JPH0416630A - Residence base construction method - Google Patents

Residence base construction method

Info

Publication number
JPH0416630A
JPH0416630A JP12056490A JP12056490A JPH0416630A JP H0416630 A JPH0416630 A JP H0416630A JP 12056490 A JP12056490 A JP 12056490A JP 12056490 A JP12056490 A JP 12056490A JP H0416630 A JPH0416630 A JP H0416630A
Authority
JP
Japan
Prior art keywords
foundation
building
concrete
members
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP12056490A
Other languages
Japanese (ja)
Inventor
Akira Kishi
明 岸
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Misawa Homes Co Ltd
Original Assignee
Misawa Homes Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Misawa Homes Co Ltd filed Critical Misawa Homes Co Ltd
Priority to JP12056490A priority Critical patent/JPH0416630A/en
Publication of JPH0416630A publication Critical patent/JPH0416630A/en
Pending legal-status Critical Current

Links

Abstract

PURPOSE:To shorten the construction period by erecting supporting members at the position corresponding to the columns of a house, arranging forms on both sides of the supporting members connected to each other, pouring concrete slurry in the forms, and building the house while the concrete slurry is cured. CONSTITUTION:Supporting members 9 to 11 are erected at the positions in a construction site corresponding to the positions for the columns of a house 3 to be built on a base 2 and are connected to each other by connecting members 12... and 13... made of precast concrete. Next, forms 43... are arranged on both sides of the lower sections of the supporting members 9 to 11 and connecting members 12... and 13..., and concrete slurry is poured in the forms 43.... While the concrete slurry is cured, the house 3 is built on the supporting members 9 to 11 and connecting members 12... and 13....

Description

【発明の詳細な説明】 〔産業上の利用分野〕 本発明は、住宅のコンクリート製基礎を施工する方法に
係り、ユニット住宅の基礎や、鉄骨軸組みを含めた在来
工法による住宅の基礎に利用できるものである。
[Detailed Description of the Invention] [Field of Industrial Application] The present invention relates to a method of constructing concrete foundations for houses, and is applicable to foundations of unit houses and houses using conventional construction methods, including steel frames. It is available.

〔背景技術〕[Background technology]

複数の住宅ユニットを組み合わせることにより建てられ
るユニット住宅や、鉄骨軸組みを含めた在来工法による
住宅では、従来において、建設現場の捨てコンクリート
の上に型枠を糾み立て、この型枠内にコンクリートスラ
リーを打設することによって基礎を作り、この基礎の完
成後、基礎の上に建てられる建物の建築作業か始められ
ていた。
Conventionally, for unit houses built by combining multiple housing units and houses built using conventional construction methods including steel frames, a formwork is erected on top of the abandoned concrete at the construction site, and the inside of this formwork is A foundation was created by pouring concrete slurry, and once this foundation was completed, construction work on the building that would be built on top of the foundation began.

また、基礎のベース部と立上部の両方について、工場で
予め製作された短寸法のプレキャストコンクリートを建
設現場で並へて連結することにより基礎を作ることも行
われていた(特開昭62−112825、特開昭64−
83747、特開昭60−92517等)か、このよう
な従来技術でも、基礎の完成後に基礎の上の建物の建築
作業が開始されていた。
In addition, for both the base and upright parts of the foundation, the foundation was also constructed by connecting short precast concrete pieces prefabricated at a factory in parallel at the construction site (Japanese Patent Application Laid-Open No. 1983-1999-1). 112825, Japanese Patent Publication No. 64-
83747, Japanese Unexamined Patent Publication No. 60-92517, etc.), and even with such conventional techniques, construction work for a building on the foundation was started after the foundation was completed.

すなわち、従来では、基礎を作る作業が終了した後に基
礎の上の建物の建築作業が行われていた。
That is, in the past, construction work for a building on the foundation was performed after the work to create the foundation was completed.

〔発明が解決しようとする課題〕[Problem to be solved by the invention]

このような従来技術によると、基礎が完成した後でなけ
れば建物の建築作業を始めることができないため、それ
だけ住宅の施工期間が長くなるという問題があった。
According to such conventional technology, the construction work of the building cannot be started until after the foundation is completed, so there is a problem that the construction period of the house becomes longer.

特に、ユニット住宅は、工場で予め生産された住宅ユニ
ットを使用するユニット工法で建てられ、工業化率の向
上、建設現場作業割合の低下を図ることにより建設現場
作業期間を短縮することを主要目的としており、基礎の
完成後でなければ基礎より上の建物の建築作業を始める
ことができないことは、基礎施工作業期間性だけ建設現
場での住宅の施工期間が長くなるため、ユニット住宅の
上記主要目的を基礎施工作業のため十分に達成できない
ことになる。
In particular, unit housing is built using the unit construction method, which uses housing units pre-produced in factories, with the main purpose of shortening the construction site work period by improving the industrialization rate and reducing the proportion of construction site work. However, construction work on the building above the foundation cannot begin until after the foundation is completed, which means that the construction period for the house at the construction site is longer due to the period of foundation construction work. This cannot be fully achieved due to foundation construction work.

また、プレキャストコンクリートを使用している従来技
術では、基礎のベース部もプレキャストコンクリート製
となっているため、捨てコンクリートの正確なレベル出
し作業を必要とし、それだけ作業性が悪かった。
In addition, in the conventional technology using precast concrete, the base of the foundation is also made of precast concrete, which requires accurate leveling of the discarded concrete, which makes workability that much worse.

本発明の目的は、基礎の完成7前から基礎より上の建物
の建築作業を完成でき、このため建設現場での住宅の施
工期間を短縮でき、また、捨てコンクリートの正確なレ
ベル出し作業が不要になる住宅の基礎施工方法を提供す
るところにある。
The purpose of the present invention is to be able to complete the construction work of the building above the foundation seven days before the foundation is completed, thereby shortening the construction period of the house at the construction site, and eliminating the need for accurate leveling of waste concrete. The purpose is to provide a method for constructing the foundation of a home that will become a reality.

〔課題を解決するための手段〕[Means to solve the problem]

本発明に係る住宅の基礎施工方法は、基礎より上に建て
られる建物の柱の位置と対応する建設現場の位置に支柱
部材を立て、これらの支柱部材をプレキャストコンクリ
ート製の連結部材で連結するとともに、前記支柱部材お
よびこの連結部材の下部両側に型枠を配置し、この型枠
内にコンクリートスラリーを打設し、前記支柱部材およ
び前記連結部材の上で前記建物を建てる建築作業を前記
コンクリートスラリーの養生と同時進行させて行うこと
を特徴とするものである。
The method for constructing a foundation for a house according to the present invention includes the steps of: erecting strut members at positions on a construction site corresponding to the positions of pillars of a building to be built above the foundation; connecting these strut members with connecting members made of precast concrete; , formwork is placed on both sides of the lower part of the support member and the connection member, concrete slurry is poured into the formwork, and construction work for constructing the building on the support member and the connection member is carried out using the concrete slurry. It is characterized by being carried out at the same time as the curing of the body.

前記建物を建てる建築作業は型枠内にコンクリートスラ
リーを打設した後に始めてもよいが、型枠の配置作業後
であってスラリー打設作業前に始めてもよく、または型
枠の配置作業前から始めてもよい。
The construction work for constructing the building may be started after pouring the concrete slurry into the formwork, but it may also be started after the formwork placement work and before the slurry pouring work, or even before the formwork placement work. You can start.

〔作用〕[Effect]

それぞれの支柱部材を連結部材で連結すると、支柱部材
は互いに位置が定まって倒れない状態になるため、これ
らの支柱部材および連結部材の上で建物の建築作業を開
始できる。この建築作業中における建物の重量は支柱部
材により支持される。
When the respective support members are connected by the connecting members, the positions of the support members are determined relative to each other and the construction work of the building can be started on these support members and the connecting members. The weight of the building during this construction work is supported by the support members.

このため、前記型枠内に打設するコンクリートスラリー
が凝固するのを待って建物の建築作業を開始する必要が
なく、これにより建設現場における作業期間を短縮でき
る。
Therefore, there is no need to wait until the concrete slurry poured into the formwork solidifies before starting the building construction work, thereby shortening the work period at the construction site.

また、型枠にコンクリートスラリーを打設すると、この
スラリーはプレキャストコンクリート製の前記連結部材
の下側に入り込むため、捨てコンクリートがレベル出し
作業を行われていないものとなっていても、捨てコンク
リートと連結部材を確実に連結できる。
In addition, when concrete slurry is poured into the formwork, this slurry enters the underside of the connecting member made of precast concrete, so even if the waste concrete has not been leveled, it is considered waste concrete. Connecting members can be reliably connected.

〔実施例〕〔Example〕

以下に本発明の一実施例を添付図面に基づいて説明する
An embodiment of the present invention will be described below based on the accompanying drawings.

第1図は本実施例が適用された住宅1の、全体概略図を
示し、この図では住宅1の基礎2は、基礎2の上に立て
られる建物3の建築作業開始時の状態で示されている。
FIG. 1 shows an overall schematic diagram of a house 1 to which this embodiment is applied, and in this figure, the foundation 2 of the house 1 is shown in the state at the start of the construction work of a building 3 to be erected on the foundation 2. ing.

本実施例に係る住宅lは建物3が複数の住宅ユニット4
で構成されるユニット住宅となっており、第12図は住
宅ユニット4の骨組み5を示す。骨組み5は四隅の4本
の柱6の上端間、下端間を各4本の上梁7、下梁8で結
合することにより構成され、骨組み4に壁材や天井材、
床材等が工場で取り付けられ、このように工場で予め生
産された複数の住宅ユニット4を第13図の通り建設現
場で組み合わすことにより住宅lの建物3がユニット工
法で建てられる。
In the housing l according to this embodiment, the building 3 has a plurality of housing units 4.
12 shows the frame 5 of the housing unit 4. The frame 5 is constructed by connecting the upper and lower ends of four pillars 6 at the four corners with four upper beams 7 and four lower beams 8, and the frame 4 has wall materials, ceiling materials,
Flooring materials and the like are installed in a factory, and the building 3 of the house 1 is constructed using the unit construction method by combining a plurality of housing units 4, which have been produced in advance at the factory, at the construction site as shown in FIG. 13.

第1図で示されている基礎2は第1、第2、第3の各支
柱部材9,10.11と第1、第2の各連結部材12.
13とを含んで構成されたものとなっている。各支柱部
材9,10.11は建物3の柱、すなわち、本実施例で
は住宅ユニット4の前記柱6が配置される位置と対応し
た建設現場の位置に配置される。これらのうち、第1支
柱部材9は柱6が複数本寄せ集まっていない部分の下側
、具体的には1本の柱6だけがある建物3の出隅みコー
ナ部分の下側に配置され、第2支柱部材10は柱6が2
本寄せ集まっている部分の下側、具体的には2個の住宅
ユニット4が前後または左右に隣り合っている部分の下
側に配置され、第3支柱部材11は柱6が4本寄せ集ま
っている部分の下側、具体的には4個の住宅ユニット4
が前後および左右に隣り合っている部分の下側に配置さ
れる。
The foundation 2 shown in FIG.
13. Each pillar member 9, 10.11 is arranged at a position on the construction site corresponding to the position where the pillar of the building 3, that is, the pillar 6 of the housing unit 4 in this embodiment is arranged. Among these, the first support member 9 is arranged under the part where multiple pillars 6 are not gathered together, specifically under the protruding corner part of the building 3 where there is only one pillar 6. , the second support member 10 has two pillars 6
The third pillar member 11 is arranged under a part where four pillars 6 are gathered together, specifically, under a part where two housing units 4 are adjacent to each other in the front and back or left and right. The lower part of the housing unit 4, specifically the 4 housing units
are placed below the adjacent parts front to back and left and right.

第1、第2の各連結部材12.13は支柱部材9.10
.11を互いに連結するためのものであり、かつ、これ
らのうち、第1連結部材12は基礎2の外回り壁部2A
を構成するものとなっており、第2連結部材13は基礎
2の中通り壁部2Bを構成するものとなっている。また
、これらの連結部材12.13は工場で予め製作された
プレキャストコンクリート製となっている。
Each of the first and second connecting members 12.13 is a support member 9.10.
.. 11 to each other, and among these, the first connecting member 12 is connected to the outer wall portion 2A of the foundation 2.
The second connecting member 13 constitutes the middle wall portion 2B of the foundation 2. Further, these connecting members 12 and 13 are made of precast concrete manufactured in advance at a factory.

第2図は第1支柱部材9を示し、この支柱部材9は1本
の角柱材14からなり、直交する2つの側面にはボルト
孔15付きのブラケット16が接合され、上端および下
端にはベースプレート17、トッププレート18が取り
付けられている。トッププレート18にはグラウト材1
9が充填されるシース管20とレベル調整ボルト21と
が各1個取り付けられている。
FIG. 2 shows the first support member 9. This support member 9 is made of a single prismatic member 14, and brackets 16 with bolt holes 15 are joined to two orthogonal sides, and base plates are attached to the upper and lower ends. 17, a top plate 18 is attached. Grout material 1 is applied to the top plate 18.
One sheath tube 20 filled with 9 and one level adjustment bolt 21 are attached.

第3図は第2支柱部材10を示し、この支柱部材10は
2本の角柱材14からなり、3つの側面には前記ブラケ
ット16が接合されているとともに、下端および上端に
はベースプレート22、トッププレート23が取り付け
られ、トッププレート23には前記シース管20と前記
レベル調整ボルト21が各2個取り付けられている。
FIG. 3 shows a second support member 10, which is made up of two prismatic members 14, and has the brackets 16 joined to three sides, a base plate 22 at the lower end and an upper end, and a top support member 10. A plate 23 is attached, and two sheath tubes 20 and two level adjustment bolts 21 are attached to the top plate 23, respectively.

第4図は第3支柱部材11を示し、この支柱部材11は
4本の角柱材14からなり、180度反対側の2つの側
面には前記ブラケット16が接合されているとともに、
下端および上端にはベースプレート24、トッププレー
ト25か取り付けられ、トッププレート25には前記シ
ース管20とレベル調整ボルト21が各4個取り付けら
れている。
FIG. 4 shows a third support member 11, which is made up of four prismatic members 14, and the brackets 16 are joined to two sides 180 degrees opposite each other.
A base plate 24 and a top plate 25 are attached to the lower and upper ends, and the sheath tube 20 and four level adjustment bolts 21 are attached to the top plate 25, respectively.

以上において、それぞれのシース管20は、第1支柱部
材9について示している第9図の通り、角柱材14の内
部に接合配置されたブラケット26に載せられて支持さ
れている。
In the above description, each sheath tube 20 is supported by being mounted on a bracket 26 that is connected and arranged inside the prismatic member 14, as shown in FIG. 9 for the first support member 9.

第5図は第1連結部材12を示し、この連結部材12の
長手方向両端部は切欠部27により薄肉部12Aとなっ
ており、薄肉部12Aの先端面は45度の傾斜面12B
となっている。切欠部27の側面27Aにはボルト孔2
8付きのブラケット29が設けられ、また連結部材12
の下面にはレベル調整ボルト30か設けられている。こ
のレベル調整ボルト30が螺合されたナツト31および
ブラケット29は連結部材12の内部に埋設されている
配筋材32に接合されている。
FIG. 5 shows the first connecting member 12. Both ends of the connecting member 12 in the longitudinal direction are formed into thin-walled portions 12A by notches 27, and the tip surface of the thin-walled portions 12A is a 45-degree inclined surface 12B.
It becomes. A bolt hole 2 is provided in the side surface 27A of the notch 27.
A bracket 29 with 8 is provided and also a connecting member 12
A level adjustment bolt 30 is provided on the bottom surface. The nut 31 to which the level adjustment bolt 30 is screwed and the bracket 29 are joined to a reinforcing member 32 buried inside the connecting member 12.

この第1連結部材12の長さは前記住宅二ニット4の柱
6相互の間隔に基づいて定められ、複数の連結部材12
を長手方向に並べると柱6相互の間隔と同じになるよう
に設定する。柱6相互の間隔が住宅ユニット4の前後方
向と左右方向とで異なる場合には、2種類の連結部材1
2を用意する。
The length of the first connecting member 12 is determined based on the distance between the pillars 6 of the housing unit 4, and the length of the first connecting member 12 is
When arranged in the longitudinal direction, the spacing between the pillars 6 is set to be the same as that between the pillars 6. If the distance between the pillars 6 is different in the front-rear direction and the left-right direction of the housing unit 4, two types of connecting members 1 are used.
Prepare 2.

第6図は第2連結部材13を示す。この連結部材13の
長手方向両端部には縦溝33が形成され、この縦溝33
を貫通するように連結部材13の両端部にはボルト孔3
4が設けられている。また連結部材13の下面には前記
レヘル調整ホル)30か設けられ、このレベル調整ホル
)30が螺合されたナツト31は連結部材13の内部に
埋設されている配筋材35に接合されている。
FIG. 6 shows the second connecting member 13. A vertical groove 33 is formed at both longitudinal ends of the connecting member 13.
Bolt holes 3 are provided at both ends of the connecting member 13 so as to penetrate through the
4 is provided. Further, the level adjustment hole 30 is provided on the lower surface of the connecting member 13, and the nut 31 into which the level adjusting hole 30 is screwed is joined to the reinforcing material 35 buried inside the connecting member 13. There is.

この第2連結部材13の長さも住宅ユニット4の柱6相
互の間隔に基ついて定められ、複数の連結部材13を長
手方向に並へると柱6相互の間隔と同じになるように設
定する。
The length of this second connecting member 13 is also determined based on the mutual spacing between the columns 6 of the housing unit 4, and is set so that when the plurality of connecting members 13 are lined up in the longitudinal direction, the distance is the same as the mutual spacing between the columns 6. .

次に基礎2の施工作業について説明する。Next, the construction work for foundation 2 will be explained.

建設現場の根切り底には捨てコンクリート36(第9図
参照)が打設され、この捨てコンクリ−ト36上におい
て第1、第2、第3の支柱部材9゜10.11をそれぞ
れ所定位置に立てる。この後、第1図の通り前記外回り
壁部2Aを構成する第1連結部材12を前記レベル調整
ボルト30で高さレベルを調整しながら第1支柱部材9
、第2支柱部材IOの間に配置し、第7図の通りこれら
の支柱部材9,10のブラケット16と連結部材12の
ブラケット29とをボルト37、ナツト38で連結し、
また隣り合う連結部材12のブラケット29相互をコネ
クトプレート39とボルト37、ナツト38とで連結す
る。
A sacrificial concrete 36 (see Fig. 9) is placed at the bottom of the root cut at the construction site, and the first, second, and third support members 9, 10, and 11 are placed at predetermined positions on this sacrificial concrete 36, respectively. stand on After this, as shown in FIG.
, and the brackets 16 of these support members 9 and 10 and the bracket 29 of the connecting member 12 are connected with bolts 37 and nuts 38, as shown in FIG.
Further, the brackets 29 of adjacent connecting members 12 are connected to each other by a connect plate 39, bolts 37, and nuts 38.

これにより外回り壁部2Aが出来上がり、連結部材12
には支柱部材9,10を後ろ側に隠す前記薄肉部12A
が設けられているため、支柱部材9.12は外側に露出
せず、外回り壁部2Aは、外見上、プレキャストコンク
リート製の連結部材12のみとなる。また、連結部材1
2の両端面には45度の傾斜面12Bが設けられている
ため、第1支柱部材9が配置された出隅みコーナ部分に
2個の連結部材12を隙間なく直角に配置でき、かつ、
複数の連結部材12を長手方向に隙間なく直線的に配置
することもでき、従って、基礎2の直角部分と直線部分
について連結部材12を共通して使用できる。
As a result, the outer wall portion 2A is completed, and the connecting member 12
The thin wall portion 12A hides the support members 9 and 10 on the rear side.
are provided, the support members 9.12 are not exposed to the outside, and the outer wall portion 2A appears to consist of only the connecting member 12 made of precast concrete. In addition, the connecting member 1
Since the 45 degree inclined surfaces 12B are provided on both end surfaces of 2, the two connecting members 12 can be arranged at right angles without any gaps in the protruding corner portion where the first support member 9 is arranged, and
A plurality of connecting members 12 can also be arranged linearly in the longitudinal direction without gaps, so that the connecting members 12 can be used in common for the right-angled portion and the straight portion of the foundation 2.

第1図の通り基礎2の中通り壁部2Bを構成する第2連
結部材13は第2支柱部材10と第3支柱部材11の間
に前記レベル調整ボルト30で高さレベルが調整されな
がら配置される。この配置作業は上方から行われ、これ
により第7図の通り連結部材13の前記縦溝33に支柱
部材10,11のブラケット16を挿入し、ボルト40
、ナツト41で支柱部材10,11と連結部材13とを
連結する。隣り合う連結部材13相互の連結はこれらの
縦溝33に挿入したコネクトプレート42とボルト40
、ナツト41とで行う。
As shown in FIG. 1, the second connecting member 13 constituting the middle wall portion 2B of the foundation 2 is placed between the second support member 10 and the third support member 11, with the height level being adjusted by the level adjustment bolt 30. be done. This arrangement work is performed from above, and as a result, as shown in FIG.
, the support members 10 and 11 and the connecting member 13 are connected by a nut 41. Adjacent connecting members 13 are connected to each other by connecting plates 42 and bolts 40 inserted into these vertical grooves 33.
, Nut41.

以上により、全ての支柱部材9,10.11は連結部材
12.13を介して互いに連結されたことになり、この
ため支柱部材9. 1’0. 11は直立状態を維持し
、倒れないものとなる。
As a result of the above, all the strut members 9, 10.11 are connected to each other via the connecting members 12.13, and therefore the strut members 9. 1'0. 11 will maintain an upright state and will not fall over.

以上の作業後、第1図の通り外回り壁部2Aおよび中通
り壁部2Bの下部両側、すなわち支柱部材9,10.1
1および連結部材12.13の下部両側に型枠43を配
置する。そして両側の型枠43を溶接等される連結材4
4で連結する。本実施例ではこの型枠43は第8図の通
りアングル材からなり、その高さ寸法は小さく、第9図
、第1O図の通り支柱部材9,10,11、連結部材1
2.13の下部のみを囲むものとなっている。
After the above work, as shown in FIG.
Formwork 43 is placed on both sides of the lower part of 1 and the connecting member 12.13. Then, the connecting material 4 is welded to the formwork 43 on both sides.
Connect with 4. In this embodiment, the formwork 43 is made of an angle material as shown in Fig. 8, and its height dimension is small, and as shown in Figs.
It encloses only the lower part of 2.13.

これらの型枠43によりスラリー打設空間45が形成さ
れ、この空間45に第11図の通りコンクリートスラリ
ー46を打設する。
A slurry pouring space 45 is formed by these formworks 43, and a concrete slurry 46 is poured into this space 45 as shown in FIG.

このコンクリートスラリー46の打設作業が終了した後
にただちに、すなわちコンクリートスラリー46が凝固
するのを待たずに、基礎2より上の前記建物3の建築作
業を始める。コンクリートスラリー46が凝固する前に
建物3の建築作業を始めても、前述の通り全ての支柱部
材9,10゜11は連結部材12.13で連結されてい
て倒れない状態になっているため、建物3の重量を支柱
部材9,10.11で確実に支持しながら建物3の建築
作業を行なえる。
Immediately after the pouring of the concrete slurry 46 is completed, that is, without waiting for the concrete slurry 46 to solidify, the construction work of the building 3 above the foundation 2 is started. Even if construction work on the building 3 is started before the concrete slurry 46 solidifies, the building will not collapse because all the support members 9, 10 and 11 are connected by the connecting members 12 and 13 as mentioned above. The construction work of the building 3 can be carried out while the weight of the building 3 is surely supported by the support members 9, 10, 11.

建物3の建築作業は初めに1階用の前記住宅ユニット4
をクレーンで吊り上げることから開始され、この住宅ユ
ニット4を徐々に降ろし、第9図の通り住宅ユニット4
の柱6から下方へ突設されたアンカ一部材47を支柱部
材9,10.11の前記グラウト材19が充填されたシ
ース管20内に挿入しながら、柱6の下端を前記レベル
調整ボルト21に当接させる。この作業を全ての1階用
の住宅ユニット4について行い、レベル調整ボルト21
を回転操作してこれらの住宅ユニット4を所定の高さ位
置とする。この後、1階用住宅ユニット4相互を結合す
る作業、および1階用住宅ユニット4の上に2階用住宅
ユニット4をクレーンで積み上げる作業等を行い、また
、それぞれの住宅ユニット4の内部の仕上げ作業等を行
う。前記グラウト材19が凝固することにより、支柱部
材9.10.11と1階用住宅ユニット4とが結合され
る。
The construction work of building 3 will first begin with the construction of the housing unit 4 for the first floor.
The housing unit 4 is then gradually lowered, and the housing unit 4 is lifted up by a crane as shown in Figure 9.
While inserting the anchor member 47 projecting downward from the pillar 6 into the sheath pipe 20 filled with the grout material 19 of the pillar member 9, 10.11, the lower end of the pillar 6 is inserted into the level adjustment bolt 21. bring it into contact with. Perform this work for all first floor housing units 4, and then
is rotated to bring these housing units 4 to a predetermined height position. After this, work was carried out to connect the first-floor housing units 4 to each other, and to stack the second-floor housing units 4 on top of the first-floor housing units 4 using a crane. Perform finishing work, etc. By solidifying the grout material 19, the strut members 9, 10, 11 and the first floor housing unit 4 are connected.

以上の建物3の建築作業が終了した頃には前記コンクリ
ートスラリー46は凝固しており、前記基礎2が完成し
ている。基礎2の完成後、第11図の通り建設現場の根
切り作業で生じた土48を基礎2の住宅外側部分に被せ
る。
By the time the construction work of the building 3 is completed, the concrete slurry 46 has solidified and the foundation 2 has been completed. After the foundation 2 is completed, as shown in FIG. 11, the outer part of the foundation 2 is covered with soil 48 generated from the root cutting work at the construction site.

以上のように本実施例によれば、スラリー打設空間45
に打設されたコンクリートスラリー46が凝固する前に
基礎2より上の建物3の建築作業が開始され、建物3の
建築作業がコンクリートスラリー46の養生と同時進行
で行われるため、コンクリートスラリー46の養生期間
分だけ建設現場作業期間を短縮できる。これにより住宅
の建築コストの低減を図ることが可能となり、この効果
は、建設現場作業期間を短縮することを主要目的として
いるユニット住宅の場合に特に大きく発揮される。
As described above, according to this embodiment, the slurry pouring space 45
The construction work of the building 3 above the foundation 2 is started before the concrete slurry 46 cast in the concrete slurry 46 solidifies, and the construction work of the building 3 is carried out at the same time as the curing of the concrete slurry 46. The construction site work period can be shortened by the curing period. This makes it possible to reduce the construction cost of a house, and this effect is particularly significant in the case of unit houses whose main purpose is to shorten the construction site work period.

また、前記スラリー打設空間45に打設されたコンクリ
ートスラリー46が凝固すると、捨てコンクリート36
と連結部材12.13とがこのコンクリートによって連
結され、このコンクリートか基礎2のヘース部となるた
め、捨てコンクリート36の打設時に上面のレベル出し
作業を行う必要がなく、換言すると、捨てコンクリート
36の上面に凹凸が存在していてもよく、このため、捨
てコンクリート36についての作業性が良好となる。
Further, when the concrete slurry 46 cast in the slurry casting space 45 solidifies, the waste concrete 36
and the connecting members 12.13 are connected by this concrete, and this concrete becomes the base part of the foundation 2, so there is no need to level the top surface when pouring the sacrificial concrete 36. In other words, the sacrificial concrete 36 There may be irregularities on the upper surface of the concrete 36, which improves the workability of the concrete 36.

本発明はユニット住宅だけではなく、鉄骨軸組みを含め
た在来工法による住宅にも適用可能である。在来工法に
よる住宅に適用する場合には、支柱部材に上方へ突出す
るアンカ一部材を設け、このアンカ一部材を利用して鉄
製の柱のベースプレートや木製の土台を結合すればよい
The present invention is applicable not only to unit houses but also to houses built using conventional construction methods, including steel frames. When applied to a house using conventional construction methods, an upwardly protruding anchor member may be provided on the support member, and this anchor member may be used to connect the base plate of the iron column or the wooden foundation.

また、前記実施例ではコンクリートスラリー46の打設
作業終了後に基礎2より上の建物3の建築作業を始めた
が、この建物3の建築作業は、型枠3を配置してスラリ
ー打設空間45を形成した後であってコンクリートスラ
リー打設作業前に開始してもよく、また、支柱部材9,
10.11を連結部材12.13で連結した後であれば
、型枠43の配置作業前から開始してもよい。
Furthermore, in the embodiment described above, the construction work of the building 3 above the foundation 2 was started after the concrete slurry 46 casting work was completed, but the construction work of this building 3 was carried out by arranging the formwork 3 and filling the slurry casting space 45. It may be started after forming the concrete slurry and before the concrete slurry pouring work.
10.11 may be started before the formwork 43 is placed, as long as it is after the connecting members 12.13 are connected.

〔発明の効果〕〔Effect of the invention〕

本発明によれば、コンクリートスラリーが凝固する前に
、すなわち基礎が完成する前に基礎より上の建物の建築
作業を始めることができ、基礎施工作業中に建物の建築
作業を行なえるため、建設現場における住宅の施工期間
を短縮できるようになる。
According to the present invention, the construction work of the building above the foundation can be started before the concrete slurry solidifies, that is, before the foundation is completed, and the construction work of the building can be carried out during the foundation construction work. It will be possible to shorten the construction period for housing on site.

また、捨てコンクリートのレベル出し作業が不要になる
ため、捨てコンクリートについての作業性が良好になる
Further, since the work of leveling the waste concrete is not required, the workability of the waste concrete becomes better.

【図面の簡単な説明】[Brief explanation of drawings]

第1図はコンクリートスラリー打設前の基礎を示す住宅
の全体概略図、第2図、第3図、第4図は第1図で示し
た第1、第2、第3の支柱部材を示す斜視図、第5図、
第6図は第1図で示した第1、第2の連結部材を示す斜
視図、第7図は基礎の要部拡大平面図、第8図は同拡大
斜視図、第9図、第10図は第1図のIX−IX線、x
−X線断面図、第11図はコンクリートスラリー打設後
の状態を示す第10図と同様の図、第12図は基礎より
上の建物を構成する住宅ユニットの骨組みの斜視図、第
13図は第12図の住宅ユニットを組み合わせて建てら
れる建物の概略全体図である。
Figure 1 is an overall schematic diagram of the house showing the foundation before pouring concrete slurry, and Figures 2, 3, and 4 show the first, second, and third support members shown in Figure 1. Perspective view, Figure 5,
Fig. 6 is a perspective view showing the first and second connecting members shown in Fig. 1, Fig. 7 is an enlarged plan view of the main part of the foundation, Fig. 8 is an enlarged perspective view of the same, Figs. The figure is the IX-IX line in Figure 1, x
- An X-ray sectional view, Figure 11 is a view similar to Figure 10 showing the state after concrete slurry pouring, Figure 12 is a perspective view of the frame of the housing unit that constitutes the building above the foundation, Figure 13 is a schematic overall view of a building constructed by combining the housing units shown in FIG. 12.

Claims (1)

【特許請求の範囲】[Claims] (1)基礎より上に建てられる建物の柱の位置と対応す
る建設現場の位置に支柱部材を立て、これらの支柱部材
をプレキャストコンクリート製の連結部材で連結すると
ともに、前記支柱部材およびこの連結部材の下部両側に
型枠を配置し、この型枠内にコンクリートスラリーを打
設し、前記支柱部材および前記連結部材の上で前記建物
を建てる建築作業を前記コンクリートスラリーの養生と
同時進行させて行うことを特徴とする住宅の基礎施工方
法。
(1) Erect strut members at positions on the construction site that correspond to the positions of the pillars of the building to be built above the foundation, connect these strut members with precast concrete connecting members, and connect the aforementioned strut members and this connecting member. A formwork is placed on both sides of the lower part of the building, a concrete slurry is poured into the formwork, and the construction work of constructing the building on the support member and the connecting member is performed simultaneously with the curing of the concrete slurry. A housing foundation construction method characterized by:
JP12056490A 1990-05-09 1990-05-09 Residence base construction method Pending JPH0416630A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP12056490A JPH0416630A (en) 1990-05-09 1990-05-09 Residence base construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP12056490A JPH0416630A (en) 1990-05-09 1990-05-09 Residence base construction method

Publications (1)

Publication Number Publication Date
JPH0416630A true JPH0416630A (en) 1992-01-21

Family

ID=14789431

Family Applications (1)

Application Number Title Priority Date Filing Date
JP12056490A Pending JPH0416630A (en) 1990-05-09 1990-05-09 Residence base construction method

Country Status (1)

Country Link
JP (1) JPH0416630A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306874A (en) * 1993-04-27 1994-11-01 Shiyua Seisakusho:Kk Concrete block for footing

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS529047A (en) * 1975-07-04 1977-01-24 Ciba Geigy Ag Method of dyeing thermoplastic resins
JPS55152223A (en) * 1977-11-06 1980-11-27 Mitsuko Mitsuo Foundation

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS529047A (en) * 1975-07-04 1977-01-24 Ciba Geigy Ag Method of dyeing thermoplastic resins
JPS55152223A (en) * 1977-11-06 1980-11-27 Mitsuko Mitsuo Foundation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06306874A (en) * 1993-04-27 1994-11-01 Shiyua Seisakusho:Kk Concrete block for footing

Similar Documents

Publication Publication Date Title
JPH09209451A (en) Joint construction of up and down columns with beam and joint method
JPH02164931A (en) Foundation construction method for building
JPH0416630A (en) Residence base construction method
JPH02164930A (en) Foundation structure for building
JP2884440B2 (en) Formwork for construction of concrete prism and construction method of column using it
JPH02164934A (en) Foundation construction method
JPH09296565A (en) Precast concrete column, its manufacture, and execution method
JPS6157732A (en) Construction of multilayered building skeletal by precast reinforced concrete unit
JPS6195136A (en) Construction of multistoried building skeletal by precast reinforced concrete unit
JP2759361B2 (en) Pillar support members for building reinforced concrete buildings
JP2000160687A (en) Construction method for composite structure and precast concrete column
JPH0366878A (en) Construction method for precast column and beam and precast anti-seismic wall
JP2759360B2 (en) Construction method of reinforced concrete building
JP2554382B2 (en) Dwelling
JPS6043547A (en) Mold frame and reinforcement iron integral assembling and constructing method
JPH0447737B2 (en)
JP2811211B2 (en) Flat slab construction method
JPH08193373A (en) Non-bearing wall construction pedestal and construction method of non-bearing wall using the pedestal
JPS62182329A (en) Construction of concrete structure
JPH04155015A (en) Execution method for foundation of house
JPH07103621B2 (en) Construction method for steel reinforced concrete structures
JP2780055B2 (en) Construction method of reinforced concrete building
JP2984626B2 (en) PC pillar construction method and its PC pillar
JPH09256631A (en) Construction method of building reinforced concrete wall
JPH0470458B2 (en)