JPS61270462A - Construction of reinforced concrete structure - Google Patents
Construction of reinforced concrete structureInfo
- Publication number
- JPS61270462A JPS61270462A JP60113367A JP11336785A JPS61270462A JP S61270462 A JPS61270462 A JP S61270462A JP 60113367 A JP60113367 A JP 60113367A JP 11336785 A JP11336785 A JP 11336785A JP S61270462 A JPS61270462 A JP S61270462A
- Authority
- JP
- Japan
- Prior art keywords
- beams
- reinforcing bars
- reinforced concrete
- construction
- formwork
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02E—REDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
- Y02E60/00—Enabling technologies; Technologies with a potential or indirect contribution to GHG emissions mitigation
- Y02E60/10—Energy storage using batteries
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
(57)【要約】本公報は電子出願前の出願データであるた
め要約のデータは記録されません。(57) [Summary] This bulletin contains application data before electronic filing, so abstract data is not recorded.
Description
【発明の詳細な説明】
産業上の利用分野
この発明は高層鉄筋コンクリート構造の施工法特にその
梁部分の施工法の改良に係るものである。DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention relates to an improvement in the method of constructing a high-rise reinforced concrete structure, particularly the method of constructing a beam portion thereof.
発明の解決しようとする問題点
鉄筋コンクIJ−ト構造物の施工に際して省力化高品質
化等をはかるため、種々のプレハブ工法が開発されてい
る。そして梁を高度にプレハブ化したPC梁工法は前記
目的を達成するに適した工法であるがPC梁相互の接続
が最大の問題点となる。Problems to be Solved by the Invention Various prefabrication methods have been developed to save labor and improve quality when constructing reinforced concrete IJ structures. The PC beam construction method, in which the beams are highly prefabricated, is suitable for achieving the above objective, but the biggest problem is the connection between the PC beams.
例えばPC梁を中央で接続する場合、PC梁のコンクリ
ートを500m程度打ち残しておき、鉄筋を溶接接合し
た後、梁のスタラップ筋を施工しその周囲に型枠を組立
ててコンクリートを打設することになるが、溶接の作業
性、鉄筋の精度、溶接による縮み等の問題がある。For example, when connecting PC beams at the center, leave about 500 meters of concrete for the PC beams, weld the reinforcing bars together, construct stirrup bars for the beams, assemble formwork around them, and pour concrete. However, there are problems with welding workability, precision of reinforcing bars, and shrinkage due to welding.
また二方向をPC梁とした場合には柱の部分での納りが
むずかしくなる。すなわち一方向の梁をセットした後他
方向の梁をセットすることとなるが、下端鉄筋が2段配
筋の場合はこの工法は採用できない。そこでプレハブ化
率は前記の二方向PCC梁上シも落ちるが一方向PC梁
案が考えられる。その場合一方向の梁をPC化し、他方
向は現場で鉄筋を組むことになるが現場で鉄筋を組むの
では工期短縮ができない。Also, if PC beams are used in two directions, it will be difficult to fit the pillars together. In other words, the beams in one direction are set and then the beams in the other direction are set, but this method cannot be used if the lower end reinforcing bars are arranged in two stages. Therefore, the prefabrication rate is lower than that of the two-way PCC beam, so a one-way PC beam plan can be considered. In that case, the beams in one direction would be made of PC, and the reinforcing bars in the other direction would be erected on-site, but erecting reinforcing bars on-site would not shorten the construction period.
以上の通り、PC梁に埋め込まれた鉄筋相互を接続する
ことは作業性が悪い。しかしPC梁相互を接続しない場
合の鉄筋を現場で組むのも作業性が悪い。そこでPC梁
に直交する梁の鉄筋は地組ヤードでPC梁筋に先組みさ
れたプレハブ筋として揚重、組立てる工法としたのがこ
の発明である。As mentioned above, it is difficult to connect reinforcing bars embedded in PC beams with each other. However, it is also difficult to assemble reinforcing bars on site when the PC beams are not connected to each other. Therefore, in this invention, the reinforcing bars of the beams perpendicular to the PC beams are lifted and assembled as prefabricated bars that are pre-assembled to the PC beam bars at a ground assembly yard.
問題点を解決するだめの手段
この発明の要旨とする構成は、一方の梁をプレキャスト
鉄筋コンクリート部材、すなわちpc梁とし、他方の梁
の鉄筋を先組して前記一方の梁に直交状態に組立てて単
位部材とし、この単位部材を柱間に建込み、前記一方の
pc梁を支保工によって支持するとともに、前記先組し
た他方の梁の鉄筋を梁型枠内に配置し、梁型枠内にコン
クリートを打設し柱、梁を一体的に構成する。Means to Solve the Problem The configuration that is the gist of the present invention is to use a precast reinforced concrete member, that is, a PC beam, as one beam, and assemble the reinforcing bars of the other beam in advance so as to be orthogonal to the one beam. As a unit member, this unit member is erected between the pillars, one of the PC beams is supported by shoring, and the reinforcing bars of the other previously assembled beam are placed within the beam form. Concrete will be poured and the columns and beams will be integrated.
実施例
地組ヤードで予め製作される梁を構成する単位部材Aは
二方向の梁を連続的に組合せたもので、一方の梁1をプ
レキャスト鉄筋コンクリート部材(20部材)とし、端
部には鉄筋を突設しておくまた他方の梁2の鉄筋を先組
して梁1に直交状態に組立てておく。この単位部材Aは
第1図に図示したようにT状、I状、キ状等に形成され
る。すなわち20部材部分は一方で1スパンあるいは2
スパンとし梁2の鉄筋はスパン中間で接続するようにす
る。Example A unit member A constituting a beam manufactured in advance at a construction yard is a continuous combination of beams in two directions, one of which is a precast reinforced concrete member (20 members), with reinforcing steel at the end. In addition, the reinforcing bars of the other beam 2 are preassembled so as to be perpendicular to the beam 1. This unit member A is formed in a T-shape, an I-shape, a square shape, etc. as shown in FIG. That is, the 20 member section has one span or two
The reinforcing bars of beam 2 will be connected at the middle of the span.
なおpc梁1は上端鉄筋およびフープ筋の上部は露出し
た構成とする。Note that the PC beam 1 has a structure in which the upper end reinforcing bars and the upper portions of the hoop bars are exposed.
施工に際しては既設建物躯体Bを利用して外側に盛替え
用の足場Cを設置する。次いで性用プレハブ鉄筋3を既
設躯体B上に吊込み、かつ柱型枠4を建込む。(第3,
4図参照)次いで盛替え用の梁型枠5を内部竪空間を利
用して揚重盛替して既設躯体上に設置し、(第5図参照
)先ずpc梁1に直交する梁型枠5は下げてセットして
おくとともに床型枠6または薄肉PC板を必要によりサ
ポート7を利用して設置する。次いで床型枠6を作業床
として柱コンクリートを打設する。(第6図参照)
次いで梁の構成部材となる単位部材Aを吊込みPC部材
1は支保工8によって正規の高さに支持する。(第7図
参照)
他方の梁2の鉄筋は接続しその後に梁型枠5を正規の位
置に上げ(第8図参照)次いで梁および床のコンクリー
トを打設する。(第9図参照)以上の工程を順次繰返し
て所要の高さまで建築する。During construction, the existing building frame B will be used and scaffolding C for replacement will be installed on the outside. Next, the prefabricated reinforcing bars 3 are hung onto the existing frame B, and the column forms 4 are erected. (Third,
(See Figure 4) Next, the beam formwork 5 for replacement is lifted up and replaced using the internal vertical space and installed on the existing frame (see Figure 5). First, the beam formwork 5 perpendicular to the PC beam 1 is is lowered and set, and the floor formwork 6 or thin PC board is installed using supports 7 if necessary. Next, column concrete is placed using the floor formwork 6 as a working floor. (See FIG. 6) Next, the unit member A, which will become a component of the beam, is suspended, and the PC member 1 is supported at a regular height by the support 8. (See Fig. 7) The reinforcing bars of the other beam 2 are connected, and then the beam form 5 is raised to its normal position (see Fig. 8). Next, concrete for the beam and floor is poured. (See Figure 9) The above steps are repeated in order to build the building to the required height.
発明の効果
この発明は以上の構成からなり、鉄筋コンクリート構造
物の施工に際して梁型枠の盛替工法を実施するに際して
一方をPC梁化し、他方を先組した鉄筋とすることによ
り、工期短縮と施工時の鉄筋接続の作業性をそれぞれバ
ランスして向上することに成功したものである。Effects of the Invention This invention has the above-mentioned configuration, and when carrying out the replacement method of beam formwork when constructing a reinforced concrete structure, one side is made of PC beams and the other is made of pre-assembled reinforcing bars, thereby shortening the construction period and improving the construction time. This work succeeded in improving the workability of reinforcing bar connections in a well-balanced manner.
第1図a、b、G、dは梁を構成する単位部材の平面図
、第2図は単位部材の配置状態の平面図第3図、第4図
、第5図、第6図、第7図、第8図および第9図は施工
過程の概要を示した立面図である。
A・・単位部材、B・・既設躯体
C・・足場
1・・pc梁、2・・梁鉄筋
3・・住用プレハブ鉄筋、4・・柱型枠5・・梁型枠、
6・・床型枠、7・・サポート8・・支保工。
第3図
第4図
第5図
第6図
第7図
第8図Figures 1 a, b, G, and d are plan views of the unit members constituting the beam, and Figure 2 is a plan view of the arrangement of the unit members. Figures 3, 4, 5, 6, and Figures 7, 8, and 9 are elevational views showing an overview of the construction process. A... Unit member, B... Existing frame C... Scaffolding 1... PC beam, 2... Beam reinforcing bar 3... Prefabricated reinforcing bar for residential use, 4... Column formwork 5... Beam formwork,
6. Floor formwork, 7. Support 8. Shoring. Figure 3 Figure 4 Figure 5 Figure 6 Figure 7 Figure 8
Claims (1)
方の梁の鉄筋を先組して前記一方の梁に直交状態に組立
てた単位部材を柱間に建込み前記一方の梁を支保工によ
って支持するとともに、前記先組した他方の梁の鉄筋を
梁型枠内に配置し、梁型枠内にコンクリートを打設する
ことを特徴とする鉄筋コンクリート構造の施工法。One of the beams is a precast reinforced concrete member, and the reinforcing bars of the other beam are pre-assembled and unit members assembled perpendicular to the one beam are erected between the columns and the one beam is supported by shoring; A construction method for a reinforced concrete structure characterized by placing the reinforcing bars of the other previously assembled beam within the beam formwork, and pouring concrete within the beam formwork.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60113367A JPS61270462A (en) | 1985-05-27 | 1985-05-27 | Construction of reinforced concrete structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP60113367A JPS61270462A (en) | 1985-05-27 | 1985-05-27 | Construction of reinforced concrete structure |
Publications (2)
Publication Number | Publication Date |
---|---|
JPS61270462A true JPS61270462A (en) | 1986-11-29 |
JPH0571747B2 JPH0571747B2 (en) | 1993-10-07 |
Family
ID=14610481
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP60113367A Granted JPS61270462A (en) | 1985-05-27 | 1985-05-27 | Construction of reinforced concrete structure |
Country Status (1)
Country | Link |
---|---|
JP (1) | JPS61270462A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61286431A (en) * | 1985-06-12 | 1986-12-17 | 東急工建株式会社 | Connection of pc pillar and beam |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61221460A (en) * | 1985-03-28 | 1986-10-01 | 清水建設株式会社 | Beam |
-
1985
- 1985-05-27 JP JP60113367A patent/JPS61270462A/en active Granted
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61221460A (en) * | 1985-03-28 | 1986-10-01 | 清水建設株式会社 | Beam |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS61286431A (en) * | 1985-06-12 | 1986-12-17 | 東急工建株式会社 | Connection of pc pillar and beam |
JPH0443131B2 (en) * | 1985-06-12 | 1992-07-15 | Tokyu Koken Kk |
Also Published As
Publication number | Publication date |
---|---|
JPH0571747B2 (en) | 1993-10-07 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPS61270462A (en) | Construction of reinforced concrete structure | |
JP2000160687A (en) | Construction method for composite structure and precast concrete column | |
JPH03279533A (en) | Constructing method for rigid-frame type rc super-high building | |
JP3008051B2 (en) | Reinforced preassembly with formwork and reinforced preassembly method with formwork | |
JP3187618B2 (en) | How to assemble beam reinforcement | |
JPH0673783A (en) | Construction of steel framed reinforced concrete column and steel beam | |
JPS6195136A (en) | Construction of multistoried building skeletal by precast reinforced concrete unit | |
JPH01214641A (en) | Construction of steel-pipe precast concrete pole | |
JPS6198870A (en) | Construction method of precast reinforced concrete earthquake-proof wall | |
JPS61196035A (en) | Construction of concrete building | |
JP2518568Y2 (en) | Connection structure of steel beams to concrete columns | |
JPS5926001Y2 (en) | Precast beam and girder joint structure | |
JP2651506B2 (en) | How to apply underground beams | |
JPH0459978B2 (en) | ||
JPH1122106A (en) | Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member | |
JPH0781355B2 (en) | Construction method of joist slab using precast concrete girder | |
JPH1113141A (en) | Constructing method of composite structure | |
JPH0588331B2 (en) | ||
JPH0692669B2 (en) | Frame method using shaped steel for beam with rebar concrete structure | |
JPS645134B2 (en) | ||
JPH06257285A (en) | Construction of multistoried building | |
JPS6375231A (en) | Building housing | |
JPS62233340A (en) | Installation of anchor bolt in column base of steel work | |
JPH04128429A (en) | Reinforced concrete foundation | |
JPH0621469B2 (en) | Multi-story building frame construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
EXPY | Cancellation because of completion of term |