JP2817591B2 - Construction method of steel reinforced concrete building - Google Patents

Construction method of steel reinforced concrete building

Info

Publication number
JP2817591B2
JP2817591B2 JP5278000A JP27800093A JP2817591B2 JP 2817591 B2 JP2817591 B2 JP 2817591B2 JP 5278000 A JP5278000 A JP 5278000A JP 27800093 A JP27800093 A JP 27800093A JP 2817591 B2 JP2817591 B2 JP 2817591B2
Authority
JP
Japan
Prior art keywords
steel
steel columns
temporary
columns
erected
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP5278000A
Other languages
Japanese (ja)
Other versions
JPH07127261A (en
Inventor
浩 勝間田
晴也 川口
修治 荒木
博 森口
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP5278000A priority Critical patent/JP2817591B2/en
Publication of JPH07127261A publication Critical patent/JPH07127261A/en
Application granted granted Critical
Publication of JP2817591B2 publication Critical patent/JP2817591B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明はスパン方向に耐震壁が
配置される高層建物を構築する、鉄骨鉄筋コンクリート
造建物の構築方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a steel reinforced concrete building for constructing a high-rise building in which earthquake-resistant walls are arranged in a span direction.

【0002】[0002]

【従来技術及び発明が解決しようとする課題】高層集合
住宅等で、スパン方向と桁行方向の耐震要素がそれぞれ
耐震壁と柱・梁のフレームである鉄骨鉄筋コンクリート
造建物の構築方法は、鉄骨柱の継手を各層に配置し、鉄
骨柱を立設する毎に下層から柱・梁及び壁と床スラブの
配筋とコンクリートの打設によって上層へ施工していく
方法と、数層分の長さを持つ鉄骨柱を建物の最上層まで
先行して立設,接続した後に下層から上層へ配筋とコン
クリートの打設をしていく方法に大別される。
2. Description of the Related Art In a high-rise apartment house or the like, a method of constructing a steel-framed reinforced concrete building in which the seismic elements in the span direction and the girder direction are a shear wall and a frame of columns and beams, respectively, is known. Each time a steel column is erected, the joints are placed on each layer and the upper layer is constructed by placing columns, beams, walls and floor slabs and placing concrete from the lower layer, and the length of several layers Steel pillars are first erected and connected to the top of the building, connected, and then laid out from the bottom to the top, and concrete is poured.

【0003】前者の方法は鉄骨柱の建方が層毎に分断す
るため、クレーン等の仮設費が上昇する他、工期が長期
化する傾向があり、後者の方法は長辺化した鉄骨柱の自
立性を確保するための大断面の鉄骨梁を架設する必要が
あるため、工費が上がり、また鉄骨柱が先行することに
よる高所作業を伴うため、安全対策に充てる費用も上が
る。
[0003] In the former method, since the construction of the steel column is divided into layers, the temporary construction cost of a crane and the like tends to increase, and the construction period tends to be longer. The latter method requires the steel column having a longer side. It is necessary to lay a steel beam with a large cross section to ensure independence, which increases construction costs. In addition, steel columns are required to work at heights, leading to higher costs for safety measures.

【0004】この発明は上記背景を踏まえてなされたも
ので、工費を低減し、工期を短縮する構築方法を提案す
るものである。
[0004] The present invention has been made in view of the above background, and proposes a construction method that reduces the construction cost and the construction period.

【0005】[0005]

【課題を解決するための手段】本発明では鉄骨柱に数層
分の長さを与え、数層を1節とした場合に少なくとも1
節分の鉄骨柱を立設する毎に配筋とコンクリートの打設
を行うことにより工期の短縮化を図り、繰り返して使用
される仮設梁と耐震壁内に埋め込まれるブレースの使用
によって鉄骨柱の自立性を確保することにより工費の低
減を図る。
According to the present invention, a steel column is provided with a length of several layers, and when the number of layers is one section, at least one is obtained.
The construction period is shortened by arranging reinforcing bars and concrete every time a steel column for a node is erected, and the steel column is self-supported by using repeatedly used temporary beams and braces embedded in the earthquake-resistant wall. The construction cost will be reduced by ensuring safety.

【0006】鉄骨柱は基礎上にスパン方向に対向し、桁
行方向に並列して立設され、スパン方向にはブレースが
架設される。
[0006] The steel columns are opposed to each other in the span direction on the foundation, are erected in parallel in the girder direction, and braces are erected in the span direction.

【0007】仮設梁はスパン方向に対向する鉄骨柱の頂
部間に架設され、その下方の層までの施工が終了する毎
に鉄骨柱から切り離され、上層側へ盛り替えられる。
The temporary beam is erected between the tops of the steel columns facing in the span direction, and is cut off from the steel columns every time the construction to the layer below the temporary columns is completed, and is replaced to the upper layer side.

【0008】ブレースは対向する鉄骨柱と仮設梁とで囲
まれたフレーム内に架設され、耐震壁のコンクリート中
に埋設される。鉄骨柱が数層分の長さを持つことによる
安定性の低下は仮設梁とブレースによって補われ、鉄骨
柱の安定性は確保される。
[0008] The brace is erected in a frame surrounded by opposing steel columns and temporary beams, and buried in the concrete of the earthquake-resistant wall. Temporary beams and braces compensate for the decrease in stability due to the length of the steel column having several layers, and the stability of the steel column is ensured.

【0009】ブレースの架設後、仮設梁の下方の層まで
において、桁行方向に並列する鉄骨柱間に鉄骨梁を架設
し、鉄骨柱回り及び鉄骨梁回りと、各層と、対向する鉄
骨柱間に配筋してコンクリートを打設した後、仮設梁を
鉄骨柱から切り離し、更に鉄骨柱上に鉄骨柱を立設して
互いに接続し、この新規に設置され、スパン方向に対向
する鉄骨柱間に下層の鉄骨柱から切り離された仮設梁と
新たなブレースを架設する、という手順を繰り返して躯
体が構築される。
After the brace is erected, up to the lower layer of the temporary beam, a steel beam is erected between the steel columns parallel to each other in the girder direction, and around the steel column and around the steel beam, between each layer and between the opposing steel columns. After placing the concrete and placing concrete, the temporary beams are separated from the steel columns, and furthermore, the steel columns are erected on the steel columns and connected to each other, and between the newly installed steel columns opposing in the span direction. The skeleton is constructed by repeating the procedure of erection of temporary beams and new braces separated from the lower steel columns.

【0010】躯体の施工が1節分の、または数節分の鉄
骨柱の長さに相当する数層単位で進行することにより工
期の短縮化が可能になる。また数層分の長さを持つ鉄骨
柱の安定性が盛り替えられる仮設梁と、ブレースによっ
て確保されることにより、鉄骨柱を自立させるための格
別の部材を要せず、その部材の架設に伴う費用が不要に
なり、工費の上昇が抑えられる。
[0010] The construction period can be shortened by the construction of the skeleton proceeding in units of several layers corresponding to the length of a steel column of one node or several nodes. In addition, the stability of a steel column with a length of several layers is rebuilt and the brace secures it, so there is no need for a special member to make the steel column self-supporting. The accompanying costs are unnecessary, and the increase in construction costs is suppressed.

【0011】[0011]

【実施例】この発明は数層分の長さを持つ、少なくとも
1節分の鉄骨柱1を基礎2上に立設し、これをスパン方
向に架設される仮設梁3とブレース4によって自立させ
た状態で、仮設梁3の下方の層までの配筋とコンクリー
ト7の打設を行う、という手順を繰り返して鉄骨鉄筋コ
ンクリート造の建物を構築する方法である。鉄骨柱1,
1はスパン方向にはブレース4を内蔵した耐震壁5を構
成し、桁行方向には鉄骨梁6によって柱・梁のフレーム
を構成する。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS In the present invention, a steel column 1 having at least one node and having a length of several layers is erected on a foundation 2, and this is self-supported by a temporary beam 3 and a brace 4 erected in the span direction. This is a method of constructing a steel reinforced concrete building by repeating the procedure of arranging reinforcing bars up to the layer below the temporary beams 3 and placing concrete 7 in the state. Steel column 1,
Reference numeral 1 denotes a shear wall 5 having a built-in brace 4 in the span direction, and a column / beam frame formed by a steel beam 6 in the girder direction.

【0012】施工手順を説明する。The construction procedure will be described.

【0013】まず図1,図2に示すように鉄骨柱1をス
パン方向に対向させ、桁行方向に並列させて立設し、ス
パン方向に対向する鉄骨柱1,1の頂部間に仮設梁3を
架設すると共に、対向する鉄骨柱1,1と仮設梁3とで
囲まれたフレーム内にブレース4を架設し、鉄骨柱1を
仮設梁3の下方までの施工終了まで自立させる。鉄骨柱
1の建て入れ調整は図示するようにブレース4の一部に
ターンバックル41を接続することにより行える。
First, as shown in FIGS. 1 and 2, the steel columns 1 are opposed to each other in the span direction, are erected in parallel in the row direction, and are erected, and the temporary beams 3 are provided between the tops of the steel columns 1, 1 opposed in the span direction. And a brace 4 is erected in a frame surrounded by the opposing steel columns 1 and 1 and the temporary beam 3, and the steel column 1 is self-supported until the construction below the temporary beam 3 is completed. The installation adjustment of the steel column 1 can be performed by connecting a turnbuckle 41 to a part of the brace 4 as shown in the figure.

【0014】実施例では鉄骨柱1に3層分の長さを与
え、3層を1節とした場合に1節分の鉄骨柱1を立設す
る毎に配筋とコンクリート7の打設を行う場合を示して
いるが、数節分の鉄骨柱1を立設,接続し、これを仮設
梁3とブレース4で自立させた状態で配筋とコンクリー
ト7の打設を行う場合もある。図1は基礎2から2節目
の鉄骨柱1を立設し、6層分の躯体工事が終了した段階
を示している。
In the embodiment, the length of three layers is given to the steel column 1, and when the three layers are made into one section, every time the steel column 1 of one node is erected, reinforcing bars and concrete 7 are poured. Although the case is shown, the steel columns 1 for several nodes may be erected and connected, and the reinforcing bars and the concrete 7 may be placed in a state where the steel columns 1 are self-supported by the temporary beams 3 and the braces 4. FIG. 1 shows the stage where the steel column 1 of the second section from the foundation 2 has been erected and the frame work for six layers has been completed.

【0015】スパン方向へのブレース4の架設と並行し
て、仮設梁3の架設位置の下方の層までにおいて、桁行
方向に並列する鉄骨柱1,1間への鉄骨梁6の架設と、
鉄骨柱1回りへの柱筋及び鉄骨梁6回りへの梁筋と、各
層のスラブ筋及び対向する鉄骨柱1,1への壁筋の各配
筋と、型枠の組み立てを各層毎に行い、コンクリート7
を各層毎に打設する。ブレース4は耐震壁5のコンクリ
ート7中に埋設される。
In parallel with the installation of the brace 4 in the span direction, up to the layer below the installation position of the temporary beam 3, the installation of the steel beam 6 between the steel columns 1, 1 arranged in the row direction,
Assembling the column reinforcement around the steel column 1 and the beam reinforcement around the steel beam 6, the slab reinforcement of each layer and the wall reinforcement to the opposing steel columns 1, 1 and the assembling of the formwork are performed for each layer. , Concrete 7
For each layer. The brace 4 is buried in the concrete 7 of the earthquake-resistant wall 5.

【0016】コンクリート7は仮設梁3の架設位置の下
方の床スラブ8、実施例の場合、鉄骨柱1の1節が3層
分の長さを持つことから、1回目は各層毎に4階まで、
2回目は各層毎に7階の床スラブ8まで打設される。図
2中、10は鉄筋コンクリート梁を示す。
The concrete 7 is a floor slab 8 below the position where the temporary beam 3 is erected. In the case of the embodiment, one section of the steel column 1 has a length of three layers. Until,
In the second run, the floor slab 8 on the seventh floor is cast for each layer. In FIG. 2, reference numeral 10 denotes a reinforced concrete beam.

【0017】その後、仮設梁3を鉄骨柱1,1から切り
離し、更に鉄骨柱1上に鉄骨柱1’を立設して互いに接
続し、この新規に設置され、スパン方向に対向する鉄骨
柱1’,1’の頂部間に下層で切り離された仮設梁3を
架設すると共に、仮設梁3の下に新たにブレース4’を
架設する、という手順を最上階まで繰り返し、躯体が構
築される。
Thereafter, the temporary beam 3 is cut off from the steel columns 1 and 1, and furthermore, the steel columns 1 'are erected on the steel columns 1 and connected to each other, and the newly installed steel columns 1 opposed in the span direction are connected. The procedure of erection of the temporary beam 3 separated at the lower layer between the tops of the ', 1' and erection of a new brace 4 'under the temporary beam 3 is repeated to the top floor, and a frame is constructed.

【0018】最上階まで施工が完了した後、仮設梁3は
撤去されるか、またはそのまま残されて鉄筋コンクリー
トで被覆される。
After the construction is completed to the top floor, the temporary beam 3 is removed or left as it is and covered with reinforced concrete.

【0019】耐震壁5は鉄筋コンクリート造でも構造的
には成立するが、図2のx−x線断面図である図3に示
すように場合により、内部にはプレート9が配置され
る。プレート9は仮設梁3と床スラブ8間,もしくは撤
去された仮設梁3の位置に配置される。
Although the earthquake-resistant wall 5 is structurally established even in the case of a reinforced concrete structure, as shown in FIG. 3, which is a cross-sectional view taken along the line xx in FIG. The plate 9 is disposed between the temporary beam 3 and the floor slab 8 or at the position of the removed temporary beam 3.

【0020】[0020]

【発明の効果】鉄骨柱に数層分の長さを与え、数層を1
節とした場合に少なくとも1節分の鉄骨柱を立設する毎
に配筋とコンクリートの打設を行うため、躯体の施工が
数層単位で進行し、工期の短縮化を図ることができる。
According to the present invention, a steel column is given a length of several layers,
In the case of a knot, at least one steel column of at least one knot is erected every time a steel column is erected, so that the construction of the skeleton proceeds in units of several layers, and the construction period can be shortened.

【0021】また繰り返して使用される仮設梁と、耐震
壁内に埋め込まれるブレースを使用して鉄骨柱の自立性
を確保するため、鉄骨柱の安定性確保に格別の部材を要
せず、その部材の架設に伴う費用が不要になり、工費の
低減を図ることができる。
[0021] In addition, since the self-sustainability of the steel column is ensured by using the temporary beam repeatedly used and the braces embedded in the earthquake-resistant wall, no special member is required for ensuring the stability of the steel column. The cost associated with the installation of the member is not required, and the construction cost can be reduced.

【図面の簡単な説明】[Brief description of the drawings]

【図1】本発明の施工要領を示した桁行方向の立面図で
ある。
FIG. 1 is an elevational view in a girder direction showing a construction procedure of the present invention.

【図2】建物の平面図である。FIG. 2 is a plan view of a building.

【図3】図2のx−x線断面図である。FIG. 3 is a sectional view taken along line xx of FIG. 2;

【符号の説明】[Explanation of symbols]

1,1’……鉄骨柱、2……基礎、3……仮設梁、4,
4’……ブレース、41……ターンバックル、5……耐震
壁、6……鉄骨梁、7……コンクリート、8……床スラ
ブ、9……プレート、10……鉄筋コンクリート梁。
1, 1 '... steel column, 2 ... foundation, 3 ... temporary beam, 4,
4 ': brace, 41: turnbuckle, 5: earthquake-resistant wall, 6: steel beam, 7: concrete, 8: floor slab, 9: plate, 10: reinforced concrete beam.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 森口 博 神奈川県横浜市中区太田町4丁目51番地 鹿島建設株式会社横浜支店内 (56)参考文献 特開 昭63−125743(JP,A) 特開 昭56−25533(JP,A) 特開 昭47−33415(JP,A) 特開 平5−17996(JP,A) 実開 昭57−187356(JP,U) (58)調査した分野(Int.Cl.6,DB名) E04G 21/14──────────────────────────────────────────────────続 き Continuation of front page (72) Inventor Hiroshi Moriguchi 4-51, Otacho, Naka-ku, Yokohama-shi, Kanagawa Prefecture Kashima Construction Co., Ltd. Yokohama Branch (56) References JP-A-63-125743 (JP, A) JP-A-56-25533 (JP, A) JP-A-47-33415 (JP, A) JP-A-5-17996 (JP, A) JP-A-57-187356 (JP, U) (58) Int.Cl. 6 , DB name) E04G 21/14

Claims (1)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 数層分の長さを持つ鉄骨柱を基礎上に、
スパン方向に対向させ、桁行方向に並列させて立設し、
スパン方向に対向する鉄骨柱の頂部間に仮設梁を架設す
ると共に、対向する鉄骨柱と仮設梁とで囲まれたフレー
ム内にブレースを架設し、仮設梁の下方の層までにおい
て、桁行方向に並列する鉄骨柱間に鉄骨梁を架設し、鉄
骨柱回り及び鉄骨梁回りと、各層と、対向する鉄骨柱間
に配筋してコンクリートを打設した後、仮設梁を鉄骨柱
から切り離し、更に鉄骨柱上に鉄骨柱を立設して互いに
接続し、この新規に設置され、スパン方向に対向する鉄
骨柱間に前記の切り離された仮設梁と新たなブレースを
架設する、という手順を繰り返して躯体を構築する鉄骨
鉄筋コンクリート造建物の構築方法。
1. A steel column having a length of several layers on a foundation,
Stand in the span direction, parallel in the column direction,
A temporary beam is erected between the tops of the steel columns opposed in the span direction, and a brace is installed in a frame surrounded by the opposed steel columns and the temporary beams. After laying steel beams between the parallel steel columns, laying concrete around the steel columns and around the steel beams, each layer, and between the opposing steel columns, placing concrete, then separating the temporary beams from the steel columns, The procedure of erecting the steel columns on the steel columns and connecting them to each other, erection of this newly installed temporary beam and a new brace between the newly installed steel columns opposed in the span direction, was repeated. Construction method of steel-framed reinforced concrete building for building frame.
JP5278000A 1993-11-08 1993-11-08 Construction method of steel reinforced concrete building Expired - Fee Related JP2817591B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP5278000A JP2817591B2 (en) 1993-11-08 1993-11-08 Construction method of steel reinforced concrete building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP5278000A JP2817591B2 (en) 1993-11-08 1993-11-08 Construction method of steel reinforced concrete building

Publications (2)

Publication Number Publication Date
JPH07127261A JPH07127261A (en) 1995-05-16
JP2817591B2 true JP2817591B2 (en) 1998-10-30

Family

ID=17591236

Family Applications (1)

Application Number Title Priority Date Filing Date
JP5278000A Expired - Fee Related JP2817591B2 (en) 1993-11-08 1993-11-08 Construction method of steel reinforced concrete building

Country Status (1)

Country Link
JP (1) JP2817591B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6655297B2 (en) * 2015-03-27 2020-02-26 株式会社Subaru Processing equipment and method of manufacturing processing equipment
CN104866659B (en) * 2015-05-13 2018-09-18 江苏新蓝天钢结构有限公司 Steel construction integral hoisting method based on BIM
CN106193624A (en) * 2016-08-05 2016-12-07 轩重建筑节能科技(上海)有限公司 A kind of wall of aerated concrete block cracking-proof construction technology of improvement

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS605747B2 (en) * 1979-08-07 1985-02-13 清水建設株式会社 Construction method for high-rise buildings
JPS6115147Y2 (en) * 1981-05-23 1986-05-12
JPS63125743A (en) * 1986-11-13 1988-05-28 三井建設株式会社 Construction of building
JPH0517996A (en) * 1991-07-10 1993-01-26 Haseko Corp Building constructing method

Also Published As

Publication number Publication date
JPH07127261A (en) 1995-05-16

Similar Documents

Publication Publication Date Title
US20040055246A1 (en) Column and beam construction and method
US3890750A (en) Construction system
CA1179519A (en) Precast building element and method
US4344262A (en) Long span structural frame
JP3752999B2 (en) Upper and lower integrated bridge and its construction method
JP3069753B2 (en) Construction method of framed reinforced concrete structure
JP2817591B2 (en) Construction method of steel reinforced concrete building
CN112681511A (en) Reinforced concrete structure construction method using section steel to replace part of reinforcing steel bars
JPH10159344A (en) Building method of multi-layered structure provided with a plurality of super beam
JPS6314937A (en) Reinforced steel composite column
JP2897663B2 (en) How to build underground structures
JP2000160687A (en) Construction method of mixed structure and precast concrete column
KR0150304B1 (en) A method of simultaneously constructing frameworks for floors and basements of a building
US3349539A (en) Construction of two-way composite building system
JPH0447737B2 (en)
JPH08270255A (en) Seismic isolation structure method for existing buildings
JPH0657769A (en) Underground structure and its construction method
JP2026003816A (en) Column and beam frame construction method
JP2026003814A (en) Column and beam frame construction method
JPH0376972A (en) Construction of multistory parking lot
JP2026003815A (en) Mounting and assembly method
JPH0261238A (en) Steel plate concrete method
JP2001032376A (en) Floor slab frame and construction method for skeleton
JPH04140366A (en) Preceding erection method of prefabricated column bar and semi-pc girder in pc construction
JPS58113450A (en) Body structure of fire resistant building

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19980721

LAPS Cancellation because of no payment of annual fees