JPH08105062A - Footing structure and executing method thereof - Google Patents

Footing structure and executing method thereof

Info

Publication number
JPH08105062A
JPH08105062A JP27022994A JP27022994A JPH08105062A JP H08105062 A JPH08105062 A JP H08105062A JP 27022994 A JP27022994 A JP 27022994A JP 27022994 A JP27022994 A JP 27022994A JP H08105062 A JPH08105062 A JP H08105062A
Authority
JP
Japan
Prior art keywords
precast concrete
foundation
foundations
footing
floor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP27022994A
Other languages
Japanese (ja)
Other versions
JP3086384B2 (en
Inventor
Akira Kishi
明 岸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP06270229A priority Critical patent/JP3086384B2/en
Publication of JPH08105062A publication Critical patent/JPH08105062A/en
Application granted granted Critical
Publication of JP3086384B2 publication Critical patent/JP3086384B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Foundations (AREA)

Abstract

PURPOSE: To provide a footing structure that is able to simplify the construction work of foundation in omitting a bundle footing and an individual footing, capable of improving the extent of dimensional accuracy, and of securing the maintenance of strong rigidity extending over a long period of time. CONSTITUTION: Plural pieces of precast concrete wall plates 20 mounted on each of footing parts 16 are installed in space between two sides of a precast concrete strip footing 10 erected in parallel with other. This PC wall plate 20 is made of precast concrete and formed into a rectangular parallelopipedic structure, and a notch 24 is installed in the cross direction side face 20a and a pedestrian port 22 in the side, respectively. This notch 24 is installed almost in the center of a distance between two elections, and the pedestrian port 22 is installed in a position being slightly more deflected than a central part. A floor beam 30 is installed in space between these two PC wall plates 20, and it is inserted into the notch 24 of the PC wall plate 20 and joined and locked by two anchor bolts 34 and the like.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、建築物の地盤に構築さ
れる基礎構造及び基礎の施工方法に関し、特に、束基礎
又は独立基礎を省略できる基礎構造及び基礎の施工方法
に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a foundation structure constructed on the ground of a building and a construction method of the foundation, and more particularly to a foundation structure and a construction method of the foundation which can omit a bundle foundation or an independent foundation.

【0002】[0002]

【従来の技術及び発明が解決しようとする課題】現場施
工に携わる熟練作業者の確保の困難性、工期の短縮及び
住宅品質の均一化等の見地から、住宅の工業化が進んで
いる。すなわち、工場にてできるだけ部品完成度を高
め、建築現場での作業項目を減少させるよう試みられて
いる。
2. Description of the Related Art Houses have been industrialized from the standpoint of difficulty in securing skilled workers involved in on-site construction, shortening of construction period, and uniformization of house quality. That is, it is attempted to increase the degree of completion of parts in the factory as much as possible and reduce the work items on the construction site.

【0003】この住宅の工業化として、建築物の基礎を
予め工場にてプレキャストしておき、このプレキャスト
(以下、PCと略記する)製基礎を用いて、建築現場に
て基礎を構築する方法が知られている。例えば1階の床
を支持するための基礎は、PC基礎施工法により図5に
示すようにして構築されていた。
As an industrialization of this house, there is known a method of precasting a foundation of a building in a factory in advance and using the precast (hereinafter abbreviated as PC) foundation to construct the foundation at a construction site. Has been. For example, the foundation for supporting the floor on the first floor was constructed by the PC foundation construction method as shown in FIG.

【0004】すなわち、同図において、建物の外周位置
に外部布基礎80が構築され、これら外部布基礎80及
び内部布基礎82の上には、図示しない台輪が敷き込ま
れる。そして、これら外部布基礎80及び内部布基礎8
2の間には、束基礎84が構築され、この束基礎84の
上には、床受材86が取り付けられている。例えばパネ
ル公報においては、こうして構築された基礎の上に床パ
ネルを敷き込んで、床パネルの外端に半土台(図示せ
ず)を取り付けて1階の床部が構築される。
That is, in the figure, an outer cloth foundation 80 is constructed at the outer peripheral position of the building, and a pedestal wheel (not shown) is laid on the outer cloth foundation 80 and the inner cloth foundation 82. Then, the outer cloth foundation 80 and the inner cloth foundation 8
A bundle foundation 84 is constructed between the two, and a floor support material 86 is mounted on the bundle foundation 84. For example, in the panel gazette, a floor panel is laid on the foundation thus constructed, and a semi-base (not shown) is attached to the outer end of the floor panel to construct the floor portion of the first floor.

【0005】ここで、束基礎84は、床受材86を取り
付けて床パネルを支持するものであるが、この束基礎8
4を構築するには、割栗石を敷き込んだり、杭を打ち込
んだりしなければならないので手間がかかるものであっ
た。しかも、束基礎は、布基礎のように連続させずに点
在させるものであることからも、基礎地業が面倒であっ
た。さらに、多数の束基礎84一つずつについて、それ
ぞれ水平レベル調整を行う必要があり、その作業も煩雑
となっていた。
Here, the bundle foundation 84 attaches a floor support 86 to support the floor panel.
In order to build No. 4, it was troublesome because it required laying split stones and driving piles. Moreover, since the bundle foundation is scattered like the cloth foundation instead of being continuous, the foundation groundwork was troublesome. Further, it is necessary to adjust the horizontal level for each of the many bundle foundations 84, and the work is complicated.

【0006】本発明は、上記した従来技術の問題点を解
決するためになされたものであって、その目的とすると
ころは、束基礎を省略して、基礎の構築作業を簡略化で
きる基礎構造及び基礎の施工方法を提供することにあ
る。
The present invention has been made in order to solve the above-mentioned problems of the prior art, and its purpose is to eliminate the bundle foundation and to simplify the construction work of the foundation. And to provide a foundation construction method.

【0007】また、本発明の他の目的は、水平レベル調
整作業を簡略化しながらも、床梁の取り付け寸法精度の
向上が可能な基礎構造及び基礎の施工方法を提供するこ
とにある。
Another object of the present invention is to provide a foundation structure and a foundation construction method capable of improving the mounting dimension accuracy of a floor beam while simplifying the horizontal level adjustment work.

【0008】また、本発明のさらに他の目的は、基礎上
に載置される床との強固な接合固定を可能にし、かつ長
期間に亘る強い剛性を維持できる基礎構造及び基礎の施
工方法を提供することにある。
Still another object of the present invention is to provide a foundation structure and a method of constructing a foundation, which enables strong joining and fixing to a floor placed on a foundation and can maintain strong rigidity for a long period of time. To provide.

【0009】[0009]

【課題を解決するための手段】請求項1の発明に係る基
礎構造は、建物の構築領域で地盤を連続的に掘削して形
成された根切り部に所定間隔で設置される複数のプレキ
ャストコンクリート底盤と、鉛直方向に直立して建物を
支持する立上部と、この立上部の下部から側方に突出す
るフーティング部と、を有し、前記プレキャストコンク
リート底盤間に平行に複数架設されるプレキャストコン
クリート基礎と、平行な前記プレキャストコンクリート
基礎の各々の前記フーティング部上に両端が載置される
ことで、平行な前記プレキャストコンクリート基礎間に
架設され、前記プレキャストコンクリート基礎間に配置
される床梁を支持するプレキャストコンクリート壁板
と、を有することを特徴とする。
According to a first aspect of the present invention, there is provided a foundation structure in which a plurality of precast concretes are installed at predetermined intervals at root cutting portions formed by continuously excavating the ground in a building construction area. A precast concrete that has a bottom plate, a rising part that stands upright in the vertical direction to support the building, and a footing part that projects laterally from the lower part of this rising part, and is installed in parallel between the precast concrete bottom plates. A floor beam that is installed between the parallel precast concrete foundations by placing both ends on the footing portion of each of the concrete foundations and the parallel precast concrete foundations, and is placed between the precast concrete foundations. And a precast concrete wall board for supporting.

【0010】請求項2の発明は、請求項1において、前
記プレキャストコンクリート壁板は、前記立上部の上面
とほぼ面一となる上端面と、この上端面より前記床梁の
厚さ分だけ切り欠いた切欠部と、を有し、前記プレキャ
ストコンクリート基礎間にて該基礎に平行に配置される
前記床梁を、前記切欠部にて支持することを特徴とす
る。
According to a second aspect of the present invention, in the first aspect, the precast concrete wallboard is cut at an upper end surface that is substantially flush with the upper surface of the rising portion, and cut from the upper end surface by the thickness of the floor beam. The floor beam, which has a notch portion and which is arranged in parallel to the precast concrete foundation between the foundations, is supported by the notch portion.

【0011】請求項3の発明は、請求項1において、前
記プレキャストコンクリート壁板は、前記立上部の上面
より前記床梁の厚さ分だけ低い上端面を有し、前記プレ
キャストコンクリート基礎間にて該基礎に直交して配置
される前記床梁を、前記上端面にて支持することを特徴
とする。
According to a third aspect of the present invention, in the first aspect, the precast concrete wall board has an upper end surface that is lower than an upper surface of the upright portion by a thickness of the floor beam. The floor beam arranged orthogonally to the foundation is supported by the upper end surface.

【0012】請求項4の発明は、請求項1乃至3のいず
れかにおいて、前記プレキャストコンクリート基礎は、
前記立上部の側面に、前記プレキャストコンクリート壁
板の端部を挿入する溝部を有することを特徴とする。
[0012] The invention of claim 4 is the precast concrete foundation according to any one of claims 1 to 3,
It is characterized in that a groove portion into which an end portion of the precast concrete wall plate is inserted is provided on a side surface of the rising portion.

【0013】請求項5の発明は、請求項1乃至乃至4の
いずれかにおいて、前記プレキャストコンクリート壁板
は、その一方の側面より他方の側面に貫通する人道口を
有することを特徴とする。
A fifth aspect of the present invention is characterized in that, in any one of the first to fourth aspects, the precast concrete wall board has a humanitarian opening that penetrates from one side surface to the other side surface.

【0014】請求項6の発明に係る基礎の施工方法は、
建物の構築領域で地盤を連続的に掘削して形成された根
切り部に所定間隔で複数のプレキャストコンクリート底
盤を設置する工程と、鉛直方向に直立して建物を支持す
る立上部と、この立上部の下部から側方に突出するフー
ティング部と、を有するプレキャストコンクリート基礎
を、前記プレキャストコンクリート底盤間に平行に複数
架設する工程と、平行な前記プレキャストコンクリート
基礎の各々の前記フーティング部の上に、プレキャスト
コンクリート壁板の両端を載置して、前記プレキャスト
コンクリート基礎と直角に前記プレキャストコンクリー
ト壁板を架設する工程と、を有することを特徴とする。
A method of constructing a foundation according to the invention of claim 6 is
The process of installing a plurality of precast concrete bottom plates at predetermined intervals in the root cutting part formed by continuously excavating the ground in the construction area of the building, and the rising part that vertically stands upright to support the building, and this standing part. A step of laterally projecting a precast concrete foundation having a footing portion protruding laterally from a lower part of the upper part, and a step of installing a plurality of precast concrete foundations in parallel between the precast concrete bottom plates, and above the footing portion of each of the parallel precast concrete foundations. And placing both ends of the precast concrete wallboard and erecting the precast concrete wallboard at right angles to the precast concrete foundation.

【0015】[0015]

【作用】請求項1及び6の各発明によれば、予め工場段
階において製造されたプレキャストコンクリート壁板を
建築現場において対向するフーティング部間に設置し、
床梁をプレキャストコンクリート壁板に取付固定すれ
ば、この床梁にて床を支持できるので、地業作業及び水
平レベル作業の繁雑な従来技術の束基礎や独立基礎を省
略することができ、束工事の他に地業、砕石締め固めを
することなどが不用となるため基礎工事の工程が短縮で
き、建築現場における基礎部構築作業をより簡略化かつ
迅速化できる。
According to each of the first and sixth aspects of the invention, the precast concrete wall boards manufactured in advance at the factory stage are installed between the facing footing parts at the construction site,
If the floor beam can be attached and fixed to the precast concrete wall board, the floor beam can support the floor beam, so that it is possible to omit the bundling foundation and the independent foundation of the conventional technology, which are complicated in the earthwork work and the horizontal level work. In addition to the construction work, it is not necessary to perform ground work and crushed stone compaction, so the process of foundation work can be shortened, and the work of building the foundation at the construction site can be simplified and speeded up.

【0016】また、プレキャストコンクリート底盤の水
平レベル調整を行えば、その上に設置されるプレキャス
トコンクリート基礎のフーティング部、すなわちプレキ
ャストコンクリート壁位置の取り付け面の水平レベルの
精度を確保できる。したがって、床梁を支持する基準面
を備えたプレキャストコンクリート壁板の水平レベル調
整が不要となり、あるいは簡略化される。
Further, by adjusting the horizontal level of the precast concrete bottom plate, it is possible to ensure the accuracy of the horizontal level of the footing portion of the precast concrete foundation installed thereon, that is, the mounting surface of the precast concrete wall position. Therefore, the horizontal level adjustment of the precast concrete wallboard having the reference surface for supporting the floor beam is unnecessary or simplified.

【0017】しかも、基礎部分をプレキャストコンクリ
ート基礎及び壁板により枠組状にすることが可能とな
り、床構面を小さくすることができるので、水平荷重及
び鉛直荷重に対する強度が強まり、かつ地盤上に支点を
つくることができ支点間距離が小さくなるので構造耐力
が強まり床荷重を安全に土台に伝えることができ、かつ
断熱性及び耐久性に優れる等の効果も期待できる。
Moreover, since the foundation portion can be framed by the precast concrete foundation and the wall plate, and the floor structure can be made small, the strength against horizontal load and vertical load is increased, and the fulcrum is supported on the ground. Since the distance between the fulcrums can be made smaller, the structural yield strength can be increased, the floor load can be safely transmitted to the foundation, and the effects such as excellent heat insulation and durability can be expected.

【0018】また、プレキャストコンクリート壁板の配
置位置は、例えばパネル工法を採用する場合には、部屋
構造に適った床パネルの設置方向及び枚数に従って設定
することで、部屋構造に応じた構造耐力の強度を確保で
きる。
Further, when the panel construction method is adopted, for example, the arrangement position of the precast concrete wall boards is set according to the installation direction and the number of floor panels suitable for the room structure so that the structural yield strength corresponding to the room structure can be improved. The strength can be secured.

【0019】さらに、連続基礎のようにコンクリートで
連結しておらず、プレキャストコンクリート壁板をユニ
ット化し、各プレキャストコンクリート壁板を現場にて
組立接合するので、建築現場での部材点数が減り、施工
作業の簡略化が期待でき、かつ経済性に優れる。
Further, since the precast concrete wall boards are not united with concrete like continuous foundations and each precast concrete wall board is assembled and joined on site, the number of members at the construction site is reduced, and the construction work is performed. Can be expected to simplify the work and is highly economical.

【0020】請求項2及び3の各発明では、2つのプレ
キャストコンクリート基礎の間にて該基礎と平行にある
いは直交して配置される床梁を、プレキャストコンクリ
ート壁板によりそれぞれれ支持できる。
In each of the second and third aspects of the present invention, the floor beams arranged between the two precast concrete foundations in parallel or at right angles to the foundations can be supported by the precast concrete wall boards.

【0021】請求項4の発明によれば、プレキャストコ
ンクリート基礎の側面に溝部を形成することで、プレキ
ャストコンクリート壁板の位置決めが容易となり、しか
も、溝部内に打設することで基礎及び壁板の接合を強固
にできる。
According to the invention of claim 4, the groove portion is formed on the side surface of the precast concrete foundation, whereby the positioning of the precast concrete wall board is facilitated, and furthermore, by placing it in the groove portion, the foundation and the wall board can be formed. The joint can be strengthened.

【0022】請求項5の発明によれば、2つのプリキャ
ストコンクリート基礎内の空間を仕切るプレキャストコ
ンクリート壁板に人道口を設けることで、床部構築後の
配管、メンテナンス作業を可能としている。
According to the fifth aspect of the present invention, the precast concrete wall board for partitioning the space in the two precast concrete foundations is provided with the human passage opening, so that the piping and maintenance work after the floor construction can be performed.

【0023】[0023]

【実施例】以下、本発明に係る実施例について図面に基
づいて説明する。
Embodiments of the present invention will be described below with reference to the drawings.

【0024】実施例1 建築物構築領域に立ち上げ形成された基礎の構造の一部
において、床梁を外周布基礎に平行に配置する場合の基
礎構造を図1及び図2を用いて説明する。
Example 1 In a part of the structure of a foundation that has been erected and formed in a building construction area, a basic structure in which a floor beam is arranged parallel to an outer peripheral fabric foundation will be described with reference to FIGS. 1 and 2. .

【0025】図1は、実施例1に係る基礎構造の一部を
切り欠いた斜視図である。図2は、図1におけるPC布
基礎10上に床パネル40を載置した状態を示す斜視図
である。
FIG. 1 is a perspective view in which a part of the basic structure according to the first embodiment is cut away. FIG. 2 is a perspective view showing a state in which the floor panel 40 is placed on the PC cloth foundation 10 in FIG.

【0026】図1には、予め工場段階で製造された2つ
のプレキャストコンクリート(以下PCと記す)布基礎
10が、相平行に構築されている状態が示されている。
なお、地盤を布堀りして形成された根切り部のコーナー
部及びこのコーナー部間の所定位置に、PC底盤(図示
せず)を複数設置させ、このPC底盤間にPC布基礎1
0が架設される。また、図1において例えば一方のPC
布基礎10は建築物の外周に沿って構築され、他方のP
C布基礎10は建築物の内部に構築されている。
FIG. 1 shows a state in which two precast concrete (hereinafter referred to as PC) cloth foundations 10 manufactured in advance at a factory stage are constructed in parallel with each other.
A plurality of PC bottom plates (not shown) are installed at the corners of the root cutting part formed by dug the ground and at predetermined positions between the corners, and the PC cloth foundation 1 is provided between the PC bottom plates.
0 is erected. Further, in FIG. 1, for example, one PC
The cloth foundation 10 is constructed along the outer periphery of the building, and the other P
The C cloth foundation 10 is built inside the building.

【0027】前記PC布基礎10は、立上部12、溝部
14、及びフーティング部16を有する。
The PC cloth foundation 10 has a rising portion 12, a groove portion 14, and a footing portion 16.

【0028】立上部12は、鉛直方向に直立して上端面
12bに建物を載置して支持するもので、所定の長さ及
び厚さで直方体形状に形成され、内部には図示しない補
強用の鉄筋が配筋され、コンクリートにて埋設され構成
されている。
The upright part 12 stands upright in the vertical direction and mounts and supports the building on the upper end face 12b. The upright part 12 is formed in a rectangular parallelepiped shape with a predetermined length and thickness, and is provided inside for reinforcement not shown. The steel bars are reinforced and are buried in concrete.

【0029】溝部14は、相平行に立設された2つのP
C布基礎10の対向側面12a上に所定間隔で形成さ
れ、その溝幅は後述するPC壁板20の厚さより若干長
い幅に保てられ、後述するPC壁板20が填め込み可能
となっている。
The groove portion 14 has two Ps that are erected parallel to each other.
It is formed on the opposite side surfaces 12a of the C cloth foundation 10 at predetermined intervals, and its groove width is kept slightly longer than the thickness of the PC wall board 20 described later, so that the PC wall board 20 described later can be fitted. There is.

【0030】フーティング部16は、立上部12を直立
させて支持するものであって、立上部12の両側面12
a及び12cの下端から側方に直角に突出して形成され
ている。このフーティング部16は、立上部12と一体
又は別体にて、補強筋入りコンクリートで構成され、そ
の上面16aは水平で滑らかな面となっている。また、
前記フーティング部16には、その上面16aに開口す
るコンクリート充填口18が形成されている。
The footing portion 16 supports the rising portion 12 so as to stand upright, and both side surfaces 12 of the rising portion 12 are supported.
It is formed so as to project laterally at a right angle from the lower ends of a and 12c. The footing portion 16 is integrally or separately formed from the rising portion 12 and is made of reinforced concrete, and its upper surface 16a is horizontal and smooth. Also,
The footing portion 16 is provided with a concrete filling opening 18 which is open on the upper surface 16a thereof.

【0031】コンクリート充填口18は、フーティング
部16の上面16aから下面に貫通する複数の矩形の穴
であって所定間隔に形成され、このコンクリート充填口
18からコンクリートを打設養生し固化させて、フーテ
ィング部16を地盤70に強固に固定できるようになっ
ている。
The concrete filling port 18 is a plurality of rectangular holes penetrating from the upper surface 16a to the lower surface of the footing portion 16 and is formed at predetermined intervals. The concrete filling port 18 is cured by pouring and solidifying the concrete. The footing portion 16 can be firmly fixed to the ground 70.

【0032】この相平行に立設されたPC布基礎10の
2辺間には、その両端がフーティング部16上に支持さ
れて架設されるPC壁板20が設けられている。また、
PC壁板20の両端は、PC布基礎10の溝部14に填
め込んである。
Between the two sides of the PC cloth foundation 10 which are erected in parallel with each other, a PC wall plate 20 is installed, the both ends of which are supported and erected on the footing portion 16. Also,
Both ends of the PC wall plate 20 are fitted into the groove portions 14 of the PC cloth foundation 10.

【0033】PC壁板20は、上述したPC布基礎10
と同様、PC製で直方体状の構造をなし、厚みがPC布
基礎10とほぼ同程度となっている。また、PC壁板2
0の高さは、フーティング部16の上端面16aからP
C布基礎10の上端面12bまでの距離と同一となって
いる。これにより、PC布基礎10の上端面12bとP
C壁板20の上端面20aが面一となる。そして、PC
壁板50の下端面は、滑らかな面となっているので、フ
ーティング部16の上端面16aに安定して載置できる
ようになっている。
The PC wallboard 20 is the PC cloth foundation 10 described above.
Similarly to the above, it is made of PC and has a rectangular parallelepiped structure, and its thickness is almost the same as that of the PC cloth foundation 10. Also, the PC wall board 2
The height of 0 is P from the upper end surface 16a of the footing portion 16
It is the same as the distance to the upper end surface 12b of the C cloth foundation 10. As a result, the upper end surface 12b of the PC cloth foundation 10 and the P
The upper end surface 20a of the C wall plate 20 is flush. And PC
Since the lower end surface of the wall plate 50 is a smooth surface, it can be stably placed on the upper end surface 16a of the footing portion 16.

【0034】前記PC壁板20の上端側面20aには切
欠部24が形成され、さらに、側面20bには人道口2
2が貫通形成されている。
A notch 24 is formed on the upper end side surface 20a of the PC wall plate 20, and the humanitarian entrance 2 is formed on the side surface 20b.
2 is formed through.

【0035】前記切欠部24は、PC壁板20間に床梁
30を架け渡して設置できるようにするものである。本
実施例1では、切欠部24の切欠深さは、床梁30の厚
さと等しくされている。前記人道口22は、建築現場で
の施工作業前後において、人が出入できるように設けら
れているものである。さらに、図1では、切欠部24は
架設間距離のほぼ中心に設けられ、人道口22は前記中
心部分よりやや偏位した位置に設けられている。尚、人
道口22の位置は、この限りではなく、PC壁板20上
のどの位置でも複数個設けてもよい。また、その大きさ
も人の通行が可能であれば、どんな大きさでもよい。
The notch 24 allows the floor beam 30 to be installed between the PC wall plates 20. In the first embodiment, the notch depth of the notch 24 is equal to the thickness of the floor beam 30. The humanway entrance 22 is provided so that a person can enter and exit before and after the construction work at the construction site. Further, in FIG. 1, the notch 24 is provided substantially at the center of the distance between the installations, and the human passage 22 is provided at a position slightly offset from the central portion. The position of the humanitarian opening 22 is not limited to this, and a plurality of positions may be provided at any position on the PC wallboard 20. Further, the size may be any size as long as it can pass a person.

【0036】PC布基礎10間に複数架設されたPC壁
板20間には、床梁30が架設されており、前記PC壁
板20の切欠部24に挿入され、取付ボルト34(アン
カーボルト等)により床梁30とPC壁板20とが取付
固定されている。
A floor beam 30 is installed between a plurality of PC wall plates 20 installed between the PC cloth bases 10, and is inserted into the cutout portion 24 of the PC wall plate 20, and a mounting bolt 34 (anchor bolt, etc.) is installed. The floor beam 30 and the PC wall board 20 are fixedly attached by the above.

【0037】床梁30は、図2に示す床パネル40を支
持するために設けられており、材質は木材であってもよ
いが、近年の木材の価値高謄に鑑みて、複数の木片より
成る集成材、あるいはH形鋼などの鋼材を用いることが
できる。鋼材を用いた場合は、防蟻処理が不要であると
いう利点もある。
The floor beam 30 is provided to support the floor panel 40 shown in FIG. 2, and the material thereof may be wood. However, in view of the recent high value of wood, a plurality of wood pieces are used. It is possible to use a laminated laminated material or a steel material such as an H-shaped steel. The use of steel also has the advantage that no ant-proof treatment is required.

【0038】また、床梁30とPC壁板20との取付固
定は、PC壁板20の切欠部24に設けられた取付ボル
ト(アンカーボルト等)により、床梁30との取付固定
が容易に行えるようになっている。すなわち、床梁30
には、図1に示すように、数ヶ所に存在する切欠部又は
端部に取付板が設けられ、この取付板に形成された取付
穴に取付ボルト(アンカーボルト等)を挿通して、ナッ
トにて固定することで、床梁30をPC壁板20に取付
固定することができる。尚、ナットを用いる代わりに、
めねじが形成されたインサート部材をPC壁板20の切
欠部24の上端面に埋込み形成しておき、このめねじに
ボルトを螺合させて床梁30を取付固定するようにして
もよい。
Further, the floor beam 30 and the PC wall board 20 can be attached and fixed easily with the floor beam 30 by using attachment bolts (anchor bolts or the like) provided in the notches 24 of the PC wall board 20. It can be done. That is, the floor beam 30
As shown in FIG. 1, a mounting plate is provided at several notches or ends, and mounting bolts (anchor bolts, etc.) are inserted through the mounting holes formed in the mounting plate to attach the nut to the nut. The floor beam 30 can be attached and fixed to the PC wall board 20 by fixing the floor beam 30. Instead of using nuts,
An insert member having a female screw may be embedded in the upper end surface of the cutout portion 24 of the PC wall plate 20, and a bolt may be screwed into the female screw to attach and fix the floor beam 30.

【0039】この床梁30とPC壁板20との取付固定
により、床梁30の上面30aとPC壁板20の上面2
0aとは面一となり、床パネル40の支持面を形成す
る。なお、床梁30は、取り付け位置の領域が切り欠か
れ、床梁30の固定に用いるナット又はボルトの頭部
は、上面30aより上方に突出しないようになってい
る。
By attaching and fixing the floor beam 30 and the PC wall plate 20, the upper surface 30a of the floor beam 30 and the upper surface 2 of the PC wall plate 20 are fixed.
It is flush with 0a and forms the support surface of the floor panel 40. In addition, the floor beam 30 is notched in a region where the floor beam 30 is attached, and the heads of nuts or bolts used for fixing the floor beam 30 do not project above the upper surface 30a.

【0040】次に、PC壁板20間の距離と床パネル4
0の幅との関係を図1及び図2に基づいて説明する。
Next, the distance between the PC wall boards 20 and the floor panel 4
The relationship with the width of 0 will be described based on FIGS. 1 and 2.

【0041】図1及び図2に示すように、床パネル20
の短辺の長さをA、長辺の長さをBとする。この時、2
つの相平行なPC壁板20間の距離をnA(ただし、n
は自然数)に設定しておくと、PC布基礎10及びPC
壁板20上にn枚の床パネル40を載置した際に、床パ
ネル40の幅Aに合わせることができ、床構面を小さく
することができるので基礎部分の構造耐力が強まる。ま
た、床梁30(大引き)の撓みを防ぐことができる。な
お、床梁30を従来通りの曲げ剛性とした場合、n=1
〜3に設定することが好ましい。
As shown in FIGS. 1 and 2, floor panel 20.
Let A be the length of the short side and B be the length of the long side. At this time, 2
The distance between two parallel PC wall plates 20 is nA (however, n
Is a natural number), PC cloth foundation 10 and PC
When n floor panels 40 are placed on the wall plate 20, the width A of the floor panels 40 can be matched, and the floor structure can be reduced, so that the structural strength of the foundation portion is strengthened. Further, it is possible to prevent the floor beam 30 (large pull) from bending. When the floor beam 30 has the conventional bending rigidity, n = 1
It is preferable to set to ~ 3.

【0042】また、PC布基礎10に対して床パネル4
0の短辺Aを平行に設置する図2の場合には、床パネル
40の長辺距離Bの中心に床梁30がくるので、固定後
の構造耐力が強化される。なお、構造耐力を確保しよう
として、予めPC壁板20間距離を小さくする場合など
は、床パネル40の短辺寸法Aのn倍にPC壁板20間
距離を設定すればよい。
The floor panel 4 is attached to the PC cloth foundation 10.
In the case of FIG. 2 in which the short side A of 0 is installed in parallel, the floor beam 30 comes to the center of the long side distance B of the floor panel 40, so that the structural proof strength after fixing is strengthened. When the distance between the PC wallboards 20 is reduced in advance in order to secure structural strength, the distance between the PC wallboards 20 may be set to n times the short side dimension A of the floor panel 40.

【0043】また、PC壁板20及びPC布基礎10を
枠組状にしてあるので水平荷重及び鉛直荷重に対する強
度が強まる支点を地盤上に確保でき、支点間距離が小さ
くなるので構造耐力が高まり、床荷重を安全に土台に伝
えることができる。
Further, since the PC wallboard 20 and the PC cloth foundation 10 are framed, it is possible to secure a fulcrum on the ground where the strength against horizontal load and vertical load is increased, and the distance between the fulcrums is reduced, so that the structural strength is increased, The floor load can be safely transmitted to the base.

【0044】また、予めレベル調整された各PC部材
(この場合、PC布基礎10のフーティング部16)上
に、PC壁板30を置くので、床梁30を支持する支持
面の寸法精度が向上する。
Further, since the PC wall board 30 is placed on each PC member (in this case, the footing portion 16 of the PC cloth foundation 10) whose level is adjusted in advance, the dimensional accuracy of the supporting surface for supporting the floor beam 30 is improved. improves.

【0045】また、連続基礎のようにコンクリートで連
結しておらず、PC壁板30をユニット化し、各PC壁
板30を現場にて組立接合するので、建築現場での部材
点数が減り、施工作業の簡略化が期待できる。
Further, unlike the continuous foundation, the PC wallboards 30 are not united with concrete but are unitized and the respective PC wallboards 30 are assembled and joined on site, so that the number of members at the construction site is reduced and the construction is carried out. It can be expected to simplify the work.

【0046】次に、本実施例に係る作用説明すなわち施
工方法を図1及び図2を用いて説明する。
Next, the operation of this embodiment, that is, the construction method will be described with reference to FIGS. 1 and 2.

【0047】予め工場段階でPC布基礎10及びPC壁
板20を製造し、建築現場へ輸送する。尚、PC布基礎
10及びPC壁板20は、予め工場段階で表面が処理さ
れた状態となっている。また、PC壁板20の長手方向
の長さは、床パネル40の長辺距離Bとほぼ等しくなる
よう工場段階で設定され、製造される。
The PC cloth foundation 10 and the PC wallboard 20 are manufactured in advance at the factory stage and transported to the construction site. The surfaces of the PC cloth foundation 10 and the PC wallboard 20 are preliminarily processed at the factory stage. Further, the length of the PC wall plate 20 in the longitudinal direction is set and manufactured in a factory stage so as to be substantially equal to the long side distance B of the floor panel 40.

【0048】建築現場において、地盤を布堀りして根切
り部を形成し、この根切り部のコーナー部及び所定位置
にPC底盤を設置する。
At the construction site, the ground is dug to form a root cutting portion, and the PC bottom board is installed at a corner portion and a predetermined position of the root cutting portion.

【0049】そして、このPC底盤を根切り部に設置す
るときには、このPC底盤の設置位置にモルタルの山を
載置し、このモルタルの山を潰すようにしてPC底盤を
載置する。そして、このPC底盤を掛矢等で叩いて所定
の高さで上面がほぼ水平になるよう調整作業を行う。な
お、この作業は、水糸や水準器やレーザー光線による水
準装置等を用いて水平レベルおよび高さを確認しながら
行う。
When the PC bottom plate is installed at the root cutting portion, the mortar pile is placed at the installation position of the PC bottom plate, and the PC bottom plate is placed so as to crush the mortar pile. Then, this PC bottom board is hit with a hanging arrow or the like to perform an adjusting operation so that the upper surface becomes substantially horizontal at a predetermined height. This work is performed while checking the horizontal level and height using a water thread, a level, or a leveling device using a laser beam.

【0050】次にPC布基礎10をPC底盤間に架設す
る。この時、既にPC底盤は所定の高さで水平に設置さ
れているので、PC布基礎10は、ただPC底盤間に掛
け渡して設置するだけで所定の高さで水平になる。従っ
て、PC底盤の上面にPC布基礎の設置位置の墨出しを
行い、設置位置だけを確認しながら載置するだけでこの
PC布基礎の設置作業は完了する。よって、このPC布
基礎は、凹部の下端面を架設部としてPC底盤に載置で
きる。そして、隣接するPC布基礎同士を図示しない治
具にて結合し、この凹部の内部に鉄筋を配設してコンク
リートを打設し、PC布基礎同士を連結させ、建物の基
礎が構築される。
Next, the PC cloth foundation 10 is installed between the PC bottom boards. At this time, since the PC bottom plate is already installed horizontally at a predetermined height, the PC cloth foundation 10 becomes horizontal at a predetermined height simply by being installed between the PC bottom plates. Therefore, the installation work of the PC cloth foundation is completed only by marking out the installation position of the PC cloth foundation on the upper surface of the PC bottom plate and placing it while checking only the installation position. Therefore, this PC cloth foundation can be placed on the PC bottom board by using the lower end surface of the concave portion as the erected portion. Then, the adjacent PC cloth foundations are joined together by a jig (not shown), the reinforcing bars are arranged inside the recesses, concrete is poured, and the PC cloth foundations are connected to each other to construct a building foundation. .

【0051】この時、一方のPC布基礎10と相平行に
設置される他方のPC布基礎10は、PC布基礎10間
ピッチが、床パネル40の長辺距離Bと等しくなるよう
に構築される。
At this time, the other PC cloth foundation 10 installed in parallel with the one PC cloth foundation 10 is constructed so that the pitch between the PC cloth foundations 10 becomes equal to the long side distance B of the floor panel 40. It

【0052】また、PC布基礎10の下部には予め工場
段階でフーティング部16が一体的に形成されているの
で、建築現場でフーティングを構築する必要がなく、P
C布基礎10同様、フーティング部16の上端面も水平
で滑らかとなっている。
Further, since the footing portion 16 is integrally formed in advance at the lower part of the PC cloth foundation 10 at the factory stage, it is not necessary to construct the footing at the construction site.
Like the C cloth foundation 10, the upper end surface of the footing portion 16 is horizontal and smooth.

【0053】こうしてPC布基礎10が設置固定される
と、図1に示すように、PC壁板20を一方のPC布基
礎10と他方のPC布基礎10との間にて、かつ、各基
礎10のフーティング部16の上に設置する。
When the PC cloth foundation 10 is installed and fixed in this way, as shown in FIG. 1, the PC wallboard 20 is provided between the one PC cloth foundation 10 and the other PC cloth foundation 10 and each of the PC cloth foundations 10 is fixed. It is installed on the footing part 16 of 10.

【0054】このとき、PC壁板20の両端は、PC布
基礎10の溝部14に填め込まれる。この後、PC壁板
20の両端は、PC布基礎10の溝部14にコンクリー
トを打設することで、PC布基礎10と固定される。そ
して、この固定作業は、PC布基礎10及びPC壁板2
0の設置後、床梁30の取り付け前に行うのが最も効率
的である。
At this time, both ends of the PC wall plate 20 are fitted into the groove portions 14 of the PC cloth foundation 10. After that, both ends of the PC wall board 20 are fixed to the PC cloth foundation 10 by placing concrete in the grooves 14 of the PC cloth foundation 10. Then, this fixing work is performed by the PC cloth foundation 10 and the PC wall board 2.
It is most efficient to do this after installing 0 and before installing the floor beam 30.

【0055】具体的には、フーティング部16に形成さ
れたコンクリート充填口18にコンクリートを打設、養
生し固化する作業を行って、フーティング部16を地盤
70に固定するとともに、PC壁板20の下端部をもコ
ンクリートにて固定するだけで足りる。又、PC壁板2
0の下には、アンカーボルト又はアンカー鉄筋を突出さ
せて設けておき、これらをコンクリートと一体化させて
固定することが好ましい。
Specifically, concrete is poured into the concrete filling opening 18 formed in the footing portion 16 to fix and harden the footing portion 16 on the ground 70, and at the same time, to fix the PC wall board. It is enough to fix the lower end of 20 with concrete. Also, PC wall board 2
It is preferable that anchor bolts or anchor rebars are provided below 0, and these are integrally fixed to concrete.

【0056】また、PC底盤にてPC布基礎10を架設
すると、地盤70とフーティング部16との間に隙間が
形成されるので、コンクリートを打設した時にこの隙間
から侵入しコンクリートが前記コンクリート充填口18
に下から満たされて、上端部から溢れ出たことを確認し
てコンクリートの充填確実に行うことができる。
Further, when the PC cloth foundation 10 is laid on the PC bottom board, a gap is formed between the ground 70 and the footing portion 16. Therefore, when the concrete is placed, the concrete penetrates through the gap and the concrete becomes the concrete. Filling port 18
It can be surely filled with concrete by confirming that it is filled from below and overflowed from the upper end.

【0057】この作業は、建築現場においてフーティン
グ全体を構築する作業と比較すると、打設するコンクリ
ートが少量なので養生期間も短期間で足り、コンクリー
ト打設、養生し固化すると、このフーティング部16を
地盤70にしっかりと固定することができる。
Compared with the work of constructing the entire footing at the construction site, this work requires a small amount of concrete to be placed, so that the curing period is short and if the concrete is placed, cured and solidified, the footing portion 16 Can be firmly fixed to the ground 70.

【0058】こうして、PC布基礎10とPC壁板20
の取付固定が行われた後に、前記PC壁板20の切欠部
24に床梁30を挿入設置し、PC壁板20間に床梁3
0を架設する。その後、アンカーボルト等により、PC
壁板20と床梁30とを接合固定する。
Thus, the PC cloth foundation 10 and the PC wall board 20
After the fixing and fixing of the floor beams 30 are performed, the floor beams 30 are inserted and installed in the cutout portions 24 of the PC wall plates 20, and the floor beams 3 are provided between the PC wall plates 20.
Build 0. After that, with anchor bolts, etc., PC
The wall plate 20 and the floor beam 30 are joined and fixed.

【0059】その後、図2に示すように、PC布基礎1
0、PC壁板20、及び床梁30の上に床パネル40を
接合固定する。この時、PC壁板20間距離が、床パネ
ル40の短辺距離Aのn倍(nは床パネルの枚数)に予
め設定されている。また、床パネルの取り付けは、取付
誤差を小さくために、建物の中心より行うとよい。
Then, as shown in FIG. 2, the PC cloth foundation 1
The floor panel 40 is bonded and fixed onto the 0, the PC wall plate 20, and the floor beam 30. At this time, the distance between the PC wall plates 20 is preset to n times the short side distance A of the floor panel 40 (n is the number of floor panels). Also, the floor panel should be installed from the center of the building to reduce the installation error.

【0060】以上のように本実施例によれば、予め工場
段階において製造されたPC壁板20を建築現場におい
て対向するフーティング部16間に設置し、床梁30を
PC壁板20に取付固定すれば、この床梁30にて床を
支持できるので、図5の従来例に示すような束基礎84
や独立基礎を省略することができ、束工事の他に地業、
砕石締め固めをすることなどが不用となるため基礎工事
の工程が短縮でき、建築現場における基礎部構築作業を
より簡略化かつ迅速化できる。
As described above, according to this embodiment, the PC wall boards 20 manufactured in advance at the factory stage are installed between the facing footing parts 16 at the construction site, and the floor beams 30 are attached to the PC wall boards 20. If fixed, the floor beam 30 can support the floor, so that the bundle foundation 84 as shown in the conventional example of FIG.
And independent foundations can be omitted.
Since it is unnecessary to compact crushed stones, the process of foundation work can be shortened, and the work of constructing the foundation at the construction site can be simplified and speeded up.

【0061】また、図5に示す従来例のように束基礎や
独立基礎の水平レベル調整をPC布基礎と別個にしなけ
ればならなかったのに対し、本実施例ではPC布基礎1
0の水平レベル調整によって、PC壁板20の水平レベ
ル調整を兼用できる。すなわち、予め工場段階で寸法設
定されたPC布基礎10のフーティング部16の滑らか
な上面16aは、寸法精度が高いことに加えて、PC壁
板20を設置する前に、予め水平レベル調整されてい
る。このフーティング部16の上面16aに、プリキャ
ストされた寸法精度の高いPC壁板20を設置するの
で、PC壁板20の水平レベル調整は不要となる。この
ように、本実施例によれば、水平レベル調整の手間を簡
略化して作業効率の向上を図りながら、床梁30の支持
面の寸法精度を確保できる。
Further, unlike the conventional example shown in FIG. 5, the horizontal level adjustment of the bundle foundation and the independent foundation had to be made separately from the PC cloth foundation, whereas in this embodiment, the PC cloth foundation 1
By adjusting the horizontal level of 0, the horizontal level of the PC wallboard 20 can also be adjusted. That is, the smooth upper surface 16a of the footing portion 16 of the PC cloth foundation 10 preliminarily dimensioned at the factory stage has high dimensional accuracy and is preliminarily leveled before the PC wallboard 20 is installed. ing. Since the precast PC wallboard 20 having high dimensional accuracy is installed on the upper surface 16a of the footing portion 16, it is not necessary to adjust the horizontal level of the PC wallboard 20. As described above, according to the present embodiment, it is possible to secure the dimensional accuracy of the support surface of the floor beam 30 while simplifying the labor of horizontal level adjustment and improving the work efficiency.

【0062】また、このPC壁板20の下部には、フー
ティング部が形成されておらず軽量なので、建築現場へ
の輸送が便利である。さらに、PC壁板20の配置位置
を、部屋構造に適った床パネルの方向及び枚数に従って
設定し、予め所定間隔で設けられたPC布基礎10の溝
部14に前記PC壁板20を填め込み固定することによ
って、部屋構造に応じた構造耐力の強度を確保できる。
また、床パネル40の短辺寸法Aのn倍にPC壁板20
間距離を設定すればよいので、床パネル40を有効に使
用することができ、経済性に優れる。なお、床梁30を
鋼材にした場合には、部材の強度が強化され、さらに構
造耐力が強まり、入手困難な木材に比べてコストの削減
を図ることができる。
Further, since the footing portion is not formed on the lower portion of the PC wall board 20, the PC wall board 20 is light in weight, so that it can be easily transported to the construction site. Further, the arrangement position of the PC wallboard 20 is set according to the direction and the number of floor panels suitable for the room structure, and the PC wallboard 20 is fixed by being fitted in the groove portions 14 of the PC cloth foundation 10 provided at predetermined intervals in advance. By doing so, it is possible to secure the strength of structural proof strength according to the room structure.
In addition, the PC wallboard 20 is n times the short side dimension A of the floor panel 40.
Since it is only necessary to set the distance, the floor panel 40 can be effectively used and the economy is excellent. In addition, when the floor beam 30 is made of steel, the strength of the member is strengthened, and the structural yield strength is further strengthened, so that the cost can be reduced as compared with the wood which is difficult to obtain.

【0063】実施例2 次に、本発明に係る実施例2について図面に基づいて説
明する。尚、前記実施例1と実質的に同様の構成を有す
る部材には同一の符号を符し、その詳細な説明を省略す
る。
Second Embodiment Next, a second embodiment according to the present invention will be described with reference to the drawings. The members having substantially the same structure as those in the first embodiment are designated by the same reference numerals, and detailed description thereof will be omitted.

【0064】建築物構築領域に立ち上げ形成された基礎
の構造の一部において、床梁を外周布基礎に直角に配置
する場合の基礎構造を図3及び図4を用いて説明する。
In a part of the structure of the foundation that has been raised in the building construction area, the basic structure in the case of arranging the floor beams at right angles to the peripheral cloth foundation will be described with reference to FIGS. 3 and 4.

【0065】図3は、実施例2に係る基礎構造の一部を
切り欠いた斜視図である。図4は、図3におけるPC布
基礎10上に床パネル40を載置した状態を示す斜視図
である。
FIG. 3 is a perspective view in which a part of the basic structure according to the second embodiment is cut away. FIG. 4 is a perspective view showing a state in which the floor panel 40 is placed on the PC cloth foundation 10 in FIG.

【0066】前記実施例1同様、2つの相平行なPC布
基礎10間に、PC壁板50が架設されている。 PC
壁板50は、PC布基礎10同様、PC製で直方体状の
構造をなし、厚みがPC布基礎10とほぼ同程度となっ
ている。また、その高さは、フーティング部16の上端
面16aからPC布基礎10の上端面12bまでの距離
よりも、床梁60の厚さを引いた距離となっている。こ
れにより、PC壁板50の上端面に床梁60を取付固定
した際に、PC布基礎10の上端面12bと床梁60の
上端面60aが面一となる。そして、PC壁板50の下
端面は、滑らかな面となっているので、フーティング部
16の上端面に安定して載置できるようになっている。
また、このPC壁板50にも、長手方向側面には人道口
52が設けられている。
Similar to the first embodiment, the PC wall board 50 is installed between the two parallel PC cloth bases 10. PC
Similar to the PC cloth foundation 10, the wall plate 50 is made of PC and has a rectangular parallelepiped structure, and the thickness thereof is substantially the same as that of the PC cloth foundation 10. Further, the height is a distance obtained by subtracting the thickness of the floor beam 60 from the distance from the upper end surface 16a of the footing portion 16 to the upper end surface 12b of the PC cloth foundation 10. Thereby, when the floor beam 60 is attached and fixed to the upper end surface of the PC wall plate 50, the upper end surface 12b of the PC cloth foundation 10 and the upper end surface 60a of the floor beam 60 are flush with each other. Since the lower end surface of the PC wall plate 50 is a smooth surface, it can be stably placed on the upper end surface of the footing portion 16.
Further, the PC wall board 50 is also provided with a human entrance 52 on the side surface in the longitudinal direction.

【0067】次に、PC壁板50間の距離と床パネル4
0の幅との関係を図3及び図4に基づいて説明する。
Next, the distance between the PC wall boards 50 and the floor panel 4
The relationship with the width of 0 will be described based on FIGS. 3 and 4.

【0068】図3及び図4に示すように、床パネル40
の短辺の長さをA、長辺の長さをBとする。この時、2
つの相平行なPC布基礎10間の配列ピッチをnA(た
だし、nは自然数)に設定しておくと、PC布基礎10
及びPC壁板50上にn枚の床パネル40を載置した際
に、床パネルの幅Aに合わせることができ、床構面を小
さくすることができるので基礎部分の構造耐力が強ま
る。特に、床梁30がPC壁板50上に取付固定されて
いるので、実施例1に比べてさらに強度が増す。
As shown in FIGS. 3 and 4, floor panel 40.
Let A be the length of the short side and B be the length of the long side. At this time, 2
If the arrangement pitch between two parallel PC cloth foundations 10 is set to nA (where n is a natural number), the PC cloth foundation 10
Also, when n floor panels 40 are placed on the PC wall board 50, the width A of the floor panels can be matched, and the floor construction surface can be reduced, so that the structural strength of the foundation portion is strengthened. Particularly, since the floor beam 30 is attached and fixed on the PC wall plate 50, the strength is further increased as compared with the first embodiment.

【0069】また、PC布基礎10に対して床パネル4
0の短辺Aを直角に設置する場合には、床パネル40の
長辺距離Bの両端部がPC壁板50に支持されるので、
固定後の構造耐力が強化される。逆に、構造耐力を確保
しようとして、予めPC布基礎10間距離を小さくする
場合などは、床パネル40の短辺寸法Aのn倍にPC布
基礎10間ピッチを設定すればよいので、床パネル40
を有効に使用することができる。
The floor panel 4 is attached to the PC cloth foundation 10.
When the short side A of 0 is installed at a right angle, both end portions of the long side distance B of the floor panel 40 are supported by the PC wall board 50.
The structural yield strength after fixing is strengthened. On the contrary, when the distance between the PC cloth foundations 10 is reduced in advance in order to secure the structural strength, the pitch between the PC cloth foundations 10 may be set to n times the short side dimension A of the floor panel 40. Panel 40
Can be used effectively.

【0070】また、PC壁板50間距離を床パネル40
の長辺距離Bに合わせるか、或いは、長辺距離B以下に
することにより、さらに床構面を小さくすることがで
き、基礎部分の構造耐力が強まる。
Further, the distance between the PC wall boards 50 is set to the floor panel 40.
By adjusting to the long side distance B of the above, or by setting it to be the long side distance B or less, the floor structure can be further reduced, and the structural strength of the foundation portion is strengthened.

【0071】本実施例における施工方法は、前記実施例
1と同様、予め工場段階で製造されたPC布基礎10及
びPC壁板50を、建築現場において組み立てるという
方法を採用している。
The construction method in this embodiment employs a method of assembling the PC cloth foundation 10 and the PC wallboard 50 manufactured in advance at the factory stage at the construction site, as in the first embodiment.

【0072】本実施例2における効果は、前記実施例1
と同様の効果を奏しながらも、床梁60下部にPC壁板
50があるので実施例1に比べてさらに強度が強まる。
The effects of the second embodiment are the same as those of the first embodiment.
Although the same effect as described above is obtained, since the PC wall plate 50 is provided under the floor beam 60, the strength is further increased as compared with the first embodiment.

【0073】尚、本発明は上記実施例に限定されるもの
ではなく、本発明の要旨の範囲内で種々の変形実施が可
能である。例えば、本発明により構築される基礎の上の
床部の構築については、上記実施例のパネル工法以外の
工法を採用できることはいうまでもない。
The present invention is not limited to the above embodiment, and various modifications can be made within the scope of the gist of the present invention. For example, it goes without saying that a construction method other than the panel construction method of the above-mentioned embodiment can be adopted for the construction of the floor portion on the foundation constructed according to the present invention.

【0074】[0074]

【発明の効果】請求項1〜6の各発明によれば、地業作
業、水平レベル調整作業がそれぞれ必要な束基礎、独立
基礎等を省略でき、現場施工を簡略化できる。また、基
礎部分を枠組状にすることが可能となり、床構面を小さ
くすることができるので、水平荷重及び鉛直荷重に対す
る強度が強まり、かつ地盤上に支点をつくることができ
支点間距離が小さくなるので構造耐力が高まるなどの効
果を奏することができる。
According to the inventions of claims 1 to 6, it is possible to omit the bundle foundation, the independent foundation, etc., which respectively require the earthwork work and the horizontal level adjustment work, and to simplify the on-site construction. In addition, since the foundation part can be framed and the floor structure can be made smaller, the strength against horizontal load and vertical load is increased, and fulcrums can be created on the ground, and the distance between fulcrums is small. Therefore, it is possible to obtain an effect such as an increase in structural yield strength.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の実施例1に係る基礎構造の一部を切り
欠いた斜視図である。
FIG. 1 is a perspective view in which a part of a basic structure according to a first embodiment of the present invention is cut away.

【図2】図1におけるPC布基礎上に床パネルを載置し
た状態を示す斜視図である。
FIG. 2 is a perspective view showing a state in which a floor panel is placed on the PC cloth foundation in FIG.

【図3】本発明の実施例2に係る基礎構造の一部を切り
欠いた斜視図である。
FIG. 3 is a perspective view in which a part of a basic structure according to a second embodiment of the present invention is cut away.

【図4】図3におけるPC布基礎上に床パネルを載置し
た状態を示す斜視図である。
FIG. 4 is a perspective view showing a state in which a floor panel is placed on the PC cloth foundation in FIG.

【図5】従来の基礎の概略斜視図である。FIG. 5 is a schematic perspective view of a conventional foundation.

【符号の説明】[Explanation of symbols]

10 PC布基礎 12 立上部 14 溝部 16 フーティング部 18 コンクリート充填口 20、50 PC壁板 22、52 人道口 24 切欠部 30、60 床梁 34 取付ボルト 70 地盤 10 PC cloth foundation 12 Vertical part 14 Groove part 16 Footing part 18 Concrete filling port 20, 50 PC wall plate 22, 52 Human way entrance 24 Notch part 30, 60 Floor beam 34 Mounting bolt 70 Ground

Claims (6)

【特許請求の範囲】[Claims] 【請求項1】 建物の構築領域で地盤を連続的に掘削し
て形成された根切り部に所定間隔で設置される複数のプ
レキャストコンクリート底盤と、 鉛直方向に直立して建物を支持する立上部と、この立上
部の下部から側方に突出するフーティング部と、を有
し、前記プレキャストコンクリート底盤間に平行に複数
架設されるプレキャストコンクリート基礎と、 平行な前記プレキャストコンクリート基礎の各々の前記
フーティング部上に両端が載置されることで、平行な前
記プレキャストコンクリート基礎間に架設され、前記プ
レキャストコンクリート基礎間に配置される床梁を支持
するプレキャストコンクリート壁板と、 を有することを特徴とする基礎構造。
1. A plurality of precast concrete bottom plates installed at predetermined intervals in a root cutting portion formed by continuously excavating the ground in a building construction area, and an upright portion which stands vertically and supports the building. And a footing portion that projects laterally from the lower part of the rising portion, and a plurality of precast concrete foundations that are installed in parallel between the precast concrete bottom boards, and the foot of each of the parallel precast concrete foundations. A precast concrete wall board that is installed between the precast concrete foundations that are parallel to each other and that supports the floor beams that are arranged between the precast concrete foundations, by placing both ends on the towing portion. Foundation structure to do.
【請求項2】 請求項1において、 前記プレキャストコンクリート壁板は、前記立上部の上
面とほぼ面一となる上端面と、この上端面より前記床梁
の厚さ分だけ切り欠いた切欠部と、を有し、前記プレキ
ャストコンクリート基礎間にて該基礎に平行に配置され
る前記床梁を、前記切欠部にて支持することを特徴とす
る基礎構造。
2. The precast concrete wall plate according to claim 1, wherein the precast concrete wall plate has an upper end surface that is substantially flush with the upper surface of the upright portion, and a cutout portion cut out from the upper end surface by the thickness of the floor beam. And the floor beams arranged between the precast concrete foundations in parallel with the foundations are supported by the notches.
【請求項3】 請求項1において、 前記プレキャストコンクリート壁板は、前記立上部の上
面より前記床梁の厚さ分だけ低い上端面を有し、前記プ
レキャストコンクリート基礎間にて該基礎に直交して配
置される前記床梁を、前記上端面にて支持することを特
徴とする基礎構造。
3. The precast concrete wallboard according to claim 1, wherein the precast concrete wallboard has an upper end surface lower than an upper surface of the rising portion by a thickness of the floor beam, and is orthogonal to the precast concrete foundation between the foundations. A foundation structure, characterized in that the floor beams arranged as a structure are supported by the upper end surface.
【請求項4】 請求項1乃至3のいずれかにおいて、 前記プレキャストコンクリート基礎は、前記立上部の側
面に、前記プレキャストコンクリート壁板の端部を挿入
する溝部を有することを特徴とする基礎構造。
4. The foundation structure according to claim 1, wherein the precast concrete foundation has a groove portion on a side surface of the rising portion into which an end portion of the precast concrete wall board is inserted.
【請求項5】 請求項1乃至乃至4のいずれかにおい
て、 前記プレキャストコンクリート壁板は、その一方の側面
より他方の側面に貫通する人道口を有することを特徴と
する基礎構造。
5. The foundation structure according to any one of claims 1 to 4, wherein the precast concrete wall board has a human way opening that penetrates from one side surface to the other side surface.
【請求項6】 建物の構築領域で地盤を連続的に掘削し
て形成された根切り部に所定間隔で複数のプレキャスト
コンクリート底盤を設置する工程と、 鉛直方向に直立して建物を支持する立上部と、この立上
部の下部から側方に突出するフーティング部と、を有す
るプレキャストコンクリート基礎を、前記プレキャスト
コンクリート底盤間に平行に複数架設する工程と、 平行な前記プレキャストコンクリート基礎の各々の前記
フーティング部の上に、プレキャストコンクリート壁板
の両端を載置して、前記プレキャストコンクリート基礎
と直角に前記プレキャストコンクリート壁板を架設する
工程と、 を有することを特徴とする基礎の施工方法。
6. A step of installing a plurality of precast concrete bottom plates at a predetermined interval in a root cutting part formed by continuously excavating the ground in a building construction area, and a vertical standing upright to support the building. A step of installing a plurality of precast concrete foundations having an upper portion and a footing portion projecting laterally from the lower portion of this rising portion in parallel between the precast concrete bottom boards, and each of the parallel precast concrete foundations A step of placing both ends of the precast concrete wall board on the footing part and erecting the precast concrete wall board at a right angle to the precast concrete foundation.
JP06270229A 1994-10-07 1994-10-07 Foundation structure and foundation construction method Expired - Fee Related JP3086384B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP06270229A JP3086384B2 (en) 1994-10-07 1994-10-07 Foundation structure and foundation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP06270229A JP3086384B2 (en) 1994-10-07 1994-10-07 Foundation structure and foundation construction method

Publications (2)

Publication Number Publication Date
JPH08105062A true JPH08105062A (en) 1996-04-23
JP3086384B2 JP3086384B2 (en) 2000-09-11

Family

ID=17483355

Family Applications (1)

Application Number Title Priority Date Filing Date
JP06270229A Expired - Fee Related JP3086384B2 (en) 1994-10-07 1994-10-07 Foundation structure and foundation construction method

Country Status (1)

Country Link
JP (1) JP3086384B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020012330A (en) * 2018-07-20 2020-01-23 矢野 秀夫 Building foundation block

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101457432B1 (en) * 2014-05-16 2014-11-12 제이씨코리아 주식회사 A Device for applying a nail applique, a sheet of nail appliques and a method for applying a nail applique

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2020012330A (en) * 2018-07-20 2020-01-23 矢野 秀夫 Building foundation block

Also Published As

Publication number Publication date
JP3086384B2 (en) 2000-09-11

Similar Documents

Publication Publication Date Title
JP6871495B1 (en) Solid foundation formwork and solid foundation construction method
KR101880813B1 (en) A sandwitch pc pannel structure and construction method of structure using thereof
JP3086384B2 (en) Foundation structure and foundation construction method
JP2000220150A (en) Bundled stone-like body, and forming method for pressure-resisting board type foundation
JP3191951B2 (en) Foundation construction method
JPH09151463A (en) Column-integrated column base anchoring foundation structire and work execution method therefor
JP2860501B2 (en) Concrete foundation
JP2784450B2 (en) Reinforced concrete foundation
JP2004285581A (en) Steel framed foundation material for building and formation method of concrete foundation for building making use of steel framed base foundation material
JP3244102U (en) Steel house foundation structure and anchor set used therein
JP3143324B2 (en) Foundation structure and foundation construction method
EA021900B1 (en) Method for producing prefabricated structural parts
JP3609451B2 (en) Precast concrete foundation structure
JPH06306874A (en) Concrete block for footing
JP3776544B2 (en) Building basic structure
JPH05239835A (en) Independent foundation with form
JP2905056B2 (en) Foundation structure
JP3729890B2 (en) Single-sided precast concrete underground beam and its components
JPH0782755A (en) Foundation structure and constructing method for foundation
JP3249076B2 (en) Building floor and foundation structure
JPH084029A (en) Precast concrete foundation structure
JP2512254B2 (en) Structure of artificial ground and structure of house
JPH084027A (en) Foundation structure
JP2005320686A (en) Reinforcement assembly body used for housing foundation and construction method of the housing foundation making use of the assembly body
JPH08189044A (en) Mat foundation structure and method for construction thereof

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20000627

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080707

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090707

Year of fee payment: 9

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313111

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090707

Year of fee payment: 9

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090707

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100707

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110707

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130707

Year of fee payment: 13

LAPS Cancellation because of no payment of annual fees