JP5209546B2 - Construction method of the structure under the track - Google Patents

Construction method of the structure under the track Download PDF

Info

Publication number
JP5209546B2
JP5209546B2 JP2009056105A JP2009056105A JP5209546B2 JP 5209546 B2 JP5209546 B2 JP 5209546B2 JP 2009056105 A JP2009056105 A JP 2009056105A JP 2009056105 A JP2009056105 A JP 2009056105A JP 5209546 B2 JP5209546 B2 JP 5209546B2
Authority
JP
Japan
Prior art keywords
construction
girder
track
side wall
construction girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2009056105A
Other languages
Japanese (ja)
Other versions
JP2010209570A (en
Inventor
忠良 石橋
智明 森山
秀之 小泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
East Japan Railway Co
Original Assignee
East Japan Railway Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East Japan Railway Co filed Critical East Japan Railway Co
Priority to JP2009056105A priority Critical patent/JP5209546B2/en
Publication of JP2010209570A publication Critical patent/JP2010209570A/en
Application granted granted Critical
Publication of JP5209546B2 publication Critical patent/JP5209546B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

本発明は線路下の地盤中に構造物を構築する方法に関する。   The present invention relates to a method for constructing a structure in the ground under a track.

従来、鉄道線路下の地盤中に構造物を構築する方法として、工事桁による開削工法、鋼製エレメントを地中に挿入して本体構造物とする非開削工法が知られている。
図3は工事桁による開削工法を説明する図で、図3(a)は断面図、図3(b)は平面図である。
この工法は、軌道(レール)1を受ける工事桁2を、軌道に沿って施工した複数の杭10で受けた後、H型鋼等からなる土留杭13を多数施工することで土留壁を形成し、土留壁で囲んだ中の地盤3を掘削し、開削した領域に構造物5を構築するものである。この例では、構造物5内に歩道と車道とが形成されている。なお、図中、11は工事桁2と杭10との間に介在させるゴムシュー等からなる支点である。
Conventionally, as a method for constructing a structure in the ground below a railway track, an open-cut method using a construction girder and a non-open-cut method using a steel element inserted into the ground to form a main body structure are known.
FIGS. 3A and 3B are diagrams for explaining an excavation method using a construction girder. FIG. 3A is a cross-sectional view and FIG. 3B is a plan view.
This construction method forms a retaining wall by receiving a construction girder 2 that receives a track (rail) 1 by a plurality of piles 10 constructed along the track, and then constructing a large number of retaining piles 13 made of H-shaped steel or the like. The structure 5 is constructed in the excavated area by excavating the ground 3 surrounded by the retaining wall. In this example, a sidewalk and a roadway are formed in the structure 5. In the figure, reference numeral 11 denotes a fulcrum made of a rubber shoe or the like interposed between the construction beam 2 and the pile 10.

図4は鋼製エレメントを地中に挿入して本体構造物とする非開削工法を説明する図であり、このような工法については、例えば、下記特許文献に開示されている。
図示は省略するが、発進立坑、到達立坑を掘削してそれぞれ土留工を施工した後、レール1の下方の地盤3の中に鋼製エレメント7を内部の土砂を掘削排土しながら発進立坑側から到達立坑側へ向けて順次挿入する。エレメント同士は継手で連結され、既設のエレメントの継手をガイドとして隣接するエレメントを順次挿入してエレメント内、エレメント間にコンクリートを打設し、エレメントで囲んだ領域を掘削する。こうして、鋼製エレメントを本体構造物とした地下構造物5が形成される。この例では、構造物5内に歩道と車道とが形成されている。なお、図中、9は軌道1を構成しているバラストである。
FIG. 4 is a diagram for explaining a non-open cutting method in which a steel element is inserted into the ground to form a main body structure. Such a method is disclosed in, for example, the following patent documents.
Although illustration is omitted, after excavating the start shaft and the reaching shaft and constructing the earth retaining work, respectively, the start vertical shaft side while excavating and discharging the steel element 7 in the ground 3 below the rail 1 and excavating the soil inside Are inserted sequentially from the top to the end of the shaft. The elements are connected by a joint, and adjacent elements are sequentially inserted using a joint of the existing elements as a guide, and concrete is placed in and between the elements, and a region surrounded by the elements is excavated. Thus, the underground structure 5 having the steel element as the main body structure is formed. In this example, a sidewalk and a roadway are formed in the structure 5. In the figure, 9 is a ballast constituting the track 1.

特開2005−282115号公報   JP 2005-282115 A

しかしながら、上記した工事桁による開削工法、鋼製エレメントを地中に挿入して本体構造物とする非開削工法では、施工が夜間の線路閉鎖間合いに制限される工種が多いため、工期が長期化し、結果的に工費がかかってしまうという問題があった。例えば、工事桁による開削工法では、工事桁を受ける杭や土留杭を施工するなど夜間の線路閉鎖時間内に行う作業が多く、また、鋼製エレメントを地中に挿入する工法では、少なくとも上床板エレメントの施工は夜間の線路閉鎖時間内に行わなければならず、いずれの工法でも工期を短縮するのは困難であった。   However, in the above-mentioned open-cut method using construction girders and the non-open-cut method in which steel elements are inserted into the ground to make the main body structure, the work period is prolonged because there are many work types that are limited to the time when the track is closed at night. As a result, there was a problem that the construction cost was increased. For example, in the excavation method using construction girders, there are many operations that are performed during the night time when the track is closed, such as constructing piles that receive construction girders or retaining piles. The construction of the elements had to be done within the night time when the track was closed, and it was difficult to shorten the construction period by either method.

本発明は上記課題を解決しようとするものであり、線路下横断構造物の作業時間を要している工種、施工順序等を見直すことにより、安全性、及び施工性を向上させ、線路下横断工法の工期短縮を図ることを目的とする。
本発明の線路下構造物の構築方法は、軌道を受ける工事桁を施工する段階、
工事桁下方の軌道下地盤中に側壁部エレメントを挿入し、コンクリートを打設して施工した左右側壁部で工事桁を受け換える段階、
工事桁下方の左右側壁部間を掘削し、上床版、下床版を施工する段階を有することを特徴とする。
また、本発明は、工事桁が短スパンの工事桁からなり、工事桁を接続して連続化するとともに各短スパンの工事桁を左右側壁部でそれぞれ受けかえることを特徴とする。
また、本発明は、工事桁が長スパンであり、左右側壁部で工事桁を受けるとともに、左右側壁部間に工事桁杭を施工して工事桁を受けることを特徴とする。
The present invention is intended to solve the above-mentioned problems, and by reviewing the work type and construction sequence that require work time of the crossing structure under the track, safety and workability are improved, and the crossing under the track is performed. The purpose is to shorten the construction period.
The construction method of the under-track structure of the present invention is a step of constructing a construction girder that receives a track,
Inserting the side wall element into the track base plate below the work girder and replacing the work girder at the left and right side wall parts constructed by placing concrete,
It is characterized by excavating between the left and right side walls below the construction girder and constructing an upper floor slab and a lower floor slab.
Further, the present invention is characterized in that the construction girders are short span construction girders, and the construction girders are connected and made continuous, and the short span construction girders are respectively received by the left and right side wall portions.
Further, the present invention is characterized in that the construction girder has a long span, receives the construction girder at the left and right side walls, and constructs the construction girder pile between the left and right side walls to receive the construction girder.

本発明は、側壁部エレメントを挿入してコンクリートを打設し、施工した左右側壁部で工事桁を受け換えた後、工事桁の下方、左右側壁部内を掘削して上床版、下床版を施工することで、支持杭の施工、土留杭の施工をせず、営業時間内の工種を増やすことができ、工期の短縮を図ることができる。   The present invention inserts a side wall element and casts concrete, and after exchanging the construction girder at the constructed left and right side wall parts, excavating the inside of the left and right side wall parts below the construction girder, By constructing, it is possible to increase the types of work within business hours without shortening the work period without constructing support piles and retaining piles.

鋼製エレメントを用いる本実施形態の施工方法を説明する図である。It is a figure explaining the construction method of this embodiment using a steel element. 本実施形態の他の例を説明する図である。It is a figure explaining the other example of this embodiment. 工事桁による開削工法を説明する図である。It is a figure explaining the excavation method by a construction girder. 非開削工法を説明する図である。It is a figure explaining a non-cutting method.

以下、本発明の実施の形態について説明する。
図1は鋼製エレメントを用いる本実施形態の施工方法を説明する図である。
図示は省略するが、現場の状況によっては、発進立坑、到達立坑を掘削してそれぞれ土留工を施工する。図1(a)に示すように、地下構造物の施工場所30の地盤上に直接、或いは簡易な支持材(図示せず)を設けて短スパンの工事桁21、22を施工し、軌道1を防護する。23は短スパン工事桁21、22の対向箇所を示している。次いで、発進立坑側から到達立坑側へ向けて軌道下地盤中に左右の側壁部を構成するための鋼製エレメント31、31を挿入し(図1(b))、コンクリートを充填して鋼製エレメントからなる側壁部33を構築する(図1(c))。このとき、短スパンの工事桁21、22は鋼製エレメントからなる左右側壁上部の路盤上に設置されていて、工事桁と左右側壁部との間にゴムシュー等からなり、高さ調整のためにコンクリートを打設したり、鋼材を挟んだりした支承部34を挿入して、左右側壁部33により工事桁を受け換える。工事桁21、22は左右側壁部により支持されるため、それらの対向箇所23において添接板等で接続して連続化し、工事桁20とする。次いで、工事桁下方を1次掘削して上床版コンクリート35を施工し(図1(d))、さらに、2次掘削して下床版コンクリート37を施工する(図1(e))。上床版、下床版を施工した後、工事桁を撤去して地下構造物が構築される(図1(f))が、工事桁は本設工事桁として残置してもよい。なお、上記においては、1次掘削して上床版を施工した後、2次掘削して下床版の施工を行うようにしたが、下床版位置まで一度に掘削して下床版、上床版を施工するようにしてもよい。また、工事桁は短スパンのものを2つ使用したが、左右側壁の間隔が大きい場合には3つ以上使用してもよく、また、状況によっては単一の連続スパンのものを使用するようにしてもよい。
Embodiments of the present invention will be described below.
FIG. 1 is a diagram for explaining a construction method according to this embodiment using a steel element.
Although illustration is omitted, depending on the situation at the site, excavation shafts and reaching shafts are excavated and earth retaining works are respectively constructed. As shown in FIG. 1 (a), the short span construction girders 21 and 22 are constructed directly on the ground of the construction site 30 of the underground structure or by providing a simple support material (not shown), and the track 1 Protect. Reference numeral 23 denotes an opposite portion of the short span construction girders 21 and 22. Next, steel elements 31 and 31 for configuring the left and right side walls are inserted into the track base plate from the starting shaft side to the reaching shaft side (FIG. 1 (b)) and filled with concrete to make steel. A side wall 33 made of elements is constructed (FIG. 1 (c)). At this time, the short span construction girders 21 and 22 are installed on the roadbed at the upper part of the left and right side walls made of steel elements, and are composed of rubber shoes or the like between the construction girders and the left and right side wall parts for height adjustment. A support part 34 in which concrete is placed or a steel material is sandwiched is inserted, and the construction girder is exchanged by the left and right side wall parts 33. Since the construction girders 21 and 22 are supported by the left and right side wall portions, the construction girders 20 are connected by connecting them with an attachment plate or the like at the facing portions 23 to form the construction girders 20. Next, the upper floor slab concrete 35 is constructed by first excavating the lower part of the work girder (FIG. 1 (d)), and further, the lower floor slab concrete 37 is constructed by performing the second excavation (FIG. 1 (e)). After the upper floor slab and the lower floor slab are constructed, the construction girder is removed to construct the underground structure (FIG. 1 (f)), but the construction girder may be left as the main construction girder. In the above, the first excavation and the upper floor slab were constructed, and then the second excavation was performed to construct the lower floor slab. A plate may be constructed. Also, two construction girders with short spans were used, but three or more may be used if the distance between the left and right side walls is large, and depending on the situation, one with a single continuous span may be used. It may be.

本実施形態では、工事桁の設置は線路閉鎖時に行う必要があるが、側壁部の施工は営業運転中でも可能であり、先ず、側壁部を施工して工事桁を支持するとともに、側壁部を土留壁として内部を掘削して上床版、下床版を施工できるため、工事桁杭、土留杭などの施工が必要なくなり、ほとんどの工事を営業運転中に行うことが可能となって工期の短縮を図ることができる。   In this embodiment, it is necessary to install the construction girder when the track is closed. However, the side wall can be installed even during commercial operation. First, the side wall is constructed to support the construction girder, and the side wall is fixed to the earth retaining wall. Since the upper floor slab and lower floor slab can be constructed by excavating the interior as a wall, it is no longer necessary to perform construction girder piles, retaining piles, etc., and most work can be done during commercial operation, shortening the construction period Can be planned.

図2は本実施形態の他の例を説明する図で、地下構造物のスパンが長く、地盤が良い(支持層が浅い)場合に適用する工法を説明する図である。
図示は省略するが、現場の状況によっては、発進立坑、到達立坑を掘削してそれぞれ土留工を施工するのは同じである。図2(a)に示すように、スパンの長い地下構造物の施工場所30の地盤上に直接、或いは簡易な支持材(図示せず)を設けて長い工事桁20を施工し、軌道1を防護する。次いで、発進立坑側から到達立坑側へ向けて左右の側壁部を構成するための鋼製エレメントを軌道下の地盤中に挿入してコンクリートを充填し、左右側壁部40を施工する。次いで、工事桁と左右側壁部40との間にゴムシュー等からなり、高さ調整のためにコンクリートを打設したり、鋼材を挟んだりした支承部41を挿入して、側壁部を支承として工事桁を受け換えるとともに、左右側壁部の中間位置に、工事桁を受ける杭43を施工する(図2(b))。次いで、工事桁下方を1次掘削し、上床版コンクリート45を施工し(図1(c))、さらに、2次掘削して下床版コンクリート47を施工する(図1(d))。上床版、下床版を施工した後、工事桁、支持杭を撤去して地下構造物が構築される(図2(e))が、工事桁は本設工事桁として残置してもよい。また、上記においては、1次掘削して上床版を施工した後、2次掘削して下床版の施工を行うようにしたが、下床版位置まで一度に掘削して下床版コンクリート、上床版コンクリートを施工するようにしてもよい。
FIG. 2 is a diagram for explaining another example of the present embodiment, and is a diagram for explaining a construction method applied when the span of the underground structure is long and the ground is good (the support layer is shallow).
Although illustration is omitted, depending on the situation at the site, excavation of the start shaft and the reaching shaft and construction of the earth retaining works are the same. As shown in FIG. 2A, a long construction girder 20 is constructed directly on the ground of the construction site 30 of a long span underground structure or by providing a simple support material (not shown), and the track 1 is Protect. Next, steel elements for configuring the left and right side wall portions from the starting shaft side to the reaching shaft side are inserted into the ground under the track and filled with concrete, and the left and right side wall portions 40 are constructed. Next, it is made of rubber shoes between the work girder and the left and right side wall parts 40, and a concrete part is placed for height adjustment or a support part 41 with steel material sandwiched is inserted, and the side wall part is used as a support. While changing a girder, the pile 43 which receives a construction girder is constructed in the intermediate position of a right-and-left side wall part (FIG.2 (b)). Next, the lower excavation girder is primarily excavated and upper floor slab concrete 45 is constructed (FIG. 1 (c)), and further, the lower excavation concrete 47 is constructed (FIG. 1 (d)). After the upper floor slab and the lower floor slab are constructed, the construction girders and support piles are removed to construct the underground structure (FIG. 2 (e)), but the construction girders may be left as permanent construction girders. Also, in the above, after the first excavation and the upper floor slab was constructed, the second excavation was performed to construct the lower floor slab. You may make it construct upper floor slab concrete.

本実施形態においても、側壁部の施工は営業運転中でも可能であり、先ず、側壁部を施工して工事桁を支持するとともに、側壁部間に工事桁杭を施工し、側壁部を土留壁として内部を掘削して上床版、下床版を施工できるため、土留杭などの施工が必要なくなり、ほとんどの工事を営業運転中に行うことが可能となって工期の短縮を図ることができる。   Also in this embodiment, the construction of the side wall part is possible even during commercial operation. First, the side wall part is constructed to support the construction girder, the construction girder pile is constructed between the side wall parts, and the side wall part is used as a retaining wall. Since the upper floor slab and lower floor slab can be constructed by excavating the interior, it is not necessary to construct earth retaining piles, etc., and it is possible to carry out most of the construction during commercial operation, thereby shortening the construction period.

本発明は、支持杭の施工、土留杭の施工をせず、営業時間内の工種を増やすことができるので、工期を短縮し、安全性、施工性を向上させた線路下横断工法に利用することができる。   Since the present invention can increase the types of work within business hours without constructing support piles and retaining piles, it can be used for under-track crossing methods that shorten the construction period and improve safety and workability. be able to.

1…軌道、3…地盤、20,21,22…工事桁、33,40…側壁部、35,45…上床版、37,47…下床版。 DESCRIPTION OF SYMBOLS 1 ... Track, 3 ... Ground, 20, 21, 22 ... Construction girder, 33, 40 ... Side wall part, 35, 45 ... Upper floor slab, 37, 47 ... Lower floor slab.

Claims (3)

軌道を受ける工事桁を施工する段階、
工事桁下方の軌道下地盤中に側壁部エレメントを挿入し、コンクリートを打設して施工した左右側壁部で工事桁を受け換える段階、
工事桁下方の左右側壁部間を掘削し、上床版、下床版を施工する段階、
を有する線路下構造物の構築方法。
The stage to construct the construction girder that receives the track,
Inserting the side wall element into the track base plate below the work girder and replacing the work girder at the left and right side wall parts constructed by placing concrete,
Drilling between the left and right side walls below the construction girder and constructing the upper and lower floor slabs,
The construction method of the structure under the track having
前記工事桁が短スパンの工事桁からなり、工事桁を接続して連続化するとともに各短スパンの工事桁を左右側壁部でそれぞれ受けかえることを特徴とする請求項1記載の線路下構造物の構築方法2. The under-track structure according to claim 1, wherein the construction girder is composed of a short-span construction girder, and the construction girder is connected and continuous, and each short-span construction girder is received by the left and right side walls . How to build . 前記工事桁が長スパンであり、左右側壁部で工事桁を受けるとともに、左右側壁部間に工事桁杭を施工して工事桁を受けることを特徴とする請求項1記載の線路下構造物の構築方法。
2. The under-track structure according to claim 1, wherein the construction girder has a long span, receives the construction girder at the left and right side wall portions, and constructs the construction girder pile between the left and right side wall portions to receive the construction girder. Construction method.
JP2009056105A 2009-03-10 2009-03-10 Construction method of the structure under the track Expired - Fee Related JP5209546B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2009056105A JP5209546B2 (en) 2009-03-10 2009-03-10 Construction method of the structure under the track

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2009056105A JP5209546B2 (en) 2009-03-10 2009-03-10 Construction method of the structure under the track

Publications (2)

Publication Number Publication Date
JP2010209570A JP2010209570A (en) 2010-09-24
JP5209546B2 true JP5209546B2 (en) 2013-06-12

Family

ID=42970008

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2009056105A Expired - Fee Related JP5209546B2 (en) 2009-03-10 2009-03-10 Construction method of the structure under the track

Country Status (1)

Country Link
JP (1) JP5209546B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101847356B1 (en) 2017-11-14 2018-04-09 티알이엔씨(주) Half excavation cross roadway construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3396051B2 (en) * 1993-03-11 2003-04-14 東日本旅客鉄道株式会社 Simple girder guard girder device
JP2971835B2 (en) * 1997-06-30 1999-11-08 東日本旅客鉄道株式会社 Tunnel construction method
JP4148607B2 (en) * 1999-09-03 2008-09-10 東日本旅客鉄道株式会社 Construction method of underground structure using floor girder for construction girder

Also Published As

Publication number Publication date
JP2010209570A (en) 2010-09-24

Similar Documents

Publication Publication Date Title
KR101344063B1 (en) The construction method of steel-concrete underpass
KR101111594B1 (en) Method for constructing underground structure
KR101710075B1 (en) PC Method for constructing underground structure having Precast wall using Hpile and underground structure constructed by the same
KR20110132910A (en) Underpass using precast concrete pile and bottom slab and method for constructing the same
JP6186267B2 (en) How to build an underground tunnel
JP6543176B2 (en) Building method
CN202298633U (en) Arch root pile isolation piling wall
JP4881555B2 (en) Construction method of underground structure
JP6177468B1 (en) Installation or replacement of tunnel inverts in service
KR101293550B1 (en) Construction method of underground structure
JP4406577B2 (en) Digging road
JP3893056B2 (en) Construction method of underground structure
JP5209546B2 (en) Construction method of the structure under the track
JP5915074B2 (en) How to form an underground space under a ground transportation
KR101651495B1 (en) Constructing Method of Non-Bridge Seat Bridge
JP5192422B2 (en) Support pile construction method for construction of crossing structure under track
JP4226954B2 (en) Underpinning method and viaduct
JP4865300B2 (en) Semi-underground road construction method
KR20170010881A (en) Method for connecting precast wall and slab, and underground structure constructed by the same
JP2006249735A (en) Construction method of crossing underground structure and crossing underground structure
JP4926092B2 (en) How to build a box structure
KR101237492B1 (en) Method for constructing substructure of railroad using auger and lifting apparatus
KR101234091B1 (en) Method of underground railway crossing over direct installation of precast concrete slab
JP3380301B2 (en) Viaduct construction method
KR101710716B1 (en) Underground structure having Precast wall using H­pile

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20120104

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20121226

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20130111

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20130117

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20130215

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20130221

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20160301

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

Ref document number: 5209546

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees