JP7368685B2 - Bridge reconstruction method and bridge superstructure - Google Patents

Bridge reconstruction method and bridge superstructure Download PDF

Info

Publication number
JP7368685B2
JP7368685B2 JP2019173549A JP2019173549A JP7368685B2 JP 7368685 B2 JP7368685 B2 JP 7368685B2 JP 2019173549 A JP2019173549 A JP 2019173549A JP 2019173549 A JP2019173549 A JP 2019173549A JP 7368685 B2 JP7368685 B2 JP 7368685B2
Authority
JP
Japan
Prior art keywords
bridge
superstructure
existing
existing bridge
bridge superstructure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2019173549A
Other languages
Japanese (ja)
Other versions
JP2021050512A (en
Inventor
光商 大庭
忠良 石橋
満 清水
Original Assignee
Jr東日本コンサルタンツ株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jr東日本コンサルタンツ株式会社 filed Critical Jr東日本コンサルタンツ株式会社
Priority to JP2019173549A priority Critical patent/JP7368685B2/en
Publication of JP2021050512A publication Critical patent/JP2021050512A/en
Application granted granted Critical
Publication of JP7368685B2 publication Critical patent/JP7368685B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Description

本発明は、既設橋梁を撤去し、新設橋梁を架設する架替工法に関するものである。 The present invention relates to a reconstruction method for removing an existing bridge and constructing a new bridge.

一般にコンクリートの寿命は60~100年と言われている。コンクリートや鉄を主材料とする土木構造物も半世紀以上経過すると、大規模補修をして長寿命化を図るか、既設構造物を撤去して新設するかを検討することが多い。 Generally, the lifespan of concrete is said to be 60 to 100 years. After more than half a century has passed since civil engineering structures made primarily of concrete or steel, it is often necessary to consider whether to make large-scale repairs to extend their lifespan, or to demolish the existing structures and construct new ones.

橋梁においても、既設橋梁を撤去し、新設橋梁を架設する架替が検討されている。しかしながら、橋梁周辺環境による制約により施工条件が厳しいことが多い。また、架替工事は、撤去工程と新設工程を含むため、長期化しやすい。そのため、施工条件に応じて、様々な架替工法が提案されている(例えば、特許文献1)。 Regarding bridges, consideration is being given to replacing existing bridges by removing them and constructing new ones. However, construction conditions are often severe due to constraints imposed by the environment surrounding the bridge. In addition, rebuilding work tends to take a long time because it includes a removal process and a new installation process. Therefore, various rebuilding methods have been proposed depending on the construction conditions (for example, Patent Document 1).

たとえば、特許文献1開示の架替工法では、まず、橋脚に架設された既設橋桁を運搬台車上に設置されたジャッキにより下方から支持する。橋脚径間より短い長さで既設橋桁の両端を切断する。ジャッキを操作して既設橋桁を降下させる。ジャッキで既設橋桁を下方より支持した状態で、運搬台車により既設橋桁を搬出する。 For example, in the rebuilding method disclosed in Patent Document 1, first, an existing bridge girder installed on a bridge pier is supported from below by a jack installed on a transport vehicle. Cut both ends of the existing bridge girder to a length shorter than the pier span. Operate the jack to lower the existing bridge girder. The existing bridge girders are supported from below by jacks and then transported using a transport truck.

一方、新設橋桁架替位置に隣接する残部既設橋桁上で新設橋桁を構築する。さらに新設橋桁を大型クレーン吊りあげて橋脚間に架設する。 Meanwhile, a new bridge girder will be constructed on the remaining existing bridge girder adjacent to the new bridge girder replacement location. Furthermore, the new bridge girders will be hoisted up by a large crane and installed between the piers.

特開2003-034911号公報JP2003-034911A

図12は、既設橋梁の一例である。都市部では狭隘な谷部に複数の鉄道が並走し、谷を跨ぎ線路と立体交差するように橋梁が架けられていることもある。半世紀以上前に架けられた橋梁は一般に径間が短く、両端の橋台に加えて、橋脚により支持されている。複数の鉄道が橋脚間または橋台橋脚間を通過している。 Figure 12 is an example of an existing bridge. In urban areas, multiple railways run parallel to each other in narrow valleys, and bridges are sometimes built to span the valleys and intersect with the railroad tracks. Bridges built over half a century ago generally have short spans and are supported by piers in addition to abutments at both ends. Multiple railroads are passing between the piers or between the abutment piers.

上記のような橋梁において点検やメンテナンスをする際は、必ず、鉄道運行状況を考慮する必要がある。特に、線路に挟まれた橋脚の点検やメンテナンスは非常に作業条件が厳しい。したがって、架替の方が好ましいと判断される場合もある。なお、近年、径間が長くなる傾向にあり、橋脚による支持は不要となる。橋梁構造が単純化すれば点検やメンテナンスも容易となる。 When inspecting or maintaining bridges such as those mentioned above, it is necessary to take into account the railway operating conditions. In particular, inspection and maintenance of bridge piers sandwiched between railroad tracks requires extremely difficult work conditions. Therefore, it may be determined that rebuilding is more preferable. In recent years, spans have tended to become longer, making support by piers unnecessary. If the bridge structure is simplified, inspection and maintenance will be easier.

特許文献1記載の架替工法は、橋梁下において運搬台車を待機させている。図12に示す施工条件下では、橋梁下において運搬台車を待機させることは好ましくなく、特許文献1記載の架替工法の適用は困難である。上記施工条件に適した架替工法を検討する必要がある。 In the bridge reconstruction method described in Patent Document 1, a transport truck is placed on standby under a bridge. Under the construction conditions shown in FIG. 12, it is not preferable to have a transport vehicle waiting under the bridge, and it is difficult to apply the rebuilding method described in Patent Document 1. It is necessary to consider a reconstruction method suitable for the above construction conditions.

本発明は上記課題を解決するものであり、橋梁下の施工条件が厳しい場合にも適用可能な橋梁の架替工法を提供することを目的とする。 The present invention solves the above problems, and aims to provide a bridge reconstruction method that can be applied even when the construction conditions under the bridge are severe.

上記課題を解決する本発明は橋梁の架替工法である。新設橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられており、既設橋梁上部構造上面を搬路として、前記新設橋梁上部構造を搬入し、既設橋梁上部構造の上部に、前記新設橋梁上部構造を仮設し、前記新設橋梁上部構造の両端を仮支持し、前記第1接続手段と第2接続手段とを接続するとともに、前記第2接続手段を介して、前記既設橋梁上部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、前記既設橋梁上部構造の撤去相当部を切断し、前記既設橋梁上部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させて、撤去し、複数の前記既設橋梁上部構造の撤去相当部の撤去を繰り返し、前記既設橋梁上部構造を撤去し、前記新設橋梁上部構造を降下させて本設する。 The present invention, which solves the above problems, is a bridge reconstruction method. A first connecting means extending in the bridge axis direction is provided on the lower surface side of the new bridge superstructure, and the new bridge superstructure is carried in using the upper surface of the existing bridge superstructure as a transportation path, and the existing bridge superstructure is Temporarily installing the new bridge superstructure on top of the superstructure, temporarily supporting both ends of the new bridge superstructure, connecting the first connecting means and the second connecting means, and connecting the first connecting means and the second connecting means via the second connecting means. the part of the existing bridge superstructure that corresponds to removal is suspended and supported by the new bridge superstructure, the part of the existing bridge superstructure that corresponds to removal is cut, the part of the existing bridge superstructure that corresponds to removal is lifted; by sliding the bridge via the first connecting means and removing it, repeating the removal of the portions of the existing bridge superstructure that correspond to the removal, removing the existing bridge superstructure, lowering the new bridge superstructure, and then removing the existing bridge superstructure. Set up

上記手順において、橋梁下での作業はなく、既設橋梁上部構造上面を利用してほとんどの作業を行える。これにより、橋梁下の施工条件が厳しい場合にも適用可能となる。 In the above procedure, there is no work under the bridge, and most of the work can be done using the top surface of the existing bridge superstructure. This makes it applicable even when construction conditions under bridges are severe.

また、新設橋梁上部構造の仮支持状態を既設橋梁上部構造撤去の仮設設備として利用できる。 In addition, the temporarily supported state of the newly constructed bridge superstructure can be used as temporary equipment for removing the existing bridge superstructure.

なお、本願において、上部構造とは、桁と床版とを含む。 In addition, in this application, a superstructure includes a girder and a floor slab.

上記発明において好ましくは、前記既設橋梁上部構造の撤去相当部の撤去において、前記既設橋梁上部構造の残部上に吊り降ろし、前記既設橋梁上部構造の残部上面を搬路とする。 In the above invention, preferably, in removing the portion corresponding to removal of the existing bridge superstructure, the part is suspended onto the remaining part of the existing bridge superstructure, and the upper surface of the remaining part of the existing bridge superstructure is used as a transport path.

このように、既設橋梁上部構造の残部を有効活用できる。すなわち、橋梁下での作業を無くすことができる。 In this way, the remaining part of the existing bridge superstructure can be effectively utilized. In other words, work under the bridge can be eliminated.

上記発明において好ましくは、前記既設橋梁上部構造の撤去相当部の撤去において、摺動状態にて既設橋梁の外部に搬出する。 Preferably, in the above invention, when removing the portion of the existing bridge superstructure that corresponds to removal, the removed portion is carried out in a sliding state to the outside of the existing bridge.

これにより、既設橋梁上部構造の残部を作業エリアとして有効活用できる。 This allows the remaining part of the existing bridge superstructure to be effectively used as a work area.

上記発明において好ましくは、前記第2接続手段を介して、前記既設橋梁下部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、前記既設橋梁下部構造の撤去相当部を切断し、前記既設橋梁下部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させ、撤去し、複数の前記既設橋梁下部構造の撤去相当部の撤去を繰り返し、前記既設橋梁下部構造を撤去する。 In the above invention, preferably, the part of the existing bridge substructure corresponding to removal is suspended and supported by the new bridge superstructure via the second connecting means, the part of the existing bridge substructure corresponding to removal is cut, and the part of the existing bridge substructure corresponding to removal is suspended from the existing bridge substructure. Lift up the portion of the bridge substructure that corresponds to removal, further slide it through the first connecting means, remove it, repeat the removal of the portion of the existing bridge substructure that corresponds to removal, and remove the existing bridge substructure. do.

本願工法は、既設橋梁下部構造の撤去にも適用できる。なお、本願において、下部構造とは、橋脚と橋台とを含む。 The proposed construction method can also be applied to the removal of existing bridge substructures. In addition, in this application, a lower structure includes a bridge pier and an abutment.

上記発明において好ましくは、前記第2接続手段は、橋軸直交方向に2以上設けられ、前記第2接続手段同士は、吊桁を介して連結されている。 In the above invention, preferably, two or more of the second connecting means are provided in a direction perpendicular to the bridge axis, and the second connecting means are connected to each other via a hanging girder.

これにより、吊位置を調整できるとともに、吊状態が安定する。 This makes it possible to adjust the hanging position and stabilize the hanging condition.

上記発明において好ましくは、前記新設橋梁上部構造本設後も、前記第1接続手段が設けられた状態を維持する。 In the above invention, preferably, the state in which the first connection means is maintained is maintained even after the new bridge superstructure is permanently installed.

これにより、本設後の点検時等にも再利用可能となる。 This makes it possible to reuse it during inspections after permanent installation.

上記発明において好ましくは、前記既設橋梁上部構造は、橋軸交差方向に延設される線路または道路の上に設けられている。 Preferably, in the above invention, the existing bridge superstructure is provided on a railroad or road extending in a direction crossing the bridge axis.

本願工法は、このような橋梁下の施工条件が厳しい場合に、好適である。橋梁下での作業はなく、橋梁下の状況に影響されにくい。 The construction method of the present application is suitable when the construction conditions under such a bridge are severe. There is no work under the bridge, so it is not easily affected by the conditions under the bridge.

上記課題を解決する本発明は橋梁上部構造である。新設橋梁上部構造の下面側には、橋軸方向に延設されているレール状の第1接続手段が設けられている。 The present invention that solves the above problems is a bridge superstructure. A rail-shaped first connection means extending in the bridge axis direction is provided on the lower surface side of the newly constructed bridge superstructure.

すなわち、第1接続手段は新設橋梁の一部であり、本設後も再利用可能である。 That is, the first connecting means is a part of the newly constructed bridge and can be reused even after the bridge is permanently constructed.

上記課題を解決する本発明は橋梁上部構造である。下面側に、橋軸方向に延設されているレール状の第1接続手段が設けられ、第2接続手段が前記第1接続手段と接続される状態で、前記第1接続手段に沿って摺動可能である。 The present invention that solves the above problems is a bridge superstructure. A rail-shaped first connecting means extending in the bridge axis direction is provided on the lower surface side, and the second connecting means is slidable along the first connecting means in a state where the second connecting means is connected to the first connecting means. It is possible to move.

第1接続手段と第2接続手段とからなる接続機構は架替工事の撤去工程にて利用できる。また、第1接続手段は本設後も再利用可能である。 The connection mechanism consisting of the first connection means and the second connection means can be used in the removal process of rebuilding work. Furthermore, the first connection means can be reused even after permanent installation.

本発明に係る架替工法によれば、橋梁下の施工条件が厳しい場合にも適用可能である。 According to the bridge reconstruction method according to the present invention, it is applicable even when the construction conditions under a bridge are severe.

本願システム断面図Cross-sectional diagram of the system of the present application 接続機構(実施例および変形例)Connection mechanism (examples and modifications) 接続機構(変形例)Connection mechanism (modified example) 既設上部構造撤去例斜視図(前半)Perspective view of existing superstructure removal example (first half) 既設上部構造撤去例斜視図(後半)Perspective view of example of removal of existing superstructure (second half) 既設下部構造撤去例斜視図Perspective view of existing substructure removal example 新設上部構造架設例斜視図Perspective view of new superstructure construction example 新設橋梁例斜視図Perspective view of newly constructed bridge example 既設上部構造撤去例斜視図(変形例)Perspective view of existing superstructure removal example (modified example) 既設上部構造撤去例斜視図(変形例)Perspective view of existing superstructure removal example (modified example) 既設上部構造撤去例斜視図(変形例)Perspective view of existing superstructure removal example (modified example) 既設橋梁例斜視図Perspective view of existing bridge example

~既設橋梁例~
図12は、本発明が適用される既設橋梁10の例である。都市部では狭隘な谷部に複数の鉄道が並走し、谷を跨ぎ線路と立体交差するように橋梁10が架けられている。既設橋梁は一般に径間が短いことが多く、上部構造(橋桁や床版を含む広義の概念)11が、両端の橋台12,12や橋脚13,13の下部構造により支持されている。なお、支承等その他の構成については図示を省略する。複数の鉄道が橋脚13,13間または橋台12橋脚13間を通過している。
~Existing bridge example~
FIG. 12 is an example of an existing bridge 10 to which the present invention is applied. In urban areas, a plurality of railways run parallel to each other in narrow valleys, and bridges 10 are built to span the valleys and intersect with the railroad tracks. Existing bridges generally have short spans, and a superstructure (a broad concept including bridge girders and deck slabs) 11 is supported by lower structures of abutments 12, 12 and piers 13, 13 at both ends. Note that illustrations of other components such as supports are omitted. A plurality of railways are passing between the piers 13 and 13 or between the abutments 12 and 13.

架替工事は、撤去工程と新設工程が錯綜するため、複雑になる。また、架替工事では、必ず、鉄道運行状況を考慮する必要がある。例えば、列車の運行のない夜間に架替工事を行なうとしても、資機材の搬入搬出に時間を要し、仮設設備等も毎回撤去する必要があり、橋梁下での作業は事実上困難である。 Reconstruction work is complicated because the removal process and new installation process are intertwined. In addition, when rebuilding a bridge, it is necessary to consider the railway operating conditions. For example, even if bridge reconstruction work is carried out at night when trains are not operating, it takes time to bring in and remove materials and equipment, and temporary equipment must be removed each time, making it virtually difficult to work under the bridge. .

上記施工条件下では、橋梁下での作業は可能な限りないことが好ましい。 Under the above construction conditions, it is preferable that there be as little work under the bridge as possible.

~特徴的構成~
本実施形態に係る架替工法は、特徴的構成を有するシステムにより行われる。
~Characteristic composition~
The rebuilding method according to this embodiment is performed by a system having a characteristic configuration.

図1は、本システムの断面図である。本システムは、既設橋梁10(図12参照)と新設橋梁20(図8参照)とを接続する接続機構30とを有する。接続機構30は、第1接続手段31と第2接続手段32とが接続されることにより、形成される。 FIG. 1 is a cross-sectional view of the system. This system includes a connection mechanism 30 that connects the existing bridge 10 (see FIG. 12) and the new bridge 20 (see FIG. 8). The connection mechanism 30 is formed by connecting the first connection means 31 and the second connection means 32.

第1接続手段31は、橋軸方向にレール状に延設される構造となっている。2本の第1接続手段31,31が新設橋梁上部構造21の下面側において橋軸方向に延設されている(後述する図4参照)。 The first connecting means 31 has a structure that extends in the bridge axis direction in the form of a rail. Two first connecting means 31, 31 extend in the bridge axis direction on the lower surface side of the newly constructed bridge superstructure 21 (see FIG. 4, which will be described later).

第2接続手段32は吊ロッドである。吊ロッド32は、一端が既設撤去対象と連結されて吊支持可能であるとともに、他端が第1接続手段31上を摺動可能に第1接続手段31と接続している。吊ロッド32は長さ調整により既設撤去対象を吊上可能である。 The second connecting means 32 is a hanging rod. The hanging rod 32 has one end connected to the existing object to be removed so that it can be suspended and supported, and the other end connected to the first connecting means 31 so as to be able to slide on the first connecting means 31 . The length of the hanging rod 32 can be adjusted to lift up the existing object to be removed.

図1の例では、吊ロッド32は上側の吊ロッド33と下側の吊ロッド34とからなる。 In the example of FIG. 1, the hanging rod 32 consists of an upper hanging rod 33 and a lower hanging rod 34.

吊ロッド33の上端は第1接続手段31と摺動可能に接続されている。吊ロッド33の下端は、吊桁35に結合している。第1接続手段31と吊ロッド33との接続機構は、例えばJES継手による嵌合構造である。 The upper end of the hanging rod 33 is slidably connected to the first connecting means 31. The lower end of the hanging rod 33 is coupled to a hanging beam 35. The connection mechanism between the first connection means 31 and the hanging rod 33 is a fitting structure using, for example, a JES joint.

図2Aは接続機構の実施例であるJES継手である。JES継手は、断面C状の一端が瘤状となっており、互いのC状空間に瘤状を挿入し合うことにより、継手同士が嵌合している。図2Bは接続機構の変形例である。断面馬蹄形状空間を有する第1接続手段31内を吊ロッド33上端の円筒状係合部が摺動する。吊ロッド33は橋軸方向に幅を有していてもよい。 FIG. 2A is a JES joint, which is an example of a connection mechanism. JES joints have a C-shaped cross section with a knob at one end, and the joints are fitted together by inserting the knobs into each other's C-shaped spaces. FIG. 2B shows a modification of the connection mechanism. A cylindrical engagement portion at the upper end of the hanging rod 33 slides within the first connecting means 31 having a space with a horseshoe shape in cross section. The suspension rod 33 may have a width in the bridge axis direction.

図3は接続機構の別の変形例である。溝31が新設橋梁上部構造21の下面側において橋軸方向に延設されている。言い換えると、溝を有する第1接続手段31が新設橋梁上部構造21の下面側において橋軸方向に延びるように埋設されている。 FIG. 3 shows another modification of the connection mechanism. A groove 31 extends in the bridge axis direction on the lower surface side of the newly constructed bridge superstructure 21. In other words, the first connecting means 31 having a groove is buried in the lower surface side of the newly constructed bridge superstructure 21 so as to extend in the bridge axis direction.

吊ロッド34の上端はジャッキ36を介して吊桁35に係合している。吊ロッド34の下端は、既設撤去対象(たとえば既設橋梁上部構造の撤去相当部11A)下面に設けられる留具37を介して既設撤去対象に係合している。 The upper end of the hanging rod 34 is engaged with a hanging beam 35 via a jack 36. The lower end of the suspension rod 34 is engaged with the existing object to be removed via a fastener 37 provided on the lower surface of the existing object to be removed (for example, the removed portion 11A of the existing bridge superstructure).

なお、留具37による係合に代えて、後施工アンカによる結合とすることにより、橋梁下での作業を可能な限り減らすことができる。 In addition, by replacing the engagement with the fasteners 37 with connection using post-installed anchors, the work under the bridge can be reduced as much as possible.

吊桁35は橋軸直交方向を長手方向とするように配置され、接続機構30は吊桁35の両端2か所に設けられている。すなわち、吊ロッド32,32は吊桁35を介して連結している。吊桁35を介することで、既設撤去対象の吊位置を調整できる。 The suspension girder 35 is arranged so that its longitudinal direction is perpendicular to the bridge axis, and the connection mechanisms 30 are provided at two locations on both ends of the suspension girder 35. That is, the suspension rods 32, 32 are connected via the suspension girder 35. By using the hanging girder 35, the hanging position of the existing equipment to be removed can be adjusted.

ジャッキ36は例えば、センターホールジャッキである。ジャッキ36により吊ロッド34を緊張することで、既設撤去対象を吊上可能となる。 The jack 36 is, for example, a center hole jack. By tensioning the lifting rod 34 with the jack 36, the existing object to be removed can be lifted up.

各構成間の相互作用については、架替工事手順において説明する。 The interaction between each component will be explained in the rebuilding procedure.

~架替工事手順~
図4および図5は、既設上部構造撤去例の斜視図である。架替工事は、撤去工程と新設工程とを含む。とくに、本願手順では、撤去工程と新設工程とが相互連動していることを特徴とする。
~Reconstruction work procedure~
4 and 5 are perspective views of an example of removing the existing superstructure. The rebuilding work includes a removal process and a new installation process. In particular, the present procedure is characterized in that the removal process and the new installation process are interlocked with each other.

予め、既設橋梁上部構造11外部において、新設橋梁上部構造21を構築しておく。桁長を調整できるように、両端に架設桁を延設してもよい。既設橋梁上部構造11上面を搬路として、新設橋梁上部構造21を搬入する。 A new bridge superstructure 21 is constructed in advance outside the existing bridge superstructure 11. Erection girders may be extended at both ends so that the girder length can be adjusted. The new bridge superstructure 21 is carried in using the upper surface of the existing bridge superstructure 11 as a transport path.

もしくは、既設橋梁上部構造11外部より新設橋梁上部構造21の構成部品を搬入し、既設橋梁上部構造11上面において新設橋梁上部構造21を構築してもよい。なお、新設橋梁上部構造21との搬入とは、構成部品の搬入も含む。 Alternatively, the components of the new bridge superstructure 21 may be brought in from outside the existing bridge superstructure 11, and the new bridge superstructure 21 may be constructed on the top surface of the existing bridge superstructure 11. Note that the delivery of the newly constructed bridge superstructure 21 also includes the delivery of component parts.

既設橋梁上部構造11の両端であって、既設橋台12の橋軸直角方向両脇の地山(半透明で図示)に仮設ベント41,41を設ける。なお、仮設ベント41,41間隔を広げることにより、既設橋梁上部構造11上面にアクセス容易となる。 Temporary vents 41, 41 are provided at both ends of the existing bridge superstructure 11 and in the ground (shown as semi-transparent) on both sides of the existing bridge abutment 12 in the direction perpendicular to the bridge axis. In addition, by widening the interval between the temporary vents 41 and 41, it becomes easier to access the upper surface of the existing bridge superstructure 11.

仮設ベント41,41により新設橋梁上部構造21の両端を仮支持しながら、ジャッキアップし、既設橋梁上部構造11の上部に、新設橋梁上部構造21を仮設する。なお、新設橋梁上部構造21幅を既設橋梁上部構造残部11幅より広くしている。 The new bridge superstructure 21 is temporarily installed on top of the existing bridge superstructure 11 by jacking it up while temporarily supporting both ends of the new bridge superstructure 21 with the temporary vents 41 , 41 . Note that the width of the new bridge superstructure 21 is made wider than the width of the remaining bridge superstructure 11 of the existing bridge.

次いで、既設橋梁上部構造撤去相当部11Aにおいて接続機構30を介して、既設橋梁上部構造撤去相当部11Aと新設橋梁上部構造21とを接続する(図1参照)。その結果、既設橋梁上部構造撤去相当部11Aは新設橋梁上部構造21に吊支持される。なお、安定性の観点より長手物の吊支持は4点以上が一般的である(図4参照)。 Next, the existing bridge superstructure removal equivalent portion 11A and the new bridge superstructure 21 are connected via the connection mechanism 30 in the existing bridge superstructure removal equivalent portion 11A (see FIG. 1). As a result, the existing bridge superstructure removed portion 11A is suspended and supported by the new bridge superstructure 21. Note that from the viewpoint of stability, long objects are generally suspended from four or more points (see Fig. 4).

吊支持状態において、既設橋梁上部構造撤去相当部11Aを切断し撤去ブロックとする。ジャッキ36を介して撤去ブロック11Aを吊り上げ、撤去ブロック11A下面が既設橋梁上部構造残部11B上面位置より高くなるようにする(図4参照)。これにより、撤去ブロック11Aは摺動可能となる。 In the suspended and supported state, the portion 11A corresponding to removal of the existing bridge superstructure is cut to form a removal block. The removed block 11A is lifted up using the jack 36, so that the lower surface of the removed block 11A is higher than the upper surface of the remaining part of the existing bridge superstructure 11B (see FIG. 4). Thereby, the removal block 11A becomes slidable.

既設橋梁上部構造撤去相当部11Aに隣接する既設橋梁上部構造残部11Bに搬出台車42を待機させておく。第1接続手段31を介して撤去ブロック11Aを摺動させ、ジャッキ36を介して撤去ブロック11Aを搬出台車42に吊り降ろす(図5参照)。 The unloading cart 42 is kept on standby in the remaining portion of the existing bridge superstructure 11B adjacent to the portion 11A corresponding to removal of the existing bridge superstructure. The removal block 11A is slid through the first connecting means 31, and the removal block 11A is lowered onto the carry-out cart 42 through the jack 36 (see FIG. 5).

既設橋梁上部構造残部11B上面を搬出台車42の搬路とし、撤去ブロック11Aを搬出する。このとき仮設ベント41,41間隔が充分に広ければ、仮設ベント41,41間より外部に搬出できる。 The upper surface of the remaining part 11B of the existing bridge superstructure is used as a transportation route for the carrying cart 42, and the removed block 11A is carried out. At this time, if the space between the temporary vents 41 and 41 is sufficiently wide, the material can be carried out from between the temporary vents 41 and 41.

図6は既設下部構造撤去例の斜視図である。既設橋梁上部構造撤去相当部11Aの一部を搬出し、開口ができれば、上方より既設橋脚撤去相当部13Aにアクセス可能となる。 FIG. 6 is a perspective view of an example of removing the existing lower structure. If a part of the existing bridge superstructure removal equivalent part 11A is carried out and an opening is made, it will be possible to access the existing bridge pier removal equivalent part 13A from above.

接続機構30を介して、既設橋脚撤去相当部13Aと新設橋梁上部構造21とを接続する結果、既設橋脚撤去相当部13Aは新設橋梁上部構造21に吊支持される。なお、図示のように2点支持としてもよい。 As a result of connecting the existing bridge pier removal equivalent portion 13A and the new bridge superstructure 21 via the connection mechanism 30, the existing bridge pier removal equivalent portion 13A is suspended and supported by the new bridge superstructure 21. Note that it may be supported at two points as shown in the figure.

吊支持状態において、既設橋脚撤去相当部13Aを切断し撤去ブロックとする。撤去ブロック11Aを搬出した手順にて、第1接続手段31を介して撤去ブロック13Aを摺動させ搬出する。 In the suspended support state, the existing bridge pier removal equivalent portion 13A is cut to form a removal block. The removal block 13A is slid and carried out via the first connecting means 31 in the same manner as the removal block 11A was carried out.

撤去ブロック11Aおよび撤去ブロック13Aを搬出した手順を繰り返し、既設橋梁上部構造残部11Bや既設橋脚残部13Bを撤去する。 The procedure for carrying out the removal block 11A and the removal block 13A is repeated to remove the existing bridge superstructure remaining portion 11B and the existing bridge pier remaining portion 13B.

図7は新設上部構造架設例の斜視図である。既設橋梁上部構造11および既設橋脚13を全て撤去した状態において、第1接続手段31と第2接続手段32との接続を解除し、第2接続手段32を取り外す。そして、仮設ベント41,41により新設橋梁上部構造21の両端を仮支持しながら、ジャッキダウンする。桁長を調整するように、両端架設桁を外す。新設橋梁上部構造21を降下させ、既設橋台12,12の所定位置に本設する。 FIG. 7 is a perspective view of an example of constructing a new superstructure. With the existing bridge superstructure 11 and the existing bridge piers 13 all removed, the connection between the first connecting means 31 and the second connecting means 32 is released, and the second connecting means 32 is removed. Then, the new bridge superstructure 21 is jacked down while temporarily supporting both ends of the bridge superstructure 21 using the temporary vents 41, 41. Remove the girders at both ends to adjust the girder length. The new bridge superstructure 21 is lowered and permanently installed at a predetermined position on the existing bridge abutments 12, 12.

~効果~
上記手順を概略化すると、撤去対象の吊支持→切断→吊り上げ→摺動→既設橋梁上部構造上面への吊り降ろし→搬出の繰り返しである。上記手順において、原則として橋梁下での作業はなく、既設橋梁上部構造11上面を利用してほとんどの作業を行うことができる。
~Effect~
To summarize the above procedure, it is a repetition of suspension support of the object to be removed → cutting → lifting → sliding → lifting and lowering to the top surface of the existing bridge superstructure → carrying out. In the above procedure, in principle, there is no work under the bridge, and most of the work can be performed using the top surface of the existing bridge superstructure 11.

すなわち、鉄道運行状況に影響されずに、架替工事を行なうことができる。尤も、施工実務では安全優先の観点から、実際は、列車運行のない夜間に行なわれるものと思われる。しかし、夜間施工に限定されたとしても、列車運行中も既設橋梁上部構造上面にて準備作業ができ、また、線路への資機材搬入搬出や仮設工事がないことから、大幅な工期短縮、安全性の確保が期待でき、その結果、コスト削減となる。 In other words, rebuilding work can be carried out without being affected by railway operating conditions. However, due to safety concerns in construction, it is believed that the work will actually be carried out at night when there are no trains running. However, even if construction is limited to nighttime work, preparatory work can be done on the top of the existing bridge superstructure while trains are in operation, and there is no need to carry materials and equipment onto the tracks or perform temporary construction, significantly shortening the construction period and ensuring safety. It is expected that the performance will be ensured, and as a result, the cost will be reduced.

また、撤去工程と新設工程とが相互連動している、言い換えると、新設橋梁上部構造21の仮支持状態を既設橋梁上部構造11撤去および既設橋脚13撤去の仮設設備として利用できるため、この点でも工期短縮およびコスト削減が期待できる。 In addition, the removal process and the new installation process are interlocked, in other words, the temporarily supported state of the newly constructed bridge superstructure 21 can be used as temporary equipment for the removal of the existing bridge superstructure 11 and the existing bridge pier 13, so this also applies in this respect. It is expected to shorten the construction period and reduce costs.

このように、本実施形態に係る架替工法は、橋梁交差方向に複数の鉄道が並走するような橋梁下での施工条件が厳しい場合にも適用可能である。 In this way, the rebuilding method according to the present embodiment is applicable even when construction conditions under a bridge are severe, such as when a plurality of railways run parallel to each other in the bridge crossing direction.

~本設後の第1接続手段の利用~
図8は、本発明より架け替えされた新設橋梁20の例である。接続機構30のうち第2接続手段32は取り外すが、本設後も第1接続手段31は新設橋梁上部構造21の下面側に設置されている状態を維持する。すなわち、第1接続手段31は、新設橋梁20の一部である。
~Using the first connection method after installation~
FIG. 8 is an example of a newly constructed bridge 20 rebuilt according to the present invention. Although the second connecting means 32 of the connecting mechanism 30 is removed, the first connecting means 31 remains installed on the lower surface side of the newly constructed bridge superstructure 21 even after the permanent installation. That is, the first connecting means 31 is a part of the newly constructed bridge 20.

新設橋梁上部構造21の下面側の点検やメンテナンスの際は、第1接続手段31を利用して、作業ゴンドラ(図示省略)を吊り下げて摺動させる。これにより、点検やメンテナンスのための仮設工事が大幅に軽減され、点検やメンテナンスが容易となる。 When inspecting or maintaining the lower surface of the newly constructed bridge superstructure 21, the first connecting means 31 is used to suspend and slide a working gondola (not shown). This greatly reduces the need for temporary construction for inspection and maintenance, making inspection and maintenance easier.

~変形例~
本願発明の理解を容易にするために、一例として上記実施形態について説明したが、本願発明は上記実施形態に限定されず、本発明の技術思想の範囲で種々の変形が可能である。
~Variation example~
In order to facilitate understanding of the present invention, the above embodiment has been described as an example; however, the present invention is not limited to the above embodiment, and various modifications can be made within the scope of the technical idea of the present invention.

図9は既設上部構造撤去変形例の斜視図である。上記実施形態では、撤去ブロック11Aを吊り上げ(図4参照)後、摺動させ、搬出台車42に吊り降ろし、(図5参照)、既設橋梁上部構造残部11B上面を搬出台車42の搬路として搬出しているのに対し、変形例では、撤去ブロック11Aを吊り上げ(図4参照)後、第1接続手段31末端まで摺動させ、吊り降ろし、既設橋梁10端部より搬出する。 FIG. 9 is a perspective view of a modified example of removing the existing superstructure. In the embodiment described above, the removal block 11A is lifted up (see FIG. 4), then slid and lowered onto the carry-out cart 42 (see FIG. 5), and the upper surface of the remaining part 11B of the existing bridge superstructure is used as a transport path for the carry-out cart 42. On the other hand, in the modified example, after lifting the removal block 11A (see FIG. 4), it is slid to the end of the first connecting means 31, lowered, and carried out from the end of the existing bridge 10.

すなわち、変形例においては、既設橋梁上部構造残部11B上面を搬路として利用しない。これにより、既設橋梁上部構造残部11B上面を作業スペースとして有効利用でき、施工性や安全性が更に向上する。 That is, in the modified example, the upper surface of the existing bridge superstructure remaining portion 11B is not used as a transport path. As a result, the upper surface of the existing bridge superstructure remaining portion 11B can be effectively used as a work space, further improving workability and safety.

図10は別の既設上部構造撤去変形例の斜視図である。上記実施形態では、既設橋梁上部構造11および既設橋脚13については撤去し、既設橋台12については再利用しているのに対し、変形例では、既設橋台12も撤去し、新設橋台22を設ける。 FIG. 10 is a perspective view of another modified example of removing the existing superstructure. In the above embodiment, the existing bridge superstructure 11 and the existing bridge piers 13 are removed and the existing bridge abutments 12 are reused, whereas in the modified example, the existing bridge abutments 12 are also removed and new bridge abutments 22 are provided.

まず、既設橋台12,12の橋軸方向外側に新設橋台22,22を設ける。新設橋台22,22に仮設ベント41,41を設け、新設橋梁上部構造21の両端を仮支持する。 First, new abutments 22, 22 are provided outside the existing abutments 12, 12 in the bridge axis direction. Temporary vents 41, 41 are provided on the newly constructed bridge abutments 22, 22 to temporarily support both ends of the newly constructed bridge superstructure 21.

撤去ブロック11Aおよび撤去ブロック13Aを搬出した手順にて、既設橋台12を切断して撤去ブロックとし、第1接続手段31を介して撤去ブロック摺動させ搬出する。このとき、撤去ブロックを新設橋台22まで摺動させ、新設橋台22から搬出すると、既設橋梁上部構造残部11B全面を作業スペースとして有効利用できる。 In the procedure for carrying out the removal block 11A and the removal block 13A, the existing bridge abutment 12 is cut to form a removal block, and the removal block is slid and carried out via the first connecting means 31. At this time, by sliding the removed block to the new abutment 22 and carrying it out from the new abutment 22, the entire remaining portion 11B of the existing bridge superstructure can be effectively used as a work space.

既設橋梁上部構造11および既設橋梁上部構造12,13を全て撤去した状態において、新設橋梁上部構造21を降下させ、新設橋台22,22の所定位置に本設する。 With the existing bridge superstructure 11 and the existing bridge superstructures 12 and 13 all removed, the new bridge superstructure 21 is lowered and permanently installed at a predetermined position on the new bridge abutments 22 and 22.

なお、新設橋台22幅を既設橋台12幅より広くするとともに、新設橋梁上部構造21幅を既設橋梁上部構造残部11B幅より広くすると、広い搬出スペースを確保でき、施工性がさらに向上する。 In addition, by making the width of the new bridge abutment 22 wider than the width of the existing bridge abutment 12, and making the width of the new bridge superstructure 21 wider than the width of the remaining part 11B of the existing bridge superstructure, a wide unloading space can be secured and construction efficiency is further improved.

図11は別の既設上部構造撤去変形例の斜視図である。撤去ブロック11Aを吊り上げ後、摺動させ、隣接する既設橋梁上部構造残部11Bに吊り降ろし、既設橋梁上部構造残部11B上で小割し、搬出する。 FIG. 11 is a perspective view of another modified example of removing the existing superstructure. After lifting the removed block 11A, it is slid and lowered onto the remaining portion of the existing bridge superstructure 11B adjacent to it, and is divided into small pieces on the remaining portion of the existing bridge superstructure 11B and carried out.

図12に示す既設橋梁例では、既設橋脚13の存在を前提としたが、本願発明は橋脚のない既設橋梁にも適用できる。その場合、当然、既設橋脚13の撤去工程は不要である。すなわち、本願発明において、既設橋脚13撤去は必須でない。 Although the example of the existing bridge shown in FIG. 12 is based on the existence of the existing bridge piers 13, the present invention can also be applied to existing bridges without piers. In that case, the process of removing the existing pier 13 is naturally unnecessary. That is, in the present invention, removal of the existing pier 13 is not essential.

ところで、半世紀以上前に架けられた既設橋梁は一般に径間長が短いが、断面構造や材料を検討したり、PC橋、アーチ橋、斜張橋、吊橋としたり、適宜、近年の技術を用いることで、新設橋梁の径間長を長くできる。その結果、新設橋脚は不要である。 By the way, existing bridges built more than half a century ago generally have short span lengths, but we have examined the cross-sectional structure and materials, and have used modern technology as appropriate, such as using PC bridges, arch bridges, cable-stayed bridges, and suspension bridges. By using it, the span length of new bridges can be increased. As a result, new piers are not required.

上記実施形態では、橋梁下での施工条件が厳しい例として、橋梁交差方向に複数の鉄道が並走する(図12参照)場合を挙げたが、橋梁下にて主要幹線道路が交差する場合や、河川が交差し、流れが速く台船を停泊困難な場合等においても好適である。 In the above embodiment, as an example of severe construction conditions under a bridge, the case where multiple railways run parallel in the direction of crossing the bridge (see Fig. 12) was given, but there are also cases where major arterial roads intersect under the bridge. It is also suitable in cases where rivers intersect and the current is fast and it is difficult to anchor the barge.

図12に示す既設橋梁例では、道路橋としたが、鉄道橋でもよい。 In the example of the existing bridge shown in FIG. 12, it is a road bridge, but it may also be a railway bridge.

10 既設橋梁
11 既設橋梁上部構造
12 既設橋台(下部構造)
13 既設橋脚(下部構造)
20 新設橋梁
11 新設橋梁上部構造
12 既設橋台(下部構造)
30 接続機構
31 第1接続手段(レール状)
32 第2接続手段(吊ロッド)
33 上側吊ロッド
33 下側吊ロッド
35 吊桁
36 ジャッキ
37 留具
41 仮設ベント
42 搬出台車
10 Existing bridge 11 Existing bridge superstructure 12 Existing bridge abutment (substructure)
13 Existing pier (substructure)
20 New bridge 11 New bridge superstructure 12 Existing bridge abutment (substructure)
30 Connection mechanism 31 First connection means (rail type)
32 Second connection means (hanging rod)
33 Upper hanging rod 33 Lower hanging rod 35 Hanging girder 36 Jack 37 Fastener 41 Temporary vent 42 Carrying out trolley

Claims (6)

既設橋梁上部構造は既設橋梁下部構造に支持されており、
新設橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられており、
既設橋梁上部構造上面を搬路として、前記新設橋梁上部構造を搬入し、
既設橋梁上部構造の上部に、前記新設橋梁上部構造を仮設し、前記新設橋梁上部構造の両端を仮支持し、
前記第1接続手段と第2接続手段とを接続するとともに、前記第2接続手段を介して、前記既設橋梁上部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、
前記既設橋梁上部構造の撤去相当部を切断し、
前記既設橋梁上部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させて、撤去し、
複数の前記既設橋梁上部構造の撤去相当部の撤去を繰り返し、前記既設橋梁上部構造を撤去し、
前記新設橋梁上部構造を降下させて本設する工法であって、
前記既設橋梁上部構造の残部は前記既設橋梁下部構造に支持された状態で、
前記既設橋梁上部構造の撤去相当部の撤去において、
前記既設橋梁上部構造の残部上に吊り降ろし、
前記既設橋梁上部構造の残部上面を搬路とする
ことを特徴とする橋梁の架替工法。
The existing bridge superstructure is supported by the existing bridge substructure.
A first connection means extending in the bridge axis direction is provided on the lower surface side of the new bridge superstructure,
Transporting the new bridge superstructure using the top surface of the existing bridge superstructure as a transportation route,
Temporarily installing the new bridge superstructure on top of the existing bridge superstructure, temporarily supporting both ends of the new bridge superstructure,
connecting the first connecting means and the second connecting means, and suspending and supporting the removed portion of the existing bridge superstructure on the new bridge superstructure via the second connecting means;
Cut off the portion of the existing bridge superstructure that corresponds to the removal,
Lifting up a portion of the existing bridge superstructure that corresponds to removal, and further sliding it through the first connecting means and removing it;
Repeating the removal of the portions of the plurality of existing bridge superstructures that correspond to the removal, and removing the existing bridge superstructures;
A construction method in which the newly constructed bridge superstructure is lowered and permanently installed,
The remaining part of the existing bridge superstructure is supported by the existing bridge substructure,
In the removal of the portion equivalent to the removal of the existing bridge superstructure,
suspended over the remainder of the existing bridge superstructure;
The upper surface of the remaining portion of the existing bridge superstructure will be used as the transportation route.
A bridge reconstruction method characterized by:
既設橋梁上部構造は既設橋梁下部構造に支持されており、
新設橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられており、
既設橋梁上部構造上面を搬路として、前記新設橋梁上部構造を搬入し、
既設橋梁上部構造の上部に、前記新設橋梁上部構造を仮設し、前記新設橋梁上部構造の両端を仮支持し、
前記第1接続手段と第2接続手段とを接続するとともに、前記第2接続手段を介して、前記既設橋梁上部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、
前記既設橋梁上部構造の撤去相当部を切断し、
前記既設橋梁上部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させて、撤去し、
複数の前記既設橋梁上部構造の撤去相当部の撤去を繰り返し、前記既設橋梁上部構造を撤去し、
前記新設橋梁上部構造を降下させて本設する工法であって、
前記既設橋梁上部構造の残部は前記既設橋梁下部構造に支持された状態で、
前記既設橋梁上部構造の撤去相当部の撤去において、
摺動状態にて前記既設橋梁上部構造の残部上を通過させて既設橋梁の外部に搬出する
ことを特徴とする橋梁の架替工法。
The existing bridge superstructure is supported by the existing bridge substructure.
A first connection means extending in the bridge axis direction is provided on the lower surface side of the new bridge superstructure,
Transporting the new bridge superstructure using the top surface of the existing bridge superstructure as a transportation route,
Temporarily installing the new bridge superstructure on top of the existing bridge superstructure, temporarily supporting both ends of the new bridge superstructure,
connecting the first connecting means and the second connecting means, and suspending and supporting the removed portion of the existing bridge superstructure on the new bridge superstructure via the second connecting means;
Cut off the portion of the existing bridge superstructure that corresponds to the removal,
Lifting up a portion of the existing bridge superstructure that corresponds to removal, and further sliding it through the first connecting means and removing it;
Repeating the removal of the portions of the plurality of existing bridge superstructures that correspond to the removal, and removing the existing bridge superstructures;
A construction method in which the newly constructed bridge superstructure is lowered and permanently installed,
The remaining part of the existing bridge superstructure is supported by the existing bridge substructure,
In the removal of the portion equivalent to the removal of the existing bridge superstructure,
Pass it over the remaining part of the existing bridge superstructure in a sliding state and carry it out to the outside of the existing bridge.
A bridge reconstruction method characterized by:
前記第2接続手段を介して、前記既設橋梁下部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、
前記既設橋梁下部構造の撤去相当部を切断し、
前記既設橋梁下部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させ、撤去し、
複数の前記既設橋梁下部構造の撤去相当部の撤去を繰り返し、前記既設橋梁下部構造を撤去する
ことを特徴とする請求項1または2いずれか記載の橋梁の架替工法。
suspending and supporting the removed portion of the existing bridge lower structure on the new bridge upper structure via the second connection means;
Cut off the portion of the existing bridge substructure that corresponds to the removal,
Lifting up a portion of the existing bridge substructure equivalent to removal, further sliding it via the first connecting means, and removing it;
3. The bridge reconstruction method according to claim 1, wherein the existing bridge substructures are removed by repeatedly removing portions of a plurality of the existing bridge substructures.
前記第2接続手段は、橋軸直交方向に2以上設けられ、
前記第2接続手段同士は、吊桁を介して連結されている
ことを特徴とする請求項1~3いずれか記載の橋梁の架替工法。
The second connecting means is provided at least two in a direction perpendicular to the bridge axis,
4. The bridge reconstruction method according to claim 1 , wherein the second connecting means are connected to each other via a hanging girder.
前記新設橋梁上部構造本設後も、前記第1接続手段が設けられた状態を維持する
ことを特徴とする請求項1~4いずれか記載の橋梁の架替工法。
5. The bridge reconstruction method according to claim 1, wherein the first connecting means remains installed even after the new bridge superstructure is permanently installed.
前記既設橋梁上部構造は、橋軸交差方向に延設される線路または道路の上に設けられている
ことを特徴とする請求項1~5いずれか記載の橋梁の架替工法。
6. The method for rebuilding a bridge according to claim 1, wherein the existing bridge superstructure is installed on a railroad or road extending in a direction crossing the bridge axis.
JP2019173549A 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure Active JP7368685B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019173549A JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019173549A JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Publications (2)

Publication Number Publication Date
JP2021050512A JP2021050512A (en) 2021-04-01
JP7368685B2 true JP7368685B2 (en) 2023-10-25

Family

ID=75157300

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019173549A Active JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Country Status (1)

Country Link
JP (1) JP7368685B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7215633B1 (en) * 2022-10-14 2023-01-31 Jfeエンジニアリング株式会社 Bridge replacement device and bridge replacement method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002332613A (en) 2002-06-25 2002-11-22 Nippon Sharyo Seizo Kaisha Ltd Bridge removal working machine
JP2003253623A (en) 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2006265884A (en) 2005-03-23 2006-10-05 Ps Mitsubishi Construction Co Ltd Method of removing existing pier of viaduct
JP2007321476A (en) 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP2009052306A (en) 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2014015808A (en) 2012-07-11 2014-01-30 Mitsui Eng & Shipbuild Co Ltd Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction
JP2014066007A (en) 2012-09-24 2014-04-17 Nexco-East Engineering Co Ltd Removal method of existent bridge and renewal method of existent bridge
US20140251936A1 (en) 2013-03-06 2014-09-11 Mark Carney Bridge span replacement system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003253623A (en) 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2002332613A (en) 2002-06-25 2002-11-22 Nippon Sharyo Seizo Kaisha Ltd Bridge removal working machine
JP2006265884A (en) 2005-03-23 2006-10-05 Ps Mitsubishi Construction Co Ltd Method of removing existing pier of viaduct
JP2007321476A (en) 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP2009052306A (en) 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2014015808A (en) 2012-07-11 2014-01-30 Mitsui Eng & Shipbuild Co Ltd Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction
JP2014066007A (en) 2012-09-24 2014-04-17 Nexco-East Engineering Co Ltd Removal method of existent bridge and renewal method of existent bridge
US20140251936A1 (en) 2013-03-06 2014-09-11 Mark Carney Bridge span replacement system

Also Published As

Publication number Publication date
JP2021050512A (en) 2021-04-01

Similar Documents

Publication Publication Date Title
US11634877B2 (en) Method for removal of temporary support system for road bridge pre-fabricated small box girder-type concealed bent cap, and equipment therefor
CN100464026C (en) Girder-exchange construction method for existing railway bridge by successively incremeantal launching framework process
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
JP2009052306A (en) Construction method for replacing bridge girder
JP3728657B2 (en) Railway bridge replacement method
JP2003253623A (en) Rebuilding construction method for bridge beam
JP7368685B2 (en) Bridge reconstruction method and bridge superstructure
KR100454406B1 (en) Method and apparatus for changing steel bridge of supporting rail into concrete bridge using temporary bent
RU2495184C1 (en) Method to disassemble bridge span and device for realisation of this method
CN102733321B (en) Suspension bracket system for existing bridge reinforcing and building method of suspension bracket system
RU2293810C1 (en) Reinforced concrete sleeper
KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
KR20100021874A (en) Method for removing, installing and replacing an upper structure of bridge, and lifting apparatus and transportation vehicle of the upper structure of bridge for the method
KR101234090B1 (en) Method for changing girder of railway plate girder bridge
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
CN106192761A (en) A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section
JP4424744B2 (en) Bridge replacement method
KR100865752B1 (en) Shift method of bridge bearing of railroad
CN114875813B (en) Construction equipment and construction method for dismantling and rebuilding reinforced concrete steel frame arch bridge
CN114808772A (en) Method for decomposing, reinforcing and dismantling beam lattice over existing railway continuous beam bridge
JP2007321476A (en) Bridge and its construction method
CN113026539A (en) Upper connecting rail structure of integral cast-in-place frame bridge and construction method
CN102444293A (en) Cutting and slipping method for extension of existing large-span truss structure
KR102557944B1 (en) Demolition method of bridge superstructure using temporary through truss

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220913

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230421

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230704

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230913

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230922

R150 Certificate of patent or registration of utility model

Ref document number: 7368685

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150