JPS621954A - Construction of housing of building - Google Patents

Construction of housing of building

Info

Publication number
JPS621954A
JPS621954A JP14136685A JP14136685A JPS621954A JP S621954 A JPS621954 A JP S621954A JP 14136685 A JP14136685 A JP 14136685A JP 14136685 A JP14136685 A JP 14136685A JP S621954 A JPS621954 A JP S621954A
Authority
JP
Japan
Prior art keywords
floor
column
temporary
frame
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP14136685A
Other languages
Japanese (ja)
Other versions
JPH0417262B2 (en
Inventor
播 繁
福島 正隆
康 足立
小野 紀一
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP14136685A priority Critical patent/JPS621954A/en
Publication of JPS621954A publication Critical patent/JPS621954A/en
Publication of JPH0417262B2 publication Critical patent/JPH0417262B2/ja
Granted legal-status Critical Current

Links

Landscapes

  • Casings For Electric Apparatus (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。
(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.

Description

【発明の詳細な説明】 (j )           ’J、/11゜〔産業
上の利用分野〕 この発明は建物の架構床部分をコンクリートスラブとし
た建物の架構施工法に関するもので、特に高層建物ある
いは超高層建物の施工に適する。
[Detailed Description of the Invention] (j) 'J, /11゜ [Industrial Application Field] This invention relates to a method of constructing a building frame in which the frame floor portion of the building is a concrete slab, and in particular relates to a method for constructing a building frame in which the frame floor portion of the building is a concrete slab. Suitable for construction of high-rise buildings.

〔従来の技術およびその問題点〕[Conventional technology and its problems]

高層建物、超高層建物等においても、従来の鉄骨主体の
架構に対し、複合柱やアンボンドプレストレストコンク
IJ −)スラブ(以下、アンボンドPCスラブという
)を用いて、経済的な断面を有する建物が設計されてき
ている。
Even in high-rise buildings and super high-rise buildings, buildings with economical cross-sections are designed using composite columns and unbonded prestressed concrete IJ-) slabs (hereinafter referred to as unbonded PC slabs) instead of conventional steel-based frames. It has been done.

しかし、下階より順次構築して行く方法では床コンクリ
ート打設のための型枠の組立、解体。
However, in the method of building sequentially from the lower floors, the formwork for pouring concrete on the floor must be assembled and dismantled.

移動等に手間がかかり、また多くの仮設資料を必要とす
るほか、工数も多いので、作業待ちの時間が長くなる。
It takes time to move, requires a lot of temporary materials, and requires a lot of man-hours, so the waiting time for work becomes long.

また、低層の建物でフラットスラブ構造とする場合は地
上で数階分のスラブを形成し、リフトアップする工法も
知られているが、高層建物に適用するのは困難である。
Furthermore, when constructing a flat slab structure for a low-rise building, a construction method is known in which several floors of slabs are formed on the ground and lifted up, but this method is difficult to apply to high-rise buildings.

この発明は上述のような問題点の解決を目的としたもの
である。
This invention aims to solve the above-mentioned problems.

〔問題点を解決するための手段〕[Means for solving problems]

この発明の工法は床架構5の施工を上階から順次下階へ
向けて行なうものであり、まずセンターコア1の構築を
先行させ、続いてセンタ−コア1外部の柱鉄骨2を所定
高さまで立上げて行く。
The construction method of this invention is to construct the floor frame 5 sequentially from the upper floor to the lower floor. First, the center core 1 is constructed first, and then the column steel frame 2 outside the center core 1 is constructed to a predetermined height. I'll start it up and go.

センターコア1はエレベータ−室ヤ機械室等を集中させ
た部分で、スライディングフオーム工法あるいはジャン
ピングフォーム工法などで壁部分のコンクリート工事を
行なうことができる。また柱鉄骨2については施工中、
仮設の水平ブレース3でセンターコア1と連結するなど
して立上げて行く。
The center core 1 is a part where the elevator room, machine room, etc. are concentrated, and the concrete work of the wall part can be performed using the sliding form method or the jumping form method. Also, pillar steel frame 2 is under construction.
It is connected to the center core 1 using a temporary horizontal brace 3 and then started up.

次に立上げた柱鉄骨2の上部に、センターコア1を取囲
むようにして仮設ステージ4を組立てる。仮設ステージ
4は鉄骨フレーム4aと鉄骨フレーム4a上に設けた型
枠4b等で構成し、センターコア1および柱鉄骨2に泊
ってスライドできるようにする。
Next, a temporary stage 4 is assembled on top of the erected steel column 2 so as to surround the center core 1. The temporary stage 4 is composed of a steel frame 4a, a formwork 4b provided on the steel frame 4a, etc., and is made to be able to slide by resting on the center core 1 and the column steel frame 2.

次に、仮設ステージ4上に必要な配筋工事等を行なった
後、床コンクリートを打設し、順次仮設ステージ4を1
階ずつ下げて下階の床コンクリートを打設して行く。な
お、仮設ステージ4上に形成されるスラブはフラットス
ラブに限らず、染付スラブ等の場合もある。
Next, after performing the necessary reinforcing work on the temporary stage 4, the floor concrete is poured, and the temporary stage 4 is moved to 1.
The building will be lowered one floor at a time and the concrete floor for the lower floors will be poured. Note that the slab formed on the temporary stage 4 is not limited to a flat slab, and may be a dyed slab or the like.

以上により、センターコア1と柱鉄骨2および床架構5
とからなる架構が形成され、また柱を鉄骨鉄筋コンクリ
ート柱等の複合柱とする場合は、続いて柱鉄骨2周囲の
配筋およびコンクリート工事を行なう。
As described above, the center core 1, the column steel frame 2, and the floor frame 5
When a frame is formed, and the columns are composite columns such as steel reinforced concrete columns, reinforcing and concrete work around the column steel frames 2 are then performed.

また、建物の階数が多い場合は、以上の作業を二以上の
高さで分けて行ない、センターコア1の先行構築、柱鉄
骨2の立上げ、仮設ステージ4による上階から下階へ向
けての床架構5の形成といった作業を繰り返すことにな
る。
In addition, if the building has many floors, the above work is divided into two or more heights, and the center core 1 is constructed in advance, the column steel frame 2 is erected, and the temporary stage 4 is used to move from the upper floor to the lower floor. The work of forming the floor frame 5 will be repeated.

〔実 施 例〕〔Example〕

次に、図示した実施例について説明する。 Next, the illustrated embodiment will be described.

第5図は施工時における架構の平面図、第6図は柱およ
び床部分の構造を示す断面斜視図で、センターコア1は
壁部分をスライディングフオームあるいはジャンビング
ツオーム工法で構築し、そのまわりに鉄骨鉄筋コンクリ
ート製の複合柱で支持されるアンボンドPCスラブの床
架構5を形成している。
Figure 5 is a plan view of the frame during construction, and Figure 6 is a cross-sectional perspective view showing the structure of the columns and floor. A floor frame 5 of unbonded PC slabs supported by composite columns made of steel-framed reinforced concrete is formed.

床架構5は床スラブ5a部分と梁5b部分とからなり、
格子状鉄筋による床鉄筋11、懸垂線状のアンボンドP
Cストランド12および梁鉄筋13を配しである。また
柱については柱鉄骨2の周囲に上下刃向の主筋およびせ
ん断補強筋としてフープ筋、スパイラル筋等の柱鉄筋1
0を配し、コンクリート7を打設しである。
The floor frame 5 consists of a floor slab 5a portion and a beam 5b portion,
Floor reinforcing bars 11 made of lattice reinforcing bars, unbonded P in the form of catenary lines
C strand 12 and beam reinforcing bars 13 are arranged. In addition, for columns, column reinforcing bars 1 such as hoop bars, spiral bars, etc. are placed around the column steel frame 2 as main bars in the vertical direction and as shear reinforcing bars.
0 is placed and concrete 7 is poured.

計2図〜第4図は仮設ステージ4の一例を示したもので
、H形鋼等の鉄骨により、鉄骨フレーム4aを組み、そ
の上に型枠4bを設けたものである。柱鉄骨2への固定
は第3図および第4図に示すように、各階位置に取り付
けた接合プレートへのボルト接合によつ℃行なうことが
できる。また、仮設ステージ4の型枠4bには柱位置に
コンクリート打設用の穴8を形成してあり、柱鉄骨2と
鉄筋コンクリ−1・を組合わせまた複合柱を形成できる
ようになっている。
Figures 2 to 4 show an example of the temporary stage 4, in which a steel frame 4a is constructed of steel frames such as H-shaped steel, and a formwork 4b is provided on top of the steel frame 4a. As shown in FIGS. 3 and 4, fixing to the column steel frame 2 can be carried out by bolting to joint plates attached to each floor. In addition, holes 8 for pouring concrete are formed in the formwork 4b of the temporary stage 4 at the column positions, so that the column steel frame 2 and the reinforced concrete 1 can be combined to form a composite column. .

オフ図〜計9図は他の実施例として、仮設ステージ4の
吊降しを柱鉄骨2の頂部に設置したセンターホールジヤ
ツキ14で行なう場合を示したものである。この例では
柱鉄骨2について1本あたり4個のセンターホールジヤ
ツキ14を用意し、ワイヤーロープ15を介して仮設ス
テージ4の仮設フレーム4aを吊支持している。
The off-line diagrams to nine diagrams in total show another embodiment in which the temporary stage 4 is suspended by a center hole jack 14 installed at the top of the steel column 2. In this example, four center hole jacks 14 are prepared for each column steel frame 2, and the temporary frame 4a of the temporary stage 4 is suspended and supported via a wire rope 15.

床コンクリートの施工に際しては柱鉄骨2にボルト等で
固定した受金具16上にジヤツキ17を介して、仮設ス
テージ4を下から支持するようになっている。仮設ステ
ージ4の吊降し作業は受金具16およびジヤツキ17を
撤去し、センターホールジヤツキ14の操作により、徐
々に下げて行き、下階位置の受金具16およびジヤツキ
17上に設置する。なお、図中18はワイヤーガイドで
ある。
When constructing the floor concrete, the temporary stage 4 is supported from below via jacks 17 on a receiving metal fitting 16 fixed to the column steel frame 2 with bolts or the like. To suspend the temporary stage 4, remove the bracket 16 and jack 17, gradually lower it by operating the center hole jack 14, and install it on the bracket 16 and jack 17 at the lower floor position. In addition, 18 in the figure is a wire guide.

また、仮設ステージ4はセンターコア1にも同様に支持
させることができ、センターコア1の壁面に受金具取付
用の埋込みポルI・を用意して、柱鉄骨2位置と同様に
1または複数のセンターホールジヤツキ14を用い、同
時に吊降し作業を行なう。
In addition, the temporary stage 4 can be supported by the center core 1 in the same way, and by preparing an embedded pole I for mounting a bracket on the wall of the center core 1, one or more Using the center hole jack 14, the lifting work is carried out at the same time.

珂・1図(a)〜(g)は−例として、この発明を利用
して地上48階の超高層ビルを構築する場合を示したも
ので、次のような手順で作業を行なう。
Figures 1 (a) to (g) show, as an example, the construction of a 48-story skyscraper using the present invention, and the work is carried out in the following steps.

■ スライディングフォームエ法あるいはジャンビング
ツオーム工法によりセンターコア1を所定高さまで先行
させて構築する(2・1図(a)参照)。
■ Build the center core 1 to a predetermined height using the sliding form method or the jumping two-ohm construction method (see Figure 2.1 (a)).

■ 柱鉄骨2を立上げ、仮設ステージ4を18階の床位
置に組立てる(第1図(+))参照)。柱鉄骨2は仮設
の水平ブレース3により、センターコア1と連結してお
き、まず18階部分について配筋等性なった後、床コン
クリートを打設する。
■ Erect the column steel frame 2 and assemble the temporary stage 4 at the floor position of the 18th floor (see Figure 1 (+)). The column steel frame 2 is connected to the center core 1 by a temporary horizontal brace 3, and after the reinforcement is arranged on the 18th floor, the floor concrete is poured.

■ 仮設ステージ4を1階分吊降しく第1図(C)参照
)、17階部分の床架槽5を施工する。
- Lower the temporary stage 4 by one floor (see Figure 1 (C)) and construct the floor tank 5 on the 17th floor.

■ 以下、同様の作業を4階まで繰返す(第1図(d)
参照)。なお、4階以下の低層部6については従来と同
様下から建方を行ない、この部分の作業を並行作業とし
ている。また、この間センターコア1をさらに上方へ構
築して行く。
■ From now on, repeat the same operation up to the 4th floor (Fig. 1 (d)
reference). As for the low-rise part 6 of the fourth floor and below, erection is carried out from the bottom as in the past, and the work for this part is carried out in parallel. Also, during this time, the center core 1 is constructed further upward.

■ 柱鉄骨2を上方へ立上げ、解体した仮設ステージ4
を32階の床位置に移動させ(之・1図(e)参照)、
32階から19階まで順次、床架槽5を施工する。また
、それと並行して、4階から上方へ順次柱コンクリート
を打設して複合柱を形成させるとともに、センターコア
1の上方への構築を完了させる。
■ Temporary stage 4 with pillar steel frame 2 raised upwards and dismantled
was moved to the floor position on the 32nd floor (see Figure 1 (e)),
Floor tanks 5 will be constructed sequentially from the 32nd floor to the 19th floor. At the same time, concrete columns are sequentially placed upwards from the fourth floor to form composite columns, and the construction of the center core 1 upwards is completed.

■ 仮設ステージ4を屋根スラブ位置に移動させ(計1
図(f)参照)、順次66階まで床架槽5を施工する。
■ Move temporary stage 4 to the roof slab position (1 stage in total)
(See Figure (f)), the floor tanks 5 will be constructed sequentially up to the 66th floor.

また、同時に19階から柱コンクIJ −1−を打設し
、順次上方へ複合柱を形成させて行き、下階からは上方
へ向けてカーテンウオールの取り付けを開始する。
At the same time, concrete columns IJ-1- will be cast from the 19th floor, and composite columns will be sequentially formed upwards, and installation of curtain walls will begin upwards from the lower floors.

■ すべての架構作業を完了しくA−1図(g)参照)
、カーテンウオールの作業を継続する。
■ Complete all structural work (see Figure A-1 (g))
, continue work on the curtain wall.

以」二の作業において、センターコア1の立上げの速度
は1日に1階分、床架槽5の施工は5日で1階分、柱コ
ンクリートの施工が2日で1階分を想定しており、床架
槽5の施工と、センターコア1の上方階の施工、さらに
床架槽5の施工と下方階の柱コンクリートの施工等を並
行作業として行なうことができる。
In the work mentioned above, it is assumed that the construction speed of center core 1 will be one floor per day, the construction of floor tank 5 will be one floor in five days, and the construction of column concrete will be one floor in two days. Therefore, the construction of the floor tank 5 and the construction on the upper floor of the center core 1, and the construction of the floor rack tank 5 and the construction of column concrete on the lower floor, etc. can be performed in parallel.

〔発明の効果〕〔Effect of the invention〕

■ 上層階で組立てた仮設ステージを繰り返し使用する
ので仮設資料が少なくて済み、経済的である。
■ Since the temporary stages assembled on the upper floors are used repeatedly, fewer temporary materials are required, making it economical.

■ 仮設ステージは解体せずに移動できるので作業の手
間が少なく、省力化が図れる。
■ Temporary stages can be moved without being dismantled, reducing work effort and saving labor.

■ コンクリートの硬化待ちの作業が少なくなるため、
並行作業により大幅な工期短縮が図れる。
■ There is less work to do while waiting for the concrete to harden.
Parallel work can significantly shorten the construction period.

【図面の簡単な説明】[Brief explanation of drawings]

第1図(a)〜(g)はこの発明の一実施例における施
工手順を示す正面図、計2図は仮設ステージの鉄骨フレ
ームの底面図、2・5図は計2図の■−■断面図、刀・
4図は計6図の1−If断面図、之・5図は施工途中に
おける平面図、計6図は床および柱部分の構造を示す断
面斜視図、刀・7図は他の実施例における要部の正面図
、第8図は側面図、珂・9図は平面図である。 1・・・・・・センターコア、2・・・・・・柱鉄骨、
3・・・・・・水平ブレース、4・・・・・・仮設ステ
ージ、4a・・・・・・鉄骨フレーム、4b・・・・・
・型枠、5・・・・・・床架槽、5a・・・・・・床ス
ラブ、5b・・・・・・梁、6・・・・・・低層部、7
・・・・・・柱コンクリート、8・・・・・・柱コンク
リート打設用の穴、9・・・・・・接合プレート、10
・・・・・・柱鉄筋、11・・・・・・床鉄筋、12・
・・・・・アンボンドPCストランド、13・・・・・
・梁鉄筋、14・・・・・・センターホールジヤツキ、
15・・・・・・ワイヤーロープ、16・・・・・・受
金具、17・・・・・・ジヤツキ、18・・・・・・ワ
イヤーガイド。 第1図(a)  第1図(b) 第1図(C)   第1図(d) 第1図(e)    第1図(f) 第1図(9) 第2図 第3図 第4図
Figures 1 (a) to (g) are front views showing the construction procedure in one embodiment of the present invention, two figures in total are bottom views of the steel frame of the temporary stage, and figures 2 and 5 are two figures - ■ Cross section, sword/
Figure 4 is a 1-If sectional view of Figure 6 in total, Figure 5 is a plan view during construction, Figure 6 is a cross-sectional perspective view showing the structure of the floor and column parts, and Figure 7 is a cross-sectional view of another example. Figure 8 is a front view of the main parts, Figure 8 is a side view, and Figure 9 is a plan view. 1...Center core, 2...Column steel frame,
3...Horizontal brace, 4...Temporary stage, 4a...Steel frame, 4b...
・Formwork, 5...Floor tank, 5a...Floor slab, 5b...Beam, 6...Low-rise section, 7
......Column concrete, 8...Hole for pouring column concrete, 9...Joining plate, 10
......Column reinforcing bars, 11...Floor reinforcing bars, 12.
...Unbonded PC strand, 13...
・Beam reinforcing bar, 14... Center hole jack,
15... Wire rope, 16... Bracket, 17... Jacket, 18... Wire guide. Figure 1 (a) Figure 1 (b) Figure 1 (C) Figure 1 (d) Figure 1 (e) Figure 1 (f) Figure 1 (9) Figure 2 Figure 3 Figure 4 figure

Claims (3)

【特許請求の範囲】[Claims] (1)センターコアの構築を先行させ、続いてセンター
コア外部の柱鉄骨を所定高さまで立上げて行き、該柱鉄
骨に沿つてスライド可能な仮設ステージを、立上げた前
記柱鉄骨上部にセンターコアを取囲むようにして組立て
、該仮設ステージを1階ずつ下げながら仮設ステージ上
に順次下階の床コンクリートを打設して行くことを特徴
とする建物の架構施工法。
(1) The center core is constructed first, and then the column steel frames outside the center core are erected to a predetermined height, and a temporary stage that can slide along the column steel frames is placed at the center on top of the erected column steel frames. A building frame construction method characterized by assembling the core so as to surround it, and successively pouring floor concrete for the lower floors onto the temporary stage while lowering the temporary stage one floor at a time.
(2)柱鉄骨は仮設の水平ブレースでセンターコアと連
結しながら立上げる特許請求の範囲第1項記載の建物の
架構施工法。
(2) The building frame construction method according to claim 1, wherein the column steel frame is erected while being connected to the center core by a temporary horizontal brace.
(3)仮設ステージは鉄骨フレームと該鉄骨フレーム上
に設けた型枠とからなる特許請求の範囲第1項または第
2項記載の建物の架構施工法。
(3) The method of constructing a building frame according to claim 1 or 2, wherein the temporary stage comprises a steel frame and a formwork provided on the steel frame.
JP14136685A 1985-06-27 1985-06-27 Construction of housing of building Granted JPS621954A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP14136685A JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP14136685A JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Publications (2)

Publication Number Publication Date
JPS621954A true JPS621954A (en) 1987-01-07
JPH0417262B2 JPH0417262B2 (en) 1992-03-25

Family

ID=15290311

Family Applications (1)

Application Number Title Priority Date Filing Date
JP14136685A Granted JPS621954A (en) 1985-06-27 1985-06-27 Construction of housing of building

Country Status (1)

Country Link
JP (1) JPS621954A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01263334A (en) * 1988-04-14 1989-10-19 Takenaka Komuten Co Ltd Core part precedence type construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH01263334A (en) * 1988-04-14 1989-10-19 Takenaka Komuten Co Ltd Core part precedence type construction method

Also Published As

Publication number Publication date
JPH0417262B2 (en) 1992-03-25

Similar Documents

Publication Publication Date Title
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
JP5003253B2 (en) RC beam construction method
JPH0657956A (en) Construction of concrete structure
JPS621954A (en) Construction of housing of building
JPS61109827A (en) Construction of basement
US3435583A (en) Method of forming buildings
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JP3187618B2 (en) How to assemble beam reinforcement
JPH0437893B2 (en)
JP2804219B2 (en) Reinforced steel pipe unit and building construction method using the same
JPH0642184A (en) Construction of skeleton using half precast floor board
JP2990216B2 (en) Construction method of reinforced concrete building
JP3364426B2 (en) How to build pillars
JPS63312437A (en) Construction of underground structure
JPH0827903A (en) All weather type building method
JP3224152B2 (en) Construction method of cross beam in concrete building
JPH03197734A (en) Lift up method by replacement of scaffold body
SU1048093A1 (en) Method of erecting multistorey building by floor-rising technique
JPH083926A (en) Construction method for composite structure pier
JP2000265546A (en) Construction method for column, and construction method for column and beam
JPH0681476A (en) Building method for concrete structure
JPH0571747B2 (en)
JPH06288095A (en) Haunch reinforcing bar pre-assembly method for building built of reinforced concrete
JPH11301973A (en) Crane for tower execution and stage lifintg up execution method
JPS62170675A (en) Construction of reinforced concrete tower shaped struucture