30 | 株式会社デンソー | ノード診断方法およびノード診断システム |
JP2002196845A (ja) * | 2000-12-27 | 2002-07-12 | Matsushita Electric Ind Co Ltd | マイクロコンピュータの制御方法 |
US7411314B2 (en) * | 2003-08-19 | 2008-08-12 | Dunstan Robert A | Automatic shut off of backup power source in the extended absence of AC power |
TWI377763B (en) * | 2008-12-31 | 2012-11-21 | Ups aparatus and method of power saving thereof |
-
2010
- 2010-09-24 WO PCT/JP2010/066492 patent/WO2012039049A1/ja active Application Filing
- 2010-09-24 JP JP2012534865A patent/JP5556894B2/ja active Active
-
2013
- 2013-03-14 US US13/803,409 patent/US9116682B2/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS63251845A (ja) * | 1987-04-08 | 1988-10-19 | Hitachi Ltd | プログラム異常検出装置 |
JP2000316239A (ja) * | 1999-04-28 | 2000-11-14 | Nec Corp | 無停電電源装置および無停電電源装置の給電制御方法 |
JP2007272756A (ja) * | 2006-03-31 | 2007-10-18 | Toshiba Corp | 無停電電源装置および電源管理方法 |
JP2009183044A (ja) * | 2008-01-30 | 2009-08-13 | Fuji Electric Systems Co Ltd | 電源管理装置および無停電電源装置 |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103713721A (zh) * | 2012-10-04 | 2014-04-09 | 纬创资通股份有限公司 | 不断电系统及其电源控制系统 |
US9244509B2 (en) | 2012-10-04 | 2016-01-26 | Wistron Corporation | Uninterruptible power system and power control system thereof |
CN103713721B (zh) * | 2012-10-04 | 2016-04-27 | 纬创资通股份有限公司 | 不断电系统及其电源控制系统 |
JP6020707B2 (ja) * | 2013-03-18 | 2016-11-02 | 富士通株式会社 | 情報処理装置、情報処理装置の停止方法、及び情報処理装置の停止プログラム |
JPWO2014147700A1 (ja) * | 2013-03-18 | 2017-02-16 | 富士通株式会社 | 情報処理装置、情報処理装置の停止方法、及び情報処理装置の停止プログラム |
Also Published As
Publication number | Publication date |
---|---|
JPWO2012039049A1 (ja) | 2014-02-03 |
US9116682B2 (en) | 2015-08-25 |
JP5556894B2 (ja) | 2014-07-23 |
US20130198537A1 (en) | 2013-08-01 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5556894B2 (ja) | 無停電電源装置及び電子計算機システム | |
JP3711559B2 (ja) | 情報処理装置および方法、記録媒体、並びにプログラム | |
EP2720052B1 (en) | System and method for automated failure detection of hold-up power storage devices | |
US7831860B2 (en) | System and method for testing redundancy and hot-swapping capability of a redundant power supply | |
JP5289616B2 (ja) | 電子モジュール形態の無停電電源装置のための回路および方法 | |
US7203846B2 (en) | System and method for intelligent control of power consumption of distributed services during periods of reduced load | |
US6957353B2 (en) | System and method for providing minimal power-consuming redundant computing hardware for distributed services | |
US7043650B2 (en) | System and method for intelligent control of power consumption of distributed services during periods when power consumption must be reduced | |
US7844844B2 (en) | System and method for reserving information handling system battery charge to perform diagnostics | |
US20090066529A1 (en) | Remaining battery level management system and method of controlling the same | |
US20100244571A1 (en) | System and method for changing power states of a power device | |
JP2003150280A (ja) | バックアップ管理システムおよび方法 | |
US20150082071A1 (en) | Smart Monitoring Apparatus | |
CN106648016B (zh) | 供电电路、供电设备及供电方法 | |
JP3711557B2 (ja) | 情報処理装置および方法、記録媒体、並びにプログラム | |
CN112667470A (zh) | 一种服务器功率评估及检测的系统、方法及介质 | |
US20090138740A1 (en) | Method and computer device capable of dealing with power fail | |
CN111984471A (zh) | 一种机柜电源bmc冗余管理系统及方法 | |
US20030023887A1 (en) | Computer system with backup management for handling embedded processor failure | |
JP4304624B2 (ja) | 情報処理装置、無停電電源装置、給電方法、記録媒体、および、プログラム | |
US7793115B2 (en) | Method and apparatus for operating a power feed in a computer system | |
JP4543328B2 (ja) | 情報処理装置、無停電電源装置、給電方法、記録媒体、および、プログラム | |
KR101154064B1 (ko) | 전원 감시 장치 및 방법 | |
JP6446948B2 (ja) | 電子機器、電源装置および電源監視方法 | |
US20240219986A1 (en) | Multi-node system and power supply control method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 10857543 Country of ref document: EP Kind code of ref document: A1 |
|
ENP | Entry into the national phase |
Ref document number: 2012534865 Country of ref document: JP Kind code of ref document: A |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
122 | Ep: pct application non-entry in european phase |
Ref document number: 10857543 Country of ref document: EP Kind code of ref document: A1 |