KR100834076B1 - None open cut tunnelling method and tunnel - Google Patents

None open cut tunnelling method and tunnel Download PDF

Info

Publication number
KR100834076B1
KR100834076B1 KR1020060089993A KR20060089993A KR100834076B1 KR 100834076 B1 KR100834076 B1 KR 100834076B1 KR 1020060089993 A KR1020060089993 A KR 1020060089993A KR 20060089993 A KR20060089993 A KR 20060089993A KR 100834076 B1 KR100834076 B1 KR 100834076B1
Authority
KR
South Korea
Prior art keywords
tunnel
steel pipe
slab
diameter steel
steel plate
Prior art date
Application number
KR1020060089993A
Other languages
Korean (ko)
Other versions
KR20080025478A (en
Inventor
김현경
Original Assignee
김현경
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김현경 filed Critical 김현경
Priority to KR1020060089993A priority Critical patent/KR100834076B1/en
Publication of KR20080025478A publication Critical patent/KR20080025478A/en
Application granted granted Critical
Publication of KR100834076B1 publication Critical patent/KR100834076B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/005Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries by forcing prefabricated elements through the ground, e.g. by pushing lining from an access pit
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Soil Sciences (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

본 발명에 따른 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체는 상부에 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향연결강판의 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계와, 상기 작업터널의 상부를 개방시켜 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함하므로, 대구경강관과 소구경강관의 횡방향 연결강판을 이용하여 난공사인 터널의 상부면의 형성이 대단히 용이하게 시공되므로 공기가 월등하게 단축되고 사용인력이 절감되며 공사 종료시까지 끊임없이 기반이 침하되는 기존공법의 문제점을 해결하였으며 시공시 사용된 소구경강관과 하부의 횡방향 연결강판이 회수되어 재사용할 수 있으며 터널의 지지기둥과 벽체도 조립식 공법으로 시공이 용이토록 하므로 구조적 안정성을 구축하였으며 공사중 일시적 지반보강후에는 상부 노반이 절대로 침하되지 않아 공사중에도 상부 교통시설을 안전하게 사용할 수 있게 되는 것이다.Non-adhesive tunnel excavation method and a tunnel structure installed by the method according to the present invention at a predetermined interval in the width direction of the tunnel at the height of the tunnel to be excavated from two to five large diameter steel pipe is fixed to the transverse connecting steel plate on the top The step of the earth excavation in the longitudinal direction of the tunnel and spaced apart, and the small-diameter steel pipe is fixed in the longitudinal direction of the tunnel is fixed to the horizontal connection steel plate spaced up and down with a predetermined width between the large diameter steel pipes Connecting the large diameter steel pipe to the transverse direction by excavation and removing the earth and sand existing between the small diameter pipe and the transverse connecting steel plate, and making the base between the horizontal connecting steel plate from which the soil is removed. While installing the slab while pressing the upper slab of the tunnel, and collecting the small diameter steel pipe, both sides of the lower side of the large diameter steel pipe Press-installing the steel pipe for earth retaining; forming a small work tunnel under the large-diameter steel pipe and forming a foundation; and opening the upper portion of the work tunnel to join the base of the slab and the work tunnel. Forming a step, and excavating the tunnel surrounded by the concrete support wall and the slab, and placing the slab in the lower portion of the excavated tunnel to combine with the base to complete the tunnel, large diameter steel pipe and small diameter The construction of the upper surface of the tunnel, which is a difficult construction, is made very easily by using the lateral connecting steel plate of the steel pipe, which greatly reduces the air, reduces the manpower, and solves the problems of the existing construction method, in which the foundation is continuously submerged until the end of construction. The small diameter steel pipe used in the process and the transverse connecting steel plate at the bottom can be recovered and reused. Support pillars and walls of the tunnel is also constructed so yitorok for prefabricated construction method was to build the structural stability after the temporary ground reinforcement construction will never be able to top the roadbed does not sink under construction can safely use the upper transport.

Description

비개착식 터널굴착방법 및 상기 방법에 의하여 설치된 터널구조체{None open cut tunnelling method and tunnel}Non-open tunnel tunneling method and tunnel structure installed by the method {None open cut tunneling method and tunnel}

도1은 본 발명에 따른 비개착식 터널굴착방법에 의해 굴착된 터널구조체의 종단면도1 is a longitudinal cross-sectional view of a tunnel structure excavated by a non-adhesive tunnel excavation method according to the present invention;

도2는 본 발명에 따른 비개착식 터널굴착방법의 공정도Figure 2 is a process diagram of the non-adhesive tunnel excavation method according to the invention

도3a는 본 발명에 따른 비개착식 터널굴착방법의 제1단계인 대구경강관의 배치상태를 보인 개략적인 터널단면도Figure 3a is a schematic cross-sectional view showing the arrangement of the large diameter steel pipe as a first step of the non-adhesive tunnel excavation method according to the present invention

도3b는 본 발명의 제2단계인 소구경강관과 대구경강관과의 연결배치상태를 보인 개략적인 터널단면도Figure 3b is a schematic cross-sectional view showing a connection arrangement between the small diameter steel pipe and the large diameter steel pipe of the second step of the present invention

도3c는 본 발명에서 횡방향 연결강판사이의 토사를 제거하는 상태를 도시한 개략적인 터널단면도Figure 3c is a schematic cross-sectional view showing a state of removing the soil between the lateral connecting steel sheet in the present invention

도3d은 본 발명에서 상부 슬래브를 설치하는 상태를 도시한 개략적인 터널단면도Figure 3d is a schematic cross-sectional view showing a state of installing the upper slab in the present invention

도3e은 본 발명에서 흙막이용 강관의 설치상태를 도시한 개략적인 터널단면도Figure 3e is a schematic cross-sectional view showing the installation state of the steel pipe for use in the present invention

도3f은 본 발명에서 작업터널을 형성하고 기반부를 형성한 상태를 도시한 개략적인 터널단면도Figure 3f is a schematic cross-sectional view showing a state in which the working tunnel is formed and the base portion formed in the present invention

도3g는 본 발명에서 콘크리트지지벽체를 형성하는 단계를 도시한 개략적인 터널단면도Figure 3g is a schematic cross-sectional view showing the step of forming a concrete support wall in the present invention

도3h는 터널을 굴착하는 단계를 도시한 개략적인 터널단면도Fig. 3h is a schematic tunnel sectional view showing the step of digging a tunnel;

도4는 대구경강관의 일부를 점진적으로 개방하면서 소구경강관을 삽입시키는 것을 도시한 종단면도Figure 4 is a longitudinal sectional view showing the insertion of a small diameter steel pipe while gradually opening a portion of the large diameter steel pipe;

도5는 상부 슬래브의 설치시 상부 슬래브의 단면을 도시한 개략적인 단면도5 is a schematic cross-sectional view showing a cross section of the upper slab in the installation of the upper slab;

도6a는 도5의 I의 부분 상세도이고, 도6b는 도5의 II부분의 부분상세도FIG. 6A is a partial detailed view of I of FIG. 5, and FIG. 6B is a partial detailed view of II of FIG.

도7a,7b는 흙막이용 강관의 서로 다른 실시예를 도시한 개략적인 단면도Figures 7a, 7b is a schematic cross-sectional view showing different embodiments of the retaining steel pipe

도8a,8b는 횡방향 연결강판의 삽입단부와 파지단부의 서로 다른 실시예를 도시한 개략적인 단면도8A and 8B are schematic cross-sectional views showing different embodiments of the insertion end and the gripping end of the transverse connecting steel sheet.

도9a,9b는 측면부와 중앙부의 콘크리트지지벽체의 설치를 도시한 개략적인 상세단면도9A and 9B are schematic detailed cross-sectional views showing the installation of the concrete support walls at the side and center portions;

도10은 본 발명의 다른 실시예에 따른 시공방법을 보인 개략적인 종단면도10 is a schematic longitudinal cross-sectional view showing a construction method according to another embodiment of the present invention.

* 도면의 주요부분에 대한 부호의 설명 *Explanation of symbols on the main parts of the drawings

1. 대구경강관 2. 소구경강관 3. 상부 슬래브1. Large diameter steel pipe 2. Small diameter steel pipe 3. Upper slab

4. 흙막이용 강관 5. 작업터널 6. 기반부4. Steel pipe for soil barrier 5. Work tunnel 6. Foundation

7. 콘크리트지지벽체 7. Concrete support wall

본 발명은 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체에 관한 것으로, 더욱 구체적으로 설명하면, 개착이 불가능한 고속도로횡단이나 철도노반횡단, 기타 지상 및 지하지장물을 횡단하는 터널굴착방법으로 주변환경의 훼손을 최소화하면서도 시공기간이 단축되고 시공중 지반침하의 우려가 없어 통행의 안전이 보장되며 종단곡선 및 평면곡선상의 제한없이 간단한 방식으로 굴착이 가능하게 되어 시공비용이 절감되고 사용되는 일부의 자재를 회수하여 다시 사용하는 것이 가능하게 되어 재활용성이 우수하고, 초기 지반보강 이후 지반침하가 전혀 발생되지 않아 안정성이 뛰어난 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체에 관한 것이다.The present invention relates to a non-adhesive tunnel excavation method and a tunnel structure installed by the method. More specifically, the present invention relates to a tunnel excavation method that crosses highway crossings, rail road crossings, and other ground and underground obstacles that cannot be attached. While minimizing damage to the surrounding environment, the construction period is shortened and there is no fear of ground subsidence during construction, which ensures the safety of traffic, and the excavation can be carried out in a simple manner without limiting the vertical and planar curves. The present invention relates to a non-entry tunnel excavation method and a tunnel structure installed by the method, which are excellent in recyclability and have no ground subsidence after initial ground reinforcement, and have excellent stability.

일반적으로, 비개착식으로 시공되는 터널굴착방법으로는 여러가지방식이 사용되고 있으나 가장 널리 사용되는 공법으로 전방견인공법(Front jacking method)이 보편적으로 사용되고 있다. 이러한 전방견인공법은 이미 프리캐스팅된 박스를 전진기지에 배치시키고 도로 또는 철로 건너편에 관통된 케이블에 유압잭을 설치하여 박스를 견인하여 일정거리씩 전진하면서 전진된 박스내부에서 도로 또는 철로의 노반을 굴착하는 방법으로 암반지역에서는 이러한 방법을 사용할 수 없고 토사지역에서만 가능하므로 지질학적인 제한이 있게되며 상부슬래브 윗면 이완토사에 채운 모래주머니의 견인시 흐트러짐으로 인하여 상부노반이 과다하게 침하되므로 차량의 안전운행이나 열차의 탈선을 방지하도록 하기 위한 지속적인 노반관리와 박스를 견인하기전 설치된 상부와 측면의 강관은 그대로 매몰되므로 공사비가 커지는 요인이 되고, 사용이 불가능한 선단슈제작 및 견인비로 인하여 공사비가 과다하게 되고 특히 터널의 길이가 길게 될 경우에는 연결부의 취약점인 누수가 발생할 우려가 많으며 박스가 비대칭구조일 경우에는 유압잭에 의한 견인이 불가능할 뿐만 아니라 종단곡선 및 평면곡선상에 견인이 불가능하여 터널을 설치할 수 없으므로 구조형식의 제한뿐만 아니라 비효율적인 공간성으로 인하여 공사비가 과다하게 들게 되는 문제점이 있었다.In general, a variety of methods are used as a non-removable tunnel excavation method, but the front jacking method is widely used as the most widely used method. This forward towing method places the precast box at the forward base and installs a hydraulic jack on the cable penetrated across the road or the railroad tow the box and advances it by a certain distance while excavating the roadbed or the roadbed in the forward box. This method cannot be used in the rock area but only in the soil area.There is a geological limitation, and the upper roadbed sinks excessively due to the disturbance during the towing of the sandbag filled in the upper and lower slabs of the upper slab. Continuous roadbed management to prevent derailment of trains and steel pipes on top and side installed prior to towing boxes are buried as a result of increasing construction costs, and excessive construction costs due to unusable tip shoe production and towing costs. If the tunnel becomes long In the case of asymmetrical structure, not only is it impossible to pull by hydraulic jack, but also it is impossible to pull on the vertical and planar curves. Due to the space, there was a problem that the construction cost is excessive.

본 발명의 목적은, 이러한 문제점을 해결하기 위한 것으로, 대구경강관과 소구경강관의 횡방향 연결강판을 이용하여 난공사인 터널의 상부면의 형성이 대단히 용이하게 시공되므로 공기가 월등하게 단축되고 사용인력이 절감되며 공사종료시까지 끊임없이 지반이 침하되는 기존공법의 문제점을 해결하였으며 시공시 사용된 소구경강관과 하부의 횡방향 연결강판이 회수되어 재사용할 수 있으며 터널의 지지기둥과 벽체도 조립식 공법으로 시공이 용이토록하므로 구조적 안전성을 추구하였으며 공사중 일시적 지반보강후에는 상부 노반이 절대로 침하되지 않아 공사중에도 상부 교통시설을 안전하게 사용할 수 있게 하는 것이 가능한 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체를 제공하는 것이다.An object of the present invention is to solve this problem, the formation of the upper surface of the tunnel is difficult construction by using the transverse connecting steel plate of the large diameter steel pipe and small diameter steel pipe is very easy construction is greatly shortened air and the labor force It solved the problem of the existing construction method that the ground continuously sinks until the end of the construction.The small diameter steel pipe and the horizontal connecting steel plate used in the construction can be recovered and reused, and the support column and the wall of the tunnel are also constructed by the assembly method. As this facilitates the structural safety, and after temporary ground reinforcement during construction, the upper roadbed never sinks, so the non-adhesive tunnel excavation method and tunnel structure installed by the method can be used safely. To provide.

본 발명의 이러한 목적은 상부에 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향연결강판의 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계와, 상기 작업터널의 상부를 개방시켜 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함하는 본 발명에 따른 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체에 의하여 달성된다.This object of the present invention is to be excavated in the longitudinal direction of the tunnel to be spaced apart at regular intervals in the width direction of the tunnel from the height of the tunnel to be excavated two to five large diameter steel pipe fixed to the lateral connecting steel plate on the top Press-fitting and connecting small-diameter steel pipes fixed with lateral connecting steel plates spaced at a predetermined width between the large-diameter steel pipes in a longitudinal direction by tunneling in the longitudinal direction of the tunnel and press-fitted to connect the large-diameter steel pipes in a transverse direction; And removing the earth and sand existing between the small diameter tube and the transverse connecting steel plate, and installing the slab while pressing the upper slab of the tunnel manufactured between the transverse connecting steel plate from which the soil is removed. In addition, the step of recovering the small-diameter steel pipe, the step of installing and pressing the steel pipe for earth retaining on both sides of the lower diameter of the large-diameter steel pipe, and the large-diameter steel Forming a small work tunnel below the base and forming a foundation, forming a concrete support wall to open the upper portion of the work tunnel and joining the slab and the base of the work tunnel; and to the concrete support wall and the slab. In the non-attached tunnel excavation method and tunnel structure installed by the method comprising the step of excavating the enclosed tunnel, and placing the slab in the lower portion of the excavated tunnel to combine with the base to complete the tunnel Is achieved.

본 발명에 따른 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체는 첨부된 도면을 참고로 하여 이하에 상세히 기술되는 실시예에 의하여 그 특징 및 장점들을 보다 명백하게 이해할 수 있을 것이다.Non-removable tunnel excavation method and a tunnel structure installed by the method according to the present invention will be more clearly understood by the embodiments described in detail below with reference to the accompanying drawings.

본 발명의 특징은 터널공사중의 난공사인 터널의 상부시공을 대구경강관과 대구경강관사이에 소구경강관을 배치하고 상기 대구경강관과 소구경강관상에 횡방 향 연결강판을 형성하여 대구경강관과 소구경강관을 연결하므로서 터널공사중의 난공사인 터널의 상부시공을 대단히 용이하게 수행할 수 있는 새로운 공법을 연구 도입하였으므로 향후 철도노반, 도로, 지상대형건물 및 교량 또는 지하차도등의 지하지장물을 안전하게 통과할 수 있어 지하차도, 도시철도, 지하보도, 도심터널의 횡단 등에 종단곡선 및 평면곡선상의 제한 없이 폭넓게 활용할 수 있다는 것이다.The present invention is characterized by arranging a small diameter steel pipe between a large diameter steel pipe and a large diameter steel pipe, and forming a transverse connecting steel plate on the large diameter steel pipe and the small diameter steel pipe, and forming a large diameter steel pipe and a small diameter steel pipe. By connecting and researching and introducing a new construction method that can easily perform the upper construction of the tunnel, which is a difficult construction during the tunnel construction, it can safely pass underground roadblocks such as railway roadbeds, roads, large-scale buildings and bridges or underground roadways. It can be widely used for underground roads, urban railroads, underground walkways, and cross-sections of urban tunnels without any limitations on longitudinal curves and planar curves.

본 발명의 일실시예에 따른 비개착식 터널굴착방법은, 상부에 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향 연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경강관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향 연결강판 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계와, 상기 작업터널의 상부를 개방시켜 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함한다.In the non-adhesive tunnel excavation method according to an embodiment of the present invention, two to five large-diameter steel pipes having a lateral connecting steel plate fixed thereon are spaced apart at regular intervals in the width direction of the tunnel from the height of the tunnel to be excavated. And excavating the soil in the longitudinal direction of the tunnel; and excavating the small-diameter steel pipe in which the transverse connecting steel plates are fixed with a predetermined width between the large-diameter steel pipes and fixed in the longitudinal direction of the tunnel. Connecting the large diameter steel pipe to the transverse direction by press-fitting, removing the earth and sand existing between the small-diameter steel pipe and the transverse connecting steel plate, and forming a tunnel between the horizontal connecting steel plates from which the soil is removed. While installing the slab while pressing the upper slab and recovering the small-diameter steel pipe, and press-fitting the steel pipe for earth retaining on both sides of the lower side of the large-diameter steel pipe And forming a small work tunnel under the large-diameter steel pipe and forming a base, and forming a concrete support wall to open the upper portion of the work tunnel and to join the slab and the base of the work tunnel. Excavating the tunnel surrounded by the concrete support wall and the slab; and placing the slab in the lower portion of the excavated tunnel to combine with the foundation to complete the tunnel.

상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계는 그 순서가 바뀌어도 무방하며 이와 같이 순서가 바뀐 방법도 본 발명의 범위에 포함된다고 할 것이다.The step of press-installing the steel pipe for earth retaining on both sides of the lower side of the large-diameter steel pipe, and the step of forming a small work tunnel and forming the base portion of the lower side of the large-diameter steel pipe may be changed in the order, and thus the order changed It will be said that it is included in the scope of the present invention.

상기 횡방향 연결강판(11,21)은 상기 대구경강관(1)의 상부에는 착탈가능하도록 볼트와 너트에 의하여 고정되고 측면에는 횡방향 연결강판(11)을 용접으로 고정하였으며,상기 소구경강관(2)의 상하부에는 착탈가능하도록 볼트와 너트에 의하여 고정된다. 본 실시예에서 상기 대구경강관(1)은 직경이 2400mm의 것이 사용되었고, 소구경강관(2)의 직경은 800mm의 것이 사용되었으나 이에 제한되는 것은 아니라고 할 것이다.The transverse connecting steel plates 11 and 21 are fixed to the upper part of the large diameter steel pipe 1 by detachable bolts and nuts, and fixed to the side by welding welding the transverse connecting steel plates 11 to the small diameter steel pipes. The upper and lower parts of 2) are fixed by bolts and nuts to be detachable. In this embodiment, the large diameter steel pipe (1) of the diameter of 2400mm was used, the diameter of the small diameter steel pipe (2) of 800mm was used, but will not be limited thereto.

상기 횡방향 연결강판(11,21)은, 도8a,8b에 도시된 바와 같이, 일단에는 삽입용 삽입단부(111,211)가 형성되고 타단에는 다른 횡방향 연결강판(11,21)의 삽입단부(111,211)가 삽입되도록 일부가 개방된 삽입홈(112,212)이 형성된 파지용 파지단부(113,213)가 형성되어 인접하는 횡방향 연결강판(11,21)의 삽입단부(111,211)가 삽입고정되게 되는 것이다.As illustrated in FIGS. 8A and 8B, insertion ends 111 and 211 for insertion are formed at one end and insertion ends of other transverse connection steel plates 11 and 21 at the other end of the transverse connecting steel plates 11 and 21. Holding end portions 113 and 213 for holding gripping portions 112 and 212 which are partially opened to insert 111 and 211 are formed so that insertion ends 111 and 211 of adjacent transverse connecting steel plates 11 and 21 are inserted and fixed.

도4에 도시된 바와 같이, 상기 대구경강관(1)과 소구경강관(2)의 횡방향 연결강판(11,21)이 연결설치된 후에는 상기 대구경강관(1)의 횡방향 연결강판(11)사이의 부분을 절개하고 절개된 부분에 소구경강관(2)을 끼우게 된다. 상기 소구경강관(2)을 추가로 삽입시키는 이유는 상부 슬래브가 통과하는 공간의 대구경강관의 토사의 압력을 지탱하기 위해서이다.As shown in FIG. 4, after the transverse connecting steel plates 11 and 21 of the large-diameter steel pipe 1 and the small-diameter steel pipe 2 are connected and installed, the transverse connecting steel plate 11 of the large-diameter steel pipe 1 is installed. Section between the incision and the incision is inserted into the small diameter steel pipe (2). The reason for further inserting the small-diameter steel pipe 2 is to support the pressure of the soil of the large-diameter steel pipe in the space through which the upper slab passes.

상기 횡방향 연결강판(11,21)이 설치된 후에는 지반을 보강하기 위하여 시멘 트 지반보강 그라우팅공사를 수행한다. 지반보강 그라우팅공사는 횡방향연결강판의 상부와 하부에 수행하게 된다. After the transverse connecting steel plates 11 and 21 are installed, cement ground reinforcing grouting is performed to reinforce the ground. Ground reinforcement grouting work is performed on the upper and lower parts of the transverse connecting steel sheet.

상기 지반보강 그라우팅공사가 종료되면 대구경강관(1)내에 상부 슬래브(3)를 안내하는 가이드레일(31)을 설치하고 대구경강관(1)의 하방을 절개하고 절개된 부분을 H빔(12)으로 보강하여 대구경강관(1)의 하방을 보강하는 단계가 추가된다.When the ground reinforcement grouting work is completed, the guide rail 31 for guiding the upper slab 3 is installed in the large diameter steel pipe 1 and the lower portion of the large diameter steel pipe 1 is cut and the cut portion is cut into the H beam 12. Reinforcing the lower portion of the large diameter steel pipe (1) is reinforced.

도3c에 도시된 상기 소구경관(2)사이와 횡방향 연결강판(21)사이에 존재하는 토사를 제거하는 단계는 토사에 고압의 물을 분사하여 용이하게 토사를 제거할 수 있다.The step of removing the earth and sand existing between the small-diameter tube 2 and the transverse connecting steel plate 21 shown in Figure 3c can be easily removed by spraying high-pressure water to the soil.

상기 횡방향 연결강판(11,21)내의 토사를 제거한 후에 실시되는 상부 슬래브(3)압입 작업전에 우선 상부 및 하부의 횡방향 연결강판을 상부 슬래브를 압입하는 방향측에서 흙막이공 가시설에 고정시키므로 상부 슬래브 압입에 의하여 이동되지 않도록 조치한다. 이후,소구경강관(2)의 상부 및 하부에 설치된 횡방향 연결강판(21)의 볼트결합을 해제시킨다.The upper and lower transverse connecting steel plates are first fixed to the mud masonry on the side in which the upper slab is press-fitted before the upper slab 3 pressing operation performed after removing the soil in the transverse connecting steel plates 11 and 21. Take care not to move by slab indentation. Thereafter, the bolt coupling of the transverse connecting steel plate 21 installed on the upper and lower portions of the small diameter steel pipe (2) is released.

이와 같이 소구경강관(2)과 상부 및 하부 횡방향 연결강판(21)의 결합이 해제된 상태에서 기제작된 상부 슬래브(3)를 압입시키면 소구경강관(2)이 반대편으로 배출되면서 회수할 수 있게 되는 것이다.As such, when the small slab steel pipe 2 is press-fitted into the prefabricated upper slab 3 while the upper and lower transverse connecting steel plates 21 are released from each other, the small-diameter steel pipe 2 is discharged to the opposite side to be recovered. It will be possible.

상기 상부 슬래브(3)는 압입이송을 용이하게 수행할 수 있도록,도5에 도시된 바와 같이, 제작시에 상부 슬래브(3)의 상부면(3a)보다 약간 상방으로 돌출되게 안내레일(32)이 형성되어 이송시 안내레일(32)이 상부 횡방향 연결강판(21)에 접하게 되므로 마찰저항이 줄어들게 되어 용이하게 상부 슬래브(3)를 이송할 수 있게 되는 것이다.(도6a에 상세도시) 또한, 도6b에 도시된 바와 같이, 상기 상부 슬래브(3)의 하방에는 상부 슬래브(3)의 전방의 직진이동이 가능하도록 안내홈(33)이 설치되어 상기 안내홈(33)이 하부 횡방향 연결강판(21)의 결합대(22)에 끼워져 횡방향 이동이 구속된 상태에서 결합대(22)와 안내홈(33)의 협동에 의하여 상부 슬래브(3)의 직진이동이 보장된다. 이와 같이 터널의 길이 방향으로 다수의 상부 슬래브(3)를 연속적으로 압입시켜 터널 일측의 상부골조가 설치 종료되고, 본 실시예에서는 이와 같은 방식으로 인접한 다른 터널의 상부골조도 설치를 종료시킬 수 있게 되는 것이다.As illustrated in FIG. 5, the upper slab 3 protrudes slightly above the upper surface 3a of the upper slab 3 so as to easily perform the press-in transfer. This is because the guide rail 32 is in contact with the upper transverse connecting steel plate 21 during the transfer, so that the frictional resistance is reduced to facilitate the transfer of the upper slab (3) (detailed in Figure 6a) 6B, a guide groove 33 is installed below the upper slab 3 to enable a straight forward movement of the upper slab 3 so that the guide groove 33 is connected in the lower transverse direction. A straight movement of the upper slab 3 is ensured by cooperation of the coupling table 22 and the guide groove 33 in a state where the movement of the steel plate 21 is coupled to the coupling table 22. In this way, the upper frame of one side of the tunnel is continuously installed by pressing a plurality of upper slabs 3 continuously in the longitudinal direction of the tunnel, and in this embodiment, the upper frame of another adjacent tunnel can also be terminated. Will be.

상기 상부 슬래브(3)의 압입설치가 종료되고, 상기 대구경강관(1)의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계에서, 본 실시예에서는, 도7a에 도시된 바와 같이, 측면에 상하 연장강판(41',41",41'",41"")이 고정된 소구경강관(42)을 압입설치하는 방식을 채택하였으나, 도7b에 도시된 바와 같이, 흙막이용 대구경강관(43)을 압입설치하고 흙막이 방지대를 설치할 수 있으며 이 경우에는 토립자유출방지대(44)가 설치되는 구조이다. 이와 같이 상기 대구경강관(1)의 하방의 양 측면에 흙막이용 강관(4)의 압입설치가 종료된 후에는 하방의 터널부위의 지반보강 그라우팅작업을 실시한다.The press-installation of the upper slab 3 is completed, and in the step of press-installing the steel pipe for earth retaining on both sides of the large diameter steel pipe 1 below, in this embodiment, as shown in Figure 7a, Although the upper and lower extension steel plates 41 ', 41 ", 41'", 41 "" are adopted to press-fit the small-diameter steel pipe 42 to which it is fixed, as shown in FIG. ) Can be press-installed and installed the earthquake prevention guards, in which case the tortilla spill prevention guards 44 are installed. As described above, after the press-fitting installation of the retaining steel pipe 4 on both sides of the large-diameter steel pipe 1 is completed, the ground reinforcing grouting of the tunnel portion below is performed.

상기 대구경강관(1)의 하방에 소형 작업터널(5)을 형성하고 기반부(6)를 형성하는 단계에서는 상단덮개(51)를 착탈가능하게 설치한 터널프레임(52)을 1~2m의 일정한 간격으로 이격되게 설치하고 이격간격에는 토류판(도시않함)을 설치하면서 작업터널(5)을 굴진한다. 이와 같이 작업터널을 관통한 후에는 작업터널(5)의 상단 덮개(51)를 목재버팀대(도시않함)로 교체하고 대구경강관(1)과 양 측면의 흙막이용 강관(4)으로 둘러쌓인 토사를 소형작업터널(5)로 배토시키고, 터널프레임(52)과 측면의 상하연장강판(41",41"")을 결속장치시설(45)로 묶어주어 터널프레임(52)이 밀리지 않도록 고정시킨 다음에 기반부(6)를 형성할 수 있을 것이다. 상기 기반부(6)를 형성하기 전에 압입된 양측의 상부 슬래브단부가 만나는 중앙지지부에서 양측 상부 슬래브를 연결볼트로 묶어준다. 또한, 연약지반인 경우에는 상부에서 전달되는 하중을 지지하도록 저면에 다수의 마이크로파일(63)이 설치된 말뚝공사를 선행하여 작업할 수도 있을 것이다. 상기 기반부(6)의 작업시 기반부(6)상에는 벽체안내레일(61)이 설치되고 소형터널의 측벽에서 연장되는 안내레일(62)이 콘크리트조립벽(71)을 지지하게 된다. 상기 콘크리트조립벽(71)의 하방에는 상기 벽체안내레일(61)이 삽입되는 안내홈(711)이 형성되어 있다.In the step of forming a small work tunnel (5) below the large-diameter steel pipe (1) and forming the base (6), the tunnel frame 52, which is detachably installed with the top cover 51, is fixed at a constant of 1 to 2 m. Install the spaced apart at intervals and install the earth plate (not shown) in the spaced interval to drill the work tunnel (5). After passing through the work tunnel like this, the upper cover 51 of the work tunnel 5 is replaced with a wooden brace (not shown), and the earth and sand surrounded by the large-diameter steel pipe (1) and the steel pipe (4) for both sides of the soil is removed. Top up and down the tunnel frame 52 and the vertical extension steel sheets 41 ", 41" "of the side by the binding device facility 45 to fix the tunnel frame 52 so as not to be pushed. It is possible to form the base portion 6. At the central support portion where the upper slab ends of the press-fitted sides meet before the base portion 6 is formed, both upper slabs are bundled with connecting bolts. In this case, a pile construction in which a plurality of micropiles 63 are installed on the bottom may be performed in advance to support the load transmitted from the upper part. 61 is installed and extends from the sidewall of the small tunnel The guide rail 62 is to support the concrete assembly wall 71. The guide groove 711 is formed below the concrete assembly wall 71 is inserted into the wall guide rail 61.

상기 작업터널(5)과 기반부(6)가 완성되고 대구경강관(1)과 작업터널(5)이 상하로 관통된 관통공간(S1)이 형성되면, 기제작된 조립식 콘크리트조립벽(71)이 기반부(6)의 벽체안내레일(61)상에 배치되고 콘크리트조립벽(71)을 전방으로 밀게되면 콘크리트조립벽(71)의 안내홈(711)이 벽체안내레일(61)을 타고 이동되어 차례로 일렬로 배치조립되면서 이후에 기술될 기본적인 콘크리트지지벽체(7)를 형성하게 되는 것이다.When the work tunnel 5 and the base 6 are completed and the large diameter steel pipe 1 and the work tunnel 5 penetrate up and down are formed, the prefabricated concrete assembly wall 71 is manufactured. The guide groove 711 of the concrete assembly wall 71 moves on the wall guide rail 61 when it is disposed on the wall guide rail 61 of the base 6 and pushes the concrete assembly wall 71 forward. In order to be arranged in series in order to form a basic concrete support wall (7) to be described later.

특히, 터널의 중앙 기둥역할을 수행하는 중간의 콘크리트지지벽체(7)의 상부에 위치되는 압입된 양측의 상부 슬래브(3)가 만나는 부분에서는 상부 슬래브(3)의 이동이 방지되도록 양측 상부 슬래브(3)를 연결볼트와 같은 고정수단(35)으로 묶어 고정시킨다.In particular, at the portion where the upper slabs 3 of the press-fitted two sides located at the upper part of the intermediate concrete support wall 7 serving as the central pillar of the tunnel meet, both upper slabs (2) are prevented from moving. 3) is tied to the fixing means 35, such as connecting bolts and fixed.

이와 같이 일련의 콘크리트조립벽(71)이 각 대구경강관(1)의 하방에 형성된 후, 슬래브(3)의 하단과 콘크리트조립벽(71)의 상단에 철근을 겹이음한 후 콘크리트를 타설하여 연결시키고 콘크리트조립벽(71)의 하단과 기반부(6)에 철근을 겹이음 한 후 콘크리트를 타설하여 연결시켜 콘크리트지지벽체(7)를 형성하게 되는 것이다.As described above, after a series of concrete assembly walls 71 are formed below each large diameter steel pipe 1, the reinforcing bars are stacked on the bottom of the slab 3 and the top of the concrete assembly wall 71, and then concrete is poured to connect them. After the reinforcing bars on the bottom and the base 6 of the concrete assembly wall 71, the concrete is poured by connecting to form a concrete support wall (7).

본 발명의 기술중 상부 슬래브를 하부에서 지지하는 구조물을 통칭하여 콘크리트지지벽체(7)로 기술하였으나, 이는 이해를 돕기 위하여 설명을 단순하게 기술하기 위한 것으로 실제로는 터널의 벽에 위치되는 콘크리트지지벽체와 터널의 중간에 설치되는 콘크리트 지지기둥으로 구별될 수 있으나 양자는 모두 상부 슬래브를 하부에서 지지하는 구조이므로 설명상 구분없이 통칭하여 콘크리트지지벽체(7)로 기술하였다. In the description of the present invention, the structure supporting the upper slab at the bottom is collectively described as a concrete support wall (7), but this is for the purpose of simply describing the description for the purpose of understanding and concrete support wall which is actually located on the wall of the tunnel. Although it can be distinguished from the concrete support pillar is installed in the middle of the tunnel and both of the structure to support the upper slab at the bottom, it is collectively described as a concrete support wall (7) without distinction in the description.

이와 같이 콘크리트지지벽체(7)에 의하여 슬래브(3)와 기반부(6)가 연결설치된후에 터널내의 토사를 굴착하면 하부의 횡방향 연결강판(21)과 흙막이용 강관(42")과 상하연장강판(41"',41"")이 토사굴착과 함께 회수되게 되는 것이다. 또한, 흙막이용 강관(42')내부(S3)에 흄관을 압입하고 내부공간(S2)에 무수축채움재를 채운후 와이어 등으로 당겨 흙막이용 강관(42')과 상하연장강판(41")을 회수하는 것이다. 이와 같이 하여 터널내의 토사를 제거한 후, 공간으로 잔존하는 대구경강관(1)과 소형작업터널 외측공간(S4)과 작업터널(5)의 빈공간에 콘크리트를 타설하여 채운다.After the slab 3 and the foundation 6 are connected to each other by the concrete support wall 7, excavation of the earth and sand in the tunnel is carried out. The transverse connecting steel plate 21 at the lower part and the steel pipe 42 " The steel sheets 41 "', 41" "are recovered together with the earth and sand excavation. In addition, the fume pipe is press-fitted into the inner portion S3 and the non-shrink filling material is filled in the inner space S2, and then pulled with a wire or the like to hold the seizure steel pipe 42 'and the upper and lower extension steel sheets 41 ". In this way, after removing the earth and sand in the tunnel, concrete is poured into the empty space of the large-diameter steel pipe 1 remaining in the space, the outer space S4 and the work tunnel 5 remaining in the space.

이상태에서 굴착된 터널의 하부에 슬래브를 타설하고 기반부와 결합시켜 터널이 완공되게 되는 것이다.In this state, the slab is placed at the bottom of the excavated tunnel and combined with the foundation to complete the tunnel.

따라서 이와 같은 본 발명의 비개착식 터널굴착방법에 따라 형성된 본 발명에 따른 터널구조체(A)는 터널의 상부에는 지반보강 그라우팅층이 형성되고 상부 횡방향 연결강판(11,21)이 배치되고 상기 상부 횡방향 연결강판(11,21)의 하부에는 터널의 상부를 형성하는 상부 슬래브(3)가 배치되고 상부 슬래브(3)가 콘크리트지지벽체(7)에 의하여 지지되는 구조이다.Therefore, in the tunnel structure A according to the present invention formed according to the non-adhesive tunnel excavation method of the present invention, the ground reinforcing grouting layer is formed on the upper part of the tunnel, and the upper transverse connecting steel plates 11 and 21 are disposed. An upper slab 3 is formed below the upper transverse connecting steel plates 11 and 21 and the upper slab 3 is supported by the concrete support wall 7.

도10에 도시된 바와 같이, 본 발명의 다른 실시예에 따른 비개착식 터널굴착방법은, 소형 작업터널(5)대신에 측면에 상하 연장강판(41',41",41'",41"")이 고정된 소구경강관(42)을 압입설치하는 방식을 채택하였다. 본 발명의 상기 실시예에 따른 비개착식 터널굴착방법은 상부에 커버플레이트를 포함하는 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향 연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경강관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향 연결강판 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 다수의 흙막이용 강관을 상하로 연결되게 압입설치하는 단계와, 상기 흙막이용 강관사이의 토사를 굴 착하고 기반부를 형성하는 단계와, 상기 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하면서 콘크리트지지벽체의 내측에 설치된 흙막이용 강관을 회수하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함한다. 콘크리트지지벽체의 외측에 위치되는 흙막이용 강관은 상하연장강판과의 볼트와 너트의 결합이 해제되고 콘크리트지지벽체에 인접한 상하 연장강판과 흙막이용 강관은 무수축채움재를 압입하는 압출방법에 의하여 회수되고 틈은 몰탈로 충진된다. 상기의 실시예에 따른 비개착식 터널굴착방법에 의하여 시공된 터널구조체는 터널의 상부에는 지반보강 그라우팅층이 형성되고 상부 횡방향 연결강판(11,21)이 배치되고 상기 상부 횡방향 연결강판(11,21)의 하부에는 터널의 상부를 형성하는 상부 슬래브(3)가 배치되고 상부 슬래브(3)가 콘크리트지지벽체(7)에 의하여 지지되고 콘크리트지지벽체(7)의 외측에는 수평으로 연장된 그리드 플레이트가 용접된 상하 연장강판이 매설되는 구조이다. As shown in Fig. 10, in the non-adhesive tunnel excavation method according to another embodiment of the present invention, the up and down extension steel plates 41 ', 41 ", 41'", 41 "on the side instead of the small work tunnel (5). Adopted a method of press-installing small diameter steel pipe (42) is fixed. In the non-adhesive tunnel excavation method according to the embodiment of the present invention, a predetermined interval in the width direction of the tunnel from the height of the tunnel to which two to five large-diameter steel pipes in which a transverse connecting steel plate including a cover plate is fixed thereon is fixed. And the step of press-fitting soil excavation in the longitudinal direction of the tunnel, and the small-diameter steel pipe in which the transverse connecting steel plates are fixed with a predetermined width between the large-diameter steel pipes and fixed in the longitudinal direction of the tunnel. Connecting the large diameter steel pipe with the large diameter steel pipe and transversely by excavating the earth and sand; and removing the earth sand existing between the small diameter steel pipe and the transverse connecting steel plate, and between the horizontal connecting steel plate from which the soil sand has been removed. While installing the slab while pressing the upper slab of the fabricated tunnel and recovering the small diameter steel pipe, both sides of the lower side of the large diameter steel pipe Press-installing a plurality of retaining steel pipes to be connected up and down, excavating the soil between the retaining steel pipes and forming a foundation, and forming a concrete support wall to be coupled with the foundation of the slab and the work tunnel. And recovering the steel pipe for the earth retaining wall installed inside the concrete support wall while excavating the tunnel surrounded by the concrete support wall and the slab, and placing the slab in the lower part of the excavated tunnel to combine with the foundation to complete the tunnel. It comprises the step of. The retaining steel pipe located outside the concrete supporting wall is released from the bolt and nut of the upper and lower extension steel plates, and the upper and lower extension steel plates and the retaining steel pipe adjacent to the concrete supporting wall are recovered by the extrusion method of pressurizing the non-contraction filling material. The gap is filled with mortar. In the tunnel structure constructed by the non-adhesive tunnel excavation method according to the above embodiment, the ground reinforcing grouting layer is formed on the upper part of the tunnel, and the upper transverse connecting steel plates 11 and 21 are disposed, and the upper transverse connecting steel plate ( The upper slab 3 which forms the upper part of the tunnel is arrange | positioned at the lower part of 11 and 21, and the upper slab 3 is supported by the concrete support wall 7, and horizontally extended outside the concrete support wall 7 The upper and lower extension steel plates welded with the grid plate are embedded.

이상과 같이 본 발명에 따른 비개착식 터널굴착방법 및 그 방법에 의하여 설치된 터널구조체는 상부에 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계 와, 상기 소구경강관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향연결강판의 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계와, 상기 작업터널의 상부를 개방시켜 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하는 단계와, 굴착된 터널의 하부에 슬래브를 구축하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함하므로, 대구경강관과 소구경강관의 횡방향 연결강판을 이용하여 난공사인 터널의 상부면의 형성이 대단히 용이하게 시공되므로 공기가 월등하게 단축되고 사용인력이 절감되며 공사 종료시까지 끊임없이 지반이 침하되는 기존공법의 문제점을 해결하였으며 시공시 사용된 소구경강관과 하부의 횡방향 연결강판이 회수되어 재사용할 수 있으며 터널의 지지기둥과 벽체도 조립식 공법으로 시공이 용이토록하므로 구조적 안정선을 구축하였으며 공사중 일시적 지반보강 후에는 상부 노반이 절대로 침하되지 않아 공사중에도 상부 교통시설을 안전하게 사용할 수 있게 되는 것이다.As described above, the non-adhesive tunnel excavation method and the tunnel structure installed by the method in the width direction of the tunnel at the height of the tunnel to be excavated two to five large diameter steel pipe is fixed to the transverse connecting steel plate on the top A step of excavating the earth and sand in the longitudinal direction of the tunnel and spaced apart at regular intervals, and a small diameter steel pipe having a horizontal connection steel plate fixed with a vertical width spaced apart from the large diameter steel pipes by a predetermined width. Connecting the large diameter steel pipe and the transverse direction by press-fitting and excavating the soil in the direction; and removing the earth and sand existing between the small-diameter steel pipe and the transverse connecting steel plate, and removing the earth connection of the horizontal connecting steel plate. While installing the slab while pressing the upper slab of the pre-fabricated tunnel in between and recovering the small diameter steel pipe, and the large diameter steel pipe Press-installing the steel pipes for both sides of the room, forming a small work tunnel under the large-diameter steel pipe and forming a base, and opening the upper portion of the work tunnel to couple with the base of the slab and the work tunnel. Forming a concrete support wall, and excavating the tunnel surrounded by the concrete support wall and the slab; and constructing a slab at the lower part of the excavated tunnel to combine the foundation with the foundation to complete the tunnel. The problem of the existing construction method is that the upper surface of the tunnel, which is difficult construction, is constructed very easily by using the lateral connecting steel plate of the steel pipe and the small-diameter steel pipe, which greatly shortens the air, reduces the manpower, and continuously subsides the ground until the end of construction. The small diameter steel pipe used in the construction and the transverse connecting steel plate at the bottom were recovered and You can use and support pillars and walls of the tunnels, so yitorok for the prefabricated construction method was built after the construction of structural anjeongseon temporarily ground reinforcement will be able top do not ballast can never sink to safely use the upper transport facilities under construction.

Claims (15)

비개착식 터널굴착방법에 있어서, In the non-attached tunnel excavation method, 상부에 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경강관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향연결강판의 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 흙막이용 강관을 압입설치하는 단계와, 상기 대구경강관의 하방에 소형 작업터널을 형성하고 기반부를 형성하는 단계와, 상기 작업터널의 상부를 개방시켜 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함하는 것을 특징으로 하는 비개착식 터널굴착방법2 to 5 large-diameter steel pipe in which the lateral connecting steel plate is fixed on the upper portion is spaced apart at regular intervals in the width direction of the tunnel at the height of the tunnel to be excavated, and the earth-excavation is pressed in the longitudinal direction of the tunnel; Connecting the small-diameter steel pipe with the horizontally-connected steel plates spaced apart from each other in large-diameter steel pipes with a predetermined width in a predetermined width by earth excavation in the longitudinal direction of the tunnel and press-fitting them to the large-diameter steel pipe in the transverse direction; Removing the earth and sand existing between the steel pipe and the transverse connecting steel plate, and installing the slab while pressing the upper slab of the tunnel manufactured between the transverse connecting steel plate from which the soil is removed, Recovering and pressing-installing the steel pipe for earth retaining into both side surfaces of the large diameter steel pipe, and a small work place below the large diameter steel pipe. Forming a base and forming a base, opening an upper portion of the work tunnel to form a concrete support wall for joining the slab with the base of the work tunnel, and excavating a tunnel surrounded by the concrete support wall and the slab. And placing a slab on the lower part of the excavated tunnel and combining it with the base to complete the tunnel. 청구항 2은(는) 설정등록료 납부시 포기되었습니다.Claim 2 was abandoned when the setup registration fee was paid. 제1항에 있어서, 상기 횡방향 연결강판(11,21)은 상기 대구경강관(1)상부와 상기 소구경강관(2)상하부에는 착탈가능하도록 볼트와 너트에 의하여 결합되는 것 을 특징으로 하는 비개착식 터널굴착방법.According to claim 1, wherein the lateral connecting steel plates (11, 21) is characterized in that the upper and lower parts of the large diameter steel pipe (1) and the small diameter steel pipe (2) is coupled to the removable by bolts and nuts. Open tunnel excavation method. 청구항 3은(는) 설정등록료 납부시 포기되었습니다.Claim 3 was abandoned when the setup registration fee was paid. 제1항에 있어서, 상기 대구경강관과 소구경강관이 횡방향 연결강판에 의하여 연결된 단계뒤에는, 상기 대구경강관(1)내에 상부 슬래브(3)를 안내하는 가이드레일(31)을 설치하고 대구경강관(1)의 하방을 절개하고 절개된 부분을 H빔(12)으로 보강하여 대구경강관(1)의 하방을 보강하는 단계가 추가로 구성된 것을 특징으로 하는 비개착식 터널굴착방법.According to claim 1, After the step of connecting the large-diameter steel pipe and the small-diameter steel pipe by the transverse connecting steel plate, the guide rail 31 for guiding the upper slab (3) in the large-diameter steel pipe (1) is installed and the large-diameter steel pipe ( Reinforcing the lower part of 1) and reinforcing the cut portion with the H-beam (12) to reinforce the downward of the large diameter steel pipe (1) Non-adhesive tunnel excavation method, characterized in that further configured. 청구항 4은(는) 설정등록료 납부시 포기되었습니다.Claim 4 was abandoned when the registration fee was paid. 제1항에 있어서, 상기 소구경강관(2)사이와 횡방향 연결강판(21)사이에 존재하는 토사를 제거하는 단계는 토사에 고압의 물을 분사하여 용이하게 토사를 제거하는 것을 특징으로 하는 비개착식 터널굴착방법The method of claim 1, wherein the step of removing the earth and sand existing between the small-diameter steel pipe (2) and the lateral connecting steel plate 21 is characterized in that to remove the earth and sand easily by spraying high pressure water to the soil. Non-removable tunnel excavation method 제1항에 있어서, 상기 횡방향 연결강판(21)은 일단에는 삽입용 삽입단부(211)가 형성되고 타단에는 다른 횡방향 연결강판(21)의 삽입단부(211)가 삽입되도록 일부가 개방된 삽입홈(212)이 형성된 파지용 파지단부(213)가 형성되어 인접하는 횡방향 연결강판(21)의 삽입단부(211)가 삽입고정되게 되는 방식으로 연결되는 것을 특징으로 하는 비개착식 터널굴착방법.According to claim 1, wherein the transverse connecting steel plate 21 is inserted into the insertion end portion 211 is formed at one end and the other end is opened so that the insertion end portion 211 of the other transverse connecting steel plate 21 is inserted Non-removable tunnel excavation, characterized in that the gripping end portion 213 for gripping with the insertion groove 212 is formed so that the insertion end portion 211 of the adjacent transverse connecting steel plate 21 is inserted and fixed. Way. 청구항 6은(는) 설정등록료 납부시 포기되었습니다.Claim 6 was abandoned when the registration fee was paid. 제1항에 있어서, 상기 횡방향 연결강판(11,21)내의 토사를 제거한 후에 실시되는 상부 슬래브(3)압입작업전에 우선 소구경강관(2)의 상부 및 하부에 설치된 횡 방향 연결강판(21)의 볼트결합을 해제시키는 것을 특징으로 하는 비개착식 터널굴착방법.The transverse connecting steel plate (21) provided in the upper and lower portions of the small-diameter steel pipe (2) according to claim 1, before the upper slab (3) press-in operation carried out after removing the soil in the connecting steel plates (11, 21). The non-attached tunnel excavation method, characterized in that to release the bolt coupling. 제1항에 있어서, 상기 콘크리트지지벽체를 형성시키는 단계에서 콘크리트조립벽(71)이 각 대구경강관(1)의 하방에 배치된 후, 슬래브(3)의 하단과 콘크리트조립벽(71)의 상단에 철근이음후에 콘크리트를 타설하여 연결시키고 콘크리트조립벽(71)의 하단과 기반부(6)에 철근이음후 콘크리트를 타설하여 연결시켜 콘크리트지지벽체(7)를 형성하게 되는 것을 특징으로 하는 비개착식 터널굴착방법According to claim 1, After the concrete assembly wall 71 is disposed below each large diameter steel pipe 1 in the step of forming the concrete support wall, the lower end of the slab 3 and the upper end of the concrete assembly wall 71 Non-adhesive, characterized in that the concrete support wall (7) is formed by connecting the concrete after the reinforcing bars in the concrete assembly wall 71 and the concrete after the reinforcing bars connected to the concrete after the reinforcing bars. Tunnel Excavation Method 제1항에 있어서, 상기 콘크리트지지벽체를 형성시키는 단계에서, 기제작된 조립식 콘크리트조립벽(71)이 기반부(6)의 벽체안내레일(61)상에 배치되고 콘크리트조립벽(71)을 전방으로 밀게되면 콘크리트조립벽(71)이 벽체안내레일(61)을 타고 이동되어 차례로 일렬로 배치조립되면서 콘크리트지지벽체(7)를 형성하게 되는 것을 특징으로 하는 비개착식 터널굴착방법According to claim 1, In the step of forming the concrete support wall, the prefabricated prefabricated concrete assembly wall 71 is disposed on the wall guide rail 61 of the base portion 6 and the concrete assembly wall 71 When pushed forward the non-adhesive tunnel excavation method, characterized in that the concrete assembly wall 71 is moved in the wall guide rail 61 and arranged in a row in order to form a concrete support wall (7) 제1항에 따른 방법에 의하여 시공되어 터널의 상부에는 지반보강 그라우팅층이 형성되고 상부 횡방향 연결강판(11,21)이 배치되고 상기 상부 횡방향 연결강판(11,21)의 내부에는 터널의 상부를 형성하는 상부 슬래브(3)가 배치되고 상부 슬래브(3)가 콘크리트조립벽(71)이 일렬로 배치되고 기반부(6)와 일체로 형성된 콘크리트지지벽체(7)에 의하여 지지되는 것을 특징으로 하는 터널구조체Constructed by the method according to claim 1, the ground reinforcement grouting layer is formed on the upper part of the tunnel, and the upper transverse connecting steel plates 11 and 21 are disposed, and the upper transverse connecting steel plates 11 and 21 are formed inside the tunnel. An upper slab 3 forming an upper part is disposed, and the upper slab 3 is supported by the concrete support wall 7 formed with the concrete assembly walls 71 in a row and integrally formed with the base 6. Tunnel structure 청구항 10은(는) 설정등록료 납부시 포기되었습니다.Claim 10 was abandoned upon payment of a setup registration fee. 제9항에 있어서, 상기 상부 슬래브(3)는 상부 슬래브(3)의 상부면(3a)보다 약간 상방으로 돌출되게 안내레일(32)이 형성된 것을 특징으로 하는 터널구조체.10. Tunnel structure according to claim 9, characterized in that the upper slab (3) is formed with a guide rail (32) to protrude slightly above the upper surface (3a) of the upper slab (3). 청구항 11은(는) 설정등록료 납부시 포기되었습니다.Claim 11 was abandoned upon payment of a setup registration fee. 제9항에 있어서, 상기 기반부(6)상에는 벽체안내레일(61)이 설치되고 상기 콘크리트조립벽(71)의 하방에는 상기 벽체안내레일(61)이 삽입되는 안내홈(711)이 형성된 것을 특징으로 하는 터널구조체.10. The method of claim 9, wherein the wall guide rail 61 is installed on the base portion 6 and the guide groove 711 is formed below the concrete assembly wall 71 is inserted into the wall guide rail 61 Tunnel structure characterized in that. 청구항 12은(는) 설정등록료 납부시 포기되었습니다.Claim 12 was abandoned upon payment of a registration fee. 제9항에 있어서, 상기 횡방향 연결강판(11,21)은 일단에는 삽입용 삽입단부(211)가 형성되고 타단에는 다른 횡방향 연결강판(21)의 삽입단부(211)가 삽입되도록 일부가 개방된 삽입홈(212)이 형성된 파지용 파지단부(213)가 형성되어 인접하는 횡방향 연결강판(21)의 삽입단부(211)가 삽입고정되게 되게 연결된 것을 특징으로 하는 터널구조체The transverse connecting steel plates 11 and 21 are partially inserted such that an insertion end 211 for insertion is formed at one end and an insertion end 211 of the other transverse connecting steel plate 21 is inserted at the other end thereof. A gripping end portion 213 having an open insertion groove 212 formed therein is a tunnel structure, characterized in that the insertion end portion 211 of the adjacent transverse connecting steel plate 21 is connected and fixedly inserted. 청구항 13은(는) 설정등록료 납부시 포기되었습니다.Claim 13 was abandoned upon payment of a registration fee. 비개착식 터널굴착방법에 있어서,In the non-attached tunnel excavation method, 상부에 커버플레이트를 포함하는 횡방향연결강판이 고정된 2개 내지 5개의 대구경강관을 굴착될 터널의 높이에서 터널의 폭방향으로 일정간격으로 이격되게 배치되어 터널의 길이방향으로 토사굴착을 하며 압입시키는 단계와, 상기 대구경강관들사이에 일정폭으로 상하간격을 갖게 이격된 횡방향 연결강판이 고정된 소구경강관을 터널의 길이방향으로 토사굴착을 하며 압입시켜 대구경강관과 횡방향으로 연결시키는 단계와, 상기 소구경강관사이와 횡방향연결강판사이에 존재하는 토사를 제거하는 단계와, 상기 토사가 제거된 횡방향 연결강판 사이에 기제작된 터널의 상부 슬래브를 압입시키면서 슬래브를 설치함과 아울러 소구경강관을 회수하는 단계와, 상기 대구경강관의 하방의 양 측면에 다수의 흙막이용 강관을 상하로 연결되게 압입설치하는 단계와, 상기 흙막이용 강관사이의 토사를 굴착하고 기반부를 형성하는 단계와, 상기 슬래브와 작업터널의 기반부와 결합시키는 콘크리트지지벽체를 형성시키는 단계와, 상기 콘크리트지지벽체와 슬래브로 둘러싸인 터널을 굴착하면서 콘크리트지지벽체의 내측에 설치된 흙막이용 강관을 회수하는 단계와, 굴착된 터널의 하부에 슬래브를 타설하여 기반부와 결합시켜 터널을 완성시키는 단계를 포함하는 것을 특징으로 하는 비개착식 터널굴착방법 Two to five large-diameter steel pipes having a lateral connecting steel plate including a cover plate fixed thereon are arranged at a predetermined interval in the width direction of the tunnel from the height of the tunnel to be excavated, and the earth excavation is carried out in the longitudinal direction of the tunnel. And a small-diameter steel tube having a horizontal connection steel plate spaced apart from each other by a predetermined width between the large-diameter steel pipes fixed in the longitudinal direction of the tunnel and press-fitted to connect the large-diameter steel pipe to the transverse direction. And removing the earth and sand existing between the small diameter steel pipe and the transverse connecting steel plate, and installing the slab while pressing the upper slab of the tunnel manufactured between the transverse connecting steel plate from which the soil is removed. Recovering the small-diameter steel pipe, and press-installed so as to connect a plurality of earth pipe steel pipe up and down on both sides of the large diameter steel pipe below And excavating earth and sand between the earthen steel pipe and forming a foundation, forming a concrete support wall coupled with the slab and the foundation of the working tunnel, and a tunnel surrounded by the concrete support wall and the slab. Recovering the steel pipe for the retaining wall installed inside the concrete support wall while excavating, and placing the slab on the lower part of the excavated tunnel, combining with the base to complete the tunnel, characterized in that it comprises a Excavation method 청구항 14은(는) 설정등록료 납부시 포기되었습니다.Claim 14 was abandoned when the registration fee was paid. 제13항에 따른 방법에 의하여 시공되어 터널의 상부에는 지반보강 그라우팅층이 형성되고 상부 횡방향 연결강판(11,21)이 배치되고 상기 상부 횡방향 연결강판(11,21)의 내부에는 터널의 상부를 형성하는 상부 슬래브(3)가 배치되고 상부 슬래브(3)가 콘크리트조립벽(71)이 일렬로 배치되고 기반부(6)와 일체로 형성된 콘크리트지지벽체(7)에 의하여 지지되고 콘크리트지지벽체(7)의 외측에는 수평으로 연장된 그리드 플레이트가 용접된 상하 연장강판이 매설된 것을 특징으로 하는 터널구조체Constructed by the method according to claim 13, the ground reinforcing grouting layer is formed on the upper part of the tunnel, and the upper transverse connecting steel plates 11 and 21 are disposed, and the upper transverse connecting steel plates 11 and 21 are formed inside the tunnel. An upper slab 3 forming an upper part is disposed, and the upper slab 3 is supported by the concrete supporting wall 7 formed with the concrete assembly wall 71 in a line and integrally formed with the foundation 6 and supported by the concrete. Tunnel structure, characterized in that the outer side of the wall (7) is embedded with vertically extending steel plate welded to the horizontally extending grid plate 청구항 15은(는) 설정등록료 납부시 포기되었습니다.Claim 15 was abandoned upon payment of a registration fee. 제9항에 있어서, 터널의 중앙 기둥역할을 수행하는 중간의 콘크리트지지벽 체(7)의 상부에 위치되는 압입된 양측의 상부 슬래브(3)가 만나는 부분에서 양측 상부 슬래브(3)를 고정수단(35)으로 묶어 일체화시킨 것을 특징으로 하는 터널구조체10. The fixing means according to claim 9, wherein both upper slabs (3) are secured at a portion where the indented upper slabs (3) located on the upper part of the intermediate concrete support wall (7) serving as the central pillar of the tunnel meet. Tunnel structure characterized in that the bundle is integrated with (35)
KR1020060089993A 2006-09-18 2006-09-18 None open cut tunnelling method and tunnel KR100834076B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020060089993A KR100834076B1 (en) 2006-09-18 2006-09-18 None open cut tunnelling method and tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020060089993A KR100834076B1 (en) 2006-09-18 2006-09-18 None open cut tunnelling method and tunnel

Publications (2)

Publication Number Publication Date
KR20080025478A KR20080025478A (en) 2008-03-21
KR100834076B1 true KR100834076B1 (en) 2008-06-04

Family

ID=39413281

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020060089993A KR100834076B1 (en) 2006-09-18 2006-09-18 None open cut tunnelling method and tunnel

Country Status (1)

Country Link
KR (1) KR100834076B1 (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101073523B1 (en) 2009-03-10 2011-10-17 (주)나우이앤씨 The tunel execution method and the using fabric
KR101142783B1 (en) 2010-12-03 2012-05-08 (주)나우이앤씨 A train railroad outline area tunnel extension work-method and that structure
KR101255517B1 (en) * 2010-07-14 2013-04-23 (주)고려씨엔씨 The tunel execution method and the using fabric
CN103244143A (en) * 2013-05-27 2013-08-14 中铁工程设计咨询集团有限公司 Underground engineering tunneling construction method and underground station

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101017295B1 (en) * 2008-12-19 2011-02-28 (주)미래기술단 Hybrid type safety structure for preventing falling rocks
KR101662096B1 (en) * 2015-02-25 2016-10-14 (주)나우기술 The Construction Method of Non-excavation tunnel what press in extruding Steel pipe by Arch type Precast Upperslab
CN108002288A (en) * 2017-12-10 2018-05-08 建研地基基础工程有限责任公司 A kind of horizontal directional drilling machine assembled hoistable platform for the construction of tunnel vertical duct curtain
CN113175329A (en) * 2021-05-24 2021-07-27 中建八局华南建设有限公司 Tunnel portal construction method for parallel pipe-jacking tunnel

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60144696U (en) 1984-03-06 1985-09-25 住友金属工業株式会社 Underpass using pipe beams
JPH04203200A (en) * 1990-11-30 1992-07-23 Okumura Corp Ground reinforcing method in deep depth
JPH0835391A (en) * 1994-07-22 1996-02-06 Ohbayashi Corp Preceding leg reinforcing type fore piling method by heading
KR970070352A (en) * 1996-04-03 1997-11-07 김기수 New construction method of underground structures under non-installation
KR20040098322A (en) * 2003-05-14 2004-11-20 김현경 None open cut tunnelling of arch type with hume pipe and con'c rib

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS60144696U (en) 1984-03-06 1985-09-25 住友金属工業株式会社 Underpass using pipe beams
JPH04203200A (en) * 1990-11-30 1992-07-23 Okumura Corp Ground reinforcing method in deep depth
JPH0835391A (en) * 1994-07-22 1996-02-06 Ohbayashi Corp Preceding leg reinforcing type fore piling method by heading
KR970070352A (en) * 1996-04-03 1997-11-07 김기수 New construction method of underground structures under non-installation
KR20040098322A (en) * 2003-05-14 2004-11-20 김현경 None open cut tunnelling of arch type with hume pipe and con'c rib

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101073523B1 (en) 2009-03-10 2011-10-17 (주)나우이앤씨 The tunel execution method and the using fabric
KR101255517B1 (en) * 2010-07-14 2013-04-23 (주)고려씨엔씨 The tunel execution method and the using fabric
KR101142783B1 (en) 2010-12-03 2012-05-08 (주)나우이앤씨 A train railroad outline area tunnel extension work-method and that structure
CN103244143A (en) * 2013-05-27 2013-08-14 中铁工程设计咨询集团有限公司 Underground engineering tunneling construction method and underground station

Also Published As

Publication number Publication date
KR20080025478A (en) 2008-03-21

Similar Documents

Publication Publication Date Title
KR101022382B1 (en) Precast horizontality tubular roof and tunnel construction method using the same
KR100834076B1 (en) None open cut tunnelling method and tunnel
US9322137B2 (en) Method for building structures, particularly passages under operating railways or the like
CN110042716B (en) Widening construction method for high-fill roadbed with foamed light soil
KR101090400B1 (en) Construction method of road for extending breadth of road on slope face
KR200415268Y1 (en) Tubular arch tunnel for underground tunnelling
WO2023213117A1 (en) Widening structure and construction method for existing subgrade embankment wall section near river
KR100538272B1 (en) The methods of trenchless underway construction using pre-cast assembly concrete box
KR20090114863A (en) Parallelly connected iron tube and construction method for underground structure using the same
JP4881555B2 (en) Construction method of underground structure
KR101206860B1 (en) Excavation tunnel constructing method using vertical side wall and arch ceiling
CN211922133U (en) Large cantilever structure suitable for widening old road of cliff road section
CN110230238B (en) Railway line protection device and protection method
KR100509707B1 (en) None open cut tunnelling of arch type with hume pipe and con'c rib
KR100784201B1 (en) Method for construction of tunnel
KR20210078779A (en) Underground roadway removed upper structure between upper slab and surface of road after constructing the steel continuous wall in the earth by top-down method and method for constructing the same
CN206721920U (en) Assembly type pipe gallery
CN112983493B (en) Reinforcing structure for shield to closely penetrate large-section bridge and culvert downwards and construction method
CN215906845U (en) Large-span vestibule mounting structure in foundation pit
KR100605495B1 (en) Trenchless method of underground passage and structure thereof
CN210561510U (en) Railway line protection device
KR101255517B1 (en) The tunel execution method and the using fabric
CN212247676U (en) Structure is rebuild to existing railway roadbed underground drainage system
CN210163739U (en) Town road constructed based on prestressed concrete sheet piles
KR102105229B1 (en) Temporary facility construction method for underground construction fo railroad track lower pass

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20110525

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee