US20150367917A1 - Production Support and Storage Vessel - Google Patents

Production Support and Storage Vessel Download PDF

Info

Publication number
US20150367917A1
US20150367917A1 US14/651,217 US201314651217A US2015367917A1 US 20150367917 A1 US20150367917 A1 US 20150367917A1 US 201314651217 A US201314651217 A US 201314651217A US 2015367917 A1 US2015367917 A1 US 2015367917A1
Authority
US
United States
Prior art keywords
vessel
seafloor
production support
bulk storage
storage silos
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Abandoned
Application number
US14/651,217
Other languages
English (en)
Inventor
Daal Hallam Jaffers
Michael Howitt
Roland Berndt
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nautilus Minerals Pacific Pty Ltd
Original Assignee
Nautilus Minerals Pacific Pty Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Priority claimed from AU2012905437A external-priority patent/AU2012905437A0/en
Application filed by Nautilus Minerals Pacific Pty Ltd filed Critical Nautilus Minerals Pacific Pty Ltd
Publication of US20150367917A1 publication Critical patent/US20150367917A1/en
Abandoned legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/30Arrangement of ship-based loading or unloading equipment for transfer at sea between ships or between ships and off-shore structures
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B25/00Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby
    • B63B25/02Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods
    • B63B25/04Load-accommodating arrangements, e.g. stowing, trimming; Vessels characterised thereby for bulk goods solid
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/10Arrangement of ship-based loading or unloading equipment for cargo or passengers of cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/22Arrangement of ship-based loading or unloading equipment for cargo or passengers of conveyers, e.g. of endless-belt or screw-type
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B35/4413Floating drilling platforms, e.g. carrying water-oil separating devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B43/00Improving safety of vessels, e.g. damage control, not otherwise provided for
    • B63B43/02Improving safety of vessels, e.g. damage control, not otherwise provided for reducing risk of capsizing or sinking
    • B63B43/04Improving safety of vessels, e.g. damage control, not otherwise provided for reducing risk of capsizing or sinking by improving stability
    • B63B43/06Improving safety of vessels, e.g. damage control, not otherwise provided for reducing risk of capsizing or sinking by improving stability using ballast tanks
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/8833Floating installations
    • E02F3/885Floating installations self propelled, e.g. ship
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/8858Submerged units
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/8858Submerged units
    • E02F3/8866Submerged units self propelled
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F3/00Dredgers; Soil-shifting machines
    • E02F3/04Dredgers; Soil-shifting machines mechanically-driven
    • E02F3/88Dredgers; Soil-shifting machines mechanically-driven with arrangements acting by a sucking or forcing effect, e.g. suction dredgers
    • E02F3/90Component parts, e.g. arrangement or adaptation of pumps
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/005Equipment for conveying or separating excavated material conveying material from the underwater bottom
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/02Conveying equipment mounted on a dredger
    • E02F7/023Conveying equipment mounted on a dredger mounted on a floating dredger
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/04Loading devices mounted on a dredger or an excavator hopper dredgers, also equipment for unloading the hopper
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F7/00Equipment for conveying or separating excavated material
    • E02F7/06Delivery chutes or screening plants or mixing plants mounted on dredgers or excavators
    • E02F7/065Delivery chutes or screening plants or mixing plants mounted on dredgers or excavators mounted on a floating dredger
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02FDREDGING; SOIL-SHIFTING
    • E02F9/00Component parts of dredgers or soil-shifting machines, not restricted to one of the kinds covered by groups E02F3/00 - E02F7/00
    • E02F9/06Floating substructures as supports
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21CMINING OR QUARRYING
    • E21C50/00Obtaining minerals from underwater, not otherwise provided for
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B3/00Hulls characterised by their structure or component parts
    • B63B3/14Hull parts
    • B63B2003/147Moon-pools, e.g. for offshore drilling vessels
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B27/00Arrangement of ship-based loading or unloading equipment for cargo or passengers
    • B63B27/16Arrangement of ship-based loading or unloading equipment for cargo or passengers of lifts or hoists
    • B63B2027/165Deployment or recovery of underwater vehicles using lifts or hoists
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B35/00Vessels or similar floating structures specially adapted for specific purposes and not otherwise provided for
    • B63B35/44Floating buildings, stores, drilling platforms, or workshops, e.g. carrying water-oil separating devices
    • B63B2035/4486Floating storage vessels, other than vessels for hydrocarbon production and storage, e.g. for liquid cargo
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63BSHIPS OR OTHER WATERBORNE VESSELS; EQUIPMENT FOR SHIPPING 
    • B63B2207/00Buoyancy or ballast means
    • B63B2207/02Variable ballast or buoyancy
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B63SHIPS OR OTHER WATERBORNE VESSELS; RELATED EQUIPMENT
    • B63HMARINE PROPULSION OR STEERING
    • B63H25/00Steering; Slowing-down otherwise than by use of propulsive elements; Dynamic anchoring, i.e. positioning vessels by means of main or auxiliary propulsive elements
    • B63H25/42Steering or dynamic anchoring by propulsive elements; Steering or dynamic anchoring by propellers used therefor only; Steering or dynamic anchoring by rudders carrying propellers
    • B63H2025/425Propulsive elements, other than jets, substantially used for steering or dynamic anchoring only, with means for retracting, or otherwise moving to a rest position outside the water flow around the hull

Definitions

  • the transport vessel then transports the material to a storage vessel that includes bulk storage for the gathered seafloor material.
  • a storage vessel that includes bulk storage for the gathered seafloor material.
  • the transport vessel can transport the material directly to a land based storage facility. Either way, typically two or three transport vessels need to be employed, more for longer distances, to provide sufficient capacity to transport the gathered seafloor material from the support vessel to the storage vessel or facility. Once sufficient ore has been stored it is loaded onto export vessels that take the ore to market.
  • the logistics in receiving and transporting the seafloor material therefore requires a significant fleet of vessels. This increases the cost and complexity of transporting gathered seafloor material from the source to market. Furthermore, many mooring operations between the vessels are required, in some cases more than 500 per year. Each mooring operation has a chance of a vessel collision and damage to equipment.
  • a production support vessel for use on a body of water, the production support vessel comprising:
  • seafloor material receiver that receives seafloor material from below the surface of the body of water
  • seafloor material processor that processes seafloor material from the seafloor material receiver
  • one or more bulk storage silos that store processed seafloor material from the seafloor material processor
  • an unloading system configured to offload processed seafloor material from the bulk storage silos to a transport vessel moored alongside the production support vessel.
  • the bulk storage silos occupy a significant portion, preferably a majority portion, of an internal space defined by a hull of the production support vessel.
  • the one or more bulk storage silos preferably have a combined capacity of more than one week's worth of production, preferably more than 20,000 t of ore, even more preferably more than 30,000 t of ore, still more preferably more than 40,000 t of ore.
  • four bulk storage silos are provided having a combined capacity of between 40,000 t and 50,000 t, preferably around 45,000 t.
  • the four bulk storage silos are preferably arranged in two pairs of adjacent bulk storage silos.
  • One pair of adjacent bulk storage silos is preferably located toward the aft and another pair of adjacent bulk storage silos is preferably located toward the bow.
  • the bulk storage silos are preferably aligned along a longitudinal axis of the vessel.
  • the loading system preferably distributes seafloor material, preferably ore, from the seafloor material processor to the one or more bulk storage silos.
  • the loading system comprises one or more loading conveyors, preferably including one or more scraper or chain conveyors, to distribute the ore to the bulk storage silos.
  • a single loading system is capable of distributing the ore to any of the bulk storage silos.
  • the loading system also has the ability to bypass the storage silos and deliver ore directly to the transport vessel moored alongside the production support vessel.
  • the loading conveyors include longitudinal and transverse conveyors to distribute the ore to the bulk storage silos.
  • the ore is distributed evenly in each bulk storage silo to maximise volume stored and to provide for ship loading ballast and stability considerations.
  • the unloading conveyor system includes at least mechanical grab which delivers ore to a hopper that feeds a vertical lifter system.
  • the unloading conveyor system also preferably includes a vertical lifter, preferably a C-conveyor, that receives material from the grab and hopper and a boom conveyor that receives material from the vertical lifter.
  • the boom conveyor is preferably configured to offload the material, typically to a transportation vessel.
  • the seafloor material receiver preferably includes at least a portion of a riser and the seafloor material processor preferably includes a dewatering plant.
  • the seafloor material processor may comprise a lime storage and dosing system.
  • the production support vessel preferably further comprises at least one crane.
  • the production support vessel includes two cranes, a forward crane and an aft crane, that are preferably located on the same side of the vessel.
  • the vessel preferably further comprises one or more vehicle bays configured to store seafloor vehicles.
  • the seafloor vehicles are preferably seafloor mining vehicles that are unloaded and loaded from the vessel via the vehicle bays.
  • a lift winch and/or hydraulic power unit (HPU) are preferably provided for unloading and loading each seafloor mining vehicle.
  • a vehicle bay may be provided for a seafloor stockpiling bulk cutter, a seafloor auxiliary cutter, and/or a seafloor collecting machine.
  • a vehicle bay and corresponding winch and HPU are provided for each of a seafloor stockpiling bulk cutter, a seafloor auxiliary cutter, and a seafloor collecting machine.
  • the vessel preferably further comprises a moon pool that extends vertically through at least a portion of the vessel.
  • the moon pool is preferably an open moon pool that is located in a central portion of the vessel, preferably along a centreline of the vessel.
  • the moon pool is preferably substantially square or rectangular. In a preferred form, the moon pool is a 10 m ⁇ 10 m square.
  • a derrick is preferably located adjacent the moon pool. In a preferred form, the derrick is located directly above the moon pool.
  • the vessel has a length between perpendiculars (BP) of between 150 and 250 m, preferably between 180 and 230 m, even more preferably between 200 and 220 m, most preferably around 210 m.
  • BP perpendiculars
  • the vessel has a breadth of between 20 and 60 m, preferably between 30 and 50 m, even more preferably between 35 and 45 m, and most preferably around 40 m.
  • a method of processing material gathered from the seafloor comprising the steps of:
  • the step of storing processed seafloor material on the vessel preferably includes storing at least one full day's worth of production, more preferably at least three day's worth of production, and even more preferably at least five day's worth of production.
  • the step of storing processed seafloor material on the vessel includes storing at least one week's worth of production which is, preferably, approximately 45,000 t of processed seafloor material.
  • the method may further comprise the step of transporting the seafloor mining vehicles on the vessel, and lowering the one or more seafloor mining vehicles from the vessel to the seafloor.
  • the method may also further comprise retrieving one or more seafloor mining vehicles from the seafloor and placing them on the vessel.
  • the seafloor is greater than 500 m below sea level, even more preferably greater than 1,000 m below sea level, even more preferably greater than 2,000 m below sea level, and the steps of lower and retrieving the seafloor mining vehicles comprises lowering and retrieving the vehicles over a distance of at least 500 m, more preferably over a distance of at least 1,000 m, even more preferably over a distance of at least 2,000 m.
  • the step of conveying stored seafloor material from the one or more bulk storage silos to a transport vessel includes conveying the stored seafloor material to the transport vessel whilst at sea.
  • the seafloor material is conveyed using one or more scoopers, one or more bucket elevators or C-conveyors, and one or more boom conveyors.
  • the step of conveying stored seafloor material preferably comprises retrieving the stored seafloor material from the one or more bulk storage silos using a scooper and placing it in a bucket elevator which transfers the seafloor material to a boom conveyor which offloads the material to the transport vessel.
  • FIG. 1 is a partially transparent side elevation view of a production support vessel according to an aspect of the invention
  • FIG. 2 is a plan view of the production support vessel illustrated in FIG. 1 ;
  • FIG. 3 is a plan view of the production support vessel illustrated in FIG. 1 with a transport vessel moored thereto;
  • FIG. 4 is a plan view showing the deck of the production support vessel illustrated in FIG. 1 ;
  • FIG. 5 is a cross sectional view of the production support vessel illustrated in FIG. 1 ;
  • FIG. 6 is a flowchart of an overview of a method according to an aspect of the invention.
  • FIGS. 1 to 5 illustrate a production support vessel 100 having a hull 110 which supports a mining and processing equipment portion 120 and an administration and accommodation portion 180 .
  • the vessel 100 has a seafloor material receiver in the form of a riser 200 that is connected to seafloor mining equipment (not shown), which typically operates at depths of 1,000-2,500+ metres below sea level, during seafloor mining operations.
  • the mining and processing equipment portion 120 of the production support vessel 100 has three vehicle bays for storing seafloor mining vehicles used in the seafloor mining operations, including a stockpiling bulk cutter (SBC) vehicle bay 126 , an auxiliary cotter (AC) vehicle bay 128 , and a collecting machine (CM) vehicle bay 130 that house an SBC 126 ′, AC 128 ′, and CM 130 ′.
  • SBC stockpiling bulk cutter
  • AC auxiliary cotter
  • CM collecting machine
  • Adjacent the SBC vehicle bay 126 is an SBC lift winch 132 and SBC hydraulic power unit 134 ; adjacent the AC vehicle bay 128 is an AC lift winch 136 and AC hydraulic power unit 138 ; and adjacent the CM vehicle bay 130 is a CM lift winch 140 and CM hydraulic power unit 142 .
  • the lift winches 132 , 136 , and 140 and hydraulic power units 134 , 138 , and 142 may be utilised in the loading and unloading of the SBC 126 ′, AC 128 ′, and CM 130 ′ vehicles from the vessel 100 .
  • a derrick 144 is provided that extends vertically above a 10 m square moon pool 146 that, as shown in FIG. 1 , extends vertically through the hull 110 of the vessel 100 .
  • the riser 200 passes through the moon pool 146 to equipment located at or near the seafloor during seafloor mining operations.
  • the moon pool 146 is located generally centrally on the vessel 100 , being centred with respect to the vessel's centreline 10 . Adjacent the moon pool 146 is a derrick substructure 144 ′.
  • the production support vessel 100 has a loading system that includes loading conveyors 150 , which preferably include transverse chain conveyors, that distribute processed ore from the dewatering plant 300 to the bulk storage silos 400 , 420 , 440 , and 460 .
  • the loading conveyors 150 are able to selectively distribute processed ore to any one of the bulk storage silos 400 , 420 , 440 , and 460 .
  • the production support vessel 100 has an unloading system that includes two unloading conveyor systems that each retrieve ore from adjacent pairs of bulk storage silos 400 , 420 , 440 , and 460 .
  • An aft unloading conveyor system comprises a longitudinal scooper 402 and a transverse scooper (not shown) located in bulk storage silo 400 , a longitudinal scooper 422 and transverse scooper (not shown) located in bulk storage silo 420 , a vertical lifter in the form of a bucket elevator 430 located between the aft pair of bulk storage silos 400 and 420 , and a boom conveyor 432 .
  • a forward unloading conveyor system is similar to the aft unloading conveyor system, and comprises a longitudinal scooper 442 and a transverse scooper (not shown) located in bulk storage silo 440 , a longitudinal scooper 462 and transverse scooper (not shown) located in bulk storage silo 460 , a vertical lifter in the form of a bucket elevator 450 located between the forward pair of bulk storage silos 440 and 460 , and a boom conveyor 452 .
  • the boom conveyors 432 and 452 have respective offload ranges 432 ′ and 452 ′ as illustrated in FIGS. 2 and 3 .
  • a transport vessel 50 is shown moored to the production support vessel 100 .
  • the transport vessel 50 has a plurality of cargo holds 52 that are each at least partially covered by the offload ranges 432 ′ and 452 ′ of the boom conveyers 432 and 452 .
  • the transport vessel 50 has a total carrying capacity of approximately 30,000 t DWT.
  • the boom conveyors 432 and 452 have the ability to lift and lower an earth moving machine (not shown) into and out of the cargo holds 52 of vessel 50 .
  • the earth moving machine is capable of levelling the material delivered to the cargo holds 52 of vessel 50 . This levelling ensures safe shipment of the processed material in the holds 52 .
  • the earth moving machine (not shown) is stored on the deck of the vessel 100 .
  • the production support vessel 100 has a length between perpendiculars (BP) of approximately 210 m, a length overall (OA) of approximately 227 m, and a breadth of approximately 40 m.
  • BP perpendiculars
  • OA length overall
  • the dimensions of the production support vessel 100 have been very carefully selected, and the layout of components carefully designed, to provide a single vessel 100 that caters for all surface support aspects of seafloor mining operations.
  • the production support vessel travels to a desired location carrying the SBC 126 ′, AC 128 ′, and CM 130 ′ vehicles.
  • the vehicles are lowered to the seafloor where they commence seafloor mining operations where they gather seafloor material (step 1000 of FIG. 6 ). Gathered seafloor material is transferred from the seafloor, typically over 1,000 m below sea level, to the production support vessel 100 (step 1100 of FIG. 6 ) via riser 200 where it is processed (step 1200 of FIG. 6 ) by dewatering plant 300 and distributed to bulk storage silos 400 , 420 , 440 , and 460 (step 1300 of FIG. 6 ).
  • the processed seafloor material is then stored in the bulk storage silos 400 , 420 , 440 , and 460 (step 1400 of FIG. 6 ) and then subsequently conveyed from the bulk storage silos 400 , 420 , 440 , and 460 to the transport vessel 50 (step 1500 of FIG. 6 ).
  • the capacity of the bulk storage silos 400 , 420 , 440 , and 460 is relatively high, ore is transferred to, and stored in, the bulk storage silos 400 , 420 , 440 , and 460 for approximately a week before it is unloaded to the transport vessel 50 .
  • the scoopers 402 , 422 , 442 , and 462 scrape ore from the top of the stored ore in the bulk storage silos 400 , 420 , 440 , and 460 and convey the ore to the bucket elevators 430 and 450 .
  • the bucket elevators 430 and 450 then convey the ore to the boom conveyors 432 and 452 which then offload the ore to the cargo holds 52 of the transport vessel 50 .
  • the transport vessel 50 then transports the ore to a designated location, e.g. to market, and the production support vessel 100 continues receiving, processing, and storing ore from the seafloor mining operations.
  • the production support vessel 100 can transport and undertake all aspects of seafloor mining operations including transporting and deploying the seafloor mining vehicles, SBC 126 ′, AC 128 ′, and CM 130 ′, receiving and processing gathered seafloor material, and providing bulk storage for the processed seafloor material to allow relatively large transport vessels 50 to subsequently receive the seafloor material and take it directly to market, or the like, without having to accumulate the materials at a further storage location such as a silo ship or on land.
  • the reduced number of mooring operations compared to a traditional production support vessel significantly increases efficiency while also reducing the risk of collision, personal injury, or environmental contamination occurring. In general, there is also increased safety and efficiency due to less personnel transfers, perishable transfers, and bunkering operations.
  • the large ballast of the production support vessel 100 reduces the impact between launch and recovery of mining equipment and vessel mooring operations, particularly when offloading significant quantities of stored material to the transport vessel 50 .
  • the ballast also allows the vessel 100 to adjust its draft or trim and/or heel to suit operations being performed by or in conjunction with the vessel 100 .
  • the safety is increased as mooring and lifting operations are simplified and there is a reduced risk of accident due to changes in relative freeboard between the two vessels.
  • the production support vessel 100 has a relatively large mass, which can be kept high with the large ballast capacity, the vessel 100 is more stable and has reduced motions and as a result the dynamic positioning system requires less fuel consumption to keep the vessel 100 in location.
  • the increased mass advantageously reduces motion of the vessel which improves crew comfort and safety.
  • the described loading and unloading system is preferred as it minimises space occupied by the loading and unloading equipment enabling the volume for storage of ore to be maximised.
  • seafloor seabed, subsea, or the like are for convenience only and could equally be applied to other bodies of water such as, for example, a lake with a lakebed, etc.
  • adjectives such as first and second, left and right, top and bottom, and the like may be used solely to distinguish one element or action from another element or action without necessarily requiring or implying any actual such relationship or order.
  • reference to an integer or a component or step (or the like) is not to be interpreted as being limited to only one of that integer, component, or step, but rather could be one or more of that integer, component, or step etc.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Mechanical Engineering (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Ship Loading And Unloading (AREA)
  • Warehouses Or Storage Devices (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
US14/651,217 2012-12-11 2013-11-28 Production Support and Storage Vessel Abandoned US20150367917A1 (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
AU2012905437 2012-12-11
AU2012905437A AU2012905437A0 (en) 2012-12-11 Production support and storage vessel
PCT/AU2013/001380 WO2014089599A1 (en) 2012-12-11 2013-11-28 Production support and storage vessel

Publications (1)

Publication Number Publication Date
US20150367917A1 true US20150367917A1 (en) 2015-12-24

Family

ID=50933563

Family Applications (1)

Application Number Title Priority Date Filing Date
US14/651,217 Abandoned US20150367917A1 (en) 2012-12-11 2013-11-28 Production Support and Storage Vessel

Country Status (7)

Country Link
US (1) US20150367917A1 (zh)
EP (1) EP2931594A4 (zh)
JP (2) JP6455842B2 (zh)
KR (1) KR102214432B1 (zh)
CN (1) CN104870305B (zh)
AU (1) AU2013359998A1 (zh)
WO (1) WO2014089599A1 (zh)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105539753B (zh) * 2016-01-19 2018-06-12 吴淑真 海洋江河可移动隐形消防自救燃油储存库加油平台
CN106379496B (zh) * 2016-11-02 2019-09-03 湖北海洋工程装备研究院有限公司 一种供应船母船
CN110159268A (zh) * 2017-12-28 2019-08-23 武汉船舶设计研究院有限公司 一种深海采矿输送硬管夹持摇摆装置
CN109372047B (zh) * 2018-10-29 2023-11-07 中交天津航道局有限公司 一种适用于绞吸式挖泥船的三缆定位系统
CN109973096B (zh) * 2019-04-19 2023-12-22 中国海洋大学 一种深海多金属结核矿采矿作业系统

Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3140686A (en) * 1960-04-11 1964-07-14 Olivotti Elia Hull of special stabilized shape
US3191998A (en) * 1963-04-29 1965-06-29 Huron Portland Cement Company Dual cargo ship
US3387721A (en) * 1966-02-04 1968-06-11 Mcdowell Wellman Eng Co Bucket chain conveyor
US4054104A (en) * 1975-08-06 1977-10-18 Haselton Frederick R Submarine well drilling and geological exploration station
US4347798A (en) * 1978-06-01 1982-09-07 Gallagher John J Buffer system for tankvessels
US4422400A (en) * 1981-06-08 1983-12-27 Gibeshemael Incorporation Marine system for unloading and loading bulk product
US4795298A (en) * 1986-11-24 1989-01-03 Nelson Arthur J Marine transportation of bulk cargo
US5564878A (en) * 1994-11-04 1996-10-15 Texmarc Conveyor Company Apparatus and method for continuous handling of bulk materials
US20040065474A1 (en) * 2002-10-04 2004-04-08 Halliburton Energy Services, Inc. Methods and apparatus for open hole drilling
US20070095427A1 (en) * 2004-10-15 2007-05-03 Ehrhardt Mark E Subsea cryogenic fluid transfer system
US20080083435A1 (en) * 2006-10-06 2008-04-10 Myers Craig W Method of inhibiting corrosion in storage and transport vessels
US20080267716A1 (en) * 2007-04-30 2008-10-30 D Souza Richard Shallow/intermediate water multipurpose floating platform for arctic environments
US20080295526A1 (en) * 2007-05-29 2008-12-04 Boatman L Terry Floating lng regasification facility with lng storage vessel
US20120217019A1 (en) * 2011-02-24 2012-08-30 Foro Energy, Inc. Shear laser module and method of retrofitting and use
US20130042798A1 (en) * 2011-06-22 2013-02-21 Magnuss Ltd Vertically-Variable Ocean Sail System
US20130283825A1 (en) * 2010-11-30 2013-10-31 Adam Bernays Floating lng plant
US20130312296A1 (en) * 2010-06-18 2013-11-28 Glen Robert Jones System For Seafloor Mining

Family Cites Families (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3522670A (en) * 1967-07-11 1970-08-04 Newport News S & D Co Apparatus for underwater mining
US4010560A (en) * 1975-05-14 1977-03-08 Diggs Richard E Deep sea mining apparatus and method
JPS521882A (en) * 1975-06-24 1977-01-08 Nippon Kokan Kk <Nkk> Ship installed loading eqipment
JPS629196Y2 (zh) * 1981-03-03 1987-03-03
JPS63251390A (ja) * 1987-04-08 1988-10-18 Mitsubishi Heavy Ind Ltd ばら積貨物払出し装置
NO174615C (no) * 1990-10-05 1994-06-08 Norsk Hydro As Losseutstyr.
GB9103622D0 (en) * 1991-02-21 1991-04-10 Ugland Eng Unprocessed petroleum gas transport
US5364218A (en) * 1993-06-16 1994-11-15 Skarhar, Inc. Bulk material conveyor unloading system for ships
US5950732A (en) * 1997-04-02 1999-09-14 Syntroleum Corporation System and method for hydrate recovery
AU689419B3 (en) * 1997-06-16 1998-03-26 Ralph Downham Stabilising method
JPH11349146A (ja) * 1998-06-08 1999-12-21 Aoishin Kensetsu Kk 粉粒体の荷揚げ保管供給処理システム及び粉粒体の荷揚げ保管供給処理装置
KR20080111463A (ko) * 2006-03-15 2008-12-23 우드사이드 에너지 리미티드 Lng의 선상 재기화
JP2009280960A (ja) * 2008-05-19 2009-12-03 Tokai Univ 揚水機構および水底資源回収装置
GB2462801B (en) * 2008-07-02 2012-09-26 Marine Resources Exploration Internat Bv A method of mining and processing seabed sediment
EP2184407A1 (en) * 2008-11-06 2010-05-12 Spauwer Dredging BV Suction Dredger
AU2011267843B2 (en) * 2010-06-18 2016-05-19 Eda Kopa (Solwara) Limited Method and apparatus for bulk seafloor mining

Patent Citations (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3140686A (en) * 1960-04-11 1964-07-14 Olivotti Elia Hull of special stabilized shape
US3191998A (en) * 1963-04-29 1965-06-29 Huron Portland Cement Company Dual cargo ship
US3387721A (en) * 1966-02-04 1968-06-11 Mcdowell Wellman Eng Co Bucket chain conveyor
US4054104A (en) * 1975-08-06 1977-10-18 Haselton Frederick R Submarine well drilling and geological exploration station
US4347798A (en) * 1978-06-01 1982-09-07 Gallagher John J Buffer system for tankvessels
US4422400A (en) * 1981-06-08 1983-12-27 Gibeshemael Incorporation Marine system for unloading and loading bulk product
US4795298A (en) * 1986-11-24 1989-01-03 Nelson Arthur J Marine transportation of bulk cargo
US5564878A (en) * 1994-11-04 1996-10-15 Texmarc Conveyor Company Apparatus and method for continuous handling of bulk materials
US20040065474A1 (en) * 2002-10-04 2004-04-08 Halliburton Energy Services, Inc. Methods and apparatus for open hole drilling
US20070095427A1 (en) * 2004-10-15 2007-05-03 Ehrhardt Mark E Subsea cryogenic fluid transfer system
US20080083435A1 (en) * 2006-10-06 2008-04-10 Myers Craig W Method of inhibiting corrosion in storage and transport vessels
US20080267716A1 (en) * 2007-04-30 2008-10-30 D Souza Richard Shallow/intermediate water multipurpose floating platform for arctic environments
US20080295526A1 (en) * 2007-05-29 2008-12-04 Boatman L Terry Floating lng regasification facility with lng storage vessel
US20130312296A1 (en) * 2010-06-18 2013-11-28 Glen Robert Jones System For Seafloor Mining
US20130283825A1 (en) * 2010-11-30 2013-10-31 Adam Bernays Floating lng plant
US20120217019A1 (en) * 2011-02-24 2012-08-30 Foro Energy, Inc. Shear laser module and method of retrofitting and use
US20130042798A1 (en) * 2011-06-22 2013-02-21 Magnuss Ltd Vertically-Variable Ocean Sail System

Also Published As

Publication number Publication date
EP2931594A1 (en) 2015-10-21
KR102214432B1 (ko) 2021-02-09
CN104870305A (zh) 2015-08-26
AU2013359998A1 (en) 2015-05-28
JP6455842B2 (ja) 2019-01-23
WO2014089599A1 (en) 2014-06-19
JP2016501772A (ja) 2016-01-21
EP2931594A4 (en) 2016-08-10
JP2019034739A (ja) 2019-03-07
CN104870305B (zh) 2017-11-10
KR20150086282A (ko) 2015-07-27

Similar Documents

Publication Publication Date Title
US20150367917A1 (en) Production Support and Storage Vessel
RU2384510C2 (ru) Способ и система для перегрузки груза
US8858149B2 (en) Remote docking port
EP2252502A2 (en) Offshore pipe and riser handling drilling vessel
JP2016501772A5 (ja) 産出物支援貯蔵船および海底から採集される物質の処理方法
US20020071743A1 (en) Container cargo transfer system
US4483655A (en) Vessel loading method
CN103787096A (zh) 船舶大舱货物装卸装置
EP2377801B1 (en) Method of serving a complex including two and more mobile wharf boom cranes
AU2016363678A1 (en) Super shallow draft bulk carrier
US9499239B2 (en) Integrated heavy lift and logistics vessel
US6863484B2 (en) Catamaran transfer vessel
WO1993004914A1 (en) Jumbo barge carrier fast sealift and port system
CN104291128B (zh) 集装船、卸船、运输于一体的多功能船
KR101652695B1 (ko) 바지선을 이용한 벌크 화물 선적 시스템
KR20110081662A (ko) 컨테이너 하역 시스템 및 방법
CN202193464U (zh) 浮式趸船散货装船系统
KR101725138B1 (ko) 벌크 화물 선적 시스템에 이용되는 선적용 바지선
CN203820093U (zh) 船舶大舱货物装卸装置
KR20140056837A (ko) 채광선박, 그 채광선박의 다중 분리형 화물창 적재시스템 및 채광선박의 다중 분리형 화물창 적재방법
KR101621238B1 (ko) 바지선을 이용한 벌크 화물 선적방법
AU2011245072C1 (en) Handling of bulk cargo
Reeves Effective Solutions for the JLOTS Sea State 3 Problem: Use of Commercial Offshore Cargo Handling Technology
KR20160052818A (ko) 벌크 화물 선적용 바지선의 컨베이어벨트 슈트장치
JPS59220486A (ja) 巾広大型バルクキヤリア

Legal Events

Date Code Title Description
STCB Information on status: application discontinuation

Free format text: ABANDONED -- FAILURE TO RESPOND TO AN OFFICE ACTION