JPH0437893B2 - - Google Patents

Info

Publication number
JPH0437893B2
JPH0437893B2 JP23528584A JP23528584A JPH0437893B2 JP H0437893 B2 JPH0437893 B2 JP H0437893B2 JP 23528584 A JP23528584 A JP 23528584A JP 23528584 A JP23528584 A JP 23528584A JP H0437893 B2 JPH0437893 B2 JP H0437893B2
Authority
JP
Japan
Prior art keywords
formwork
slab
wall
floor
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired
Application number
JP23528584A
Other languages
Japanese (ja)
Other versions
JPS61113965A (en
Inventor
Hidejiro Kawanishi
Toshinosuke Ootani
Bunji Machi
Kinro Ogasawara
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Original Assignee
Shimizu Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd filed Critical Shimizu Construction Co Ltd
Priority to JP23528584A priority Critical patent/JPS61113965A/en
Publication of JPS61113965A publication Critical patent/JPS61113965A/en
Publication of JPH0437893B2 publication Critical patent/JPH0437893B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 産業上の利用分野 本発明は鉄筋コンクリート造の建築物の構築工
法にかかり、詳しくは建築物が壁式構造である場
合における壁体と各階床版の施工方法及びその工
法に用いられる構築用装置に関するものである。 一般に壁式構造は各階の平面構成が下階から上
階にかけて比較的変化が少く、中高層規模の建築
物に採用される方式であつて、柱、梁の架構によ
る軸組構造部を耐力壁の組合わせにおきかえるも
のであることから、主体となる鉄筋コンクリート
の構築にあたつてはその型枠計画と施工方法に特
徴がある分野とされている。 従つて型枠を規格のものとし、工場生産とする
いわゆるプレハブ工法が多用される面も多いが、
一方において多量生産の条件が具備されない個別
の独立建築物にあつては、現場打ちのコンクリー
トによる構築方法は依然として一つの主流となつ
ている。 従来の技術 コンクリート工事では、現場打ち工法による場
合にはとくに型枠工事に伴う足場の計画が重要な
工程上の問題点となる。高層、中層の壁式構造の
建築物にあつては、内外面のコンクリート型枠と
内部足場外部足場は一体のものとして計画され、
通常は1階分ごとの施工の進行に伴つて、コンク
リートの打設工程に合わせて足場付の型枠を上昇
させ、または特殊な状況下では型枠を連続して上
昇させる滑揚型枠工法が採用されている。即ち、
壁体部分を既設部分に支持させて上方に進行させ
ることによつて工程の垂直方向への合理化を図つ
ているのである。しかしながら、かかる従来工法
では、床コンクリートの施工のために、上記とは
別個に床コンクリート及びその支保支柱の打設の
水平及び垂直方向の工程が介入する。したがつ
て、上述のように壁体工程の垂直方向への合理化
による利点を最大限に発揮させるには、床コンク
リート施工の面でさらに工夫が必要とされてい
る。 一方、工事現場で使用される揚重設備は、各種
形式のクレーンを用いるほか、架台を用いてその
上面に揚重設備を装備し、揚程では制限を受けな
がら安定した吊持ちが可能な面で活用され、クレ
ーンの大型化に対処されていた。 発明が解決しようとする問題点 また、従来の工法では床コンクリートを現場打
ちとする場合スラブ下面の支保支柱がコンクリー
ト硬化の制約を受けて作業工程に影響するばかり
でなく作業の妨害となる欠点があつた。また、ス
ラブをプレハブ、コンクリート板とする工法で
は、上記欠点は避けられるとしても、必ず大型の
揚重設備を要することとなり、工事現場の規模に
よつては設置場所に制約を受けたり、高揚程のも
のが要求されたりして工事原価に影響し、あるい
は稼動効率を低下させることとなつていた。 したがつて従来工法の難点は、前記したような
垂直方向の壁体の施工に対して、水平方向のスラ
ブの施工が常に工程計画を複雑にする点にあり、
主としてスラブの施工を合理化された壁体の施工
法に対応させる新しい工法が望まれていた。 問題点を解決するための手段 そこで本発明においては、壁式構造の壁体を構
成するコンクリートの構築は、足場付の外部型枠
と内部側の型枠とを大型のパネルに構成して1階
分ごとに順次に揚昇する工法によるとともに、壁
体の内側に壁体に接して支柱を立て、その頂部を
連結する梁によつて架台を構成し、この架台には
移動可能に揚重器を設け、スラブ用の型枠を懸垂
装備することによつて壁体の構築と上方における
スラブPC版の製作を前後して平行に行えるよう
にし、この架台もコンクリートの構築進行にとも
なつて上昇させる一連の工法とすることを要旨と
するものであつて、これによつて内部型枠の上昇
を可能にするとともに大型クレーンの設置を不要
とし、壁体と床スラブとの平行構築によつて工期
の短縮と労務の省力化を企図することができる効
果を達成しようとするものであり、そのためにさ
らに、その工法に用いられる構築用の装置を提供
しようとするものである。 実施例 以下図面に示す本発明の一実施例について本発
明を詳細に説明する。 第1図は本発明の壁式構造建築物の構築工法を
実施する態様を示すもので、1は構築される壁式
構造の建築物1Aの室空間であり、2,3は構築
済みの壁体とスラブとを示している。2A,3A
はスラブ3上の当該階において構築される壁体と
直上階用のスラブであつて、通常は1階分の工程
で施工される。 4は壁体構築のためのコンクリート用外部型枠
であつて、外方に上下2段の外部作業足場41を
設けてあり、大型の型枠パネルに形成され、壁体
外面に沿つて連設される。 5は同じくコンクリート用の内部型枠であつ
て、同様に大型の型枠パネルに形成され、脚部5
1によつてスラブ3上に据付けられる。 6は内外の大型型枠の相互をコンクリートの打
設に備えて緊結する多数のセパレータであり、7
は既設コンクリート部分2に外部型枠4を自立可
能に支持固定する固定ボルトである。 8は壁体2のコンクリート中に埋設された補強
鉄筋であつて通常は複筋に構成されて先組された
組立体として使用される。 次には本発明の主要構築装置となる架台であ
つて、支柱10,10頂部間に梁装置11を架け
わたして台形の鉄骨架構に構成される。ここで各
柱10は例えばH形鋼−300×300×10を用い、第
2図に示すように、壁体2で囲まれる室空間1の
内部に、一方のフランジを壁体2の内側に接して
各辺の中央部に菱形を形成して配置され、その高
さは建築物の3階分以上に選び、当該階の下階か
ら立設させ、壁体2に植設したボルト12,12
によつて壁体2に固定され、それぞれに自立して
いる。 次に13は前記室空間の4隅部に配置されるガ
イド柱であつて、柱10と同じ材料を使用し、同
様に下階から立設されているが、スラブ3Aの面
積を広くするのに障害にならないように、高さは
当該階における内外型枠5,4と同一レベルとし
てある。 前記梁装置11は第3図に示すように、柱1
0,10に対応して菱形に組まれた4本の梁14
と、梁14に固着支持されて室空間1の対角線方
向に配置された2本の梁15とからなり、梁1
4,14の会合点において柱10に対して着脱自
在に架設されることによつて架台を構成する。
ここで梁14は例えばH型鋼250×250×9とし、
梁15はI型鋼−300×150×10に選ばれる。梁1
5は下弦フランジにトロリーホイストTを走行自
在に装着して走行梁となつており、その駆動操作
は、前記外部作業足場41から行えるように配線
16する。かくして、支柱10と梁装置11とが
結合されたときには架台は揚重設備を兼ねる構
築装置を構成する。 第1図においては、スラブ3Aは架台からト
ロリーホイストTによつて吊持されており、小梁
付きに設計されたスラブ3Aは下面型枠17,1
7Aによつて構築される。そして、このスラブ3
Aを構築する高さにおいて、各支柱10の中段部
の内側には鉄骨のスラブ受梁18が枢着されてお
り、内方に張り出してスラブ型枠17を下面から
支持する片持梁の位置と、下方に垂下して柱10
に沿つて折りたたまれる位置との2つの姿勢をと
るように固定または枢動自在に構成されて、架台
9の構成の一部となつている。ここで構築された
スラブ3Aは第3図に示されるように、スラブの
上方に貫通して存在する柱10,10、ガイド柱
13に臨む部分に所定の切欠き19を有してお
り、各柱とスラブとの相対移動を許すようになつ
ている。なお第1図中の20,20は既施のスラ
ブ3の支保用の支柱であつて、上記切欠き19を
後刻補充してスラブを完成させるときにも使用さ
れる。 以上によつて代表的な実施例について説明した
が、室空間1の上方で製作されるスラブ3Aには
設計変更が可能であり、柱10,13に臨む部分
に構造上の問題があるときには切欠き19を設け
ず、内部型枠5の大型型枠を小形部分に分解組立
可能に構成して、スラブ3Aの水平移動を行うこ
となく、小形の型枠部材として移動上昇させるこ
とも可能である。 作 用 本発明の壁式構造建築物の構築工法は、前記実
施例の構築装置を使用して建築物1Aを構築する
ときの作用として第1図および第4図以下の工程
図によつて説明される。ただし、各図面では複数
の時点における実施の態様が一部重複して表現さ
れている点がある。 まず第1図の状態では当該階のスラブ3のレベ
ルにおいて、外壁2の構築のための外部型枠4と
内部型枠5がセツトされ、両者間にコンクリート
が打設されて壁体2Aが構築されている。一方、
スラブ3の上方においては架台の支持のもと
で、当階の施工の一環としての上階のスラブ3A
が壁体2Aと平行した作業で構築されている。本
発明の基本の構成がこの平行作業であるから、こ
の段階からの工程を第1,4〜10図にもとづい
て上階への一連の工程のサイクルとして説明す
る。 (1) まず打設された壁体2Aに硬化期間をおいた
のち、内部型枠5を脱型する。型枠5の脚部5
1は折りたたみ式または着脱式とされていてス
ラブ3上での控えをはずし内部型枠5の厚さを
減じ、ついで緊結金物6をはずす。 (2) 第4図ではスラブ3Aが上方からトロリーホ
イストTで吊り下げられており、外部足場4上
からの操作によつてその吊持のまま図上の右方
に移動させられる。このとき、スラブ3Aの左
端の端縁が柱10の内方に移動して、内部型枠
5の上方にその厚さに余猶を加えた寸法の空所
を生じ、かつ、スラブ3Aの右端の対辺と図上
の前後方向の側辺に設けた切欠き19がそれぞ
れ柱10と衝接しない範囲の移動が行われる。 (3) そこで建設現場内に別個に設けられた工事用
の揚重設備例えばタワークレーンCによつて内
部型枠5を大型パネルのまま吊りあげる。この
吊りあげは支柱10とガイド柱13の側面の溝
形もしくは溝形とフランジとを利用してガイド
させながら行い、型枠5の下端がスラブ3Aの
高さを越えたところで支柱10側から片持ち仮
支持させ、他端側には補助支線を設けて支持す
ることとする。 (4) 次に第5図から明らかなように、上記(2)の工
程を逆方向即ち図上の左方向に実施して、右側
の内部型枠5の上方にスラブ3Aをかわす空間
を形成させ、上記(3)と同様に右側の内部型枠5
を上昇させる。 (5) 第4図ではスラブ3Aの上面に、次の上階の
スラブを構築するための資機材17Bが積載さ
れていて、これらの準備作業も上記工程と平行
して行われる。 (6) 第6図はスラブ3Aの設置の工程を示す。架
の所定上方位置で製作されたプレキヤスト
コンクリートのスラブ3Aはトロリーホイスト
Tによつて吊りさげられ、簡易に移動されたの
ち、製作当初の中央の正規の位置に戻され、そ
こでホイストTの昇降操作によつて下降させら
れる。スラブ3Aは所定の寸法に製作されて周
囲の壁体2Aの上端に着座させられ、ついで下
面型枠17,17Aを順次脱型させられ、また
一方において下方のスラブ3から支持用支柱2
0を施して支持させることにより、トロリーホ
イストTによる吊持を解除することが可能にな
るとともに、以後の作業における積載荷重をも
支持可能となる。 (7) 第7図では新しい上階での作業を説明する。
この段階ではスラブ3Aの階での内部型枠5の
設置が行われる。外部クレーンCによつて再び
内部型枠5を吊持し、その保持のもとで支柱1
0による仮支持を解き、内部型枠5をスラブ3
A上に下降させ、脚部51を用いて所定位置に
設置する。 (8) 一方、スラブ3A上では資機材17Bを使用
して新しい上階のスラブ3Bのための型枠を構
築する。17Cは作業員の頭上に高さを確保す
る枠組足場等を用いた台であり、17Dはスラ
ブ3AからHの高さに設置されるスラブ3Bの
ための下面型枠であつて、大引、根太など公知
の構成を持つている。ここでHとして定められ
る高さは、トロリーホイストTの作動揚程とと
もに支柱10の高さを決定する基準とされるも
のである。 (9) これらの工程に前後して、さらに梁装置11
の移動が行われる。即ち梁装置11は各支柱1
0との結合を解かれたのち、クレーンCによつ
て吊り下げられ、一連の治具として隣位の室空
間の上方に位動させられ転用がはかられるとと
もに作業空間の上方を全く自由とする。 (10) 壁体2Aとスラブ3Aの結合は、壁体2A中
の鉄筋8の延長部とスラブ3Aの端縁に設けら
れるコツターまたはスラブ鉄筋の延長などとの
結合によつてこの段階で準備される。 第8図に示される主工程は、各支柱10,1
0とガイド柱13の上昇ならびにスラブと壁体
への鉄筋配筋である。 (11) 各支柱10の上昇は、先行階における固定ボ
ルト12の解除からはじまり、梁装置11を解
離した頂部においてクレーンCによつて吊り上
げ、1階分上昇させてからあらためて壁体2A
の固定ボルト12でスラブ3上で壁体2Aに固
定する。この間に支柱10は内部型枠5によつ
て相対的にガイドされるから、上昇は安定して
円滑に行われる。ガイド柱13の上昇も支柱1
0の場合と同様である。 (12) スラブ構築のこの段階での作業は配筋であつ
て、地上で先組みされたスラブ鉄筋21を型枠
17D上に配置する。 (13) 壁体2の構築にはまず内部型枠5の外面にお
いて鉄筋を配筋する。それには地上で先組みさ
れた鉄筋8AをクレーンCで吊り上げ、下方の
鉄筋8の上部と接続する。 (14) 内外部の型枠を順次に1階分ごとに上昇させ
るいわゆる「ジヤンプアツプ」型枠工法では次
段の外部型枠4の上昇も上記(13)の工程と一連に
周知であつて、外部型枠4は下方の固定ボルト
7をはずし、外部型枠4を大型の型枠に組み足
場をつけたままクレーンCで吊り上げて上昇さ
せ、壁体2Aの固定ボルト7に盛り替えること
によつて行なわれる(第9図)。 (15) 第9図にはさらにスラブ3Bの構築工程が示
されている。即ち、クレーンCによつて再び梁
装置11を吊り、他工区から当工区に復帰させ
て支柱10,10に組付け架台を形成させ
る。そして走行梁15上でトロリーホイストT
を移動させて型枠17Dを吊り、1階高分上昇
させる。ついで型枠17Dを支柱10、梁14
等からワイヤーロープWによつて吊支させると
ともに、各支柱10のスラブ受梁18,18を
枢着点で上方に回転させ、型枠17Dを下方か
ら支持する姿勢で固定する。これによつてスラ
ブ3Bのプレハブ工の準備を完了するので、型
枠17D上にコンクリートを打設すればプレキ
ヤスト・コンクリートのスラブ3Bの製作が終
了する。スラブ3Bの養生にはスラブ3Aから
支柱20を立て、さらに上面に被覆体Sをかぶ
せ内部に蒸気を通し、蒸気養生を加えてスラブ
コンクリートとしての強度を早期に発現させる
のが望ましい。 (16) 第10図は最終工程を示す図面であつて、上
方のスラブ3Bは養生中であり、壁体2Aの上
方において、外部型枠4と内部型枠5を緊結し
て壁体2Bのコンクリートが打設される。この
打設作業は実質的にはスラブ3Bのコンクリー
トの蒸気養生と壁体コンクリートの硬化とのタ
イミングをはかつて前後して行われる。そして
このコンクリート打設によつて壁体2Aとスラ
ブ3Aとの結合も同時に完了する。 (17) ついでスラブ受梁18を下方に枢動させ、ワ
イヤWを解除し、支柱20を徹去すれば、スラ
ブ3Aのレルを基準とする第1図と同じ状態と
なり、同様の工程を上方に繰返す構築工法が一
連のサイクルとして実施できる。こうして、本
発明の構築工法では、壁体部分の現場打ちコン
クリート工事と、室空間上方におけるスラブ部
分のプレキヤストコンクリート工事とを、一連
の「平行作業」として達成させるものである。 なお実施例の項で説明したスラブの構成におけ
る切欠き19の変化については、前記の工程中(2)
〜(4)のスラブの水平移動は行われず、内部型枠5
の脱型後の上階への盛り替えは、上方に上昇空間
が得られないことから、内部型枠5を小形部分に
分解し、小運搬によつて実施することができる。 発明の効果 本発明の構築工法では、壁体用型枠の設置と同
時にその上方階にてプレキヤストコンクリート床
スラブ構築用のスラブ型枠を組むことができるの
で、壁コンクリートの打設と同時にその直上階の
プレキヤストコンクリート床スラブ製作を平行し
て実施することができ、このため工期の短縮が顕
著であり、しかも、プレキヤストコンクリート床
スラブ製作を建築物内の限られたスースの中で達
成でき、プレキヤストコンクリート床スラブの設
置も脱型してそのまま降下させるだけで行え、し
かもこれら床及び壁の構築工程を同様に繰り返す
のみで建築物を構築できるので、それに伴う労務
の省力化が期待できる。 また、本発明の構築装置では、揚重器が設けら
れているので外部の大型クレーン設備を小型化し
て軽減でき、その設置、規模の制約を緩めるとと
もに場内での作業効率を改善することができる。
また、この構築装置には各支柱の中段部に水平位
置に姿勢を固定できるスラブ構築用受梁を垂下状
態に枢動自在に設けているので、プレキヤストコ
ンクリート床スラブ構築後もスラブ構築用受梁を
水平姿勢から垂下状態に枢動させるだけでその支
持を簡単に解除させることができる。
[Detailed Description of the Invention] Industrial Application Field The present invention relates to a method of constructing a building made of reinforced concrete, and more specifically, a method of constructing walls and each floor slab when the building has a wall structure, and a construction method therefor. This relates to construction equipment used for construction. In general, wall-type structures have relatively little change in the planar configuration of each floor from the lower floors to the upper floors, and are a method adopted for medium-to-high-rise buildings. Because it can be replaced by combinations, the field is characterized by formwork planning and construction methods when constructing reinforced concrete, which is the main material. Therefore, the so-called prefabricated construction method, in which the formwork is standardized and manufactured in a factory, is often used.
On the other hand, for individual independent buildings that do not have the conditions for mass production, the construction method using cast-in-place concrete remains one of the mainstream methods. BACKGROUND TECHNOLOGY In concrete work, planning of scaffolding associated with formwork work becomes an important process problem, especially when using the cast-in-place method. For high-rise and medium-rise wall-type buildings, the concrete formwork on the inside and outside surfaces, the internal scaffolding, and the external scaffolding are planned as one unit.
Normally, as construction progresses one floor at a time, the formwork with scaffolding is raised in accordance with the concrete pouring process, or under special circumstances, the formwork is raised continuously. has been adopted. That is,
By having the wall part supported by the existing part and moving it upward, the process is streamlined in the vertical direction. However, in such conventional construction methods, in order to construct the floor concrete, horizontal and vertical steps of pouring the floor concrete and its supporting columns are involved separately from the above. Therefore, in order to maximize the benefits of streamlining the wall process in the vertical direction as described above, further improvements are required in terms of floor concrete construction. On the other hand, the lifting equipment used at construction sites uses various types of cranes, and also uses a trestle with lifting equipment on the top surface, which allows stable lifting while being limited in lifting height. It was used to cope with the need for larger cranes. Problems to be Solved by the Invention In addition, in conventional construction methods, when floor concrete is poured on-site, the supporting columns at the bottom of the slab are restricted by the hardening of the concrete, which not only affects the work process but also obstructs the work. It was hot. In addition, even if the above-mentioned drawbacks can be avoided in construction methods that use prefabricated slabs or concrete plates, large-scale lifting equipment is always required, and depending on the scale of the construction site, there may be restrictions on the installation location or high-lift This would affect construction costs and reduce operational efficiency. Therefore, the drawback of conventional construction methods is that the construction of horizontal slabs always complicates the process planning, compared to the construction of vertical walls as described above.
There was a need for a new construction method that would mainly make slab construction compatible with the streamlined wall construction method. Means for Solving the Problems Therefore, in the present invention, the concrete constituting the wall of the wall type structure is constructed by configuring the external formwork with scaffolding and the internal formwork into large panels. In addition to using a construction method in which each floor is raised sequentially, a support is erected inside the wall in contact with the wall, and a frame is constructed with a beam that connects the top of the support. By installing a container and suspending the formwork for the slab, it is possible to construct the wall and manufacture the slab PC board above in parallel. The main purpose of this method is to use a series of construction methods that allow the internal formwork to be raised, eliminate the need for large cranes, and allow for parallel construction of walls and floor slabs. The purpose of this invention is to achieve the effects of shortening the construction period and saving labor, and to this end, it also seeks to provide construction equipment that can be used in this construction method. Embodiment The present invention will be described in detail below with reference to an embodiment of the present invention shown in the drawings. FIG. 1 shows an embodiment of the construction method of a wall-type structure building according to the present invention, in which 1 is a room space of a wall-type structure building 1A to be constructed, and 2 and 3 are walls that have already been constructed. It shows the body and the slab. 2A, 3A
is a wall constructed on the floor above the slab 3 and a slab for the floor immediately above, and is usually constructed in a process for one floor. Reference numeral 4 denotes an external formwork for concrete for constructing a wall, which is provided with external working scaffolds 41 in two stages, upper and lower, on the outside, formed into a large formwork panel, and arranged in series along the outer surface of the wall. be done. 5 is an internal formwork for concrete, which is also formed into a large formwork panel, and has leg parts 5.
1 on the slab 3. 6 is a large number of separators that connect the inner and outer large formworks together in preparation for pouring concrete;
are fixing bolts that support and fix the external formwork 4 to the existing concrete portion 2 so that it can stand on its own. Reference numeral 8 denotes reinforcing reinforcing bars embedded in the concrete of the wall body 2, and is usually constructed into multiple reinforcing bars and used as a pre-assembled assembly. Next, reference numeral 9 denotes a frame which is the main construction device of the present invention, and a beam device 11 is spanned between the tops of columns 10 and 10 to form a trapezoidal steel frame. Here, each column 10 is made of, for example, H-shaped steel - 300 x 300 x 10, and as shown in Fig. 2, one flange is placed inside the room space 1 surrounded by the wall 2. Bolts 12 are arranged in contact with each other in the center of each side to form a rhombus, the height of which is selected to be at least the third floor of the building, the bolts 12 are erected from the lower floor of the relevant floor, and are planted in the wall body 2. 12
are fixed to the wall body 2 by means of , and are independent from each other. Next, guide columns 13 are placed at the four corners of the room space, and are made of the same material as the columns 10, and are also erected from the lower floor, but they are designed to increase the area of the slab 3A. The height is set at the same level as the inner and outer formworks 5 and 4 on the relevant floor so as not to cause any obstruction. The beam device 11, as shown in FIG.
Four beams 14 arranged in a diamond shape corresponding to 0 and 10
and two beams 15 fixedly supported by the beam 14 and arranged in the diagonal direction of the room space 1.
The pedestal 9 is configured by being removably installed on the pillar 10 at the meeting point of the mounts 4 and 14.
Here, the beam 14 is made of, for example, H-shaped steel 250 x 250 x 9,
Beam 15 is selected from I-shaped steel - 300 x 150 x 10. Beam 1
Reference numeral 5 is a traveling beam with a trolley hoist T attached to the lower string flange so that it can run freely, and wiring 16 is provided so that the driving operation thereof can be performed from the external work platform 41. Thus, when the support column 10 and the beam device 11 are combined, the frame 9 constitutes a construction device that also serves as a lifting facility. In FIG. 1, the slab 3A is suspended from a pedestal 9 by a trolley hoist T, and the slab 3A designed with a small beam is attached to the bottom formwork 17, 1
Constructed by 7A. And this slab 3
At the height of construction A, a steel slab support beam 18 is pivotally attached to the inside of the middle part of each support column 10, and the position of the cantilever beam that extends inward and supports the slab formwork 17 from below is determined. , and the column 10 hangs downward.
It is configured to be fixed or pivotable so as to take two postures, including a folded position along the axis, and is a part of the configuration of the pedestal 9. As shown in FIG. 3, the slab 3A constructed here has a predetermined notch 19 in the portion facing the pillars 10, 10 and the guide pillar 13 that penetrate above the slab, and each It is designed to allow relative movement between the column and the slab. Incidentally, numerals 20 and 20 in FIG. 1 are pillars for supporting the already applied slab 3, and are also used when the above-mentioned notch 19 is filled in later to complete the slab. Although typical embodiments have been described above, the slab 3A manufactured above the room space 1 can be modified in design, and can be cut if there is a structural problem in the part facing the columns 10, 13. It is also possible to disassemble and assemble the large formwork of the internal formwork 5 into small parts without providing the cutout 19, and to move and raise the slab 3A as a small formwork member without horizontally moving the slab 3A. . Function The method for constructing a wall-type structure building according to the present invention will be explained with reference to the process diagrams shown in FIG. 1 and FIG. be done. However, in each drawing, embodiments at multiple points in time are partially duplicated. First, in the state shown in Figure 1, the external formwork 4 and internal formwork 5 for constructing the external wall 2 are set at the level of the slab 3 of the floor concerned, and concrete is poured between them to construct the wall 2A. has been done. on the other hand,
Above the slab 3, under the support of the frame 9 , the slab 3A of the upper floor as part of the construction of this floor
is being constructed in parallel with wall 2A. Since the basic structure of the present invention is this parallel work, the steps from this stage will be explained as a cycle of a series of steps to the upper floor based on FIGS. 1 and 4 to 10. (1) First, the cast wall 2A is given a hardening period, and then the internal formwork 5 is demolded. Legs 5 of formwork 5
1 is of a foldable or detachable type, and the retainer on the slab 3 is removed to reduce the thickness of the internal formwork 5, and then the fastening hardware 6 is removed. (2) In Fig. 4, the slab 3A is suspended from above by a trolley hoist T, and is moved to the right in the figure while being suspended by operation from the external scaffolding 4. At this time, the left end edge of the slab 3A moves inward of the pillar 10, creating a space above the internal formwork 5 with a dimension equal to the thickness plus the margin, and the right end of the slab 3A The notch 19 provided on the opposite side and the side side in the front-rear direction in the drawing is moved within a range where the notch 19 does not collide with the pillar 10, respectively. (3) Therefore, the internal formwork 5 is lifted up as a large panel using lifting equipment for construction work, such as a tower crane C, which is installed separately on the construction site. This lifting is performed while being guided by the grooves or grooves and flanges on the side surfaces of the pillars 10 and guide pillars 13, and when the lower end of the formwork 5 exceeds the height of the slab 3A, it is lifted off from the pillar 10 side. It will be temporarily supported by holding it, and an auxiliary branch line will be provided at the other end for support. (4) Next, as is clear from Fig. 5, the step (2) above is carried out in the opposite direction, that is, to the left in the figure, to form a space above the internal formwork 5 on the right side for the slab 3A. Then, as in (3) above, remove the inner formwork 5 on the right side.
to rise. (5) In Fig. 4, materials and equipment 17B for constructing the next upper floor slab are loaded on the top surface of the slab 3A, and these preparatory works are also carried out in parallel with the above steps. (6) Figure 6 shows the process of installing slab 3A. The precast concrete slab 3A manufactured at a predetermined upper position of the pedestal 9 is suspended by a trolley hoist T, and after being easily moved, it is returned to its original central position at the time of manufacture. , where it is lowered by raising and lowering the hoist T. The slab 3A is manufactured to a predetermined size and is seated on the upper end of the surrounding wall 2A, and then the lower formwork 17, 17A is successively demolded.
By applying and supporting the trolley hoist T, it becomes possible to release the suspension by the trolley hoist T, and it also becomes possible to support the load during subsequent work. (7) Figure 7 explains the work on the new upper floor.
At this stage, the internal formwork 5 is installed on the floor of the slab 3A. The internal formwork 5 is suspended again by the external crane C, and the support column 1 is
The temporary support by 0 is released, and the internal formwork 5 is attached to the slab 3.
A and set it in a predetermined position using the legs 51. (8) Meanwhile, on the slab 3A, construct the formwork for the new upper floor slab 3B using the materials and equipment 17B. 17C is a platform using a framework scaffolding or the like to secure the height above the workers' heads, and 17D is the lower formwork for slab 3B installed at a height of H from slab 3A; It has a known structure such as joists. The height defined as H here is used as a reference for determining the operating lift of the trolley hoist T as well as the height of the support column 10. (9) Before and after these steps, the beam device 11
will be moved. That is, the beam device 11
After being uncoupled from 0, it was suspended by crane C and moved as a series of jigs above the adjacent room space, allowing it to be repurposed and completely freeing the space above the work space. do. (10) The connection between the wall 2A and the slab 3A is prepared at this stage by connecting the extension of the reinforcing bar 8 in the wall 2A to the extension of the cotter or slab reinforcing bar provided at the edge of the slab 3A. Ru. The main process shown in FIG.
0 and the raising of the guide column 13 and the reinforcement placement on the slab and wall. (11) The lifting of each support column 10 begins with releasing the fixing bolts 12 on the preceding floor, and lifts the beam device 11 at the disassembled top using the crane C, raises it by one floor, and then lifts it up again to the wall 2A.
It is fixed to the wall 2A on the slab 3 with fixing bolts 12. During this time, the support column 10 is relatively guided by the internal formwork 5, so that the ascent is performed stably and smoothly. The rise of guide column 13 is also caused by column 1.
This is the same as the case of 0. (12) The work at this stage of slab construction is reinforcing, and the slab reinforcing bars 21, which have been preassembled on the ground, are placed on the formwork 17D. (13) To construct the wall 2, first, reinforcing bars are placed on the outer surface of the internal formwork 5. To do this, the reinforcing bars 8A that have been pre-assembled on the ground are lifted up by a crane C and connected to the upper part of the reinforcing bars 8 below. (14) In the so-called "jump up" formwork construction method in which the internal and external formwork is raised one floor at a time, the raising of the next stage of external formwork 4 is well known as a series of the steps in (13) above. The external formwork 4 is constructed by removing the lower fixing bolts 7, assembling the external formwork 4 into a large formwork, lifting it up with the crane C with the scaffolding attached, and replacing it with the fixing bolts 7 of the wall 2A. (Figure 9). (15) FIG. 9 further shows the construction process of slab 3B. That is, the beam device 11 is lifted again by the crane C, returned to the present construction section from another construction section, and assembled to the columns 10, 10 to form the pedestal 9 . Then, the trolley hoist T is placed on the traveling beam 15.
is moved to hang the formwork 17D and raise it to the height of the first floor. Next, formwork 17D is attached to pillars 10 and beams 14.
At the same time, the slab support beams 18, 18 of each support column 10 are rotated upward at the pivot point, and the formwork 17D is fixed in a position to support it from below. This completes the preparation for prefabrication of the slab 3B, and the production of the precast concrete slab 3B is completed by pouring concrete onto the formwork 17D. For the curing of the slab 3B, it is desirable to erect support columns 20 from the slab 3A, further cover the top surface with a cover S, and allow steam to pass through the inside to add steam curing to quickly develop the strength of slab concrete. (16) Figure 10 is a drawing showing the final process, in which the upper slab 3B is being cured, and the outer formwork 4 and the inner formwork 5 are tightly connected above the wall body 2A to form the wall body 2B. Concrete is poured. This pouring work is actually performed at the same timing as the steam curing of the concrete of the slab 3B and the hardening of the wall concrete. By this concrete pouring, the connection between the wall 2A and the slab 3A is also completed at the same time. (17) Next, by pivoting the slab support beam 18 downward, releasing the wire W, and removing the support column 20, the situation will be the same as that shown in Fig. 1 based on the rail of the slab 3A, and the same process will be performed upward. The construction method can be implemented repeatedly as a series of cycles. Thus, in the construction method of the present invention, the on-site concrete work for the wall portion and the precast concrete work for the slab portion above the room space are accomplished as a series of "parallel work." Regarding the change in the notch 19 in the structure of the slab explained in the example section, please refer to step (2) above.
The horizontal movement of the slab in ~(4) is not performed, and the internal formwork 5
Since no upward space is available for relocation to the upper floor after demolding, the inner formwork 5 can be disassembled into small parts and transported in small parts. Effects of the Invention In the construction method of the present invention, the slab formwork for constructing the precast concrete floor slab can be constructed on the floor above the wall formwork at the same time as the wall formwork is being installed. The production of precast concrete floor slabs for the floors directly above can be carried out in parallel, which significantly shortens the construction period.Moreover, the production of precast concrete floor slabs can be accomplished within the limited space within the building. Pre-cast concrete floor slabs can be installed by simply removing the mold and lowering them.Furthermore, buildings can be constructed by simply repeating the floor and wall construction process, which is expected to result in labor savings. can. Furthermore, since the construction equipment of the present invention is equipped with a lifting device, it is possible to downsize and reduce the need for large external crane equipment, loosen restrictions on its installation and scale, and improve work efficiency within the site. .
In addition, this construction equipment is equipped with a slab construction support beam that can be freely pivoted in a hanging state at the middle part of each support column, allowing the slab construction support beam to be fixed in a horizontal position. The support can be easily released by simply pivoting the beam from a horizontal position to a hanging position.

【図面の簡単な説明】[Brief explanation of drawings]

図面は本発明の構築工法とその構築装置の実施
例の図面であつて、第1図は構築工法の一基準時
を建築物の断面で示す工程図、第2図は第1図の
−線に沿う断面平面図、第3図は第1図の
−線に沿う平面図、第4図ないし第10図は第
1図の状態以後の各工程を建築物の断面で示す工
程図である。 1……室空間、2……壁体、3……スラブ、4
……外部型枠、5……内部型枠、8,21……鉄
筋、……架台、10……支柱、11……梁装
置、12……固定ボルト、13……ガイド柱、1
4……梁、15……走行梁、17……スラブ型
枠、18……スラブ受梁、19……切欠き、T…
…トロリーホイスト。
The drawings are drawings of an embodiment of the construction method and the construction device of the present invention, and FIG. 1 is a process diagram showing a cross section of the building at one reference time of the construction method, and FIG. FIG. 3 is a plan view taken along the - line in FIG. 1, and FIGS. 4 to 10 are process diagrams showing each step after the state shown in FIG. 1 in cross sections of the building. 1... Room space, 2... Wall, 3... Slab, 4
... External formwork, 5 ... Internal formwork, 8, 21 ... Reinforcing bars, 9 ... Frame, 10 ... Support column, 11 ... Beam device, 12 ... Fixing bolt, 13 ... Guide column, 1
4... Beam, 15... Running beam, 17... Slab formwork, 18... Slab support beam, 19... Notch, T...
…Trolley hoist.

Claims (1)

【特許請求の範囲】 1 (a) 既施工の壁体の内部側に固定されて自立
する複数の支柱の頂部に梁装置を架け渡して架
台を構成するとともにこの架台に揚重器を装備
させてなる構築装置を設け、構築しようとする
階の壁体用内部型枠及び外部型枠を設置して当
該階の壁コンクリートを打設する工程に平行し
て、上記揚重器によつてスラブ型枠を当該階の
上方に懸垂装備したその上で当該階の直上階の
プレキヤストコンクリート床スラブ型を製作す
る工程を行い、 (b) しかるのちに壁体用内部型枠を脱型して上記
揚重器によつて壁体上に上記床スラブ型枠を下
降させるとともにスラブ型枠を脱型し、さらに
外部型枠を脱型するとともに上記支柱の固定を
外して外部の揚重設備によつて上記外部型枠と
上記支柱を一階分上昇させて工程(a)(b)を繰り返
す、 ことを特徴とする壁式構造建築物の構築工法。 2 プレキヤスト・コンクリートのスラブには架
台の支柱に臨んで切欠きを設け、内部型枠の脱型
は構築装置から吊持したプレキヤスト・コンクリ
ートのスラブをその切欠きによつて支柱をかわし
つつ水平移動させたのち該スラブと壁体との間の
空間を利用して脱型した壁体の内部型枠を上階に
盛替えて行なうようにした特許請求の範囲第1項
に記載の構築工法。 3 壁式構造建築物を構築するために用いられる
構築装置であつて、該構築装置は既施工の壁体の
内部側に固定されて自立する複数の支柱と、この
支柱の頂部に架けわたされる梁装置とを結合して
架台に形成され、該梁装置は上記支柱と結合され
る複数の梁材に、移動自在に揚重器を装備した走
行梁を組付けて構成され、上記各支柱の中段部に
は水平位置に姿勢を固定できるスラブ構築用受梁
を垂下状態に枢動自在に設けたことを特徴とする
壁式構造建築物の構築装置。 4 支柱と梁装置とは梁装置の梁材を介して着脱
自在に結合されている特許請求の範囲第3項に記
載の構築装置。
[Scope of Claims] 1 (a) A beam device is spanned over the tops of a plurality of self-supporting columns that are fixed to the inside of an already constructed wall to constitute a pedestal, and this pedestal is equipped with a lifting device. In parallel with the process of installing internal and external formwork for the walls of the floor to be constructed and pouring concrete for the walls of the floor concerned, the slab is The formwork is suspended above the relevant floor, and then the process of manufacturing the precast concrete floor slab mold for the floor directly above the relevant floor is carried out, and (b) the internal formwork for the wall is then removed from the mold. The above-mentioned floor slab formwork is lowered onto the wall by the above-mentioned lifting device, and the slab formwork is removed from the formwork, and the external formwork is also removed from the formwork, and the above-mentioned support columns are unfixed and attached to external lifting equipment. Therefore, a method for constructing a wall-type structure building, characterized in that steps (a) and (b) are repeated by raising the external formwork and the pillars by one floor. 2. A notch is provided in the precast concrete slab facing the support of the frame, and to remove the internal formwork, the precast concrete slab suspended from the construction equipment is moved horizontally through the notch while dodging the support. The construction method according to claim 1, wherein the internal formwork of the demolded wall is transferred to the upper floor using the space between the slab and the wall. 3. A construction device used to construct a wall-type structure building, which consists of a plurality of self-supporting columns that are fixed to the inside of an already constructed wall, and a structure that spans the tops of these columns. The beam device is connected to a beam device to form a frame, and the beam device is constructed by assembling a traveling beam equipped with a movable lifting device to a plurality of beams connected to the above-mentioned pillars, and A device for constructing a wall-type structural building, characterized in that a support beam for constructing a slab that can be fixed in a horizontal position is provided in the middle part so as to be freely pivotable in a hanging state. 4. The construction device according to claim 3, wherein the support and the beam device are detachably connected via the beam material of the beam device.
JP23528584A 1984-11-09 1984-11-09 Construction of wall type building and construction apparatus used therein Granted JPS61113965A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP23528584A JPS61113965A (en) 1984-11-09 1984-11-09 Construction of wall type building and construction apparatus used therein

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP23528584A JPS61113965A (en) 1984-11-09 1984-11-09 Construction of wall type building and construction apparatus used therein

Publications (2)

Publication Number Publication Date
JPS61113965A JPS61113965A (en) 1986-05-31
JPH0437893B2 true JPH0437893B2 (en) 1992-06-22

Family

ID=16983838

Family Applications (1)

Application Number Title Priority Date Filing Date
JP23528584A Granted JPS61113965A (en) 1984-11-09 1984-11-09 Construction of wall type building and construction apparatus used therein

Country Status (1)

Country Link
JP (1) JPS61113965A (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20010069329A (en) * 2001-03-08 2001-07-25 김영림 structure for mounting a mould
KR100968068B1 (en) * 2007-07-30 2010-07-08 (주)바로건설기술 Multi-Horizontal Structure Member Forming Method
JP5532184B2 (en) * 2011-12-05 2014-06-25 新日鐵住金株式会社 Frame structure and box-like structure

Also Published As

Publication number Publication date
JPS61113965A (en) 1986-05-31

Similar Documents

Publication Publication Date Title
JP3940211B2 (en) Construction method of horizontal beams for concrete main tower.
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
US5012627A (en) Construction process for multiple-story concrete building
JPH0643686B2 (en) Construction method of arch bridge by precast members
KR101140884B1 (en) Gangform device constructed for wall and constructing method this using
JPH0959932A (en) Construction method of column head of overhanging erection girder bridge
JPH0437893B2 (en)
JP5003253B2 (en) RC beam construction method
JPH0657956A (en) Construction of concrete structure
JP2829363B2 (en) Formwork equipment for pillar construction
JP6449637B2 (en) Building construction method
JPH0642184A (en) Construction of skeleton using half precast floor board
JPH0681463A (en) Building method for stair
JPH0429820B2 (en)
JPH08105229A (en) Construction of building
JPH1082019A (en) Constructing method of pier
JPH108725A (en) Constructing method for building frame
JP3605661B2 (en) Construction method of concrete structure
JPH04146345A (en) Self-ascending device for large roof for architectural work, and constructing method for medium/high-rise building
JPS621954A (en) Construction of housing of building
JPH03197734A (en) Lift up method by replacement of scaffold body
JPH0967824A (en) Double slab construction method
JPH0715177B2 (en) How to build a reinforced concrete structure
JPH0827903A (en) All weather type building method
JP2761526B2 (en) How to build structures