JPH0571747B2 - - Google Patents

Info

Publication number
JPH0571747B2
JPH0571747B2 JP60113367A JP11336785A JPH0571747B2 JP H0571747 B2 JPH0571747 B2 JP H0571747B2 JP 60113367 A JP60113367 A JP 60113367A JP 11336785 A JP11336785 A JP 11336785A JP H0571747 B2 JPH0571747 B2 JP H0571747B2
Authority
JP
Japan
Prior art keywords
reinforcing bars
formwork
beams
assembled
reinforced concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP60113367A
Other languages
Japanese (ja)
Other versions
JPS61270462A (en
Inventor
Keiji Himi
Ichiro Abe
Noboru Fujii
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP60113367A priority Critical patent/JPS61270462A/en
Publication of JPS61270462A publication Critical patent/JPS61270462A/en
Publication of JPH0571747B2 publication Critical patent/JPH0571747B2/ja
Granted legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E60/00Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
    • Y02E60/10Energy storage using batteries

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】 [産業上の利用分野] この発明は高層鉄筋コンクリート構造の施工法
の改良に係るものである。
[Detailed Description of the Invention] [Industrial Application Field] This invention relates to an improvement in the construction method of high-rise reinforced concrete structures.

[発明が解決しようとする問題点] 鉄筋コンクリート構造物の施工に際して省力化
高品質化等をはかるため、種々のプレハブ工法が
開発されている。そして梁を高度にプレハブ化し
たPC梁工法は前記目的を達成するに適した工法
であるがPC梁相互の接続が最大の問題点となる。
例えばPC梁を中央で接続する場合、PC梁のコン
クリートを500mm程度打ち残しておき、鉄筋を溶
接接合した後、梁のスタラツプ筋を施工しその周
囲に型枠を組立ててコンクリートを打設すること
になるが、500mm程度の間隔では溶接作業空間が
狭く、またPC梁に埋設された鉄筋位置の誤差を
吸収するため鉄筋を曲げるには長さが十分でな
く、また鉄筋を溶接すると1ヶ所当り0.5〜1.0mm
程度縮むが250mm程度の長さでは残留応力が生じ
て好ましくない等の問題がある。
[Problems to be Solved by the Invention] Various prefabricated construction methods have been developed to save labor and improve quality when constructing reinforced concrete structures. The PC beam construction method, in which the beams are highly prefabricated, is suitable for achieving the above objectives, but the biggest problem is the connection between the PC beams.
For example, when connecting PC beams at the center, leave about 500 mm of concrete on the PC beam, weld the reinforcing bars together, then construct the beam's starp bars, assemble the formwork around it, and pour the concrete. However, with a spacing of about 500 mm, the welding work space is narrow, and the length is not sufficient to bend the reinforcing bars to absorb errors in the position of the reinforcing bars embedded in the PC beam. 0.5~1.0mm
Although the length may be reduced to a certain extent, there are problems such as undesirable residual stress occurring at a length of about 250 mm.

また直交する二方向をPC梁とした場合には柱
と梁の交差部分の納まりがむずかしくなる。すな
わち一方向の梁をセツトした後、他方向の梁をセ
ツトすることとなるが、鉄筋が上下2段配筋の場
合鉄筋を交差させることは困難である。そこでプ
レハブ化率は前記二方向PC梁案よりも落ちるが
一方向PC梁案が考えられる。その場合一方向の
梁をPC化し、他方向は現場で鉄筋を組むことに
なるが現場で鉄筋を組むのでは工期短縮ができな
い。
Also, if two perpendicular directions are made of PC beams, it will be difficult to accommodate the intersection of the column and beam. That is, after setting the beams in one direction, the beams in the other direction are set, but if the reinforcing bars are arranged in two stages, upper and lower, it is difficult to intersect the reinforcing bars. Therefore, a one-way PC beam plan can be considered, which has a lower prefabrication rate than the two-way PC beam plan. In that case, the beams in one direction would be converted to PC, and the reinforcing bars in the other direction would be erected on-site, but erecting reinforcing bars on-site would not shorten the construction period.

以上の通り、PC梁に埋め込まれた鉄筋相互を
接続することは作業性が悪い。また鉄筋を現場で
組むのも作業性が悪い。そこでPC梁に直交する
梁の鉄筋は地組ヤードPC梁筋に先組みされたプ
レハブ筋として揚重、組立てる工法としたのがこ
の発明である。
As mentioned above, it is difficult to connect reinforcing bars embedded in PC beams. Also, it is difficult to assemble reinforcing bars on site. Therefore, in this invention, the reinforcing bars of the beams perpendicular to the PC beams are lifted and assembled as prefabricated bars that are pre-assembled to the PC beam bars in the ground assembly yard.

[問題点を解決するための手段] この発明の要旨とする構成は、一方の梁をプレ
キヤスト鉄筋コンクリート部材、すなわちPC梁
とし、一方の梁に直交する他方の梁の鉄筋を先組
して前記一方の梁に直交状態に組立てて単位部材
とし、この単位部材を柱間に建込み、前記一方の
PC梁を支保工によつて支持するとともに、前記
先組した他方の梁の鉄筋をスパン中間で接続して
梁型枠内に配置し、梁型枠内に現場打ちコンクリ
ートを打設して他方の梁を構成して鉄筋コンクリ
ート梁を一体的に構成する。
[Means for Solving the Problems] The configuration that is the gist of the present invention is that one beam is a precast reinforced concrete member, that is, a PC beam, and the reinforcing bars of the other beam orthogonal to the one beam are preassembled to form one beam. This unit member is assembled perpendicularly to the beam of the
While supporting the PC beam with shoring, the reinforcing bars of the other previously assembled beam are connected at the mid-span and placed inside the beam formwork, and cast-in-place concrete is poured inside the beam formwork. The reinforced concrete beam is integrally constructed by configuring the beams.

[実施例] 地組ヤードで予め製作される梁を構成する単位
部材Aは二方向の梁を連続的に組合せたもので、
一方の梁1をプレキヤスト鉄筋コンクリート部材
(PC部材)とし、端部には鉄筋を突設しておく。
また前記一方の梁1に直交する他方の梁2の鉄筋
を先組して梁1に直交状態に組立てておく。この
単位部材Aは第1図に図示したようにT状、I
状、キ状等に形成される。すなわち一方の梁1の
PC部材部分は1スパンあるいは2スパンとし他
方の梁2の鉄筋はスパン中間で接続するようにす
る。
[Example] Unit member A constituting a beam manufactured in advance at a construction yard is a continuous combination of beams in two directions,
One of the beams 1 is a precast reinforced concrete member (PC member), with reinforcing bars protruding from the ends.
Further, the reinforcing bars of the other beam 2 perpendicular to the one beam 1 are assembled in advance so as to be perpendicular to the beam 1. This unit member A is T-shaped and I-shaped as shown in FIG.
It is formed in a shape such as a square shape or a square shape. In other words, one beam 1
The PC member part will have one or two spans, and the reinforcing bars of the other beam 2 will be connected at the middle of the span.

なおPC梁1は上端鉄筋およびフープ筋の上部
は露出した構成とする。
Note that the PC beam 1 has a structure in which the top reinforcing bars and the tops of the hoop bars are exposed.

施工に際しては既設建物躯体Bを利用して外側
に盛替え用の足場Cを設置する。次いで柱用プレ
ハブ鉄筋3を既設躯体B上に吊込み、かつ柱型枠
4を建込む。(第3,4図参照)次いで盛替え用
の梁型枠5を内部堅空間を利用して揚重盛替して
既設躯体上に設置し、(第5図参照)先ずPC梁1
に直交する梁型枠5は下げてセツトしておくとと
もに床型枠6または薄肉PC板を必要によりサポ
ート7を利用して設置する。次いで床型枠6を作
業床として柱コンクリートを打設する。(第6図
参照) 次いで梁の構成部材となる単位部材Aを吊込
み、PC部材1は支保工8によつて正規の高さに
支持する。(第7図参照) かつ柱9上に突出した柱主筋10間に梁鉄筋2
を位置させる。(第10図参照) 他方の梁2の鉄筋は接続しその後に梁型枠5を
正規の位置に上げ(第8図参照)次いで梁および
床の現場打ちコンクリートを打設する。(第9図
参照) 以上の工程を順次繰返して所要の高さまで建築
する。
During construction, the existing building frame B will be used and scaffolding C for replacement will be installed on the outside. Next, the prefabricated reinforcing bars 3 for columns are hung onto the existing frame B, and the column formwork 4 is erected. (See Figures 3 and 4) Next, the beam formwork 5 for replacement is lifted up and replaced using the internal space and installed on the existing frame. (See Figure 5) First, the PC beam 1
The beam formwork 5 perpendicular to the beam formwork 5 is lowered and set, and the floor formwork 6 or thin PC board is installed using supports 7 if necessary. Next, column concrete is placed using the floor formwork 6 as a working floor. (See Figure 6) Next, the unit member A that will become the component of the beam is suspended, and the PC member 1 is supported at a regular height by the shoring 8. (See Figure 7) Also, the beam reinforcing bars 2
position. (See Fig. 10) The reinforcing bars of the other beam 2 are connected, and then the beam formwork 5 is raised to its normal position (see Fig. 8).Then, cast-in-place concrete for the beam and floor is poured. (See Figure 9) The above steps are repeated in order to build the building to the required height.

[発明の効果] この発明は以上の構成からなり、鉄筋コンクリ
ート構造物の施工に際して梁型枠の盛替工法を実
施するに際して一方をPC梁化し、これに直交す
る他方の梁鉄筋を先組した鉄筋することにより、
柱位置で鉄筋を直交状に現場組立作業をする必要
がなく、工場で鉄筋の組立の大部分を実施するの
で高所作業が少なくなり、施工が安全であり、工
期短縮と施工時の鉄筋接続の作業性をそれぞれバ
ランスして向上することに成功したものである。
[Effects of the Invention] This invention has the above-mentioned configuration, and when implementing a beam formwork replacement method during the construction of a reinforced concrete structure, one of the beams is made into a PC beam, and the other beam reinforcing bar perpendicular to this is made of pre-assembled reinforcing bars. By doing so,
There is no need to assemble the reinforcing bars orthogonally at the column location on-site, and most of the reinforcing bars are assembled in the factory, which reduces work at heights, makes construction safer, shortens the construction period, and makes it easier to connect reinforcing bars during construction. We have succeeded in improving the workability of each in a well-balanced manner.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図a,b,c,dは梁を構成する単位部材
の平面図、第2図は単位部材の配置状態の平面
図、第3図、第4図、第5図、第6図、第7図、
第8図および第9図は施工過程の概要を示した立
面図、第10図は柱と梁の鉄筋配置状態の平面図
である。 A……単位部材、B……既設躯体、C……足
場、1……PC梁、2……梁鉄筋、3……柱用プ
レハブ鉄筋、4……柱型枠、5……梁型枠、6…
…床型枠、7……サポート、8……支保工、9…
…柱、10……柱主筋。
Figures 1a, b, c, and d are plan views of the unit members constituting the beam, Figure 2 is a plan view of the arrangement of the unit members, Figures 3, 4, 5, 6, Figure 7,
FIGS. 8 and 9 are elevational views showing an outline of the construction process, and FIG. 10 is a plan view showing the reinforcing bars for columns and beams. A... Unit member, B... Existing frame, C... Scaffolding, 1... PC beam, 2... Beam reinforcing bar, 3... Prefabricated reinforcing bar for column, 4... Column formwork, 5... Beam formwork ,6...
...floor formwork, 7...support, 8...shoring, 9...
...Column, 10...Column main reinforcement.

Claims (1)

【特許請求の範囲】[Claims] 1 一方の梁をプレキヤスト鉄筋コンクリート部
材とし、一方の梁に直交する他方の梁の鉄筋を先
組して前記一方の梁に直交状態に組立てた単位部
材を柱間に建込み、前記一方の梁を支保工によつ
て支持するとともに、前記先組した他方の梁の鉄
筋をスパン中間で接合して梁型枠内に配置し、梁
型枠内に現場打ちコンクリートを打設して他方の
梁を構成することを特徴とする鉄筋コンクリート
構造の施工法。
1 One beam is a precast reinforced concrete member, the reinforcing bars of the other beam that are orthogonal to one beam are pre-assembled, and the unit members assembled in a state perpendicular to the one beam are erected between the columns, and the one beam is In addition to supporting it with shoring, the reinforcing bars of the other previously assembled beam are joined at the mid-span and placed within the beam formwork, and cast-in-place concrete is poured into the beam formwork to support the other beam. A construction method for reinforced concrete structures characterized by:
JP60113367A 1985-05-27 1985-05-27 Construction of reinforced concrete structure Granted JPS61270462A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP60113367A JPS61270462A (en) 1985-05-27 1985-05-27 Construction of reinforced concrete structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP60113367A JPS61270462A (en) 1985-05-27 1985-05-27 Construction of reinforced concrete structure

Publications (2)

Publication Number Publication Date
JPS61270462A JPS61270462A (en) 1986-11-29
JPH0571747B2 true JPH0571747B2 (en) 1993-10-07

Family

ID=14610481

Family Applications (1)

Application Number Title Priority Date Filing Date
JP60113367A Granted JPS61270462A (en) 1985-05-27 1985-05-27 Construction of reinforced concrete structure

Country Status (1)

Country Link
JP (1) JPS61270462A (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61286431A (en) * 1985-06-12 1986-12-17 東急工建株式会社 Connection of pc pillar and beam

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61221460A (en) * 1985-03-28 1986-10-01 清水建設株式会社 Beam

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS61221460A (en) * 1985-03-28 1986-10-01 清水建設株式会社 Beam

Also Published As

Publication number Publication date
JPS61270462A (en) 1986-11-29

Similar Documents

Publication Publication Date Title
JPH0571747B2 (en)
JP3187618B2 (en) How to assemble beam reinforcement
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP3008051B2 (en) Reinforced preassembly with formwork and reinforced preassembly method with formwork
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JPH06193133A (en) Mixed structure of building mainly made of reinforced concrete
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH01214641A (en) Construction of steel-pipe precast concrete pole
JPH0447737B2 (en)
JPH0448136B2 (en)
JPH0588331B2 (en)
JP2651506B2 (en) How to apply underground beams
JP2554535B2 (en) Steel beam / reinforced concrete column composite construction method
JPH03293445A (en) Structure of building and construction
JP2984626B2 (en) PC pillar construction method and its PC pillar
JPH0528248Y2 (en)
JPH0367166B2 (en)
JPH01102142A (en) Construction of high building made of reinforced concrete
JPS62182329A (en) Construction of concrete structure
JPS645134B2 (en)
JPH0621469B2 (en) Multi-story building frame construction method
JPH0410954B2 (en)
JPH04237731A (en) Constructing method for rc pillar with core reinforcement bar

Legal Events

Date Code Title Description
EXPY Cancellation because of completion of term