JP2971835B2 - Tunnel construction method - Google Patents

Tunnel construction method

Info

Publication number
JP2971835B2
JP2971835B2 JP9174757A JP17475797A JP2971835B2 JP 2971835 B2 JP2971835 B2 JP 2971835B2 JP 9174757 A JP9174757 A JP 9174757A JP 17475797 A JP17475797 A JP 17475797A JP 2971835 B2 JP2971835 B2 JP 2971835B2
Authority
JP
Japan
Prior art keywords
tunnel
traffic path
construction method
track
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP9174757A
Other languages
Japanese (ja)
Other versions
JPH1122366A (en
Inventor
時春 古谷
俊彦 下飯坂
明彦 美浦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HIGASHINIPPON RYOKAKU TETSUDO KK
TOKYO ERUGUUDO KK
Ishikawajima Kenzai Kogyo Co Ltd
Original Assignee
HIGASHINIPPON RYOKAKU TETSUDO KK
TOKYO ERUGUUDO KK
Ishikawajima Kenzai Kogyo Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HIGASHINIPPON RYOKAKU TETSUDO KK, TOKYO ERUGUUDO KK, Ishikawajima Kenzai Kogyo Co Ltd filed Critical HIGASHINIPPON RYOKAKU TETSUDO KK
Priority to JP9174757A priority Critical patent/JP2971835B2/en
Publication of JPH1122366A publication Critical patent/JPH1122366A/en
Application granted granted Critical
Publication of JP2971835B2 publication Critical patent/JP2971835B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【発明の属する技術分野】この発明は、線路と道路の立
体交差あるいは線路、道路の下方に上下水道、電力、ガ
ス等の地下洞道を新設する場合等のトンネルの構築工法
に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing a tunnel in a case where an underpass for water and sewage, electric power, gas and the like is newly provided below a railway or a road, or a three-dimensional intersection of a railway and a road.

【0002】[0002]

【従来の技術】線路と道路の立体交差あるいは線路、道
路の下方に下水道、電力、ガス等の地下洞道を新設する
場合、特に線路においては、列車の往来を止めることな
く構築する工法が要求されており、このため、例えば、
線路を工事桁によって仮受けした後、その下方の地盤を
掘削し、この掘削箇所にトンネルの壁体を構築する構築
工法が採用されていた。
2. Description of the Related Art When constructing an underpass for a sewer, electric power, gas, etc. under an overpass of a track or a road, or under a track or a road, a construction method is required especially for a track without stopping train traffic. For this reason, for example,
After the rails were temporarily received by construction girders, the construction method of excavating the ground below and constructing a tunnel wall at this excavation point was adopted.

【0003】[0003]

【発明が解決しようとする課題】ところで、上記工法の
場合、線路を仮受けする工事桁を支持するために、工事
桁の両端における軌道内にて、杭を打ち込んで仮橋台を
構築しなければならず、このため、車両を徐行させなけ
ればならないという問題があった。
By the way, in the case of the above-mentioned construction method, in order to support a construction girder for temporarily receiving a track, a temporary abutment must be constructed by driving a pile into a track at both ends of the construction girder. Therefore, there is a problem that the vehicle must be slowed down.

【0004】この発明は、上記事情に鑑みてなされたも
ので、車両の往来に影響を与えることなく、極めて容易
に線路、道路の下方側にトンネルを構築することが可能
なトンネルの構築工法を提供することを目的としてい
る。
The present invention has been made in view of the above circumstances, and provides a tunnel construction method capable of extremely easily constructing a tunnel below a track or road without affecting traffic of vehicles. It is intended to provide.

【0005】[0005]

【課題を解決するための手段】上記目的を達成するため
に、請求項1記載のトンネルの構築工法は、線路、道路
等の車両の通行路の下方にて、該通行路と交差する方向
へトンネルを構築するトンネルの構築工法であって、前
記通行路の下方に、トンネルの側壁となる部分に側方か
ら複数のエレメントを推進させて上下方向へ併設し、該
エレメントの上端に工事桁を架け渡せ、該工事桁によっ
て前記通行路を支持させ、その後、前記側壁間における
前記通行路の下方側の地盤を掘削し、前記エレメントの
上端に床版を架け渡せるとともに前記工事桁を撤去し、
該床版によって前記通行路を支持させることを特徴とし
ている。
According to a first aspect of the present invention, there is provided a method for constructing a tunnel, the method comprising: In a tunnel construction method for constructing a tunnel, a plurality of elements are propelled from the side to a portion serving as a side wall of the tunnel below the traffic path, and are vertically installed side by side, and a construction girder is provided at an upper end of the element. Overhang, the work girder supports the traffic path, and then excavates the ground under the traffic path between the side walls, allows a floor slab to be bridged over the upper end of the element, and removes the work girder,
The traffic path is supported by the floor slab.

【0006】請求項2記載のトンネル構築工法は、線
路、道路等の車両通行路の下方に、該通行路と交差する
方向へトンネルを構築するトンネルの構築工法であっ
て、前記通行路の下方にて、トンネルの側壁となる部分
に側方から複数のエレメントを推進させて上下方向へ併
設し、該エレメント間における上部近傍の地盤を前記通
行路ごと撤去し、この地盤を撤去した部分に、予め上部
に所定長さの通行路を敷設した床版を前記エレメントの
上端にスライドさせて架け渡せ、その後、前記側壁間に
おける前記通行路の下方側の地盤を掘削することを特徴
としている。
A tunnel construction method according to a second aspect of the present invention is a tunnel construction method for constructing a tunnel below a vehicle traffic path such as a track, a road, or the like in a direction intersecting the traffic path. At, a plurality of elements are propelled from the side to the side wall of the tunnel and are installed side by side, and the ground near the upper part between the elements is removed together with the above-mentioned passage, and the removed part of the ground is The present invention is characterized in that a floor slab, in which a predetermined length of a passage is previously laid, can be slid over the upper end of the element, and thereafter, ground below the passage between the side walls is excavated.

【0007】[0007]

【発明の実施の形態】以下、本発明の実施の形態のトン
ネルの構築工法を図によって説明する。図1及び図2に
おいて、符号1は、トンネルである。このトンネル1
は、線路(通行路)2の下側に構築されたもので、複数
のエレメント3を有する側壁4及びこれら側壁4の下端
同士の間に設けられた底版5をコンクリートによって一
体に形成した断面U字型の躯体部6と、この躯体部6の
上部に架け渡された複数の床版エレメント7からなる床
版8とから構成されている。そして、このトンネル1を
構成する床版8の上部に前記線路2が敷設されている。
なお、図1中符号11は、躯体部6の両端部に設けられ
た支持部であり、符号12及び13は、それぞれ発進
坑、到達坑である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS A tunnel construction method according to an embodiment of the present invention will be described below with reference to the drawings. 1 and 2, reference numeral 1 denotes a tunnel. This tunnel 1
Is a cross section U constructed on the lower side of a track (traffic path) 2 in which a side wall 4 having a plurality of elements 3 and a bottom plate 5 provided between lower ends of these side walls 4 are integrally formed of concrete. It is composed of a V-shaped skeleton 6 and a slab 8 composed of a plurality of slab elements 7 spanned over the skeleton 6. The track 2 is laid on the floor slab 8 constituting the tunnel 1.
In addition, the code | symbol 11 in FIG. 1 is the support part provided in the both ends of the frame part 6, and the codes | symbols 12 and 13 are a starting pit and a reaching pit, respectively.

【0008】次に、上記構成のトンネルの構築工法をそ
の施工手順に沿って説明する。 (1)図3及び図4に示すように、まず、トンネル1の
構築箇所における線路2の一方側に発進坑12を構築す
るとともに他方側に到達坑13を構築し、さらに、発進
坑12側にエレメント3の推進装置15を昇降架台16
に支持させ、この推進装置15によってエレメント3を
線路2の下側のトンネル1の側壁4部分となる箇所にお
ける地盤へ推進させる。 (2)上記のようにしてエレメント3を推進させたら、
発進坑12の推進装置15を撤去するとともに、エレメ
ント3の内部及びエレメント3同士の間にコンクリート
を打設して一体化させ、さらに、図5及び図6に示すよ
うに、発進坑12及び到達坑13においてエレメント3
の両端部分にコンクリートを打設してU字型の支持部1
1を構築する。
Next, the construction method of the tunnel having the above configuration will be described in accordance with the construction procedure. (1) As shown in FIGS. 3 and 4, first, the starting pit 12 is constructed on one side of the track 2 at the construction point of the tunnel 1 and the reaching pit 13 is constructed on the other side, and further, the starting pit 12 side The propulsion device 15 for the element 3
The element 3 is propelled by the propulsion device 15 to the ground at a location that becomes the side wall 4 portion of the tunnel 1 below the track 2. (2) If the element 3 is propelled as described above,
The propulsion device 15 of the starting pit 12 is removed, and concrete is poured into the inside of the element 3 and between the elements 3 to be integrated, and further, as shown in FIGS. Element 3 in pit 13
Concrete is cast at both ends of the U-shaped support 1
Build 1.

【0009】(3)次いで、図7から図9に示すよう
に、発進坑12に、支持架台17によって一対のガイド
レール18を、側壁4の上端部を構成するエレメント3
aと面一となるように支持し、このガイドレール18上
に複数の床版エレメント7を載置させる。 (4)車両の停止時間帯にて、図7から図10に示すよ
うに、線路2に工事桁22を敷設し、この工事桁22
を、エレメント3aの外側に設けた支承用のエレメント
3bの上端部に支承させる。 (5)この状態において、側壁4間における線路2の下
方側の地盤を掘削してトンネル1の空間を構築し、ガイ
ドレール18上に支持された床版エレメント7を、工事
桁22によって支持された線路2の下方(図7及び図9
中矢印イ方向)へ移動させ、これら床版エレメント7を
工事桁22によって支持されている線路2の下方に設置
し、側壁4の上端部を構成するエレメント3aに架け渡
す。
(3) Next, as shown in FIGS. 7 to 9, a pair of guide rails 18 is supported on the starting pit 12 by a support base 17, and an element 3 constituting the upper end of the side wall 4.
a, and a plurality of floor slab elements 7 are placed on the guide rails 18. (4) A construction girder 22 is laid on the railroad track 2 during the vehicle stop time as shown in FIGS.
Is supported on the upper end of a support element 3b provided outside the element 3a. (5) In this state, the ground below the track 2 between the side walls 4 is excavated to construct a space for the tunnel 1, and the floor slab element 7 supported on the guide rail 18 is supported by the construction girder 22. 7 and FIG.
The floor slab element 7 is installed below the track 2 supported by the construction girder 22 and is bridged over the element 3 a constituting the upper end of the side wall 4.

【0010】(6)上記のように床版エレメント7を設
置したら、これら床版エレメント7からなる床版8上に
設置された線路2にバラストを充填し、その後、工事桁
22を撤去する。
(6) After the floor slab elements 7 are installed as described above, the track 2 installed on the floor slab 8 composed of the floor slab elements 7 is filled with ballast, and then the construction girder 22 is removed.

【0011】以上、説明したように、上記トンネルの構
築工法によれば、線路2を工事桁22によって支持する
とともに、線路2の下方側にて線路2と交差する水平方
向へ推進させたエレメント3によって工事桁22を支承
した状態にて、その下方側の地盤を掘削してトンネル1
を構築するので、線路2の軌道内における作業を極力減
らすことができ、これにより、車両の運行にほとんど影
響を与えることなく、トンネル1を構築することができ
る。
As described above, according to the above-described tunnel construction method, the line 2 is supported by the construction girder 22, and the element 3 is propelled in the horizontal direction crossing the line 2 below the line 2. In the state where the construction girder 22 is supported by the
Is constructed, the work in the track of the track 2 can be reduced as much as possible, whereby the tunnel 1 can be constructed with almost no influence on the operation of the vehicle.

【0012】次に、他の手順のトンネルの構築工法を説
明する。 (A)まず、上記(1)〜(3)の作業を行う。 (B)この状態において、図11に示すように、ガイド
レール18上に載置させた床版エレメント7からなる床
版8の上面に所定長さの線路2′を敷設し、バラストを
充填しておく。 (C)車両の停止時間帯にて、側壁4間における線路2
を撤去しその下方側の地盤を、例えばブルドーザー等に
よって側壁4の上端部を構成するエレメント3aの高さ
以下となるように取り除くとともに、所定長さの線路
2′が敷設された床版8をガイドレール18に沿って移
動させて、線路2の撤去部分に配置させ、線路2、2′
同士を連結する。 (D)その後、床版8の下方側を掘削し、トンネル1を
完成させる。
Next, a tunnel construction method of another procedure will be described. (A) First, the above operations (1) to (3) are performed. (B) In this state, as shown in FIG. 11, a line 2 'having a predetermined length is laid on the upper surface of the floor slab 8 composed of the floor slab elements 7 mounted on the guide rails 18, and the ballast is filled. Keep it. (C) The track 2 between the side walls 4 during the stop time of the vehicle
And remove the ground on the lower side of the floor slab 8 with a bulldozer or the like so as to have a height equal to or less than the height of the element 3a constituting the upper end of the side wall 4, and remove the floor slab 8 on which the track 2 'having a predetermined length is laid. It is moved along the guide rail 18 and arranged at the removed portion of the track 2, and the tracks 2, 2 '
Connect each other. (D) Thereafter, the lower side of the floor slab 8 is excavated to complete the tunnel 1.

【0013】そして、このトンネルの構築工法によれ
ば、線路2の構築するトンネル1の上部に配置されてい
る部分を、予め床版8の上部に所定長さだけ敷設した線
路2′と車両の停止時間帯にて交換するので、構築作業
の迅速化を図ることができるとともに、前述の構築工法
と同様に、車両の運行にほとんど影響を与えることな
く、トンネルを構築することができる。なお、上記の実
施の形態では、いずれも鉄道の線路の下方側にトンネル
を構築する場合を例にとって説明したが、自動車の道路
の下方側にトンネルを構築する場合も上記と同様の作業
を行えば良い。
According to this tunnel construction method, a portion of the track 2, which is disposed above the tunnel 1, to be constructed, is previously laid on the floor slab 8 by a predetermined length with the track 2 ′. Since the replacement is performed during the stop time, the construction work can be speeded up, and the tunnel can be constructed with almost no influence on the operation of the vehicle, similarly to the construction method described above. In the above-described embodiments, the case where a tunnel is constructed below the railroad track is described as an example. However, the same operation as described above is performed when constructing a tunnel below the road of a car. Good.

【0014】なおまた、エレメント3としては、トンネ
ル1の壁体となるものであれば、矩形状の鋼製エレメン
トに限らず、例えば、コンクリート製のパイプ等であっ
ても良い。また、特に長尺のトンネルを構築する場合
は、エレメント3の途中をアンカーにて地盤に支持させ
ることにより施工作業を容易にかつ確実に行うことがで
きる。
The element 3 is not limited to a rectangular steel element but may be, for example, a concrete pipe or the like as long as it serves as a wall of the tunnel 1. In particular, when constructing a long tunnel, the construction work can be easily and reliably performed by supporting the middle of the element 3 on the ground with an anchor.

【0015】[0015]

【発明の効果】以上、説明したように、本発明のトンネ
ルの構築工法によれば、下記の効果を得ることができ
る。請求項1記載のトンネルの構築工法によれば、線路
あるいは道路等の車両の通行路を工事桁によって支持す
るとともに、通行路の下方側にて水平方向へ推進させた
エレメントによって工事桁を支承した状態にて、その下
方側の地盤を掘削してトンネルを構築するので、通行路
を通行する車両の運行にほとんど影響を与えることな
く、トンネルを構築することができる。
As described above, according to the tunnel construction method of the present invention, the following effects can be obtained. According to the construction method of the tunnel according to the first aspect of the present invention, the road of vehicles such as a track or a road is supported by the construction girder, and the construction girder is supported by an element which is propelled in a horizontal direction below the passage. In this state, a tunnel is constructed by excavating the ground below the ground, so that the tunnel can be constructed with almost no influence on the operation of vehicles passing through the traffic path.

【0016】請求項2記載のトンネルの構築工法によれ
ば、構築するトンネルの上部の線路あるいは道路等の車
両の通行路を、予め床版の上部に所定長さだけ敷設した
通行路と交換するので、車両の運行にほとんど影響を与
えることなく極めて迅速に構築作業を行うことができ
る。即ち、通行路が線路の場合、車両の停止時間帯内に
て迅速に工事を完了させることができ、通行路が道路の
場合、車両の規制時間を短くすることができる。
According to the construction method of the tunnel according to the second aspect, the traffic path of a vehicle such as a track or a road above the tunnel to be constructed is exchanged with a traffic path previously laid by a predetermined length above the floor slab. Therefore, the construction work can be performed very quickly without substantially affecting the operation of the vehicle. That is, when the traffic path is a track, the construction can be completed quickly within the vehicle stop time zone, and when the traffic path is a road, the regulation time of the vehicle can be shortened.

【図面の簡単な説明】[Brief description of the drawings]

【図1】 本発明の実施の形態のトンネルの構築工法に
よって構築されたトンネルの構造を説明する側断面図で
ある。
FIG. 1 is a side sectional view illustrating a structure of a tunnel constructed by a tunnel construction method according to an embodiment of the present invention.

【図2】 本発明の実施の形態のトンネルの構築工法に
よって構築されたトンネルの構造を説明する一部を断面
視した正面図である。
FIG. 2 is a front view, partially in section, illustrating a structure of a tunnel constructed by a tunnel construction method according to an embodiment of the present invention.

【図3】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の側断面図である。
FIG. 3 is a side sectional view of a tunnel construction site for explaining a tunnel construction method according to the embodiment of the present invention.

【図4】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の正面図である。
FIG. 4 is a front view of a tunnel construction site for explaining a tunnel construction method according to the embodiment of the present invention.

【図5】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の側断面図である。
FIG. 5 is a side sectional view of a tunnel construction location for explaining a tunnel construction method according to the embodiment of the present invention.

【図6】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の正面図である。
FIG. 6 is a front view of a tunnel construction site for explaining a tunnel construction method according to the embodiment of the present invention.

【図7】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の側断面図である。
FIG. 7 is a side sectional view of a tunnel construction site for explaining a tunnel construction method according to the embodiment of the present invention.

【図8】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の正面図である。
FIG. 8 is a front view of a tunnel construction site for explaining a tunnel construction method according to the embodiment of the present invention.

【図9】 本発明の実施の形態のトンネルの構築工法を
説明するトンネルの構築箇所の平面図である。
FIG. 9 is a plan view of a tunnel construction location for explaining a tunnel construction method according to the embodiment of the present invention.

【図10】 本発明の実施の形態のトンネルの構築工法
を説明するトンネルの構築箇所の断面図である。
FIG. 10 is a sectional view of a tunnel construction location for explaining a tunnel construction method according to the embodiment of the present invention.

【図11】 本発明の他の実施の形態のトンネルの構築
工法を説明するトンネルの構築箇所の側断面図である。
FIG. 11 is a side sectional view of a tunnel construction site for explaining a tunnel construction method according to another embodiment of the present invention.

【符号の説明】[Explanation of symbols]

1 トンネル 2 線路(通行路) 3、3a、3b エレメント 4 側壁 8 床版 22 工事桁 DESCRIPTION OF SYMBOLS 1 Tunnel 2 Track (passageway) 3, 3a, 3b Element 4 Side wall 8 Floor slab 22 Construction girder

───────────────────────────────────────────────────── フロントページの続き (72)発明者 下飯坂 俊彦 東京都港区東新橋1丁目2番7号 東京 エルグード株式会社内 (72)発明者 美浦 明彦 東京都千代田区有楽町一丁目12番1号 石川島建材工業株式会社内 (56)参考文献 特開 平8−170487(JP,A) 特開 平4−14595(JP,A) 特公 平4−39559(JP,B2) (58)調査した分野(Int.Cl.6,DB名) E21D 9/04 ──────────────────────────────────────────────────続 き Continuing on the front page (72) Inventor Toshihiko Shimoizaka 1-2-7 Higashi-Shimbashi, Minato-ku, Tokyo Inside Tokyo Elgoud Co., Ltd. (72) Inventor Akihiko Miura 1-12-1 Yurakucho, Chiyoda-ku, Tokyo Ishikawajima (56) References JP-A-8-170487 (JP, A) JP-A-4-14595 (JP, A) JP-B-4-39559 (JP, B2) (58) Fields surveyed ( Int.Cl. 6 , DB name) E21D 9/04

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 線路、道路等の車両の通行路の下方に、
該通行路と交差する方向へトンネルを構築するトンネル
の構築工法であって、 前記通行路の下方にて、トンネルの側壁となる部分に側
方から複数のエレメントを推進させて上下方向へ併設
し、該エレメントの上端に工事桁を架け渡せ、該工事桁
によって前記通行路を支持させ、その後、前記側壁間に
おける前記通行路の下方側の地盤を掘削し、前記エレメ
ントの上端に床版を架け渡せるとともに前記工事桁を撤
去し、該床版によって前記通行路を支持させることを特
徴とするトンネルの構築工法。
Claims 1. Below the traffic path of a vehicle such as a track, a road, etc.,
A tunnel construction method for constructing a tunnel in a direction intersecting with the traffic path, wherein a plurality of elements are propelled from the side to a side wall of the tunnel below the traffic path, and the tunnels are juxtaposed. A construction girder can be bridged over the upper end of the element, the construction girder supports the passage, and then the ground below the passage between the side walls is excavated, and a floor slab is suspended on the upper end of the element. A method for constructing a tunnel, wherein the construction girder is removable and the construction girder is removed, and the floor slab supports the traffic path.
【請求項2】 線路、道路等の車両通行路の下方に、該
通行路と交差する方向へトンネルを構築するトンネルの
構築工法であって、 前記通行路の下方にて、トンネルの側壁となる部分に側
方から複数のエレメントを推進させて上下方向へ併設
し、該エレメント間における上部近傍の地盤を前記通行
路ごと撤去し、この地盤を撤去した部分に、予め上部に
所定長さの通行路を敷設した床版を前記エレメントの上
端にスライドさせて架け渡せ、その後、前記側壁間にお
ける前記通行路の下方側の地盤を掘削することを特徴と
するトンネルの構築工法。
2. A tunnel construction method for constructing a tunnel below a vehicle traffic path such as a track, a road or the like in a direction crossing the traffic path, wherein the tunnel is formed below the traffic path as a side wall of the tunnel. A plurality of elements are propelled from the side to the part and installed in the vertical direction, the ground near the upper part between the elements is removed together with the above-mentioned traffic path, and the part where the ground is removed has a predetermined length of A tunnel construction method, wherein a floor slab on which a road is laid is slid over an upper end of the element so as to be bridged, and thereafter, a ground under the traffic path between the side walls is excavated.
JP9174757A 1997-06-30 1997-06-30 Tunnel construction method Expired - Lifetime JP2971835B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP9174757A JP2971835B2 (en) 1997-06-30 1997-06-30 Tunnel construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP9174757A JP2971835B2 (en) 1997-06-30 1997-06-30 Tunnel construction method

Publications (2)

Publication Number Publication Date
JPH1122366A JPH1122366A (en) 1999-01-26
JP2971835B2 true JP2971835B2 (en) 1999-11-08

Family

ID=15984156

Family Applications (1)

Application Number Title Priority Date Filing Date
JP9174757A Expired - Lifetime JP2971835B2 (en) 1997-06-30 1997-06-30 Tunnel construction method

Country Status (1)

Country Link
JP (1) JP2971835B2 (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4096106B2 (en) * 2003-03-14 2008-06-04 大成建設株式会社 Underpass structure and construction method
JP5209546B2 (en) * 2009-03-10 2013-06-12 東日本旅客鉄道株式会社 Construction method of the structure under the track
CN108867664B (en) * 2018-09-04 2023-09-15 临沂大学 Road-to-bridge Duan Jikeng supporting structure based on reverse construction method and construction method thereof

Also Published As

Publication number Publication date
JPH1122366A (en) 1999-01-26

Similar Documents

Publication Publication Date Title
KR101401934B1 (en) Method for constructing underground structure of railroad using steel pipe roof of two-side semicircle arch type and apparatus for pressing guidance pipe
JPH11152761A (en) Underground structure and construction method thereof
JP2008115628A (en) Construction method for elevated structure
JP3586864B2 (en) Underground structure construction method and elevated traffic path
KR102105230B1 (en) Railroad bridge construction method for keeping preexistence railroad track and rail service
JP4406577B2 (en) Digging road
JP2971835B2 (en) Tunnel construction method
JP2006214269A (en) Erected girder
JP2006502323A (en) Fixed track for railway transportation and method for manufacturing the same
JP4104781B2 (en) Construction method of underground joint structure
JP3938777B2 (en) Construction method of crossing underground structure and crossing underground structure
JP2000008304A (en) Pedestal for rail road work beam and execution method of pedestal for rail road work beam
JP3910135B2 (en) Building construction method and beam member used therefor
JP2860751B2 (en) Construction method of underpass introduction section
JP3380301B2 (en) Viaduct construction method
JP3146333B2 (en) Tunnel construction method
JP2004308225A (en) Work method and overhead bypass road
JP2006249734A (en) Construction method of crossing underground structure and crossing underground structure
KR200331521Y1 (en) None open cut tunnelling of arch type with with hume pipe and con'c rib
JP5167578B2 (en) Construction method for underground structures
JPH07259108A (en) Constructing method for underground structure
SU981495A1 (en) Road passage through embankment of acting railway and method of constructing same
JPS6237497A (en) Pipe beam structure
JPH06294280A (en) Method for constructing underground structure crossing under traffic road
JPS6131593A (en) Construction of crossing structure under traffic road

Legal Events

Date Code Title Description
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 19990727

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20070827

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20080827

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090827

Year of fee payment: 10

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100827

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110827

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110827

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120827

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120827

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130827

Year of fee payment: 14

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S111 Request for change of ownership or part of ownership

Free format text: JAPANESE INTERMEDIATE CODE: R313117

S531 Written request for registration of change of domicile

Free format text: JAPANESE INTERMEDIATE CODE: R313531

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

S533 Written request for registration of change of name

Free format text: JAPANESE INTERMEDIATE CODE: R313533

R350 Written notification of registration of transfer

Free format text: JAPANESE INTERMEDIATE CODE: R350

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term