CN106192761A - A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section - Google Patents

A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section Download PDF

Info

Publication number
CN106192761A
CN106192761A CN201610668987.3A CN201610668987A CN106192761A CN 106192761 A CN106192761 A CN 106192761A CN 201610668987 A CN201610668987 A CN 201610668987A CN 106192761 A CN106192761 A CN 106192761A
Authority
CN
China
Prior art keywords
girder
plug
mobile formwork
nose girder
tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610668987.3A
Other languages
Chinese (zh)
Other versions
CN106192761B (en
Inventor
李红斌
周烽
尹育文
谌荣华
李祖勇
黄文俊
苏良平
李伟清
曹智波
匡旭
苗林峰
黄敏
杨磊
张正刚
张琴
康晖
何智超
仇建坤
刘汉华
熊宾松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NO 3 ENGINEERING Co Ltd ZHONGTIE 25 BUREAU GROUP
China Railway 25th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 25th Bureau Group Co Ltd
Original Assignee
NO 3 ENGINEERING Co Ltd ZHONGTIE 25 BUREAU GROUP
China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NO 3 ENGINEERING Co Ltd ZHONGTIE 25 BUREAU GROUP, China Railway 25th Bureau Group Co Ltd filed Critical NO 3 ENGINEERING Co Ltd ZHONGTIE 25 BUREAU GROUP
Priority to CN201610668987.3A priority Critical patent/CN106192761B/en
Publication of CN106192761A publication Critical patent/CN106192761A/en
Application granted granted Critical
Publication of CN106192761B publication Critical patent/CN106192761B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section, before mobile formwork assembly, girder bottom welding installs track advancing, and its position, physical dimension guide rail existing with nose girder are identical;After last a piece of beam makes, mobile formwork is moved in tunnel, progressively removes plug-in;After plug-in dismounting, exit in tunnel, more piecemeal remove mobile formwork nose girder, girder and, connect system and before, during and after supporting leg.The present invention is a kind of simple to operate, safe and reliable, method disassembling mobile formwork in bridge tunnel narrow short transition time section of low cost.

Description

A kind of method disassembling mobile formwork in bridge tunnel narrow short transition time section
Technical field
The present invention relates to a kind of method disassembling mobile formwork, particularly relate to one and disassemble shifting in bridge tunnel narrow short transition time section The method of dynamic model frame.
Background technology
The up self-propelled moveable formwork of DSZ32/900 type designs for the construction of special line for passenger trains double-line full span box, Mould bases uses girder to be placed in bridge floor top structure, utilizes beam-ends, bridge pier to install supporting leg, it is possible to upside-down mounting supporting leg voluntarily, has good Stability.Mould bases is mainly by girder system, plug-in, transverse-moving mechanism and locking mechanism, outer modular system, rear running mechanism, prop up afterwards Lower limb, middle support oil cylinder, front leg strut upper framework, suspension rod, lifting dolly, overhead traveling crane and 5t electric hoist, electric hydraulic system and auxiliary set The part composition, wherein: girder divides 1# girder, 2# girder, 3# girder three sections, wherein: 1# girder 12.9m, 2# girder, 3# master such as execute Beam is respectively 12.0m;Nose girder divides 1# nose girder, 2# nose girder, 3# nose girder three sections, length 11.0m respectively;Total length reaches 69.9m.Plug-in Plug-in including 1#, 2# is plug-in, 3# is plug-in, 4# is plug-in, 5# is plug-in, 6# is plug-in, 7# is plug-in and 8# is plug-in.
Conventional mobile formwork assembling method is: the common disassembling method of mobile formwork is after beam processed, will movement Mould bases moves to roadbed, carries out using crane to disassemble piecemeal on roadbed.
Being positioned between two tunnels for lower dam bridge, between the bridge tunnel of big mileage direction, changeover portion is less than 10m.For bridge between tunnel The erection of beam, typically uses support cast-in-place method or treats that after beam field is prefabricated tunnel holing through uses the methods such as Bridge Erector erection to carry out Bridge erection.Lower dam bridge pier body height is more than 50 meters, and up to 70 meters, construction site is high mountains and precipitous paths, and tunnel cannot shift to an earlier date Through, according to owner's Design of Construction Organization requirement, lower dam bridge uses mobile formwork cast-in-place construction, complete at mobile formwork beam After, mobile formwork to be solved is in the dismounting of bridge tunnel changeover portion less than 10 meters, disintegration problem.Bridge big mileage direction, lower dam bridge tunnel Between changeover portion (containing abutment) less than 10m, and DSZ32-900 mobile formwork body total length reaches 69.9m, due to construction site very Narrow, after setting a roof beam in place, disassemble mobile formwork difficulty at narrow short bridge tunnel changeover portion the biggest.
Summary of the invention
The technical problem to be solved is to provide the narrow at bridge tunnel of a kind of simple to operate, safe and reliable, low cost Short transition time section disassembles the method for mobile formwork.
In order to solve above-mentioned technical problem, the method disassembling mobile formwork in bridge tunnel narrow short transition time section that the present invention provides, Before mobile formwork assembly, girder bottom welding installs track advancing, and its position, physical dimension guide rail existing with nose girder are identical; After last a piece of beam makes, mobile formwork is moved in tunnel, progressively removes plug-in;After plug-in dismounting, from Exit in tunnel, more piecemeal remove mobile formwork nose girder, girder and, connect system and before, during and after supporting leg.
Specifically comprise the following steps that
(1), Main Girder Welding guide rail:
Before starting to set a roof beam in place, at girder corresponding to nose girder guide rail position welding same size, the guide rail of identical material, and with Nose girder guide rail carries out weldering even, it is desirable to the spreading guide rail that girder is welded with is on the prolongation straight line of nose girder guide rail, and smooth, straight;
(2), system is set a roof beam in place complete:
After system is set a roof beam in place, mobile formwork is in following state: 2#, 3# nose girder stretches in tunnel, and middle support oil cylinder is placed in Mobile formwork load is born at abutment top, and rear running mechanism is supported on and sets up on beam face, and front leg strut upper framework is placed in abutment top, By driving and the tourelle of front leg strut upper framework of rear travel structure, it is achieved mobile formwork moves forward and backward relative to tunnel;
(3), mobile formwork and front leg strut upper framework are moved:
Moving forward mould bases plug-in near abutment to 8#, then fixing middle supporting leg, uses overhead traveling crane toward direction handling in tunnel Front leg strut upper framework is to 3# nose girder medium position, and installs fixing;
(4), remove plug-in:
Utilize bridge tunnel changeover portion roadbed as job platform, install 50t crane each along line direction and changeover portion both sides Platform, carries out removing plug-in operation: first remove 8# plug-in, then mobile formwork reach, and 7# is plug-in near abutment;Remove 7# plug-in, Then mobile formwork reach, 6# is plug-in near abutment;Removing 6# plug-in, then mobile formwork reach, 5# is plug-in near abutment;With This analogizes, until all of plug-in whole dismountings are complete;
(5), beam body retreats:
After plug-in whole dismounting, mobile formwork beam body divides three steps to exit tunnel, only stays 3# nose girder in bridge tunnel roadbed mistake The section of crossing;
The first step: front leg strut upper framework remains stationary as, reverse starting rear support leg running mechanism, beam body retreats, until 3# leads Beam front end is moved at leading supporting leg upper framework;
Second step: supporting leg in fixing, overhead traveling crane handling front leg strut upper framework is to Abutment;
3rd step: fixing front leg strut upper framework, supporting leg in contraction, reverse starting rear support leg running mechanism, beam body retreats, directly Move at front leg strut upper framework to 3# nose girder rear end, i.e. 3# nose girder is positioned at bridge tunnel basement transition stage;
(6), nose girder is removed:
Use the 50t crane installed, after 3# nose girder is disassembled in lifting, 3# nose girder is transported outward transition, 2# nose girder by trailer Move forward at basement transition stage;After 2# nose girder is disassembled in lifting, by trailer, 2# nose girder being transported outward transition in time, 1# nose girder moves forward to At basement transition stage;After 1# nose girder is disassembled in lifting, in time 1# nose girder being transported outward transition, 3# girder moves forward at basement transition stage;
(7), girder and running gear are removed:
Using the 50t crane installed, after 3# girder is disassembled in lifting, transport outward transition by trailer in time, 2# girder moves forward To basement transition stage;After 2# girder is disassembled in lifting, transporting outward transition in time by trailer in time, 1# girder remains stationary as in situ; Bridge on crane, disassembles rear support leg and running mechanism, lifts 1# girder entrucking transition on bridge;
(8), running gear is removed:
Crane lifting rear support leg, rear running mechanism and front leg strut upper framework, cleaning lifting place, complete mobile formwork solution Body.
Using the method disassembling mobile formwork in bridge tunnel narrow short transition time section of technique scheme, its patented technology feature is such as Under:
1, the present invention is by being welded with track advancing on girder, by girder movement on track advancing, makes mobile mould Frame can move in tunnel, can remove nose girder, girder piecemeal, until completing the dismounting of whole section of mobile formwork;
2, mobile formwork disassembling operation in the present invention is suitable for straight tunnel, for curved tunnel, should be determined by measurement Whether curved section possesses the condition that mobile formwork straight line retreats;Really do not satisfy the requirements, can be by strengthening tunnel cross-section chi Very little solution mobile formwork problem of movement in tunnel;
3, the successful Application of the present invention, successfully solves the assembled via in place of narrow bridge tunnel changeover portion mobile formwork and beam processed After bridge tunnel changeover portion disintegrate problem, expanded the range of application of mobile formwork, for complicated topographical conditions ground iron leg The organization arrangement that road system is set a roof beam in place provides reference, is adapted to very much the construction that works to tight deadlines that mountain area system is set a roof beam in place;
4, the present invention only relies on the movement of " track advancing " set up on mobile formwork " front leg strut upper framework " girder and i.e. solves The problem that mobile formwork of having determined retreats traveling;Outstanding technology of tearing open is used i.e. to solve the problem that mobile formwork segmentation is removed, operation letter Single, safe and reliable, reduce equipment investment cost, not only save cost, in terms of energy-saving and emission-reduction and environmental conservation, effect is also Fairly obvious.
In sum, the present invention be a kind of simple to operate, safe and reliable, low cost disassemble shifting in bridge tunnel narrow short transition time section The method of dynamic model frame.
Accompanying drawing explanation
Fig. 1 is the process chart of the present invention.
Fig. 2 is the Main Girder Welding guide rail schematic diagram of the present invention.
Fig. 3 is that the system of the present invention is set a roof beam in place complete schematic diagram.
Fig. 4 is mobile mobile formwork and the schematic diagram of front leg strut upper framework of the present invention.
Fig. 5 be the present invention start remove plug-in schematic diagram.
Fig. 6 is the schematic diagram removing plug-in midway of the present invention.
Fig. 7 is the plug-in schematic diagram completed of dismounting of the present invention.
Fig. 8 is the schematic diagram of the beam body retrogressing first step of the present invention.
Fig. 9 is the schematic diagram of the beam body retrogressing second step of the present invention.
Figure 10 is the schematic diagram of beam body retrogressing the 3rd step of the present invention.
Figure 11 is that 2# nose girder when removing nose girder of the present invention moves forward to the schematic diagram at basement transition stage.
Figure 12 is that 1# nose girder when removing nose girder of the present invention moves forward to the schematic diagram at basement transition stage.
Figure 13 is that 3# girder when removing nose girder of the present invention moves forward to the schematic diagram at basement transition stage.
Figure 14 is that 2# girder when removing girder and running gear of the present invention moves forward to the schematic diagram at basement transition stage.
Figure 15 is the schematic diagram that when removing girder and running gear, 1# girder remains stationary as in situ of the present invention.
Figure 16 is the schematic diagram lifting 1# girder entrucking transition when removing girder and running gear on bridge of the present invention.
Figure 17 is the schematic diagram removing running gear of the present invention.
Detailed description of the invention
The invention will be further described with embodiment below in conjunction with the accompanying drawings.
Under the railway of cloud osmanthus, Bridge Pier abutment body average pier height in dam has exceeded 54.3m, according to Design of Construction Organization and scheme requirement, under Dam bridge uses the cast-in-place beam processed of DSZ32-900 mobile formwork.
Between the bridge tunnel of bridge big mileage direction, lower dam, changeover portion (containing abutment) is less than 10m, and DSZ32-900 mobile formwork body Total length reaches 69.9m, owing to construction site is the narrowest, after setting a roof beam in place, disassembles mobile mould at narrow short bridge tunnel changeover portion Frame difficulty is the biggest.
The up self-propelled moveable formwork of DSZ32/900 type designs for the construction of special line for passenger trains double-line full span box, Mould bases uses girder to be placed in bridge floor top structure, utilizes beam-ends, bridge pier to install supporting leg, it is possible to upside-down mounting supporting leg voluntarily, has good Stability.Mould bases mainly by girder system, plug-in, transverse-moving mechanism and locking mechanism, outer modular system, rear running mechanism 11, after Supporting leg 22, middle support oil cylinder 10, front leg strut upper framework 12, suspension rod, lifting dolly, overhead traveling crane 24 and 5t electric hoist, electric hydraulic system The part composition such as system and auxiliary equipment, wherein: girder divides 1# girder 1,2# girder 2,3# girder 3 three sections, wherein: 1# girder 12.9m, 2# girder, 3# girder are respectively 12.0m;Nose girder divides 1# nose girder 6,2# nose girder 7,3# nose girder 8 three sections, and length is respectively 11.0m;Total length reaches 69.9m.Plug-in include that 1# is plug-in 21,2# is plug-in 20,3# is plug-in 19,4# is plug-in 18,5# is plug-in 17, outside 6# Extension 16,7# plug-in 15 and 8# plug-in 14.
Lower dam bridge is positioned between two tunnels, and between the bridge tunnel of big mileage direction, changeover portion is less than 10m.For bridge between tunnel Set up, typically use support cast-in-place method or after beam field is prefabricated, treats that tunnel holing through uses the methods such as Bridge Erector erection to carry out bridge Set up.Lower dam bridge pier body height is more than 50 meters, and up to 70 meters, and cloud osmanthus railway is high mountains and precipitous paths, tunnel cannot pass through in advance Logical, according to owner's Design of Construction Organization requirement, lower dam bridge uses mobile formwork cast-in-place construction, complete at mobile formwork beam After, mobile formwork to be solved is in the dismounting of bridge tunnel changeover portion less than 10 meters, disintegration problem.
Through on-the-spot actual survey with measure, mobile formwork top width 7.6m, with the tunnel clear span of mobile formwork top corresponding height 12.106m, have more than needed 2.253m in both sides;Mobile formwork height (containing track) 4.9m, the vertical corresponding tunnel clear height of two sides 7.952m, height 3.052m more than needed;By relative analysis, in tunnel, possesses the condition accommodating mobile formwork;
Between the bridge tunnel of bridge big mileage direction, lower dam, changeover portion is plus the length of abutment, and total length is less than 10 meters, and both sides are shallow Cutting, can suitably widen, and possesses the condition of crane operation;
According to the version of mobile formwork, and on-the-spot actual condition, it is determined that disassemble shifting in bridge tunnel narrow short transition time section The method of dynamic model frame is: before mobile formwork assembly, and girder bottom welding installs track advancing, its position, physical dimension and nose girder Existing guide rail is identical;After last a piece of beam makes, mobile formwork is moved in tunnel, progressively removes plug-in;Outward Hang remove after, exit in tunnel, more piecemeal remove mobile formwork nose girder, girder and, connect system and before, during and after supporting leg.
Seeing Fig. 1, in the method that bridge tunnel narrow short transition time section disassembles mobile formwork, it specifically comprises the following steps that
1, Main Girder Welding guide rail:
See Fig. 2, before starting to set a roof beam in place, at girder corresponding to nose girder guide rail position welding same size, identical material Track advancing 4, and carry out weldering even with nose girder guide rail 5, it is desirable to the prolongation that the spreading guide rail 4 that girder is welded with is in nose girder guide rail 5 is straight On line and smooth, straight;
In this achievement in research, it is possible to use when assembly, the track advancing 4 of welding carries out disintegration slideway.
2, system is set a roof beam in place complete
Seeing Fig. 3, after system is set a roof beam in place, mobile formwork is in following state: 2# nose girder 7,3# nose girder 8 stretch in tunnel 9, Middle support oil cylinder 10 is placed in abutment top and bears mobile formwork load, and rear running mechanism 11 is supported on and sets up on beam face, front Lower limb upper framework 12 is placed in abutment 13 and pushes up, by driving and the tourelle of front leg strut upper framework 12 of rear travel structure 11, it is achieved Mobile formwork moves forward and backward relative to tunnel 9;
3, mobile formwork and front leg strut upper framework are moved
Seeing Fig. 4, move forward mould bases to 8# plug-in 14 near abutment 13, then fixing middle support oil cylinder 10, uses sky Car 24 is toward direction handling front leg strut upper framework 12 to 3# nose girder 8 medium position in tunnel 9, and installs fixing.
4, remove plug-in
See Fig. 5, Fig. 6 and Fig. 7, utilize bridge tunnel changeover portion roadbed as job platform, along line direction and changeover portion two Each one of 50t crane is installed in side, carries out removing plug-in operation: first remove 8# plug-in 14, then mobile formwork reach, 7# plug-in 15 Near abutment 13;Removing 7# plug-in 15, then mobile formwork reach, 6# plug-in 16 is near abutment;Remove 6# plug-in 16, then move Dynamic model frame moves forward, and 5# plug-in 17 is near abutment 13;By that analogy, until all of plug-in whole dismountings are complete;
5, beam body retreats
After plug-in whole dismounting, mobile formwork beam body divides three steps to exit tunnel 9, only stays 3# nose girder 8 at bridge tunnel roadbed Changeover portion.
The first step: see Fig. 8, front leg strut upper framework 12 remains stationary as, and reverse starting rear support leg running mechanism 11, after beam body Move back, until 3# nose girder 8 front end is moved at leading supporting leg upper framework 12;
Second step: see Fig. 9, fixing middle support oil cylinder 10, at overhead traveling crane 24 handling front leg strut upper framework 12 to abutment 13;
3rd step: see Figure 10, fixing front leg strut upper framework 12, support oil cylinder 10 in contraction, reverse starting rear support leg is walked Row mechanism 11, beam body retreats, until 3# nose girder 8 rear end moves at front leg strut upper framework 12, i.e. 3# nose girder 8 is positioned at bridge tunnel roadbed Changeover portion.
6, nose girder is removed
Using the 50t crane installed, after 3# nose girder 8 is disassembled in lifting, by trailer, 3# nose girder 8 is transported outward transition, 2# leads Beam 7 moves forward at basement transition stage (such as Figure 11);After 2# nose girder 7 is disassembled in lifting, by 2# nose girder 7 by trailer outer operating in time , 1# nose girder 6 moves forward at basement transition stage (such as Figure 12);After 1# nose girder 6 is disassembled in lifting, in time 1# nose girder 6 is transported outward transition, 3# girder 3 moves forward at basement transition stage (such as Figure 13);
7, girder and running gear are removed
Use the 50t crane installed, after 3# girder 3 is disassembled in lifting, transport outward transition by trailer in time, before 2# girder 2 Move at basement transition stage (such as Figure 14);After 2# girder is disassembled in lifting, transporting outward transition in time by trailer in time, 1# girder is in situ Remain stationary as (such as Figure 15);Bridge on crane, disassembles rear support leg and running mechanism, lifts 1# girder entrucking transition (such as figure on bridge 16);
8, running gear is removed
Seeing Figure 17, crane lifting rear support leg 22, rear running mechanism 11 and front leg strut upper framework 12, cleaning lifts place, Complete mobile formwork to disintegrate.

Claims (2)

1. the method disassembling mobile formwork in bridge tunnel narrow short transition time section, is characterized in that: before mobile formwork assembly, bottom girder Welded and installed track advancing, its position, physical dimension guide rail existing with nose girder are identical;After last a piece of beam makes, Mobile formwork is moved in tunnel, progressively removes plug-in;After plug-in dismounting, exit in tunnel, then remove shifting piecemeal Dynamic model frame nose girder, girder and, connect system and before, during and after supporting leg.
The method disassembling mobile formwork in bridge tunnel narrow short transition time section the most according to claim 1, is characterized in that: concrete steps As follows:
(1), Main Girder Welding guide rail:
Before starting to set a roof beam in place, weld same size, the guide rail of identical material, and and nose girder at girder corresponding to nose girder guide rail position Guide rail carries out weldering even, it is desirable to the spreading guide rail that girder is welded with is on the prolongation straight line of nose girder guide rail, and smooth, straight;
(2), system is set a roof beam in place complete:
After system is set a roof beam in place, mobile formwork is in following state: 2#, 3# nose girder stretches in tunnel, and middle support oil cylinder is placed in abutment Mobile formwork load is born at top, and rear running mechanism is supported on and sets up on beam face, and front leg strut upper framework is placed in abutment top, passes through The driving of rear travel structure and the tourelle of front leg strut upper framework, it is achieved mobile formwork moves forward and backward relative to tunnel;
(3), mobile formwork and front leg strut upper framework are moved:
Move forward mould bases plug-in near abutment to 8#, then fixing middle supporting leg, use overhead traveling crane to prop up before direction handling in tunnel Lower limb upper framework is to 3# nose girder medium position, and installs fixing;
(4), remove plug-in:
Utilize bridge tunnel changeover portion roadbed as job platform, install each one of 50t crane along line direction and changeover portion both sides, enter Row removes plug-in operation: first remove 8# plug-in, then mobile formwork reach, and 7# is plug-in near abutment;Remove 7# plug-in, then move Dynamic model frame moves forward, and 6# is plug-in near abutment;Removing 6# plug-in, then mobile formwork reach, 5# is plug-in near abutment;With this type of Push away, until all of plug-in whole dismountings are complete;
(5), beam body retreats:
After plug-in whole dismounting, mobile formwork beam body divides three steps to exit tunnel, only stays 3# nose girder at bridge tunnel basement transition stage;
The first step: front leg strut upper framework remains stationary as, reverse starting rear support leg running mechanism, beam body retreats, until before 3# nose girder At the mobile leading supporting leg upper framework of end;
Second step: supporting leg in fixing, overhead traveling crane handling front leg strut upper framework is to Abutment;
3rd step: fixing front leg strut upper framework, supporting leg in contraction, reverse starting rear support leg running mechanism, beam body retreats, until 3# Nose girder rear end moves at front leg strut upper framework, i.e. 3# nose girder is positioned at bridge tunnel basement transition stage;
(6), nose girder is removed:
Using the 50t crane installed, after 3# nose girder is disassembled in lifting, by trailer, 3# nose girder is transported outward transition, 2# nose girder moves forward To basement transition stage;After 2# nose girder is disassembled in lifting, by trailer, 2# nose girder being transported outward transition in time, 1# nose girder moves forward to roadbed At changeover portion;After 1# nose girder is disassembled in lifting, in time 1# nose girder being transported outward transition, 3# girder moves forward at basement transition stage;
(7), girder and running gear are removed:
Using the 50t crane installed, after 3# girder is disassembled in lifting, transport outward transition by trailer in time, 2# girder moves forward to road Ji Guoduduanchu;After 2# girder is disassembled in lifting, transporting outward transition in time by trailer in time, 1# girder remains stationary as in situ;Crane Upper bridge, disassembles rear support leg and running mechanism, lifts 1# girder entrucking transition on bridge;
(8), running gear is removed:
Crane lifting rear support leg, rear running mechanism and front leg strut upper framework, cleaning lifting place, complete mobile formwork and disintegrate.
CN201610668987.3A 2016-08-12 2016-08-12 A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel Active CN106192761B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610668987.3A CN106192761B (en) 2016-08-12 2016-08-12 A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610668987.3A CN106192761B (en) 2016-08-12 2016-08-12 A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel

Publications (2)

Publication Number Publication Date
CN106192761A true CN106192761A (en) 2016-12-07
CN106192761B CN106192761B (en) 2017-09-12

Family

ID=57521531

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610668987.3A Active CN106192761B (en) 2016-08-12 2016-08-12 A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel

Country Status (1)

Country Link
CN (1) CN106192761B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109505262A (en) * 2018-12-29 2019-03-22 中铁局集团有限公司 A kind of mobile formwork bridge fabrication machine girder turns around construction method
CN112482226A (en) * 2020-11-19 2021-03-12 中铁大桥局集团有限公司 Overhead variable-span length construction method for upstroke movable formwork
CN113073556A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第一工程有限公司 Descending type beam mold combination movable mold frame and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003293319A (en) * 2002-04-03 2003-10-15 Oriental Construction Co Ltd Movable timbering
CN101818479A (en) * 2009-10-10 2010-09-01 中交二公局第二工程有限公司 Construction process for overhead back-up movement and dismantlement of movable shuttering form
CN102653938A (en) * 2011-12-29 2012-09-05 中交第四公路工程局有限公司 Offshore dismantling construction method of descending form traveler
CN105297637A (en) * 2015-11-25 2016-02-03 中铁二十局集团有限公司 Method for integrally disassembling descending movable formwork bridging machine
CN205152809U (en) * 2015-11-25 2016-04-13 中铁二十局集团有限公司 Downgoing movable formwork bridge construction machine is demolishd and is used hanging device

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003293319A (en) * 2002-04-03 2003-10-15 Oriental Construction Co Ltd Movable timbering
CN101818479A (en) * 2009-10-10 2010-09-01 中交二公局第二工程有限公司 Construction process for overhead back-up movement and dismantlement of movable shuttering form
CN102653938A (en) * 2011-12-29 2012-09-05 中交第四公路工程局有限公司 Offshore dismantling construction method of descending form traveler
CN105297637A (en) * 2015-11-25 2016-02-03 中铁二十局集团有限公司 Method for integrally disassembling descending movable formwork bridging machine
CN205152809U (en) * 2015-11-25 2016-04-13 中铁二十局集团有限公司 Downgoing movable formwork bridge construction machine is demolishd and is used hanging device

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109505262A (en) * 2018-12-29 2019-03-22 中铁局集团有限公司 A kind of mobile formwork bridge fabrication machine girder turns around construction method
CN109505262B (en) * 2018-12-29 2020-06-05 中铁一局集团有限公司 Construction method for turning around main beam of movable formwork bridge building machine
CN112482226A (en) * 2020-11-19 2021-03-12 中铁大桥局集团有限公司 Overhead variable-span length construction method for upstroke movable formwork
CN113073556A (en) * 2021-03-19 2021-07-06 中铁大桥局集团第一工程有限公司 Descending type beam mold combination movable mold frame and construction method thereof
CN113073556B (en) * 2021-03-19 2023-12-22 中铁大桥局集团第一工程有限公司 Construction method of movable formwork of downlink beam formwork combination

Also Published As

Publication number Publication date
CN106192761B (en) 2017-09-12

Similar Documents

Publication Publication Date Title
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN107675636A (en) A kind of universal bridge structure thing method for dismounting and system
CN206070393U (en) A kind of asynchronous construction hanging basket of Wavelike steel webplate composite beam bridge
CN107060823B (en) Non-dismantling trolley for tunnel anchor section secondary lining concrete construction
CN106087768B (en) A kind of method of the assembled mobile formwork in the narrow short transition time section of bridge tunnel
CN202544854U (en) Lining trolley for subway station
CN104329096A (en) Shield station-crossing launching translation construction process
CN106192761B (en) A kind of method for disassembling mobile formwork in the narrow short transition time section of bridge tunnel
CN103485282A (en) Method for gantry machine to go into and out of tunnels to erect box girders
CN210561749U (en) Multi-frame juxtaposed double-cantilever bridge girder erection machine
CN109680614B (en) Method and equipment for quickly transferring ultra-large bridge girder erection machine of assembled steel-concrete combined bridge
CN208151861U (en) The traversing supporting leg of Bridge Erector
CN211524827U (en) Large-span telescopic movable trestle
CN104179123A (en) Bridge fabrication machine capable of building and assembling two bridge segments
KR101234090B1 (en) Method for changing girder of railway plate girder bridge
CN205012236U (en) Single double track railway bridge is torn open and is changed planes
CN112211112A (en) Steel box girder installation method adopting double-guide-girder erection machine on existing bridge
CN113322819B (en) Method for erecting first-span T beam at tunnel outlet
CN110805452B (en) Large-span telescopic movable trestle
CN204112226U (en) A kind of holes connects does section assembling bridge manufacturing machine
CN212128890U (en) Box girder transverse pushing device
CN205188823U (en) Construction of light rail prestressing force bent cap and end -blocking work platform
CN210370698U (en) Mould shifting trolley for shed tunnel lining arch construction
JP7368685B2 (en) Bridge reconstruction method and bridge superstructure
CN203729163U (en) Track laying machine low-position jacking fast shifting span-changing device

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant