JPH0522787B2 - - Google Patents

Info

Publication number
JPH0522787B2
JPH0522787B2 JP16753885A JP16753885A JPH0522787B2 JP H0522787 B2 JPH0522787 B2 JP H0522787B2 JP 16753885 A JP16753885 A JP 16753885A JP 16753885 A JP16753885 A JP 16753885A JP H0522787 B2 JPH0522787 B2 JP H0522787B2
Authority
JP
Japan
Prior art keywords
column
spiral
steel frame
concrete
main reinforcement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP16753885A
Other languages
Japanese (ja)
Other versions
JPS6229673A (en
Inventor
Shinichiro Yagi
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsui Construction Co Ltd
Original Assignee
Mitsui Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsui Construction Co Ltd filed Critical Mitsui Construction Co Ltd
Priority to JP16753885A priority Critical patent/JPS6229673A/en
Publication of JPS6229673A publication Critical patent/JPS6229673A/en
Publication of JPH0522787B2 publication Critical patent/JPH0522787B2/ja
Granted legal-status Critical Current

Links

Description

【発明の詳細な説明】 (産業上の利用分野) 本発明は、鉄骨鉄筋コンクリート柱の施工法に
関する。
DETAILED DESCRIPTION OF THE INVENTION (Field of Industrial Application) The present invention relates to a method of constructing a steel reinforced concrete column.

(従来の技術) 従来、鉄骨柱にセンタジヨイント形式あるいは
ブラケツト形式の鉄骨梁を接合すると共に鉄骨柱
の外周にスパイラル帯筋を配筋する鉄骨鉄筋コン
クリート柱の施工法として、柱鉄骨の外周に畳ん
だ状態の複数個のスパイラル帯筋を嵌め、次いで
前記鉄骨の所定の位置に梁の一部または梁接続用
ブラケツトを固着し、次いで前記鉄骨を施工現場
で建込んで、スパイラル帯筋内に主筋を挿通し、
かつスパイラル帯筋を所定ピツチになるように延
ばして主筋と結合し、次いで結合された主筋とス
パイラル帯筋の外周に型枠を組み、最上部より型
枠内にコンクリートを打ち込み、柱をコンクリー
ト打設する方法がある。
(Prior art) Conventionally, as a construction method for steel reinforced concrete columns, a center joint or bracket type steel beam is connected to a steel column and spiral stirrups are arranged around the outer periphery of the steel column. A plurality of spiral stirrups in the open state are fitted, then a part of the beam or a beam connection bracket is fixed to a predetermined position of the steel frame, and then the steel frame is erected at the construction site and the main reinforcing bars are inserted into the spiral stirrups. Insert the
Then, extend the spiral stirrups to a specified pitch and connect them to the main reinforcements, then construct a formwork around the outer periphery of the combined main reinforcements and spiral stirrups, pour concrete into the formwork from the top, and concrete the column. There is a way to set it.

(発明が解決しようとする問題点) 上記従来方法によれば、センタージヨイント形
式あるいはブラケツト形式の鉄骨鉄筋コンクリー
ト構造柱の場合でも、スパイラル帯筋の配筋が可
能であり、現場での主筋との組立も容易であると
いう利点があるが、多層性に亘る場合には、下層
階の主筋及び配筋の周りにコンクリートが十分に
行きわたらず、堅固な柱が構築できない恐れがあ
つた。また鉄骨を建てた後に主筋等の揚重があ
り、更に鉄骨まわりの鉄筋の施工が高層部で行な
われるため、掲重機の効率や安全性に大きな問題
があつた。
(Problems to be Solved by the Invention) According to the above-mentioned conventional method, even in the case of center joint type or bracket type steel frame reinforced concrete structural columns, it is possible to arrange spiral stirrups, and it is possible to arrange them with the main reinforcement on site. Although it has the advantage of being easy to assemble, in the case of multi-story structures, there was a risk that concrete would not be sufficiently spread around the main reinforcement and reinforcement on the lower floor, making it impossible to construct strong columns. In addition, after the steel frame is erected, the main reinforcing bars must be lifted, and the reinforcing bars around the steel frame must be installed in high-rise areas, which poses major problems with the efficiency and safety of hoisting equipment.

本発明は、このような不都合が無い鉄骨鉄筋コ
ンクリート柱の施工法を得ることをその目的とす
るものである。
The object of the present invention is to provide a method for constructing steel-framed reinforced concrete columns that is free from such inconveniences.

(問題点を解決するための手段) 本発明は、柱鉄骨の外周に畳んだ状態の複数個
のスパイラル帯筋を嵌め、該柱鉄骨の所定位置に
該スパイラル帯筋を挟んで梁の一部又は梁接続用
ブラケツトを複数個固着する工程と、該スパイラ
ル帯筋内に柱主筋を挿通し、柱鉄骨の長さ方向に
互いに隣接する2つの該梁又は該ブラケツト間の
区間に介在するスパイラル帯筋を延ばして該区間
の下部を除いて柱主筋に所定ピツチで結合する工
程と、該柱鉄骨を所定の位置に建込んだ状態で柱
主筋にスパイラル帯筋が結合されない前記区間の
下部の近傍にホツパの先端を配置して該区間の下
部の柱主筋で囲まれた空間より、下階の柱主筋及
びスパイラル帯筋で囲まれた1階分に相当する空
間及びその周りにコンクリートを打ち込むコンク
リート打ち込み工程と、更に順次繰り返して行な
われるコンクリートを打ち込むためにホツパを配
置した前記区間の下部の柱主筋にスパイラル帯筋
を延ばして所定ピツチで結合する結合工程及び該
結合工程の終了後当該階に上階からコンクリート
を打ち込むコンクリート打ち込み工程とから成る
ことを特徴とする。
(Means for Solving the Problems) The present invention involves fitting a plurality of folded spiral stirrups around the outer periphery of a column steel frame, and sandwiching the spiral stirrups at predetermined positions of the column steel frame to form a part of the beam. or a process of fixing a plurality of beam connection brackets, and inserting a column main reinforcement into the spiral stirrup, and a spiral band interposed in the section between two beams or brackets that are adjacent to each other in the length direction of the column steel frame. The process of extending the reinforcement and connecting it to the column main reinforcement at a predetermined pitch except for the lower part of the section, and the vicinity of the lower part of the section where the spiral stirrup is not connected to the column main reinforcement with the column steel frame erected at a predetermined position. Concrete is poured from the space surrounded by the main column reinforcement at the bottom of the section by placing the tip of the hopper in the space corresponding to one floor surrounded by the main column reinforcement and spiral stirrups on the lower floor and around it. A pouring process, a connecting process in which spiral stirrups are extended and connected at a predetermined pitch to the column main reinforcement at the bottom of the section where the hopper is placed in order to pour concrete, and after the completion of the connecting process, the concrete is placed on the floor. It is characterized by a concrete pouring process in which concrete is poured from the upper floors.

(実施例) 以下、その実施例を図面により詳細に説明す
る。
(Example) Hereinafter, the example will be described in detail with reference to the drawings.

図面において、1は例えばH形鋼からなる柱鉄
骨で、該柱鉄骨1は例えば3層階の寸法を有する
ものとする。例えば、鉄骨工場において、第1図
示のように、柱鉄骨1の外周にスパイラル帯筋2
を上下に圧縮した畳んだ状態にして例えば2個嵌
め、次いで、柱鉄骨1の側面における所定の位置
に梁3(又は梁を接続するブラケツト)を溶接等
により固着する。
In the drawings, reference numeral 1 denotes a column steel frame made of, for example, H-beam steel, and the column steel frame 1 has dimensions of, for example, three stories. For example, in a steel frame factory, as shown in the first diagram, spiral tie bars 2 are placed around the outer periphery of a column steel frame 1.
For example, two of them are fitted in a vertically compressed folded state, and then a beam 3 (or a bracket for connecting the beam) is fixed at a predetermined position on the side surface of the column steel frame 1 by welding or the like.

この際、各スパイラル帯筋2は梁3の間に挾ま
れるようにする。
At this time, each spiral tie reinforcement 2 is sandwiched between the beams 3.

次いで、上記柱鉄骨1を施工現場に搬入して、
第2図示のように、架台4にセツトし、柱鉄骨1
の脚部にスパイラル帯筋2を嵌める。この状態の
まま、柱主筋取付用治具5を梁3に取付け(第3
図)、その孔6を介して柱主筋7を柱鉄骨1の周
りでスパイラル帯筋2の内側に挿通して組み立て
る。
Next, the above-mentioned column steel frame 1 is transported to the construction site,
As shown in the second diagram, set it on the pedestal 4 and
Insert the spiral ties 2 into the legs of. In this state, attach the column main reinforcement installation jig 5 to the beam 3 (the third
(Fig.), the main column reinforcement 7 is inserted through the hole 6 into the inside of the spiral tie reinforcement 2 around the column steel frame 1, and assembled.

次いで、柱主筋7の2つの梁3に挟まれた区間
の下側(図面の左側)の所定の長さ例えば1m分
を除いてスパイラル帯筋2を所定のピツチになる
ように延ばして柱主筋7に例えばなまし鉄線によ
り結束する。柱鉄骨1の脚部のスパイラル帯筋2
については、該脚部全長に亘つて延ばして所定の
ピツチにし、柱主筋7に結束する(第4図)。
Next, the spiral stirrups 2 are extended to a predetermined pitch except for a predetermined length, for example, 1 m, on the lower side (left side in the drawing) of the section sandwiched between the two beams 3 of the column main reinforcements 7. 7. Bind the wires with, for example, annealed iron wire. Spiral stirrups 2 at the legs of column steel frame 1
, the legs are stretched over the entire length to form a predetermined pitch and tied to the column main reinforcing bars 7 (FIG. 4).

そして、この柱鉄骨1を、第5図示のように、
クレーンで吊り上げて所定の位置に建込み、柱鉄
骨1の脚部に嵌めた所定ピツチのスパイラル帯筋
2の周りに柱型枠8を組み立てる。次いで、2階
の、スパイラル帯筋2が施されていない柱主筋7
の下部の近傍にホツパ9の先端を配置し、バケツ
ト10からホツパ9を経て梁3の下方の柱型枠8
内にコンクリートを打ち込み、柱11を打設す
る。打ち込みが終了した後は、2階のスパイラル
帯筋2を柱主筋7の下部まで延ばし、該スパイラ
ル帯筋2を所定のピツチで柱主筋7に固着する。
次いで、第6図に示すように、上記と同様に2階
の柱主筋7とスパイラル帯筋2の周りに柱側枠8
を組み立て、3階の、スパイラル帯筋2が施され
ていない柱主筋7の下部から2階の柱側枠8内に
コンクリートを打ち込み、柱を打設する。3階に
ついても同様に行なう。
Then, as shown in the fifth diagram, this column steel frame 1 is
It is hoisted by a crane and erected at a predetermined position, and a column formwork 8 is assembled around the spiral ties 2 of a predetermined pitch fitted to the legs of the column steel frame 1. Next, the main column reinforcement 7 on the second floor without the spiral stirrups 2
The tip of the hopper 9 is placed near the bottom of the column formwork 8 below the beam 3 from the bucket 10 through the hopper 9.
Concrete is poured inside and pillar 11 is placed. After the driving is completed, the spiral ties 2 on the second floor are extended to the lower part of the column main reinforcements 7, and the spiral ties 2 are fixed to the column main reinforcements 7 at a predetermined pitch.
Next, as shown in FIG. 6, the column side frames 8 are installed around the main column reinforcements 7 and spiral stirrups 2 on the second floor in the same manner as above.
concrete is poured into the column side frame 8 on the second floor from the lower part of the column main reinforcement 7 on the third floor to which the spiral ties 2 are not applied, and the columns are cast. Do the same for the third floor.

尚、上記実施例では、柱鉄骨の脚部にスパイラ
ル筋を嵌める工程及びスパイラル筋を主筋に結合
する工程を建築現場で行なうようにしたが、これ
等の固定を工場において行なつてもよい。
In the above embodiment, the process of fitting the spiral reinforcement into the leg of the column steel frame and the process of connecting the spiral reinforcement to the main reinforcement were performed at the construction site, but these fixings may be performed at the factory.

(発明の効果) 本発明によれば、センタージヨント形式あるい
はブラケツト形式の鉄骨鉄筋コンクリート構造中
でもスパイラル帯筋の配筋が可能であるとともも
に、隣接する2つの梁又はブラケツト間の区間の
下部を除いてスパイラル帯筋を柱主筋に所定ピツ
チで結合し、該下部から該下部に隣接する梁又は
ブラケツトより下方の柱主筋及びスパイラル帯筋
の周りにコンクリートを打ち込み、打ち込んだそ
の下部の柱主筋にスパイラル帯筋を所定ピツチで
固着したから、各階の柱のコンクリート打設が同
じ条件で行なわれて確実であり、また鉄骨を建て
る前に主筋等を配筋するため揚重機の効率及び安
全性において優れる等の効果がある。
(Effects of the Invention) According to the present invention, it is possible to arrange spiral stirrup reinforcement even in a center joint type or bracket type steel reinforced concrete structure, and it is also possible to provide spiral reinforcement in the lower part of the section between two adjacent beams or brackets. Connect the spiral stirrups to the column main reinforcement at a predetermined pitch except for Since the spiral stirrups are fixed at a predetermined pitch, concrete placement for columns on each floor can be carried out under the same conditions and is reliable.In addition, since the main reinforcement etc. are arranged before the steel frame is erected, the efficiency and safety of the lifting machine are improved. It has excellent effects.

【図面の簡単な説明】[Brief explanation of drawings]

図面は、本発明の実施例による順を追つた各施
工過程の説明図で、第1図、第2図、第4図、第
5図及び第6図はその正面図、第3図は側面図で
ある。 1……柱鉄骨、2……スパイラル帯筋、3……
梁、4……架台、7……柱主筋、8……柱型枠。
The drawings are explanatory diagrams of each step-by-step construction process according to the embodiment of the present invention, and FIGS. 1, 2, 4, 5, and 6 are front views, and FIG. 3 is a side view. It is a diagram. 1...Column steel frame, 2...Spiral stirrup, 3...
Beam, 4... Frame, 7... Column main reinforcement, 8... Column formwork.

Claims (1)

【特許請求の範囲】[Claims] 1 柱鉄骨の外周に畳んだ状態の複数個のスパイ
ラル帯筋を嵌め、該柱鉄骨の所定位置に該スパイ
ラル帯筋を挟んで梁の一部又は梁接続用ブラケツ
トを複数個固着する工程と、該スパイラル帯筋内
に柱主筋を挿通し、柱鉄骨を長さ方向に互いに隣
接する2つの該梁又は該ブラケツト間の区間に介
在するスパイラル帯筋を延ばして該区間の下部を
除いて柱主筋に所定ピツチで結合する工程と、該
柱鉄骨を所定の位置に建込んだ状態で柱主筋にス
パイラル帯筋が結合されない前記区間の下部の近
傍にホツパの先端を配置して該区間の下部の柱主
筋で囲まれた空間より、下階の柱主筋及びスパイ
ラル帯筋で囲まれた1階分に相当する空間及びそ
の周りにコンクリートを打ち込むコンクリート打
ち込み工程と、更に順次繰り返して行なわれるコ
ンクリートを打ち込むためにホツパを配置した前
記区間の下部の柱主筋にスパイラル帯筋を延ばし
て所定ピツチで結合する結合工程及び該結合工程
の終了後当該階に上階からコンクリートを打ち込
むコンクリート打ち込み工程とから成ることを特
徴とする鉄骨鉄筋コンクリート柱の施工法。
1. Fitting a plurality of folded spiral stirrups around the outer periphery of a column steel frame, and fixing a part of a beam or a plurality of beam connection brackets to a predetermined position of the column steel frame with the spiral stirrups sandwiched therebetween; The column main reinforcement is inserted into the spiral stirrup, and the spiral stirrup interposed in the section between the two longitudinally adjacent beams or the brackets is extended to remove the column main reinforcement except for the lower part of the section. The step of connecting the column steel frame at a predetermined pitch to the main reinforcement of the column, and placing the tip of the hopper near the bottom of the section where the spiral stirrup is not connected to the column main reinforcement with the column steel frame in a predetermined position, A concrete pouring process in which concrete is poured from the space surrounded by the main column reinforcements into a space equivalent to one floor surrounded by the main column reinforcements and spiral stirrups on the lower floor, and around it, and then concrete is poured in a sequential manner. The method consists of a joining process in which spiral stirrups are extended to the column main reinforcement at the bottom of the section where hoppers have been placed and joined at a predetermined pitch, and a concrete pouring process in which concrete is poured into the relevant floor from the upper floor after the joining process is completed. A construction method for steel-framed reinforced concrete columns.
JP16753885A 1985-07-31 1985-07-31 Construction of reinforced concrete pillar Granted JPS6229673A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP16753885A JPS6229673A (en) 1985-07-31 1985-07-31 Construction of reinforced concrete pillar

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP16753885A JPS6229673A (en) 1985-07-31 1985-07-31 Construction of reinforced concrete pillar

Publications (2)

Publication Number Publication Date
JPS6229673A JPS6229673A (en) 1987-02-07
JPH0522787B2 true JPH0522787B2 (en) 1993-03-30

Family

ID=15851553

Family Applications (1)

Application Number Title Priority Date Filing Date
JP16753885A Granted JPS6229673A (en) 1985-07-31 1985-07-31 Construction of reinforced concrete pillar

Country Status (1)

Country Link
JP (1) JPS6229673A (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2810066B2 (en) * 1988-10-05 1998-10-15 株式会社日立製作所 Repair method of neutron flux monitor housing
JP2010013898A (en) * 2008-07-07 2010-01-21 Fujita Corp Steel reinforced concrete column assembling method

Also Published As

Publication number Publication date
JPS6229673A (en) 1987-02-07

Similar Documents

Publication Publication Date Title
CN113356370A (en) Mutual anchoring connection construction method for shear wall, frame column and concrete beam bracket
JP2747678B2 (en) Composite beam
JPH0522787B2 (en)
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JPH0673783A (en) Construction of steel framed reinforced concrete column and steel beam
JPH01214641A (en) Construction of steel-pipe precast concrete pole
CN215759634U (en) Mutual anchor connection structure of shear force wall and frame post and concrete beam bracket
JP2003013493A (en) Beam-column connection joint and beam-column connection method
JP3187618B2 (en) How to assemble beam reinforcement
JPH084107A (en) Connecting method for column/beam connection
JP2972956B2 (en) Column and beam joining method and its structure
JP2910551B2 (en) Lap joint method of main reinforcement of SRC column
JPH01137032A (en) Method of lap joint construction of main reinforcement in post and beam joining section
JPH0118229B2 (en)
JP2764334B2 (en) Lift slab construction method
JPS6255377A (en) Steel bar assembling construction method of reinforced concrete structure
JP2723011B2 (en) Construction method of steel frame reinforced concrete structure
JPH07310368A (en) Reinforced concrete frame and construction method thereof
JPS61207765A (en) Construction of building skeletal composed of reinforcement bars
JPH0431523A (en) Binding method of column and beam and construction thereof
JPH02282538A (en) Construction method of reinforced concrete-made building frame
JP2813816B2 (en) Lift-up method using synthetic steel beams
JPH01214668A (en) Preassembling method for beam reinforcement
JPS61225448A (en) Reinforcing bar composite pillar
JPH02157360A (en) Body constructing method of steel framed reinforced concrete multistoried building