JPH01263334A - Core part precedence type construction method - Google Patents

Core part precedence type construction method

Info

Publication number
JPH01263334A
JPH01263334A JP9248888A JP9248888A JPH01263334A JP H01263334 A JPH01263334 A JP H01263334A JP 9248888 A JP9248888 A JP 9248888A JP 9248888 A JP9248888 A JP 9248888A JP H01263334 A JPH01263334 A JP H01263334A
Authority
JP
Japan
Prior art keywords
construction
core
steel frame
tower crane
core part
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP9248888A
Other languages
Japanese (ja)
Other versions
JP2668237B2 (en
Inventor
Masamitsu Kikuchi
菊池 正光
Hirohisa Sonobe
薗部 廣久
Sakatoshi Ito
栄俊 伊藤
Takashi Kimura
隆 木村
Hidehiro Tanaka
田中 英裕
Atsushi Nomura
野村 篤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Takenaka Komuten Co Ltd
Original Assignee
Takenaka Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Takenaka Komuten Co Ltd filed Critical Takenaka Komuten Co Ltd
Priority to JP63092488A priority Critical patent/JP2668237B2/en
Publication of JPH01263334A publication Critical patent/JPH01263334A/en
Application granted granted Critical
Publication of JP2668237B2 publication Critical patent/JP2668237B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To shorten the construction period and economize the construction cost by previously executing the steel frame construction and body construction for a core part to the uppermost floor by using a tower crane and executing the steel frame construction and the body construction for an outer shell structure part by using the tower crane. CONSTITUTION:A tower crane 1 is installed at a core part A, and the steel frame construction and body construction for the core part A are executed to the uppermost floor by using the tower crane 1, and the outer peripheral part steel frame construction and outer peripheral part body construction for an outer shell structure part B are executed by using the tower crane 1. The steel frame pillar 3 of the core part A is erected through the joint with the steel frame of a supporting pile, and the construction of the core part A on the ground, pit excavation, body construction for the underground floor structure part D are executed in parallel. Therefore, the number of used tower cranes 1 can be economized, and the previous utilization of the installation of an elevator, toilet, and staircase, etc., for the main construction in the core A is permitted, and the temporary construction cost can be economized.

Description

【発明の詳細な説明】 産業上の利用分野 この発明は、剛強で重量が大きい耐力構造のコア部の外
周に外周部鉄骨柱と梁及び壁板などによる比較的軽量で
耐力もさほど大きくない外殻構造部分(ベアリングウオ
ール構造とも云う)が複合的に構築されて成る高層及び
超高層建物の構築に実施されるコア部先行型の建築工法
に関する。
DETAILED DESCRIPTION OF THE INVENTION Field of Industrial Application This invention provides a relatively lightweight structure with a relatively light but not very large load-bearing capacity, which is constructed by surrounding steel columns, beams, wall plates, etc. on the outer periphery of a core part of a strong and heavy load-bearing structure. The present invention relates to a core-first construction method used in the construction of high-rise and ultra-high-rise buildings in which a shell structure (also called a bearing wall structure) is constructed in a composite manner.

従来の技術 従来、高層及び超高層建物の構築は、その構造の如何を
問わず、地上階から」二層階へと順に各階層の構造を積
み」−げてゆく所謂積層工法が一般的に実施されている
。この場合、地下躯体工事がほぼ完成してから、その後
に地」二鉄骨工事に着手するのが通常の手順とされてい
る。
Conventional Technology Conventionally, in the construction of high-rise and super-high-rise buildings, regardless of their structure, the so-called layered construction method has been generally used, in which the structure of each floor is built up in sequence from the ground floor to the second floor. It has been implemented. In this case, the normal procedure is to begin construction of the underground steel frame after the underground structure work is almost complete.

本発明が解決しようとする課題 例えば第6図に平面図を例示したように、コア部Aと外
殻構造部分B、Bとの複合化構造による大規模な高層建
物を従来の積層工法で構築する場合は、最大作業半径の
吊り能力がi o 1−ンで最大吊り荷重は18トン級
の大型タワークレーンclを2基必要とするのが普通で
ある。そのI−に、最大作業半径の吊り能力が101−
ン級の小型クレーンC2も2基ぐらいは必要であり、合
計4基のクレーンで建物全平面をカバーして施工するの
が通例である。
Problems to be Solved by the Invention For example, as shown in the plan view in Fig. 6, a large-scale high-rise building with a composite structure of a core part A and outer shell structural parts B, B is constructed using the conventional layered construction method. In this case, two large tower cranes with a maximum working radius of io 1-1 and a maximum lifting load of 18 tons are usually required. The I- has a lifting capacity of 101- at the maximum working radius.
About two small C2 cranes are also required, and it is customary to use a total of four cranes to cover the entire building surface during construction.

何故なら、積層工法による場合の材料置場は、建物外周
の敷地(空地)内に求めるほがなく、したがって、クレ
ーンの作業半径はどうしても大きくなり勝ちであるが、
クレーンは作業半径に反比例して吊り荷重が制限される
。−・方、コア部Aを構成する大形重量鉄骨は必ず建物
外周の敷地から大きな作業半径で吊込まねばならず、こ
のためコア部鉄骨は1ピースの重量を10トン以下ぐら
いに軽くしないと揚重不可能となる。その結果、鉄骨等
のジヨイント数が増え、−「数がががった。
This is because when using the layered construction method, material storage must be located within the premises (open space) around the building, and therefore the working radius of the crane is likely to be large.
The lifting load of cranes is limited in inverse proportion to the working radius. - On the other hand, the large heavy steel frame that makes up core section A must be suspended from the site around the building's periphery within a large working radius, and for this reason, the weight of each core section steel frame must be reduced to about 10 tons or less. Lifting becomes impossible. As a result, the number of joints in steel frames, etc. increased, and the number of joints increased.

また、大型タワークレーンc1の旋回中心o1は、前記
コア部Aの大形重量鉄骨を建物外周がら吊込める作業゛
V−径位置に選定しなければならず、必然その位置が限
定されるので、不足分は小型クレーンC2でカバーしな
ければならない。したがって、クレーン台数が増える欠
点がある。勿論、超大型のタワークレーンを使用すれば
りly−ン台数を減らずことは可能であるが、そうした
汎用機種以上のタワークレーンを使用すると、J)ly
−ン使用料がはね−1−ってとうてい施土費の採算が合
わない。よって、第6図のように割安な小型クレーンC
2の併用で間に合わゼているのが通例である。しかし、
このように多数のり1/−ンC1,c2を1Jl用した
場合には、クレーンブームか玉なり合う作業範囲では、
車前に作業順序をきっちり整理してブームがかち合う危
険がないように段取りを組まねばばらす、これが実際上
J1常に面倒である。
In addition, the center of rotation o1 of the large tower crane c1 must be selected at a V-diameter position where the large heavy steel frame of the core section A can be lifted from the outer periphery of the building, and the position is inevitably limited. The shortfall must be covered by small crane C2. Therefore, there is a drawback that the number of cranes increases. Of course, it is possible to reduce the number of cranes by using a super-large tower crane, but if a tower crane larger than a general-purpose model is used,
-1- The construction costs are not profitable when the usage fees are high. Therefore, as shown in Figure 6, an inexpensive small crane C
Usually, you can make do with using 2 together. but,
In this way, when a large number of cranes 1/-c1 and c2 are used for 1 Jl, in the working range where the crane boom or ball is aligned,
In practice, this is always troublesome on the J1, as you have to organize the work order exactly in front of the car and make arrangements to avoid the risk of the boom colliding.

また、従来の積層−「法における大型タワークレーンC
1の旋回中心o1は、第6図に例示したように大ていは
コア部Aの外方、即ち耐力が低い外殻構造部分B内に位
置せしめられている。このためタワークレーンのマスト
を支持するために特別な補強を必要とする場合が多く、
手間と費用がかかることが問題点になっている。
In addition, conventional lamination--Large tower crane C under the Act
As illustrated in FIG. 6, the center of rotation o1 of the rotor 1 is generally located outside the core portion A, that is, within the outer shell structure portion B having low proof stress. For this reason, special reinforcement is often required to support the tower crane mast.
The problem is that it takes time and money.

さらに、従来の積層工法の場合は、まず地下躯体工事を
完成し、次いで地−L鉄骨工事に着手するのが通例の手
順であり、工程のラップ(並行着r、)ができないため
、下期の短縮にネックとなっている。
Furthermore, in the case of the conventional layered construction method, the usual procedure is to first complete the underground structure work and then start the underground steel frame work, which makes it impossible to wrap the process (parallel construction). Shortening has become a bottleneck.

したがって、本発明の目的は、りly−ンの吊り能力を
作業半径の大小に区分して効率的に使用することでその
実質必要台数を減らすこと、及び・箇所に隼申して配置
された耐力が大きいコア部にクレーンを設置することに
よってクレーンマストの支持を必要1分になさしめ、ま
た、コア部の構築を先行することでコア部に集中する設
備、トイレ、エレベータ等のニ「事の早期着手を可能な
らしめ建築施工の工期短縮と安全性の向−1−が図れる
ように改良したコア部先行型建築下法を提供することで
ある。
Therefore, an object of the present invention is to reduce the actual number of lynes required by dividing the lifting capacity of lynes into large and small working radii and use them efficiently; By installing the crane in the core area, which has a large core area, the crane mast can be supported in just one minute.Also, by constructing the core area in advance, it is possible to eliminate the need for equipment, toilets, elevators, etc. that are concentrated in the core area. It is an object of the present invention to provide a core part advance construction method that has been improved so as to enable early start, shorten the construction period, and improve safety.

課題を解決するための手段 1−4記従来技術の課題を解決するための手段として、
この発明に係るコア部先行型建築工法は、図面の第1図
〜第5図に好適な実施例を示したとおり、 剛強な耐力構造のコア部Aの外周に外周部鉄骨柱と梁及
び壁板などによる外殻構造部分Bが複合的に構築されて
成る高層及び超高層建物の建築工法において、 コア部Aにタワークレーン1を設装置し、同タワークレ
ーン1を使用してコア部1の鉄骨建方及びコア部躯体工
事を先行して最−L階まで行ない、しかる後に前記のタ
ワークレーン1を使用して外殻構造部分Bの外周部鉄骨
建方及び外周部躯体工事を行なうことを特徴とする。
Means for Solving the Problems 1-4 As a means for solving the problems of the prior art,
As shown in preferred embodiments in FIGS. 1 to 5 of the drawings, the core-based construction method according to the present invention includes steel columns, beams, and walls on the outer periphery of the core portion A, which has a strong load-bearing structure. In a construction method for high-rise and super high-rise buildings in which an outer shell structure part B made of boards or the like is constructed in a composite manner, a tower crane 1 is installed in the core part A, and the tower crane 1 is used to move the core part 1. Steel frame erection and core structure work will be carried out up to the Lth floor in advance, and then the outer peripheral steel frame construction and outer peripheral structure work of outer shell structure portion B will be carried out using the tower crane 1. Features.

なお、上記のコア部先行型建築工法において、コア部1
の鉄骨柱3は支持杭の鉄骨と接合して建て、地上におけ
るコア部lの構築と、根切り工事及び地F階構造部分C
の構築とは並行して行なうことも特徴とする。
In addition, in the above-mentioned core part advance construction method, core part 1
The steel frame column 3 was built by connecting it with the steel frame of the support pile, and the construction of the core part l on the ground, the root cutting work, and the structural part C of the basement F floor were carried out.
It is also characterized by the fact that it is carried out in parallel with the construction of.

作     用 コア部Aにタワーり1/−ン1を設置するので、同タワ
ークレーンlのマストは耐力が大きいコア部Aにて強固
に支持され、クレーンマストの支持のための補強などは
−・切必要としない。
Since the tower crane 1/-1 is installed in the working core part A, the mast of the tower crane 1 is firmly supported by the core part A, which has a large bearing capacity, and reinforcement for supporting the crane mast is... Not desperately needed.

コア部Aの鉄骨建方及びコア部躯体]「事は外殻構造部
分Bに先行して独立に行なうので、コア部Aの資材類は
、コア部A外周の本来なら外殻構造部分Bの平面内であ
るべき位置に置いてこれをタワークレーン1で吊り込む
ことができる。従って、コア部Aの資材類はタワークレ
ーン1の作業半径か比較的小さい範囲内で吊ることがで
き、その917部鉄骨は1ピースをかなり大形、大重量
のものとして吊り込むことができる。よって、高所での
鉄骨等のジヨイント数を減らすことができるのである。
Steel frame erection of core part A and core part frame] ``Because the work is carried out independently before and independently of the outer shell structure part B, the materials of the core part A are the same as those of the outer shell structure part B, which should be on the outer periphery of the core part A. It is possible to place it at a position within a plane and lift it with the tower crane 1. Therefore, the materials of the core part A can be lifted within a relatively small range of the working radius of the tower crane 1, and its 917 One piece of steel frame can be suspended as a fairly large and heavy piece.Therefore, the number of joints of steel frames etc. at high places can be reduced.

一方、外殻構造部分Bたる外周部鉄骨建方及び外周部躯
体工事を行なう場合、その資材類は建物平面の外周敷地
(空地)に置くほかはないが、この外周部鉄骨及び外周
1m体部材は本来1ピースか比較的1量小形のものであ
るため、タワークレーンによる大きな作業半径での吊り
込みにも格別支障はないのである。
On the other hand, when constructing the outer steel frame and constructing the outer frame, which is the outer shell structure part B, the materials must be placed on the outer site (open space) of the building plane, but the outer steel frame and the 1m outer frame members Since it is originally one piece or relatively small in size, there is no particular problem in lifting it with a tower crane in a large working radius.

要するに、タワークレーン1はその吊り能力と作業半径
とに適合した形で効率良く使い分けられるので、ひいて
はタワークレーン1の台数を汎用機縁のままで減らすこ
とかできる。その結果、ブームが屯なり合う作業範囲は
小さく(第5図)、ブームがかち合う作業は少ないので
、作業順序の自由度及び作業の安全性が高まる。
In short, the tower cranes 1 can be used efficiently depending on their lifting capacity and working radius, so that the number of tower cranes 1 can be reduced while still being a general-purpose machine. As a result, the working range in which the booms overlap is small (FIG. 5), and there are few tasks in which the booms overlap, increasing the degree of freedom in the work order and the safety of the work.

次に、コア部Aの地IL鉄骨工事と地下躯体工事とは並
行してtJなうことができ雫期着手できるので、1」U
lの短縮が図れる。また、コア部Aと外殻構造部分Bの
作業上程とは時間的に大きく前後にずれているので、資
材類の搬入やその管理あるいは置場の確保かきちんと整
理され、混乱によるミスや時間のロスを防げる。
Next, the ground IL steel frame work and underground structure work for core part A can be done in parallel and can be started during the rainy season, so 1"U
It is possible to shorten l. In addition, since there is a large time lag between the work schedule for the core part A and the outer shell structure part B, it is important to ensure that materials are brought in, managed, and stored in a well-organized manner, resulting in mistakes and time loss due to confusion. can be prevented.

先行して構築されたコア部A内には、施工期間か長くか
かるトイレや設備、エレベータ、階段などの工事を甲期
に着fでき、かつこれらを実用に供し得るので、逆に仮
設エレベータやリフトの早期解体が可能である。
In the core part A, which was constructed in advance, construction work such as toilets, equipment, elevators, stairs, etc., which would take a long time to construct, could be completed in the first stage, and these could be put to practical use. Early dismantling of the lift is possible.

実  施 例 次に、図示した本発明の詳細な説明する。Example The illustrated invention will now be described in detail.

第1図〜第4図は本発明に係るコア部先行型建築工法の
枢要な工程図を示している。
1 to 4 show important process diagrams of the core-advanced construction method according to the present invention.

まず第1図は、支持杭及び山留め用の連続地下壁6(第
2図参照)の施工後に、地上のクローラフ1/−ン2を
使用してコア部Aの鉄骨建方を行ない、同コア部A内に
大型のタワークレーンlを設置した初期段階を示してい
る。タワークレーン1は、第5図に作業平面図を示した
とおり、2基で建物全平面の揚重作業をカバーできるよ
うに、かつその旋回中心01をコア部A内に位置せしめ
て設置されている。
First of all, Fig. 1 shows that after the construction of the continuous underground wall 6 (see Fig. 2) for supporting piles and mountain retaining, the steel frame of the core part A is erected using crawler rough 1/-2 on the ground. This figure shows the initial stage of installing a large tower crane in Section A. As shown in the working plan view in Fig. 5, the tower crane 1 is installed so that two units can cover the lifting work of the entire plane of the building, and with its rotation center 01 located within the core part A. There is.

コア部Aの鉄骨柱3は、支持杭の鉄骨と接合して建てら
れている。このコア部Aは、構造上大形重量鉄骨で架構
され耐力が非常に大きいので、大型タワークレーン1の
マスト1aの支持あるいはクライミングにも格別の補強
を必要としないのである。
The steel column 3 of the core part A is connected to the steel frame of the support pile. Since this core part A is structurally constructed of a large heavy steel frame and has a very high strength, no special reinforcement is required for supporting or climbing the mast 1a of the large tower crane 1.

第2図は、前記タワークレーン1を使用してコア部Aの
鉄骨建方及びコア部躯体工事を進めると同面に、その一
方ではタラムシエル4やバックホー5などによる根切り
工事を行ない、地下階躯体部分りの構築を並行して進め
ている段階を示している。未刊けも行なわれる。図中6
が建物躯体と山留めを兼ねて施工された連続地下壁であ
る。
Figure 2 shows that while the tower crane 1 is being used to proceed with the erection of the steel frame of the core section A and the construction of the core section, at the same time, root cutting work is being carried out using the Taramsiel 4, backhoe 5, etc., and the underground floor This shows the stage in which the construction of the main body is proceeding in parallel. Unpublished works will also be held. 6 in the diagram
This is a continuous underground wall that was constructed to serve both as the building frame and as a retainer.

第3図は、タワークレーン1をクライミングさせてコア
部への鉄骨建方及びコア部躯体工事を最」二階まで先行
して構築を完成した段階を示している。この場合、地−
1−3階に相当する外殻構造部分Bの床7を資材置場と
して利用し、この」−へ搬入したコア部Aの構造資料類
をタワークレーン1で吊り1−げてコア部Aの構築作業
が行なわれている。従って、タワークレーン1は比較的
小さい作業半径で揚重作業に使用され、最大i s +
−ンぐらいの吊り能力を期待できるので、1ピースの鉄
骨重量は大きくてもよい訳である。したがって、1ピー
スを地上で大きく地組みしておくことによりジヨイント
数を減らし高所のジヨイント作業に数を減らすことがで
きる。
FIG. 3 shows the stage where the tower crane 1 is used to climb the structure, and the steel frame is erected to the core section and the core section construction work is completed up to the second floor. In this case, the ground
The floor 7 of the outer shell structure part B, which corresponds to the 1st to 3rd floors, will be used as a material storage area, and the structural materials of the core part A carried into this area will be hoisted up by the tower crane 1 to construct the core part A. work is being done. Therefore, the tower crane 1 is used for lifting operations with a relatively small working radius, up to i s +
The weight of each piece of steel frame can be large, since the lifting capacity can be expected to be approximately 100-1000 yen. Therefore, by assembling one piece into a large piece on the ground, it is possible to reduce the number of joints and reduce the number of joints required for work at high places.

また、前記地J−3階の外殻構造部分Bの床7の下の空
間9は資材M搬トラックなどの大きな通路として構成さ
れているので、地下階構造部分りの構築その他の関連作
業の遂行には一切支障を生じない。
In addition, since the space 9 under the floor 7 of the outer shell structure part B on the J-3rd floor is configured as a large passageway for materials M transport trucks, etc., the space 9 under the floor 7 of the outer shell structure part B on the J-3rd floor is configured as a large passageway for materials M transportation trucks, etc. There will be no hindrance to its execution.

コア部Aの構築と共に同コア部Aに設置するべき設備類
、トイレ、エレベータなどの工事にV期着手し並行作業
として進める。そして、不要になった仮設のエレベータ
やリフトは7期に解体撤去する。
Along with the construction of core section A, construction work on equipment, toilets, elevators, etc. to be installed in core section A will begin in phase V and will be carried out in parallel. Temporary elevators and lifts that are no longer needed will be dismantled and removed in the seventh phase.

第4図は、コア部Aを先行して最上階までの構築を完成
した後、同じタワークレーン1を使用して外殻構造部分
Bの外周部鉄骨8などを吊り込み、外周部鉄骨建方及び
外周部躯体工事を行なって外殻構造部分Bの構築を進め
る途中の段階を示]7ている。この場合、外殻構造部分
Bの資材類は建物平面の外周敷地(空地)内に置いて、
これをタワークレーン1で吊り込むことになるが、外周
部鉄骨8及び外周部躯体部材(PCa板)などは本来1
ピースが比較的軽量なので、タワークレーンlの最大作
業半径による吊り込みでも吊り能力に不足は生じないの
である。
Figure 4 shows that after the construction of the core part A is completed up to the top floor, the same tower crane 1 is used to lift the outer steel frame 8 of the outer shell structure part B, and the outer steel frame is erected. [7] shows the stage in the middle of construction of the outer shell structure part B by carrying out construction of the outer peripheral frame. In this case, the materials for the outer shell structure part B are placed within the outer perimeter site (open space) of the building plane,
This will be lifted by the tower crane 1, but the outer peripheral steel frame 8 and outer peripheral frame members (PCa plates) should originally be lifted by the tower crane 1.
Since the pieces are relatively lightweight, there is no shortage of lifting capacity even when lifting with the maximum working radius of the tower crane I.

本発明が奏する効果 以上に実施例と併せて詳述したとおりであって、この発
明に係るコア部先行型建築工法によれば、汎用縁の大型
タワークレーン1の使用台数を最少数に減らしてコスト
の節減を図れるほか、耐力が大きいコア部Aにタワーク
レーン1を設置し、コア部Aの構築の進捗に応じて同コ
ア部A内に未設用のエレベータや設備類、トイレ、階段
を設置してその先行利用ができるので、これらにより仮
設工事及び仮設費の節減が促進される。
As described in detail in conjunction with the embodiments, the effects of the present invention are as follows.According to the core-advanced construction method according to the present invention, the number of general-purpose large-scale tower cranes 1 to be used can be reduced to the minimum number. In addition to reducing costs, the tower crane 1 can be installed in the core part A, which has a large bearing capacity, and as the construction progresses in the core part A, uninstalled elevators, equipment, toilets, and stairs can be installed in the core part A. Since they can be installed and used in advance, they facilitate the reduction of temporary construction work and temporary construction costs.

また、コア部Aの構築工程と外殻構造部分Bの構築工程
とが時間的に大きく前後にずれていて、各々に必要な構
造資材類の現場への搬入時期が大きく前後にずれるので
、資材類の調達やその管理及び置場スペースの確保など
が極めて容易で、誤認混同のおそれがない。したがって
、安全施工にも寄与するのである。
In addition, the construction process of the core part A and the construction process of the outer shell structure part B are significantly different in time, and the timing of delivering the necessary structural materials to the site is also significantly different. It is extremely easy to procure materials, manage them, secure storage space, etc., and there is no risk of misidentification or confusion. Therefore, it also contributes to safe construction.

さらに、コア部Aの地上鉄骨と地下階構造部分りの地下
躯体工事とを並行して早期着手でき、また、コア部Aの
構築が進むことにより設備類やエレベータ、トイレ等の
早期着手が行なえるので、工期を数カ月短縮することに
も寄与するのである。
Furthermore, construction of the above-ground steel frame for core section A and the underground structure for the basement floor structure can be started at an early stage in parallel, and as construction of core section A progresses, equipment, elevators, toilets, etc. can be started at an early stage. This also contributes to shortening the construction period by several months.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第4図は本発明に係るコア部先行型建築工法の
枢要な工程を示した立面図、第5図はタワークレーンの
配置を示した平面図、第6図は従来のタワークレーンの
配置を示した平面図である。 A・・・コア部      B・・・外殻構造部分l・
・・タワークレーン  8・・・外周部鉄骨第1図 夕 第4図 第3図
Figures 1 to 4 are elevational views showing the important steps of the core-advanced construction method according to the present invention, Figure 5 is a plan view showing the arrangement of tower cranes, and Figure 6 is a conventional tower construction method. FIG. 3 is a plan view showing the arrangement of cranes. A...Core part B...Outer shell structure part l.
... Tower crane 8 ... Outer steel frame Figure 1 Figure 4 Figure 3

Claims (1)

【特許請求の範囲】 【1】剛強なコア部の外周に外周部鉄骨柱と梁及び壁板
などによる外殻構造部分が構築されて成る高層建物の建
築工法において、 コア部にタワークレーンを設置し、同タワークレーンを
使用してコア部鉄骨建方及びコア部躯体工事を先行して
最上階まで行ない、 しかる後に前記タワークレーンを使用して外殻構造部分
の外周部鉄骨建方及び外周部躯体工事を行なうこと、 を特徴とするコア部先行型建築工法。 【2】コア部の鉄骨柱は支持杭の鉄骨と接合して建て、
地上におけるコア部の構築と、根切り工事及び地下階構
造部分の躯体工事とを並行して行なうことを特徴とする
特許請求の範囲第1項に記載したコア部先行型建築工法
[Scope of Claims] [1] In a construction method for a high-rise building in which an outer shell structure including peripheral steel columns, beams, wall plates, etc. is constructed around the outer periphery of a strong core, a tower crane is installed in the core. Then, the same tower crane was used to construct the core steel frame and the core structure up to the top floor in advance, and then the tower crane was used to construct the outer steel frame of the outer shell structure and construct the outer circumference. A core construction method that is characterized by carrying out frame work. [2] The core steel column is connected to the steel frame of the support pile, and
1. The core part-first construction method as set forth in claim 1, wherein the construction of the core part above ground, the root cutting work, and the frame work of the underground floor structure part are carried out in parallel.
JP63092488A 1988-04-14 1988-04-14 Core leading construction method Expired - Fee Related JP2668237B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP63092488A JP2668237B2 (en) 1988-04-14 1988-04-14 Core leading construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP63092488A JP2668237B2 (en) 1988-04-14 1988-04-14 Core leading construction method

Publications (2)

Publication Number Publication Date
JPH01263334A true JPH01263334A (en) 1989-10-19
JP2668237B2 JP2668237B2 (en) 1997-10-27

Family

ID=14055686

Family Applications (1)

Application Number Title Priority Date Filing Date
JP63092488A Expired - Fee Related JP2668237B2 (en) 1988-04-14 1988-04-14 Core leading construction method

Country Status (1)

Country Link
JP (1) JP2668237B2 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04317976A (en) * 1991-04-16 1992-11-09 Ohbayashi Corp Method for constructing elevator shaft
KR20020041064A (en) * 2000-11-27 2002-06-01 김희, 이방주 Pc core pre-construction method
CN102787720A (en) * 2011-05-20 2012-11-21 上海庞源机械租赁股份有限公司 Externally attached built-in tower crane fixing structure
CN102797292A (en) * 2012-09-10 2012-11-28 中国建筑第二工程局有限公司 Large-diameter spherical steel structure and super-altitude installation method thereof
CN103046753A (en) * 2011-10-13 2013-04-17 永升建设集团有限公司 Overhanging base frame construction method adopting U-shaped fastener
CN112482561A (en) * 2020-12-02 2021-03-12 上海席得建筑设计有限公司 Wall structure attaches in core section of thick bamboo

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS621954A (en) * 1985-06-27 1987-01-07 鹿島建設株式会社 Construction of housing of building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS621954A (en) * 1985-06-27 1987-01-07 鹿島建設株式会社 Construction of housing of building

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04317976A (en) * 1991-04-16 1992-11-09 Ohbayashi Corp Method for constructing elevator shaft
KR20020041064A (en) * 2000-11-27 2002-06-01 김희, 이방주 Pc core pre-construction method
CN102787720A (en) * 2011-05-20 2012-11-21 上海庞源机械租赁股份有限公司 Externally attached built-in tower crane fixing structure
CN103046753A (en) * 2011-10-13 2013-04-17 永升建设集团有限公司 Overhanging base frame construction method adopting U-shaped fastener
CN102797292A (en) * 2012-09-10 2012-11-28 中国建筑第二工程局有限公司 Large-diameter spherical steel structure and super-altitude installation method thereof
CN112482561A (en) * 2020-12-02 2021-03-12 上海席得建筑设计有限公司 Wall structure attaches in core section of thick bamboo

Also Published As

Publication number Publication date
JP2668237B2 (en) 1997-10-27

Similar Documents

Publication Publication Date Title
US3895473A (en) Process for the manufacture of low cost housing at the site
CN107090932A (en) Large span thin-walled planar based on stiffness ring beam encircles the construction method of truss
CN106894639A (en) The hanging reverse construction method of installation of steel construction under a kind of
CN114232805B (en) Construction method of ultrahigh-height large-span steel concrete beam hanging structure
AU761901B2 (en) Method for the production of high, large diameter towers in sliding molding
JPH01263334A (en) Core part precedence type construction method
CN107269085A (en) A kind of construction method of large-diameter concrete silo top conical shell structure
US4312167A (en) Method of constructing a storage tank
CN110589690B (en) Climbing method of internal climbing tower crane in narrow space
JPH09317183A (en) Construction method of building
CN114134991B (en) High-rise building construction method with conversion structure
CN114961335A (en) Demolition construction method for large-span reinforced concrete supporting beam
JPH0483060A (en) Building construction
US3552080A (en) Method for erecting multistory buildings
JP2761528B2 (en) How to build structures
CN218714838U (en) Self-lifting heavy-load construction platform
CN215479362U (en) Lifting type protection platform
JP2008169676A (en) Construction method of tower-like structure
CN115744693A (en) Recyclable assembled type dado lifting and dismantling method for expanded-base foundation pit
SU977176A1 (en) Apparatus for installing underground reinforced concrete vessels
JPH0527744B2 (en)
JPS63312437A (en) Construction of underground structure
JPH0742179A (en) Modified inversion placing construction method
JP3002054U (en) Tower crane with multiple main columns as tower mast
CN115506563A (en) Self-lifting heavy-load construction platform and construction method thereof

Legal Events

Date Code Title Description
LAPS Cancellation because of no payment of annual fees