JPH0762875A - Construction method of floor - Google Patents

Construction method of floor

Info

Publication number
JPH0762875A
JPH0762875A JP21677693A JP21677693A JPH0762875A JP H0762875 A JPH0762875 A JP H0762875A JP 21677693 A JP21677693 A JP 21677693A JP 21677693 A JP21677693 A JP 21677693A JP H0762875 A JPH0762875 A JP H0762875A
Authority
JP
Japan
Prior art keywords
floor
steel frame
girder steel
floor slab
slab unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP21677693A
Other languages
Japanese (ja)
Inventor
Katsuo Takeda
勝男 武田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shimizu Construction Co Ltd
Shimizu Corp
Original Assignee
Shimizu Construction Co Ltd
Shimizu Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shimizu Construction Co Ltd, Shimizu Corp filed Critical Shimizu Construction Co Ltd
Priority to JP21677693A priority Critical patent/JPH0762875A/en
Publication of JPH0762875A publication Critical patent/JPH0762875A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To increase safety of working and reduce the construction period. CONSTITUTION:A plurality of reinforcement units 3 installed between small beams are laid down on a temporarily assembled base 11 and connected one after another on a plane and small beam steel skeletons 2 are fixed to complete a floor slab unit 10 placed between large beams. The completed floor slab unit 10 is suspended on the floor of a building assembled with large beam steel skeletons 1. After this second process has been completed, the small beam steel skeletons 2 and the large beam steel skeletons 1 and also the floor slab unit 10 and the large beam steel skeletons 1 are connected respectively.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、床の施工方法に係り、
特に、鉄骨鉄筋コンクリート造または鉄骨造の建築物の
床の施工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a floor construction method,
In particular, it relates to a method of constructing a floor of a steel frame reinforced concrete structure or a steel frame structure.

【0002】[0002]

【従来の技術】鉄骨鉄筋コンクリート造や鉄骨造の建築
物の床の施工方法としては、ファブデッキ(伊藤忠商事
販売)を用いたものがある。以下、ファブデッキを用い
た従来の床の施工方法を図2を参照して説明する。図2
に示すように、ファブデッキを用いた床の施工方法は、
まず、施工すべき建築物を大梁鉄骨1および小梁鉄骨2
まで建て方をした後、これら小梁鉄骨2の上に工場等で
予め完成した鉄筋ユニット3を吊り込んで架設して床の
施工位置に敷き込む。そして、この敷き込みの完了した
鉄筋ユニット3を、作業者が現場で大梁鉄骨1や小梁鉄
骨2や隣接する他の鉄筋ユニット3と接続する。鉄筋ユ
ニット3は、下面に図示しない型枠が固定されてなり、
建て方された小梁鉄骨2の間に吊り込まれた後、コンク
リートを現場打ちすることにより、全体を一体化して建
築物の床を形成するようになっている。
2. Description of the Related Art As a method of constructing a floor of a steel frame reinforced concrete structure or a steel frame structure, there is a method using a fab deck (sold by ITOCHU Corporation). Hereinafter, a conventional floor construction method using a fab deck will be described with reference to FIG. Figure 2
As shown in, the floor construction method using the fab deck is
First, the building to be constructed is a girder steel frame 1 and a girder steel frame 2
After erection, the rebar unit 3 completed in advance at a factory is hung on the beam girder steel frame 2 and erected and laid at the floor construction position. Then, the worker connects the reinforcing bar unit 3 having been laid down with the large beam steel frame 1, the small beam steel frame 2 and another adjacent reinforcing bar unit 3 on site. The rebar unit 3 has a formwork (not shown) fixed to the lower surface,
After being suspended between the beamed steel frames 2 that have been built, the concrete is cast in situ to integrally form the whole and form the floor of the building.

【0003】[0003]

【発明が解決しようとする課題】しかしながら、前記の
ような床の施工方法の場合、以下のような問題が生じて
いた。すなわち、床の施工位置に敷き込んだ鉄筋ユニッ
ト3の大梁鉄骨1や小梁鉄骨との接続および鉄筋ユニッ
ト3同志の接続作業は、建て方において高所作業が多く
なるため作業者に落下の危険がある。また、鉄筋ユニッ
ト3の吊り込み時には、作業者が手を挟まれる等の危険
性もあるため、作業に細心の注意を払う必要があり、作
業能率の低下および工期の延長の原因となっていた。
However, in the case of the above floor construction method, the following problems have occurred. In other words, the connection work of the reinforcing bar unit 3 laid at the construction position of the floor with the girder steel frame 1 and the girder steel frame and the connecting work of the reinforcing bar unit 3 require a lot of work at a high place in the way of building, and therefore there is a risk of falling to the worker. There is. In addition, when the reinforcing bar unit 3 is suspended, there is a risk that an operator may get his or her hand caught, so that it is necessary to pay close attention to the work, which causes a reduction in work efficiency and an extension of the construction period. .

【0004】本発明は、前述の課題に鑑みてなされたも
ので、作業の安全性が向上し、かつ工期も短縮すること
ができる床の施工方法を提供することを目的とするもの
である。
The present invention has been made in view of the above problems, and an object of the present invention is to provide a floor construction method capable of improving work safety and shortening the construction period.

【0005】[0005]

【課題を解決するための手段】本発明では、鉄筋骨組み
の下に型枠を固定してなり、小梁間に架設される鉄筋ユ
ニットを、複数仮組み架台上に敷き込んで互いに面方向
に接続し、かつ小梁鉄骨を固定することにより、大梁間
に架設される床版ユニットを完成する第1の工程と、完
成した床版ユニットを、大梁鉄骨を組んでなる建築物の
床の位置に吊り込む第2の工程と、第2の工程の完了
後、小梁鉄骨と大梁鉄骨、床版ユニットと大梁鉄骨とを
それぞれ接続する第3の工程とを有することを特徴とす
る床の施工方法を前記課題の解決手段とした。
According to the present invention, a rebar unit having a formwork fixed under a rebar frame and laid between beam beams is laid on a plurality of temporary assembly frames and connected to each other in a plane direction. Then, the first step of completing the floor slab unit installed between the girders by fixing the girder steel frame, and the completed floor slab unit to the position of the floor of the building constructed with the girder steel frame. A method for constructing a floor, comprising a second step of suspending and a third step of connecting the girder steel frame and the girder steel frame, and the floor slab unit and the girder steel frame, respectively, after the completion of the second step. Was used as a means for solving the above problems.

【0006】[0006]

【作用】本発明の床の施工方法によれば、地組みした床
版ユニットを大梁鉄骨間に架設することにより、吊り込
み作業の回数を減少する。また、鉄筋ユニット同志の接
続は、地組みで床版ユニットを完成することにより、建
て方での作業を大幅に減少する。
According to the floor construction method of the present invention, the number of lifting operations is reduced by erection of the floor slab unit assembled in the ground between the girder steel frames. In addition, the connection of rebar units will greatly reduce the work involved in building by completing the floor slab unit with the ground structure.

【0007】[0007]

【実施例】以下本発明の一実施例を、図1を参照して説
明する。図中符号10は、本発明の床の施工方法で施工
された鉄骨鉄筋コンクリート造の建築物の床を構成する
床版ユニットである。図1に示すように、床版ユニット
10は、前述の図2に示した鉄筋ユニット3を同一平面
上に接続することにより、隣接する4本の大梁鉄骨1で
囲まれた部分に設置可能な長方形版状に形成されてい
る。床版ユニット10の下面には、小梁鉄骨2が固定さ
れている。そして、床版ユニット10は、建て方の完了
した大梁鉄骨1の間に設置して、大梁鉄骨1と小梁鉄骨
2とをボルト締めで固定するとともに、現場打ちコンク
リートを打設することにより建築物の床を形成するよう
になっている。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENT An embodiment of the present invention will be described below with reference to FIG. Reference numeral 10 in the figure denotes a floor slab unit that constitutes a floor of a steel frame reinforced concrete building constructed by the floor construction method of the present invention. As shown in FIG. 1, the floor slab unit 10 can be installed in a portion surrounded by four adjacent girder steel frames 1 by connecting the reinforcing bar units 3 shown in FIG. 2 on the same plane. It is formed in a rectangular plate shape. The girder steel frame 2 is fixed to the lower surface of the floor slab unit 10. Then, the floor slab unit 10 is installed between the girder steel frames 1 that have been built, the girder steel frame 1 and the girder steel frame 2 are fixed by bolts, and in-situ concrete is poured to build the building. It is designed to form a floor for things.

【0008】以下、本発明の床の施工方法を説明する。
本発明の床の施工方法は、まず、施工すべき建築物に近
接した地盤上に架台を組み上げ、この架台を利用して床
版ユニット10を施工する。(第1の工程)床版ユニッ
ト10の施工は、完成した架台上に小梁鉄骨2,2,…
を所定位置で設置し、さらに、これら小梁鉄骨2,2,
…の上に鉄筋ユニット3,3,…を敷き込んで、小梁鉄
骨2と鉄筋ユニット3とを互いに溶接止めする。鉄筋ユ
ニット3の小梁鉄骨2への固定が完了したら、鉄筋ユニ
ット3同志の鉄筋をジョイントするとともに、スタッド
ジベルを小梁鉄骨2に打設し、鉄筋ユニット3上面上に
突出した状態とする。
The floor construction method of the present invention will be described below.
In the floor construction method of the present invention, first, a pedestal is assembled on the ground close to a building to be constructed, and the floor slab unit 10 is constructed using this pedestal. (First step) The construction of the floor slab unit 10 is carried out by mounting the beam girders 2, 2, ...
Is installed at a predetermined position, and these beam girder steel frames 2, 2,
.. are laid on top of each other, and the beam girder frame 2 and the reinforcing bar unit 3 are welded to each other. When the fixing of the reinforcing bar unit 3 to the beam girder steel frame 2 is completed, the reinforcing bars of the reinforcing bar unit 3 are jointed together, and the stud dowel is driven into the beam girder steel frame 2 so as to project onto the upper surface of the reinforcing bar unit 3.

【0009】床版ユニット10が完成したら、図2に示
すように、この床版ユニット10を大梁鉄骨1,1,…
を組んでなる建築物の床の位置に吊り込む(第2の工
程)。この際、床版ユニット10は、小梁鉄骨2が施工
すべき建築物の建て方の位置に収まるように位置決めす
る。
When the floor slab unit 10 is completed, the floor slab unit 10, as shown in FIG.
It is hung at the floor position of the building that is assembled (second step). At this time, the floor slab unit 10 is positioned so that the girder steel frame 2 fits within the position of the building to be constructed.

【0010】床版ユニット10の吊り込みが完了した
ら、小梁鉄骨2と大梁鉄骨1とをハイテンションボルト
で締結し、床版ユニット10と大梁鉄骨1とを溶接し、
大梁鉄骨1の周囲に配設される梁鉄筋と床版ユニット1
0の鉄筋とをジョイントする(第3の工程)。この際、
小梁鉄骨2と大梁鉄骨1との締結作業は、床版ユニット
10の下面から行なうことにより、十分な作業空間が確
保される。床版ユニット10の大梁鉄骨1との一体化が
完了したら、後の工程で現場打ちコンクリートを打設す
ることにより建築物の床が完成される。
When the suspension of the floor slab unit 10 is completed, the small beam steel frame 2 and the large beam steel frame 1 are fastened with high tension bolts, the floor slab unit 10 and the large beam steel frame 1 are welded,
Beam reinforcement and floor slab unit 1 arranged around the large beam steel frame 1
Joint with 0 reinforcing bars (third step). On this occasion,
The fastening work between the small beam steel frame 2 and the large beam steel frame 1 is performed from the lower surface of the floor slab unit 10 to ensure a sufficient working space. When the integration of the floor slab unit 10 with the girder steel frame 1 is completed, the floor of the building is completed by pouring cast-in-place concrete in a later step.

【0011】以下、本実施例の作用および効果を説明す
る。前記した床の施工方法によれば、地組みした床版ユ
ニット10を大梁鉄骨1,1,…間に架設することによ
り、吊り込み作業の回数を減少して、作業能率が大幅に
向上し工期が短縮する。また、鉄筋ユニット3,3,…
同志の接続作業は、殆ど地上となるので、建て方での作
業を大幅に減少して、作業者の落下事故等の懸念が無く
なり、安全性が向上する。
The operation and effect of this embodiment will be described below. According to the floor construction method described above, the ground floor slab unit 10 is erected between the large beam steel frames 1, 1, ..., By reducing the number of lifting operations, the work efficiency is significantly improved, and the construction period is improved. Is shortened. In addition, the rebar units 3, 3, ...
Since the connection work of the comrades is almost on the ground, the work in the way of building is greatly reduced, there is no concern about the worker's fall accident, and the safety is improved.

【0012】[0012]

【発明の効果】以上説明したように、本発明の床の施工
方法によれば、鉄筋骨組みの下に型枠を固定してなり、
小梁間に架設される鉄筋ユニットを、複数仮組み架台上
に敷き込んで互いに面方向に接続し、かつ小梁鉄骨を固
定することにより、大梁間に架設される床版ユニットを
完成する第1の工程と、完成した床版ユニットを、大梁
鉄骨を組んでなる建築物の床の位置に吊り込む第2の工
程と、第2の工程の完了後、小梁鉄骨と大梁鉄骨、床版
ユニットと大梁鉄骨とをそれぞれ接続する第3の工程と
を有することを特徴とするから、地組みした床版ユニッ
トを大梁鉄骨間に架設することにより、吊り込み作業の
回数を減少して、作業能率が大幅に向上し、工期が短縮
する上、鉄筋ユニット同志の接続作業が、殆ど地上とな
るので、建て方での作業を大幅に減少して、作業者の落
下事故等の懸念が無くなり、安全性が向上するといった
優れた効果を奏する。
As described above, according to the floor construction method of the present invention, the formwork is fixed under the reinforcing bar frame,
A slab unit to be erected between girders is completed by laying a plurality of rebar units erected between girders on a temporary mounting frame, connecting them in the plane direction, and fixing girder steel frames. Step, and the completed floor slab unit is hung at the floor position of the building made up of girder steel frames, and after the completion of the second step, girder steel frame and girder steel frame, floor slab unit Since it has a third step of connecting the girder steel frame and the girder steel frame, respectively, by installing the floor slab unit assembled in the ground between the girder steel frames, the number of hanging operations can be reduced and the work efficiency can be improved. Is significantly improved, the construction period is shortened, and the work of connecting the reinforcing bar units is almost on the ground, so the work of building is greatly reduced, and there is no concern about worker accidents such as falling accidents. Excellent effect such as improved .

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明の床の施工方法で施工されたを示す平面
図である。
FIG. 1 is a plan view showing a construction performed by the floor construction method of the present invention.

【図2】従来例を示す平面図である。FIG. 2 is a plan view showing a conventional example.

【符号の説明】[Explanation of symbols]

1 大梁鉄骨 2 小梁鉄骨 3 鉄筋ユニット 10 床版ユニット 1 Large beam steel frame 2 Small beam steel frame 3 Reinforcing bar unit 10 Floor slab unit

Claims (1)

【特許請求の範囲】[Claims] 【請求項1】 鉄骨鉄筋コンクリート造または鉄骨造の
建築物の床の施工方法であって、鉄筋骨組みの下に型枠
を固定してなり、小梁間に架設される鉄筋ユニットを、
複数仮組み架台上に敷き込んで互いに面方向に接続し、
かつ小梁鉄骨を固定することにより、大梁間に架設され
る床版ユニットを完成する第1の工程と、 完成した床版ユニットを、大梁鉄骨を組んでなる建築物
の床の位置に吊り込む第2の工程と、 第2の工程の完了後、小梁鉄骨と大梁鉄骨、床版ユニッ
トと大梁鉄骨とをそれぞれ接続する第3の工程とを有す
ることを特徴とする床の施工方法。
1. A method for constructing a floor of a steel-framed reinforced concrete structure or a steel-framed structure, wherein a formwork is fixed under a reinforced frame, and a reinforced frame unit is erected between the beams.
Lay on multiple temporary mounting bases and connect to each other in the plane direction,
In addition, the first step of completing the floor slab unit installed between the girders by fixing the girder steel frame, and suspending the completed floor slab unit at the floor position of the building constructed with the girder steel frame. A method for constructing a floor, comprising: a second step; and, after completion of the second step, a third step of connecting the girder steel frame and the girder steel frame, and the floor slab unit and the girder steel frame, respectively.
JP21677693A 1993-08-31 1993-08-31 Construction method of floor Pending JPH0762875A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21677693A JPH0762875A (en) 1993-08-31 1993-08-31 Construction method of floor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21677693A JPH0762875A (en) 1993-08-31 1993-08-31 Construction method of floor

Publications (1)

Publication Number Publication Date
JPH0762875A true JPH0762875A (en) 1995-03-07

Family

ID=16693721

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21677693A Pending JPH0762875A (en) 1993-08-31 1993-08-31 Construction method of floor

Country Status (1)

Country Link
JP (1) JPH0762875A (en)

Similar Documents

Publication Publication Date Title
JPH05287901A (en) Construction of stairs
JPH0762875A (en) Construction method of floor
JPH0657710A (en) Construction of concrete main tower
JP3187618B2 (en) How to assemble beam reinforcement
JP2002256643A (en) Construction method for steel-framed reinforced concrete(src) structure
JP2817591B2 (en) Construction method of steel reinforced concrete building
JPH0517996A (en) Building constructing method
JP2001200594A (en) Method for constructing structure consisting of column with large section and beam
JP2972955B2 (en) Column and beam joining method and its structure
JPH08253909A (en) Ferroconcrete floor slab for bridge and form therefor
JPH0642184A (en) Construction of skeleton using half precast floor board
JP2702778B2 (en) How to build a steel staircase
JPH02157360A (en) Body constructing method of steel framed reinforced concrete multistoried building
JP2001032376A (en) Floor slab frame and construction method for skeleton
JPH0881918A (en) Pipe and construction method thereof
JPH0522787B2 (en)
JPH1113141A (en) Constructing method of composite structure
JPH0432901B2 (en)
JP2907047B2 (en) How to build a composite frame
JPH04272344A (en) Reinforcement pre-framing construction
JPH0266237A (en) Construction method and structure of framework bridge
JPH0518114A (en) Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building
JPH04140366A (en) Preceding erection method of prefabricated column bar and semi-pc girder in pc construction
JPH0723625B2 (en) Construction method of concrete structure
JPH0571747B2 (en)

Legal Events

Date Code Title Description
A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20001128