CN104179123A - Bridge fabrication machine capable of building and assembling two bridge segments - Google Patents
Bridge fabrication machine capable of building and assembling two bridge segments Download PDFInfo
- Publication number
- CN104179123A CN104179123A CN201410422238.3A CN201410422238A CN104179123A CN 104179123 A CN104179123 A CN 104179123A CN 201410422238 A CN201410422238 A CN 201410422238A CN 104179123 A CN104179123 A CN 104179123A
- Authority
- CN
- China
- Prior art keywords
- bridge
- truss
- girder
- main
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
一种两孔连做节段拼装造桥机,属于桥梁建筑技术领域,其特征是:造桥机主梁采用两组平行的两整跨主桁架和一短节尾部桁架,主桁架下部设下托梁系统,桁架下方设托轮系支承在待造桥跨桥墩上,桁架上方设有沿桁架纵向走行提梁吊机。有益效果是:采用桥址旁梁场预制箱梁节段,运梁车运送梁节到达造桥机尾部,提梁吊机吊放梁节就位,浇筑混凝土湿接缝,张拉预应力筋成桥,造桥机过孔的造桥方式。具有承受荷载大,一次过孔同时造两孔桥梁,节省工期,降低建设成本等特点,适用于高速铁路、客运专线或高速公路40m及以上跨度简支箱梁桥的造桥工作。
A two-hole segmental assembly bridge-building machine, which belongs to the technical field of bridge construction, is characterized in that: the main girder of the bridge-building machine adopts two sets of parallel two full-span main trusses and a short-section tail truss, and the lower part of the main truss is set Joy beam system, under the truss, a supporting wheel system is supported on the pier of the bridge span to be built, and above the truss, there is a girder lifting crane running along the longitudinal direction of the truss. The beneficial effect is: the box girder section is prefabricated in the girder yard next to the bridge site, the girder transport vehicle transports the girder section to the tail of the bridge building machine, the girder crane lifts the girder section into place, pours concrete wet joints, and stretches the prestressed tendons to form Bridge, the bridge-building method of the bridge-building machine passing through the hole. It has the characteristics of bearing large loads, building two-hole bridges at the same time through one hole, saving construction period, and reducing construction costs.
Description
技术领域 technical field
本发明属于桥梁建筑技术领域。 The invention belongs to the technical field of bridge construction. the
背景技术 Background technique
目前国内外节段箱梁拼装造桥机,通常由一个工作跨和前(后)导梁组成,在工作跨上摆放箱梁节段,浇筑混凝土湿接缝,张拉预应力筋,完成一孔桥梁的制作。这类造桥机可制作跨度大,梁体重的桥梁,在40m以上跨度的桥梁施工中得到广泛的应用。但此类造桥机每次只能拼装施工一孔桥梁,之后造桥机前移过孔,进行下一孔的节段箱梁拼装作业,其缺点是施工工期长,完成一孔桥梁的造桥任务平均需要十天以上时间,成本相对较高。 At present, the segmental box girder assembly bridge building machines at home and abroad are usually composed of a working span and front (rear) guide beams. Box girder segments are placed on the working span, concrete wet joints are poured, and prestressed tendons are stretched to complete. Fabrication of a one-hole bridge. This type of bridge building machine can make bridges with large spans and heavy girders, and is widely used in bridge construction with spans of more than 40m. However, this type of bridge building machine can only assemble and construct a bridge with one hole at a time, and then the bridge building machine moves forward through the hole to carry out the assembling operation of the segmental box girder in the next hole. The bridge task takes more than ten days on average, and the cost is relatively high. the
发明内容 Contents of the invention
本发明的目的是:提供一种两孔连做节段拼装造桥机,它在一次过孔就位后,可同时完成两孔箱梁的造桥工作。 The object of the present invention is to provide a bridge-building machine for segmental assembly with two holes, which can simultaneously complete the bridge-building work of the two-hole box girder after the hole is put in place once. the
本发明的技术方案是:由主梁1、下托梁系统2、前支点托轮系3、中支点托轮系4、前支腿5、后支点横梁6、提梁吊机7等部分组成。 The technical solution of the present invention is: it is composed of main beam 1, lower joist system 2, front fulcrum supporting wheel system 3, middle fulcrum supporting wheel system 4, front outrigger 5, rear fulcrum beam 6, beam lifting crane 7 and other parts. the
造桥机主梁1采用两组平行的两整跨主桁架11和一短节尾部桁架12;主桁架下部设下托梁系统2;桁架下方设托轮系3、4支承在待造桥跨桥墩上;桁架上方设有沿桁架纵向走行提梁吊机7。 The main girder 1 of the bridge-building machine adopts two sets of parallel two full-span main trusses 11 and a short section tail truss 12; the lower part of the main truss is provided with a joist system 2; On the pier; above the truss is provided with a girder lifting crane 7 running longitudinally along the truss. the
主梁桁架为两片式结构,由桁架弦杆、斜杆、竖杆和联接系拼组而成;主梁桁架在过孔时为两跨连续梁式,造桥时,通过拆解前后跨连接处上弦杆的连接销13,造桥机主梁桁架形成两跨独立的简支梁。两组桁架之间在前跨前端、后跨前端、后跨后端分别通过前支腿横梁51、中间横梁8、后支点横梁6相连接。 The main girder truss is a two-piece structure, which is composed of truss chords, oblique rods, vertical rods and connecting systems; the main girder truss is a two-span continuous beam type when passing through the hole. The connecting pin 13 of the upper chord at the joint, and the main girder truss of the bridge building machine form two independent simply supported beams. The two groups of trusses are connected at the front end of the front span, the front end of the rear span, and the rear end of the rear span through the front outrigger beam 51, the middle beam 8, and the rear fulcrum beam 6, respectively. the
主桁架12在前跨121前端下部设前支点托轮系3,前后跨连接处下部设中支点托轮系4,托轮系支承在待造桥跨桥墩上,为过孔造桥机走行提供滚动支承;过孔到位后,前、中支点托轮系转换成前、中支点,承受造桥时箱梁节段和湿接缝的重量;前支点可沿主桁架后移,以适应不同跨度的造桥需要。主桁架12后跨122后端的后支点横梁6支承在已造箱梁端部,作为造桥机的重载后支点,后支点可沿主桁架前移,以适应不同跨度的造桥需要。主桁架前端设前支腿5,用于辅助造桥机过孔。 The main truss 12 is provided with a front fulcrum support wheel system 3 at the lower part of the front end of the front span 121, and a middle fulcrum support wheel system 4 at the lower part of the connection between the front and rear spans. Rolling support; after the hole is put in place, the front and middle fulcrum support wheels are converted into front and middle fulcrums to bear the weight of the box girder segment and wet joints during bridge construction; the front fulcrum can be moved backward along the main truss to adapt to different spans bridge building needs. The rear fulcrum beam 6 at the rear end of the rear span 122 of the main truss 12 is supported on the end of the built box girder as the heavy-duty rear fulcrum of the bridge building machine. The rear fulcrum can move forward along the main truss to adapt to the needs of bridge building with different spans. The front end of the main truss is provided with a front outrigger 5 for assisting the passage of the bridge building machine. the
下托梁系统2由纵横梁连接组成,下托梁横梁21为分体式,中间通过螺栓、钢销连接成一体,横梁两端分别与两侧主桁连接,过孔时,拆解横梁中部连接,横梁可沿两侧翻起避让桥墩;下托梁纵梁22沿主桁方向布置,两端与横梁21连接,纵梁上设丝杠或液压顶升装置23,用以调节箱梁线形。 The lower joist system 2 is composed of vertical and horizontal beams. The lower joist beam 21 is a split type, and the middle is connected by bolts and steel pins. The two ends of the beam are respectively connected with the main trusses on both sides. , the beam can be turned up along both sides to avoid the pier; the lower joist longitudinal beam 22 is arranged along the direction of the main truss, and the two ends are connected with the beam 21, and a screw or hydraulic jacking device 23 is provided on the longitudinal beam to adjust the line shape of the box girder. the
提梁吊机7为门式起重机,可沿两跨主桁12和尾部桁架11上方的走行轨道纵向走行,实现从运梁车9上吊装梁节和在造桥机腹部摆放梁节的功能。 The beam lifting crane 7 is a gantry crane, which can run longitudinally along the running track above the two-span main truss 12 and the tail truss 11, so as to realize the functions of lifting the beam section from the beam transport vehicle 9 and placing the beam section on the belly of the bridge building machine. the
本发明的有益效果是:采用桥址旁梁场预制箱梁节段,运梁车运送梁节到达造桥机尾部,提梁吊机吊放梁节就位,浇筑混凝土湿接缝,张拉预应力筋成桥,造桥机过孔的造桥方式。具有承受荷载大,一次过孔同时造两孔桥梁,节省工期,降低建设成本等特点,适用于高速铁路、客运专线或高速公路40m及以上跨度简支箱梁桥的造桥工作。 The beneficial effects of the present invention are as follows: the box girder section is prefabricated in the girder field next to the bridge site, the girder section is transported by the girder truck to the tail of the bridge building machine, the girder section is hoisted by the girder crane, and the concrete wet joint is poured. Stress tendons form a bridge, and the bridge-building machine passes through the bridge-building method. It has the characteristics of bearing large loads, building two-hole bridges at the same time through one hole, saving construction period, and reducing construction costs. the
附图说明 Description of drawings
图1为造桥机立面示意图; Figure 1 is a schematic diagram of the elevation of the bridge building machine;
图2是图1的A-A截面图; Fig. 2 is the A-A sectional view of Fig. 1;
图3是图1的B-B截面图; Fig. 3 is the B-B sectional view of Fig. 1;
图4是图1的C-C截面图; Fig. 4 is the C-C sectional view of Fig. 1;
图5是图1的D-D截面图; Fig. 5 is a D-D sectional view of Fig. 1;
图6是主梁桁架立面示意图; Figure 6 is a schematic diagram of the elevation of the main beam truss;
图7A是下托梁系统主视图; Figure 7A is a front view of the bottom joist system;
图7B是下托梁系统俯视图; Figure 7B is a top view of the lower joist system;
图7C是下托梁系统侧视图; Figure 7C is a side view of the bottom joist system;
图8A、B、C、D、E、F、G、H、I、J是造桥机造桥、过孔作业程序示意图。 Fig. 8 A, B, C, D, E, F, G, H, I, J are the schematic diagrams of the bridge building machine and the drilling operation program.
具体实施方式 Detailed ways
实施例1 Example 1
下面结合附图对本发明做进一步描述: The present invention will be further described below in conjunction with accompanying drawing:
如图1、2、3、4、5所示,1是主梁、2是下托梁系统、3是前支点托轮系、4是中支点托轮系、5是前支腿、6是后支点横梁、7是提梁吊机、8是中间横梁、9是运梁车、51是前支腿横梁。 As shown in Figures 1, 2, 3, 4, and 5, 1 is the main beam, 2 is the lower joist system, 3 is the front fulcrum supporting wheel system, 4 is the middle fulcrum supporting wheel system, 5 is the front outrigger, 6 is Rear fulcrum crossbeam, 7 are beam lifting cranes, 8 are intermediate crossbeams, 9 are beam transport vehicles, and 51 is a front outrigger crossbeam.
如图6所示,11是主桁架、12是短节尾部桁架、13是主桁上弦钢销。 As shown in Figure 6, 11 is the main truss, 12 is the puppet tail truss, and 13 is the steel pin of the main truss upper chord. the
如图7所示21是下托梁横梁、22是下托梁纵梁、23是丝杠或液压顶升装置。 As shown in Figure 7, 21 is a lower joist beam, 22 is a lower joist longitudinal beam, and 23 is a leading screw or a hydraulic jacking device. the
由主梁1、下托梁系统2、前支点托轮系3、中支点托轮系4、前支腿5、后支点横梁6、提梁吊机7等部分组成。造桥机主梁1采用两组平行的两整跨主桁架11和一短节尾部桁架12;主桁架下部设下托梁系统2;桁架下方设托轮系3、4支承在待造桥跨桥墩上;桁架上方设有沿桁架纵向走行提梁吊机7。 It consists of main girder 1, lower joist system 2, front fulcrum supporting wheel system 3, middle fulcrum supporting wheel system 4, front outrigger 5, rear fulcrum beam 6, beam lifting crane 7 and other parts. The main girder 1 of the bridge-building machine adopts two sets of parallel two full-span main trusses 11 and a short section tail truss 12; the lower part of the main truss is provided with a joist system 2; On the pier; above the truss is provided with a girder lifting crane 7 running longitudinally along the truss. the
主梁桁架为两片式结构,由桁架弦杆、斜杆、竖杆和联接系拼组而成;主梁桁架在过孔时为两跨连续梁式,造桥时,通过拆解前后跨连接处上弦杆的连接销13,造桥机主梁桁架形成两跨独立的简支梁。两组桁架之间在前跨前端、后跨前端、后跨后端分别通过前支腿横梁51、中间横梁8、后支点横梁6相连接。 The main girder truss is a two-piece structure, which is composed of truss chords, oblique rods, vertical rods and connecting systems; the main girder truss is a two-span continuous beam when passing through the hole. The connecting pin 13 of the upper chord at the connection, the main girder truss of the bridge building machine forms two independent simply supported beams. The two groups of trusses are connected at the front end of the front span, the front end of the rear span, and the rear end of the rear span through the front outrigger beam 51, the middle beam 8, and the rear fulcrum beam 6, respectively. the
主桁架12在前跨121前端下部设前支点托轮系3,前后跨连接处下部设中支点托轮系4,托轮系支承在待造桥跨桥墩上,为过孔造桥机走行提供滚动支承;过孔到位后,前、中支点托轮系转换成前、中支点,承受造桥时箱梁节段和湿接缝的重量;前支点可沿主桁架后移,以适应不同跨度的造桥需要。主桁架12后跨122后端的后支点横梁6支承在已造箱梁端部,作为造桥机的重载后支点,后支点可沿主桁架前移,以适应不同跨度的造桥需要。主桁架前端设前支腿5,用于辅助造桥机过孔。 The main truss 12 is provided with a front fulcrum support wheel system 3 at the lower part of the front end of the front span 121, and a middle fulcrum support wheel system 4 at the lower part of the connection between the front and rear spans. Rolling support; after the hole is put in place, the front and middle fulcrum support wheels are converted into front and middle fulcrums to bear the weight of the box girder segment and wet joints during bridge construction; the front fulcrum can be moved backward along the main truss to adapt to different spans bridge building needs. The rear fulcrum beam 6 at the rear end of the rear span 122 of the main truss 12 is supported on the end of the built box girder as the heavy-duty rear fulcrum of the bridge building machine. The rear fulcrum can move forward along the main truss to adapt to the needs of bridge building with different spans. The front end of the main truss is provided with a front outrigger 5 for assisting the passage of the bridge building machine. the
下托梁系统2由纵横梁连接组成,下托梁横梁21为分体式,中间通过螺栓、钢销连接成一体,横梁两端分别与两侧主桁连接,过孔时,拆解横梁中部连接,横梁可沿两侧翻起避让桥墩;下托梁纵梁22沿主桁方向布置,两端与横梁21连接,纵梁上设丝杠或液压顶升装置23,用以调节箱梁线形。 The lower joist system 2 is composed of vertical and horizontal beams. The lower joist beam 21 is a split type, and the middle is connected by bolts and steel pins. The two ends of the beam are respectively connected with the main trusses on both sides. , the beam can be turned up along both sides to avoid the pier; the lower joist longitudinal beam 22 is arranged along the direction of the main truss, and the two ends are connected with the beam 21, and a screw or hydraulic jacking device 23 is provided on the longitudinal beam to adjust the line shape of the box girder. the
提梁吊机7为门式起重机,可沿两跨主桁12和尾部桁架11上方的走行轨道纵向走行,实现从运梁车9上吊装梁节和在造桥机腹部摆放梁节的功能。 The beam lifting crane 7 is a gantry crane, which can run longitudinally along the running track above the two-span main truss 12 and the tail truss 11, so as to realize the functions of lifting the beam section from the beam transport vehicle 9 and placing the beam section on the belly of the bridge building machine. the
本发明两孔连做节段拼装造桥机的施工方法如下: The construction method of the segmental assembly bridge building machine with two holes connected in series of the present invention is as follows:
A、造桥机过孔到位后完成前、中、后三支点的造桥支承(将前、中托轮系形成支座),闭合下托梁系,拔出主桁上弦钢销,使前后两孔主桁形成两孔独立的简支梁,避免主桁变形影响相邻孔桥梁的线形控制。 A. After the bridge-building machine passes through the holes in place, the bridge-building support of the front, middle and rear fulcrums is completed (the front and middle supporting wheel systems are formed as supports), the lower joist system is closed, and the upper chord steel pin of the main truss is pulled out to make the front and rear The two-hole main truss forms a simple-supported beam with two independent holes, which prevents the deformation of the main truss from affecting the linear control of the bridge with adjacent holes.
B、预制箱梁节段由桥面运梁车运输至主梁尾部桁架处提梁吊机下方,由提梁吊机把梁节提起纵走至前跨,并按由前向后的顺序将梁节摆放到下托梁上。 B. The prefabricated box girder segment is transported by the bridge deck girder truck to the bottom of the girder crane at the truss at the end of the main girder. The girder crane lifts the girder section to the front span, and lifts the girder section in the order from front to back. Place it on the bottom joist. the
C、前孔梁节吊放完毕后,进行线形调整、浇筑湿接缝混凝土、预应力张拉等后续工作,与此同时继续吊放后孔梁节。 C. After the front hole beam section is hoisted, follow-up work such as alignment adjustment, wet joint concrete pouring, prestressed tensioning, etc. is carried out, and at the same time, the rear hole beam section continues to be hoisted. the
D、后孔梁节吊放完毕后,进行线形调整、浇筑湿接缝混凝土、预应力张拉等后续工作。 D. After the beam section of the rear hole is hoisted, follow-up work such as alignment adjustment, pouring of wet joint concrete, and prestressed tensioning is carried out. the
E、两孔梁造完后开始做过孔准备:恢复托轮系的滚动支承功能(撤出形成支座的构件),插入主桁上弦钢销形成两孔连续主梁,打开下托梁系统(打开的下托梁如侧面图所示),运梁车上安装过孔横梁并与主梁尾部桁架相连。 E. After the two-hole beam is completed, the hole preparation is started: restore the rolling bearing function of the supporting wheel system (withdraw the components forming the support), insert the upper chord steel pin of the main truss to form a two-hole continuous main beam, and open the lower joist system (The opened lower joist is shown in the side view), and the cross beam is installed on the beam truck and connected with the tail truss of the main beam. the
F、运梁车悬挂略微升高使后支点离开桥面,运梁车缓慢前行推动整机过孔。 F. The suspension of the beam transport vehicle is slightly raised to make the rear fulcrum leave the bridge deck, and the beam transport vehicle moves forward slowly to push the whole machine through the hole. the
G、前行40m后将提梁吊机移至造桥机尾部作为配重,保证继续过孔时的倾覆稳定性和运梁车所需的竖向压力。 G. After moving forward for 40m, move the beam lifting crane to the tail of the bridge building machine as a counterweight to ensure the overturning stability and the vertical pressure required by the beam transport vehicle when continuing to pass through the hole. the
H、继续前行24m,主梁前端至前方桥墩,打好前支腿,利用提梁吊机将尾部托轮系吊至前方墩顶并安装就位,完成第一孔过孔作业。 H. Continue to move forward for 24m, the front end of the main girder reaches the front pier, lay the front outriggers, use the beam lifting crane to hoist the rear supporting wheel system to the top of the front pier and install it in place, and complete the first hole through operation. the
I、按第一孔的过孔程序进行第二孔过孔。 I. Carry out the second hole via the hole procedure of the first hole. the
J、第二孔过孔完成后,关闭下托梁系,做好造桥准备工作,开始下两孔造桥。 J. After the completion of the second hole, close the lower joist system, make preparations for bridge construction, and start the construction of the next two holes. the
1、主梁:主梁1包括两组平行的桁架结构,每组桁架结构由两整跨主桁架11和一短节尾部桁架12组成一个整体;每组桁架均为两片式结构,由桁架弦杆、斜杆、竖杆和联接系拼组而成;主梁桁架在过孔时为两跨连续梁式,造桥时,通过拆解前后跨连接处上弦杆的连接销13,造桥机主梁桁架形成两跨独立的简支梁。两组桁架之间在前跨前端、后跨前端、后跨后端分别通过前支腿横梁51、中间横梁8、后支点横梁6相连接,形成一个稳定的空间结构。 1. Main beam: The main beam 1 includes two sets of parallel truss structures, and each set of truss structures is composed of two full-span main trusses 11 and a short section tail truss 12 as a whole; each set of trusses is a two-piece structure, consisting of Chords, inclined bars, vertical bars and connecting systems are assembled; the main girder truss is a two-span continuous beam type when passing through the hole. The machine main girder truss forms two independent simply supported beams. The two groups of trusses are connected at the front end of the front span, the front end of the rear span, and the rear end of the rear span respectively through the front outrigger beam 51, the middle beam 8, and the rear pivot beam 6 to form a stable spatial structure. the
2、下托梁:下托梁系统2由纵横梁连接组成,下托梁横梁21为分体式,中间通过螺栓、钢销连接成一体,横梁两端分别与两侧主桁连接,过孔时,拆解横梁中部连接,横梁可沿两侧翻起避让桥墩,横梁的翻转动作由液压系统实现;下托梁纵梁22沿主桁方向布置,两端与横梁21连接,纵梁上设丝杠或液压顶升装置23,用以调节箱梁线形。 2. Bottom joist: Bottom joist system 2 is composed of vertical and horizontal beams. The bottom joist beam 21 is a split type, and the middle is connected by bolts and steel pins. The two ends of the beam are connected with the main truss on both sides. , disassemble the connection in the middle of the crossbeam, the crossbeam can be turned up along both sides to avoid the bridge pier, the overturning action of the crossbeam is realized by the hydraulic system; A bar or a hydraulic jacking device 23 is used to adjust the line shape of the box girder. the
3、支承系统:在造桥状态和过孔状态,造桥机采用两套支承系统。在造桥状态,造桥机通过前支点(由前支点托轮系3转换而来)支承在前跨前方桥墩,通过中支点(由中支点托轮系4转换而来)支承在前跨后方桥墩,通过后支点横梁6支承在后跨后方已造箱梁顶面;在过孔状态,造桥机前、中、后三点分别通过前支点托轮系、3中支点托轮系4和运梁车过孔横梁支承,过孔期间,造桥机每前行一整跨,需要借助前支腿5临时支承于前方桥墩,然后将最后一个托轮系前移至前方桥墩。 3. Supporting system: The bridge building machine adopts two sets of supporting systems in the bridge-building state and the passing-through state. In the bridge-building state, the bridge-building machine is supported on the pier in front of the front span by the front fulcrum (converted from the front fulcrum supporting wheel system 3), and supported on the rear of the front span by the middle fulcrum (converted from the middle fulcrum supporting wheel system 4). The bridge pier is supported on the top surface of the built box girder behind the rear span by the rear fulcrum beam 6; in the state of passing through the hole, the front, middle and rear points of the bridge building machine respectively pass through the front fulcrum support wheel system, 3 middle fulcrum support wheel system 4 and The beam carrier is supported by the crossbeam through the hole. During the passage, the bridge building machine needs to be temporarily supported on the front pier by means of the front outrigger 5 every time it moves forward for a full span, and then the last supporting wheel system is moved forward to the front pier. the
4、提梁吊机:提梁吊机由门架结构、大车走行系统、起升系统、电气控制系统等部分组成,用于箱梁节段的吊装。其中门架结构主要由主梁,端横梁、直立支腿和下横梁组成;大车走行系统由四组大车走行机构组成,每组大车走行机构由主从动轮组总成组成,大车走行采用单轨形式,变频电机驱动,启制动冲击小;起升系统由两台卷扬机、定滑轮组、动滑轮组和吊具组成。 4. Lifting beam crane: The beam lifting crane is composed of gantry structure, cart running system, lifting system, electrical control system and other parts, and is used for hoisting of box girder segments. Among them, the mast structure is mainly composed of the main beam, the end beam, the upright legs and the lower beam; The running adopts a single-rail form, driven by a frequency conversion motor, and the impact of starting and braking is small; the lifting system is composed of two hoists, a fixed pulley block, a movable pulley block and a spreader. the
5、过孔方式:造完两孔桥后,恢复托轮系的滚动支承功能,插入主桁上弦钢销13形成两孔连续主梁,打开下托梁系统2,运梁车9上安装过孔横梁并与主梁尾部桁架11相连;运梁车9悬挂略微升高使后支点离开桥面,运梁车9缓慢前行推动整机过孔;前行40m后将提梁吊机7移至造桥机尾部作为配重,保证继续过孔时的倾覆稳定性和运梁车所需的竖向压力;继续前行24m,主梁前端到达前方桥墩,打好前支腿5,利用提梁吊机7将尾部托轮系吊至前方墩顶并安装就位,完成第一孔过孔作业;按第一孔的过孔程序进行第二孔过孔;第二孔过孔完成后,关闭下托梁系2,做好造桥准备工作,开始下两孔造桥。 5. Hole passing method: After the two-hole bridge is built, restore the rolling support function of the supporting wheel system, insert the upper chord steel pin 13 of the main truss to form a continuous main beam with two holes, open the lower joist system 2, and install the over-girder on the beam transport vehicle 9 The hole beam is connected with the tail truss 11 of the main beam; the suspension of the beam transporter 9 is slightly raised to make the rear fulcrum leave the bridge deck, and the beam transporter 9 moves forward slowly to push the whole machine through the hole; after moving forward for 40m, the beam lifting crane 7 is moved to The tail of the bridge building machine is used as a counterweight to ensure the overturning stability and the vertical pressure required by the beam truck when continuing to pass the hole; continue to move forward for 24m, the front end of the main girder reaches the front pier, lay the front outrigger 5, and use the girder to lift the bridge Machine 7 lifts the rear supporting wheel system to the top of the front pier and installs it in place to complete the first hole passing operation; carry out the second hole passing according to the first hole passing procedure; after the second hole passing is completed, close the lower Joist system 2, do a good job in bridge construction preparations, and start to build bridges with two holes. the
Claims (5)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410422238.3A CN104179123A (en) | 2014-08-26 | 2014-08-26 | Bridge fabrication machine capable of building and assembling two bridge segments |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201410422238.3A CN104179123A (en) | 2014-08-26 | 2014-08-26 | Bridge fabrication machine capable of building and assembling two bridge segments |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN104179123A true CN104179123A (en) | 2014-12-03 |
Family
ID=51960443
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201410422238.3A Pending CN104179123A (en) | 2014-08-26 | 2014-08-26 | Bridge fabrication machine capable of building and assembling two bridge segments |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN104179123A (en) |
Cited By (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105648919A (en) * | 2016-01-18 | 2016-06-08 | 中国铁建大桥工程局集团有限公司 | Precast segment double-span circulating assembly construction method for prestressed concrete bridge |
| CN106522096A (en) * | 2016-10-09 | 2017-03-22 | 张小东 | Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers |
| CN110258352A (en) * | 2019-07-31 | 2019-09-20 | 河南省交通规划设计研究院股份有限公司 | Construction method of steel-concrete composite bridge with two spans |
| CN110344334A (en) * | 2019-07-31 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector |
| CN113136810A (en) * | 2021-05-26 | 2021-07-20 | 中交第二航务工程局有限公司 | Bridge girder erection machine for integral erection construction of superstructure of long-span bridge and construction method |
| CN115467239A (en) * | 2022-09-28 | 2022-12-13 | 河南省交通规划设计研究院股份有限公司 | Method for constructing long-span steel-concrete composite beams based on bridge erecting machine |
| CN119900224A (en) * | 2025-02-13 | 2025-04-29 | 中国铁建大桥工程局集团有限公司 | A new multifunctional double-hole continuous bridge-building machine |
Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE10046681A1 (en) * | 2000-09-21 | 2002-04-25 | Bilfinger Berger Ag | Construction method for bridge superstructure with bridge plates constructed off-site moved over installed plates and suspended from crane trolley to be lowered into place |
| CN101831876A (en) * | 2010-04-15 | 2010-09-15 | 中铁大桥局集团第五工程有限公司 | Movable bridge fabrication machine and bridging method thereof |
| CN102409614A (en) * | 2011-09-02 | 2012-04-11 | 中铁上海工程局第一工程有限公司 | Segmental supporting cross girders for segmental girder assembly bridge fabrication machine |
| CN202247704U (en) * | 2011-09-19 | 2012-05-30 | 广西建工集团第一建筑工程有限责任公司 | Movable framework bridge fabrication machine |
| CN102535351A (en) * | 2012-03-11 | 2012-07-04 | 中铁二十局集团第二工程有限公司 | Web plate type bridge fabrication machine for constructing bridge under strong wind and high altitude conditions and construction process |
| CN203049466U (en) * | 2012-11-30 | 2013-07-10 | 山东省路桥集团有限公司 | Downward bracket self-moving formwork bridge fabrication machine |
| CN204112226U (en) * | 2014-08-26 | 2015-01-21 | 中国铁建大桥工程局集团有限公司 | A kind of holes connects does section assembling bridge manufacturing machine |
-
2014
- 2014-08-26 CN CN201410422238.3A patent/CN104179123A/en active Pending
Patent Citations (7)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| DE10046681A1 (en) * | 2000-09-21 | 2002-04-25 | Bilfinger Berger Ag | Construction method for bridge superstructure with bridge plates constructed off-site moved over installed plates and suspended from crane trolley to be lowered into place |
| CN101831876A (en) * | 2010-04-15 | 2010-09-15 | 中铁大桥局集团第五工程有限公司 | Movable bridge fabrication machine and bridging method thereof |
| CN102409614A (en) * | 2011-09-02 | 2012-04-11 | 中铁上海工程局第一工程有限公司 | Segmental supporting cross girders for segmental girder assembly bridge fabrication machine |
| CN202247704U (en) * | 2011-09-19 | 2012-05-30 | 广西建工集团第一建筑工程有限责任公司 | Movable framework bridge fabrication machine |
| CN102535351A (en) * | 2012-03-11 | 2012-07-04 | 中铁二十局集团第二工程有限公司 | Web plate type bridge fabrication machine for constructing bridge under strong wind and high altitude conditions and construction process |
| CN203049466U (en) * | 2012-11-30 | 2013-07-10 | 山东省路桥集团有限公司 | Downward bracket self-moving formwork bridge fabrication machine |
| CN204112226U (en) * | 2014-08-26 | 2015-01-21 | 中国铁建大桥工程局集团有限公司 | A kind of holes connects does section assembling bridge manufacturing machine |
Non-Patent Citations (1)
| Title |
|---|
| 唐经世等: "《桥隧线工程机械》", 31 January 2003, article "移动支架法建造桥梁", pages: 313-316 * |
Cited By (9)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN105648919A (en) * | 2016-01-18 | 2016-06-08 | 中国铁建大桥工程局集团有限公司 | Precast segment double-span circulating assembly construction method for prestressed concrete bridge |
| CN106522096A (en) * | 2016-10-09 | 2017-03-22 | 张小东 | Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers |
| CN110258352A (en) * | 2019-07-31 | 2019-09-20 | 河南省交通规划设计研究院股份有限公司 | Construction method of steel-concrete composite bridge with two spans |
| CN110344334A (en) * | 2019-07-31 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector |
| CN110344334B (en) * | 2019-07-31 | 2021-08-24 | 河南省交通规划设计研究院股份有限公司 | Construction method for two-span continuous steel-concrete composite bridge by adopting back cable type bridge girder erection machine |
| CN113136810A (en) * | 2021-05-26 | 2021-07-20 | 中交第二航务工程局有限公司 | Bridge girder erection machine for integral erection construction of superstructure of long-span bridge and construction method |
| CN115467239A (en) * | 2022-09-28 | 2022-12-13 | 河南省交通规划设计研究院股份有限公司 | Method for constructing long-span steel-concrete composite beams based on bridge erecting machine |
| CN115467239B (en) * | 2022-09-28 | 2024-12-13 | 河南省交通规划设计研究院股份有限公司 | Method for constructing long-span steel-concrete composite beams based on bridge erection machine |
| CN119900224A (en) * | 2025-02-13 | 2025-04-29 | 中国铁建大桥工程局集团有限公司 | A new multifunctional double-hole continuous bridge-building machine |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN108330842B (en) | Bridge girder erection machine for erection construction of large-span reinforced concrete composite girder and construction method | |
| CN104179123A (en) | Bridge fabrication machine capable of building and assembling two bridge segments | |
| CN110130229B (en) | A multi-span parallel double cantilever bridge erecting machine and its beam erection and span crossing method | |
| CN101787678B (en) | Large-span section assembling bridge manufacturing machine and assembling construction process thereof | |
| CN101250854B (en) | Bridge-building machine for long-span double-track box girder stringing method | |
| KR20140084107A (en) | Self-Launching Movable Scaffolding System | |
| CN105421249A (en) | Novel dragging- hoisting combined type hanging basket structure and construction method | |
| CN101736703B (en) | 3000t special bridge girder erection machine for integrally erecting 120m-span double-layer four-line steel beam bridge for highway and railway | |
| CN207714163U (en) | A kind of combined type Hanging Basket | |
| CN101462672A (en) | Big elevating capacity and big elevating height hoisting crane | |
| CN109024291A (en) | A kind of integration Bridge Erector and its working method | |
| CN104695335B (en) | Construction method and construction device of integral binding and hoisting of steel bars in upward mobile formwork | |
| CN101481903B (en) | The method of erecting the main truss of the suspension bridge in mountainous area by reversing the cable-span crane | |
| CN110820602A (en) | A single-segment box girder bridge erecting machine and its operation method | |
| CN100497833C (en) | High-altitude framework type simple plate supporting machine | |
| CN108203934A (en) | Based on the whole segment lifting erection crane of the traversing cable-stayed bridge composite beam of unbalance loading | |
| CN205205685U (en) | Span wire pier is function portal device at most | |
| CN110700098A (en) | Safe crossing method for double-guide-beam type bridge girder erection machine | |
| CN106758872A (en) | Wavelike steel webplate SCC engineering methods hang movable hanging basket and the method using its construction with car convolution | |
| CN113931068A (en) | Bridge deck crane for mounting steel and concrete superposed beams and beam erecting method thereof | |
| CN212052371U (en) | Hanging basket device for variable width concrete box girder suspension casting construction | |
| CN110512521B (en) | Butt joint device and joint method of large segment steel truss girder | |
| CN204112226U (en) | A kind of holes connects does section assembling bridge manufacturing machine | |
| CN102071641B (en) | Cement beam packs bridge machine cloth supporting leg type integration of transporting and building Bridge Erector and bridge formation engineering method thereof | |
| CN111851307A (en) | Construction method of large-span prefabricated corrugated web composite box girder transport frame |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
| WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20141203 |