JPH03293445A - Structure of building and construction - Google Patents

Structure of building and construction

Info

Publication number
JPH03293445A
JPH03293445A JP9551990A JP9551990A JPH03293445A JP H03293445 A JPH03293445 A JP H03293445A JP 9551990 A JP9551990 A JP 9551990A JP 9551990 A JP9551990 A JP 9551990A JP H03293445 A JPH03293445 A JP H03293445A
Authority
JP
Japan
Prior art keywords
steel
column
construction
steel frame
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP9551990A
Other languages
Japanese (ja)
Inventor
Kazuhiro Hatakeyama
一宏 畠山
Hisanori Taniguchi
尚範 谷口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP9551990A priority Critical patent/JPH03293445A/en
Publication of JPH03293445A publication Critical patent/JPH03293445A/en
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

PURPOSE:To reduce cost, by placing and fixing a large steel frame beam made of steel frame and reinforced concrete at the end thereof on the upper end of a steel reinforced concrete post. CONSTITUTION:After a unit of previously assembled steel rods with main reinforcement of a column, hoop steel rods are fastened at the main reinforcement of the column protrusively provided on the underfloor slab, a steel pipe with the same length as the size under the beam is erected as a robber mold at the outer side and concrete is placed on the inside to form a column 1. Next, large steel frame beams 2, 3 are installed and then upper and lower main reinforcement, spiral stirrups, etc., are arranged at the ends 2b, 3b. Next, after beams 2, 3 are laid and fixed at the upper end of the column 1, the edges 2b, 3b are covered with concrete to be unified with the column 1. And then a small beam 4 is fitted to the steel frame of the beam 2 via a gusset plate and further, a floor slab 5 is applied. In this way, the structure can be simply constructed and steel frames can be economized and moreover the rigidity of the beam ends is increased with adjustment.

Description

【発明の詳細な説明】 「産業上の利用分野」 本発明は、各種建築物の骨組となる構造体およびその施
工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION "Field of Industrial Application" The present invention relates to a structure that serves as the frame of various buildings and a construction method thereof.

「従来の技術およびその課題」 周知のように、建築物の骨組となる構造体は、鉄骨造(
S造)、鉄筋コンクIJ −構造(RC造)、鉄骨鉄筋
コンクリート造(SRC造)によるものが−般的である
が、S造は工期の点では有利であるものの工費の点で不
利であり、また、RC造は鉄筋工事、型枠工事、コンク
リート打設工事等の各種工事か必要であるのでS造に比
して施工が繁雑なものであるとともに、近年においては
それら各種工事の熟練工不足による労務費や資材の高騰
から工費の点でもそれほどの利点がなくなりつつあり、
さらに、SRC造は構造強度の点では最も有利であるが
工期や工費の点では不利なものである。
"Conventional technology and its problems" As is well known, the structure that forms the framework of a building is a steel frame structure (
S construction), reinforced concrete IJ structure (RC construction), and steel reinforced concrete construction (SRC construction) are common, but although S construction has an advantage in terms of construction period, it is disadvantageous in terms of construction cost. In addition, RC structures require various types of work such as reinforcing steel work, formwork work, concrete pouring work, etc., and are therefore more complicated to construct than steel structures. Due to the rising cost of labor and materials, there is no longer much of an advantage in terms of construction costs.
Furthermore, although SRC construction is most advantageous in terms of structural strength, it is disadvantageous in terms of construction period and construction cost.

本発明は上記の事情に鑑みてなされたもので、その目的
とするところは、施工の簡略化を実現し得て工期短縮お
よび工費削減を図ることができ、また、十分な構造強度
を得られる構造体およびその施工方法を提供することに
ある。
The present invention has been made in view of the above circumstances, and its purpose is to simplify construction, shorten construction period and cost, and obtain sufficient structural strength. An object of the present invention is to provide a structure and a construction method thereof.

「課題を解決するための手段」 請求項1の発明は、柱の上端部に大梁の端部を接合して
なる建築物の構造体であって、前記柱が鉄筋コンクリー
ト造とされ、かつ、前記大梁の端部が鉄骨鉄筋コンクリ
ート造とされているとともにその大梁の中間部が鉄骨造
とされてなることを特徴とするものである。
"Means for Solving the Problem" The invention according to claim 1 is a building structure formed by joining the end of a girder to the upper end of a column, wherein the column is made of reinforced concrete, and It is characterized in that the ends of the girders are made of steel reinforced concrete, and the middle part of the girders is made of steel.

また、請求項2の発明は、請求項1に記載の建築物の構
造体の施工方法であって、先組した柱層鉄筋を建て込ん
だ後に鋼管を捨型枠として用いてその内部にコンクリー
トを打設することによって鉄筋コンクリート造の柱を梁
下の部分まで施工した後、大梁の端部となる部分に予め
梁鉄筋および吊型枠が取り付けられた鉄骨を前記柱の上
端に支持することによって架け渡し、次いで、ハーフP
C床版を前記鉄骨に支持することによって敷き込み、し
かる後に、前記梁型枠内およびノ・−フPC床版上にコ
ンクリートを打設することを特徴とするものである。
The invention of claim 2 is a method for constructing a building structure according to claim 1, in which the pre-assembled column layer reinforcing bars are erected, and then a steel pipe is used as a waste form and concrete is poured into the inside of the structure. After constructing reinforced concrete columns up to the bottom of the beams by pouring concrete beams, a steel frame with beam reinforcing bars and suspension formwork attached in advance to the ends of the girders is supported at the top of the columns. Bridge, then half P
The method is characterized in that the C deck slab is laid by being supported by the steel frame, and then concrete is poured into the beam formwork and on the nof PC deck slab.

「作用」 請求項1の発明の構造体は、柱がRC造、大梁の端部が
SRC造、大梁の中間部がS造の複合構造とされたもの
であるので、全体がRC造やSRC造とされる場合に比
して鉄筋量が削減されているとともに現場での型枠作業
やコンクリート打設作業が削減され、また、全体がS造
とされる場合に比して鉄骨量が削減される。また、大梁
の端部がSRC造とされていることによって梁端部にお
ける剛性が十分に高められ、しかも、SRC造とする部
分の長さを増減することによって梁端部の剛性を調節し
得る。
"Operation" The structure of the invention of claim 1 has a composite structure in which the columns are made of RC, the ends of the girders are made of SRC, and the middle part of the girders is made of S. Therefore, the structure as a whole is made of RC or SRC. The amount of reinforcing bars is reduced compared to when the entire building is S-framed, as well as formwork work and concrete pouring work on site, and the amount of steel is also reduced compared to when the entire structure is S-framed. be done. Furthermore, since the ends of the girders are made of SRC construction, the rigidity of the beam ends can be sufficiently increased, and the rigidity of the beam ends can be adjusted by increasing or decreasing the length of the SRC construction part. .

また、請求項2の施工方法では、柱層鉄筋として先組鉄
筋を用いるとともにその型枠として鋼管を用い、また、
鉄骨の建方に先立って梁端部となる部分に予め梁鉄筋を
取り付けておくとともに、梁型枠を鉄骨自身より吊持し
て取り付けておき、さらに、床型枠としてハーフPC床
版を用いることにより、現場での鉄筋工事や型枠工事が
削減され、施工の簡略化が実現される。
Further, in the construction method of claim 2, pre-assembled reinforcing bars are used as the column layer reinforcing bars, and steel pipes are used as the formwork, and
Prior to erecting the steel frame, beam reinforcing bars are attached to the ends of the beams, the beam formwork is suspended from the steel frame itself, and half PC slabs are used as the floor formwork. This reduces reinforcing steel work and formwork work on site, and simplifies construction.

「実施例」 以下、本発明の実施例を第1図ないし第7図を参照して
説明する。
"Embodiments" Examples of the present invention will be described below with reference to FIGS. 1 to 7.

第1図および第2図は、本発明に係る構造体をスパン長
が比較的大きく(10〜18m程度)、かつ、高さが4
〜5階程度の中層の建築物の骨組として採用した場合の
一実施例を示す立断面図および平面図(床伏図)であっ
て、図中、符号1は柱、2はスパン方向の大梁、3は桁
行方向の大梁、4は桁行方向に設けられた小梁、5は床
スラブである。
Figures 1 and 2 show a structure according to the present invention with a relatively large span length (approximately 10 to 18 m) and a height of 4 m.
An elevational cross-sectional view and a plan view (floor plan) showing an example of the case where it is adopted as the frame of a medium-rise building of about 5 to 5 stories. In the figure, reference numeral 1 indicates a column, and 2 indicates a girder in the span direction. , 3 is a large beam in the column direction, 4 is a small beam provided in the column direction, and 5 is a floor slab.

上記柱1は、後述するように、鋼管が捨型枠として用い
られてその内部にコンクリ一トが打設されて形成された
断面円形の鉄筋コンクリート造(RC造)のものである
。二の柱lにおける柱主筋としては大径鉄筋が使用され
、また、異形PC鋼棒かスパイラルフープとして使用さ
れている。
As will be described later, the pillar 1 is of reinforced concrete construction (RC construction) with a circular cross section, and is formed by using a steel pipe as a waste form and pouring concrete into the inside. Large-diameter reinforcing bars are used as the main reinforcement in the second column 1, and they are also used as deformed PC steel bars or spiral hoops.

また、大梁2,3は、それぞれ鉄骨(H形鋼)2a。Moreover, the girders 2 and 3 each have a steel frame (H-beam) 2a.

3aの端部2b、3bすなわち柱1との接合部の近傍の
部分が鉄筋コンクリートにより被覆されていることによ
り、その端部2b、3bの部分のみがSRC造とされ、
中間部分は上記鉄骨2.3自体によるS造とされたもの
である。これら大梁2,3のSRC造とされる端部2b
、3bにおける梁主筋としては大径鉄筋が使用され、ま
た、異形PC鋼棒がスパイラルスターラップとして使用
されている。
Since the ends 2b and 3b of 3a, that is, the part near the joint with the column 1, are covered with reinforced concrete, only the ends 2b and 3b are made of SRC construction,
The middle part is an S structure made of the steel frame 2.3 itself. The ends 2b of these girders 2 and 3 are made of SRC
, 3b, large-diameter reinforcing bars are used as the main beam reinforcements, and deformed PC steel bars are used as spiral stirrups.

また、小梁4はH形鋼からなるS造のものであって、こ
れら小梁4の両端は上記大梁2の側面(ウェブ)にガセ
ットプレート(図示時)を介してビン接合されたものと
なっている。なお、小梁4としてハ〜フPC梁を用いる
ことでも良い。
Furthermore, the small beams 4 are of S construction made of H-shaped steel, and both ends of these small beams 4 are joined to the side surfaces (webs) of the large beam 2 via gusset plates (as shown). It has become. Note that a half-PC beam may be used as the small beam 4.

さらに、床スラブ5はRC造のものであるが、上記大梁
2,3および小梁4に支持されて敷き込まれたハーフP
C床版上にコンクリートが打設されることによって形成
されている。
Furthermore, although the floor slab 5 is of RC construction, a half P
It is formed by pouring concrete onto the C slab.

上記の構造体は、柱lがRC造、大梁2.3の端部2b
、3bがSRC造、大梁2,3の中間部が鉄骨2*、3
a自体からなるS造の複合構造とされていることから、
全体をRC造やSRC造とする場合に比して鉄筋量が削
減されているとともに現場でのコンクリート打設作業が
削減され、したがって、施工が簡略化されて工期の短縮
を図ることができるとともに、全体をS造とする場合に
比して鉄骨の使用量を削減できるので工費削減にも寄与
できるものである。
In the above structure, the column l is made of RC, and the end part 2b of the girder 2.3
, 3b is SRC construction, the middle part of girders 2 and 3 is steel frame 2*, 3
Since it is a composite structure of S construction consisting of a itself,
Compared to the case where the entire structure is made of RC or SRC, the amount of reinforcing bars is reduced, and the amount of concrete pouring work on site is also reduced, which simplifies construction and shortens the construction period. Since the amount of steel used can be reduced compared to the case where the entire structure is made of steel, it can also contribute to a reduction in construction costs.

そして、上記の構造体では、大梁2.3の端部2b、3
bがSRC造とされていることによって梁端部における
剛性が十分に高められ、しかも、SRC造とする部分の
長さを増減することによって梁端部の剛性を最適なもの
となるように調節することができるものである。なお、
SRC造とする梁端部の部分をRC造とみなして構造計
算を行うことにより、梁端部の剛性に十分な安全率を見
込むことができる。
In the above structure, the ends 2b, 3 of the girder 2.3
b is made of SRC construction, the rigidity at the beam end is sufficiently increased, and by increasing or decreasing the length of the SRC construction, the rigidity of the beam end can be adjusted to the optimum. It is something that can be done. In addition,
By performing structural calculations assuming that the end portion of the beam made of SRC is RC construction, a sufficient safety factor can be expected for the rigidity of the beam end.

次に、上記構造体の施工方法の一例を第3図ないし第7
図を参照して説明する。
Next, an example of the construction method for the above structure is shown in Figures 3 to 7.
This will be explained with reference to the figures.

まず、第3図に示すように、柱主筋10およびスパイラ
ル7−プ11を予め一体に組み立てた先組鉄筋12を、
最下階の床スラブ上に予め突設されている柱主筋10′
にスリーブジヨイント14等により緊結することによっ
て建て込み、その先組鉄筋12の外側に、第4図(イ)
に示すようにこの柱lの梁下寸法に略等しい長さの鋼管
13を捨型枠として建て込み、その内部にコンクリート
を打設する。これにより、鋼管13に被覆されたRC造
の柱1が梁下の部分まで施工される。この際、その柱1
の上端面に、第4図(ロ)に示すように、大梁2を締結
するためのベースプレート30を埋め込んでおく。
First, as shown in FIG.
Column main reinforcement 10' that is installed in advance on the floor slab of the lowest floor
4 (a) on the outside of the pre-assembled reinforcing bars 12.
As shown in FIG. 1, a steel pipe 13 having a length approximately equal to the beam bottom dimension of this column 1 is erected as a waste form, and concrete is poured inside it. As a result, the RC column 1 covered with the steel pipe 13 is constructed to the bottom of the beam. At this time, pillar 1
As shown in FIG. 4(B), a base plate 30 for fastening the girder 2 is embedded in the upper end surface of the base plate 30.

次に、第5図(イ)、(ロ)に示すように、スパン方向
の大梁2となる鉄骨2aを上記柱1.1の上端に支持し
て上記ベースプレート30に締結することによって架け
渡すとともに、第5図(ハ)、(ニ)に示すように、桁
行方向の大梁3となる鉄骨3aを上記鉄骨2aの側面に
ガセットプレート31を介して接合することによって柱
1.1相互間に掛は渡し、必要に応じてそれら鉄骨23
3aを仮設のサポート15により床面より支持する。
Next, as shown in FIGS. 5(a) and 5(b), the steel frame 2a, which will become the girder 2 in the span direction, is supported on the upper end of the column 1.1 and fastened to the base plate 30, thereby constructing the bridge. , as shown in FIGS. 5(c) and 5(d), the steel frames 3a, which will become the girders 3 in the column direction, are joined to the side surfaces of the steel frames 2a via gusset plates 31, so that the columns 1.1 are hung between each other. 23.
3a is supported from the floor by a temporary support 15.

この際、桁行方向の大梁3となる鉄骨3aは隣接する柱
1.1相互間の長さのものを用いるが、スパン方向の大
梁2となる鉄骨2aは複数のスパンに渡る長尺のものを
用いる。そして、それらの鉄骨2a、3aには、第5図
(ロ)にその詳細を示すように、建方に先立って予め梁
端部となる位置に梁上主筋16!、梁下主筋16bおよ
びスパイラル7−ラ/ブ17を取り付けておくとともに
、梁上主筋16aの先端部には定着板18を取り付け、
梁下主筋16bの先端には圧着スリーブ20を取り付け
ておく。これら定着板18および圧着スリーブ20は、
主筋16a、16bとコンクリートとの定着力を高める
!;めのものであるが、主筋】6a、16bを折り曲げ
てフックを形成することが可能な場合はそれらを省略し
ても良い。
At this time, the steel frames 3a that will become the girder 3 in the girder direction are the length between the adjacent columns 1.1, but the steel frames 2a that will be the girder 2 in the span direction are long ones that span multiple spans. use As shown in detail in Figure 5 (b), these steel frames 2a and 3a are pre-installed with beam main reinforcements 16 at positions that will become the beam ends prior to erection. , the lower beam main reinforcement 16b and the spiral 7-rab/b 17 are attached, and the fixing plate 18 is attached to the tip of the upper beam main reinforcement 16a,
A crimp sleeve 20 is attached to the tip of the main reinforcement 16b under the beam. These fixing plate 18 and compression sleeve 20 are
Increase the anchoring force between the main reinforcements 16a and 16b and concrete! However, if it is possible to form a hook by bending the main bars 6a and 16b, they may be omitted.

また、第6図(イ)、(ロ)に示すように、上記の鉄骨
2a、3aの梁端部2b、3bとなる部分、つまり主筋
16a、16bおよびスパイラルスターラップ17が取
り付けられている部分の外側には、梁型枠21を予め取
り付けておく。その梁型枠21としては、鋼製型枠等の
繰り返し使用可能なものを用いるとともに、その梁型枠
21を鉄骨2!、31自身に吊持させる形態で用いて、
その梁型枠21を支持するための支保工を省略する。
In addition, as shown in FIGS. 6(a) and 6(b), the portions that become the beam ends 2b and 3b of the steel frames 2a and 3a, that is, the portions to which the main reinforcements 16a and 16b and the spiral stirrup 17 are attached. A beam formwork 21 is attached in advance to the outside of the frame. As the beam formwork 21, a repeatable formwork such as a steel formwork is used, and the beam formwork 21 is a steel frame 2! , 31 is used in the form of being suspended from itself,
Shoring for supporting the beam formwork 21 is omitted.

さらに、スパン方向の大梁3となる鉄骨3aには、小梁
4をピン接合するためのガセットプレートを予め取り付
けておき、第5図(イ)、第6図(イ)に示すように、
それらガセットプレートを介して小梁4を鉄骨2a、2
a相互間に架け渡す。
Furthermore, a gusset plate for pin-joining the small beams 4 is attached in advance to the steel frame 3a that becomes the large beam 3 in the span direction, and as shown in FIG. 5 (a) and FIG. 6 (a),
The small beams 4 are connected to the steel frames 2a, 2 through these gusset plates.
a Bridge between each other.

そして、上記の梁型枠21.大梁となる鉄骨22.3a
、小梁4に支持することによって、それらの上にハーフ
PC床版22を敷き込む。このハーフPC床版22は、
床スラブ5を形成するためのコンクリート打設の際の捨
型枠となり、そのまま床スラブ5の一部となるものであ
る。
Then, the beam formwork 21. Steel frame 22.3a that becomes the girder
, and by supporting them on the small beams 4, a half PC floor slab 22 is laid on them. This half PC floor slab 22 is
It serves as a waste form when pouring concrete to form the floor slab 5, and becomes a part of the floor slab 5 as it is.

そして、上記のハーフPC床版22上にメツシュ筋を配
筋した後、梁型枠21の内側およびハーフPC床版22
の上にコンクリートを打設し、所定の養生期間を経た後
に梁型枠21を解体すれば、第7図に示すように、端部
2b、3bのみがSRC造とされた大梁2,3および床
スラブ5が完成する。以降は上階に対して以上の手順を
順次繰り返せば良い。
After mesh reinforcement is arranged on the half PC floor slab 22, the inside of the beam formwork 21 and the half PC floor slab 22 are
If concrete is poured on top and the beam formwork 21 is dismantled after a predetermined curing period, the girders 2, 3 and 3 with only the ends 2b and 3b made of SRC, as shown in Fig. 7, are formed. Floor slab 5 is completed. After that, all you have to do is repeat the above steps sequentially for the upper floors.

以上のような施工方法によれば、特に、スパン方向の大
梁2となる鉄骨2aを複数スパンにわたる長尺のものと
したことによって、各スパン毎の長さの鉄骨を用いるこ
とが一般的である従来の場合に比して鉄骨製作コストが
削減されるとともに仕口部の構造が簡略化され、鉄骨工
事の簡略化が実現される。
According to the construction method described above, in particular, by making the steel frame 2a that becomes the girder 2 in the span direction long enough to span multiple spans, it is common to use a steel frame with a length for each span. Compared to the conventional case, the steel frame manufacturing cost is reduced, the structure of the joint part is simplified, and the steel frame work is simplified.

また、柱型枠として鋼管13を捨型枠として用いるとと
もに、梁型枠21として繰り返し使用可能な吊型枠を用
い、さらに床スラブ5の捨型枠22とし、てハーフPC
床版を用いたことにより、型枠工事を大幅に簡略化でき
るし、柱主筋10および梁主筋16a、16bとして大
径鉄筋を使用し、7−プ11およびスターラップ17と
して異径PC鋼棒をスパイラル状として使用することに
より、十分な強度が得られるのみならず、従来一般の鉄
筋を用いる場合に比して鉄筋量、ジヨイント箇所数を削
減でき、しかも予め組み立てた先組鉄筋12を用いるこ
とにより現場での鉄筋工事を簡略化でき、これらに点に
おいても工期短縮、工費削減を図ることができるもので
ある。
In addition, the steel pipe 13 is used as the column formwork, a hanging formwork that can be used repeatedly is used as the beam formwork 21, and the half-PC is used as the waste formwork 22 of the floor slab 5.
By using floor slabs, the formwork work can be greatly simplified, and large-diameter reinforcing bars are used as the main column reinforcement 10 and beam main reinforcements 16a and 16b, and PC steel rods of different diameters are used as the 7-pipe 11 and stirrup 17. By using it in a spiral shape, not only can sufficient strength be obtained, but the amount of reinforcing bars and the number of joints can be reduced compared to the case where conventional general reinforcing bars are used, and moreover, pre-assembled pre-assembled reinforcing bars 12 are used. This simplifies the reinforcing steel work on site, shortens the construction period and reduces construction costs in these respects as well.

なお、大梁の端部2b、3bを形成するためのコンクリ
ートとして高強度コンクリート(F c= 300〜3
60 K g/crg2程度)を用いれば、梁端部の剛
性をより高めることができるとともに鉄筋量をより削減
することができ、また、床スラブ5を形成するだめのコ
ンクリートとして各種の強化繊維を混入したファイバー
コンクリートを用いれば、床スラブのひび割れを十分に
防止することができる。
In addition, high-strength concrete (F c = 300 to 3
60 Kg/crg2), the rigidity of the beam end can be further increased and the amount of reinforcing bars can be further reduced.In addition, various reinforcing fibers can be used as the bulk concrete for forming the floor slab 5. The use of mixed fiber concrete can sufficiently prevent cracks in the floor slab.

「発明の効果」 以上で詳細に説明したように、請求項1の発明の構造体
は、柱が鉄筋コンクリート造、大梁の端部が鉄骨鉄筋コ
ンクリート造、大梁の中間部が鉄骨造とされた複合構造
のものであるので、従来−般のRC造、SRC造の構造
物に比して施工が簡略化されて工期短縮を図ることがで
き、また、従来一般のS造の構造物に比して鉄骨量が削
減されて工費削減を図ることができる、という利点かあ
り、しかも、SRC造とされた梁端部における剛性が十
分に高められるとともに、SRC造とする部分の長さを
増減することによって梁端部の剛性を最適なものとなる
ように調節することができるという効果を有する。
"Effects of the Invention" As explained in detail above, the structure of the invention of claim 1 is a composite structure in which the columns are made of reinforced concrete, the ends of the girders are made of steel reinforced concrete, and the middle part of the girders is made of steel frame. Because it is a conventional RC or SRC structure, the construction is simpler and the construction period can be shortened, and compared to the conventional S structure. It has the advantage that the amount of steel is reduced and construction costs can be reduced.Moreover, the rigidity at the end of the beam made of SRC construction can be sufficiently increased, and the length of the part made of SRC construction can be increased or decreased. This has the effect that the stiffness of the beam end can be adjusted to an optimum value.

また、請求項2の発明の施工方法は、柱側鉄筋として先
組鉄筋を用いるとともにその型枠として鋼管を用い、ま
た、鉄骨の建方に先立って梁端部となる部分に予め梁鉄
筋および吊型枠を取り付けてお(とともに、床型枠とし
てハーフPC床版を用いることにより、現場での鉄筋工
事や型枠工事が削減されて施工の簡略化が実現され、こ
れによって、工期短縮、工費削減を十分に図ることがで
きるものであり、上記の構造体を施工する際に採用して
好適である。
Further, the construction method of the invention of claim 2 uses pre-assembled reinforcing bars as the column-side reinforcing bars, and uses steel pipes as the formwork, and also, prior to erection of the steel frame, the beam reinforcing bars and By installing hanging formwork (as well as using half PC floor slabs as floor formwork), on-site reinforcing work and formwork work are reduced, simplifying construction. This can sufficiently reduce construction costs, and is suitable for use when constructing the above structure.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図および第2図は本発明に係る構造体の一実施例を
示すもので、第1図は立話面図、第2図は平面図である
。 第3図ないし第7図は本発明に係る施工方法の一実施例
を工程順に示す図であって、第3図は立面図、第4図(
イ)は立面図、同図(ロ)は柱上端部を示す斜視図、第
5図(イ)は立面図、同図(ロ)は仕口部の拡大室断面
図、同図(ハ)は仕口部の平面図、同図(ニ)は仕口部
の側面図、第6図(イ)は立面図、同図(ロ)は大梁の
断面図、第7図は立面図である。 1 ・・・・柱、2,3・・・・・・大梁、2g、3a
・・・・・・鉄骨、2b、3b・・・・・大梁の端部、
4・・・・・・小梁、5・・・・・・床スラブ、10・
・・・・・柱主筋、11・・・・・・スパイラル7ブ、
12・・・・・・先組鉄筋、13・・・・・・鋼管、1
5・・・・・・サポート、16a、16b・・・・・・
梁主筋、17・・・・・スパイラルスターラップ、21
・・・・・・梁型枠(吊型枠)、22・・・・・・ハー
フPC床版、30・・・・・・ベースプレート、31・
・・・・・ガセットプレート。
FIGS. 1 and 2 show an embodiment of a structure according to the present invention, with FIG. 1 being an elevation view and FIG. 2 being a plan view. 3 to 7 are diagrams showing an embodiment of the construction method according to the present invention in the order of steps, and FIG. 3 is an elevational view, and FIG. 4 (
A) is an elevation view, FIG. C) is a plan view of the joint section, FIG. 6 (D) is a side view of the joint section, FIG. 6 (A) is an elevation view, FIG. It is a front view. 1... Column, 2, 3... Beam, 2g, 3a
... Steel frame, 2b, 3b ... End of girder,
4... Small beam, 5... Floor slab, 10.
...Column main reinforcement, 11...Spiral 7 bars,
12... pre-assembled reinforcing bar, 13... steel pipe, 1
5...Support, 16a, 16b...
Beam main reinforcement, 17...Spiral stirrup, 21
...Beam formwork (hanging formwork), 22 ...Half PC floor slab, 30 ...Base plate, 31.
...Gusset plate.

Claims (2)

【特許請求の範囲】[Claims] (1)柱の上端部に大梁の端部を接合してなる建築物の
構造体であって、前記柱が鉄筋コンクリート造とされ、
かつ、前記大梁の端部が鉄骨鉄筋コンクリート造とされ
ているとともにその大梁の中間部が鉄骨造とされてなる
ことを特徴とする建築物の構造体。
(1) A building structure formed by joining the end of a girder to the upper end of a column, the column being made of reinforced concrete,
A building structure characterized in that the ends of the girders are made of steel-framed reinforced concrete, and the intermediate portions of the girders are made of steel.
(2)請求項1に記載の建築物の構造体の施工方法であ
って、先組した柱用鉄筋を建て込んだ後に鋼管を捨型枠
として用いてその内部にコンクリートを打設することに
よって鉄筋コンクリート造の柱を梁下の部分まで施工し
た後、大梁の端部となる部分に予め梁鉄筋および吊型枠
が取り付けられた鉄骨を前記柱の上端に支持することに
よって架け渡し、次いで、ハーフPC床版を前記鉄骨に
支持することによって敷き込み、しかる後に、前記梁型
枠内およびハーフPC床版上にコンクリートを打設する
ことを特徴とする建築物の構造体の施工方法。
(2) A method for constructing a building structure according to claim 1, which comprises erecting pre-assembled column reinforcing bars and then using a steel pipe as a waste form and pouring concrete inside it. After constructing reinforced concrete columns up to the bottom of the beams, a steel frame with beam reinforcing bars and suspension forms attached to the ends of the large beams is supported on the upper ends of the columns, and then the half beams are constructed. A method for constructing a building structure, comprising: laying a PC floor slab by supporting it on the steel frame, and then pouring concrete into the beam formwork and onto the half PC floor slab.
JP9551990A 1990-04-11 1990-04-11 Structure of building and construction Pending JPH03293445A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9551990A JPH03293445A (en) 1990-04-11 1990-04-11 Structure of building and construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9551990A JPH03293445A (en) 1990-04-11 1990-04-11 Structure of building and construction

Publications (1)

Publication Number Publication Date
JPH03293445A true JPH03293445A (en) 1991-12-25

Family

ID=14139816

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9551990A Pending JPH03293445A (en) 1990-04-11 1990-04-11 Structure of building and construction

Country Status (1)

Country Link
JP (1) JPH03293445A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704684A (en) * 2012-06-21 2012-10-03 福建省泷澄建设集团有限公司 Construction method for high-strength shaping combined template of plank frame of shear wall
CN105735648A (en) * 2016-03-10 2016-07-06 中国五冶集团有限公司 Multi-segment formwork set-up casting construction process of steel reinforced concrete coal hopper for house of main workshop of power plant

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704684A (en) * 2012-06-21 2012-10-03 福建省泷澄建设集团有限公司 Construction method for high-strength shaping combined template of plank frame of shear wall
CN102704684B (en) * 2012-06-21 2015-01-07 福建省泷澄建设集团有限公司 Construction method for high-strength shaping combined template of plank frame of shear wall
CN105735648A (en) * 2016-03-10 2016-07-06 中国五冶集团有限公司 Multi-segment formwork set-up casting construction process of steel reinforced concrete coal hopper for house of main workshop of power plant

Similar Documents

Publication Publication Date Title
JPH04261934A (en) Building frame construction method using form member made of pre-cast concrete
JP2009013592A (en) Frame assembling method and frame of building
JPH03293445A (en) Structure of building and construction
JPH03132532A (en) Construction method of precast reinforced concrete column and beam
JPH02300439A (en) Prefabricating method
JP2001020376A (en) Sc beam construction method for building
JPH0949331A (en) Construction method of concrete building and construction member
JP3008051B2 (en) Reinforced preassembly with formwork and reinforced preassembly method with formwork
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JPH084196A (en) Panel for building
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH0447737B2 (en)
JPH0598653A (en) Steel pipe concrete pillar in underground inverter construction method
JP2592224Y2 (en) Structure of joint between RC beam and steel structure
JP3187618B2 (en) How to assemble beam reinforcement
JPH06299718A (en) Construction of wall, floor in atomic power plant and wall slab thereof
JPH04309630A (en) Skeleton construction method using pc member
JPH0132339B2 (en)
JPH01121424A (en) Pc frame device for multistoried building
JPH01121425A (en) Post and beam joint structure of multistoried building
JPH0448136B2 (en)
JPH05263526A (en) Construction method of rc construction beam
JP2677159B2 (en) Structure using covered steel tube concrete columns
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure
JP2001020297A (en) Sc-structured footing beam method for building