JP2021050512A - Bridge replacement method and bridge upper structure - Google Patents

Bridge replacement method and bridge upper structure Download PDF

Info

Publication number
JP2021050512A
JP2021050512A JP2019173549A JP2019173549A JP2021050512A JP 2021050512 A JP2021050512 A JP 2021050512A JP 2019173549 A JP2019173549 A JP 2019173549A JP 2019173549 A JP2019173549 A JP 2019173549A JP 2021050512 A JP2021050512 A JP 2021050512A
Authority
JP
Japan
Prior art keywords
bridge
existing
superstructure
removal
connecting means
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2019173549A
Other languages
Japanese (ja)
Other versions
JP7368685B2 (en
Inventor
光商 大庭
Kosho Oba
光商 大庭
石橋 忠良
Tadayoshi Ishibashi
忠良 石橋
満 清水
Mitsuru Shimizu
満 清水
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JR East Consultants Co
Original Assignee
JR East Consultants Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JR East Consultants Co filed Critical JR East Consultants Co
Priority to JP2019173549A priority Critical patent/JP7368685B2/en
Publication of JP2021050512A publication Critical patent/JP2021050512A/en
Application granted granted Critical
Publication of JP7368685B2 publication Critical patent/JP7368685B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

To provide a bridge replacement method that can be applied even when the construction conditions under the bridge are severe.SOLUTION: The replacement of an existing bridge 10 with a new bridge 20 is performed as follows. Rail-shaped first connection means 31 extending in a direction of the bridge axis is provided on a lower surface side of a new bridge upper structure 21. The new bridge upper structure 21 is carried in using an upper surface of the existing bridge upper structure as a carrying path, and the new bridge superstructure 21 is temporarily installed on an upper part of the existing bridge upper structure to temporarily support both ends via a temporary vent. The first connection means 31 is connected to second connection means 32 being a hanging rod, an existing bridge upper structure removal equivalent part 11A is suspended and supported by the new bridge upper structure 21 via the second connection means 32, the existing bridge upper structure is cut to form a removal block 11A, and the removal block 11A is lifted and slid through the first connection means 31 to be removed. The removal block 11A is repeatedly formed to remove the existing bridge upper structure, and existing bridge piers are removed in the same manner. The new bridge upper structure 21 is then lowered and installed.SELECTED DRAWING: Figure 1

Description

本発明は、既設橋梁を撤去し、新設橋梁を架設する架替工法に関するものである。 The present invention relates to a replacement method in which an existing bridge is removed and a new bridge is erected.

一般にコンクリートの寿命は60〜100年と言われている。コンクリートや鉄を主材料とする土木構造物も半世紀以上経過すると、大規模補修をして長寿命化を図るか、既設構造物を撤去して新設するかを検討することが多い。 Generally, the life of concrete is said to be 60 to 100 years. After more than half a century has passed for civil engineering structures mainly made of concrete and iron, it is often considered whether to make large-scale repairs to extend the service life or to remove existing structures and construct new ones.

橋梁においても、既設橋梁を撤去し、新設橋梁を架設する架替が検討されている。しかしながら、橋梁周辺環境による制約により施工条件が厳しいことが多い。また、架替工事は、撤去工程と新設工程を含むため、長期化しやすい。そのため、施工条件に応じて、様々な架替工法が提案されている(例えば、特許文献1)。 As for bridges, the replacement of existing bridges with new ones is being considered. However, construction conditions are often strict due to restrictions due to the environment around the bridge. In addition, the replacement work includes a removal process and a new construction process, so it is easy to take a long time. Therefore, various replacement methods have been proposed according to the construction conditions (for example, Patent Document 1).

たとえば、特許文献1開示の架替工法では、まず、橋脚に架設された既設橋桁を運搬台車上に設置されたジャッキにより下方から支持する。橋脚径間より短い長さで既設橋桁の両端を切断する。ジャッキを操作して既設橋桁を降下させる。ジャッキで既設橋桁を下方より支持した状態で、運搬台車により既設橋桁を搬出する。 For example, in the replacement method disclosed in Patent Document 1, first, the existing bridge girder erected on the pier is supported from below by a jack installed on the transport carriage. Cut both ends of the existing bridge girder with a length shorter than the pier span. Operate the jack to lower the existing bridge girder. With the existing bridge girder supported from below by the jack, the existing bridge girder is carried out by the transport trolley.

一方、新設橋桁架替位置に隣接する残部既設橋桁上で新設橋桁を構築する。さらに新設橋桁を大型クレーン吊りあげて橋脚間に架設する。 On the other hand, a new bridge girder will be constructed on the remaining existing bridge girder adjacent to the new bridge girder replacement position. In addition, a new bridge girder will be lifted by a large crane and erected between the piers.

特開2003−034911号公報Japanese Unexamined Patent Publication No. 2003-034911

図12は、既設橋梁の一例である。都市部では狭隘な谷部に複数の鉄道が並走し、谷を跨ぎ線路と立体交差するように橋梁が架けられていることもある。半世紀以上前に架けられた橋梁は一般に径間が短く、両端の橋台に加えて、橋脚により支持されている。複数の鉄道が橋脚間または橋台橋脚間を通過している。 FIG. 12 is an example of an existing bridge. In urban areas, multiple railroads run side by side in narrow valleys, and bridges may be erected so as to cross the valley and cross over the railroad tracks. Bridges built over half a century ago generally have short spans and are supported by piers in addition to the piers at both ends. Multiple railroads pass between piers or between piers.

上記のような橋梁において点検やメンテナンスをする際は、必ず、鉄道運行状況を考慮する必要がある。特に、線路に挟まれた橋脚の点検やメンテナンスは非常に作業条件が厳しい。したがって、架替の方が好ましいと判断される場合もある。なお、近年、径間が長くなる傾向にあり、橋脚による支持は不要となる。橋梁構造が単純化すれば点検やメンテナンスも容易となる。 When inspecting or maintaining bridges as described above, it is necessary to always consider the railway operation status. In particular, the work conditions for inspection and maintenance of piers sandwiched between railroad tracks are extremely strict. Therefore, it may be determined that replacement is preferable. In recent years, the span has tended to become longer, and support by piers is no longer necessary. If the bridge structure is simplified, inspection and maintenance will be easier.

特許文献1記載の架替工法は、橋梁下において運搬台車を待機させている。図12に示す施工条件下では、橋梁下において運搬台車を待機させることは好ましくなく、特許文献1記載の架替工法の適用は困難である。上記施工条件に適した架替工法を検討する必要がある。 In the replacement method described in Patent Document 1, the transport trolley is kept on standby under the bridge. Under the construction conditions shown in FIG. 12, it is not preferable to keep the transport trolley on standby under the bridge, and it is difficult to apply the replacement method described in Patent Document 1. It is necessary to consider a replacement method suitable for the above construction conditions.

本発明は上記課題を解決するものであり、橋梁下の施工条件が厳しい場合にも適用可能な橋梁の架替工法を提供することを目的とする。 The present invention solves the above problems, and an object of the present invention is to provide a bridge replacement method that can be applied even when the construction conditions under the bridge are severe.

上記課題を解決する本発明は橋梁の架替工法である。新設橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられており、既設橋梁上部構造上面を搬路として、前記新設橋梁上部構造を搬入し、既設橋梁上部構造の上部に、前記新設橋梁上部構造を仮設し、前記新設橋梁上部構造の両端を仮支持し、前記第1接続手段と第2接続手段とを接続するとともに、前記第2接続手段を介して、前記既設橋梁上部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、前記既設橋梁上部構造の撤去相当部を切断し、前記既設橋梁上部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させて、撤去し、複数の前記既設橋梁上部構造の撤去相当部の撤去を繰り返し、前記既設橋梁上部構造を撤去し、前記新設橋梁上部構造を降下させて本設する。 The present invention that solves the above problems is a bridge replacement method. A first connecting means extending in the direction of the bridge axis is provided on the lower surface side of the new bridge upper structure, and the new bridge upper structure is carried in using the upper surface of the existing bridge upper structure as a carrying path to carry in the existing bridge. The new bridge upper structure is temporarily installed on the upper part of the upper structure, both ends of the new bridge upper structure are temporarily supported, the first connecting means and the second connecting means are connected, and the second connecting means is used. Then, the part corresponding to the removal of the existing bridge upper structure is suspended and supported by the new bridge upper structure, the part corresponding to the removal of the existing bridge upper structure is cut, and the part corresponding to the removal of the existing bridge upper structure is lifted. The existing bridge upper structure is removed by sliding through the first connecting means, the removal of the plurality of existing bridge upper structures is repeated, the existing bridge upper structure is removed, and the new bridge upper structure is lowered. Set up.

上記手順において、橋梁下での作業はなく、既設橋梁上部構造上面を利用してほとんどの作業を行える。これにより、橋梁下の施工条件が厳しい場合にも適用可能となる。 In the above procedure, there is no work under the bridge, and most of the work can be performed using the upper surface of the existing bridge superstructure. This makes it applicable even when the construction conditions under the bridge are strict.

また、新設橋梁上部構造の仮支持状態を既設橋梁上部構造撤去の仮設設備として利用できる。 In addition, the temporary support state of the new bridge superstructure can be used as temporary equipment for removing the existing bridge superstructure.

なお、本願において、上部構造とは、桁と床版とを含む。 In the present application, the superstructure includes a girder and a floor slab.

上記発明において好ましくは、前記既設橋梁上部構造の撤去相当部の撤去において、前記既設橋梁上部構造の残部上に吊り降ろし、前記既設橋梁上部構造の残部上面を搬路とする。 In the above invention, preferably, in the removal of the part corresponding to the removal of the existing bridge superstructure, the bridge is hung on the remaining part of the existing bridge superstructure, and the upper surface of the remaining part of the existing bridge superstructure is used as a carrying path.

このように、既設橋梁上部構造の残部を有効活用できる。すなわち、橋梁下での作業を無くすことができる。 In this way, the rest of the existing bridge superstructure can be effectively utilized. That is, the work under the bridge can be eliminated.

上記発明において好ましくは、前記既設橋梁上部構造の撤去相当部の撤去において、摺動状態にて既設橋梁の外部に搬出する。 In the above invention, preferably, in the removal of the part corresponding to the removal of the existing bridge superstructure, the existing bridge is carried out of the existing bridge in a sliding state.

これにより、既設橋梁上部構造の残部を作業エリアとして有効活用できる。 As a result, the remaining part of the existing bridge superstructure can be effectively used as a work area.

上記発明において好ましくは、前記第2接続手段を介して、前記既設橋梁下部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、前記既設橋梁下部構造の撤去相当部を切断し、前記既設橋梁下部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させ、撤去し、複数の前記既設橋梁下部構造の撤去相当部の撤去を繰り返し、前記既設橋梁下部構造を撤去する。 In the above invention, preferably, the removal corresponding portion of the existing bridge lower structure is suspended and supported by the new bridge upper structure via the second connecting means, the removal corresponding part of the existing bridge lower structure is cut, and the existing bridge lower structure is cut. The part corresponding to the removal of the bridge lower structure is lifted, further slid and removed via the first connecting means, and the removal of the plurality of existing bridge lower structures is repeated to remove the existing bridge lower structure. To do.

本願工法は、既設橋梁下部構造の撤去にも適用できる。なお、本願において、下部構造とは、橋脚と橋台とを含む。 The construction method of the present application can also be applied to the removal of the existing bridge substructure. In the present application, the substructure includes a pier and an abutment.

上記発明において好ましくは、前記第2接続手段は、橋軸直交方向に2以上設けられ、前記第2接続手段同士は、吊桁を介して連結されている。 In the above invention, preferably, two or more of the second connecting means are provided in the direction orthogonal to the bridge axis, and the second connecting means are connected to each other via a hanging girder.

これにより、吊位置を調整できるとともに、吊状態が安定する。 As a result, the hanging position can be adjusted and the hanging state is stabilized.

上記発明において好ましくは、前記新設橋梁上部構造本設後も、前記第1接続手段が設けられた状態を維持する。 In the above invention, preferably, the state in which the first connecting means is provided is maintained even after the main construction of the new bridge superstructure.

これにより、本設後の点検時等にも再利用可能となる。 As a result, it can be reused even during inspections after the main installation.

上記発明において好ましくは、前記既設橋梁上部構造は、橋軸交差方向に延設される線路または道路の上に設けられている。 In the above invention, preferably, the existing bridge superstructure is provided on a railroad track or a road extending in the bridge axis crossing direction.

本願工法は、このような橋梁下の施工条件が厳しい場合に、好適である。橋梁下での作業はなく、橋梁下の状況に影響されにくい。 The construction method of the present application is suitable when the construction conditions under such a bridge are severe. There is no work under the bridge, and it is not easily affected by the situation under the bridge.

上記課題を解決する本発明は橋梁上部構造である。新設橋梁上部構造の下面側には、橋軸方向に延設されているレール状の第1接続手段が設けられている。 The present invention that solves the above problems is a bridge superstructure. On the lower surface side of the new bridge superstructure, a rail-shaped first connecting means extending in the direction of the bridge axis is provided.

すなわち、第1接続手段は新設橋梁の一部であり、本設後も再利用可能である。 That is, the first connecting means is a part of the new bridge and can be reused even after the main construction.

上記課題を解決する本発明は橋梁上部構造である。下面側に、橋軸方向に延設されているレール状の第1接続手段が設けられ、第2接続手段が前記第1接続手段と接続される状態で、前記第1接続手段に沿って摺動可能である。 The present invention that solves the above problems is a bridge superstructure. A rail-shaped first connecting means extending in the direction of the bridge axis is provided on the lower surface side, and the second connecting means is connected to the first connecting means and slid along the first connecting means. It is movable.

第1接続手段と第2接続手段とからなる接続機構は架替工事の撤去工程にて利用できる。また、第1接続手段は本設後も再利用可能である。 The connection mechanism including the first connection means and the second connection means can be used in the removal process of the replacement work. In addition, the first connection means can be reused even after the main installation.

本発明に係る架替工法によれば、橋梁下の施工条件が厳しい場合にも適用可能である。 According to the replacement method according to the present invention, it can be applied even when the construction conditions under the bridge are severe.

本願システム断面図Cross-sectional view of the system of the present application 接続機構(実施例および変形例)Connection mechanism (examples and modifications) 接続機構(変形例)Connection mechanism (variation example) 既設上部構造撤去例斜視図(前半)Perspective view of an example of removing the existing superstructure (first half) 既設上部構造撤去例斜視図(後半)Perspective view of an example of removing the existing superstructure (second half) 既設下部構造撤去例斜視図Perspective view of an example of removing the existing substructure 新設上部構造架設例斜視図New superstructure erection example perspective view 新設橋梁例斜視図New bridge example perspective view 既設上部構造撤去例斜視図(変形例)Example of removing the existing superstructure Perspective view (deformed example) 既設上部構造撤去例斜視図(変形例)Example of removing the existing superstructure Perspective view (deformed example) 既設上部構造撤去例斜視図(変形例)Example of removing the existing superstructure Perspective view (deformed example) 既設橋梁例斜視図Perspective view of an example of an existing bridge

〜既設橋梁例〜
図12は、本発明が適用される既設橋梁10の例である。都市部では狭隘な谷部に複数の鉄道が並走し、谷を跨ぎ線路と立体交差するように橋梁10が架けられている。既設橋梁は一般に径間が短いことが多く、上部構造(橋桁や床版を含む広義の概念)11が、両端の橋台12,12や橋脚13,13の下部構造により支持されている。なお、支承等その他の構成については図示を省略する。複数の鉄道が橋脚13,13間または橋台12橋脚13間を通過している。
~ Example of existing bridge ~
FIG. 12 is an example of an existing bridge 10 to which the present invention is applied. In urban areas, a plurality of railways run side by side in a narrow valley, and a bridge 10 is erected so as to straddle the valley and cross over a railroad track. Existing bridges generally have short spans, and the superstructure (a broad concept including bridge girders and slabs) 11 is supported by the substructures of the abutments 12 and 12 and the piers 13 and 13 at both ends. The illustration of other configurations such as bearings is omitted. A plurality of railroads pass between piers 13 and 13 or between piers 12 and 13.

架替工事は、撤去工程と新設工程が錯綜するため、複雑になる。また、架替工事では、必ず、鉄道運行状況を考慮する必要がある。例えば、列車の運行のない夜間に架替工事を行なうとしても、資機材の搬入搬出に時間を要し、仮設設備等も毎回撤去する必要があり、橋梁下での作業は事実上困難である。 The replacement work is complicated because the removal process and the new construction process are complicated. In addition, it is necessary to always consider the railway operation status in the replacement work. For example, even if the replacement work is carried out at night when there is no train operation, it takes time to carry in and out the equipment and materials, and it is necessary to remove temporary equipment every time, so it is practically difficult to work under the bridge. ..

上記施工条件下では、橋梁下での作業は可能な限りないことが好ましい。 Under the above construction conditions, it is preferable that there is no work under the bridge as much as possible.

〜特徴的構成〜
本実施形態に係る架替工法は、特徴的構成を有するシステムにより行われる。
~ Characteristic composition ~
The replacement method according to the present embodiment is performed by a system having a characteristic configuration.

図1は、本システムの断面図である。本システムは、既設橋梁10(図12参照)と新設橋梁20(図8参照)とを接続する接続機構30とを有する。接続機構30は、第1接続手段31と第2接続手段32とが接続されることにより、形成される。 FIG. 1 is a cross-sectional view of this system. This system has a connection mechanism 30 for connecting the existing bridge 10 (see FIG. 12) and the new bridge 20 (see FIG. 8). The connection mechanism 30 is formed by connecting the first connection means 31 and the second connection means 32.

第1接続手段31は、橋軸方向にレール状に延設される構造となっている。2本の第1接続手段31,31が新設橋梁上部構造21の下面側において橋軸方向に延設されている(後述する図4参照)。 The first connecting means 31 has a structure extending in a rail shape in the direction of the bridge axis. Two first connecting means 31, 31 are extended in the bridge axis direction on the lower surface side of the new bridge superstructure 21 (see FIG. 4 described later).

第2接続手段32は吊ロッドである。吊ロッド32は、一端が既設撤去対象と連結されて吊支持可能であるとともに、他端が第1接続手段31上を摺動可能に第1接続手段31と接続している。吊ロッド32は長さ調整により既設撤去対象を吊上可能である。 The second connecting means 32 is a hanging rod. One end of the suspension rod 32 is connected to the existing removal target and can be suspended and supported, and the other end is slidably connected to the first connecting means 31 on the first connecting means 31. The suspension rod 32 can suspend the existing removal target by adjusting the length.

図1の例では、吊ロッド32は上側の吊ロッド33と下側の吊ロッド34とからなる。 In the example of FIG. 1, the suspension rod 32 includes an upper suspension rod 33 and a lower suspension rod 34.

吊ロッド33の上端は第1接続手段31と摺動可能に接続されている。吊ロッド33の下端は、吊桁35に結合している。第1接続手段31と吊ロッド33との接続機構は、例えばJES継手による嵌合構造である。 The upper end of the suspension rod 33 is slidably connected to the first connecting means 31. The lower end of the hanging rod 33 is connected to the hanging girder 35. The connection mechanism between the first connecting means 31 and the suspension rod 33 is, for example, a fitting structure using a JES joint.

図2Aは接続機構の実施例であるJES継手である。JES継手は、断面C状の一端が瘤状となっており、互いのC状空間に瘤状を挿入し合うことにより、継手同士が嵌合している。図2Bは接続機構の変形例である。断面馬蹄形状空間を有する第1接続手段31内を吊ロッド33上端の円筒状係合部が摺動する。吊ロッド33は橋軸方向に幅を有していてもよい。 FIG. 2A is a JES joint which is an example of the connection mechanism. The JES joint has a hump-shaped end at one end having a C-shaped cross section, and the joints are fitted to each other by inserting the hump-shaped into each other's C-shaped space. FIG. 2B is a modified example of the connection mechanism. The cylindrical engaging portion at the upper end of the suspension rod 33 slides in the first connecting means 31 having a horseshoe-shaped space in cross section. The suspension rod 33 may have a width in the direction of the bridge axis.

図3は接続機構の別の変形例である。溝31が新設橋梁上部構造21の下面側において橋軸方向に延設されている。言い換えると、溝を有する第1接続手段31が新設橋梁上部構造21の下面側において橋軸方向に延びるように埋設されている。 FIG. 3 is another modification of the connection mechanism. The groove 31 extends in the bridge axial direction on the lower surface side of the new bridge superstructure 21. In other words, the first connecting means 31 having a groove is embedded so as to extend in the bridge axis direction on the lower surface side of the new bridge superstructure 21.

吊ロッド34の上端はジャッキ36を介して吊桁35に係合している。吊ロッド34の下端は、既設撤去対象(たとえば既設橋梁上部構造の撤去相当部11A)下面に設けられる留具37を介して既設撤去対象に係合している。 The upper end of the hanging rod 34 is engaged with the hanging girder 35 via the jack 36. The lower end of the suspension rod 34 is engaged with the existing removal target via a fastener 37 provided on the lower surface of the existing removal target (for example, the removal corresponding portion 11A of the existing bridge superstructure).

なお、留具37による係合に代えて、後施工アンカによる結合とすることにより、橋梁下での作業を可能な限り減らすことができる。 It should be noted that the work under the bridge can be reduced as much as possible by using the post-construction anchor instead of the engagement by the fastener 37.

吊桁35は橋軸直交方向を長手方向とするように配置され、接続機構30は吊桁35の両端2か所に設けられている。すなわち、吊ロッド32,32は吊桁35を介して連結している。吊桁35を介することで、既設撤去対象の吊位置を調整できる。 The suspension girders 35 are arranged so that the direction orthogonal to the bridge axis is the longitudinal direction, and connection mechanisms 30 are provided at two positions at both ends of the suspension girders 35. That is, the hanging rods 32 and 32 are connected via the hanging girder 35. The hanging position of the existing removal target can be adjusted via the hanging girder 35.

ジャッキ36は例えば、センターホールジャッキである。ジャッキ36により吊ロッド34を緊張することで、既設撤去対象を吊上可能となる。 The jack 36 is, for example, a center hole jack. By tensioning the hanging rod 34 with the jack 36, the existing removal target can be lifted.

各構成間の相互作用については、架替工事手順において説明する。 The interaction between each configuration will be described in the replacement work procedure.

〜架替工事手順〜
図4および図5は、既設上部構造撤去例の斜視図である。架替工事は、撤去工程と新設工程とを含む。とくに、本願手順では、撤去工程と新設工程とが相互連動していることを特徴とする。
~ Replacement work procedure ~
4 and 5 are perspective views of an example of removing the existing superstructure. The replacement work includes a removal process and a new construction process. In particular, the procedure of the present application is characterized in that the removal process and the new installation process are interlocked with each other.

予め、既設橋梁上部構造11外部において、新設橋梁上部構造21を構築しておく。桁長を調整できるように、両端に架設桁を延設してもよい。既設橋梁上部構造11上面を搬路として、新設橋梁上部構造21を搬入する。 A new bridge superstructure 21 is constructed in advance outside the existing bridge superstructure 11. The erection girders may be extended at both ends so that the girder length can be adjusted. The new bridge superstructure 21 is carried in using the upper surface of the existing bridge superstructure 11 as a carrying path.

もしくは、既設橋梁上部構造11外部より新設橋梁上部構造21の構成部品を搬入し、既設橋梁上部構造11上面において新設橋梁上部構造21を構築してもよい。なお、新設橋梁上部構造21との搬入とは、構成部品の搬入も含む。 Alternatively, the components of the new bridge superstructure 21 may be carried in from the outside of the existing bridge superstructure 11 to construct the new bridge superstructure 21 on the upper surface of the existing bridge superstructure 11. The carry-in with the new bridge superstructure 21 includes the carry-in of component parts.

既設橋梁上部構造11の両端であって、既設橋台12の橋軸直角方向両脇の地山(半透明で図示)に仮設ベント41,41を設ける。なお、仮設ベント41,41間隔を広げることにより、既設橋梁上部構造11上面にアクセス容易となる。 Temporary vents 41 and 41 are provided at both ends of the existing bridge superstructure 11 and on the grounds (semi-transparent and shown) on both sides of the existing bridge stand 12 in the direction perpendicular to the bridge axis. By widening the intervals between the temporary vents 41 and 41, it becomes easy to access the upper surface of the existing bridge superstructure 11.

仮設ベント41,41により新設橋梁上部構造21の両端を仮支持しながら、ジャッキアップし、既設橋梁上部構造11の上部に、新設橋梁上部構造21を仮設する。なお、新設橋梁上部構造21幅を既設橋梁上部構造残部11幅より広くしている。 While temporarily supporting both ends of the new bridge superstructure 21 by the temporary vents 41 and 41, jack up is performed, and the new bridge superstructure 21 is temporarily installed above the existing bridge superstructure 11. The width of the new bridge superstructure 21 is wider than the width of the remaining 11 width of the existing bridge superstructure.

次いで、既設橋梁上部構造撤去相当部11Aにおいて接続機構30を介して、既設橋梁上部構造撤去相当部11Aと新設橋梁上部構造21とを接続する(図1参照)。その結果、既設橋梁上部構造撤去相当部11Aは新設橋梁上部構造21に吊支持される。なお、安定性の観点より長手物の吊支持は4点以上が一般的である(図4参照)。 Next, the existing bridge superstructure removal equivalent portion 11A connects the existing bridge superstructure removal equivalent portion 11A and the new bridge superstructure 21 via the connection mechanism 30 (see FIG. 1). As a result, the existing bridge superstructure removal equivalent portion 11A is suspended and supported by the new bridge superstructure 21. From the viewpoint of stability, the suspension support of a long object is generally 4 points or more (see FIG. 4).

吊支持状態において、既設橋梁上部構造撤去相当部11Aを切断し撤去ブロックとする。ジャッキ36を介して撤去ブロック11Aを吊り上げ、撤去ブロック11A下面が既設橋梁上部構造残部11B上面位置より高くなるようにする(図4参照)。これにより、撤去ブロック11Aは摺動可能となる。 In the suspended support state, the existing bridge superstructure removal equivalent portion 11A is cut to form a removal block. The removal block 11A is lifted via the jack 36 so that the lower surface of the removal block 11A is higher than the upper surface position of the existing bridge superstructure remaining portion 11B (see FIG. 4). As a result, the removal block 11A becomes slidable.

既設橋梁上部構造撤去相当部11Aに隣接する既設橋梁上部構造残部11Bに搬出台車42を待機させておく。第1接続手段31を介して撤去ブロック11Aを摺動させ、ジャッキ36を介して撤去ブロック11Aを搬出台車42に吊り降ろす(図5参照)。 The carry-out carriage 42 is kept on standby in the existing bridge superstructure remaining portion 11B adjacent to the existing bridge superstructure removal equivalent portion 11A. The removal block 11A is slid via the first connecting means 31, and the removal block 11A is suspended from the carry-out carriage 42 via the jack 36 (see FIG. 5).

既設橋梁上部構造残部11B上面を搬出台車42の搬路とし、撤去ブロック11Aを搬出する。このとき仮設ベント41,41間隔が充分に広ければ、仮設ベント41,41間より外部に搬出できる。 The upper surface of the remaining portion 11B of the existing bridge superstructure is used as a carry-out path for the carry-out carriage 42, and the removal block 11A is carried out. At this time, if the intervals between the temporary vents 41 and 41 are sufficiently wide, the temporary vents 41 and 41 can be carried out from between the temporary vents 41 and 41.

図6は既設下部構造撤去例の斜視図である。既設橋梁上部構造撤去相当部11Aの一部を搬出し、開口ができれば、上方より既設橋脚撤去相当部13Aにアクセス可能となる。 FIG. 6 is a perspective view of an example of removing the existing substructure. If a part of the existing bridge superstructure removal equivalent portion 11A is carried out and an opening is made, the existing bridge pier removal equivalent portion 13A can be accessed from above.

接続機構30を介して、既設橋脚撤去相当部13Aと新設橋梁上部構造21とを接続する結果、既設橋脚撤去相当部13Aは新設橋梁上部構造21に吊支持される。なお、図示のように2点支持としてもよい。 As a result of connecting the existing bridge pier removal equivalent portion 13A and the new bridge superstructure 21 via the connection mechanism 30, the existing bridge pier removal equivalent portion 13A is suspended and supported by the new bridge superstructure 21. As shown in the figure, two-point support may be used.

吊支持状態において、既設橋脚撤去相当部13Aを切断し撤去ブロックとする。撤去ブロック11Aを搬出した手順にて、第1接続手段31を介して撤去ブロック13Aを摺動させ搬出する。 In the suspended support state, the existing bridge pier removal equivalent portion 13A is cut to form a removal block. In the procedure of carrying out the removal block 11A, the removal block 13A is slid and carried out via the first connecting means 31.

撤去ブロック11Aおよび撤去ブロック13Aを搬出した手順を繰り返し、既設橋梁上部構造残部11Bや既設橋脚残部13Bを撤去する。 The procedure of carrying out the removal block 11A and the removal block 13A is repeated to remove the existing bridge superstructure remaining portion 11B and the existing pier remaining portion 13B.

図7は新設上部構造架設例の斜視図である。既設橋梁上部構造11および既設橋脚13を全て撤去した状態において、第1接続手段31と第2接続手段32との接続を解除し、第2接続手段32を取り外す。そして、仮設ベント41,41により新設橋梁上部構造21の両端を仮支持しながら、ジャッキダウンする。桁長を調整するように、両端架設桁を外す。新設橋梁上部構造21を降下させ、既設橋台12,12の所定位置に本設する。 FIG. 7 is a perspective view of an example of erection of a new superstructure. In a state where the existing bridge superstructure 11 and the existing pier 13 are all removed, the connection between the first connecting means 31 and the second connecting means 32 is released, and the second connecting means 32 is removed. Then, the temporary vents 41 and 41 jack down while temporarily supporting both ends of the new bridge superstructure 21. Remove the erection girders at both ends so as to adjust the girder length. The new bridge superstructure 21 is lowered and permanently installed at predetermined positions of the existing piers 12 and 12.

〜効果〜
上記手順を概略化すると、撤去対象の吊支持→切断→吊り上げ→摺動→既設橋梁上部構造上面への吊り降ろし→搬出の繰り返しである。上記手順において、原則として橋梁下での作業はなく、既設橋梁上部構造11上面を利用してほとんどの作業を行うことができる。
~effect~
The above procedure can be outlined as follows: suspension support for removal target → cutting → lifting → sliding → suspension to the upper surface of the existing bridge superstructure → carry-out. In the above procedure, as a general rule, there is no work under the bridge, and most of the work can be performed using the upper surface of the existing bridge superstructure 11.

すなわち、鉄道運行状況に影響されずに、架替工事を行なうことができる。尤も、施工実務では安全優先の観点から、実際は、列車運行のない夜間に行なわれるものと思われる。しかし、夜間施工に限定されたとしても、列車運行中も既設橋梁上部構造上面にて準備作業ができ、また、線路への資機材搬入搬出や仮設工事がないことから、大幅な工期短縮、安全性の確保が期待でき、その結果、コスト削減となる。 That is, the replacement work can be carried out without being affected by the railway operation status. However, from the viewpoint of safety priority in construction practice, it seems that it is actually carried out at night when there is no train operation. However, even if it is limited to nighttime construction, preparatory work can be done on the upper surface of the existing bridge superstructure even during train operation, and there is no loading and unloading of materials and equipment to the railroad track or temporary construction, so the construction period is significantly shortened and safety It can be expected to secure the sex, and as a result, the cost will be reduced.

また、撤去工程と新設工程とが相互連動している、言い換えると、新設橋梁上部構造21の仮支持状態を既設橋梁上部構造11撤去および既設橋脚13撤去の仮設設備として利用できるため、この点でも工期短縮およびコスト削減が期待できる。 In addition, the removal process and the new construction process are interlocked with each other, in other words, the temporary support state of the new bridge superstructure 21 can be used as temporary equipment for removing the existing bridge superstructure 11 and removing the existing pier 13. Expected to shorten the construction period and reduce costs.

このように、本実施形態に係る架替工法は、橋梁交差方向に複数の鉄道が並走するような橋梁下での施工条件が厳しい場合にも適用可能である。 As described above, the replacement method according to the present embodiment can be applied even when the construction conditions under the bridge are severe such that a plurality of railways run in parallel in the bridge crossing direction.

〜本設後の第1接続手段の利用〜
図8は、本発明より架け替えされた新設橋梁20の例である。接続機構30のうち第2接続手段32は取り外すが、本設後も第1接続手段31は新設橋梁上部構造21の下面側に設置されている状態を維持する。すなわち、第1接続手段31は、新設橋梁20の一部である。
-Use of the first connection means after the main installation-
FIG. 8 is an example of a new bridge 20 that has been replaced according to the present invention. Although the second connecting means 32 of the connecting mechanism 30 is removed, the first connecting means 31 remains installed on the lower surface side of the new bridge superstructure 21 even after the main installation. That is, the first connecting means 31 is a part of the new bridge 20.

新設橋梁上部構造21の下面側の点検やメンテナンスの際は、第1接続手段31を利用して、作業ゴンドラ(図示省略)を吊り下げて摺動させる。これにより、点検やメンテナンスのための仮設工事が大幅に軽減され、点検やメンテナンスが容易となる。 When inspecting or maintaining the lower surface side of the new bridge superstructure 21, the work gondola (not shown) is suspended and slid by using the first connecting means 31. As a result, temporary work for inspection and maintenance is greatly reduced, and inspection and maintenance are facilitated.

〜変形例〜
本願発明の理解を容易にするために、一例として上記実施形態について説明したが、本願発明は上記実施形態に限定されず、本発明の技術思想の範囲で種々の変形が可能である。
~ Modification example ~
In order to facilitate the understanding of the present invention, the above embodiment has been described as an example, but the present invention is not limited to the above embodiment, and various modifications can be made within the scope of the technical idea of the present invention.

図9は既設上部構造撤去変形例の斜視図である。上記実施形態では、撤去ブロック11Aを吊り上げ(図4参照)後、摺動させ、搬出台車42に吊り降ろし、(図5参照)、既設橋梁上部構造残部11B上面を搬出台車42の搬路として搬出しているのに対し、変形例では、撤去ブロック11Aを吊り上げ(図4参照)後、第1接続手段31末端まで摺動させ、吊り降ろし、既設橋梁10端部より搬出する。 FIG. 9 is a perspective view of a modified example of removing the existing superstructure. In the above embodiment, the removal block 11A is lifted (see FIG. 4), slid, hung on the carry-out carriage 42 (see FIG. 5), and the upper surface of the existing bridge superstructure remaining portion 11B is carried out as a carry-out path for the carry-out carriage 42. On the other hand, in the modified example, after the removal block 11A is lifted (see FIG. 4), it is slid to the end of the first connecting means 31, hung down, and carried out from the end of the existing bridge 10.

すなわち、変形例においては、既設橋梁上部構造残部11B上面を搬路として利用しない。これにより、既設橋梁上部構造残部11B上面を作業スペースとして有効利用でき、施工性や安全性が更に向上する。 That is, in the modified example, the upper surface of the existing bridge superstructure remaining portion 11B is not used as a carrying path. As a result, the upper surface of the existing bridge superstructure remaining portion 11B can be effectively used as a work space, and workability and safety are further improved.

図10は別の既設上部構造撤去変形例の斜視図である。上記実施形態では、既設橋梁上部構造11および既設橋脚13については撤去し、既設橋台12については再利用しているのに対し、変形例では、既設橋台12も撤去し、新設橋台22を設ける。 FIG. 10 is a perspective view of another modified example of removing the existing superstructure. In the above embodiment, the existing bridge superstructure 11 and the existing pier 13 are removed and the existing pier 12 is reused, whereas in the modified example, the existing bridge 12 is also removed and a new pier 22 is provided.

まず、既設橋台12,12の橋軸方向外側に新設橋台22,22を設ける。新設橋台22,22に仮設ベント41,41を設け、新設橋梁上部構造21の両端を仮支持する。 First, new piers 22 and 22 are provided on the outside of the existing piers 12 and 12 in the bridge axis direction. Temporary vents 41 and 41 are provided on the new piers 22 and 22, and both ends of the new bridge superstructure 21 are temporarily supported.

撤去ブロック11Aおよび撤去ブロック13Aを搬出した手順にて、既設橋台12を切断して撤去ブロックとし、第1接続手段31を介して撤去ブロック摺動させ搬出する。このとき、撤去ブロックを新設橋台22まで摺動させ、新設橋台22から搬出すると、既設橋梁上部構造残部11B全面を作業スペースとして有効利用できる。 In the procedure of carrying out the removal block 11A and the removal block 13A, the existing abutment 12 is cut to form a removal block, and the removal block is slid and carried out via the first connecting means 31. At this time, if the removal block is slid to the new pier 22 and carried out from the new pier 22, the entire surface of the existing bridge superstructure remaining portion 11B can be effectively used as a work space.

既設橋梁上部構造11および既設橋梁上部構造12,13を全て撤去した状態において、新設橋梁上部構造21を降下させ、新設橋台22,22の所定位置に本設する。 In a state where the existing bridge superstructure 11 and the existing bridge superstructures 12 and 13 are all removed, the new bridge superstructure 21 is lowered and the new bridge superstructures 22 and 22 are permanently installed at predetermined positions.

なお、新設橋台22幅を既設橋台12幅より広くするとともに、新設橋梁上部構造21幅を既設橋梁上部構造残部11B幅より広くすると、広い搬出スペースを確保でき、施工性がさらに向上する。 If the width of the new bridge 22 is wider than the width of the existing bridge 12 and the width of the new bridge superstructure 21 is wider than the width of the existing bridge superstructure remaining 11B, a wide carry-out space can be secured and the workability is further improved.

図11は別の既設上部構造撤去変形例の斜視図である。撤去ブロック11Aを吊り上げ後、摺動させ、隣接する既設橋梁上部構造残部11Bに吊り降ろし、既設橋梁上部構造残部11B上で小割し、搬出する。 FIG. 11 is a perspective view of another modified example of removing the existing superstructure. After the removal block 11A is lifted, it is slid, suspended on the adjacent existing bridge superstructure remaining portion 11B, divided into small pieces on the existing bridge superstructure remaining portion 11B, and carried out.

図12に示す既設橋梁例では、既設橋脚13の存在を前提としたが、本願発明は橋脚のない既設橋梁にも適用できる。その場合、当然、既設橋脚13の撤去工程は不要である。すなわち、本願発明において、既設橋脚13撤去は必須でない。 In the example of the existing bridge shown in FIG. 12, the existence of the existing pier 13 is premised, but the present invention can be applied to the existing bridge without the pier. In that case, of course, the step of removing the existing pier 13 is unnecessary. That is, in the present invention, the removal of the existing pier 13 is not essential.

ところで、半世紀以上前に架けられた既設橋梁は一般に径間長が短いが、断面構造や材料を検討したり、PC橋、アーチ橋、斜張橋、吊橋としたり、適宜、近年の技術を用いることで、新設橋梁の径間長を長くできる。その結果、新設橋脚は不要である。 By the way, existing bridges built more than half a century ago generally have a short span length, but we have examined the cross-sectional structure and materials, made PC bridges, arch bridges, cable-stayed bridges, suspension bridges, etc. By using it, the span length of the new bridge can be lengthened. As a result, no new piers are needed.

上記実施形態では、橋梁下での施工条件が厳しい例として、橋梁交差方向に複数の鉄道が並走する(図12参照)場合を挙げたが、橋梁下にて主要幹線道路が交差する場合や、河川が交差し、流れが速く台船を停泊困難な場合等においても好適である。 In the above embodiment, as an example in which the construction conditions under the bridge are strict, a case where a plurality of railways run in parallel in the direction of the bridge intersection (see FIG. 12) is mentioned, but a case where the main highways intersect under the bridge or It is also suitable when rivers intersect and the flow is fast and it is difficult to anchor the pontoon.

図12に示す既設橋梁例では、道路橋としたが、鉄道橋でもよい。 In the example of the existing bridge shown in FIG. 12, the road bridge is used, but a railway bridge may be used.

10 既設橋梁
11 既設橋梁上部構造
12 既設橋台(下部構造)
13 既設橋脚(下部構造)
20 新設橋梁
11 新設橋梁上部構造
12 既設橋台(下部構造)
30 接続機構
31 第1接続手段(レール状)
32 第2接続手段(吊ロッド)
33 上側吊ロッド
33 下側吊ロッド
35 吊桁
36 ジャッキ
37 留具
41 仮設ベント
42 搬出台車
10 Existing bridge 11 Existing bridge superstructure 12 Existing bridge (substructure)
13 Existing pier (substructure)
20 New bridge 11 New bridge superstructure 12 Existing bridge (substructure)
30 Connection mechanism 31 First connection means (rail shape)
32 Second connection means (hanging rod)
33 Upper hanging rod 33 Lower hanging rod 35 Hanging girder 36 Jack 37 Fastener 41 Temporary vent 42 Carrying trolley

Claims (9)

新設橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられており、
既設橋梁上部構造上面を搬路として、前記新設橋梁上部構造を搬入し、
既設橋梁上部構造の上部に、前記新設橋梁上部構造を仮設し、前記新設橋梁上部構造の両端を仮支持し、
前記第1接続手段と第2接続手段とを接続するとともに、前記第2接続手段を介して、前記既設橋梁上部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、
前記既設橋梁上部構造の撤去相当部を切断し、
前記既設橋梁上部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させて、撤去し、
複数の前記既設橋梁上部構造の撤去相当部の撤去を繰り返し、前記既設橋梁上部構造を撤去し、
前記新設橋梁上部構造を降下させて本設する
ことを特徴とする橋梁の架替工法。
On the lower surface side of the new bridge superstructure, a first connecting means extending in the direction of the bridge axis is provided.
The new bridge superstructure is carried in using the upper surface of the existing bridge superstructure as a carrying path.
The new bridge superstructure is temporarily installed on the upper part of the existing bridge superstructure, and both ends of the new bridge superstructure are temporarily supported.
The first connecting means and the second connecting means are connected, and the removal corresponding portion of the existing bridge superstructure is suspended and supported by the new bridge superstructure via the second connecting means.
The part corresponding to the removal of the existing bridge superstructure was cut.
The part corresponding to the removal of the existing bridge superstructure is lifted and further slid through the first connecting means to be removed.
Repeatedly removing the parts corresponding to the removal of the plurality of existing bridge superstructures, and removing the existing bridge superstructure.
A bridge replacement method characterized in that the superstructure of the newly constructed bridge is lowered and permanently installed.
前記既設橋梁上部構造の撤去相当部の撤去において、
前記既設橋梁上部構造の残部上に吊り降ろし、
前記既設橋梁上部構造の残部上面を搬路とする
ことを特徴とする請求項1記載の橋梁の架替工法。
In the removal of the part corresponding to the removal of the existing bridge superstructure
Suspended on the rest of the existing bridge superstructure
The bridge replacement method according to claim 1, wherein the upper surface of the remaining portion of the existing bridge superstructure is used as a carrying path.
前記既設橋梁上部構造の撤去相当部の撤去において、
摺動状態にて既設橋梁の外部に搬出する
ことを特徴とする請求項1記載の橋梁の架替工法。
In the removal of the part corresponding to the removal of the existing bridge superstructure
The bridge replacement method according to claim 1, wherein the bridge is carried out of the existing bridge in a sliding state.
前記第2接続手段を介して、前記既設橋梁下部構造の撤去相当部を前記新設橋梁上部構造に吊支持させ、
前記既設橋梁下部構造の撤去相当部を切断し、
前記既設橋梁下部構造の撤去相当部を吊り上げ、さらに、前記第1接続手段を介して摺動させ、撤去し、
複数の前記既設橋梁下部構造の撤去相当部の撤去を繰り返し、前記既設橋梁下部構造を撤去する
ことを特徴とする請求項1〜3いずれか記載の橋梁の架替工法。
A portion corresponding to the removal of the existing bridge lower structure is suspended and supported by the new bridge upper structure via the second connecting means.
The part corresponding to the removal of the existing bridge substructure was cut.
The part corresponding to the removal of the existing bridge lower structure is lifted, and then slid and removed via the first connecting means.
The bridge replacement method according to any one of claims 1 to 3, wherein the removal of a plurality of existing bridge substructures corresponding to the removal is repeated, and the existing bridge substructure is removed.
前記第2接続手段は、橋軸直交方向に2以上設けられ、
前記第2接続手段同士は、吊桁を介して連結されている
ことを特徴とする請求項1〜4いずれか記載の橋梁の架替工法。
Two or more of the second connecting means are provided in the direction orthogonal to the bridge axis.
The bridge replacement method according to any one of claims 1 to 4, wherein the second connecting means are connected to each other via a suspension girder.
前記新設橋梁上部構造本設後も、前記第1接続手段が設けられた状態を維持する
ことを特徴とする請求項1〜5いずれか記載の橋梁の架替工法。
The bridge replacement method according to any one of claims 1 to 5, wherein the state in which the first connecting means is provided is maintained even after the construction of the new bridge superstructure.
前記既設橋梁上部構造は、橋軸交差方向に延設される線路または道路の上に設けられている
ことを特徴とする請求項1〜6いずれか記載の橋梁の架替工法。
The bridge replacement method according to any one of claims 1 to 6, wherein the existing bridge superstructure is provided on a railroad track or a road extending in the crossing direction of the bridge axis.
請求項1〜7いずれか記載の架替工法により架設された橋梁上部構造であって、
前記橋梁上部構造の下面側には、橋軸方向に延設されている第1接続手段が設けられている
ことを特徴とする橋梁上部構造。
A bridge superstructure constructed by the replacement method according to any one of claims 1 to 7.
A bridge superstructure characterized in that a first connecting means extending in the bridge axis direction is provided on the lower surface side of the bridge superstructure.
下面側に、橋軸方向に延設されている第1接続手段が設けられ、
第2接続手段が前記第1接続手段と接続される状態で、前記第1接続手段に沿って摺動可能である。
ことを特徴とする橋梁上部構造。
A first connecting means extending in the direction of the bridge axis is provided on the lower surface side.
The second connecting means can slide along the first connecting means in a state of being connected to the first connecting means.
The bridge superstructure is characterized by this.
JP2019173549A 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure Active JP7368685B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2019173549A JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2019173549A JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Publications (2)

Publication Number Publication Date
JP2021050512A true JP2021050512A (en) 2021-04-01
JP7368685B2 JP7368685B2 (en) 2023-10-25

Family

ID=75157300

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2019173549A Active JP7368685B2 (en) 2019-09-24 2019-09-24 Bridge reconstruction method and bridge superstructure

Country Status (1)

Country Link
JP (1) JP7368685B2 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7215633B1 (en) * 2022-10-14 2023-01-31 Jfeエンジニアリング株式会社 Bridge replacement device and bridge replacement method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH073728A (en) * 1992-09-22 1995-01-06 Hazama Gumi Ltd Removal of overhead bridge and bridge girder and device therefor
JP2002332613A (en) * 2002-06-25 2002-11-22 Nippon Sharyo Seizo Kaisha Ltd Bridge removal working machine
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2006265884A (en) * 2005-03-23 2006-10-05 Ps Mitsubishi Construction Co Ltd Method of removing existing pier of viaduct
JP2007321476A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2014015808A (en) * 2012-07-11 2014-01-30 Mitsui Eng & Shipbuild Co Ltd Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction
JP2014066007A (en) * 2012-09-24 2014-04-17 Nexco-East Engineering Co Ltd Removal method of existent bridge and renewal method of existent bridge

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US8671490B1 (en) 2013-03-06 2014-03-18 Mark Carney Bridge span replacement system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH073728A (en) * 1992-09-22 1995-01-06 Hazama Gumi Ltd Removal of overhead bridge and bridge girder and device therefor
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Rebuilding construction method for bridge beam
JP2002332613A (en) * 2002-06-25 2002-11-22 Nippon Sharyo Seizo Kaisha Ltd Bridge removal working machine
JP2006265884A (en) * 2005-03-23 2006-10-05 Ps Mitsubishi Construction Co Ltd Method of removing existing pier of viaduct
JP2007321476A (en) * 2006-06-01 2007-12-13 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd Bridge and its construction method
JP2009052306A (en) * 2007-08-28 2009-03-12 Kajima Corp Construction method for replacing bridge girder
JP2014015808A (en) * 2012-07-11 2014-01-30 Mitsui Eng & Shipbuild Co Ltd Method for constructing scaffold for rebuilding construction of bridge, and apparatus for constructing scaffold for construction
JP2014066007A (en) * 2012-09-24 2014-04-17 Nexco-East Engineering Co Ltd Removal method of existent bridge and renewal method of existent bridge

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP7215633B1 (en) * 2022-10-14 2023-01-31 Jfeエンジニアリング株式会社 Bridge replacement device and bridge replacement method

Also Published As

Publication number Publication date
JP7368685B2 (en) 2023-10-25

Similar Documents

Publication Publication Date Title
CN101914897B (en) Construction method of single main cable inclined-suspender earth anchored suspension bridge
CN102182147B (en) Steel box girder erection method
CN106192620B (en) A kind of railway ballastless track supporting layer and substructure change method
JP3728657B2 (en) Railway bridge replacement method
CN109235291B (en) Railway bridge beam replacing system
JP2009052306A (en) Construction method for replacing bridge girder
CN104947604B (en) A kind of fast quick change frame construction method of high-speed railway 900t concrete box girders
KR100651663B1 (en) Reinforcement apparatus for preventing lateral vibration of truss bridge and falling off in case of lifting truss bridge
RU2495184C1 (en) Method to disassemble bridge span and device for realisation of this method
JP2003253623A (en) Rebuilding construction method for bridge beam
CN109629449B (en) Mounting and positioning support and alignment method for steel-concrete combined section of arch foot of steel box arch bridge
CN102733321B (en) Suspension bracket system for existing bridge reinforcing and building method of suspension bracket system
JP2021050512A (en) Bridge replacement method and bridge upper structure
KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
CN111705682A (en) Construction method and equipment for removing and rebuilding superstructure of widened bridge across electrified railway
KR20100021874A (en) Method for removing, installing and replacing an upper structure of bridge, and lifting apparatus and transportation vehicle of the upper structure of bridge for the method
CN205242238U (en) Be applied to self anchored suspension bridge's main girder structure
CN109056438B (en) Construction method for transformation of urban elevated ramp
KR100865752B1 (en) Shift method of bridge bearing of railroad
JP4424744B2 (en) Bridge replacement method
Hołowaty Removing weak spots from Polish railways
Colford et al. Forth Road Bridge main cables: replacement/augmentation study
JP3086810U (en) Railroad track maintenance scaffolding
Rosignoli Industrialized construction of large-scale high speed railway projects: The Modena bridges in Italy
Kun et al. Rehabilitation of reinforced concrete Gerber bridges

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20220913

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20230421

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20230510

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20230704

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20230913

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20230922

R150 Certificate of patent or registration of utility model

Ref document number: 7368685

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150