SU981495A1 - Road passage through embankment of acting railway and method of constructing same - Google Patents
Road passage through embankment of acting railway and method of constructing same Download PDFInfo
- Publication number
- SU981495A1 SU981495A1 SU813260517A SU3260517A SU981495A1 SU 981495 A1 SU981495 A1 SU 981495A1 SU 813260517 A SU813260517 A SU 813260517A SU 3260517 A SU3260517 A SU 3260517A SU 981495 A1 SU981495 A1 SU 981495A1
- Authority
- SU
- USSR - Soviet Union
- Prior art keywords
- overpass
- extreme
- embankment
- superstructure
- track
- Prior art date
Links
Landscapes
- Bridges Or Land Bridges (AREA)
Description
Изобретение относится к мостостроению и может быть использовано при возведении путепроводов в насыпях железнодорожного полотна из трех путей и более.The invention relates to bridge construction and can be used in the construction of viaducts in embankments of a railway bed of three tracks or more.
Известен путепровод в насыпи существ- 5 вующего железнодорожного полотна, выполненный в виде монолитной Железобетонной замкнутой рамы, и способ его сооружения, включающий устройство в пере— рывах движения поездов фундаментов и пролетного строения временного моста, разработку под его прикрытием котлована с откосами, разработку в нижней части котлована по оси путепровода траншеи 15 с установкой забивных креплений, бетонирование в траншее плиты, служащую основанием для устройства пути надвижки, бетонирование в проектном уровне на плите рамы путепровода со съемными ноже- го выми стенками, устройство на другом конце плиты консоли, упоры для тяговых домкратов, установку домкратов с тягами, перемещение рамы по двум металлическим путям скольжения, расположенным на бетонном основании; продавливание рамы' путепровода в оставшуюся часть насыпи с удалением грунта, разборку временного моста [ 1 ] .Known overpass in the embankment of the existing 5 railroad tracks, made in the form of a monolithic reinforced concrete closed frame, and the method of its construction, including the device during interruptions in the movement of foundations trains and the span structure of the temporary bridge, development of a foundation pit with slopes under its cover, development in the lower part of the guideway axis excavation of the trench 15 with the installation of driven fasteners, concrete slab in the trench, serving as a base for the device sliding path, concreting in the project at the plate level p we guideway removable nozhe- Vym of walls, the device at the other end of the cantilever plate stops for traction jacks, jacks with installation rods, frames for moving the two sliding metallic paths arranged on a concrete base; punching the frame 'overpass into the remaining part of the embankment with soil removal, disassembling the temporary bridge [1].
Недостаток этого путепровода и способа его сооружения заключается в возможности перекрытия им относительно небольшого отверстия, а также в значив· тельной трудоемкости его монтажа, обусловленной необходимостью бетонирования рамы путепровода на месте, устройством временного моста с послед у юшей его разработкой, укладкой основания и пути скольжения рамы путепровода.The disadvantage of this overpass and the method of its construction is the possibility of blocking it with a relatively small hole, as well as the considerable complexity of its installation, due to the need to concrete the frame of the overpass in place, the construction of a temporary bridge with its subsequent development, laying the base and sliding path of the frame overpasses.
Наиболее близким к предлагаемому является путепровод в насыпи существующего железнодорожного полотна, включающий столбчатые опоры, насадки и установленные на них балки пролетного строения с верхним строением пути, причем верхнее строение пути содержит поперечно члененную на блоки плиту проезда, уложенную на балки пролетного строения, ,981495 4 и предназначено для однопутного дви— действующего верхнего строения пути в жения [21.Closest to the proposed one is an overpass in the embankment of the existing railway bed, including columnar supports, nozzles and beams installed on them with a superstructure with the upper track structure, the upper track structure containing a passage plate transverse to the blocks laid on the superstructure beams, 981495 4 and it is intended for a single-track moving superstructure of the pathway [21.
Известен также способ сооружения описанного путепровода в насыпи существующего железнодорожного полотна, вклю- 5 чающий удаление верхнего строения пути в зоне расположения путепровода, возведение в грунте насыпи столбчатых опор с насадками, установку на них балок пролетных строений с верхним строением ю пути и выемку грунта насыпи под путепровод, причем после устройства насадок на них устанавливают временный мост, под его защитой производят частичную выемку грунта, в перерывах движения производят разработку временного моста, устанавливают на балки пролетного строения блоки плиты с верхним строением пути, после чего производят окончательную выемку грунта насыпи и укрепление 20 головной части насыпи сборными железобетонными стенками [2) .There is also known a method of constructing the described overpass in the embankment of an existing railway track, including 5 removing the upper track structure in the zone of the overpass location, erecting columnar supports with nozzles in the soil, installing beams of spans with the upper track structure and excavating the embankment underneath overpass, and after installing the nozzles, a temporary bridge is installed on them, under its protection a partial excavation is carried out, during breaks of traffic, a temporary bridge is developed, vayut beam on the span plate blocks the upper path structure, whereupon final excavation and embankment head portion 20 strengthening embankments precast concrete walls [2).
Недостаток известного путепровода и способа его сооружения заключается в повышенной трудоемкости его монтажа, обу— 25 словленной необходимостью установки большого количества блоков плиты верхнего строения пути на балки пролетного строения, а также в существенном снижении эффективности эксплуатации железной эд дороги при сооружении путепровода вследствие необходимости устройства временного моста и блоков плиты верхнего строения пути за счет организации перерывов в движении поездов. w A disadvantage of the known overpass and the method of its construction is the increased complexity of its installation, due to the need to install a large number of blocks of the plate of the upper track structure on the beams of the superstructure, as well as to a significant decrease in the efficiency of operation of the railway ed during the construction of the overpass due to the need for a temporary bridge and blocks of the plate of the top structure of the track due to the organization of breaks in the movement of trains. w
Цель изобретения - снижение трудоемкости монтажа при сооружении путепровода в насыпи существующего железно* дорожного полотна с по меньшей мере трехпутным верхним строением пути, а также повышение эффективности эксплуатации железной дороги при сооружении путепровода.The purpose of the invention is to reduce the complexity of installation during the construction of the overpass in the embankment of the existing railway * track with at least a three-track upper track structure, as well as increasing the efficiency of the operation of the railway during the construction of the overpass.
Указанная цель достигается тем, что в путепроводе в насыпи существующего железнодорожного полотна, включающем столбчатые опоры, насадки и установленные на них балки пролетного строения о верхним строением пути, насадка каждой из опор выполнена составной по длинеί .по ^крайней мере из двух крайних и 50 одной средней секций, причем крайние секции укреплены на соответствующих столбах одоры и выполнены по торцам с выступами и оперта ими в выемки крайних секций. S5This goal is achieved by the fact that in the overpass in the embankment of the existing railway bed, including columnar supports, nozzles and beams of superstructure installed on them about the upper structure of the track, the nozzle of each of the supports is made integral in length ί at least two extreme and 50 one middle sections, and the extreme sections are mounted on the corresponding poles of the odes and are made at the ends with protrusions and supported by them in the recesses of the extreme sections. S5
При этом в способе сооружения путепровода в насыпи существующего железно-1 дорожного полотна, включающем удаление зоне расположения путепроводов, возведение в грунте насыпи столбчатых опор с насадками, установку на них балок пролетного строения с верхним строением пути и выемку грунта насыпи под путепровод, удаление действующего верхнего строения пути производят .по одному из крайних путей после '-чеуо в створе этого ' пути осуществляют выемку верхнего слоя грунта насыпи, возведение симметрично относительно поперечной оси путепровода столбчатых опор с одними крайними секциями насадок и установку на эти крайние секции балок пролетного строения с верхним строением пути, затем производят ί повторение этих операций по другому крайнему пути, после чего удаляют действующее верхнее строение -пути, по среднему пути и в створе этого пути производят выемку грунта на всю высоту насыпи, монтаж симметрично относительно поперечной оси путепровода средних секций насадок с опиранием их выступами на выемки крайних секций насадок и установку остальных балок пролетного строения на средние секции насадок опор с последующей выемкой грунта оставшейся части насыпи под крайними путями.Moreover, in the method of constructing an overpass in the embankment of the existing railroad track 1 , including removing the overpass location zone, erecting columnar supports with nozzles in the embankment, installing beams of the superstructure with the upper track structure, and excavating the embankment under the overpass, removing the existing upper the structure of the track is produced. along one of the extreme tracks after the '-cheuo in the alignment of this' track, excavation of the top layer of the soil of the embankment is carried out, the construction is symmetrical about the transverse axis of the overpass crushed supports with one extreme sections of nozzles and installation on these extreme sections of beams of the superstructure with the upper structure of the track, then repeat these operations along the other extreme track, after which the existing upper structure is removed — the track, along the middle track and in the alignment of this track excavation of the entire height of the embankment, installation symmetrically relative to the transverse axis of the overpass of the middle sections of the nozzles with their protrusions resting on the recesses of the extreme sections of the nozzles and installing the remaining beams of the span on dnie section supports nozzles followed by dredging the remainder of the mound under extreme ways.
На фиг. 1 изображен вид одного из торцов путепровода, сооруженного в насыпи железнодорожного полотна из трех путей} на фиг. 2 - конструкция насадки, вид сверху; на фиг. 3 - сооружение путепровода ца одном из крайних путей, (левом)} на фиг. 4 - то же, на другом крайнем пути, (правом); на фиг. 5 - то же, на среднем пути; на фиг. 6 - один из концов сооружаемого путепровода, вид сбоку.In FIG. 1 shows a view of one of the ends of an overpass constructed in an embankment of a railway track of three tracks} in FIG. 2 - nozzle design, top view; in FIG. 3 - construction of an overpass to one of the extreme ways, (left)} in FIG. 4 - the same, on the other extreme path, (right); in FIG. 5 - the same, on the middle path; in FIG. 6 - one of the ends of the constructed overpass, side view.
Путепровод в насыпи 1 существующего железнодорожного полотна включает столбчатые опора,: 2, составные по длине по крайней мере из двух крайних 3, 4 и одной средней 5 секции насадки и установленные на них балки 6 пролетного строения с верхним строением пути 7, причем крайние секции 3 и 4 каждой насадки укреплены на соответствующих столбах опоры 2 и выполнены по торцам с выемками 8, а средняя секция 5 насадки выполнена по торцам с выступами 9 и оперта ими в выемки 9 крайних секций насадки.The overpass in the embankment 1 of the existing railroad track includes columnar bearings: 2, composite in length of at least two extreme 3, 4 and one middle 5 sections of the nozzle and beams 6 of the superstructure with the upper track 7 installed on them, the outer sections 3 and 4 of each nozzle are mounted on the corresponding columns of the support 2 and are made at the ends with recesses 8, and the middle section 5 of the nozzle is made at the ends with projections 9 and they are supported in the recesses 9 of the extreme sections of the nozzle.
Способ сооружения описанного путепровода включает следующие основные операции: удаление действующего-верхнего строения пути 10 и 11, соответственно, на крайних и среднем путях в зоне расположения путепровода, возведение в грунте насыпи 1 столбчатых опор 2 с использованием обсадных труб 12, погружаемых с помощью монтажных обустройств 13, располагаемых со стороны - j поля путепровода, установку секций 3, 4 и 5 насадок и балок 6 пролетного .. строения пути 7, выемку грунта насыпи 1 под путепровод.The method of construction of the described overpass includes the following basic operations: removal of the existing-upper structure of the track 10 and 11, respectively, on the extreme and middle tracks in the zone of the overpass location, erection in the soil of the embankment 1 of columnar supports 2 using casing 12, immersed using mounting devices 13, located on the side - j fields of the overpass, installation of sections 3, 4 and 5 of nozzles and beams 6 of the span .. track structure 7, excavation of embankment 1 under the overpass.
При этом удаление действующего верхл.»® него строения пути 10 производят по одному из крайних путей с перекрытием движения по нему, после чего в створе этого пути осуществляют выемку верхнего слоя грунта насыпи 1, возведение сим*|$ метрично относительно поперечной оси путепровода столбчатых опор 2 с одними крайними 3 (4) секциями насадок и установку на эти крайние секции балок 6 пролетного строения с верхним строени- jQ ем пути 7 с открытием движения по этому пути. Затем перекрывают движение по другому крайнему пути и производят повторение указанных операций с открытием движения по этому крайнему пути.In this case, the removal of the existing upper. ”® structure of the path 10 is carried out along one of the extreme paths with the movement blocked along it, after which, in the alignment of this path, the upper soil layer of embankment 1 is excavated, the construction is symmetric | | $ metric with respect to the transverse axis of the column support overpass 2 with one extreme 3 (4) nozzle sections and installation on these extreme sections of beams 6 of the span with the upper structure jQ of track 7 with the opening of movement along this path. Then they block the movement along the other extreme path and repeat these operations with the opening of the movement along this extreme path.
После этого перекрывают движение по среднему пути, удаляют действующее верхнее строение пути 11 и в створе этого пути производят выемку грунта на всю высоту насыпи, монтаж симметрично χ относительно поперечной оси путепровода средних секций 5 насадок с опиранием их выступами 9 на выемки 8 крайних секций 3 и 4 насадок и установку остальных балок 6 пролетного строения на сред-jj ние секции 5 насадок опор с последующей выемкой грунта оставшейся части насыпи ' под крайними путями.After this, the movement is blocked along the middle path, the existing upper structure of track 11 is removed and, in the alignment of this path, excavation is carried out to the entire height of the embankment, installation is symmetrical χ relative to the transverse axis of the overpass of the middle sections 5 nozzles with their protrusions 9 resting on the recesses 8 of the extreme sections 3 and 4 nozzles and installation of the remaining beams of the 6 span on the middle section of the 5 nozzles of supports with subsequent excavation of the remaining part of the embankment 'under extreme paths.
Использование предлагаемого путепровода, сооружаемого описанным способом, обеспечивает снижение трудоемкости монтажа при сооружении путепровода в насыпи существующего железнодорожного полотна с по меньшей мере трехпутным верхним строением пути и повысит эффектив— ность эксплуатации железной дороги при сооружении путепроводов.The use of the proposed overpass constructed in the described way reduces the complexity of installation during the construction of the overpass in the embankment of the existing railway track with at least a three-track upper track structure and will increase the efficiency of railway operation during the construction of overpasses.
Claims (2)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813260517A SU981495A1 (en) | 1981-03-13 | 1981-03-13 | Road passage through embankment of acting railway and method of constructing same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
SU813260517A SU981495A1 (en) | 1981-03-13 | 1981-03-13 | Road passage through embankment of acting railway and method of constructing same |
Publications (1)
Publication Number | Publication Date |
---|---|
SU981495A1 true SU981495A1 (en) | 1982-12-15 |
Family
ID=20947709
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
SU813260517A SU981495A1 (en) | 1981-03-13 | 1981-03-13 | Road passage through embankment of acting railway and method of constructing same |
Country Status (1)
Country | Link |
---|---|
SU (1) | SU981495A1 (en) |
-
1981
- 1981-03-13 SU SU813260517A patent/SU981495A1/en active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US4301565A (en) | Method and system for the removal and replacement of a bridge | |
CA1037270A (en) | Precast ribbed arch subway structure and method | |
KR100571525B1 (en) | Expansion method of a bridge using concrete structure | |
CN112323627A (en) | Frame type construction system and construction method in existing railway temporary bridge construction | |
SU981495A1 (en) | Road passage through embankment of acting railway and method of constructing same | |
US6795992B2 (en) | Bridge construction method | |
US8347441B2 (en) | Load bearing construction and method for installation | |
JP2000008304A (en) | Pedestal for rail road work beam and execution method of pedestal for rail road work beam | |
JP4263935B2 (en) | Construction method and elevated detour | |
JP2971835B2 (en) | Tunnel construction method | |
CN212375729U (en) | Frame type construction system in existing railway temporary bridge construction | |
US3833960A (en) | Process for the construction of underpasses and an abutment for use therein | |
CN114382011B (en) | Beam-free construction method of bridge-tunnel cooperative construction structure | |
JP2587029B2 (en) | Viaduct construction method | |
CN109629443B (en) | Cast-in-place channel beam three-point pushing system crossing existing road and construction method | |
JP3380302B2 (en) | Viaduct construction method | |
SU863755A1 (en) | Method of constructing an underpass in the embankment of operating railway | |
Lin et al. | Lupu arch bridge, Shanghai | |
CN115198711A (en) | Construction platform structure and construction method of concrete cast-in-place pile for Yangjiang river | |
CN113123235A (en) | Construction method of cast-in-place tunnel bridge under existing line | |
CN115652818A (en) | Method for erecting near-tunnel bridge through prefabricated and assembled simply-supported box girder at last hole section | |
CN116043710A (en) | Bridge and tunnel combined construction structure and construction method thereof | |
DE1282048B (en) | Bridge structure made of reinforced or prestressed concrete for installation at crossings of existing railway lines with traffic routes to be underpassed | |
AU2004235614A1 (en) | Railway tunnel construction method | |
RU89124U1 (en) | DEVICE FOR ESTABLISHING A TUNNEL OF A SMALL LOCATION UNDER THE ROAD SECTION |