SU1048093A1 - Method of erecting multistorey building by floor-rising technique - Google Patents

Method of erecting multistorey building by floor-rising technique Download PDF

Info

Publication number
SU1048093A1
SU1048093A1 SU823389183A SU3389183A SU1048093A1 SU 1048093 A1 SU1048093 A1 SU 1048093A1 SU 823389183 A SU823389183 A SU 823389183A SU 3389183 A SU3389183 A SU 3389183A SU 1048093 A1 SU1048093 A1 SU 1048093A1
Authority
SU
USSR - Soviet Union
Prior art keywords
floor
ring
shaft
installation
lifting
Prior art date
Application number
SU823389183A
Other languages
Russian (ru)
Inventor
Евгений Петрович Дуброва
Вадим Дмитриевич Васильев
Леонид Петрович Тимофеенко
Виктор Иосифович Щербина
Original Assignee
Научно-Исследовательский Институт Автоматизированных Систем Планирования И Управления В Строительстве Госстроя Усср
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Научно-Исследовательский Институт Автоматизированных Систем Планирования И Управления В Строительстве Госстроя Усср filed Critical Научно-Исследовательский Институт Автоматизированных Систем Планирования И Управления В Строительстве Госстроя Усср
Priority to SU823389183A priority Critical patent/SU1048093A1/en
Application granted granted Critical
Publication of SU1048093A1 publication Critical patent/SU1048093A1/en

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

СПОСОБ ВОЗВЕДЕНИЯ МНОГОЭТАЖНОГО ЗДАНИЯ МЕТОДОМ ПОДЪЕМА ЭТАЖЕЙ, включающий устройство фундамента, возведение шахты, установку на ней оголовка с грузоподъемным оборудованием , изготовление пакета плит перекрытий , монтаж подъемников в подвальном помеплении, формирование на уровне первого этажа пространственной структуры этажа, подъем его на заданную отметку посредством грузоподъемного оборудовани , установленного на оголовке шахты, с последующим закреплением на шахте, отличающийс  тем, что, с целью снижени  трудоемкости монтажа, сокращени  монтажного оборудовани , после возведени  шахты на ней устанавливают вертикальные направл ющие , на отметке пола первого этажа монтируют охватывающее шахту разъемное кольцо, соедин ют его с горизонтальной платформой, а пространственную структуру поднимаемого этажа собирают на платформе и поднимают вместе с кольцом с последовательными остановками на отметках второго и третьего этажа дл  производства I отделочных работ и монтажа инженерных коммуникаций, временно закрепл ют этаж (Л на шахте, отсоедин ют платформу от кольца и опускают ее, при этом подъем этажа с на проектную отметку производ т вместе с кольцом, а после закреплени  его на шахте опускают кольцо дл  подъема следующего этажа. 5 4 СХ) о ее соMETHOD OF CONSTRUCTION OF A MULTILEVEL BUILDING BY THE METHOD OF LIFTING THE FLOOR, including building a foundation, erecting a mine, installing a head on it with lifting equipment, manufacturing a package of floor slabs, installing elevators in the basement, creating a floor structure at the level of the first floor, lifting it to a predetermined elevation by lifting equipment installed on the shaft top, followed by fixing on the shaft, characterized in that, in order to reduce the labor intensity of installation, after erection of the shaft, vertical guides are installed on it, the split ring covering the shaft is mounted on the ground floor level mark, connected to the horizontal platform, and the spatial structure of the raised floor is assembled on the platform and lifted together with the ring with successive stops on the marks the second and third floors for the production of finishing works and the installation of engineering communications, temporarily fix the floor (L on the mine, disconnect the platform from ltsa and lower it, thus lifting the floor with the projected mark manufac m together with the ring, and after fixing it on the ring shaft is lowered to lift the next floor. 5 4 CX) oh her

Description

Изобретение относитс  к строительному производству и может быть применено при возведении многоэтажных жилых и гражданских зданий с несущей центральной шахтой методом подъема этажей. Наиболее предпочтительным  вл етс -использование изобретени  при возведении многоэтажных зданий башенного типа с подвешенными этажами .The invention relates to the construction industry and can be applied in the construction of multi-storey residential and civil buildings with a bearing central shaft by the method of lifting floors. The most preferred is the use of the invention in the construction of multi-storey tower-type buildings with suspended floors.

Известен слособ возведени  многоэтажного здани  методом подъема этажей и перекрытий с несущей шахтой с жестким арматурным каркасом и проемами, включающий установку колонн здани  и жесткого арматурного каркаса шахты, изготовление пакета плит перекрытий этажей и щахты, установку подъемников с грузовыми шагами на колоннах и шахте здани  с поэтажным подъемом плит перекрытий и установкой их в проектное положение и бетонированием шахты, одновременно с установкой колонн здани  и жесткого арматурного каркаса шахты устанавливают дополнительные стойки, плиты перекрытий объедин ют между собой горизонтальными св з ми, а на стойках устанавливают передвижение рамы дл  подъемников с т гами 1.A well-known method of erecting a multi-storey building is by raising floors and floors with a supporting shaft with a rigid reinforcement cage and openings, including installation of building columns and a rigid reinforcement frame of the mine, making a package of floor slabs and bridges, installing elevators with cargo steps on columns and a building mine with floor-by-floor by raising the floor slabs and installing them in the design position and concreting the mine, simultaneously with the installation of the columns of the building and the rigid reinforcement cage of the mine, install additional body racks, floor slabs are interconnected by horizontal ties, and on racks, frame movement for lifts with traces 1 is established.

Недостатком известного способа  вл етс  его трудоемкость, что обусловлено наличием и монтажом дополнительных колоин, стоек, св зей. Кроме того, все отделочные и санитарно-технические работы по доводке здани  необходимо выполн ть на отметках этажей, что св зано с затратами труда и средств по доставке на высоту материалов и изделий. Это приводит к удлинению сроков строительства.The disadvantage of this method is its laboriousness, due to the presence and installation of additional coloins, racks, and connections. In addition, all finishing and sanitary works for building the building must be performed at the elevations of the floors, which is associated with the cost of labor and means of delivery of materials and products to the height. This leads to a longer construction time.

Известен также способ возведени  здани  методом подъема этажей, включающий возведение шахты, установку плит перекрытий по отметке первого этажа, размещени  на них полностью законченных жилых блоков, подъем их на проектную отметку и закрепление плит перекрытий на шахте 2.There is also known a method of erecting a building by raising floors, including the erection of a mine, the installation of floor slabs at the elevation of the first floor, the placement of fully completed residential blocks on them, their elevation to the design elevation, and the fixing of the floor slabs at the mine 2.

Недостатком данного способа  вл етс  необходимость выполнени  дополнительных работ по изготовлению жилых блоков, а также повышенный расход материала, обусловленный необходимостью выполнени  плиты перекрыти , плит пола и потолка блоков. В здании перекрыти  фактически имеют трехслойную структуру, что приводит к неоправданному повышению их массы.The disadvantage of this method is the need to perform additional work on the production of residential blocks, as well as increased material consumption, due to the need to perform floor slabs, floor slabs and ceiling blocks. In the building, the floors actually have a three-layer structure, which leads to an unjustified increase in their mass.

Наиболее близким по технической сущности и достигаемому результату к изобретению  вл етс  способ возведени  многоэтажного здани  методом подъема этажей, включающий устройство фундамента, возведение шахты, установку на ней оголовка с грузоподъемным оборудованием, изготовление пакета плит перекрытий, монтаж подъемников в подвальном помещении, формирование на уровне первого этажа пространственной структуры этажа, подъемThe closest in technical essence and the achieved result to the invention is the method of erection of a multi-storey building by the method of lifting floors, including the construction of the foundation, the erection of a shaft, the installation of a head on it with lifting equipment, the manufacture of a package of floor slabs, the installation of elevators in the basement the floor of the spatial structure of the floor rise

его на заданную отметку посредством грузоподъемного оборудовани , установленного на оголовке шахты с последующим закреплением на шахте 3.it is at a given mark by means of lifting equipment installed on the top of the mine, followed by fixing it on the mine 3.

Недостатком известного способа  вл етс  необходимость установки инвентарных колонн, выполнение отверстий в плитах перекрытий дл  их прохождени , тщательна  синхронизаци  работы большого числа подъемников, что приводит к увеличению трудоемкости монтажа.The disadvantage of this method is the need to install inventory columns, making holes in the floor slabs for their passage, carefully synchronizing the work of a large number of lifts, which leads to an increase in the labor intensity of installation.

Цель изобретени  - снижение трудоемкости монтажа, сокращение монтажного оборудовани .The purpose of the invention is to reduce the labor intensity of installation, reduction of installation equipment.

Цель достигаетс  тем, что согласно способу возведени  многоэтажного здани  методом подъема этажей, включающему уст0 ройство фундамента, возведение шахты, установку на ней оголовка с грузоподъемным оборудованием, изготовление пакета плит перекрытий, монтаж подъемников в подвальном помещении, формирование наThe goal is achieved in that according to the method of erection of a multi-storey building by the method of lifting floors, including the installation of the foundation, the erection of a shaft, the installation of a head on it with lifting equipment, the manufacture of a package of floor slabs, the installation of elevators in the basement, the formation of

с уровне первого этажа пространственной структуры этажа, подъем его на заданную отметку посредством грузоподъемного оборудовани , установленного на оголовке шахты с последующим закреплением на шахте, после возведени  последней на нейfrom the level of the first floor of the spatial structure of the floor, lifting it to a predetermined elevation by means of lifting equipment installed on the top of the mine, followed by fixing it on the mine, after the latter has been erected on it

0 устанавливают вертикальные направл ющие , на отметке пола первого этажа монтируют охватывающее шахту разъемное кольцо, соедин ют его с горизонтальной платформой, а пространственную структуру поднимаемого этажа собирают на плат5 форме и поднимают вместе с кольцом с последовательными остановками на отметках второго и третьего этажа дл  производства отделочных работ и монтажа инженерных коммуникаций, временно закрепQ л ют этаж на шахте, отсоедин ют платформу от кольца и опускают ее, при этом подъем этажа на проектную отметку производ т аместе с кольцом, а после закреплени  его на шахте опускают кольцо дл  подъема следующего этажа.0, vertical guides are installed, a split ring covering the shaft is mounted on the floor level of the first floor, connected to the horizontal platform, and the spatial structure of the raised floor is assembled on a plate and lifted together with the ring with successive stops on the second and third floors for the production of finishing works and installation of engineering communications, temporarily fix the floor of the mine, disconnect the platform from the ring and lower it, while raising the floor to the design elevation one place with a ring, and after fixing it on the shaft, lower the ring to lift the next floor.

5 При таком способе возведени  здани  дл  подъема, оборудовани  и отделки этажей на отметках первого - третьего этажей используют гидравлические подъемники , размещенные в подвальном помещении, а дл  подъема этажа на проектную отметку5 With this method of erecting a building, hydraulic lifts located in the basement are used for lifting, equipping and finishing floors on the first to third floors, and for raising the floor to the design level

0 используют механизмы, закрепленные на конце шахты. Благодар  подвижному разъемному кольцу на шахте, движущемус  по направл ющим, обеспечиваетс  быстрый подъем этажа на проектную отметку, закреплени  его, опускание, демонтаж и последующее использование кольца. Дл  обеспечени  цикличности работы используют преимушественно два кольца.0 use mechanisms attached to the end of the shaft. Thanks to the movable split ring on the shaft, which moves along the rails, the floor is quickly raised to the design mark, fixed, lowered, dismounted and then used. To ensure cyclical operation, two rings are used predominantly.

С другой стороны, использование платформы , соединенной с кольцом, дл  изготовлени  этажа на отметках первого - третьего этажей позвол ет достаточно быстро изготовить этаж в виде замкнутой короб .чатой структуры, имеющей высокую пространственную жесткость и устойчивость, отделать его, и с помощью подвижного кольца и подъемников на щахте осуществить подъем. На отметках первого - третьего этажей по вл етс  возможность выполн ть строительно-монтажные работы с высокой степенью механизации и автоматизации производственного цикла и обеспечить безопасность за счет увеличени  количества работ, выполн емых на отметках первых этажей здани . При этом впервые по вл етс  возможность выполнить монтаж конструкций этажа полностью из сборного железобетона, устранить тем самым неблагопри тное воздействие атмрсферных условий на производство бетонных работ. On the other hand, the use of a platform connected to the ring for the manufacture of a floor at the elevations of the first to third floors allows you to quickly produce a floor in the form of a closed box-like structure having high spatial rigidity and stability, to finish it with a movable ring and lifts on the platform to carry out lifting. At the elevations of the first to third floors, it is possible to perform construction and installation works with a high degree of mechanization and automation of the production cycle and to ensure safety by increasing the number of works performed at the elevations of the first floors of the building. In this case, for the first time, it becomes possible to install the floor structures entirely from precast concrete, thereby eliminating the adverse effect of atmospheric conditions on the production of concrete work.

На фиг. 1 изображено здание на стадии установки кольца и подъемников, поперечный разрез; на фиг. 2 - то же, на стадии монтажа платформы и последнего этажа с покрытием; на фиг. 3 - схема подъема этажей на проектную отметку; на фиг. 4 - фрагмент кольца с платформой.FIG. 1 shows a building at the stage of installing the ring and lifts, a cross-section; in fig. 2 - the same, at a stage of installation of a platform and the last floor with a covering; in fig. 3 - scheme of lifting floors to the design mark; in fig. 4 - a fragment of a ring with a platform.

Способ возведени  здани  заключаетс  в следующем.The method of erection of the building is as follows.

После устройства фундамента 1, например , из сборно-монолитных плит производ т возведение щахты 2 известными способами , преимущественно, например, из сборных объемных блоков с проемами 3, размещают на ней временный оголовок 4, на котором размещают подъемные механизмы 5 с т гами 6. Затем в подвальном помещении 7 устанавливают гидравлические подъемники 8 со щтоками 9 и инвентарными стойками 10. На нижней секции щахты 2 на отметке пола первого этажа монтируют подвижное разъемное кольцо 11, перемещаемое по направл ющим 12. Кольцо соедин ют с горизонтальной консольной платформой 13, опираемой на стойки 10, а затем на ней монтируют плиту перекрыти  14 последнего этажа, жестко соедин ют с ней наружные и внутренние стены 15, укладывают на них и жестко закрепл ют плиту потолка 16. Затем платформу 13 с помощью подъемников 8 поднимают с последовательными остановками на отметках второго и третьего этажей, где производ т оборудование этажа сантехприборами и инженерными коммуникаци ми, устанавливают стол рку , осуществл ют настилку полов, полную отделку и остекление. На этих отметкахAfter the installation of foundation 1, for example, from the assembly-monolithic slabs, erection of the sucker 2 is carried out by known methods, mainly, for example, from modular bulk blocks with openings 3, a temporary tip 4 is placed on it, on which the lifting mechanisms 5 with 6 g are placed. Then, in the basement 7, hydraulic lifts 8 are installed with brushes 9 and inventory racks 10. A movable separating ring 11 is mounted on the bottom section of Schachta 2 on the floor level of the first floor, moving along the rails 12. The ring is connected to the horizon The ntal cantilever platform 13 supported by the pillars 10 and then the slab 14 of the last floor is mounted on it, the outer and inner walls 15 are rigidly connected to it, laid on them and the ceiling plate 16 is rigidly fixed with the help of lifts 8 lift with successive stops at the marks of the second and third floors, where floor equipment is manufactured by sanitary equipment and engineering communications, a table is installed, flooring, full finishing and glazing are carried out. On these marks

оборудуют специализированные посты по выполнению указанных работ с обеспечением повыщенной механизации и автоматизации производственного процесса. Этаж временно закрепл ют на щахте с помощью консольных анкерных устройств 17 с подкосами , а платформу 13 опускают на отметку первого этажа, где осуществл ют монтаж следующего этажа, использу  новое кольцо 11. Затем готовый этаж с помощью подъемных механизмов 5 и т г б, закрепленных на кольце 11, по направл ющим 12 поднимают на проектную отметку , -где его фиксируют, закрепл ют на щахте. Кольцо 11 опускают, демонтируют, а затем используют дл  подъема следующего этажа.equip specialized posts for the implementation of these works with the provision of increased mechanization and automation of the production process. The floor is temporarily fixed on the platform with the help of console anchoring devices 17 with struts, and platform 13 is lowered onto the level of the first floor where the next floor is mounted using the new ring 11. Then the finished floor is fixed using lifting mechanisms 5 and b g on the ring 11, along the guides 12 they are raised to the design mark, where it is fixed, fixed on the drill. The ring 11 is lowered, dismantled, and then used to lift the next floor.

Таким образом, при предлагаемом способе осуществл етс  цикл монтажа этажа на отметке первого этажа, доведение его до полной готовности на отметке второго - третьего этажей. При этом, поскольку монтаж стен 15 последующего этажа на платформе производитс  при положении предыдущего этажа на отметке третьего этажа, то имеетс  возможность использовать эффективно механизмы, в том числе автокраны , автопогрузчики, средства малой механизации. Доставка необходимых отделочнйх материалов осуществл етс  как снаружи, так и через проемы 3 в щахте 2.Thus, with the proposed method, the cycle of installation of the floor at the level of the first floor is carried out, bringing it to full readiness at the level of the second - third floors. Moreover, since the installation of the walls of the 15th floor on the platform is carried out at the position of the previous floor on the third floor level, it is possible to use efficiently mechanisms, including truck cranes, lift trucks, small-scale mechanization tools. Delivery of the necessary finishing materials is carried out both outside and through openings 3 in Schachte 2.

С другой стороны, наличие подвижного кольца 11, перемещаемого по направл ющим 12 позвол ет, во-первых, ускорить подъем готовых этажей на проектную отметку , поскольку отпадает необходимость в устройстве периферийных колонн, систем домкратов, инвентарных стоек и т. п., вовторых , снизить трудоемкость монтажа, так как все трудоемкие работы сосредоточены на первом - третьем этажах, куда подвижное кольцо доставл етс  после подъема этажа с помощью т г 6. Платформа 13 используетс  только в пределах первого - третьего этажей, а кольцо 11 - по высоте всей щахты 2. В предлагаемом способе опертые на кольцо 11 этажи полной заводской готовности имеют возможность быстрого независимого подъема на проектные отметки независимо от работ по монтажу и отделке следующих этажей на отметке первого - третьего этажей. Поскольку все работы по устройству этажей выполнены внизу, то подсоединение готового этажа к коммуникаци м, размещенным в шахте 2, осуществл етс  через проемы 3.On the other hand, the presence of a movable ring 11 moved along guides 12 makes it possible, firstly, to accelerate the rise of finished floors to the design elevation, since there is no need for arranging peripheral columns, jack systems, inventory racks, etc., secondly, reduce the laboriousness of installation, since all labor-intensive work is concentrated on the first to third floors, where the movable ring is delivered after the floor has been lifted with the help of stage 6. Platform 13 is used only within the first to third floors, and ring 11 is all shchatah 2. In the proposed method, 11 full-readiness floors supported on the ring have the possibility of a quick independent rise to the design marks, regardless of the work on installation and finishing of the next floors on the mark of the first - third floors. Since all the work on the device of the floors is done below, the connection of the finished floor to the communications housed in the shaft 2 is carried out through the openings 3.

Предлагаемый способ позвол ет сократить сроки строительства и снизить трудоемкость работ.The proposed method allows to reduce the construction time and reduce the complexity of the work.

Claims (1)

СПОСОБ ВОЗВЕДЕНИЯ МНОГОЭТАЖНОГО ЗДАНИЯ МЕТОДОМ ПОДЪЕМА ЭТАЖЕЙ, включающий устройство фундамента, возведение шахты, установку на ней оголовка с грузоподъемным оборудованием, изготовление пакета плит перекрытий, монтаж подъемников в подвальном помещении, формирование на уровне первого этажа пространственной структуры этажа, подъем его на заданную отметку посредством грузоподъемного оборудования, установленного на оголовке шахты, с последующим закреплением на шахте, отличающийся тем, что, с целью снижения трудоемкости монтажа, сокращения монтажного оборудования, после возведения шахты на ней устанавливают вертикальные направляющие, на отметке пола первого этажа монтируют охватывающее шахту разъемное кольцо, соединяют его с горизонтальной платформой, а пространственную структуру поднимаемого этажа собирают на платформе и поднимают вместе с кольцом с последовательными остановками на отметках второго и третьего этажа для производства отделочных работ и монтажа инженерных g коммуникаций, временно закрепляют этаж “ на шахте, отсоединяют платформу от кольца и опускают ее, при этом подъем этажа на проектную отметку производят вместе с кольцом, а после закрепления его на шахте опускают кольцо для подъема следующего этажа.METHOD OF CONSTRUCTION OF A MULTI-STOREY BUILDING BY THE METHOD OF LIFTING FLOORS, including foundation, shaft construction, installation of a head with lifting equipment on it, production of a package of floor slabs, installation of elevators in the basement, formation of the spatial structure of the floor at the level of the first floor, lifting it to a predetermined level by means of lifting equipment installed on the head of the mine, followed by fixing on the mine, characterized in that, in order to reduce the complexity of installation, installation equipment, after the shaft is erected, vertical guides are installed on it, a detachable ring enclosing the shaft is mounted on the floor level of the first floor, connected to the horizontal platform, and the spatial structure of the raised floor is assembled on the platform and raised together with the ring with successive stops at the marks of the second and the third floor for finishing work and installation of engineering g communications, temporarily fix the floor “at the mine, disconnect the platform from the ring and lower it t of it, while raising the floor to the design elevation is carried out together with the ring, and after fixing it to the shaft, lower the ring to raise the next floor. SU„, 1048093SU „, 1048093
SU823389183A 1982-02-05 1982-02-05 Method of erecting multistorey building by floor-rising technique SU1048093A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
SU823389183A SU1048093A1 (en) 1982-02-05 1982-02-05 Method of erecting multistorey building by floor-rising technique

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
SU823389183A SU1048093A1 (en) 1982-02-05 1982-02-05 Method of erecting multistorey building by floor-rising technique

Publications (1)

Publication Number Publication Date
SU1048093A1 true SU1048093A1 (en) 1983-10-15

Family

ID=20994931

Family Applications (1)

Application Number Title Priority Date Filing Date
SU823389183A SU1048093A1 (en) 1982-02-05 1982-02-05 Method of erecting multistorey building by floor-rising technique

Country Status (1)

Country Link
SU (1) SU1048093A1 (en)

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
1. Авторское свидетельство СССР № 831942, кл. Е 04 G 21/14, 1981. 2.За вка JP № 51-42851, кл. 86/4/А, 1977. 3.Авторское свидетельство СССР № 775254, кл. Е 04 В 1/35, 1978 (прототип). *

Similar Documents

Publication Publication Date Title
US3275719A (en) Method of building in situ construction using sequential molding techniques
US3239990A (en) Multi-storey buildings
EP2852724B1 (en) High rise building elevation concept
GB1451611A (en) Building construction
US3201502A (en) Method of erecting concrete structures
US10829927B2 (en) Vertical slip form construction system with multi-function platform, and method of constructing a building therewith
US3920780A (en) Method of erecting a multi-story building and apparatus
US3831902A (en) Method of erecting a multi-story building and apparatus therefor
SU1048093A1 (en) Method of erecting multistorey building by floor-rising technique
US3552080A (en) Method for erecting multistory buildings
JP5003253B2 (en) RC beam construction method
SU552395A1 (en) The method of construction of high-rise buildings
RU2716319C1 (en) Method of erection of buildings and structures
RU190322U1 (en) Device for the construction of multi-storey underground structures
SU1079785A1 (en) Method of constructing a multistorey building by adding floors from below
RU2087650C1 (en) House-building combine
RU2026941C1 (en) Method of the building erection by means of hoisting
SU730941A1 (en) Method of erecting the framework of building
SU771268A1 (en) Method of erecting a tower-type multistorey building
KR200200364Y1 (en) High building construction apparatus
RU3952U1 (en) SLIDING FORMWORK FOR ESTABLISHING WALLS AND FLOORS
SU1067174A1 (en) Sliding forms
SU773229A1 (en) Method of erecting a building from monolithic concrete
SU1534170A1 (en) Method of assembling a building in a raising process
SU962548A1 (en) Method of erecting high-rise buildings with rigidity core by the method of floor-lifting