JPH01190842A - Method for constructing reinforced concrete column and steel girder structure - Google Patents

Method for constructing reinforced concrete column and steel girder structure

Info

Publication number
JPH01190842A
JPH01190842A JP1622688A JP1622688A JPH01190842A JP H01190842 A JPH01190842 A JP H01190842A JP 1622688 A JP1622688 A JP 1622688A JP 1622688 A JP1622688 A JP 1622688A JP H01190842 A JPH01190842 A JP H01190842A
Authority
JP
Japan
Prior art keywords
reinforcing bars
molds
floor
columns
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP1622688A
Other languages
Japanese (ja)
Inventor
Masahiro Yoshinobu
吉信 正弘
Mitsumasa Yamamoto
光政 山本
Takeshi Kitamura
健 北村
Shoei Ito
伊藤 昭栄
Akio Tomita
昭夫 富田
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP1622688A priority Critical patent/JPH01190842A/en
Publication of JPH01190842A publication Critical patent/JPH01190842A/en
Pending legal-status Critical Current

Links

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

PURPOSE:To allow a steel girder to be joined with a reinforced concrete column with ease, thereby enable reasonable construction by joining column reinforcing bars with a girder by means of joint fittings, placing concrete therein thereafter, and thereby forming a reinforced concrete column. CONSTITUTION:Columnar pre-fabricated reinforcing bars 2 having girder joint fittings 5 at girder joints, are set up on a floor slub 1 so that columnar molds 6 are set up around the bars. Then, steel girders 7 are connected with each columnar pre-fabricated reinforcing bar 2 by each girder joint fitting 5 so that connection molds 11 are installed at each girder joint. Following which, floor molds 12 are set up on each steel girder 7 so that concrete is placed in the columnar molds 6, the connection molds 11 and over the floor molds 12. And after concrete has been cured, concrete is placed over the molds. Then, after concrete has been cured, the columnar molds and the connection molds 11 are removed, one structural work cycle for the first floor is thereby completed. The construction method is so constituted that processes set forth herein above are applied repeatedly for floors above the first one.

Description

【発明の詳細な説明】 〔産業上の利用分野〕 この発明は、柱が鉄筋コンクリート構造からなり、梁が
鉄骨構造からなる鉄筋コンクリート柱鉄骨梁構造物の施
工方法に関するものである。
DETAILED DESCRIPTION OF THE INVENTION [Field of Industrial Application] The present invention relates to a method of constructing a reinforced concrete column and steel beam structure in which the columns are made of a reinforced concrete structure and the beams are made of a steel frame structure.

〔従来の技術〕[Conventional technology]

鉄筋コンクリート構造の建物を構築する場合、柱と梁を
ともに鉄骨・鉄筋コンクリート構造としないで、柱を鉄
筋コンクリートとし、梁を鉄骨構造とすることがある。
When constructing a building with a reinforced concrete structure, the columns and beams are sometimes made of reinforced concrete and the beams are made of steel, instead of having both the columns and beams of steel frame/reinforced concrete structure.

〔発明が解決しようとする問題点〕[Problem that the invention seeks to solve]

しかしながら、この種の構造方式によると、材質的相異
により、柱鉄筋の組立、鉄骨梁の設置が煩雑になって、
施工が面倒になることが免れないものであった。
However, with this type of structure, assembly of column reinforcing bars and installation of steel beams becomes complicated due to differences in materials.
It was inevitable that the construction would be troublesome.

また、柱と梁との仕口部は、材質的相違により、一体向
接合がきわめて面倒であった。
Furthermore, due to the difference in materials between the pillars and the beams, it is very difficult to join them in one direction.

この発明は、このような前記従来の問題点を解消するた
めに提案されたもので、鉄骨・鉄筋コンクリート建物を
構築するに際し、柱を鉄筋コンクリート構造によって、
梁を鉄骨構造によってそれぞれ構築する場合、柱鉄筋、
柱型枠の組立及び鉄骨梁の設置が合理的にできて施工性
がよく、しかも、柱・梁間の一体的接合を簡単におこな
えるようにした鉄筋コンクリート柱と鉄骨梁構造物の施
工方法を提供することを目的とする。
This invention was proposed to solve the above-mentioned conventional problems, and when constructing a steel frame/reinforced concrete building, columns are made of reinforced concrete structure.
When each beam is constructed with a steel structure, column reinforcement,
To provide a method for constructing a reinforced concrete column and steel beam structure that allows for rational assembly of column formwork and installation of steel beams, good workability, and easy integral connection between columns and beams. The purpose is to

C問題点を解決するための手段〕 この発明は、柱が鉄筋コンクリート構造からなり、梁が
鉄骨構造からなる鉄骨・鉄筋コンクリート構造の施工方
法に関するもので、複数本の主筋とフープ筋とから柱用
プレハブ鉄筋を構成し、この柱用プレハブ鉄筋の梁接合
部に梁接合金物を取付け、この柱用プレハブ鉄筋を床ス
ラブの上に建て付け、続いて、柱用プレハブ鉄筋の回り
に社用型枠を建て付け、続いて、柱用プレハブ鉄筋間に
鉄骨梁を架設すると共にその両端を前記梁接合金物に連
結することにより柱用プレハブ鉄筋と連結し、続いて、
前記柱用プレハブ鉄筋の梁接合部に仕口型枠を取付け、
続いて、前記鉄骨梁の上に床型枠を敷設し、続いて、柱
用型枠内、仕口型粋内及び床型枠上にコンクリートを打
設し、続いて、前記コンクリート養生後、枠上にコンク
リートを打設し、前記コンクIJ −1−#生後、前記
社用型枠及び仕口型枠を取り外すことで1階分の躯体工
事ザイクルとし、これを順次上階に繰り返すことを特徴
とする。
Means for Solving Problem C] This invention relates to a method for constructing a steel frame/reinforced concrete structure in which the columns are made of a reinforced concrete structure and the beams are made of a steel frame structure. Configure the reinforcing bars, attach beam joint hardware to the beam joints of the prefabricated reinforcing bars for the columns, erect the prefabricated reinforcing bars for the columns on top of the floor slab, and then install the company formwork around the prefabricated reinforcing bars for the columns. After erection, a steel beam is erected between the prefabricated reinforcing bars for columns and connected to the prefabricated reinforcing bars for columns by connecting both ends of the beam to the beam joint hardware, and then,
Attach a joint formwork to the beam joint of the prefabricated reinforcing bars for the column,
Next, a floor form is laid on the steel beam, concrete is poured inside the column form, inside the shikigu type, and on the floor form, and after the concrete is cured, Concrete was poured on the frame, and after the concrete IJ-1-# was completed, the company formwork and joint formwork were removed to create a cycle of frame work for one floor, and this was repeated sequentially for the upper floors. Features.

〔実施例〕〔Example〕

以下、この発明に係る施工方法を順を追って説明する。 Hereinafter, the construction method according to the present invention will be explained step by step.

■ まず、N階の床スラブ1のコンクリートを打設し、
充分に養生する(第1図参照)。
■ First, pour concrete for floor slab 1 on the N floor.
Allow sufficient curing (see Figure 1).

■ 続いて、N階の床スラブ1の上に柱用プレハブ鉄筋
2を建て付ける(第2図参照)。
■ Next, prefabricated reinforcing bars 2 for columns are erected on top of the floor slab 1 on the N floor (see Figure 2).

柱用プレハブ鉄筋2は、予め地上において複数本の主筋
3.3と、フープ筋4.4とから組み立てておく。柱用
プレハブ鉄筋2の梁接合部には、梁接合金物5,5を取
り付ける。
The prefabricated reinforcing bars 2 for columns are assembled in advance from a plurality of main bars 3.3 and hoop bars 4.4 on the ground. Beam joining hardware 5, 5 is attached to the beam joining portion of the prefabricated reinforcing bars 2 for columns.

梁接合金物5は、矩形状に形成されたリング体5aのコ
−す部にプラケソl−5b、5bを取りつけることによ
り形成されている。
The beam joint hardware 5 is formed by attaching plaque solders 1-5b, 5b to the course of a ring body 5a formed in a rectangular shape.

梁接合金物5.5のうち、下側の梁接合金物5ば、正確
な高さ調整をした後、主筋3゜3およびフープ筋4に確
実に取付け、上側の梁接合金物5は、最終的に取付ける
位置よりもやや上側部分に結束線等によって仮止めする
ことにより容易に位置変更をおこなえるようにしてお(
Among the beam joint hardware 5.5, the lower beam joint hardware 5 is securely attached to the main reinforcement 3゜3 and the hoop reinforcement 4 after accurate height adjustment, and the upper beam joint hardware 5 is finally installed. The position can be easily changed by temporarily fixing it with a binding wire, etc., slightly above the position where it will be installed (
.

このように組み立てた柱用プレハブ鉄筋2はN階の床ス
ラブ1の上に突出した直下階の柱用プレハブ鉄筋2の上
端部に建て付けるともに主筋3.3どうしを、スクイズ
継手やねじ式継手等の機械的継手あるいはガス圧接等に
よって継いで自立させる。
The prefabricated reinforcing bars 2 for columns assembled in this way are erected on the upper end of the prefabricated reinforcing bars 2 for columns on the floor immediately below that protrude above the floor slab 1 on the N floor, and the main bars 3.3 are connected to each other using squeeze joints or threaded joints. etc. or gas pressure welding to make it independent.

■ 続いて、柱用プレハブ鉄筋2の回りに柱型枠6.6
を立て付け、強固に固定する(第3図参照)。
■ Next, install the column formwork 6.6 around the prefabricated reinforcing bars 2 for the column.
Stand upright and secure it firmly (see Figure 3).

■ 続いて、柱用プレハブ鉄筋2,2間に鉄骨梁7を架
設する(第4図参照)。
■ Next, the steel beam 7 is erected between the prefabricated column reinforcing bars 2 (see Fig. 4).

鉄骨梁7の端部は、下側の梁接合金物5のブラケット5
bの上にのせる。
The end of the steel beam 7 is connected to the bracket 5 of the lower beam joint hardware 5.
Place on top of b.

また、鉄骨梁7端邪の下側には、サポート8を建て付け
、このサポート8と社用型枠6によって鉄骨梁7を支持
する。
Further, a support 8 is installed below the end of the steel beam 7, and the steel beam 7 is supported by this support 8 and the company formwork 6.

■ 続いて、上側の接合金物5を仮止めを解いて下方に
移動し、ブラケット5b、5bを鉄骨梁7,7の上にの
せる。
(2) Subsequently, the upper joining hardware 5 is released temporarily and moved downward, and the brackets 5b, 5b are placed on the steel beams 7, 7.

また、上下接合金物5,5のブラケ・ノド5b、5b間
に剪断用プレート9を取付ける。
Further, a shearing plate 9 is attached between the bracket throats 5b, 5b of the upper and lower joint metal fittings 5,5.

剪断用プレート9は、基端部にフープ筋4.4を貫通さ
せ、必要により、フープ筋4.4に溶接することにより
取付ける。
The shearing plate 9 is attached by passing the hoop reinforcement 4.4 through the proximal end and welding to the hoop reinforcement 4.4 if necessary.

■ 続いて、鉄骨梁7の位置決めをする。■ Next, position the steel beam 7.

鉄骨梁7の位置決めが完了したら、鉄骨梁7の上下フラ
ンジ7a、7aと上下梁接合金物5.5の上下ブラケッ
ト5b、5bとを複数本の高力ボルト10.10によっ
てボルト止めする。また、剪断用プレー1−9と鉄骨梁
7のウェブ7bとを複数本の高力ボルト10゜10によ
ってボルト止めする。
When the positioning of the steel beam 7 is completed, the upper and lower flanges 7a, 7a of the steel beam 7 and the upper and lower brackets 5b, 5b of the upper and lower beam joining hardware 5.5 are bolted together using a plurality of high-strength bolts 10.10. Further, the shearing play 1-9 and the web 7b of the steel beam 7 are bolted together using a plurality of high-strength bolts 10°10.

■ 続いて、柱・梁接合部の回りに仕口型枠11を取付
け、強固に固定するく第5図参照)。
■Next, attach the joint formwork 11 around the column/beam joint and secure it firmly (see Figure 5).

■ 続いて、鉄骨梁7,7間にデツキプレート等の床型
枠12を敷設する。床型枠12ば、鉄骨梁7に溶接やボ
ルト止めによって強固に固定する(第5図、第6図参照
)。
■ Next, a floor formwork 12 such as a deck plate is laid between the steel beams 7, 7. The floor formwork 12 is firmly fixed to the steel beam 7 by welding or bolting (see FIGS. 5 and 6).

■ 続いて、柱用型枠6内、仕口型枠11内、及び床型
枠12上にコンクリートを打設する。
(2) Next, concrete is poured into the column formwork 6, the joint formwork 11, and the floor formwork 12.

なお、コンクリートを打設する場合、柱用プレハブ鉄筋
2の上端部は、完全に埋めこまないで床面より所定長さ
突出しておく。
In addition, when pouring concrete, the upper end of the prefabricated reinforcing bar 2 for the column is not completely buried, but rather protrudes a predetermined length from the floor surface.

[相] 続いて、コンクリートを充分に養生し、所定の
強度に達したら脱型する。
[Phase] Next, the concrete is sufficiently cured, and when it reaches the specified strength, it is demolded.

以上、■〜[相]の作業を一工程とし、これを繰り返す
ことにより任意階数の鉄骨・鉄筋コンクリート建物を構
築することができる。
As described above, the operations from (1) to [phase] are treated as one process, and by repeating this process, a steel frame/reinforced concrete building with any number of floors can be constructed.

〔発明の効果〕〔Effect of the invention〕

この発明は、以上の構成からなるので、以下の効果を有
する。
Since the present invention has the above configuration, it has the following effects.

■ 柱用プレハブ鉄筋の組立、建て付け、鉄骨梁の架設
、鉄骨梁と柱用プレハブ鉄筋との接合、柱用型枠及び床
用型枠の組立に全く無駄がなく、合理的な施工が可能で
ある。
■ Assembling and installing prefabricated reinforcing bars for columns, erecting steel beams, joining steel beams and prefabricated reinforcing bars for columns, and assembling column formwork and floor formwork allows for streamlined construction with no waste at all. It is.

■ また、柱用プレハブ鉄筋と鉄骨梁とは、接合金物に
依って接合されているので柱と梁との一体的接合が可能
である。
■ Furthermore, since the prefabricated reinforcing bars for columns and the steel beams are connected using joining hardware, it is possible to integrally connect the columns and beams.

【図面の簡単な説明】[Brief explanation of the drawing]

第1図〜第6図は、この発明に係る施工方法を示す工程
図、第7図は、柱・梁接合部の横断面図、第8図は、そ
の縦断面図、第9図は、接合金物の斜視図である。 1・・・N階の床スラブ、2・・・柱用型枠3・・・主
筋、4・・・フープ筋、5・・・梁接合金物、6・・・
柱用型枠、7・・・鉄骨梁、8・・・サポート、9・・
・剪断プレー1−110・・・高力ボルト、11・・・
仕口型枠、12・・・床型枠。
1 to 6 are process diagrams showing the construction method according to the present invention, FIG. 7 is a cross-sectional view of a column-beam joint, FIG. 8 is a longitudinal cross-sectional view thereof, and FIG. 9 is a FIG. 3 is a perspective view of the joining hardware. 1...N floor slab, 2...Column formwork 3...Main reinforcement, 4...Hoop reinforcement, 5...Beam joint hardware, 6...
Column formwork, 7... Steel beam, 8... Support, 9...
・Shearing play 1-110...High strength bolt, 11...
Connection formwork, 12...floor formwork.

Claims (1)

【特許請求の範囲】[Claims] 複数本の主筋とフープ筋とから柱用プレハブ鉄筋を構成
し、この柱用プレハブ鉄筋の梁接合部に梁接合金物を取
付け、この柱用プレハブ鉄筋を床スラブの上に建て付け
、続いて、柱用プレハブ鉄筋の回りに柱用型枠を建て付
け、続いて、柱用プレハブ鉄筋間に鉄骨梁を架設すると
共にその両端を前記梁接合金物に連結することにより柱
用プレハブ鉄筋と連結し、続いて、前記柱用プレハブ鉄
筋の梁接合部に仕口型枠を取付け、続いて、前記鉄骨梁
の上に床型枠を敷設し、続いて、柱用型粋内、仕口型粋
内及び床型枠上にコンクリートを打設し、前記コンクリ
ート養生後、前記柱用型枠及び仕口型枠を取り外すこと
で1階分の躯体工事サイクルとし、これを順次上階に繰
り返すことを特徴とする鉄筋コンクリート柱と鉄骨梁構
造物の施工方法。
Construct prefabricated reinforcing bars for columns from multiple main bars and hoop reinforcing bars, attach beam joint hardware to the beam joints of these prefabricated reinforcing bars for columns, erect these prefabricated reinforcing bars for columns on top of the floor slab, and then, A column formwork is erected around the prefabricated reinforcing bars for columns, and then a steel beam is erected between the prefabricated reinforcing bars for columns, and both ends thereof are connected to the beam joint hardware to connect to the prefabricated reinforcing bars for columns, Next, a joint formwork is installed at the beam joint of the prefabricated reinforcing bars for the column, and then a floor formwork is laid on the steel beam, and then a column formwork and a joint formwork are installed. Concrete is poured onto the floor formwork, and after the concrete has cured, the column formwork and the joint formwork are removed to create a frame work cycle for one floor, and this is repeated sequentially for the upper floors. construction method for reinforced concrete columns and steel beam structures.
JP1622688A 1988-01-27 1988-01-27 Method for constructing reinforced concrete column and steel girder structure Pending JPH01190842A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP1622688A JPH01190842A (en) 1988-01-27 1988-01-27 Method for constructing reinforced concrete column and steel girder structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP1622688A JPH01190842A (en) 1988-01-27 1988-01-27 Method for constructing reinforced concrete column and steel girder structure

Publications (1)

Publication Number Publication Date
JPH01190842A true JPH01190842A (en) 1989-07-31

Family

ID=11910627

Family Applications (1)

Application Number Title Priority Date Filing Date
JP1622688A Pending JPH01190842A (en) 1988-01-27 1988-01-27 Method for constructing reinforced concrete column and steel girder structure

Country Status (1)

Country Link
JP (1) JPH01190842A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579092A (en) * 1991-09-19 1993-03-30 Kajima Corp Constructing method for column reinforced concrete and beam steel structure
CN103806544A (en) * 2014-02-27 2014-05-21 南京工业大学 Steel reinforced concrete L-shaped column-steel beam connecting joint

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6139457A (en) * 1984-07-31 1986-02-25 Toshiba Corp Fuel cell

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6139457A (en) * 1984-07-31 1986-02-25 Toshiba Corp Fuel cell

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579092A (en) * 1991-09-19 1993-03-30 Kajima Corp Constructing method for column reinforced concrete and beam steel structure
CN103806544A (en) * 2014-02-27 2014-05-21 南京工业大学 Steel reinforced concrete L-shaped column-steel beam connecting joint

Similar Documents

Publication Publication Date Title
JP4264916B2 (en) End RC steel beam
JPH01190842A (en) Method for constructing reinforced concrete column and steel girder structure
KR20020017571A (en) connection structure of fixing and connecting steel girder in reinforcement concrete column and construction method
JPH02300439A (en) Prefabricating method
JPH0718734A (en) Constructing method for reinforced concrete building structure
KR20020017306A (en) connetion structure of fixing and connecting steel girder in reinforcement concrete column and construction method
JP2620118B2 (en) Net formwork method for walls and floors
JP2645329B2 (en) Pillar construction method
JPH07113260A (en) Method for connecting column and beam
JPH01203537A (en) Src precast beam and junction structure of column and beam
JPH06104993B2 (en) Construction method of steel pipe precast concrete columns
JPS6141857Y2 (en)
JP3284383B2 (en) Support hardware for SRC beam construction
JP2629496B2 (en) Construction method of structure
JPH032435A (en) Construction method for jointing column and steel frame reinforced-concrete beam to each other
JP2554535B2 (en) Steel beam / reinforced concrete column composite construction method
JPH0443521Y2 (en)
JPH04309630A (en) Skeleton construction method using pc member
JPS6254943B2 (en)
JPH0533606Y2 (en)
JPS60230479A (en) Assembling of iron wire of large beam made of rc
JPH064982B2 (en) Method for supporting reinforced steel composite column and elec- tion piece used therefor
JPH03293445A (en) Structure of building and construction
JPH0531632B2 (en)
JPH0715177B2 (en) How to build a reinforced concrete structure