JPH09296565A - Precast concrete column, its manufacture, and execution method - Google Patents

Precast concrete column, its manufacture, and execution method

Info

Publication number
JPH09296565A
JPH09296565A JP8114620A JP11462096A JPH09296565A JP H09296565 A JPH09296565 A JP H09296565A JP 8114620 A JP8114620 A JP 8114620A JP 11462096 A JP11462096 A JP 11462096A JP H09296565 A JPH09296565 A JP H09296565A
Authority
JP
Japan
Prior art keywords
pillar
column
block
precast concrete
steel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP8114620A
Other languages
Japanese (ja)
Inventor
Ryohei Kurosawa
亮平 黒沢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kurosawa Construction Co Ltd
Original Assignee
Kurosawa Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kurosawa Construction Co Ltd filed Critical Kurosawa Construction Co Ltd
Priority to JP8114620A priority Critical patent/JPH09296565A/en
Priority to KR1019960018132A priority patent/KR970075140A/en
Publication of JPH09296565A publication Critical patent/JPH09296565A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/30Columns; Pillars; Struts
    • E04C3/34Columns; Pillars; Struts of concrete other stone-like material, with or without permanent form elements, with or without internal or external reinforcement, e.g. metal coverings
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • B28B23/04Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members the elements being stressed
    • B28B23/043Wire anchoring or tensioning means for the reinforcements

Abstract

PROBLEM TO BE SOLVED: To improve the execution property by making split faces of a column which is split into an upper column body and a lower column block coincide with each other and arranging the column perpendicular with reference to the lower column block. SOLUTION: A PC column is split into an upper column body 2 provided with a corbel for connecting beams and a short lower column block 3, and split faces are correctly made to coincide with each other in connection. During the execution, the block 3 is fixed perpendicular on a bed mortar 13 which is placed on an upper surface of a concrete foundation 11, and an upper end of a PC bar 12 embedded in the foundation 11 is passed through the block 3. After the mortar 13 is hardened, the column body 2 is erected thereon through a temporary receiving base block 14 by a crane to connect a lower end of a PC bar 15 inserted in the column body 2 in advance to the upper end of the bar 12. The base block 14 is removed, the adhesive is applied to the block 3 to lower the column body 2, and the bar 15 is temporarily fixed to erect the column body 2 perpendicular by itself, and then, the bar is permanently tightened. Perpendicularity can be secured without using any support wire.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【発明の属する技術分野】本発明は、多層階構築物の構
築に際して使用されるプレキャストコンクリート柱(以
下,PC柱という)の内、基礎コンクリート上に立設す
るPC柱の構造、及びそのPC柱の製造方法並びにその
PC柱を使用した施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a precast concrete column (hereinafter referred to as a PC column) used in the construction of a multi-storey floor structure, a structure of a PC column standing on a concrete foundation, and a structure of the PC column. The present invention relates to a manufacturing method and a construction method using the PC pillar.

【0002】[0002]

【従来の技術】従来からPC柱を基礎上に立設して、こ
れにプレキャストコンクリート梁を剛結させて多階構築
物を構築する施工方法が種々開発されている。一般に、
PC柱の建方の従来の方法としては、ほとんどの場合P
C柱を既設の現場打ちコンクリート基礎上に立設するよ
うにしている。
2. Description of the Related Art Conventionally, various construction methods have been developed in which a PC column is erected on a foundation and a precast concrete beam is rigidly connected to this to construct a multi-story structure. In general,
In most cases, the conventional method of erection of PC columns is P
The C pillar is erected on the existing cast-in-place concrete foundation.

【0003】従来例の一例としては、図6に示したよう
に、現場打ちのコンクリート基礎aの上面に柱埋設孔b
を開口させておき、その柱埋設孔b中にPC柱cの下端
部を挿着して直立させ、四方からの支えワイヤーdによ
って鉛直度を見ながら、PC柱cと柱埋設孔bとの隙間
に矢eを打ち込んで仮り止めし、更にPC柱と柱埋設孔
bとの隙間に、モルタルまたはコンクリートのような充
填材fを詰め、該充填材が硬化することによってPC柱
cとコンクリート基礎aとを一体化させてPC柱cを自
立させている。
As an example of a conventional example, as shown in FIG. 6, a pillar burying hole b is formed on the upper surface of a cast-in-place concrete foundation a.
Is opened, the lower end of the PC pillar c is inserted into the pillar embedding hole b to stand upright, and the PC pillar c and the pillar embedding hole b are An arrow e is driven into the gap to temporarily fix it, and a filler f such as mortar or concrete is filled in the gap between the PC column and the column embedding hole b, and when the filler is hardened, the PC column c and the concrete foundation. The PC pillar c is made independent by integrating with a.

【0004】また、他の例として、図7に示すように、
現場打ちコンクリート基礎aにPC鋼棒gの一端側を埋
め込み固定し、その他端を現場打ちコンクリート基礎a
上に突出させておき、PC柱cにはPC鋼棒hを長手方
向に挿通し、その下端をPC柱cの下端面の凹欠部j内
に突出させておき、このPC柱cを敷モルタルkを介し
て基礎aの上面に立て、支えワイヤーdによって鉛直度
を調節すると共に、基礎a側のPC鋼棒gとPC柱c側
のPC鋼棒hとを凹欠部j内でカプラーmをもって連結
し、PC鋼棒hをP柱cの上端に緊張して定着させ、P
C柱cに縦向きのプレストレスを導入して自立させ、凹
欠部jを後打ちモルタルにて埋めるようにしたものであ
る。
As another example, as shown in FIG.
One end side of the PC steel bar g is embedded and fixed in the cast-in-place concrete foundation a and the other end is cast-in-place concrete foundation a.
The PC steel rod h is inserted in the PC pillar c in the longitudinal direction, and the lower end thereof is made to protrude into the recess j of the lower end surface of the PC pillar c. It stands on the upper surface of the foundation a through the mortar k, the verticality is adjusted by the supporting wire d, and the PC steel bar g on the side of the foundation a and the PC steel bar h on the side of the PC column c are coupled in the recess j. m to connect, and the PC steel bar h is tensioned and fixed to the upper end of the P column c,
A vertical pre-stress is introduced into the C pillar c to make it self-sustaining, and the recessed portion j is filled with post-cast mortar.

【0005】[0005]

【発明が解決しようとする課題】上述のような従来の施
工方法では、それぞれPC柱の建て方に際して鉛直度の
補正は周囲の支えワイヤーの長さの調整によって行われ
るが、建物の階層が多くなるとPC柱は重量が増し、鉛
直度の補正が難しく、また施工時間も長くなり非能率的
なものである。そして、この間にPC柱の周囲に張り巡
らされた長い斜めの支えワイヤーは他の作業の障害とな
り、作業環境を悪化させている。
In the conventional construction method as described above, the verticality is corrected by adjusting the lengths of the supporting wires around the PC pillars, but many building layers are used. In this case, the weight of the PC column increases, it is difficult to correct the verticality, and the construction time becomes long, which is inefficient. In addition, the long diagonal support wires stretched around the PC pillar during this period hinder other work and deteriorate the work environment.

【0006】また、前述した柱埋設孔を設ける施工方法
では、その柱埋設孔の周囲の基礎コンクリートの強度を
大きくしておく必要があるが、現場打ちコンクリート施
工であるために強度を発現させる管理が困難であり、柱
埋設孔が深く孔の底部の水平度を確保することも難しか
った。
Further, in the construction method for providing the pillar burying hole described above, it is necessary to increase the strength of the basic concrete around the pillar burying hole. However, it was difficult to secure the horizontality of the bottom of the hole because the pillar burial hole was deep.

【0007】さらに、前述したPC鋼棒を用いる方法で
は、現地における自立前の支えワイヤーを張り巡らされ
たPC柱の頂部でPC鋼棒の緊張作業が必要となり、作
業の危険性が高く、またPC柱の下端部にはPC鋼棒を
連結するための作業空間となる凹欠部を設ける必要があ
るので、これを補うためにはPC柱の断面を大きくする
必要が生じるという問題があった。
Further, in the method using the above-mentioned PC steel rod, the work of tensioning the PC steel rod is required at the top of the PC pillar stretched around the supporting wire before the self-supporting in the field, and the work risk is high, and Since it is necessary to provide a concave portion serving as a working space for connecting the PC steel rods at the lower end portion of the PC column, there is a problem that it is necessary to increase the cross section of the PC column in order to compensate for this. .

【0008】従って、従来例においては、自立させたP
C柱の鉛直度の補正を作業的にも構成的にも簡略化する
こと、作業環境を良くし施工性の向上を図ること、に解
決しなければならない課題を有している。
Therefore, in the conventional example, the self-standing P
There are problems that must be solved in order to simplify the correction of the verticality of the C pillar both in terms of work and structure and to improve the work environment and improve workability.

【0009】[0009]

【課題を解決するための手段】前記従来例の課題を解決
する具体的な手段として、本発明はまず第1に、プレキ
ャストコンクリート柱を上部柱体と下部柱ブロックとに
分割して形成し、これら上部柱体と下部柱ブロックとを
連結させたときに垂直な一本の柱になるように、前記分
割面が一致していることを特徴とするプレキャストコン
クリート柱を提供することである。そして、前記上部柱
体と下部柱ブロックとに少なくともPC鋼材が挿通され
るシースが埋設されている構成であること、及び前記上
部柱体には、コーベルが一体に形成されているプレキャ
ストコンクリート柱を含むものである。
As a concrete means for solving the above-mentioned problems of the conventional example, the present invention firstly forms a precast concrete column by dividing it into an upper column body and a lower column block, It is to provide a precast concrete column characterized in that the dividing surfaces are aligned so as to form one vertical column when the upper column body and the lower column block are connected. The upper pillar and the lower pillar block each have a structure in which a sheath into which at least PC steel is inserted is embedded, and the upper pillar includes a precast concrete pillar integrally formed with a corbel. It includes.

【0010】第2に、プレキャストコンクリート柱を成
型する一体の型枠内に、所定の分割手段を設けて上部柱
体と下部柱ブロックとを分割した状態で同時に成型する
ことを特徴とするプレキャストコンクリート柱の製造方
法を提供するものである。そして、前記分割手段は、板
材またはシート材であること、及び型枠内の所定位置
に、PC鋼材が挿通されるシースをセットしてコンクリ
ートを打設する方法も含むものである。
Secondly, the precast concrete is characterized in that a predetermined dividing means is provided in the integral formwork for molding the precast concrete column, and the upper column body and the lower column block are simultaneously molded in the divided state. A method for manufacturing a pillar is provided. Further, the dividing means includes a plate material or a sheet material, and a method of setting a sheath into which a PC steel material is inserted and setting concrete at a predetermined position in the mold.

【0011】第3に、予め構築した現場打ちコンクリー
ト基礎にプレキャストコンクリート柱を連続させてPC
鋼材を接続し、該PC鋼材を緊張して既設現場打ちコン
クリート基礎とプレキャストコンクリート柱とを一体化
させたプレキャストコンクリート柱の立設方法であっ
て、前記プレキャストコンクリート柱は合せ面が一致す
る上部柱体と下部柱ブロックとに分割されたものを使用
し、前記現場打ちコンクリート基礎上に下部柱ブロック
の鉛直面を基準にして据え付け、その下部柱ブロック上
に上部柱体の分割面を合せて設置し、上部柱体のPC鋼
棒を下部柱ブロックのPC鋼棒に接続して所定の緊張力
を付与することを特徴とするプレキャストコンクリート
柱の施工方法を提供するものである。そして、現場打ち
コンクリート基礎上に設置した下部柱ブロック及び上部
柱体上に、上位のプレキャストコンクリート柱を順次連
結して立設する施工方法も含むものである。
Thirdly, a precast concrete column is continuously connected to a pre-constructed cast-in-place concrete foundation to form a PC.
A method for standing a precast concrete column in which steel materials are connected and the PC steel material is tensioned to integrate an existing cast-in-place concrete foundation and a precast concrete column, wherein the precast concrete column is an upper column whose mating surfaces match. Use the one divided into the body and the lower pillar block, and install it on the cast-in-place concrete foundation with the vertical plane of the lower pillar block as the reference, and install the divided surface of the upper pillar body on the lower pillar block. Then, the construction method of the precast concrete column is characterized in that the PC steel rod of the upper column body is connected to the PC steel rod of the lower column block to give a predetermined tension force. Further, it also includes a construction method in which the upper precast concrete columns are sequentially connected and erected on the lower column block and the upper column body installed on the cast-in-place concrete foundation.

【0012】本発明に係るPC柱は、上部柱体と下部柱
ブロックとを分割し、その分割面が一致するように形成
したことにより、柱の建て込みにおいて、重量が少なく
取り扱いが容易な下部柱ブロックを現場打ちコンクリー
ト基礎の上面に先に設置し、その設置の際に、正確な建
て込み位置と鉛直度とを容易に調整することができ、さ
らに、その下部柱ブロックの上に載せて上部柱体を継ぎ
足すだけであるから、作業性がより一層簡便になるので
ある。
In the PC pillar according to the present invention, the upper pillar body and the lower pillar block are divided, and the divided surfaces are formed so as to coincide with each other. The pillar block is first installed on the top surface of the cast-in-place concrete foundation, and at the time of installation, the exact building position and verticality can be easily adjusted. The workability is further simplified because the upper column is simply added.

【0013】また、上部柱体と下部柱ブロックとを分割
する際に、型枠内に仕切板などの分割手段を介在させ
て、1本の柱として形成できるので、分割面が完全に一
致した状態で効率良く形成できるのである。
Further, when the upper pillar body and the lower pillar block are divided, they can be formed as one pillar by interposing a dividing means such as a partition plate in the form, so that the dividing surfaces are completely coincident with each other. It can be formed efficiently in this state.

【0014】更に、本発明のPC柱を使用して施工を行
う場合に、軽量な下部柱ブロックをコンクリート基礎の
上面に敷モルタルを介し正確な鉛直度をもって設置する
ことができ、しかも、支えワイヤー等を四周に張り巡ら
す必要がないので、作業環境を悪化させることがなく、
敷モルタルが乾燥した後に、下部柱ブロックに上部柱体
をそのまま上載することによって自動的に鉛直度が出せ
て、PC柱の自立を容易に施工できるのである。
Further, when the PC pillar of the present invention is used for construction, a lightweight lower pillar block can be installed on the upper surface of the concrete foundation with accurate verticality through the mortar and the supporting wire can be installed. Since it is not necessary to stretch all four around, it does not deteriorate the working environment,
After the floor mortar has dried, the vertical pillar can be automatically provided by directly mounting the upper pillar body on the lower pillar block, so that the PC pillar can be easily self-supporting.

【0015】[0015]

【発明の実施の形態】次に、本発明を図示の実施例によ
り更に詳しく説明する。まず、図1は本発明に係るプレ
キャストコンクリート柱、即ちPC柱1を示すものであ
り、該PC柱1は上部柱体2と下部柱ブロック3とに分
割した構成になっている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS The present invention will be described in more detail with reference to the illustrated embodiments. First, FIG. 1 shows a precast concrete column according to the present invention, that is, a PC column 1. The PC column 1 is divided into an upper column body 2 and a lower column block 3.

【0016】この場合に、上部柱体2と下部柱ブロック
3の分割面は、両者を連結したときにピッタリと一致
し、1本の柱として歪みが全く生じないで全体が鉛直に
なるように形成してある。つまり、1本のPC柱1を上
下に分割したものであるから、その分割面が一致してお
り、両者を突き合わせれば分割面が完全にフィットして
歪みのない元の柱に復元できるという理屈になるのであ
る。
In this case, the divided surfaces of the upper columnar body 2 and the lower columnar block 3 are exactly the same when they are connected to each other so that the entire column is vertical without any distortion. Has been formed. In other words, since one PC pillar 1 is divided into upper and lower parts, the divided surfaces are the same, and if the two are abutted, the divided surfaces fit perfectly and can be restored to the original column without distortion. It makes sense.

【0017】そして、上部柱体2と下部柱ブロック3と
の分割比率は、10:0.3〜1程度であり、下部柱ブ
ロック3は作業性及び取り扱いの容易性を考慮して比較
的短く形成されている。なお、上部柱体2には梁を載せ
て接続するためのコーベル4が形成してある。このコー
ベル4は、PC柱1の使用部所によってその数が違って
くるが、少なくとも2方向以上に形成される。
The division ratio between the upper pillar 2 and the lower pillar block 3 is about 10: 0.3 to 1, and the lower pillar block 3 is relatively short in consideration of workability and easiness of handling. Has been formed. A corbel 4 for mounting and connecting a beam is formed on the upper column 2. The corbels 4 are formed in at least two directions, although the number thereof varies depending on the use part of the PC pillar 1.

【0018】これら上部柱体2及び下部柱ブロック3内
には、所要の鉄筋が埋設されていると共に、プレストレ
スを付与するPC鋼棒を挿通するための複数本のシース
が埋設され、これらシースの各端部が、各柱ブロックの
上下端において露出させてある。
In the upper column body 2 and the lower column block 3, required rebars are embedded, and a plurality of sheaths for inserting a PC steel rod to which prestress is inserted are embedded. Each end of the column block is exposed at the upper and lower ends of each column block.

【0019】前記PC柱1を製造する場合には、図2に
示したように、所定の型枠5を用いて製造する。この場
合に、PC柱1の下部となる側の所定位置に、分割手段
としての仕切板6を介在させると共に、必要な金具や鉄
筋及びシース等を挿入してコンクリートを打設する。な
お、7はコーベル4の形成部である。
When the PC pillar 1 is manufactured, as shown in FIG. 2, it is manufactured by using a predetermined mold 5. In this case, a partition plate 6 as a dividing means is interposed at a predetermined position on the lower side of the PC column 1, and necessary metal fittings, reinforcing bars, sheaths, etc. are inserted and concrete is poured. In addition, 7 is a forming part of the corbel 4.

【0020】この場合の所定位置は、例えば、PC柱の
下端部側を形成する端部側から30〜50cm程度の位
置であり、上部柱体2と下部柱ブロック3との分割面と
なる位置であり、PC柱1の長さに対応して決定される
が、下部柱ブロック3をあまり短くすると施工時におい
て鉛直度が出し難いし、余り長くすると重量が嵩んで施
工時の取り扱いに不便である。従って、取り扱い及び鉛
直度を出す上で不都合を生じない範囲の長さに設定すれ
ば良いのである。
In this case, the predetermined position is, for example, a position of about 30 to 50 cm from the end side forming the lower end side of the PC pillar, and is a position serving as a dividing surface between the upper pillar body 2 and the lower pillar block 3. It is determined according to the length of the PC pillar 1, but if the lower pillar block 3 is too short, it is difficult to obtain the verticality at the time of construction, and if it is too long, the weight becomes heavy and it is inconvenient to handle at the time of construction. is there. Therefore, the length should be set within a range that does not cause any inconvenience in handling and verticality.

【0021】型枠5内に打設したコンクリートの養生が
完了した後に、上部柱体2と下部柱ブロック3とをそれ
ぞれ型枠5から脱型して分離する。しかしながら、一つ
の型枠で一緒に形成した上部及び下部柱ブロックは、飽
くまでも1本の柱体として取り扱われるものであり、原
則として他の型枠で形成したものとは組み代えることは
しない。
After the curing of the concrete cast in the mold 5 is completed, the upper pillar 2 and the lower pillar block 3 are released from the mold 5 and separated. However, the upper and lower pillar blocks formed together by one formwork are treated as one pillar body even if tired, and in principle, they cannot be replaced with those formed by other formwork.

【0022】なお、分割手段としての仕切板6を入れる
代わりに、シート状のもので仕切りを入れたり、あるい
は一本もののPC柱1をコンクリートカッターやウオー
タジェツトで切断して下部柱ブロック3を分離させて形
成しても同様な構成になる。いずれにしても、予め仕切
板その他の分割代の分を除外して、形成されるPC柱1
の長さ寸法を正確に設定し、型枠5の大きさ等を設定す
るようにしなければならないことは当然である。
Instead of inserting a partition plate 6 as a dividing means, a sheet-like partition may be inserted, or a single PC pillar 1 may be cut with a concrete cutter or water jet to separate the lower pillar block 3. The same structure can be obtained by forming them. In any case, the PC column 1 is formed by excluding the partition plate and other division allowances in advance.
Of course, it is necessary to accurately set the length dimension of and to set the size and the like of the formwork 5.

【0023】このようにして形成した本発明のPC柱1
を使用した施工については、図3〜6を参照しながら説
明する。まず、図3に示したように、施工現場におい
て、例えば、基礎杭10の上に現場打ちコンクリート基
礎11が構築され、その上面部分11aは所定の水平度
をもって構築される。
The PC pillar 1 of the present invention thus formed
Construction using will be described with reference to FIGS. First, as shown in FIG. 3, at a construction site, for example, a cast-in-place concrete foundation 11 is constructed on a foundation pile 10, and an upper surface portion 11a thereof is constructed with a predetermined levelness.

【0024】そのコンクリート基礎11の構築の際に、
コンクリート基礎11内に複数本のPC鋼棒12を整列
させて縦方向に埋設し、その上端部をコンクリート基礎
11の上面から所定長さ突出させてある。
When constructing the concrete foundation 11,
A plurality of PC steel rods 12 are aligned and embedded in the concrete foundation 11 in a vertical direction, and an upper end portion of the PC steel rods 12 is projected from the upper surface of the concrete foundation 11 by a predetermined length.

【0025】このコンクリート基礎11の上面部分11
aに、敷モルタル13を所定の厚さ敷き均し、その上に
下部柱ブロック3を設置し、水平または鉛直になるよう
に調整する。この場合に、図4に示したように、コンク
リート基礎11の上面から突出しているPC鋼棒12を
下部柱ブロック3内に配設した対応するシース3aにそ
れぞれ挿通させて下部柱ブロック3を設置する。
The upper surface portion 11 of this concrete foundation 11
The floor mortar 13 is laid on the surface a and spread to a predetermined thickness, and the lower pillar block 3 is placed on the floor mortar 13 and adjusted so as to be horizontal or vertical. In this case, as shown in FIG. 4, the PC steel rods 12 protruding from the upper surface of the concrete foundation 11 are respectively inserted into the corresponding sheaths 3a arranged in the lower column block 3 to install the lower column block 3. To do.

【0026】そして、敷モルタル13の上で下部柱ブロ
ック3の設置状態の水平度及び鉛直度を精度良く充分に
調整して静置し、敷モルタル13の硬化を待つ。敷モル
タル13の硬化終了後の所定の強度発現をみて、その上
面に仮受け台木14を中央部に置き、前記上部柱体2を
クレーン等の重機を用いて立てる。
Then, the level and verticality of the installed state of the lower pillar block 3 are accurately and sufficiently adjusted on the floor mortar 13 and allowed to stand, and the curing of the floor mortar 13 is waited. After observing a predetermined strength after the floor mortar 13 is hardened, a temporary receiving base 14 is placed on the upper surface of the mortar 13 at the center and the upper column 2 is erected using a heavy machine such as a crane.

【0027】上部柱体2には、他の複数本のPC鋼棒1
5の挿通する各孔がシース2aによって形成され、その
下端はカプラーシース2bによって拡径され、図5に示
した長ナット16が収まるようになっている。前記PC
鋼棒15は、ナットと座金付きで予め上部柱体2内に挿
通しておき、仮受け台木14に上部柱体2を載せて立て
たときに、PC鋼棒15は上部柱体2の下部から所定長
さ突出するようになっている。
The upper column 2 has a plurality of other PC steel rods 1
The holes 5 are formed by the sheath 2a, and the lower end of the hole is expanded by the coupler sheath 2b so that the long nut 16 shown in FIG. 5 can be accommodated. The PC
The steel rod 15 with a nut and a washer is previously inserted into the upper columnar body 2, and when the upper columnar body 2 is placed on the temporary receiving base 14 and stood upright, the PC steel rod 15 is attached to the upper columnar body 2. It is designed to project from the lower portion for a predetermined length.

【0028】この状態で下部柱ブロック3に挿通させた
PC鋼棒12の上端に長ナット16をねじ込み、長ナッ
ト16の下部の半分を螺着させる。そして、長ナット1
6の上部半分は、上部柱体2の下端から突出している他
のPC鋼棒15の下端と螺着させ、各対応する夫々のP
C鋼棒を一連に接続させる。
In this state, the long nut 16 is screwed into the upper end of the PC steel rod 12 inserted through the lower column block 3, and the lower half of the long nut 16 is screwed. And long nut 1
The upper half of 6 is screwed to the lower ends of the other PC steel rods 15 protruding from the lower end of the upper columnar body 2, and the corresponding P
C steel rods are connected in series.

【0029】そして、対応する上部柱体2のPC鋼棒1
5と下部柱ブロック3のPC鋼棒12との接続が全部終
了した後に、上部柱体2を吊っているクレーン等の重機
を駆動して上部柱体2を若干持ち上げ、仮受け台木14
を外してから、下部柱ブロック3の上面に接着剤を塗布
し、クレーン等の重機を駆動して上部柱体2を垂直に降
ろし、下部柱ブロック3との分割面を結合させると、分
割面がピッタリ一致して一本のPC柱1を形成し、上部
柱体2の上部において、該上部柱体2が自立できる程度
の緊張力で各PC鋼棒15を仮定着する。この仮定着に
よって、各上部柱体2は、支えワイヤーを必要とせず
に、適正な状態で設計通りに自立することが出来るので
ある。
Then, the corresponding PC steel rod 1 of the upper column 2
After all the connection between 5 and the PC steel rod 12 of the lower pillar block 3 is completed, a heavy machine such as a crane that suspends the upper pillar body 2 is driven to slightly lift the upper pillar body 2 and the temporary receiving base 14
After removing, the adhesive is applied to the upper surface of the lower pillar block 3, the heavy equipment such as a crane is driven to vertically lower the upper pillar body 2, and the dividing surface with the lower pillar block 3 is joined. Form a single PC column 1 in close agreement with each other, and each PC steel rod 15 is hypothetically attached to the upper part of the upper column 2 with a tension force enough to make the upper column 2 self-supporting. By this hypothetical attachment, each upper column 2 can be self-supported as designed in an appropriate state without the need for a supporting wire.

【0030】このように自立させた上部柱体2と下部柱
ブロック3は、分割面が結合することで、全体的に極め
て精度の高い鉛直度をもって自立するようになる。その
後の本緊張は、前後左右の梁17をコーベル4に載せて
から行うとか、状況に合わせて元応力を発生しない緊張
をする。そして、PC鋼棒12,15とシース2a,3
aとの間隙、及びカプラーシース2bの空隙等は、本緊
張終了後にグラウトを注入し、硬化させてPC柱1の自
立施工を終わる。
The upper pillar body 2 and the lower pillar block 3 which are self-supporting as described above, become self-supporting as a whole with extremely high verticality by joining the division surfaces. The subsequent main tension is performed after the front, rear, left, and right beams 17 are placed on the corbel 4, or the tension is set so that the original stress is not generated according to the situation. Then, the PC steel rods 12 and 15 and the sheaths 2a and 3
After completion of the main tension, grout is injected into the gap with respect to a, the gap of the coupler sheath 2b, and the like, and the grout is cured to complete the self-supporting construction of the PC column 1.

【0031】各上部柱体2が自立した後に、図6で示し
たように、上層階を構成する他の柱体18が順次各上部
柱体2の上部に接着剤を介して継ぎ足され、前記PC鋼
材を長ナット16で連結したと同様の結合手段により一
連に連結される。そして、各階層毎に適宜の梁19を掛
け渡すと共に、床スラブ20などを施工して順次各階層
を構築していく。
After each upper pillar 2 is self-supporting, as shown in FIG. 6, another pillar 18 constituting the upper floor is sequentially added to the upper part of each upper pillar 2 via an adhesive, The PC steel materials are connected in series by the same connecting means as the long nut 16. Then, an appropriate beam 19 is laid over each layer, and a floor slab 20 is constructed to build each layer sequentially.

【0032】前記したように1階を構成する基礎となる
PC柱1の鉛直度を正確に確立することにより、その上
に継ぎ足される上層階のPC柱も正確な鉛直度をもって
自立するようになり、建造物が予定した設計通りに正し
く構築される。そして、PC柱の建て込みに作業におい
て、最初に重量が少なく取り扱いが容易な下部柱ブロッ
ク3を設置するだけであり、鉛直度を出すための支えワ
イヤーなどを四周に張り巡らせる必要がないことから、
作業性が著しく良好であると共に、他の作業を行う上で
全く支障を来さないのである。
As described above, by accurately establishing the verticality of the base PC pillar 1 that constitutes the first floor, the PC pillars on the upper floors that are added to it can also be self-supporting with the correct verticality. , The building is built correctly as planned. Then, in the work of building the PC pillar, only the lower pillar block 3 which is light in weight and easy to handle is first installed, and it is not necessary to stretch the supporting wires and the like around the four circumferences to obtain the verticality. ,
The workability is remarkably good, and there is no hindrance when performing other work.

【0033】また、最初に適正位置に正しく設置した下
部柱ブロック3上に、分割面を介して上部柱体2を継ぎ
足すだけであるから、正確な鉛直度が維持されて、しか
も、効率良く行えるようになり、施工期間を短縮できる
のである。
Further, since the upper columnar body 2 is simply added to the lower column block 3 which is correctly installed at the proper position at the beginning through the dividing surface, accurate verticality can be maintained and efficiently. It can be done and the construction period can be shortened.

【0034】[0034]

【発明の効果】以上説明したように、本発明に係るPC
柱は、プレキャストコンクリート柱を上部柱体と下部柱
ブロックとに分割して形成し、これら上部柱体と下部柱
ブロックとを連結させたときに垂直な一本の柱になるよ
うに、前記分割面が一致している構成にしたことによ
り、上部柱体と下部柱ブロックとを別々に取り扱うこと
ができ、しかも、下部柱ブロックは取り扱いが容易であ
ることから、現場打ちコンクリート基礎の上面に適正な
鉛直度をもって簡単に設置でき、その上に上部柱体を継
ぎ足して自立させることができるので、PC柱の施工性
が著しく容易になるという優れた効果を奏する。
As described above, the PC according to the present invention is used.
The pillar is formed by dividing a precast concrete pillar into an upper pillar body and a lower pillar block, and when the upper pillar body and the lower pillar block are connected to each other, the pillar is divided into a single vertical pillar. Since the surfaces are aligned, the upper column and the lower column block can be handled separately, and the lower column block is easy to handle, so it is suitable for the top surface of a cast-in-place concrete foundation. Since it can be easily installed with a high degree of verticality, and an upper pillar can be added to it to make it self-sustaining, the workability of the PC pillar can be remarkably facilitated.

【0035】また、本発明に係るPC柱の製造方法は、
プレキャストコンクリート柱を成型する一体の型枠内
に、所定の分割手段を設けて上部柱体と下部柱ブロック
とを分割した状態で同時に成型するようにしたことによ
り、分割面が一致し、柱体として連結したときに、連結
部分に歪みまたは角度的なずれのない、所謂鉛直度が維
持されているセットになったPC柱が簡単に製造できる
という優れた効果を奏する。
Further, the method for manufacturing a PC pillar according to the present invention is
By dividing the upper pillar and the lower pillar block at the same time by providing a predetermined dividing means in the integrated formwork for molding the precast concrete pillar, the dividing surfaces are aligned and the pillar body When connected as described above, there is an excellent effect that a PC column having a set in which the so-called verticality is maintained without distortion or angular deviation in the connected portion can be easily manufactured.

【0036】更に、本発明に係るPC柱を使用した施工
方法は、予め構築した現場打ちコンクリート基礎にプレ
キャストコンクリート柱を連続させてPC鋼材を接続
し、該PC鋼材を緊張して既設現場打ちコンクリート基
礎とプレキャストコンクリート柱とを一体化させたプレ
キャストコンクリート柱の立設方法であって、前記プレ
キャストコンクリート柱は合せ面が合致する上部柱体と
下部柱ブロックとに分割されたものを使用し、前記現場
打ちコンクリート基礎上に下部柱ブロックの鉛直面を基
準にして据え付け、その下部柱ブロック上に上部柱体の
分割面を合せて設置し、上部柱体のPC鋼棒を下部柱ブ
ロックのPC鋼棒に接続して所定の緊張力を付与するよ
うにしたことにより、最初に重量が少なく且つ取り扱い
が容易な下部柱ブロックを設置して鉛直度を出し、その
上に上部柱体を連結するだけであるから、鉛直度を出す
ための支えワイヤーなどを四周に張り巡らせる必要がな
く、作業性が著しく良好であると共に、他の作業を行う
上で全く邪魔にならず、安全性に優れるという効果を奏
する。
Further, in the construction method using the PC column according to the present invention, the precast concrete column is continuously connected to the pre-constructed cast-in-place concrete foundation to connect the PC steel material, and the PC steel material is tensioned to make the existing cast-in-place concrete. A method of standing a precast concrete column in which a foundation and a precast concrete column are integrated, wherein the precast concrete column is divided into an upper column body and a lower column block whose mating surfaces match, It is installed on the cast-in-place concrete foundation with the vertical plane of the lower pillar block as a reference, and the divided surface of the upper pillar is installed on the lower pillar block, and the PC steel rod of the upper pillar is PC steel of the lower pillar block. By connecting to the rod and applying a predetermined tension force, the lower column block which is light in weight and easy to handle is initially used. It is not necessary to tie support wires for verticality all around because it is necessary to set up the vertical poles and connect the upper pillars on it. , It has an effect of being excellent in safety without any hindrance in performing other work.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明に係る一実施例のPC柱の側面図であ
る。
FIG. 1 is a side view of a PC column according to an embodiment of the present invention.

【図2】同実施例のPC柱を製造する型枠を略示的に示
した平面図である。
FIG. 2 is a plan view schematically showing a mold for manufacturing the PC column of the embodiment.

【図3】同実施例のPC柱を使用した施工状況を示す要
部の拡大断面図である。
FIG. 3 is an enlarged cross-sectional view of a main part showing a construction situation using the PC column of the embodiment.

【図4】同実施例の下部柱ブロックをコンクリート基礎
に取り付けた状態の平面図である。
FIG. 4 is a plan view showing a state where the lower pillar block of the embodiment is attached to a concrete foundation.

【図5】同実施例におけるPC柱のPC鋼材を連結する
長ナットの側面図である。
FIG. 5 is a side view of a long nut that connects the PC steel materials of the PC column in the embodiment.

【図6】同実施例のPC柱を用いて複数階を構築する状
況を略示的に示した側面図である。
FIG. 6 is a side view schematically showing a situation in which a plurality of floors are constructed using the PC columns of the embodiment.

【図7】従来のPC柱を使用した一例の施工状況を示す
略示的側面図である。
FIG. 7 is a schematic side view showing a construction situation of an example using a conventional PC pillar.

【図8】従来のPC柱を使用した他の例の施工状況を示
す略示的側面図である。
FIG. 8 is a schematic side view showing a construction situation of another example using a conventional PC pillar.

【符号の説明】[Explanation of symbols]

1 PC柱 2 上部柱体 2a,3a シース 2b カプラーシース 3 下部柱ブロック 4 コーベル 5 型枠 6 分割手段の仕切板 7 コーベル形成部 10 基礎杭 11 コンクリート基礎 11a 上面部分 12,15 PC鋼材 14 仮受け台木 16 長ナット 17,19 梁 18 他のPC柱 DESCRIPTION OF SYMBOLS 1 PC pillar 2 Upper pillar body 2a, 3a Sheath 2b Coupler sheath 3 Lower pillar block 4 Corbel 5 Formwork 6 Partitioning plate 7 Corbel forming part 10 Foundation pile 11 Concrete foundation 11a Top part 12, 15 PC steel material 14 Temporary receiving Rootstock 16 Long nuts 17, 19 Beams 18 Other PC columns

───────────────────────────────────────────────────── フロントページの続き (51)Int.Cl.6 識別記号 庁内整理番号 FI 技術表示箇所 E04G 21/14 E04G 21/14 ──────────────────────────────────────────────────続 き Continued on the front page (51) Int.Cl. 6 Identification number Agency reference number FI Technical display location E04G 21/14 E04G 21/14

Claims (8)

【特許請求の範囲】[Claims] 【請求項1】 プレキャストコンクリート柱を上部柱体
と下部柱ブロックとに分割して形成し、これら上部柱体
と下部柱ブロックとを連結させたときに垂直な一本の柱
になるように、前記分割面が一致していることを特徴と
するプレキャストコンクリート柱。
1. A precast concrete pillar is formed by dividing it into an upper pillar and a lower pillar block, and when the upper pillar and the lower pillar block are connected to each other, a vertical pillar is formed. A precast concrete column, characterized in that the dividing surfaces are the same.
【請求項2】 上部柱体と下部柱ブロックとに少なくと
もPC鋼材が挿通されるシースが埋設されている請求項
1に記載のプレキャストコンクリート柱。
2. The precast concrete pillar according to claim 1, wherein a sheath into which at least a PC steel material is inserted is buried in the upper pillar and the lower pillar block.
【請求項3】 上部柱体には、コーベルが一体に形成さ
れている請求項1または2に記載のプレキャストコンク
リート柱。
3. The precast concrete pillar according to claim 1, wherein a corbel is integrally formed on the upper pillar.
【請求項4】 プレキャストコンクリート柱を成型する
一体の型枠内に、所定の分割手段を設けて上部柱体と下
部柱ブロックとを分割した状態で同時に成型することを
特徴とするプレキャストコンクリート柱の製造方法。
4. A precast concrete pillar, characterized in that a predetermined dividing means is provided in an integral mold for molding the precast concrete pillar, and the upper pillar body and the lower pillar block are simultaneously molded in a divided state. Production method.
【請求項5】 分割手段は、板材またはシート材である
請求項1に記載のプレキャストコンクリート柱の製造方
法。
5. The method for manufacturing a precast concrete column according to claim 1, wherein the dividing means is a plate material or a sheet material.
【請求項6】 型枠内の所定位置に、PC鋼材が挿通さ
れるシースをセットしてコンクリートを打設する請求項
4または5に記載のプレキャストコンクリート柱の製造
方法。
6. The method for producing a precast concrete column according to claim 4, wherein a sheath into which the PC steel material is inserted is set at a predetermined position in the mold and concrete is placed.
【請求項7】 予め構築した現場打ちコンクリート基礎
にプレキャストコンクリート柱を連続させてPC鋼材を
接続し、該PC鋼材を緊張して既設現場打ちコンクリー
ト基礎とプレキャストコンクリート柱とを一体化させた
プレキャストコンクリート柱の立設方法であって、前記
プレキャストコンクリート柱は合せ面が一致する上部柱
体と下部柱ブロックとに分割されたものを使用し、前記
現場打ちコンクリート基礎上に下部柱ブロックの鉛直面
を基準にして据え付け、その下部柱ブロック上に上部柱
体の分割面を合せて設置し、上部柱体のPC鋼棒を下部
柱ブロックのPC鋼棒に接続して所定の緊張力を付与す
ることを特徴とするプレキャストコンクリート柱の施工
方法。
7. A precast concrete in which a precast concrete column is connected to a preconstructed cast-in-place concrete foundation to connect PC steel, and the PC steel is tensioned to integrate the existing cast-in-place concrete foundation and the precast concrete column. A method of standing a pillar, wherein the precast concrete pillar is divided into an upper pillar body and a lower pillar block whose mating surfaces match each other, and the vertical plane of the lower pillar block is placed on the cast-in-place concrete foundation. Installed as a standard, install the divided surface of the upper pillar body on the lower pillar block, and connect the PC steel rod of the upper pillar body to the PC steel rod of the lower pillar block to give a predetermined tension force. Precast concrete pillar construction method characterized by.
【請求項8】 現場打ちコンクリート基礎上に設置した
下部柱ブロック及び上部柱体上に、上位のプレキャスト
コンクリート柱を順次連結して立設する請求項7に記載
のプレキャストコンクリート柱の施工方法。
8. The method for constructing precast concrete columns according to claim 7, wherein the upper precast concrete columns are sequentially connected and erected on the lower column block and the upper column body installed on the cast-in-place concrete foundation.
JP8114620A 1996-05-09 1996-05-09 Precast concrete column, its manufacture, and execution method Pending JPH09296565A (en)

Priority Applications (2)

Application Number Priority Date Filing Date Title
JP8114620A JPH09296565A (en) 1996-05-09 1996-05-09 Precast concrete column, its manufacture, and execution method
KR1019960018132A KR970075140A (en) 1996-05-09 1996-05-28 Precast concrete column, manufacturing method and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP8114620A JPH09296565A (en) 1996-05-09 1996-05-09 Precast concrete column, its manufacture, and execution method

Publications (1)

Publication Number Publication Date
JPH09296565A true JPH09296565A (en) 1997-11-18

Family

ID=14642424

Family Applications (1)

Application Number Title Priority Date Filing Date
JP8114620A Pending JPH09296565A (en) 1996-05-09 1996-05-09 Precast concrete column, its manufacture, and execution method

Country Status (2)

Country Link
JP (1) JPH09296565A (en)
KR (1) KR970075140A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012193596A (en) * 2011-03-01 2012-10-11 Hokukon Co Ltd Inner wall support member for constituting two upper and lower tanks-type water storage tank, and two upper and lower tanks-type water storage tank using the same
CN102922590A (en) * 2012-11-08 2013-02-13 中交第一航务工程局有限公司 Precast concrete unit vertical butt matching turnover formwork process method
CN104929314A (en) * 2015-04-30 2015-09-23 中冶建工集团有限公司 Cow-leg post concrete construction method
CN110722662A (en) * 2019-09-12 2020-01-24 北京市第三建筑工程有限公司 Manufacturing method of bracket-containing type precast concrete frame column
CN111502121A (en) * 2020-04-14 2020-08-07 中铁第四勘察设计院集团有限公司 Column base joint of assembled structure and construction method thereof
CN112030753A (en) * 2020-08-18 2020-12-04 中交路桥建设有限公司 Pier column installation method for ensuring thickness of slurry of foundation of assembled pier column

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2012193596A (en) * 2011-03-01 2012-10-11 Hokukon Co Ltd Inner wall support member for constituting two upper and lower tanks-type water storage tank, and two upper and lower tanks-type water storage tank using the same
CN102922590A (en) * 2012-11-08 2013-02-13 中交第一航务工程局有限公司 Precast concrete unit vertical butt matching turnover formwork process method
CN104929314A (en) * 2015-04-30 2015-09-23 中冶建工集团有限公司 Cow-leg post concrete construction method
CN110722662A (en) * 2019-09-12 2020-01-24 北京市第三建筑工程有限公司 Manufacturing method of bracket-containing type precast concrete frame column
CN111502121A (en) * 2020-04-14 2020-08-07 中铁第四勘察设计院集团有限公司 Column base joint of assembled structure and construction method thereof
CN112030753A (en) * 2020-08-18 2020-12-04 中交路桥建设有限公司 Pier column installation method for ensuring thickness of slurry of foundation of assembled pier column

Also Published As

Publication number Publication date
KR970075140A (en) 1997-12-10

Similar Documents

Publication Publication Date Title
JPH09296565A (en) Precast concrete column, its manufacture, and execution method
JP2003336213A (en) Concrete receiving beam and method for building girder by using it
JP2000160687A (en) Construction method for composite structure and precast concrete column
JP2004250932A (en) Rapid construction method of precast structure
JP3039295B2 (en) Manufacturing method of prefabricated member of mixed structure
JPH1077607A (en) Method of executing viaduct by using pca concrete member
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JP3408629B2 (en) Precast concrete foundation structure
JP2817591B2 (en) Construction method of steel reinforced concrete building
JP2811211B2 (en) Flat slab construction method
JPH03279533A (en) Constructing method for rigid-frame type rc super-high building
JPH11181807A (en) Construction method for underground story
JP3114071B2 (en) Embedded type leg anchoring method for steel columns
JP2759131B2 (en) Foundation beam construction method for steel reinforced concrete columns
JP2759360B2 (en) Construction method of reinforced concrete building
JP2544486B2 (en) Construction method of underground beam and its upper and lower slabs.
JPH09256383A (en) Erection method of steel framed column
JP2832622B2 (en) Semi-PCa column unit for flat slab construction
JPH08105062A (en) Footing structure and executing method thereof
JPH0967858A (en) Construction method for structural steel/reinforced concrete structure
JPH05125761A (en) Constructing method of composite structure
JPH0416630A (en) Residence base construction method
JPH0692669B2 (en) Frame method using shaped steel for beam with rebar concrete structure
JPH0449330A (en) Precast reinforced concrete foundation material and foundation execution method
JPH0497020A (en) Construction of foundation of building