US3688509A - Method of assembling a sheet piling in the earth from sheet pile sections; as well as a sheet pile section suitable for application in this method - Google Patents
Method of assembling a sheet piling in the earth from sheet pile sections; as well as a sheet pile section suitable for application in this method Download PDFInfo
- Publication number
- US3688509A US3688509A US90617A US3688509DA US3688509A US 3688509 A US3688509 A US 3688509A US 90617 A US90617 A US 90617A US 3688509D A US3688509D A US 3688509DA US 3688509 A US3688509 A US 3688509A
- Authority
- US
- United States
- Prior art keywords
- pile section
- edge portion
- channel
- earth
- sheet pile
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Lifetime
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/14—Sealing joints between adjacent sheet piles
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
- E02D5/06—Fitted piles or other elements specially adapted for closing gaps between two sheet piles or between two walls of sheet piles
Definitions
- ABSCT A method of assembling a sheet piling in the earth from sheet pile sections which are each provided on either side with a locking channel and which are successively introduced into the earth. Prior to the introduction of a sheet pile section into the earth, its locking channel which is to co-operate with the adjacent locking channel of the next sheet pile section is sealed on the lower side as well as in the lower area of the upright open side.
- a sheet pile section provided on either side with a locking channel, wherein one of said locking channels is sealed on its lower side by a lower end plate and on the upright open side by an upright side plate, which extends from the lower side of the locking channel over part of the height of said locking channel.
- the invention relates to a method of assembling a sheet piling in the earth from sheet pile sections which are each provided on either side with a locking channel.
- this method is characterized in that prior to the introduction of a sheet pile section into the earth, its locking channel which is to co-operate with the adjacent locking channel of the next sheet pile section is sealed on the lower side as well as in the lower area of the upright open side, while during the introduction of this sheet pile section into the earth a liquid having a low internal friction and a high specific gravity is fed into said locking channel, said liquid keeping the locking channel filled to approximately the level of the ground surface, while this liquid is forced out of the locking channel when the next sheet pile section is being introduced into the earth.
- the liquid prevents earth from penetrating into the locking channel, so that practically no frictional resistance will occur between the interengaging locking channels during the introduction into the earth of the next sheet pile section.
- the seal on the lower'portion of the upright side of the locking channel prevents penetration into said locking channel of earth which tends to press on the lower end of the sheet pile section while this section is being driven into the earth. This pressure is no longer active at a distance from the lower side, so that the locking channel may be caused to be completely filled with liquid with the aid of the bottom seal and of the partial lateral seal of said locking channel.
- the invention further comprises a sheet pile section suitable for application in the method described hereinbefore.
- Said sheet pile section is characterized in that one of the locking channels is sealed on its lower side by a lower end plate and on the upright open side by an upright side plate, which extends from the lower side of the locking channel over part of the height of said locking channel.
- the invention also comprises a sheet piling assembled from said sheet pile sections with the application of the method described hereinabove.
- FIG. 1 shows a portion of a sheet pile section according to the invention during the introduction into the earth, the earth in front of the sheet pile section having been omitted for greater clarity.
- FIG. 2 is a perspective view of the lower part of the locking channel shown in FIG. 1, on a larger scale.
- FIG. 3 illustrates the sheet pile section of FIG. 1 showing the reamer below the locking channel of the subsequent pile section
- FIG. 4 shows the hose for flushing liquid into the locking channel of the sheet pile section.
- FIG. 1 DESCRIPTION OF A PREFERRED EMBODIMENT
- a sheet pile section 1 is shown, which has been rammed or vibrated almost completely into the earth.
- This sheet pile section 1 comprises on either side a locking channel.
- FIG. 1 only shows the locking channel 2 which is remote from the last sheet pile section (not shown) already driven in the earth.
- this locking channel 2 is sealed on its lower side by a lower end plate 3 and on the upright open side by an upright side plate 4, which extends from the lower side of the locking channel 2 over part of this locking channel 2.
- the height of the upright side plate 4 may range from 0.5 to 1.5 meters.
- the lower end plate 3 as well as the upright side plate 4 may be made of thin sheet iron having a thickness of, for example, 1 millimeter, but the use of other materials is of course also possible.
- a liquid having a low internal friction and a high specific gravity is fed into the locking channel 2 shown.
- the other locking channel of the sheet pile section I which is not provided with an end plate 3 or with a side plate 4, engages during the introduction of the sheet pile section 1 with the adjacent locking channel of the preceding sheet pile section which has already been introduced into the earth, the latter locking channel being of the same construction as the locking channel 2.
- the liquid is first fed into a hole 5 which has been dug into the earth, from where the liquid runs into the locking channel 2.
- the liquid used may be a bentonite suspension, the stability of which, while maintaining the thixotropic properties, may be enhanced by adding a small amount of cement.
- the liquid consistently keeps the locking channel 2 filled to approximately the level of the ground surface and prevents earth from penetrating into the locking channel 2.
- a reamer 7 as shown in FIG. 3, having a height of a few centimeters, accommodated underneath the wall portion of the locking channel of said subsequent sheet pile section which interlocks with the sheet pile section 1 that has already been introduced into the earth, is fittingly received in the locking channel 2.
- This reamer may be rigidly attached to this subsequent sheet pile section and presses the liquid sideways out of the locking channel 2 with its lower end.
- the wall portion of the locking channel of the subsequent sheet pile section, which is intended to interlock with the locking channel 2, may be removed over a height from the underside which approximately corresponds to that of the upright side plate 4.
- said upright said plate 4 of a material which is deformed and compressed by the wall of the locking channel of the next sheet pile section during the introduction thereof.
- the major advantage is attained that frictional resistance in the locking channels during the introduction into the earth of the sheet pile sections is reduced to a minimum.
- a method according to claim 1, comprising fastening a reamer in the channel-shaped edge portion of said successive pile section, said reamer extending below said pile section and adapted to extend into the channel-shaped edge portion of the preceding pile section, said liquid being forced sideways and upwardly by the lower end of said reamer during assembly of said pile sections.
- a sheet pile section having on either side generally channel-shaped edge portions adapted to lockingly engage similar edge portions of adjacent contiguously positioned piling sections, one of said channel-shaped edge portions comprising an end plate-sealing the lower end thereof, and an upwardly extending side plate extendin over the open end of said edge portion said side p ate extending upwardly from the lower edge of said channel-shaped edge portion over a part of the height of the edge portion of said piling section.
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
NL696917636A NL140917B (nl) | 1969-11-22 | 1969-11-22 | Werkwijze voor het in de grond samenstellen van een damwand uit damwandprofielen; alsmede damwandprofiel, ingericht voor toepassing bij deze werkwijze. |
Publications (1)
Publication Number | Publication Date |
---|---|
US3688509A true US3688509A (en) | 1972-09-05 |
Family
ID=19808457
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
US90617A Expired - Lifetime US3688509A (en) | 1969-11-22 | 1970-11-18 | Method of assembling a sheet piling in the earth from sheet pile sections; as well as a sheet pile section suitable for application in this method |
Country Status (7)
Country | Link |
---|---|
US (1) | US3688509A (ja) |
JP (1) | JPS5234845B1 (ja) |
DE (1) | DE2057548B2 (ja) |
FR (1) | FR2069811A5 (ja) |
GB (1) | GB1301320A (ja) |
MY (1) | MY7300397A (ja) |
NL (1) | NL140917B (ja) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS523003U (ja) * | 1975-06-23 | 1977-01-10 | ||
US4419030A (en) * | 1981-09-14 | 1983-12-06 | Burkemper Methods, Inc. | Apparatus for and method of constructing a sheet piling shoring structure |
US5213166A (en) * | 1989-12-12 | 1993-05-25 | Mitsui-Cyanamid, Ltd. | Pile driving and pile removing method |
US5938375A (en) * | 1997-12-17 | 1999-08-17 | Sevonson Environmental Services, Inc. | Method of sealing joints between adjacent sheet piling sections to form a continuous barrier and barriers formed using said method |
US20050179160A1 (en) * | 2004-02-12 | 2005-08-18 | Jeff Moreau | Method for increasing the surface friction of sheet piling segments |
EP1813727A2 (en) * | 2006-01-25 | 2007-08-01 | Van de Coterlet, Jan | Method for producing a sheet pile wall and sheet pile plank therefor |
US11136738B2 (en) | 2019-03-29 | 2021-10-05 | The Trout Group, Inc. | Structural sheet spur |
Families Citing this family (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3201601A1 (de) * | 1982-01-20 | 1983-07-28 | Günther 2000 Hamburg Spranger | Verfahren zum einbringen von spundwaenden o.dgl. in erdreich durch spuelung sowie bauelement zur durchfuehrung des verfahrens. |
DE3246093C1 (de) * | 1982-12-13 | 1984-06-14 | Josef 5138 Heinsberg Krings | Verbauplatte |
GB8707116D0 (en) * | 1987-03-25 | 1987-04-29 | Serf Ltd | Sheet piling |
DE3815236A1 (de) * | 1988-05-05 | 1989-11-23 | Hoesch Stahl Ag | Verfahren zur verriegelung von spundwandschloessern |
NL8801592A (nl) * | 1988-06-22 | 1990-01-16 | Tijmen Van Halteren | Werkwijze voor het aanbrengen van een damwand, alsmede daarbij te gebruiken hulpprofiel. |
GB8904845D0 (en) * | 1989-03-03 | 1989-04-12 | Vales Enoch S | In-ground barrier |
GB2228760B (en) * | 1989-03-03 | 1993-04-07 | Univ Waterloo | In-ground barrier |
US5782583A (en) * | 1989-03-03 | 1998-07-21 | University Of Waterloo | In-ground barrier |
FR2663351B1 (fr) * | 1990-06-13 | 1992-09-18 | Unimetall Sa | Procede d'etanchement des liaisons entre palplanches, et palplanches permettant sa mise en óoeuvre. |
DE19846758A1 (de) * | 1998-10-10 | 2000-04-13 | Rudolf Braun | Abdichtvorrichtung für Spundwandschlösser |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3302412A (en) * | 1964-06-29 | 1967-02-07 | William A Hunsucker | Interlocking sheet piles and method of installation |
-
1969
- 1969-11-22 NL NL696917636A patent/NL140917B/xx not_active IP Right Cessation
-
1970
- 1970-11-18 US US90617A patent/US3688509A/en not_active Expired - Lifetime
- 1970-11-20 FR FR7041865A patent/FR2069811A5/fr not_active Expired
- 1970-11-21 JP JP45103195A patent/JPS5234845B1/ja active Pending
- 1970-11-23 DE DE2057548A patent/DE2057548B2/de active Pending
- 1970-11-23 GB GB1301320D patent/GB1301320A/en not_active Expired
-
1973
- 1973-12-30 MY MY397/73A patent/MY7300397A/xx unknown
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3302412A (en) * | 1964-06-29 | 1967-02-07 | William A Hunsucker | Interlocking sheet piles and method of installation |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS523003U (ja) * | 1975-06-23 | 1977-01-10 | ||
JPS5623403Y2 (ja) * | 1975-06-23 | 1981-06-02 | ||
US4419030A (en) * | 1981-09-14 | 1983-12-06 | Burkemper Methods, Inc. | Apparatus for and method of constructing a sheet piling shoring structure |
US5213166A (en) * | 1989-12-12 | 1993-05-25 | Mitsui-Cyanamid, Ltd. | Pile driving and pile removing method |
US5938375A (en) * | 1997-12-17 | 1999-08-17 | Sevonson Environmental Services, Inc. | Method of sealing joints between adjacent sheet piling sections to form a continuous barrier and barriers formed using said method |
US20050179160A1 (en) * | 2004-02-12 | 2005-08-18 | Jeff Moreau | Method for increasing the surface friction of sheet piling segments |
EP1813727A2 (en) * | 2006-01-25 | 2007-08-01 | Van de Coterlet, Jan | Method for producing a sheet pile wall and sheet pile plank therefor |
US20070183851A1 (en) * | 2006-01-25 | 2007-08-09 | Van De Coterlet Johannes G | Method for producing a sheet pile wall and sheet pile plank therefor |
EP1813727A3 (en) * | 2006-01-25 | 2012-02-22 | Sterk Midden Nederland B.V. | Method for producing a sheet pile wall and sheet pile plank therefor |
US8235630B2 (en) * | 2006-01-25 | 2012-08-07 | Johannes Gerardus Van De Coterlet | Method for producing a sheet pile wall and sheet pile plank therefor |
US11136738B2 (en) | 2019-03-29 | 2021-10-05 | The Trout Group, Inc. | Structural sheet spur |
Also Published As
Publication number | Publication date |
---|---|
JPS5234845B1 (ja) | 1977-09-06 |
FR2069811A5 (ja) | 1971-09-03 |
GB1301320A (ja) | 1972-12-29 |
DE2057548B2 (de) | 1974-08-01 |
MY7300397A (en) | 1973-12-31 |
NL140917B (nl) | 1974-01-15 |
DE2057548A1 (de) | 1971-06-09 |
NL6917636A (ja) | 1971-05-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US3688509A (en) | Method of assembling a sheet piling in the earth from sheet pile sections; as well as a sheet pile section suitable for application in this method | |
EP0022844B1 (en) | Method for the formation of a soil and water-retaining wall, soil and water-retaining wall formed in accordance with this method and forming mould for the formation of this soil and water-retaining wall | |
US4904124A (en) | Constructional work and method of construction of vertical retaining wall | |
US10676890B2 (en) | Retaining wall system, method of supporting same, and kit for use in constructing same | |
US4938634A (en) | Process for lowering basement | |
CA1292755C (en) | Method and apparatus for making a slurry trench or wall in the soil | |
JP4169154B2 (ja) | 基礎の施工法 | |
US4543015A (en) | Pile having wedge former | |
DE4125576A1 (de) | Verfahren zum einpressen von pulver in weichem boden | |
US3152450A (en) | Sheet pile | |
US4349298A (en) | Wedge-forming pile | |
EP1322820B1 (en) | Metal sheet piling | |
JPH04146329A (ja) | L形擁壁ブロック及びl形擁壁の構築方法 | |
JPS61134425A (ja) | 基礎杭の造成工法 | |
CN208363149U (zh) | 一种静载试验地基处理装置 | |
JPH0813405A (ja) | 道路の拡幅構造 | |
EP0026782B1 (en) | Soil and water-retaining wall, composed of prefabricated plate elements | |
GB1318853A (en) | Method of constructing a tunnel | |
JPS6141686Y2 (ja) | ||
JPH0368965B2 (ja) | ||
JP3306372B2 (ja) | L型擁壁の構築方法 | |
JPH02248528A (ja) | 地下室構造 | |
RU2018567C1 (ru) | Способ возведения фундамента | |
US3838781A (en) | Storage tank for garbage | |
KR100263660B1 (ko) | 지반 보강용 유공 보강재 |