JP3380301B2 - Viaduct construction method - Google Patents

Viaduct construction method

Info

Publication number
JP3380301B2
JP3380301B2 JP21346293A JP21346293A JP3380301B2 JP 3380301 B2 JP3380301 B2 JP 3380301B2 JP 21346293 A JP21346293 A JP 21346293A JP 21346293 A JP21346293 A JP 21346293A JP 3380301 B2 JP3380301 B2 JP 3380301B2
Authority
JP
Japan
Prior art keywords
girder
pile
embankment
line
receiving
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP21346293A
Other languages
Japanese (ja)
Other versions
JPH0748803A (en
Inventor
弘文 福島
Original Assignee
三井建設株式会社
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 三井建設株式会社 filed Critical 三井建設株式会社
Priority to JP21346293A priority Critical patent/JP3380301B2/en
Publication of JPH0748803A publication Critical patent/JPH0748803A/en
Application granted granted Critical
Publication of JP3380301B2 publication Critical patent/JP3380301B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Landscapes

  • Machines For Laying And Maintaining Railways (AREA)

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、盛土によって敷設され
た鉄道、道路等を、高架橋に切り替えるための高架橋施
工方法に関する。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing viaducts for switching railways, roads, etc. laid by embankments to viaducts.

【0002】[0002]

【従来の技術】従来、盛土によって敷設された既存の鉄
道、道路等を高架橋に切り替える際には、該既存の鉄
道、道路等が敷設された盛土の側方に仮り線を敷設して
おいて、該仮り線を供用しながら盛土を撤去し、その
後、該盛土を撤去した部分で高架橋を支持するための柱
部を施工していた。しかし、盛土地盤は軟弱であるた
め、こういった方法を行うには、既存の鉄道、道路があ
る盛土から大きく離れた位置に仮り線を敷設するか、或
いは該仮り線部分の土留めを地中深くに施工しておかな
ければならないために、用地の確保や施工工期に制限を
受けることによって、その実施が難しくなり易い。そこ
で、所謂深礎工法によって深礎杭を施工して、該深礎杭
に仮り線を支持させる手法がある。
2. Description of the Related Art Conventionally, when switching an existing railway, road, etc. laid by embankment to a viaduct, a temporary line is laid on the side of the embankment on which the existing railway, road, etc. have been laid. The embankment was removed while the temporary wire was used, and then the pillar portion for supporting the viaduct was constructed at the part where the embankment was removed. However, since the embankment board is soft, in order to carry out such a method, a temporary line should be laid at a position far away from the embankment where existing railways and roads are located, or earth retaining of the temporary line part should be performed. Since the construction must be done deep inside, it is difficult to carry out the construction if the site is secured or the construction period is restricted. Therefore, there is a method of constructing a deep foundation pile by a so-called deep foundation method and supporting the temporary wire on the deep foundation pile.

【0003】[0003]

【発明が解決しようとする課題】しかし、深礎工法を用
いる方法では、1本1本の深礎杭を施工するために要す
る施工工期及び工費自体が大きくなるので、施工費用が
高くつく。また、こういった切り替え方法のいずれも
が、長い施工工期を必要とし、その間ずっと線路が仮り
線側に移動したままになるという欠点がある。そこで、
切り替え工事中の路線は工事桁で受けるようにしておい
て、該工事桁の下側において高架橋用の柱部を施工進行
し、その後、該柱部を用いてその上に高架橋を架け替え
るようにする手法が提案されている。ところが、工事桁
を用いる方法では、該工事桁を支持するための仮橋脚を
架設しなけれなならず、こういった軟弱な盛土に仮橋脚
を架設するための適当なる方法は未だ確立されていない
のが現状である。従って、盛土上に敷設された道路、線
路等の既存の路線を工事桁で仮受けしておいて、その後
該路線を高架に切り替えすることが、的確に出来るよう
な方法の開発が望まれていた。そこで本発明は、上記事
情に鑑み、仮り線用の用地を確保したり深礎杭を打設す
る必要がなく、短い工期で、盛土を高架橋に切り替える
ことが的確に出来るようにした、高架橋施工方法を提供
するものである。
However, in the method using the deep foundation method, since the construction period and the construction cost required for constructing each one of the deep foundation piles are large, the construction cost is high. Further, each of these switching methods has a drawback that it requires a long construction period and the track is continuously moved to the temporary line side during that time. Therefore,
Make sure that the route under construction will be received by the work girder, and the pillar part for the viaduct will be constructed under the construction girder, and then the viaduct will be replaced by using the pillar part. The method of doing is proposed. However, in the method using construction girders, temporary bridge piers for supporting the construction girders must be erected, and an appropriate method for constructing temporary piers on such soft embankments has not yet been established. is the current situation. Therefore, it is desired to develop a method that allows an existing line such as a road or line laid on the embankment to be temporarily received by a construction girder and then be switched to an elevated line. It was Therefore, in view of the above circumstances, the present invention does not need to secure a site for a temporary wire or drive a deep foundation pile, and it is possible to accurately switch the embankment to a viaduct in a short construction period, viaduct construction It provides a method.

【0004】[0004]

【課題を解決するための手段】即ち本発明は、既存の路
線(5)が敷設されている盛土(21)において、前記
盛土(21)の法部(21a)に対応した位置下の地盤
(2)中に、前記路線の横断方向に複数並ぶ杭体(6)
からなる桁受け杭(60)を、該路線(5)の伸延方向
に沿って所定間隔(L1)毎に複数打設し、該桁受け杭
(60)の各杭体(6)に対応した前記法部(21a)
に前記既存の路線(5)を移設すると共に、該盛土(2
1)中に仮土留め手段(15)を、前記路線(5)の横
断方向に沿い且つ前記桁受け杭(60)を前記路線
(5)の伸延方向両側から挟む形で打設し、前記仮土留
め手段(15)上に工事桁(13)を、前記路線(5)
の伸延方向に沿って伸延する形で設置して、該工事桁
(13)上に前記移設した路線(5)を再度移設して仮
敷設し、前記仮土留め手段(15)によって、土留め
し、且つ前記工事桁(13)を支持しつつ、該盛土(2
1)中に桁受け手段(32)を、前記桁受け杭(60)
の杭体(6)間に架け渡す形で設置し、前記路線(5)
の伸延方向に沿って隣接する桁受け杭(60)間の前記
盛土(21)と、前記仮土留手段(15)とを撤去し、
該桁受け手段(32)と前記桁受け杭(60)の上部
(6b)を地上(20)に露出させ、前記仮土留め手段
(15)上に設置されていた工事桁(13)と架け替え
る形でスラブ桁(31)を、該桁受け手段(32)上に
設置して、該工事桁(13)上に仮敷設されていた前記
路線(5)を、該スラブ桁(31)上に移動敷設し、前
記スラブ桁(31)上に移動敷設した該路線(5)を、
前記地上(20)に露出した前記桁受け杭(60)の上
部(6b)を脚部とする形で高架化するようにして、構
成される。また、本発明において、前記桁受け杭(6
0)の各杭体(6)は、前記盛土(21)を介して該盛
土(21)下の地盤(2)中に押し込む形で鋼管(7)
を打設し、該鋼管(7)中にコンクリート(40)を充
填することによって形成するようにして、構成される。
なお、( )内の番号等は、図面における対応する要素
を示す、便宜的なものであり、従って、本記述は図面上
の記載に限定拘束されるものではない。以下の作用の欄
についても同様である。
[Means for Solving the Problems] That is, according to the present invention, in an embankment (21) on which an existing route (5) is laid, a ground (a position below a position corresponding to a slope (21a) of the embankment (21) is provided. 2) Inside, multiple piles lined up in the transverse direction of the line (6)
A plurality of girder receiving piles (60) made of slabs are placed at predetermined intervals (L1) along the extension direction of the line (5) to correspond to each pile body (6) of the girder receiving piles (60). The law section (21a)
The existing line (5) was relocated to the
1) In which temporary earth retaining means (15) is laid along the transverse direction of the line (5) and sandwiching the girder receiving pile (60) from both sides in the extension direction of the line (5), The work girder (13) on the temporary earth retaining means (15), and the line (5)
It is installed in the form of extending along the extension direction, and the relocated line (5) is re-installed on the construction girder (13) again for temporary laying, and the earth retaining means (15) is used for earth retaining. The embankment (2) while supporting the construction girder (13).
1) Inside the girder receiving means (32), the girder receiving pile (60)
Installed in the form of bridging between piles (6) of
The embankment (21) between the girder receiving piles (60) that are adjacent to each other along the extension direction and the temporary earth retaining means (15) are removed,
The girder receiving means (32) and the upper part (6b) of the girder receiving pile (60) are exposed to the ground (20) and bridged with the work girder (13) installed on the temporary earth retaining means (15). The slab girder (31) is installed on the girder receiving means (32) in a changed form, and the line (5) temporarily laid on the construction girder (13) is installed on the slab girder (31). The line (5) moved and laid on the slab girder (31),
It is configured such that the upper portion (6b) of the girder receiving pile (60) exposed on the ground (20) is elevated to form a leg portion. In the present invention, the girder receiving pile (6
Each pile body (6) of (0) is pushed into the ground (2) below the embankment (21) through the embankment (21) and the steel pipe (7).
Is poured and the steel pipe (7) is filled with concrete (40) to form the structure.
The numbers in parentheses () indicate the corresponding elements in the drawings for convenience, and therefore the present description is not limited to the description in the drawings. The same applies to the following action columns.

【0005】[0005]

【作用】上記した構成により、本発明は、盛土(21)
上の路線(5)を、仮土留め手段(15)によって支持
される工事桁(13)上に移設し、更に桁受け手段(3
2)を介して桁受け杭(60)によって支持されるスラ
ブ桁(31)上に移動敷設する。また、該スラブ桁(3
1)上において、地上(20)に露出した該桁受け杭
(60)の上部(6b)の高さ(H1)分だけ地盤
(2)の上方に位置するように作用する。また、本発明
において、前記桁受け杭(60)の各杭体(6)は、コ
ンクリート(40)が充填された鋼管(7)の剛性を介
して、スラブ桁(31)を支持するように作用する。
With the above-mentioned structure, the present invention provides embankment (21).
The upper line (5) is transferred to the work girder (13) supported by the temporary earth retaining means (15), and the girder receiving means (3)
2) Move and lay on the slab girder (31) supported by the girder receiving pile (60). Also, the slab girder (3
On 1), it acts so that it may be located above the ground (2) by the height (H1) of the upper part (6b) of the girder receiving pile (60) exposed on the ground (20). Further, in the present invention, each pile body (6) of the girder receiving pile (60) supports the slab girder (31) through the rigidity of the steel pipe (7) filled with concrete (40). To work.

【0006】[0006]

【実施例】図1は本発明を用いて盛土から切り替えられ
た高架橋の一例を示す図、図2は図1のII、II矢視図、
図3は乃至図10は図1に示す高架橋の施工手順の一例
を示す一連の図、図11(a)乃至(d)は本発明に用
いる基礎杭の施工手順を示す一連の図、図12は本発明
による高架橋施工方法の施工工程手順の一例を示す流れ
図、図13は本発明に用いる基礎杭において図11
(a)乃至(d)に示すものと別の施工手順を示す図、
図14は本発明に用いる基礎杭において図11(a)乃
至(d)に示すものとさらに別の施工手順を示す図であ
る。
EXAMPLE FIG. 1 is a view showing an example of a viaduct which is switched from embankment using the present invention, and FIG. 2 is a view taken along arrows II and II in FIG.
3 to 10 are a series of diagrams showing an example of the procedure for constructing the viaduct shown in FIG. 1, and FIGS. 11 (a) to 11 (d) are a sequence of diagrams showing the procedure for constructing the foundation pile used in the present invention. Is a flow chart showing an example of a construction process procedure of a viaduct construction method according to the present invention, and FIG. 13 shows a foundation pile used in the present invention in FIG.
The figure which shows the construction procedure different from what is shown in (a) thru | or (d),
FIG. 14 is a view showing a construction procedure of the foundation pile used in the present invention, which is different from that shown in FIGS. 11 (a) to 11 (d).

【0007】盛土から高架橋に切り替え中の鉄道路線の
うち、既に高架化された高架橋1は、図1又は図2に示
すように、地盤2の上方において図1左右方向に沿って
伸延する形の軌道帯3を有しており、軌道帯3上には、
既に高架に切り替えられた路線である複線の線路5、5
が、各線路5のセンターラインを図2十字印で示す位置
に配置させた形で、地面2aから所定の高さH1をなす
位置において図2紙面と交差方向に伸延するよう敷設さ
れている。各線路5は、図2一点鎖線で示す盛土21に
よって該線路5が支持されていた状態から既に高架に切
り替えられた形で、該線路5が既存していて既に撤去さ
れた盛土21位置に配置する形になっており、線路5を
支持する軌道帯3は、図1左右方向に(図2紙面と交差
方向に)示す線路5の伸延方向に沿って所定のピッチL
1毎に、線路5の横断方向に2本づつ並ぶ形で盛土21
の法部21a、21aに対応した位置下の地盤2中に打
設されたその各々が杭体である基礎杭6、6からなる桁
受け杭60によって支持された形になっている。
[0007] Among the railway lines that are being switched from embankment to viaduct, the viaduct 1 which has already been elevated is of a form extending along the horizontal direction of Fig. 1 above the ground 2, as shown in Fig. 1 or 2. It has an orbital zone 3 and on the orbital zone 3
Double track 5, 5 which has already been switched to elevated
2 is laid in such a manner that the center line of each line 5 is arranged at the position shown by the cross mark in FIG. 2 and extends in the direction intersecting with the paper surface of FIG. 2 at a position having a predetermined height H1 from the ground 2a. Each line 5 is arranged at the position of the embankment 21 where the line 5 already exists and has already been removed, with the line 5 already being supported by the embankment 21 shown in FIG. The track zone 3 supporting the track 5 has a predetermined pitch L along the extension direction of the track 5 shown in the left-right direction of FIG. 1 (in the direction intersecting the plane of FIG. 2).
For each 1 embankment 21 in the form of lining up two lines in the transverse direction of the track 5
Each of them is placed in the ground 2 below the position corresponding to the slopes 21a, 21a of the above, and each of them is supported by the girder receiving pile 60 composed of the foundation piles 6, 6 which are pile bodies.

【0008】軌道帯3は、図2に示すように、図2左右
一対に並ぶ基礎杭6、6によって構成される桁受け杭6
0上において、該左右の基礎杭6、6間に梁状に架け渡
す形で、例えば現場打設されたコンクリート材からなる
桁受け手段である受桁32と、該受桁32上に図1左右
方向に示す線路5の伸延方向に沿って伸延するよう複数
接続設置されたプレキャスト部材からなり、その上側に
線路5、5が敷設されたスラブ桁31によって構成され
ており、実施例においては受桁32の内部にはH鋼が埋
設されている。一方、スラブ桁31上にはコンクリート
製の高欄33が、該スラブ桁31上の図2左右両側にお
いて図2紙面と交差方向にそれぞれ伸延する形で施工装
着されており、なお、スラブ桁31上には、線路5を支
持するための砕石或いはコンクリートブロック等と枕木
が、前述したように各線路5を地面2aから所定の高さ
H1にレベル合わせするためにここに設置されている。
従って、スラブ桁31は、その両側に設けられた高欄3
3、33間において複線の線路5、5を載戴支持した形
で、受桁32を介してその各々が実施例においては2本
の基礎杭6、6からなる複数の桁受け杭60に支持され
た形になっており、これによって、各線路5は、桁受け
杭60の上部として各基礎杭6の地上20に露出した柱
部6bを脚部として、該柱部6bの長さに対応した高さ
H1分だけ地面2aより上側に位置する形の高架路線に
なっている。
As shown in FIG. 2, the orbital zone 3 is a girder receiving pile 6 composed of a pair of foundation piles 6, 6 arranged side by side in FIG.
0, a girder 32, which is a girder receiving means made of concrete material cast on site, for example, in the form of being bridged between the left and right foundation piles 6, 6, and the girder 32 shown in FIG. The slab girder 31 is composed of a plurality of precast members connected and installed so as to extend along the extension direction of the line 5 shown in the left-right direction, and is constituted by a slab girder 31 on which the lines 5 and 5 are laid. H steel is embedded inside the girder 32. On the other hand, concrete balustrades 33 are mounted on the slab girders 31 on the left and right sides of the slab girders 31 so as to extend in the direction intersecting with the plane of FIG. In this case, crushed stones or concrete blocks for supporting the tracks 5 and sleepers are installed here for leveling each track 5 from the ground 2a to a predetermined height H1 as described above.
Therefore, the slab girder 31 is provided with balustrades 3 provided on both sides thereof.
In the form of supporting and supporting double-track lines 5 and 5 between 3 and 33, each of them is supported via a receiving girder 32 to a plurality of girder receiving piles 60, each of which is two foundation piles 6 and 6 in the embodiment. As a result, each line 5 corresponds to the length of the pillar portion 6b by using the pillar portion 6b exposed on the ground 20 of each foundation pile 6 as the upper portion of the girder receiving pile 60 as a leg portion. The elevated line is located above the ground 2a by the height H1.

【0009】桁受け杭60を構成している各基礎杭6
は、図1又は図2に示すように、リブ付き鋼管からなる
ケーシングチューブ7をそれぞれ有しており、各ケーシ
ングチューブ7は地盤2中から地上20に跨って配置す
る形になっている。ケーシングチューブ7内にはコンク
リート40が打設充填されており、そして、基礎杭6に
は、該基礎杭6を構成しているケーシングチューブ7内
の下端部からコンクリート40が該ケーシングチューブ
7外周囲の地盤2に浸入硬化することによって、該ケー
シングチューブ7が地盤2に定着された形の地中杭が形
成された形で、地盤2中に杭部6aが形成されている。
従って、基礎杭6において杭部6aより上側の残りの部
分は、高架橋1構築後に形成された地面2aより上側に
おいてケーシングチューブ7の外周囲が地上20に露出
する形で、前記軌道帯3のスラブ桁31を載戴支持する
ための柱部6bが、桁受け杭60の上部を構成した形で
それぞれ形成されている。
Each foundation pile 6 constituting the girder receiving pile 60
As shown in FIG. 1 or FIG. 2, each has a casing tube 7 made of a ribbed steel pipe, and each casing tube 7 is arranged to extend from the ground 2 to the ground 20. Concrete 40 is poured and filled in the casing tube 7, and the foundation pile 6 is filled with the concrete 40 from the lower end of the casing tube 7 forming the foundation pile 6. When the casing tube 7 is fixed to the ground 2 to form an underground pile by being infiltrated into the ground 2, the pile portion 6a is formed in the ground 2.
Therefore, in the remaining portion of the foundation pile 6 above the pile portion 6a, the outer periphery of the casing tube 7 is exposed to the ground 20 above the ground 2a formed after the viaduct 1 is constructed. The pillar portions 6b for mounting and supporting the girders 31 are respectively formed so as to configure the upper portions of the girder receiving piles 60.

【0010】一方、盛土から高架橋に切り替え中の鉄道
路線のうち、未だ高架化されていない部分には盛土21
が、図3に示すように(図2一点鎖線で示すように)、
横断面形状山形に形成された形で後に地面2aとなる部
分の上側に配設形成されており、盛土21上の横断面左
右方向中央の頂部21bには、高架に切替えすべき既存
の路線である線路5、5が、高架後には地面2aとなる
位置から所定の高さH1をなす形で、先に述べた高架化
済みの線路5、5と接続して、ここに敷設されている。
On the other hand, among the railway lines that are being switched from embankment to viaduct, embankment 21 is applied to the part which is not elevated yet.
However, as shown in FIG. 3 (as shown by the chain line in FIG. 2),
The cross-sectional shape is formed in a mountain shape and is arranged above the part that will be the ground 2a later. The top 21b of the embankment 21 at the center of the cross-section in the left-right direction is an existing line to be switched to an elevated structure. The certain tracks 5, 5 are connected to the above-mentioned elevated tracks 5, 5 so as to form a predetermined height H1 from the position which becomes the ground 2a after the overpass and are laid here.

【0011】盛土から切り替えられる高架橋1は以上の
ような構成を有しているので、既存の盛土21を高架橋
1に切り替えるには、図12に示すように、工程手順F
LO−1に沿って、線路5の伸延方向である図1左右方
向に所定の長さをなす1区間づつ作業を行っていく形
で、切り替え作業を行っていく。まず、図3に示すよう
な現況を呈し、切り替えすべき既存の路線である線路
5、5が敷設された盛土21において、図12ST1に
よって腹付盛土23を、該盛土21上に既存する複線の
線路5、5の図3両側に形成されている法部21a、2
1aを被覆して、該腹付盛土23の頂部23aが図4に
示すように盛土21の頂部21bと略同じ高さになるよ
うに盛土施工する。
Since the viaduct 1 that can be switched from the embankment has the above-described structure, in order to switch the existing embankment 21 to the viaduct 1, as shown in FIG.
The switching work is performed along the LO-1 in a manner that the work is performed for each section having a predetermined length in the lateral direction of FIG. First, in the embankment 21 in which the existing roads 5 and 5 to be switched are laid as shown in FIG. The slopes 21a, 2 formed on both sides of the lines 5, 5 in FIG.
1a is covered and embankment is performed so that the top 23a of the belly-filled embankment 23 is approximately the same height as the top 21b of the embankment 21 as shown in FIG.

【0012】こうして腹付盛土23を図4斜線領域に盛
土形成したところで、次に、図12ST2によって、既
存の線路5の伸延方向に沿ってピッチL1ごとに、図2
左右方向に示す線路5の横断方向に一対をなす基礎杭
6、6を打設する形で基礎杭工を行う。これによって、
盛土21の法部21aに対応した位置下の地盤2中に桁
受け杭60を、線路5の伸延方向に沿ってピッチL1毎
に打設施工する。即ち、高架橋1における横断面左右の
基礎杭6、6を、図5実線で示すように各法部21a位
置下に配置させる形で施工し、該基礎杭6、6の各杭部
6aと該杭部6aの上側に続く柱部6bを形成するため
に各ケーシングチューブ7内へのコンクリート打設作業
を行う。各基礎杭6を施工するには、公知のオールケー
シング工法により基礎杭を打設するときと同様に、ま
ず、図11(a)に示すように、ケーシングチューブ7
を打ち込むべき地盤2上、即ち腹付盛土23の頂部23
aの所定の杭打設位置において、図示しないやぐら等を
組んでここからハンマグラブ9を、ワイヤロープ91で
牽引する形で吊下し、該ハンマグラブ9によって地盤2
を掴み取るように掘り下げる形で掘削する。そして、当
該ハンマグラブ9による掘削が進行した分づつ、これと
同時に、ケーシングチューブ7を地盤2中に押し込んで
いく作業を繰り返していく。なお、ケーシングチューブ
7は、図11上下方向に所定長さに形成されたものを、
掘削進行とともに継ぎ足していくことによって、所定長
さ分のケーシングチューブ7を形成し、そのうちの所定
長さ分が後に地面2aとなる部分より深い地盤2中に配
置する形になるように、ここに押し込んでいく。
In this way, when the embankment 23 with abdomen is formed in the shaded area in FIG. 4, next, as shown in FIG. 12ST2, along the extending direction of the existing line 5, at every pitch L1, as shown in FIG.
The foundation pile work is performed by placing a pair of foundation piles 6, 6 in the transverse direction of the line 5 shown in the left-right direction. by this,
The girder receiving piles 60 are placed in the ground 2 below the position corresponding to the slope 21a of the embankment 21 at every pitch L1 along the extension direction of the track 5. That is, the foundation piles 6 and 6 on the left and right of the cross-section in the viaduct 1 are constructed so as to be arranged below the positions of the slopes 21a as shown by the solid lines in FIG. 5, and the foundation piles 6 and 6 of the foundation piles 6 and 6 are Concrete pouring work is performed in each casing tube 7 to form the pillar portion 6b continuing to the upper side of the pile portion 6a. To construct each foundation pile 6, first, as shown in FIG. 11 (a), the casing tube 7 is used, as in the case of placing the foundation pile by the known all-casing method.
On the ground 2 to be driven, that is, the top 23 of the embankment 23 with belly
At a predetermined pile driving position of a, a hammer not shown is assembled to hang the hammer mug 9 from here to be pulled by the wire rope 91, and the hammer mug 9 is used to suspend the ground 2
It excavates in the form of digging down so as to grab. Then, the operation of pushing the casing tube 7 into the ground 2 is repeated at the same time as the excavation by the hammer mug 9 progresses. The casing tube 7 has a predetermined length in the vertical direction in FIG.
By adding more as the excavation progresses, a casing tube 7 of a predetermined length is formed, and the predetermined length of the casing tube 7 is arranged in the ground 2 deeper than the portion to be the ground 2a later. Push in.

【0013】こうして、掘削を行いつつ、所定長さ分の
ケーシングチューブ7を図11(b)に示すように、地
盤2中に押し込んでいくと、ケーシング7内には、該ケ
ーシング7によって孔崩れが防止された状態で地盤2が
掘削された形の杭孔70が、その地盤2によって形成さ
れる孔底70a位置がケーシングチューブ7の底端7a
位置と略一致した形でそれぞれ形成される。そこで、該
杭孔70に、基礎杭6の杭部6a及び柱部6bに必要と
される鉄筋篭10を、地上20から吊り降ろしていく形
で設置する。そこで次に、図11(c)に示すように、
ケーシングチューブ7内の杭孔70中にトレミー管11
を装填して、該トレミー管11を介して杭孔70中にコ
ンクリート40を、孔底70aから打設する。すると、
各ケーシングチューブ7は単なるリブ付き鋼管であり孔
底70aは地盤20によって形成されているものである
ところから、杭孔70に打設されたコンクリート40
は、該孔底70aを介してケーシングチューブ7外周囲
の地盤2中に該ケーシングチューブ7を環状に包囲する
よう浸入し、これによって、地盤2とケーシングチュー
ブ7の接続一体化が図られた形で、杭部6aが、図11
(d)に示すように、孔底70aから打設コンクリート
40の天端40a迄の高さD1分だけ形成される。
Thus, as the casing tube 7 of a predetermined length is pushed into the ground 2 while excavating, as shown in FIG. 11 (b), a hole collapses in the casing 7 due to the casing 7. The pile hole 70 in which the ground 2 is excavated in the state where the grounding is prevented has a hole bottom 70a formed by the ground 2, and the position of the bottom 70a is the bottom end 7a of the casing tube 7.
It is formed in a shape that substantially matches the position. Therefore, the reinforcing bar cage 10 required for the pile portion 6a and the pillar portion 6b of the foundation pile 6 is installed in the pile hole 70 in a manner of being suspended from the ground 20. Therefore, next, as shown in FIG.
The tremie pipe 11 is inserted into the pile hole 70 in the casing tube 7.
And the concrete 40 is poured from the hole bottom 70a into the pile hole 70 through the tremie pipe 11. Then,
Since each casing tube 7 is a mere ribbed steel pipe and the hole bottom 70a is formed by the ground 20, the concrete 40 poured into the pile hole 70 is
Penetrates into the ground 2 around the outer circumference of the casing tube 7 through the hole bottom 70a so as to surround the casing tube 7 in an annular shape, whereby the connection between the ground 2 and the casing tube 7 is integrated. Then, the pile portion 6a is shown in FIG.
As shown in (d), a height D1 is formed from the hole bottom 70a to the top end 40a of the cast concrete 40.

【0014】従って、先に述べたように図12ST2に
よって施工形成される桁受け杭60における図5左右両
側の基礎杭6では、図5に示すように、ケーシングチュ
ーブ7内の杭孔70にコンクリート40を、該コンクリ
ート40の天端40aが該ケーシングチューブ7の上端
部分までくるように打設充填することによって、該ケー
シングチューブ7の下部を、盛土21下の地盤2中にお
いて杭部6aとして用いる一方で、該杭部6aの上側
は、ここを後に地上20に露出させて、桁受け杭60の
柱部6bとして用いる。こうして桁受け杭60の各基礎
杭6を打設すると共に、図12ST3によって、盛土2
1の頂部21bに敷設されている既存の線路5、5の外
側に受桁用土留工を施す。即ち、図12ST2によって
打設された基礎杭6付近即ち法部21a、21aに対応
した位置の盛土21中に、図5斜線で示すように、仮土
留手段として矢板15を線路5の横断方向に沿って打ち
込むことによって、受桁用仮土留工を施す。なお、矢板
15は、図8に示すように、桁受け杭60を線路5の伸
延方向(図1左右方向)両側から挟む形で、図5紙面と
交差方向に2列に打設する。
Therefore, as described above, in the foundation piles 6 on both the left and right sides of FIG. 5 in the girder receiving pile 60 formed by ST2 of FIG. 12 as shown in FIG. 5, concrete is formed in the pile holes 70 in the casing tube 7. 40 is poured and filled so that the top end 40a of the concrete 40 reaches the upper end portion of the casing tube 7, and the lower portion of the casing tube 7 is used as a pile portion 6a in the ground 2 under the embankment 21. On the other hand, the upper side of the pile portion 6a is exposed to the ground 20 later and used as the pillar portion 6b of the girder receiving pile 60. In this way, the foundation piles 6 of the girder receiving piles 60 are placed, and the embankment 2 is formed according to FIG. 12ST3.
The girder retaining work is applied to the outside of the existing tracks 5 and 5 laid on the top 21b of No. 1. That is, as shown by the diagonal lines in FIG. 5, the sheet pile 15 is provided in the transverse direction of the track 5 as a temporary earth retaining means in the embankment 21 near the foundation pile 6 placed in FIG. 12ST2, that is, at the position corresponding to the slopes 21a, 21a. Temporary earth retaining work for receiving girder is performed by driving along. As shown in FIG. 8, the sheet piles 15 are laid in two rows in a direction intersecting the plane of FIG.

【0015】こうして盛土21の頂部21bにあった線
路5、5の外側に矢板15による受桁用仮土留工を打設
すると、該矢板15による受桁用仮土留工によって仮土
留された形で、桁受け杭60が打設された部分の腹付盛
土23が土留め支保された形になる。そこで、図12S
T4によって、盛土21上の線路5、5を、該桁受け杭
60の各基礎杭6が打設された法部21a位置、即ち頂
部21bに隣接する両側の腹付け盛土23、23上位置
に移動させる形で、軌道切替作業を行う。すると、線路
5は、単に該線路5が敷設されていた部分の外側に水平
移動させることによって、簡単且つ短時間のうちに、図
6に示すように、桁受け杭60の各基礎杭6の上側即ち
盛土21における法部21aに対応した位置に軌道切替
される。こうして各線路5が切替えられた部分の盛土2
1及び腹付盛土23は、当該軌道切替え作業前に各基礎
杭6及び矢板15によって地盤強度が確保された形で山
留されているために、この状態で、該切替えられた線路
5を、仮設線として供用することが出来る。
In this way, when a temporary earth retaining girder for the girder 15 is placed outside the tracks 5 and 5 on the top 21b of the embankment 21, the temporary earth retaining girder for the girder 15 is used. The embankment 23 with the belly in the portion where the girder receiving pile 60 is placed has a shape in which the earth retaining support is provided. Therefore, FIG. 12S
By T4, the tracks 5 and 5 on the embankment 21 are located at the slope 21a position where each foundation pile 6 of the girder receiving pile 60 is placed, that is, on the abdominal embankments 23 and 23 on both sides adjacent to the top 21b. Perform track switching work by moving it. Then, the line 5 is simply horizontally moved to the outside of the portion where the line 5 was laid, so as to easily and in a short time, as shown in FIG. The trajectory is switched to the upper side, that is, the position corresponding to the slope 21a on the embankment 21. In this way, the embankment 2 where the respective lines 5 are switched
Since 1 and the embankment 23 with belly are piled up in a form in which the ground strength is secured by the foundation piles 6 and the sheet piles 15 before the track switching work, in this state, the switched line 5 is It can be used as a temporary line.

【0016】そこで、次に図12ST5によって、先に
その外側部分が既に打設された受桁用土留工の残りの部
分の矢板15を、図6斜線部に示すように、盛土21の
頂部21b下に、線路5の横断方向に沿って打設する。
当該矢板15の打設時には、先に述べた外側の矢板15
と同様に、桁受け杭60を線路5の伸延方向両側から挟
む形で、図6紙面と交差方向に2列をなすように打設す
る。こうして桁受け杭60を線路5の伸延方向両側から
挟む形で、複数の矢板15を盛土21中の仮土留手段と
して、線路5の横断面方向に並べて打設したところで、
図12ST6によって、H形鋼及び床板材等からなる工
事桁13を、該矢板15に支持させる形で図6紙面と交
差方向に伸延するように敷設する。そこで、図12ST
7によって、先に法部21aに対応した位置の腹付け盛
土23上に移設された線路5を図7に示すように工事桁
13上に再び移設して仮敷設する形で軌道切替を行う。
すると、線路5は、先に盛土21の頂部21bから法部
21aに対応した腹付盛土23上に軌道切替えされたと
きと同様に、略水平移動される形で、短時間のうちに工
事桁13上に切替え敷設される。こうして、後に述べる
盛土撤去作業を行う以前に工事桁13上に線路5を移動
切替えすることによって、線路5を早期に、該線路5が
敷設されていた盛土21位置に戻すことが出来る。即
ち、この状態で、工事桁13上の線路5は、後に地面2
aとなる位置から所定の高さH1をなす位置に配置固定
される。
Then, next, referring to FIG. 12ST5, the sheet pile 15 of the remaining portion of the girder retaining work, the outer portion of which has been already cast, is attached to the top portion 21b of the embankment 21 as shown by the hatched portion in FIG. It is placed below along the transverse direction of the track 5.
At the time of placing the sheet pile 15, the outer sheet pile 15 described above is placed.
Similarly, the girder receiving piles 60 are placed so as to sandwich the girder receiving piles 60 from both sides in the extension direction of the track 5 so as to form two rows in the direction intersecting the plane of FIG. In this way, a plurality of sheet piles 15 were placed side by side in the cross-sectional direction of the track 5 as temporary earth retaining means in the embankment 21 with the girder receiving piles 60 sandwiched from both sides in the extension direction of the track 5.
According to FIG. 12ST6, the work girder 13 made of H-shaped steel and floor board material is laid so as to extend in the direction crossing the plane of FIG. 6 while being supported by the sheet pile 15. Therefore, FIG. 12ST
7, the track 5 is transferred to the belly embankment 23 at a position corresponding to the slope 21a, and the track 5 is transferred to the work girder 13 again and temporarily laid as shown in FIG.
Then, the line 5 is moved substantially horizontally in the same manner as when the track was previously switched from the top 21b of the embankment 21 to the belly-filled embankment 23 corresponding to the slope 21a, and in a short time, the work girder can be constructed. 13 is switched and laid. In this way, by moving and switching the line 5 on the work girder 13 before performing the embankment removal work described later, the line 5 can be returned to the position of the embankment 21 where the line 5 was laid at an early stage. That is, in this state, the track 5 on the work girder 13 will be the ground 2 later.
It is arranged and fixed at a position having a predetermined height H1 from the position a.

【0017】こうして、線路5を工事桁13上に移動切
替えすると、これによって、該線路5が敷設されていた
腹付盛土23部分が開放される。そこで次に、図12S
T8によって、該線路5が移動撤去された両側の腹付盛
土23、23部分を、図7に示すように一次掘削面21
dまで掘り下げる形で撤去することによって、両側盛土
切下げ作業を行う。こうして腹付盛土23部分の盛土切
下げを行うと、図7に示すように、先に打設された複数
の矢板15の上部が位置する盛土21の頂部21b付近
が、一次掘削面21dより上側に残留配置する。そこで
この状態で、図12ST9によって、受桁部掘削作業を
行う。即ち、複数の矢板15は、桁受け杭60を線路5
の伸延方向両側から挟む形で2列をなすよう打設された
ものであるところから、該2列の矢板15、15間にお
いて工事桁13下の盛土21を、一次掘削面21d位置
まで線路5の横断方向に掘り抜く形で掘削する。する
と、盛土21中に受桁打設空間21sが、図6点線で示
すように、先に打設された桁受け杭60の各基礎杭6を
構成しているケーシングチューブ7の杭孔70と連通し
て、工事桁13下の盛土21を線路5の横断方向に梁状
に抜き取った形で形成される。そして、受桁打設空間2
1sは、線路5の伸延方向に沿って2列をなす矢板15
によって支保される形で、孔崩れの危険性なく、受桁3
2の形状に対応した形で掘削保持される。
When the line 5 is switched to the work girder 13 in this manner, the portion of the embankment 23 with the belly on which the line 5 was laid is released. Then, next, FIG. 12S
As shown in FIG. 7, the abdominal embankments 23, 23 on both sides where the track 5 has been moved and removed by T8 are removed as shown in FIG.
The embankment is cut down on both sides by removing it in the form of digging down to d. When the embankment 23 is cut down in this way, as shown in FIG. 7, the vicinity of the top 21b of the embankment 21 where the upper portions of the plurality of sheet piles 15 that have been previously placed are located above the primary excavation surface 21d. Remain placed. Therefore, in this state, the girder excavation work is performed in accordance with FIG. 12ST9. That is, the plurality of sheet piles 15 connect the girder receiving piles 60 to the rail 5
Since it is placed so as to form two rows so as to be sandwiched from both sides in the extension direction, the embankment 21 under the work girder 13 is inserted between the two rows of sheet piles 15 and 15 up to the primary excavation surface 21d position. Excavate in the form of excavating in the transverse direction of. Then, the receiving girder placing space 21s in the embankment 21 and the pile hole 70 of the casing tube 7 constituting each foundation pile 6 of the girder receiving pile 60 that has been placed earlier, as shown by the dotted line in FIG. The embankment 21 under the construction girder 13 is communicated with each other and is formed in a beam-like shape in the transverse direction of the track 5. And the space for placing the girder 2
1s is a sheet pile 15 forming two rows along the extension direction of the line 5.
It is supported by the girder 3 without the risk of hole collapse.
It is excavated and held in a shape corresponding to the shape of 2.

【0018】そこで、こうして形成された受桁打設空間
21sに、図12ST10によって、受桁32を架設し
ながら、工事桁13を受け替えていく作業を行う。即
ち、矢板15によって土留し、且つ該矢板15によって
工事桁13を支持した状態で、工事桁13下に形成した
受桁打設空間21sに、受け桁32の形状に沿った形で
型枠を組み、該型枠中にコンクリート40を、図7左右
両側の基礎杭6、6の各ケーシングチューブ7の杭孔7
0中に打設充填されたコンクリート40に打ち継ぎ接続
する形で打設するか、或いはプレキャスト梁を設置す
る。これによって、盛土21中に形成された受桁打設空
間21sに受桁32を、桁受け杭60の基礎杭6、6に
架け渡す形で構築形成する。なお、受桁打設空間21s
の図7左右両側の各腹付盛土23は、先に両側盛土切下
げ工程によって切下げ掘削された形で、その表面部分が
一次掘削面21dに位置しているので、該受桁打設空間
21sを形成するための受桁部掘削作業及びここに型枠
組み及びコンクリート打設する形での受桁32の構築作
業を行うにあたっては、作業足場を高く組み上げる必要
なく、該一次掘削面21d上でこうした作業を円滑に進
行させることが出来る。即ち、受桁32に関する施工性
が良い。こうして基礎杭6、6間に受桁32を架設する
と、該受桁32は、図8に示すように、工事桁13下に
おいて桁受け杭60の基礎杭6、6に載戴支持された形
で、図8紙面と交差方向に伸延する梁状部材として架設
される。即ち、この状態で受桁32は、図9に示すよう
に、盛土21下の地盤2中にその脚部6aが打設形成さ
れた桁受け杭60によって支持された形で、該盛土21
及び腹付盛土23が形成している一次掘削面21dの上
側に位置するように架設設置される。
Then, the work girder 13 is replaced while the girder 32 is installed in the space 21s for placing the girder thus formed in accordance with FIG. 12ST10. That is, with the sheet pile 15 retaining the soil and supporting the construction girder 13 with the sheet pile 15, a formwork is formed in the receiving girder placing space 21 s formed under the construction girder 13 in a shape along the shape of the receiving girder 32. Assembled concrete 40 in the form, pile holes 7 of each casing tube 7 of the foundation piles 6, 6 on the left and right sides in FIG.
The concrete 40 that has been poured into the ground is cast into the concrete 40 by splicing or connection, or a precast beam is installed. As a result, the receiving girder 32 is constructed and formed in the receiving girder placing space 21 s formed in the embankment 21 so as to be bridged over the foundation piles 6, 6 of the girder receiving pile 60. In addition, the girder placing space 21s
Each of the belly-filled embankments 23 on both the left and right sides of FIG. 7 has been excavated by the both-side embankment cutting process, and the surface portion thereof is located on the primary excavation surface 21d. In carrying out excavation work of the girder part for forming and construction work of the girder 32 in which formwork and concrete are placed therein, it is not necessary to assemble the work scaffold high, and such work is performed on the primary excavation surface 21d. Can proceed smoothly. That is, the workability of the receiving girder 32 is good. When the support girder 32 is thus installed between the foundation piles 6 and 6, the support girder 32 is mounted and supported on the foundation piles 6 and 6 of the girder support pile 60 under the construction girder 13, as shown in FIG. Then, it is erected as a beam-shaped member extending in a direction intersecting with the plane of FIG. That is, in this state, as shown in FIG. 9, the receiving girder 32 is supported by the girder receiving pile 60 in which the legs 6a thereof are formed in the ground 2 under the embankment 21 so as to be supported.
And is installed so as to be located above the primary excavation surface 21d formed by the embankment with belly 23.

【0019】そこで、図12ST11によって、線路5
の伸延方向に沿って隣接する受桁32、32間の盛土2
1を掘削撤去して、図12ST12によって、仮土留で
ある矢板15を撤去する作業を行う。これを行いなが
ら、図12ST13によって、工事桁13を撤去しなが
らスラブ桁31を、図9に示すように受桁32上に架設
していく作業を、交互施工する形で行う。即ち、矢板1
5上でジャッキ等を用いて線路5等を支持しておいて、
受桁32上に設置した工事桁13をスラブ桁31と架け
替える形で、該スラブ桁31を受桁32上に架設設置す
る。すると、こうして、後に線路5を支持するための部
材であるスラブ桁31を架設する作業を、該線路5が既
に敷設されている工事桁13下で着実に進行させること
が出来る。なお、こうして架設されるスラブ桁31はH
形鋼が埋設されたプレキャスト部材であることによっ
て、該プレキャスト部材を単に受桁32上に設置してこ
れを線路伸延方向に複数接続していくだけで、簡単に所
定強度のスラブ桁31が形成構築される。こうしてスラ
ブ桁31を設置形成しながら、工事桁13上に仮敷設さ
れている線路5、5を、該スラブ桁31上に順に移し替
えていく形で移動敷設する。すると、工事桁13上に仮
敷設されていた線路5は、既に後に地面2aとなる位置
から所定の高さH1をなす位置に配置固定されていて、
該工事桁13が単にプレキャスト部材を設置するだけで
構築されるスラブ桁31に移し替えられることによっ
て、線路5の軌道切替えは極短時間のうちに完了する。
なお、元は盛土21上にあった線路5が敷設される軌道
帯3は、スラブ桁31によって形成されるコンクリート
製の高架になるので、該スラブ桁31上には砕石或いは
コンクリートブロック等の線路支持部材と枕木を設置し
て、該線路支持部材及び枕木上に線路5を敷設する
Therefore, according to FIG. 12ST11, the line 5
Embankment 2 between the girders 32, 32 adjacent to each other along the extension direction of the
1 is excavated and removed, and the work of removing the sheet pile 15, which is a temporary earth retention, is performed according to FIG. 12ST12. While doing this, according to FIG. 12ST13, the work of installing the slab girder 31 on the receiving girder 32 as shown in FIG. 9 while removing the construction girder 13 is performed alternately. That is, sheet pile 1
Support the track 5 etc. on the 5 using a jack etc.,
The slab girder 31 is erected and installed on the receiving girder 32 in a form of replacing the construction girder 13 installed on the receiving girder 32 with the slab girder 31. Then, in this way, the work of constructing the slab girder 31, which is a member for supporting the line 5 later, can be steadily progressed under the work girder 13 on which the line 5 has already been laid. The slab girder 31 thus constructed is H
Since the precast member has the shaped steel embedded therein, the slab girder 31 having a predetermined strength can be easily formed and constructed simply by installing the precast member on the receiving girder 32 and connecting a plurality of the precast members in the line extension direction. To be done. In this way, while the slab girder 31 is installed and formed, the lines 5 and 5 temporarily laid on the construction girder 13 are moved and laid on the slab girder 31 in order. Then, the track 5 temporarily laid on the construction girder 13 has already been arranged and fixed at a position having a predetermined height H1 from the position which will be the ground 2a later,
By switching the construction girder 13 to the slab girder 31 constructed by simply installing the precast member, the track switching of the line 5 is completed within an extremely short time.
Since the track belt 3 on which the track 5 was originally laid on the embankment 21 is an elevated structure made of concrete formed by the slab girder 31, on the slab girder 31 is a line such as crushed stone or a concrete block. A support member and a sleeper are installed, and the track 5 is laid on the track support member and the sleeper.

【0020】こうして、受け桁32上にスラブ桁31を
設置して、該スラブ桁31上に線路5を切り替え敷設す
ると共に、図12ST14によって、該スラブ桁31上
に高欄33を、図8点線で示す部分にコンクリート現場
打設するか或いはプレキャスト部材を取り付ける形で、
高欄部を施工する。すると、高欄33が取り付けられた
スラブ桁31が受桁32によって支持された形で軌道帯
3が構築される。そして、該軌道帯3は、盛土21下の
地盤2中に打設された、桁受け杭60の複数の基礎杭6
のそれぞれに支持された形になる。こうしておいて、図
12ST15によって、盛土21及び先に該盛土21の
法部21a、21aに盛土形成された腹付盛土23の、
未だ撤去されていない部分を、一次掘削面21dから地
面2aまで堀り下げる形で、盛土撤去作業を行う。する
と、この際、既に線路5が敷設された軌道帯3のスラブ
桁31は、盛土21の法部21aに対応した位置下の地
盤2中に打設された桁受け杭60の各基礎杭6によって
支持された形になっているために、ここに新たな土留等
を施す必要なく、安全且つ一度に盛土21及び腹付盛土
23を地面2a位置まで掘削撤去する作業を行うことが
出来る。
In this way, the slab girder 31 is installed on the receiving girder 32, the line 5 is switched and laid on the slab girder 31, and by the step ST14 of FIG. In the form shown, concrete is cast on site or precast members are attached.
Build the balustrade. Then, the orbital zone 3 is constructed such that the slab girder 31 to which the balustrade 33 is attached is supported by the receiving girder 32. The orbital zone 3 is a plurality of foundation piles 6 of the girder receiving pile 60, which are placed in the ground 2 under the embankment 21.
It becomes the shape supported by each. Thus, according to FIG. 12ST15, the embankment 21 and the belly-filled embankment 23 previously formed on the slopes 21a of the embankment 21, 21a,
The embankment removal work is performed by digging the part that has not been removed yet from the primary excavation surface 21d to the ground 2a. Then, at this time, the slab girders 31 of the track zone 3 on which the track 5 has already been laid are the foundation piles 6 of the girder receiving piles 60 placed in the ground 2 below the position corresponding to the slope 21a of the embankment 21. Since it is supported by, it is possible to safely excavate and remove the embankment 21 and the embankment 23 with the abdomen to the position of the ground 2a at one time without the need to provide new earth retention or the like.

【0021】こうして盛土撤去を行うと、そのスラブ桁
31上に線路5が敷設された軌道帯3を支持している桁
受け杭60は、該桁受け杭60の各基礎杭6の下部にお
いてケーシングチューブ7がその杭孔70中に打設充填
されたコンクリート40によって地盤2に接続定着され
た形の杭部6aを地面2a下に残す一方で、該基礎杭6
の上部が、盛土21及び腹付け盛土23の撤去によっ
て、図9に示すように、地上20に露出する形で、該桁
受け杭60には、その各基礎杭6の上部に柱部6bが形
成される。これによって、受桁32と柱部6bが地上2
0に露出する形になって、地面2aと軌道帯3との間に
は空間が形成される。そして、桁受け杭60の上側にお
いて柱部6bに接続する形で構築された受桁32上のス
ラブ桁31は、該桁受け杭60の各基礎杭6によって支
えられる形で、高架橋1が、切り替え1区間分だけ構築
完了される。即ち、軌道帯3のスラブ桁31は、盛土2
1及び腹付盛土23の撤去によって露出した各基礎杭6
の柱部6bの長さに対応した高さH1分だけ地面2aの
上方に線路5を配置させる形で、該柱部6bを脚部とし
て、高架橋1が切り替え1区間分構築されて、線路5が
高架化される。従って、線路5は、その高架化のために
該線路5が元位置していた盛土21の中央の頂部21b
から略水平移動される形で腹付盛土23上にそれぞれ切
替えられてから、再び略水平移動によって工事桁13上
に戻されて後、軌道帯3のスラブ桁31上に切り替えら
れることによって、簡単且つ安全に切り替えられるの
で、該線路5を供用中の電車等に影響を及ぼす時間が極
短くて済む。よって、施工時間が限られている場合に
も、当該線路切り替え作業を効率良く行うことが出来
る。
When the embankment is removed in this way, the girder receiving pile 60 supporting the track zone 3 in which the line 5 is laid on the slab girder 31 is used as a casing in the lower part of each foundation pile 6 of the girder receiving pile 60. While the pile portion 6a in which the tube 7 is connected and fixed to the ground 2 by the concrete 40 poured into the pile hole 70 is left below the ground 2a, the foundation pile 6
The upper portion of the girder receiving pile 60 has pillar portions 6b at the upper portions of the foundation piles 6 in a form of being exposed to the ground 20 as shown in FIG. 9 by removing the embankment 21 and the filling embankment 23. It is formed. As a result, the receiving girder 32 and the pillar portion 6b are located above the ground 2
A space is formed between the ground 2a and the orbital zone 3 by being exposed to 0. The slab girders 31 on the girders 32 constructed so as to be connected to the pillar portions 6b on the upper side of the girder receiving piles 60 are supported by the respective foundation piles 6 of the girder receiving piles 60, and the viaduct 1 is Construction is completed for one switching section. That is, the slab girder 31 of the orbital zone 3 is the embankment 2
1 and each foundation pile 6 exposed by removal of the embankment with belly 23
In the form of arranging the track 5 above the ground 2a by a height H1 corresponding to the length of the pillar 6b, the viaduct 1 is constructed for one section by switching the viaduct 1 as a leg. Is elevated. Therefore, the track 5 is the top 21b of the center of the embankment 21 where the track 5 was originally located because of its elevated structure.
It is easy to switch to the slab girders 31 of the orbital zone 3 after being switched to the belly-filled embankment 23 in a substantially horizontal movement, and then returned to the construction girder 13 by substantially horizontal movement again. In addition, since the lines can be switched safely, the time for affecting the train or the like in service of the track 5 can be extremely short. Therefore, even when the construction time is limited, the line switching work can be efficiently performed.

【0022】こうして、図12ST1からST15に示
す工程手順によって、線路5、5による鉄道路線を1区
間づつ盛土21から高架橋1に切り替えていくと、該高
架橋1を構成している軌道帯3のスラブ桁31は、受桁
32を介して、鋼管からなるケーシングチューブ7及び
これによって形成された杭孔70中と該ケーシングチュ
ーブ7の外周囲の地盤2中に打設充填されたコンクリー
ト40によって、各基礎杭6に杭部6aが形成された形
の、複数の桁受け杭60によって支持された形になる。
従って、スラブ桁31を構築する際にこれを支持するた
めに用いられた桁受け杭60は、後に該桁受け杭60の
上部が柱部6bとして地上20に露出することによっ
て、軌道帯3のスラブ桁31を支持するための脚部を構
成する形になるので、該基礎杭6を高架橋1の構造部材
として有効に用いることが出来る。そして、該基礎杭6
には、杭部6aの上側に該杭部6a部分の杭孔70に打
設されたコンクリート40に引き続くように各ケーシン
グチューブ7内にコンクリート40が打設充填されてい
る。これによって、各基礎杭6は、鋼管であるケーシン
グチューブ7とコンクリート40が保有している十分な
る剛性を保持した形で、既に撤去された元の盛土21下
において安定している地盤2にその杭部6aが定着支持
された形になっている。従って、軌道帯3のスラブ桁3
1は、盛土21の地盤性状に拘らず、十分なる剛性及び
支持強度を保有した形の基礎杭6によって支持された形
で、線路5を安定的に支持することが出来る。これによ
って、高架橋1は高い耐震性を保有する。また、線路5
の高架化のために工事桁13を敷設する際には、先に述
べたように盛土21の法部21aに位置する部分に盛土
形成した腹付盛土23上に該線路5を水平移動させる形
で仮敷設しておくことが出来ることによって、該盛土2
1の側方に十分な用地がなくとも速やかなる軌道切替作
業が実施出来、即ち、高架橋1を構築するについては、
仮り線用の用地に制限を受けることが無く、また、深礎
杭を施工する手間無く、短い施工工期で経済的に盛土2
1を高架橋1に切り替えることが的確に出来る。
In this way, when the railroad lines formed by the tracks 5 and 5 are switched from the embankment 21 to the viaduct 1 one by one in accordance with the process steps shown in FIGS. 12ST1 to ST15, the slabs of the track zone 3 constituting the viaduct 1 are changed. The girders 31 are respectively passed through the receiving girders 32 in the casing tube 7 made of a steel pipe and the pile hole 70 formed by the casing tube 7 and the concrete 40 poured and filled in the ground 2 around the outer periphery of the casing tube 7 respectively. It becomes a form in which the pile portion 6a is formed on the foundation pile 6 and is supported by the plurality of girder receiving piles 60.
Therefore, the girder receiving pile 60 used for supporting the slab girder 31 when constructing the slab girder 31 has a structure in which the upper part of the girder receiving pile 60 is exposed to the ground 20 as the pillar portion 6b later, so that Since the legs for supporting the slab girders 31 are formed, the foundation pile 6 can be effectively used as a structural member of the viaduct 1. And the foundation pile 6
In this case, the concrete 40 is poured and filled in each casing tube 7 so as to follow the concrete 40 that is placed in the pile hole 70 of the pile portion 6a above the pile portion 6a. As a result, each foundation pile 6 retains sufficient rigidity held by the casing tube 7 which is a steel pipe and the concrete 40, and is attached to the ground 2 which is stable under the already removed original embankment 21. The pile portion 6a is fixedly supported. Therefore, the slab girder 3 of the orbital zone 3
No. 1 can stably support the track 5 regardless of the ground property of the embankment 21 and is supported by the foundation pile 6 having sufficient rigidity and support strength. As a result, the viaduct 1 has high earthquake resistance. Also, track 5
When laying the work girder 13 for the purpose of raising the above-mentioned structure, the line 5 is horizontally moved on the belly-provided embankment 23 formed as the embankment at the portion located at the slope 21a of the embankment 21 as described above. The embankment 2 can be temporarily laid in
Even if there is not enough land on the side of No. 1, rapid track switching work can be carried out, that is, to build viaduct 1,
There is no restriction on the site for the temporary wire, and there is no need to construct deep foundation piles.
It is possible to accurately switch 1 to viaduct 1.

【0023】なお、上述した実施例においては、法部2
1aに対応した位置下に打設される杭体として、鋼管か
らなるケーシングチューブ7を盛土21下の地盤2中に
押し込む形で打設して該ケーシングチューブ7中にコン
クリート40を充填することによって形成構築した基礎
杭6を用い、該基礎杭6を線路5の横断方向に左右一対
に2本並べたものを桁受け杭60にした例を述べたが、
桁受け杭は線路5の横断方向に複数並ぶ杭体からなるも
のであれば、必ずしも2本一対の基礎杭6、6によって
構成されていなくとも構わない。また、実施例において
は、その孔底70aが地盤2によって形成される杭孔7
0中にコンクリート40を打設することによって、ケー
シングチューブ7の外周囲を環状に包囲するように杭部
6aを形成して、基礎杭6等の杭体を構築した例を述べ
たが、図13(a)乃至(c)に示すように、杭部6a
が該杭部6a以外の部分より拡径するように拡底した杭
体を形成しても構わない。即ち、まず、図11(a)に
示し先に述べた手順と同様にハンマグラブ11を用い
て、図13(a)に示すように、地盤2中の所定の位置
にケーシングチューブ7を打設する。これと同時に、該
ケーシングチューブ7内に前記杭孔70を形成する。そ
して、図13(b)に示すように、該形成された杭孔7
0中に前記鉄筋籠10を孔底70aまで吊り降ろす形
で、設置する。その後、図11(c)に示し先に述べた
トレミー管11を用いて、杭孔70中にコンクリート4
0を打設しながら、図13(c)に示すように、ケーシ
ングチューブ7を杭部6aの高さD1に対応した分高さ
D2分だけ上方に引上げていく。すると、ケーシングチ
ューブ7の底端7aと孔底70aとの間に形成された高
さD2分だけは、該ケーシングチューブ7が配置してい
ないことによって、杭孔70中に打設されたコンクリー
ト40が地盤2を形成している土砂間隙中に十分に浸入
していく。そこで、所定の位置でケーシングチューブ7
の引上げを中止して、さらに杭孔70中にコンクリート
40を打設充填していくと、図11に示すと略同等の手
順によって、拡底した状態の基礎杭6が形成される。す
ると、該基礎杭6は、その杭部6aが、内部に鉄筋籠1
0が埋設された状態でコンクリート40によって拡底し
た状態で形成されることによって、リブ付き鋼管からな
るケーシングチューブ7が地盤2に堅固に定着支持され
る。従って、こうして構築された基礎杭6は高架橋1の
軌道帯3を一層確実に支持することが可能となる。な
お、ケーシングチューブ7内に打設されるコンクリート
40の天端40a高さは任意である。
Incidentally, in the above-mentioned embodiment, the law unit 2
As a pile body to be placed below the position corresponding to 1a, by placing a casing tube 7 made of a steel pipe into the ground 2 below the embankment 21 and filling the casing tube 7 with concrete 40. An example was described in which the foundation pile 6 formed and constructed was used as the girder receiving pile 60 by arranging two foundation piles 6 in a pair in the transverse direction of the track 5 on the left and right sides.
The girder receiving piles do not necessarily have to be configured by the pair of foundation piles 6 and 6 as long as the girder receiving piles are composed of a plurality of piles arranged in the transverse direction of the line 5. In addition, in the embodiment, the hole bottom 70 a has a pile hole 7 formed by the ground 2.
An example of constructing a pile body such as a foundation pile 6 by forming concrete 40 in 0 to form the pile portion 6a so as to surround the outer circumference of the casing tube 7 in an annular shape was described. 13 (a) to 13 (c), the pile portion 6a
It is also possible to form a pile body whose bottom is expanded so that the diameter is larger than that of the portion other than the pile portion 6a. That is, first, as shown in FIG. 11A, the casing tube 7 is driven at a predetermined position in the ground 2 by using the hammer mug 11 in the same manner as described above and shown in FIG. . At the same time, the pile hole 70 is formed in the casing tube 7. Then, as shown in FIG. 13B, the formed pile hole 7
The rebar cage 10 is installed in a state of being hung down to the hole bottom 70a. Then, using the tremie pipe 11 shown in FIG.
13 (c), the casing tube 7 is pulled upward by a height D2 corresponding to the height D1 of the pile portion 6a while driving 0. Then, only the height D2 formed between the bottom end 7a of the casing tube 7 and the hole bottom 70a is not provided with the casing tube 7, so that the concrete 40 poured into the pile hole 70 is Satisfactorily penetrates into the soil gap forming the ground 2. Therefore, at a predetermined position, the casing tube 7
When the pulling up is stopped and the concrete 40 is further poured and filled into the pile hole 70, the foundation pile 6 in the expanded state is formed by the procedure substantially similar to that shown in FIG. Then, in the foundation pile 6, the pile portion 6a has the rebar cage 1 inside.
The casing tube 7 made of a ribbed steel pipe is firmly fixed and supported on the ground 2 by being formed in a state in which 0 is buried and expanded by the concrete 40. Therefore, the foundation pile 6 thus constructed can more reliably support the track zone 3 of the viaduct 1. It should be noted that the height of the top end 40a of the concrete 40 placed in the casing tube 7 is arbitrary.

【0024】また、基礎杭6は、図14(a)乃至
(c)に示すように、基礎杭6構築後には除去される除
去ケーシング28を用いて、杭部6a及び柱部6bを形
成するための鋼管27を正確な位置に設置する形で、一
層精度良く施工構築されることがある。即ち、前述した
ケーシングチューブ7と同等部材からなる鋼管27を設
置するために、まず、該鋼管27より大径に形成された
除去ケーシング28を、図14(a)に示すように、盛
土21を介して該盛土21下の地盤2中に打ち込む。こ
れと共に、該除去ケーシング28の内部を掘削すること
によって、ボアホール28sを所定深さ分だけ形成す
る。すると、除去ケーシング28によって孔崩れが防止
された状態でボアホール28sが、鋼管27の設置に適
した状態で該除去ケーシング28の中空形状に対応した
形状に形成される。こうして形成されたボアホール28
s中に、図14(b)に示すように、鋼管27を仮設置
し、また、該鋼管27内の中空部分を介してボアホール
28s中に鉄筋籠10を設置する。なお、鋼管27は、
その開口した底端27aが孔底28aより所定高さD3
分だけ上方に配置するように位置決めして、設置してお
く。すると、鋼管27や先に述べたケーシングチューブ
7等の鋼管部材は、これを地盤2中に直接押し込む形で
打ち込もうとすると、精度良く鉛直方向に打ち込むのが
非常に難しいが、図14に示す方法では、万一、除去ケ
ーシング28の打ち込み設置状態が悪い場合でも、ボア
ホール28s中への鋼管27の設置位置を調整すること
によって、該鋼管27は極めて正確な位置において鉛直
方向を向くように位置決めされた形になる。そこで、先
に述べて図11(c)に示すトレミー管11を用いて、
図14(c)に示すように、除去ケーシング28を引き
抜きながら、鋼管27の内部を介してボアホール28s
中にコンクリート40を打設していく。すると、コンク
リート40は、鋼管27の内部から、該鋼管27の底端
27aの開口部分を介して該鋼管27の外周囲に廻り込
む形でボアホール28sに充填されていく。また、底端
27aより下側においては、ここに鋼管27がないこと
によって、ボアホール28s周囲の地盤2の土砂間隙中
にもコンクリート40が浸入充填されていく。すると、
先に述べて図13に示すと同様に、拡底された形の杭部
6aが形成される。こうして、天端40aの高さが所定
位置になるまでコンクリート40を打設充填すると、先
に述べたようにボアホール28s中の正確な位置に仮設
置された鋼管27が、該ボアホール28中に打設充填さ
れたコンクリート40によって地盤2に定着された形
で、基礎杭6が形成構築される。すると、鋼管27によ
る基礎杭6は、先に述べて図13に示したケーシングチ
ューブ7と同様に拡底された杭部6aを形成する形にな
ると共に、該鋼管27の設置位置が、除去ケーシング2
8の打設時誤差を修正し得る形で、正確に位置決めされ
た形になることによって、堅固で且つ精密に施工構築完
了される。こうして精密に施工構築された基礎杭6は、
軌道帯3を一層確実に支持することが可能となる。従っ
て、こうした除去ケーシング28を用いれば、特に高架
橋1の施工精度が向上するので、軌道帯3下等の高架下
に駅舎部分を構築する必要がある場合に、特に有益であ
る。さらに、上述した例においては、いずれも杭体をケ
ーシングチューブ7や鋼管27等の鋼管部材で形成した
例を述べたが、こうした杭体は、必ずしも鋼管杭をオー
ルケーシング方式によって打設したものでなくとも差し
支えない。勿論、鉄筋コンクリート杭であっても構わな
い。
Further, as shown in FIGS. 14 (a) to 14 (c), the foundation pile 6 is formed with the removal casing 28 which is removed after the foundation pile 6 is constructed to form the pile portion 6a and the pillar portion 6b. There is a case where the steel pipe 27 is installed at an accurate position for more accurate construction. That is, in order to install the steel pipe 27 made of a member equivalent to the casing tube 7 described above, first, the removal casing 28 formed to have a larger diameter than the steel pipe 27 is filled with the embankment 21 as shown in FIG. It drives into the ground 2 under the embankment 21 via. Along with this, the bore hole 28s is formed to a predetermined depth by excavating the inside of the removal casing 28. Then, the bore hole 28 s is formed in a state corresponding to the hollow shape of the removal casing 28 in a state suitable for the installation of the steel pipe 27 while the removal casing 28 prevents the collapse of the hole. Bore hole 28 thus formed
As shown in FIG. 14 (b), the steel pipe 27 is temporarily installed in s, and the rebar cage 10 is installed in the bore hole 28 s through the hollow part in the steel pipe 27. The steel pipe 27 is
The open bottom end 27a has a predetermined height D3 from the hole bottom 28a.
Position it so that it will be placed upwards by the amount and install it. Then, if the steel pipe 27 or the steel pipe member such as the casing tube 7 described above is to be driven directly into the ground 2, it is very difficult to drive the steel pipe member in the vertical direction with high accuracy. According to the method shown, by adjusting the installation position of the steel pipe 27 in the bore hole 28s even if the removal casing 28 is installed in a bad installation condition, the steel pipe 27 is oriented in the vertical direction at an extremely accurate position. It becomes the positioned shape. Therefore, using the tremie tube 11 described above and shown in FIG.
As shown in FIG. 14 (c), while pulling out the removal casing 28, the bore hole 28 s is passed through the inside of the steel pipe 27.
Concrete 40 is placed inside. Then, the concrete 40 is filled in the bore hole 28s from the inside of the steel pipe 27 through the opening portion of the bottom end 27a of the steel pipe 27 and around the outer periphery of the steel pipe 27. Further, below the bottom end 27a, the concrete 40 is infiltrated and filled also in the earth-sand gap of the ground 2 around the borehole 28s due to the absence of the steel pipe 27. Then,
In the same manner as described above and shown in FIG. 13, the piled-up pile portion 6a is formed. In this way, when the concrete 40 is poured and filled until the height of the top end 40a reaches a predetermined position, the steel pipe 27 temporarily installed at the accurate position in the bore hole 28s as described above is driven into the bore hole 28s. The foundation pile 6 is formed and constructed by being fixed to the ground 2 by the concrete 40 filled and filled. Then, the foundation pile 6 made of the steel pipe 27 becomes a shape in which the pile portion 6a is expanded like the casing tube 7 shown in FIG. 13 described above, and the installation position of the steel pipe 27 is set to the removal casing 2
By accurately setting the shape, which is capable of correcting the casting error of 8, the construction can be completed firmly and precisely. The foundation pile 6 constructed and constructed in this way is
It becomes possible to more reliably support the orbital zone 3. Therefore, use of such a removal casing 28 improves the construction accuracy of the viaduct 1, and is particularly useful when it is necessary to construct the station building portion under the elevated structure such as under the track zone 3. Furthermore, in each of the above-mentioned examples, an example in which the pile body is formed of a steel pipe member such as the casing tube 7 and the steel pipe 27 has been described, but such a pile body is not necessarily one in which the steel pipe pile is driven by the all-casing method. It doesn't matter. Of course, it may be a reinforced concrete pile.

【0025】また、実施例においては、線路5の横断方
向に複数並べて打設した鋼製の矢板15を仮土留手段と
した例を述べたが、こうした仮土留手段は、線路5の横
断方向に沿い且つ桁受け杭60を線路の伸延方向両側か
ら挟む形で盛土21中に打設されるものであれば、その
構成は任意である。さらに、実施例において述べた工程
手順FLO−1では、盛土21の法部21a、21aに
腹付盛土23を盛土形成することによって、桁受け杭6
0の各基礎杭6の打設と、頂部21bから該法部21
a、21a位置に対応した位置に線路5を的確に移設し
得るようにした例を述べたが、腹付盛土23の形成は任
意である。また、実施例においては、盛土21及び腹付
盛土23を2回に分けて掘削撤去するようにした例を述
べたが、盛土撤去の手法はこれに限定されるものではな
い。また、実施例においては、本発明を鉄道路線である
複線の線路5、5に適用した例を述べたが、線路5は単
線或いは複複線であっても構わず、さらには、既存の路
線が道路である場合にも本発明を適用することが可能で
ある。
Further, in the embodiment, an example in which a plurality of steel sheet piles 15 arranged and arranged in the transverse direction of the track 5 is used as the temporary earth retaining means has been described. The structure is arbitrary as long as it is placed in the embankment 21 so as to sandwich the girder receiving pile 60 from both sides in the extension direction of the line. Further, in the process procedure FLO-1 described in the embodiment, the girder receiving pile 6 is formed by forming the embankment 23 with the belly on the slopes 21a, 21a of the embankment 21.
0 of each foundation pile 6 and from the top 21b to the slope 21
The example in which the line 5 can be accurately moved to the positions corresponding to the positions a and 21a has been described, but the formation of the belly-filled embankment 23 is optional. Further, in the embodiment, an example is described in which the embankment 21 and the belly-filled embankment 23 are excavated and removed in two steps, but the method of embankment removal is not limited to this. Further, in the embodiment, the example in which the present invention is applied to the double-tracked railroad tracks 5 and 5 has been described. However, the railroad track 5 may be a single-track or a double-track track. The present invention can also be applied to the case of a road.

【0026】[0026]

【発明の効果】以上説明したように本発明によれば、既
存の線路5等の路線が敷設されている盛土21におい
て、前記盛土21の法部21aに対応した位置下の地盤
2中に、前記路線の横断方向に複数並ぶ基礎杭6等の杭
体からなる桁受け杭60を、該路線の伸延方向に沿って
所定間隔L1毎に複数打設し、該桁受け杭60の各杭体
に対応した前記法部21aに前記既存の路線を移設する
と共に、該盛土21中に矢板15等の仮土留め手段を、
前記路線の横断方向に沿い且つ前記桁受け杭60を前記
路線の伸延方向両側から挟む形で打設し、前記仮土留め
手段上に工事桁13を、前記路線の伸延方向に沿って伸
延する形で設置して、該工事桁13上に前記移設した路
線を再度移設して仮敷設し、前記仮土留め手段によっ
て、土留めし、且つ前記工事桁13を支持しつつ、該盛
土21中に受桁32等の桁受け手段を、前記桁受け杭6
0の杭体間に架け渡す形で設置し、前記路線の伸延方向
に沿って隣接する桁受け杭60間の前記盛土21と、前
記仮土留手段とを撤去し、該桁受け手段と前記桁受け杭
60の柱部6b等の上部を地上20に露出させ、前記仮
土留め手段上に設置されていた工事桁13と架け替える
形でスラブ桁31を、該桁受け手段上に設置して、該工
事桁13上に仮敷設されていた前記路線を、該スラブ桁
31上に移動敷設し、前記スラブ桁31上に移動敷設し
た該路線を、前記地上20に露出した前記桁受け杭60
の上部を脚部とする形で高架化するようにして構成した
ので、盛土21上の路線を、仮土留め手段によって支持
される工事桁13上に移設して後、桁受け手段を介して
桁受け杭60によって支持されるスラブ桁31上に移動
敷設して、該スラブ桁31上において、地上20に露出
した該桁受け杭60の上部の高さH1分だけ地盤2の上
方に位置させる形で、該路線が元敷設されていた盛土2
1位置に配置させることが出来る。従って、路線を高架
化するにあたって、桁受け杭60の杭体6によって盛土
21の法部21aに対応した位置を補強しておいて、該
法部21aに対応した位置に既存の路線を移設し、この
状態で、該既存の路線が元敷設されていた該盛土21位
置に、その後スラブ桁31と架け替えられる工事桁13
を設置することが出来るので、該盛土21の側方に路線
を仮敷設しておくだけの十分な用地がなくとも、路線の
高架化を的確に行うことが出来る。またこの際、盛土2
1に敷設されている路線を、該盛土21の法部21aに
対応した位置に一旦移設しておいて、その後工事桁13
に再度移設することによって仮敷設してから、この状態
でスラブ桁31への架け替え作業を行うので、路線が既
存していた盛土21位置に対応していない位置に移設さ
れている期間が短くて済む。また、路線の移設作業は、
盛土21における頂部21b等の路線敷設位置と法部2
1aに対応した位置との間で、該路線を略水平に移動さ
せる形で行うことが出来るので、路線移設切替え作業
を、簡単且つ短時間のうちに行うことが出来る。そし
て、路線が仮敷設される工事桁13は、桁受け杭を路線
伸延方向に沿って挟む形で盛土21中に打設される仮土
留め手段上に設置されるので、仮土留手段により土留さ
れた盛土21の支持力を介して工事桁13が、該盛土2
1上において確実に路線を仮支持することが出来る。ま
た、路線を敷設するためのスラブ桁31は、先に述べた
ように路線の移設のために法部21aを補強する役目を
果たした桁受け杭60を用いて、その各杭体間に架け渡
す形で施工される桁受け手段上に設置されることによっ
て、簡単に所定の構築位置に構築されるので、桁受け杭
60の各杭体を有効に用いることになり、施工性が良
い。そして、桁受け手段は、工事桁を支持する仮土留手
段によって土留した状態で盛土中に施工設置されるの
で、安全施工が行われる。また、高い作業足場を要さず
その施工が簡単である。さらに、スラブ桁31が設置さ
れる桁受け手段を、盛土21下の地盤2中に打設してお
いてから該盛土21を撤去することによってその上部を
地上20に露出させる形で施工する桁受け杭60に支持
させることによって、高架橋の施工工率を上げることが
出来る。即ち、桁受け杭60の各杭体を盛土21下の地
盤2中に打設してから、後に盛土21を撤去することに
よって、高架化路線の脚部を簡単に構築し得るので、施
工効率が良い。また、該桁受け杭60の各杭体は、その
上部を地上20に露出させる一方で、該杭体の下部を盛
土21下の地盤2中に残した形で、杭部6a等の地中杭
を形成し得るので、盛土21の地盤性状が軟弱である場
合においても、該杭体によって、高架であるスラブ桁3
1を確実に支えることが出来る。従って、本発明によっ
て高架橋1等の高架橋を施工構築すれば、盛土上に敷設
された鉄道、道路等の路線を高架に切替える際に、仮り
線用の用地を確保したり深礎杭を打設する必要がなく、
短い施工工期で経済的に該路線を高架化することが可能
となる。
As described above, according to the present invention, in the embankment 21 on which existing lines such as the track 5 are laid, in the ground 2 below the position corresponding to the slope 21a of the embankment 21, A plurality of girder receiving piles 60 made of piles such as foundation piles 6 arranged in the transverse direction of the line are placed at predetermined intervals L1 along the extension direction of the line, and each pile body of the girder receiving pile 60 is arranged. The existing line is moved to the slope 21a corresponding to, and a temporary earth retaining means such as a sheet pile 15 is provided in the embankment 21.
The girder receiving piles 60 are placed along the transverse direction of the line so as to sandwich the girder receiving piles 60 from both sides in the extension direction of the line, and the construction girder 13 is extended on the temporary earth retaining means along the extension direction of the line. Shape, and the relocated line is re-moved on the construction girder 13 to be temporarily laid, and is earthed by the temporary earth retaining means, and the construction girder 13 is supported while the earth 21 The girder receiving means such as the girder 32 is provided on the girder receiving pile 6
It is installed so as to bridge between 0 pile bodies, and the embankment 21 between the girder receiving piles 60 adjacent to each other along the extension direction of the line and the temporary earth retaining means are removed, and the girder receiving means and the girder are removed. An upper portion of the pillar portion 6b of the receiving pile 60 is exposed to the ground 20, and a slab girder 31 is installed on the girder receiving means so as to replace the construction girder 13 installed on the temporary earth retaining means. The line temporarily laid on the construction girder 13 is moved and laid on the slab girder 31, and the line movably laid on the slab girder 31 is exposed to the ground 20 by the girder receiving pile 60.
Since it was constructed so as to be elevated with the upper part of the as a leg portion, the line on the embankment 21 was transferred to the work girder 13 supported by the temporary earth retaining means, and then via the girder receiving means. It is moved and laid on the slab girder 31 supported by the girder receiving pile 60, and is positioned above the ground 2 by the height H1 of the upper part of the girder receiving pile 60 exposed on the ground 20 on the slab girder 31. The embankment where the line was originally laid in shape
It can be placed in one position. Therefore, when the line is elevated, the position corresponding to the slope 21a of the embankment 21 is reinforced by the pile body 6 of the girder receiving pile 60, and the existing line is moved to the position corresponding to the slope 21a. , In this state, the construction girder 13 that can be replaced with the slab girder 31 at the position of the embankment 21 where the existing route was originally laid was then installed.
Since it is possible to install the line, it is possible to accurately raise the line even if there is not enough land for temporarily laying the line on the side of the embankment 21. At this time, the embankment 2
The line laid at No. 1 is once moved to a position corresponding to the slope 21a of the embankment 21, and then the work girder 13
After the temporary laying by relocating to the slab, the slab girder 31 is rebuilt in this state, so the period when the line is relocated to a position that does not correspond to the existing embankment 21 position is short. Complete. In addition, the relocation work of the line,
Line laying position such as the top 21b on the embankment 21 and the slope 2
Since the line can be moved substantially horizontally to the position corresponding to 1a, the line transfer switching work can be performed easily and in a short time. Since the construction girder 13 on which the line is temporarily laid is installed on the temporary earth retaining means that is placed in the embankment 21 with the girder receiving piles sandwiched along the direction of extension of the line, the temporary earth retaining means is used for retaining the earth. Through the supporting force of the embankment 21 that was created, the work girder 13
It is possible to reliably temporarily support the route on 1. In addition, the slab girder 31 for laying the line is hung between the pile bodies by using the girder receiving pile 60 which has a role of reinforcing the slope 21a for moving the line as described above. Since the pile body of the girder receiving pile 60 is effectively used by being installed on the girder receiving means which is constructed in the form of handing, it is easily constructed at a predetermined construction position, and the workability is good. Since the girder receiving means is installed and installed in the embankment in a state of being retained by the temporary earth retaining means that supports the work girder, safe construction is performed. Moreover, the construction is easy without requiring a high work scaffold. Further, a girder is installed in the ground 2 below the embankment 21 after the slab girder 31 is installed, and then the embankment 21 is removed to expose the upper part to the ground 20. By supporting the support pile 60, the construction rate of the viaduct can be increased. That is, since each pile body of the girder receiving pile 60 is placed in the ground 2 below the embankment 21 and then the embankment 21 is removed later, the legs of the elevated line can be easily constructed, so that the construction efficiency can be improved. Is good. In addition, each pile body of the girder receiving pile 60 exposes the upper portion thereof to the ground 20, while leaving the lower portion of the pile body in the ground 2 below the embankment 21 in the ground such as the pile portion 6a. Since the pile can be formed, even if the ground property of the embankment 21 is soft, the slab girder 3 which is an elevated structure is formed by the pile body.
1 can be reliably supported. Therefore, by constructing and constructing a viaduct such as viaduct 1 according to the present invention, when switching a railroad, a road or the like laid on the embankment to an elevated structure, a site for a temporary wire is secured or a deep foundation pile is laid. You do n’t have to
It is possible to economically raise the route in a short construction period.

【0027】また、本発明において、前記桁受け杭60
の各杭体は、前記盛土21を介して該盛土21下の地盤
2中に押し込む形でケーシングチューブ7等の鋼管を打
設し、該鋼管中にコンクリート40を充填することによ
って形成するようにして構成すると、前記桁受け杭60
の各杭体は、コンクリート40が充填された鋼管の剛性
を介して、スラブ桁31を支持するように作用する。即
ち杭体は鋼管コンクリートの特質を活かして高い耐震性
を発現し得る形で、スラブ桁31を支持することが出来
るので、路線の伸延方向に沿って長大な構造体となるこ
ういった高架橋を、特に有効に支えることが可能とな
る。また、杭体を構築するにあたっては、鋼管を地盤2
中に押し込み、該鋼管中にコンクリート40を打設する
形で、その1本1本を簡単に形成し得るので、効率良く
高架橋を施工することが出来る。また、こうした鋼管コ
ンクリートは経済的な施工が可能である。
Further, in the present invention, the girder receiving pile 60.
Each of the piles is formed by driving a steel pipe such as a casing tube 7 into the ground 2 below the embankment 21 through the embankment 21 and filling concrete 40 into the steel pipe. If constituted, the girder receiving pile 60
Each of the piles of 1 acts to support the slab girder 31 through the rigidity of the steel pipe filled with the concrete 40. That is, since the pile body can support the slab girder 31 in a form that can exhibit high earthquake resistance by utilizing the characteristics of steel pipe concrete, such a viaduct that becomes a long structure along the extension direction of the route It becomes possible to support particularly effectively. In addition, when constructing piles, steel pipes are
Since each one can be easily formed by pushing it in and placing concrete 40 in the steel pipe, it is possible to efficiently construct a viaduct. In addition, such steel pipe concrete can be economically constructed.

【図面の簡単な説明】[Brief description of drawings]

【図1】本発明を用いて盛土から切り替えられた高架橋
の一例を示す図である。
FIG. 1 is a diagram showing an example of viaducts switched from embankment using the present invention.

【図2】図1のII、II矢視図である。FIG. 2 is a view taken in the direction of arrows II and II in FIG.

【図3】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 3 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG.

【図4】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 4 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG.

【図5】図1に示す高架橋の施工手順の一例を示す図で
ある。
5 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG.

【図6】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 6 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG. 1.

【図7】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 7 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG. 1.

【図8】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 8 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG. 1.

【図9】図1に示す高架橋の施工手順の一例を示す図で
ある。
FIG. 9 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG. 1.

【図10】図1に示す高架橋の施工手順の一例を示す図
である。
10 is a diagram showing an example of a procedure for constructing the viaduct shown in FIG.

【図11】本発明に用いる桁受け杭用の基礎杭の施工手
順を示す一連の図である。
FIG. 11 is a series of diagrams showing a construction procedure of a foundation pile for a girder receiving pile used in the present invention.

【図12】本発明による高架橋施工方法の施工工程手順
の一例を示す流れ図である。
FIG. 12 is a flow chart showing an example of a construction process procedure of a method for constructing a viaduct according to the present invention.

【図13】本発明に用いる基礎杭において図11に示す
ものと別の施工手順を示す図である。
FIG. 13 is a view showing a construction procedure different from that shown in FIG. 11 in the foundation pile used in the present invention.

【図14】本発明に用いる基礎杭において図11に示す
ものとさらに別の施工手順を示す図である。
FIG. 14 is a diagram showing a construction procedure of the foundation pile used in the present invention, which is different from that shown in FIG. 11;

【符号の説明】[Explanation of symbols]

1……高架橋 5……既存の路線(線路) 2……地盤 20……地上 21……盛土 21a……法部 6……杭体(基礎杭) 6b……上部(柱部) 60……桁受け杭 13……工事桁 15……仮土留手段(矢板) 31……スラブ桁 32……桁受け手段(受桁) 7……鋼管(ケーシングチューブ) 40……コンクリート 1 ... Viaduct 5: Existing line (track) 2 ... Ground 20 ... ground 21 ... Embankment 21a ... Houbu 6 ... Piles (foundation piles) 6b ... Upper part (post) 60 …… Girder receiving pile 13 ... Construction girder 15 ... Temporary retaining means (sheet pile) 31 …… Slab girder 32: Digit receiving means (receive digit) 7: Steel pipe (casing tube) 40 …… Concrete

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】既存の路線が敷設されている盛土におい
て、 前記盛土の法部に対応した位置下の地盤中に、前記路線
の横断方向に複数並ぶ杭体からなる桁受け杭を、該路線
の伸延方向に沿って所定間隔毎に複数打設し、 該桁受け杭の各杭体に対応した前記法部に前記既存の路
線を移設すると共に、該盛土中に仮土留め手段を、前記
路線の横断方向に沿い且つ前記桁受け杭を前記路線伸延
方向両側から挟む形で打設し、 前記仮土留め手段上に工事桁を、前記路線の伸延方向に
沿って伸延する形で設置して、該工事桁上に前記移設し
た路線を再度移設して仮敷設し、 前記仮土留め手段によって、土留めし、且つ前記工事桁
を支持しつつ、該盛土中に桁受け手段を、前記桁受け杭
の杭体間に架け渡す形で設置し、 前記路線の伸延方向に沿って隣接する桁受け杭間の前記
盛土と、前記仮土留手段とを撤去し、該桁受け手段と前
記桁受け杭の上部を地上に露出させ、前記仮土留め手段
上に設置されていた工事桁と架け替える形でスラブ桁
を、該桁受け手段上に設置して、該工事桁上に仮敷設さ
れていた前記路線を、該スラブ桁上に移動敷設し、 前記スラブ桁上に移動敷設した該路線を、前記地上に露
出した前記桁受け杭の上部を脚部とする形で高架化する
ようにして構成した、高架橋施工方法。
1. In an embankment on which an existing line is laid, a girder receiving pile composed of a plurality of pile bodies arranged in a transverse direction of the line is provided in the ground below a position corresponding to the slope of the embankment. A plurality of them at predetermined intervals along the extension direction, the existing line is transferred to the sloped part corresponding to each pile body of the girder receiving pile, and temporary earth retaining means is provided in the embankment. The girder receiving pile is laid along the transverse direction of the line and sandwiched from both sides of the line extension direction, and the construction girder is installed on the temporary earth retaining means in a form of extending along the extension direction of the line. Then, the relocated line is relocated on the construction girder and laid temporarily, and the temporary earth retaining means is used for earth retaining, and while supporting the construction girder, a girder receiving means is provided in the embankment. It is installed in the form of bridging between the piles of the girder receiving piles, and they are adjacent along the extension direction The embankment between the girder receiving piles and the temporary earth retaining means are removed, the girder receiving means and the upper portions of the girder receiving piles are exposed to the ground, and the construction girder installed on the temporary earth retaining means A slab girder is installed on the girder receiving means in a form of being replaced, and the line temporarily laid on the construction girder is moved and laid on the slab girder, and the line is moved and laid on the slab girder. A method of constructing a viaduct, in which a line is constructed so as to be elevated in such a manner that the upper portion of the girder receiving pile exposed on the ground is a leg portion.
【請求項2】前記桁受け杭の各杭体は、前記盛土を介し
て該盛土下の地盤中に押し込む形で鋼管を打設し、該鋼
管中にコンクリートを充填することによって形成する、
請求項1記載の高架橋施工方法。
2. Each pile body of the girder receiving pile is formed by driving a steel pipe into the ground below the embankment through the embankment, and filling the steel pipe with concrete.
The method for constructing a viaduct according to claim 1.
JP21346293A 1993-08-05 1993-08-05 Viaduct construction method Expired - Fee Related JP3380301B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP21346293A JP3380301B2 (en) 1993-08-05 1993-08-05 Viaduct construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP21346293A JP3380301B2 (en) 1993-08-05 1993-08-05 Viaduct construction method

Publications (2)

Publication Number Publication Date
JPH0748803A JPH0748803A (en) 1995-02-21
JP3380301B2 true JP3380301B2 (en) 2003-02-24

Family

ID=16639614

Family Applications (1)

Application Number Title Priority Date Filing Date
JP21346293A Expired - Fee Related JP3380301B2 (en) 1993-08-05 1993-08-05 Viaduct construction method

Country Status (1)

Country Link
JP (1) JP3380301B2 (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003105703A (en) * 2001-09-28 2003-04-09 Tekken Constr Co Ltd Railway support replacement technique and structure
CN108824097A (en) * 2018-07-25 2018-11-16 中铁七局集团第工程有限公司 Prefabricated GFRP pipe concrete stake and armoured concrete slab overhead type roadbed pile slab structure
CN111519477A (en) * 2020-05-29 2020-08-11 中铁二院工程集团有限责任公司 Transition section structure of overhead pile plate structure and embankment and construction method thereof
CN111993558A (en) * 2020-08-11 2020-11-27 中铁第四勘察设计院集团有限公司 Production method of steel tube concrete sleeper

Also Published As

Publication number Publication date
JPH0748803A (en) 1995-02-21

Similar Documents

Publication Publication Date Title
US9322137B2 (en) Method for building structures, particularly passages under operating railways or the like
KR101344063B1 (en) The construction method of steel-concrete underpass
KR101111594B1 (en) Method for constructing underground structure
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
KR100834076B1 (en) None open cut tunnelling method and tunnel
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
JP4881555B2 (en) Construction method of underground structure
KR100562158B1 (en) Steel pipe roof construction method for building underground structure, roof structure therefor, and structure of steel pipe therefor
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP3380301B2 (en) Viaduct construction method
JP3893056B2 (en) Construction method of underground structure
KR100784201B1 (en) Method for construction of tunnel
KR100509707B1 (en) None open cut tunnelling of arch type with hume pipe and con'c rib
JP5915074B2 (en) How to form an underground space under a ground transportation
KR100605495B1 (en) Trenchless method of underground passage and structure thereof
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
KR101234270B1 (en) Method for non excavated excavating construction using steel pipe and steel pipe with hole
CN210141142U (en) Underground structure is built in same direction as digging in hole stake secret
JP3910135B2 (en) Building construction method and beam member used therefor
JP2587029B2 (en) Viaduct construction method
JP5073960B2 (en) Construction method of underground structure and underground structure
JP3380302B2 (en) Viaduct construction method
KR200331521Y1 (en) None open cut tunnelling of arch type with with hume pipe and con'c rib
JP4705467B2 (en) Construction method of underground structure
JP2004308225A (en) Work method and overhead bypass road

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111213

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20111213

Year of fee payment: 9

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20121213

Year of fee payment: 10

LAPS Cancellation because of no payment of annual fees