JPH0518114A - Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building - Google Patents

Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building

Info

Publication number
JPH0518114A
JPH0518114A JP3197499A JP19749991A JPH0518114A JP H0518114 A JPH0518114 A JP H0518114A JP 3197499 A JP3197499 A JP 3197499A JP 19749991 A JP19749991 A JP 19749991A JP H0518114 A JPH0518114 A JP H0518114A
Authority
JP
Japan
Prior art keywords
pillar
steel frame
construction method
steels
reinforcing bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP3197499A
Other languages
Japanese (ja)
Inventor
Taketo Watabiki
健人 綿引
Kaoru Sasaki
馨 佐々木
Yasushi Hirai
裕史 平井
Tairyo Omae
泰亮 大前
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Haseko Corp
Original Assignee
Haseko Corp
Hasegawa Komuten Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haseko Corp, Hasegawa Komuten Co Ltd filed Critical Haseko Corp
Priority to JP3197499A priority Critical patent/JPH0518114A/en
Publication of JPH0518114A publication Critical patent/JPH0518114A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

PURPOSE:To reduce the number of joint positions of a beam main reinforcement, improve construction efficiency, and dispense with a wide stockyard. CONSTITUTION:Beam main reinforcements 3 are arranged in the protruded state by the length of about 1/2 of a span from the sides of pillar steels 1. After the pillar steels 1 are erected, beam steels are hoisted and suspended between pillar steels, and end sections of the beam main reinforcements 3 butted to each other are connected between the pillar steels 1.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は、鉄骨鉄筋コンクリー
ト構造(以下「SRC構造」という。)の建物の構築に
用いられる先組鉄筋工法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a pre-assembled rebar construction method used for constructing a building having a steel-framed reinforced concrete structure (hereinafter referred to as "SRC structure").

【0002】[0002]

【従来の技術】従来より、SRC構造建物の構築に用い
られる先組鉄筋工法として、梁鉄骨に梁主筋を先組し、
柱鉄骨の建て方時に柱鉄骨間に梁主筋を先組した梁鉄骨
を吊り込み、梁鉄骨の両端を柱鉄骨に接合し、梁主筋の
両端部をスリーブ等により柱鉄骨側の鉄筋と接合するこ
とが行われている。
2. Description of the Related Art Conventionally, as a pre-assembled reinforcing bar construction method used for constructing an SRC structure building, a beam main bar is pre-assembled with a beam main bar,
When constructing a pillar steel frame, suspend a beam steel frame with a beam main bar previously assembled between the column steel frames, connect both ends of the beam steel frame to the column steel frame, and connect both ends of the beam main bar to the steel bars on the column steel frame side with a sleeve etc. Is being done.

【0003】[0003]

【発明が解決しようとする課題】従来例によると、梁主
筋のジョイント部分が多くなるために、それだけ鉄筋の
接合作業が増えて、建物の施工に手間と時間とを要して
いた。また梁主筋を先組した梁鉄骨は、梁鉄骨同志をそ
のまま重ねてストックヤードに置くことができないの
で、広いストックヤードを必要としていた。
According to the conventional example, since the number of joints of the beam main bars is increased, the work of joining the reinforcing bars is increased, and the construction of the building requires labor and time. In addition, the beam steel frame with the beam main bar pre-assembled requires a large stockyard because the beam steel frames cannot be stacked as they are in the stockyard.

【0004】この発明の目的は、梁主筋のジョイント個
所を少なくして、施工の能率化を図ることである。この
発明の他の目的は従来に比較して広いストックヤードを
必要としないようにすることである。
An object of the present invention is to reduce the number of joints of the main beam bars to improve the efficiency of construction. Another object of the present invention is to eliminate the need for a large stockyard as compared with the prior art.

【0005】[0005]

【課題を解決するための手段】この発明の先組鉄筋工法
は、予め、梁主筋を柱鉄骨の側方からスパンのほぼ1/
2の長さに突出された状態で柱鉄骨に配筋しておき、柱
鉄骨を建て方した後、梁鉄骨を柱鉄骨間に吊り込んで、
柱鉄骨間に架設し、柱鉄骨間で互いに突き合う上記梁主
筋端部同志を接続するものである。
In the pre-assembled reinforcing bar construction method of the present invention, the beam main bar is preliminarily set to approximately 1 / span of the span from the side of the column steel frame.
After reinforcing the pillar steel frame in a state of protruding to the length of 2, and after constructing the pillar steel frame, suspend the beam steel frame between the pillar steel frames,
It is installed between pillar steel frames, and connects the above-mentioned beam main bar end portions which are mutually opposed between the pillar steel frames.

【0006】[0006]

【作用】現場において、柱鉄骨間での梁主筋の接合個所
は、梁の中間部分のみですむ。
[Operation] At the site, the main reinforcement of the beam between the steel columns is only connected to the middle part of the beam.

【0007】[0007]

【実施例】以下この発明の一実施例を建物の構築方法と
共に説明する。まず、図1に示すように複数層(図示の
例では3層)の階高を有する柱鉄骨1,…を所定間隔を
置いて建て方する。建て方する前に、各柱鉄骨1には梁
鉄骨2を取付ける位置に梁接合用ブラケット2aを接合
しておくと共に、梁接合用ブラケットに沿って梁主筋3
を配筋しておき、柱主筋4,4aも配筋しておく。この
場合、柱の帯筋4aを先組しておくとよい。尚、図1及
び図2では、柱の帯筋や梁のスターラップの図示の一部
を省略している。梁主筋3は、図1の両端に位置してい
る柱鉄骨1にはL形状のものが、中間に位置している柱
鉄骨には直線状のものがそれぞれ先組みされている。そ
して柱鉄骨1から突出している梁主筋3の長さは、梁の
長さ(スパン)のほぼ1/2として、図1左右両側で隣
り合っている梁主筋同士では先端がわずかな間隙を置い
て突き合うように設定しておく。
DESCRIPTION OF THE PREFERRED EMBODIMENTS An embodiment of the present invention will be described below together with a building construction method. First, as shown in FIG. 1, pillar steel frames 1, ... Having a plurality of floors (three floors in the example shown in the figure) are built at predetermined intervals. Before building, the beam joint bracket 2a is joined to each pillar steel frame 1 at a position where the beam steel frame 2 is attached, and the beam main bars 3 are attached along the beam joint bracket.
Are laid out, and the column main bars 4, 4a are also laid out. In this case, it is preferable to first assemble the column stirrups 4a. 1 and 2, a part of the stirrup of the pillar and the stirrup of the beam is omitted. The beam main bars 3 are preassembled into the L-shaped pillar steel frames 1 located at both ends in FIG. 1 and the linear pillars in the middle pillar steel frames 1, respectively. The length of the main beam 3 of the beam protruding from the pillar steel frame 1 is set to be approximately half the length (span) of the beam. And set them to face each other.

【0008】つぎに、各層の梁接合用ブラケット2a,
2a間にクレーンによって梁鉄骨1を順次吊り込み、各
ブラケットと梁鉄骨の両端とをボルトとボルト孔を利用
して仮止めし、必要な個所のボルト孔についてはノック
ピンを挿入して固定する(図1の4工区)。
Next, the beam joining brackets 2a of the respective layers,
The beam steel frame 1 is sequentially hung between the 2a by a crane, and each bracket and both ends of the beam steel frame are temporarily fixed using bolts and bolt holes, and knock pins are inserted and fixed for bolt holes at necessary places ( 4 sections in Figure 1).

【0009】その後、図1の建物の最下層のみの柱・梁
の本締めを足場6を使って行う(3工区)。そして突き
合っている梁主筋3,3の先端部間を接続すると共にス
ターラップ3aを配筋して、梁配筋を終えてから(2工
区)、柱及び梁の型枠を組立て、スラブ筋5を配筋し
(1工区)、その後、柱・梁及びスラブのコンクリート
を打設して、図2に示すように柱7、梁8及びスラブ9
を完成させて、まず最下層(1層の)のみの施工を終了
する。
After that, the columns and beams of only the bottom layer of the building shown in FIG. 1 are fully tightened using the scaffold 6 (3 construction sections). Then, after connecting the ends of the beam main bars 3 and 3 facing each other and arranging the stirrup 3a and finishing the beam barring (2 works section), the pillar and beam formwork is assembled, and the slab bar 5 is arranged (1 construction section), and then concrete of columns / beams and slabs is placed, and as shown in FIG. 2, columns 7, beams 8 and slabs 9 are placed.
Is completed, and the construction of only the bottom layer (one layer) is completed.

【0010】その後、2層の本締めを行って上記の工程
に従って施工し、順次既設の層を利用して直上層の本締
めを行い、以下同様に上層に向って一層毎に本締めとコ
ンクリートの打設を行う。
After that, two layers of final fastening are carried out and construction is carried out according to the above-mentioned steps, and the existing layers are sequentially used to perform the final fastening of the immediately upper layer. To place.

【0011】建物の規模が大きい場合には、少ない作業
者で効率的に作業ができるようにするために、例えば図
1に示すように同一層において、本締めをする工区、柱
梁配筋をする工区、型枠の工区、スラブ配筋の工区にそ
れぞれ分けるようにしてもよい。
When a building is large in scale, in order to enable efficient work by a small number of workers, for example, as shown in FIG. It may be divided into a construction section for construction, a construction section for formwork, and a construction section for slab reinforcement.

【0012】梁接合用ブラケット2aは、この発明に必
要不可欠なものではない。
The beam joining bracket 2a is not essential to the present invention.

【0013】[0013]

【発明の効果】この発明によれば、梁主筋のジョイント
個所を少なくできるから、梁主筋の接合作業の手間を減
らすことでき、施工の能率化を図ることができる。梁鉄
骨は梁主筋を先組みしていないので、梁鉄骨を積層でき
る分だけ従来に比較して広いストックヤードを必要とし
ない。
According to the present invention, since the number of joints of the main beam of the beam can be reduced, it is possible to reduce the time and effort required for joining the main beam of the beam, and to improve the efficiency of construction. Since the beam steel is not assembled with the beam main bar first, it does not require a large stockyard as compared with the conventional one because the beam steel can be stacked.

【図面の簡単な説明】[Brief description of drawings]

【図1】一部を除いて梁主筋を先組した柱鉄骨に梁鉄骨
を架設した状態を示す正面図である。
FIG. 1 is a front view showing a state in which a beam steel frame is erected on a column steel frame in which beam main bars are assembled in advance except for a part thereof.

【図2】一部を除いて1階部分については施工を終了し
た状態を示す正面図である。
FIG. 2 is a front view showing a state in which construction has been completed for the first floor portion except a part.

【図3】柱鉄骨に梁鉄骨を架設した状態を示す一部の拡
大平面図である。
FIG. 3 is a partial enlarged plan view showing a state in which a beam steel frame is installed on a column steel frame.

【符号の説明】[Explanation of symbols]

1 柱鉄骨 2 梁鉄骨 3 梁主筋 4 柱主筋 1 Column steel frame 2 Beam steel frame 3 Beam main bar 4 Column main bar

Claims (1)

【特許請求の範囲】 【請求項1】 予め、梁主筋を柱鉄骨の側方からスパン
のほぼ1/2の長さに突出された状態で配筋しておき、
柱鉄骨を建て方した後、梁鉄骨を柱鉄骨間に吊り込ん
で、柱鉄骨間に架設し、柱鉄骨間で互いに突き合う梁主
筋端部同志を接続すること特徴とする鉄骨鉄筋コンクリ
ート構造建物の先組鉄筋工法。
Claims: 1. The main reinforcement of the beam is arranged in advance in such a manner that the main reinforcement of the beam is projected from the side of the column steel frame to a length of approximately 1/2 of the span,
After constructing the column steel frame, suspend the beam steel frame between the column steel frames, erection between the column steel frames, and connect the beam main bar end parts that abut each other between the column steel frames to each other. Pre-assembled rebar construction method.
JP3197499A 1991-07-12 1991-07-12 Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building Pending JPH0518114A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP3197499A JPH0518114A (en) 1991-07-12 1991-07-12 Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP3197499A JPH0518114A (en) 1991-07-12 1991-07-12 Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building

Publications (1)

Publication Number Publication Date
JPH0518114A true JPH0518114A (en) 1993-01-26

Family

ID=16375492

Family Applications (1)

Application Number Title Priority Date Filing Date
JP3197499A Pending JPH0518114A (en) 1991-07-12 1991-07-12 Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building

Country Status (1)

Country Link
JP (1) JPH0518114A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017503942A (en) * 2014-01-24 2017-02-02 ▲謝▼英俊 Three-dimensional lightweight steel frame formed by bidirectional continuous double beams

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017503942A (en) * 2014-01-24 2017-02-02 ▲謝▼英俊 Three-dimensional lightweight steel frame formed by bidirectional continuous double beams

Similar Documents

Publication Publication Date Title
JPH0517996A (en) Building constructing method
JPH0518114A (en) Prefabricated reinforcing bar construction method for steel framed reinforced concrete structure building
JP2797023B2 (en) Construction method of beam
JPH02252830A (en) Pre-fabricated cruciform beam construction method
JPH02236325A (en) Construction method for super-highrise building
JP3187618B2 (en) How to assemble beam reinforcement
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JP2614000B2 (en) Basics of steel frame
JP2651506B2 (en) How to apply underground beams
JPH02236328A (en) Construction method for super-highrice building
JPH05231002A (en) Reinforcing steel preassembled body with form and reinforcing steel preassembly construction method with form
JP2629496B2 (en) Construction method of structure
JP2723011B2 (en) Construction method of steel frame reinforced concrete structure
JPH0672500B2 (en) Steel frame reinforced concrete high-rise building frame construction method
JPH0213694B2 (en)
JPH0460183B2 (en)
JPH04309630A (en) Skeleton construction method using pc member
JPS61269947A (en) Construction method for reinforcing bar structure
JP2001020383A (en) Composite structure of building using sc construction beam
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure
JPH0480169B2 (en)
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JPH04140366A (en) Preceding erection method of prefabricated column bar and semi-pc girder in pc construction
JPH02167939A (en) Construction work of precast steel framed, reinforced concrete structure
JPH07166603A (en) Construction method for end part rc-made steel frame beam

Legal Events

Date Code Title Description
A621 Written request for application examination

Effective date: 20051104

Free format text: JAPANESE INTERMEDIATE CODE: A621

A131 Notification of reasons for refusal

Effective date: 20080415

Free format text: JAPANESE INTERMEDIATE CODE: A131

A521 Written amendment

Effective date: 20080616

Free format text: JAPANESE INTERMEDIATE CODE: A523

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20080909

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Effective date: 20080922

Free format text: JAPANESE INTERMEDIATE CODE: A61

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111010

Year of fee payment: 3

R150 Certificate of patent (=grant) or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 3

Free format text: PAYMENT UNTIL: 20111010

FPAY Renewal fee payment (prs date is renewal date of database)

Year of fee payment: 4

Free format text: PAYMENT UNTIL: 20121010

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20131010

Year of fee payment: 5