JP5167578B2 - Construction method for underground structures - Google Patents

Construction method for underground structures Download PDF

Info

Publication number
JP5167578B2
JP5167578B2 JP2005176992A JP2005176992A JP5167578B2 JP 5167578 B2 JP5167578 B2 JP 5167578B2 JP 2005176992 A JP2005176992 A JP 2005176992A JP 2005176992 A JP2005176992 A JP 2005176992A JP 5167578 B2 JP5167578 B2 JP 5167578B2
Authority
JP
Japan
Prior art keywords
construction
girder
underpass
section
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP2005176992A
Other languages
Japanese (ja)
Other versions
JP2006348612A (en
Inventor
貞文 井上
文行 横溝
行 太田
宏 吉川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2005176992A priority Critical patent/JP5167578B2/en
Publication of JP2006348612A publication Critical patent/JP2006348612A/en
Application granted granted Critical
Publication of JP5167578B2 publication Critical patent/JP5167578B2/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Lining And Supports For Tunnels (AREA)

Description

本発明は、工事桁を本設構造物として構築する地下構造物の構築方法に関し、特に、シールド機を用いて鉄道線路、道路等の車両軌道をアンダーパスするアンダーパス構造物を構築する方法に関する。   The present invention relates to a method for constructing an underground structure in which a construction girder is constructed as a permanent structure, and more particularly, to a method for constructing an underpass structure that underpasses a vehicle track such as a railway track or road using a shield machine. .

例えば、鉄道線路の下方をアンダーパスする地下構造物を構築する場合においては、全線を開削して施工する全線開削工法と線路の下方部分を非開削で施工し、アプローチ部を開削して施工する部分開削工法とが用いられている。全線開削工法は、営業中の鉄道線路下の支持杭間に列車が走行するための工事桁を設置し、上部荷重を工事桁で支持しながら工事桁下方の地盤を掘削して地下構造物を構築する工法である。すなわち、図19に示すように、支持杭101を鉄道線路の下方に築造し、鉄道線路の下に架設した工事桁102を支持杭101で支持し、構築予定場所の両側に土留め杭103を打設し、土留め杭103の内側で工事桁下の地盤を掘削し、この掘削した場所に地下構造物100を構築し、その後、埋戻す工法である。   For example, when constructing an underground structure that underpasses the lower part of the railroad track, the entire wire cutting method that cuts and constructs the entire line and the lower part of the track are constructed without cutting, and the approach part is opened and constructed. The partial cutting method is used. In the all-line open-cut method, a work girder is installed for the train to run between the supporting piles under the operating railway track, and the ground structure under the work girder is excavated while supporting the upper load with the work girder. This is a construction method. That is, as shown in FIG. 19, the support pile 101 is built below the railway track, the construction girder 102 installed under the railway track is supported by the support pile 101, and the earth retaining piles 103 are provided on both sides of the planned construction site. This is a construction method in which the ground under the construction girder is excavated inside the retaining pile 103, the underground structure 100 is constructed in the excavated place, and then backfilled.

また、部分開削工法として、例えば、鉄道線路と平行に発進立坑及び到達立坑を設け、鉄道線路の下方に、これを横断するように発進立坑から到達立坑へパイプルーフを推進設置し、このパイプルーフにて上部荷重を支持しながら地下構造物を構築する方法がある。すなわち、図20に示すように、パイプルーフ105を発進立坑から地中に推進設置させた後、パイプルーフ105下部の地盤を掘削しながら作業空間106を形成し、この作業空間106を利用して地下構造物104を構築する工法である(例えば、特許文献1参照)。
特開平7−259108号公報
As a partial excavation method, for example, a start shaft and a reach shaft are provided in parallel with the railroad track, and a pipe roof is propelled from the start shaft to the reach shaft so as to cross the railroad track. There is a method of constructing an underground structure while supporting the upper load. That is, as shown in FIG. 20, after the pipe roof 105 is propelled from the start shaft into the ground, a work space 106 is formed while excavating the ground below the pipe roof 105, and this work space 106 is used. This is a construction method for constructing the underground structure 104 (see, for example, Patent Document 1).
JP 7-259108 A

上述した全線開削工法においては、工事桁を設置し、この工事桁の下に掘削された場所で地下構造物を構築するために、工事桁を設置した後に地下構造物の構築作業を行うことになり、工事桁の設置作業と地下構造物の構築作業とを同時に施工することができず、工期が長くなるという問題点があった。また、地下構造物の構築作業は、工事桁下の狭隘空間で行うことになり、作業性が悪く、品質管理も困難であるという問題点があった。さらに、工事桁の下方に上床版を含む地下構造物を構築するために、車両軌道面からの土被りが大きくなり、地下構造物までのアプローチ区間の距離が長くなるという問題点があった。また、地下構造物の構築部分以上の地盤を掘削しなければならないために、環境に負荷がかかるという問題点があった。   In the above-mentioned full-line open-cut method, in order to install a construction girder and construct an underground structure at a location excavated under this construction girder, the construction work of the underground structure is performed after the construction girder is installed. Therefore, there was a problem that the installation work of the construction girder and the construction work of the underground structure could not be performed at the same time, and the construction period was long. In addition, the construction work of the underground structure is performed in a confined space under the work girder, and there is a problem that workability is poor and quality control is difficult. Furthermore, in order to construct an underground structure including an upper floor slab below the work girder, there was a problem that the earth covering from the track surface of the vehicle was increased and the distance of the approach section to the underground structure was increased. In addition, there is a problem that the environment is burdened because the ground above the construction part of the underground structure has to be excavated.

そして、上述した部分開削工法においては、立坑を掘削する作業に手間と時間がかかるために、工期が長くなり、工事費が高くなるという問題点があった。また、立坑を掘削した後に地下構造物へのアプローチ区間を構築しなければならないために、さらに工期が長くなるという問題点があった。また、立坑の掘削には、杭打ち機及び重機を使用するために、騒音・振動を低減することが困難であった。また、立坑間にパイプルーフを推進設置する際に、パイプルーフが地下構造体の外郭から大きくはみ出した範囲で山留材が敷設されるために、広い用地が必要となるという問題があった。さらに、立坑内での作業は、狭い範囲での作業で足場の確保が難しく、作業性が悪いという問題点があった。   In the above-mentioned partial excavation method, since the work for excavating the shaft takes time and effort, there is a problem that the construction period becomes long and the construction cost becomes high. Moreover, since the approach section to the underground structure has to be constructed after excavating the shaft, there is a problem that the construction period becomes longer. Moreover, since the pile driver and heavy machinery are used for excavation of the shaft, it is difficult to reduce noise and vibration. Further, when the pipe roof is propelled and installed between the shafts, there is a problem that a large site is required because the mountain retaining material is laid in a range where the pipe roof protrudes greatly from the outer shell of the underground structure. Furthermore, the work in the shaft has a problem in that it is difficult to secure a scaffold in a narrow range of work and the workability is poor.

本発明は、上記のような問題点を鑑みてなされたものであり、工事桁を地下構造物の上床版として利用する地下構造物の構築方法を提供し、短期間で経済性に優れた地下構造物を構築することを目的とする。   The present invention has been made in view of the above problems, and provides a construction method of an underground structure that uses a construction girder as an upper floor slab of an underground structure, and is an underground that has excellent economic efficiency in a short period of time. The purpose is to construct a structure.

前記目的を達成するため、本発明の地下構造物の構築工法は、既存の鉄道線路、道路等の車両軌道をアンダーパスするアンダーパス構造物を構築するための地下構造物の構築工法であって、前記車両軌道を工事桁にて支持し、シールド機にて前記車両軌道の下方にトンネルを掘削してセグメントを設置することによりトンネル部構造物を構築し、前記工事桁を前記トンネル部構造物にて支持し、前記工事桁を撤去し、本設桁を設置することにより前記アンダーパス構造物を構成することを特徴とする。 In order to achieve the above object, the underground construction method according to the present invention is an underground structure construction method for constructing an underpass structure that underpasses a vehicle track such as an existing railway track or road. The tunnel structure is constructed by supporting the vehicle track with a construction girder, excavating a tunnel below the vehicle track with a shield machine, and installing a segment. The underpass structure is formed by removing the construction girder and installing a permanent girder.

の発明の地下構造物の構築工法は、既存の鉄道線路、道路等の車両軌道をアンダーパスするアンダーパス構造物を構築するための地下構造物の構築工法であって、前記車両軌道を工事桁にて支持し、シールド機を地上部から発進させて、所定の下り勾配を有する下りアプローチ区間を構築し、前記下りアプローチ区間の終点部から、セグメントを設置することにより前記工事桁をトンネル部構造物にて支持するアンダーパス区間を構築し、前記アンダーパス区間の終点部から、所定の上り勾配を有する上りアプローチ区間を構築し、前記シールド機を地上に到達させ、前記工事桁を撤去し、本設桁を設置することにより前記アンダーパス構造物を構成することを特徴とする。 A construction method for an underground structure according to a second aspect of the present invention is a construction method for an underground structure for constructing an underpass structure that underpasses a vehicle track such as an existing railroad track or road. Support the work girder, start the shield machine from the ground, construct a descent approach section with a predetermined descent, and tunnel the work girder by installing a segment from the end point of the descent approach section Build an underpass section supported by the substructure, build an ascending approach section with a predetermined ascending slope from the end point of the underpass section, let the shield machine reach the ground, and remove the construction girder The underpass structure is configured by installing a main girder.

の発明は、第又はの発明において、前記セグメントを略U型に設置することにより略U型の前記トンネル部構造物を構築し、前記本設桁を上床板、該略U型のトンネル部構造物を壁・下床板とする前記アンダーパス構造物を構成することを特徴とする。 According to a third invention, in the first or second invention, the substantially U-shaped tunnel part structure is constructed by installing the segments in a substantially U shape, the main girder is used as an upper floor board, and the substantially U shape. The underpass structure having the tunnel part structure as a wall / lower floor plate is configured.

の発明は、第の発明において、前記上りアプローチ区間及び前記下りアプローチ区間は、掘削部分が地上に開放された半地中部を備えることを特徴とする。 In a fourth aspect based on the second aspect , the ascending approach section and the descending approach section include a semi-ground part whose excavation part is open to the ground.

の発明は、第の発明において、前記半地中部のセグメントは、環状又は矩形状に配置され、後に一部が撤去されて略U型に構築されることを特徴とする。 A fifth invention is characterized in that, in the fourth invention, the semi-ground middle segment is arranged in a ring shape or a rectangular shape, and a part thereof is later removed and constructed in a substantially U shape.

本発明の地下構造物の構築工法によれば、本設桁を地下構造物の上床版として利用するために、土被りを最小限に抑えることができる。したがって、地下構造物までのアプローチ区間の距離を短くすることができる。また、地下構造物の壁・下床版をシールド機にて掘削しながら構築する。したがって、地下構造物の構築工期を飛躍的に短縮することができる。 According to the construction method of the underground structure of the present invention, since the main girder is used as the upper floor slab of the underground structure, the earth covering can be minimized. Therefore, the distance of the approach section to the underground structure can be shortened. In addition, the walls and lower floor slabs of the underground structure will be constructed while excavating with a shield machine. Therefore, the construction period of the underground structure can be dramatically shortened.

また、本発明の地下構造物の構築工法によれば、シールド機は地上発進して地上到達する。したがって、立坑の開削作業及び構築作業が不要となり、工期を短縮することができる。また、杭打ち機等による騒音・振動も発生しない。   Moreover, according to the construction method of the underground structure of the present invention, the shield machine starts on the ground and reaches the ground. Therefore, the shaft excavation work and construction work are not required, and the construction period can be shortened. In addition, no noise or vibration is generated by a pile driver.

さらに、本発明の地下構造物の構築工法によれば、シールド機にて下りアプローチ区間、アンダーパス区間、上りアプローチ区間の順番に構築する。したがって、工事兼本設桁又は工事桁の設置作業と下りアプローチ区間の構築作業とを、また、工事兼本設桁の仮設部撤去又は本設桁の設置作業と上りアプローチ区間の構築作業とを同時に施工することができるために、工期を短縮することができる。   Furthermore, according to the construction method of the underground structure of the present invention, the shield machine is constructed in the order of the descending approach section, the underpass section, and the ascending approach section. Therefore, the installation work of the construction and permanent girder or the construction girder and the construction work of the downward approach section, and the construction and removal of the temporary part of the permanent girder or the installation work of the permanent girder and the construction work of the upward approach section are performed. Since construction can be performed at the same time, the construction period can be shortened.

以下、本発明の好ましい実施形態について図面を用いて詳細に説明する。なお、発明の理解の便宜上、鉄道線路をアンダーパスするトンネルを構築する方法について説明するが、本発明の適用対象は鉄道線路に限定されるものではなく、既設構造物の下方に構築される地下構造物に広く適用が可能である。   Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the drawings. For convenience of understanding the invention, a method for constructing a tunnel that underpasses a railroad track will be described. However, the application target of the present invention is not limited to a railroad track, and is a basement constructed below an existing structure. Widely applicable to structures.

図1は、本発明の第一実施形態に係る工事兼本設桁の設置状態を示す平面図で、図2は、図1のA−A’断面図で、図3は、図1のB−B’断面図である。   FIG. 1 is a plan view showing an installation state of a construction and permanent girder according to the first embodiment of the present invention, FIG. 2 is a cross-sectional view taken along the line AA ′ of FIG. 1, and FIG. It is -B 'sectional drawing.

図1〜図3に示すように、車両軌道である鉄道線路のレール1の両側の地盤に支持杭2を打ち込み、レール1を一時的に撤去し、両側の支持杭2の上にH形鋼からなる架台4を介して工事兼本設桁5を設置する。工事兼本設桁5の設置後は、その上にレール1を敷設し、列車の走行を可能にする。この工事兼本設桁5は、本設部5aと、その両側に連結される仮設部5bとから構成され、本設部5aと仮設部5bとの各連結面には、互いに嵌合する嵌合溝及び嵌合突部が設けられ、脱着可能である。本設部5aと仮設部5bとは嵌合し一体化された状態にて架台4の上に設置され、仮設部5bが支持杭2の上方となるように設置される。ここで、本設部5aの幅は、トンネル部構造物であるU型構造物20(後述する)の両端部20a、20bの外面幅よりも短く、かつ、内面幅よりも長くなるようにする。この工事兼本設桁5は、鉄筋コンクリート製、すなわちプレキャスト版であり、現場で製作してもよいし、工場で製作して現場に搬入してもよい。   As shown in FIGS. 1 to 3, the support pile 2 is driven into the ground on both sides of the rail 1 of the railroad track that is the vehicle track, the rail 1 is temporarily removed, and the H-section steel is placed on the support pile 2 on both sides. A construction and permanent girder 5 is installed through a gantry 4 comprising: After the installation of the construction and main girder 5, the rail 1 is laid on the girder 5 so that the train can run. The construction and permanent girder 5 is composed of a permanent portion 5a and temporary portions 5b connected to both sides thereof, and fittings that are fitted to each other on the connecting surfaces of the permanent portion 5a and the temporary portion 5b. A mating groove and a fitting projection are provided and are detachable. The main installation part 5 a and the temporary installation part 5 b are installed on the gantry 4 in a state of being fitted and integrated, and the temporary installation part 5 b is installed above the support pile 2. Here, the width of the main portion 5a is shorter than the outer surface widths of both end portions 20a and 20b of a U-shaped structure 20 (described later) that is a tunnel structure, and is longer than the inner surface width. . This construction and permanent girder 5 is made of reinforced concrete, that is, a precast plate, and may be manufactured on site or manufactured in a factory and carried into the site.

図4は、本発明の第一実施形態に係るシールド機10を用いた下りアプローチ区間12の構築方法を示す図である。   FIG. 4 is a diagram illustrating a construction method of the downlink approach section 12 using the shield machine 10 according to the first embodiment of the present invention.

本発明の地下構造物の構築工法にて構築されるトンネル11は、地上発進部15から工事兼本設桁5の下面の深度に到達するための下り勾配を有する下りアプローチ区間12と、工事兼本設桁5の下面深度にて、レール1をアンダーパスするアンダーパス区間13と、このアンダーパス区間13の終端から地上到達部16に到達するための上り勾配を有する上りアプローチ区間14とからなる。   The tunnel 11 constructed by the construction method of the underground structure of the present invention includes a down approach section 12 having a down slope for reaching the depth of the lower surface of the construction and main girder 5 from the ground starting portion 15, The underpass section 13 underpasses the rail 1 at the bottom surface depth of the main girder 5 and the up approach section 14 having an ascending slope for reaching the ground reaching unit 16 from the end of the underpass section 13. .

以下に、シールド機10にてレール1の下方をアンダーパスするトンネル11の構築工法について、トンネル11の構築手順にしたがって説明する。最初に、シールド機10による下りアプローチ区間12の構築方法について説明する。   Below, the construction method of the tunnel 11 which underpasses the downward direction of the rail 1 with the shield machine 10 is demonstrated according to the construction procedure of the tunnel 11. FIG. First, the construction method of the downlink approach section 12 by the shield machine 10 will be described.

図4に示すように、シールド機10は、地盤をカッターヘッド17により掘削するとともに、地上発進部15から地中へ所定の下り勾配で進入する。カッターヘッド17で掘削された土砂は、隔壁を介してカッターヘッド17のすぐ後方にある掘削室内18で撹拌され、必要に応じて掘削土砂の塑性流動化を促進するための作泥剤が注入される。そして、塑性流動化した土砂は、スクリューコンベア等の排土装置19によりシールド機10本体の後方へ送給される。   As shown in FIG. 4, the shield machine 10 excavates the ground with the cutter head 17 and enters the ground from the ground starting portion 15 into the ground with a predetermined downward slope. The earth and sand excavated by the cutter head 17 is agitated in the excavation chamber 18 immediately behind the cutter head 17 through a partition wall, and a mud-forming agent for promoting plastic fluidization of the excavated earth and sand is injected as needed. The The plastic fluidized sediment is fed to the back of the shield machine 10 main body by a soil removal device 19 such as a screw conveyor.

シールド機10により下りアプローチ区間12を掘進しながら、シールド機10の後方には、掘削した部分の内面に順次セグメントを設置することにより下りアプローチ区間12が構築される。下りアプローチ区間12は、U型にセグメントを配設してU型構造物20を構築し、上方が地上に開放した半地下状態の半地中部となる。   While digging down the descending approach section 12 by the shield machine 10, the descending approach section 12 is constructed by sequentially installing segments on the inner surface of the excavated portion behind the shield machine 10. The descending approach section 12 is a semi-ground part in a semi-underground state in which a U-shaped structure 20 is constructed by arranging segments in a U shape and the upper part is open to the ground.

次に、アンダーパス区間13を掘削する方法について説明する。
図5は、本発明の第一実施形態に係るシールド機10を用いたアンダーパス区間13の構築方法を示す図で、図6は、図5のC−C’矢視図である。図5に示すように、下りアプローチ区間12を構築した後に、連続してアンダーパス区間13を構築する。ここで、シールド機10本体の勾配をアンダーパス区間13の所定の勾配、つまり工事兼本設桁5の勾配と同じにし、かつ、シールド機10による掘削断面の上面が、工事兼本設桁5の下面から支承(後述する)を配設するための所定の隙間分だけ下方の位置となるようにシールド機10を調整する。そして、シールド機10を掘進させ、図6に示すように、工事兼本設桁5の真下を掘削して工事兼本設桁5の下面を露出させる。
Next, a method for excavating the underpass section 13 will be described.
FIG. 5 is a view showing a construction method of the underpass section 13 using the shield machine 10 according to the first embodiment of the present invention, and FIG. 6 is a view taken along the line CC ′ of FIG. As shown in FIG. 5, after constructing the downlink approach section 12, the underpass section 13 is constructed continuously. Here, the slope of the shield machine 10 main body is the same as the slope of the underpass section 13, that is, the slope of the construction and permanent girder 5, and the top surface of the excavation cross section by the shield machine 10 is the construction and permanent girder 5. The shield machine 10 is adjusted so as to be at a position below a predetermined gap for disposing a support (described later) from the lower surface of the shield. Then, the shield machine 10 is dug, and as shown in FIG. 6, the lower surface of the construction and permanent girder 5 is exposed by excavating directly under the construction and permanent girder 5.

図7は、本発明の第一実施形態に係るシールド機10が通過した後のアンダーパス区間13の横断方向断面図である。シールド機10を工事兼本設桁5の真下に掘進させながら、後方にU型のセグメントを設置することによりU型構造物20を構築し、図7に示すように、工事兼本設桁5を、積層ゴム6aとこの積層ゴム6aを固定する無収縮モルタル6bとから構成される支承6を介してU型構造物20にて支持する。ここで、支承6の積層ゴム6aをアンカーバー(図示せず)等の固定材にて工事兼本設桁5に固定し、また、積層ゴム6aの下部をU型構造物20に取り付けられた型枠内に配設し、この型枠内に無収縮モルタル6bを充填して固化することによりU型構造物20に固定する。そして、シールド機10にて掘進する際は、U型構造物20の両端部20a、20bが本設部5aの両端部のそれぞれ所定の位置に近接するように、掘削の中心軸と本設部5aの中心軸とを一致させて掘削する。   FIG. 7 is a cross-sectional view in the transverse direction of the underpass section 13 after the shield machine 10 according to the first embodiment of the present invention has passed. A U-shaped structure 20 is constructed by installing a U-shaped segment in the rear while the shield machine 10 is digging directly under the construction and permanent girder 5, and as shown in FIG. Is supported by the U-shaped structure 20 via a support 6 composed of a laminated rubber 6a and a non-shrink mortar 6b for fixing the laminated rubber 6a. Here, the laminated rubber 6a of the support 6 is fixed to the construction and permanent girder 5 with a fixing material such as an anchor bar (not shown), and the lower part of the laminated rubber 6a is attached to the U-shaped structure 20. It arrange | positions in a mold, and it fixes to the U-shaped structure 20 by filling this mold with the non-shrink mortar 6b and solidifying. When digging with the shield machine 10, the central axis of the excavation and the main installation part are arranged so that both end parts 20a, 20b of the U-shaped structure 20 are close to predetermined positions on both end parts of the main installation part 5a. Drilling with the central axis of 5a aligned.

次に、上りアプローチ区間14を構築する方法について説明する。
図8は、本発明の第一実施形態に係るシールド機10を用いた上りアプローチ区間14の構築方法を示す図である。図8に示すように、アンダーパス区間13を構築した後に、連続して上りアプローチ区間14を構築する。ここで、シールド機10本体の勾配を上りアプローチ区間14の所定の勾配と同じになるようにシールド機10を調整し、地上到達部16へ向けて所定の上り勾配で掘進する。シールド機10により上りアプローチ区間14を掘削しながら、シールド機10の後方に、上述した下りアプローチ区間12と同様に、セグメントを配設してU型構造物20を構築し、上方が地上に開放した状態の半地中部とする。
Next, a method for constructing the uplink approach section 14 will be described.
FIG. 8 is a diagram illustrating a construction method of the uplink approach section 14 using the shield machine 10 according to the first embodiment of the present invention. As shown in FIG. 8, after constructing the underpass section 13, the uplink approach section 14 is constructed continuously. Here, the shield machine 10 is adjusted so that the gradient of the main body of the shield machine 10 is the same as the predetermined gradient of the ascending approach section 14, and the digging is performed toward the ground reaching unit 16 with the predetermined ascending gradient. While excavating the ascending approach section 14 by the shield machine 10, a U-shaped structure 20 is constructed by arranging segments behind the shield machine 10 in the same manner as the approach approach section 12 described above, and the upper part is open to the ground. It will be the middle part of the semi-finished area.

図9は、本発明の第一実施形態に係るアンダーパス区間13の断面図である。上りアプローチ区間14を構築した後に、図9に示すように、仮設部5b、架台4、支持杭2を撤去する。仮設部5b、架台4等を撤去し、パラペット22を取り付け、工事兼本設桁5を上床版、U型構造物20を壁・下床版とするアンダーパス区間13を構築する。   FIG. 9 is a cross-sectional view of the underpass section 13 according to the first embodiment of the present invention. After constructing the ascending approach section 14, as shown in FIG. 9, the temporary portion 5b, the gantry 4 and the support pile 2 are removed. The temporary portion 5b, the gantry 4 and the like are removed, the parapet 22 is attached, and the underpass section 13 is constructed with the construction and main girder 5 as the upper floor slab and the U-shaped structure 20 as the wall / lower floor slab.

なお、本実施形態においては、上りアプローチ区間14を構築した後に、仮設部5b、架台4等を撤去する方法について説明したが、これに限定されるものではなく、上りアプローチ区間14を構築しながら仮設部5b、架台4等を撤去する方法を用いてもよい。   In the present embodiment, the method of removing the temporary part 5b, the gantry 4 and the like after the ascending approach section 14 is constructed has been described. However, the present invention is not limited to this. You may use the method of removing the temporary part 5b, the mount frame 4 grade | etc.,.

図10は、本発明の第一実施形態に係る地下構造物の構築工法にて構築したトンネル11を示す図である。図10に示すように、トンネル11は、シールド機10により掘削され、U型構造物20を壁・下床版とする下りアプローチ区間12と、工事兼本設桁5を上床版、U型構造物20を壁・下床版とするアンダーパス区間13と、U型構造物20を壁・下床版とする上りアプローチ区間14とから構成される。   FIG. 10 is a diagram showing the tunnel 11 constructed by the underground construction method according to the first embodiment of the present invention. As shown in FIG. 10, the tunnel 11 is excavated by the shield machine 10, the down approach section 12 having the U-shaped structure 20 as the wall / lower floor slab, and the construction / main girder 5 as the upper floor slab, U-shaped structure. An underpass section 13 having the object 20 as a wall / lower floor slab and an ascending approach section 14 having the U-shaped structure 20 as a wall / lower floor slab are configured.

図11は、本発明の第一実施形態に係る地下構造物の構築工法にて構築したトンネル11とレール1との交差部を示す平面図である。図11の道路Aと道路B、道路Cと道路Dに示すように、レール1の横断方向にトンネル11を構築したことにより、従来は1つであった道路を分断してしまい近隣住民が不便になるために、レール1近傍の下りアプローチ区間12及び上りアプローチ区間14の上部に道路Aと道路Bとを、道路Cと道路Dとを接続するための道路橋23をそれぞれ設置し、近隣住民の利便性を図る。   FIG. 11 is a plan view showing an intersection of the tunnel 11 and the rail 1 constructed by the underground construction method according to the first embodiment of the present invention. As shown in road A and road B, road C and road D in FIG. 11, the construction of the tunnel 11 in the crossing direction of the rail 1 divides the road, which was conventionally one, inconvenience to neighboring residents. Therefore, the road bridge 23 for connecting the road A and the road B and the road C and the road D are installed above the down approach section 12 and the up approach section 14 near the rail 1, respectively. The convenience of

本実施形態における地下構造物の構築工法にあっては、工事兼本設桁5をトンネル11の上床版として利用するために、土被りを最小限に抑えることができる。したがって、下り・上りアプローチ区間12、14の距離を短くすることができる。   In the construction method of the underground structure in the present embodiment, since the construction and permanent girder 5 is used as the upper floor slab of the tunnel 11, the earth covering can be minimized. Therefore, the distance between the downlink / uplink approach sections 12 and 14 can be shortened.

また、トンネル11の壁・下床版として利用するU型構造物20をシールド機10にて掘削しながら構築する。したがって、トンネル11の構築工期を飛躍的に短縮することができる。   Further, a U-shaped structure 20 used as a wall / lower floor slab of the tunnel 11 is constructed while excavating with the shield machine 10. Therefore, the construction period of the tunnel 11 can be dramatically shortened.

そして、シールド機10は地上発進して地上到達する。したがって、立坑の開削作業及び構築作業が不要となり、工期を短縮することができる。また、杭打ち機等による騒音・振動も発生しない。   And the shield machine 10 starts on the ground and reaches the ground. Therefore, the shaft excavation work and construction work are not required, and the construction period can be shortened. In addition, no noise or vibration is generated by a pile driver.

さらに、シールド機10にて下りアプローチ区間12、アンダーパス区間13、上りアプローチ区間14の順番に構築する。したがって、工事兼本設桁5の設置作業と下りアプローチ区間12の構築作業とを、工事兼本設桁5の仮設部5b撤去作業と上りアプローチ区間14の構築作業とを同時に施工することができるために、工期を短縮することができる。   Further, the shield machine 10 is constructed in the order of the down approach section 12, the underpass section 13, and the up approach section 14. Therefore, the installation work of the construction and permanent girder 5 and the construction work of the downward approach section 12 can be performed simultaneously with the construction work of the temporary construction 5b of the construction and permanent girder 5 and the construction work of the upward approach section 14. Therefore, the construction period can be shortened.

なお、本実施形態においては、本設部5aと仮設部5bとからなる工事兼本設桁5を用い、アンダーパス区間13の構築時に仮設部5bを撤去する方法について説明したが、これに限定されるものではなく、本設部5aのみからなる工事兼本設桁5を用いる方法でもよい。ここで、この方法用いる場合は架台4、支持版3、支持杭2は埋め殺しとなる。   In the present embodiment, the method of removing the temporary part 5b when the underpass section 13 is constructed using the construction and permanent girder 5 including the permanent part 5a and the temporary part 5b has been described. However, the present invention is not limited thereto. Instead of this, a method using the construction and permanent girder 5 consisting only of the permanent portion 5a may be used. Here, when this method is used, the gantry 4, the support plate 3, and the support pile 2 are buried.

次に、本発明における第一実施形態と異なる実施形態を示す。下記に示す説明において、第一実施形態と同様の技術を用いたものと対応する部分には同一の符号を付して、説明を省略する。   Next, an embodiment different from the first embodiment in the present invention will be described. In the following description, the same reference numerals are given to portions corresponding to those using the same technique as in the first embodiment, and description thereof is omitted.

図12は、本発明の第二実施形態に係る工事桁の設置状態を示す断面図である。図12に示すように、鉄道線路のレール1の両側の地盤に支持杭2を打ち込み、レール1を一時的に撤去し、支持杭2の上に架台4を介して工事桁8を設置する。工事桁8の設置後は、その上にレール1を敷設し、列車の走行を可能にする。工事桁8は、鉄筋コンクリート製、すなわちプレキャスト版であり、現場で製作してもよいし、工場で製作して現場に搬入してもよい。   FIG. 12 is a cross-sectional view showing the installation state of the construction beam according to the second embodiment of the present invention. As shown in FIG. 12, the support pile 2 is driven into the ground on both sides of the rail 1 of the railroad track, the rail 1 is temporarily removed, and the work girder 8 is installed on the support pile 2 via the gantry 4. After the construction girder 8 is installed, the rail 1 is laid on the girder 8 so that the train can run. The construction girder 8 is made of reinforced concrete, that is, a precast version, and may be manufactured on site or manufactured at a factory and carried into the site.

図13は、本発明の第二実施形態に係るシールド機10を用いた下りアプローチ区間12の構築方法を示す図である。
本発明の地下構造物の構築工法にて構築されるトンネル31は、地上発進部15から工事桁8の下面の深度に到達するための下りアプローチ区間12と、工事桁8の下面深度にて、レール1をアンダーパスするアンダーパス区間33と、このアンダーパス区間33の終端から地上到達部16に到達するための上りアプローチ区間14とからなる。
FIG. 13 is a diagram illustrating a construction method of the downlink approach section 12 using the shield machine 10 according to the second embodiment of the present invention.
The tunnel 31 constructed by the construction method of the underground structure of the present invention has a downward approach section 12 for reaching the depth of the lower surface of the work girder 8 from the ground starting portion 15 and the lower surface depth of the work girder 8. The underpass section 33 underpasses the rail 1 and the ascending approach section 14 for reaching the ground arrival unit 16 from the end of the underpass section 33.

図13に示すように、シールド機10は、第一実施形態と同様に、地上発進部15から地中へ所定の下り勾配で進入する。そして、シールド機10により下りアプローチ区間12を掘進しながら、順次セグメントを設置することにより下りアプローチ区間12が構築される。下りアプローチ区間12は、U型にセグメントを配設してU型構造物20を構築し、上方が地上に開放した半地下状態の半地中部となる。   As shown in FIG. 13, the shield machine 10 enters the ground from the ground starting portion 15 into the ground with a predetermined downward slope, as in the first embodiment. Then, the descending approach section 12 is constructed by sequentially installing the segments while digging the descending approach section 12 by the shield machine 10. The descending approach section 12 is a semi-ground part in a semi-underground state in which a U-shaped structure 20 is constructed by arranging segments in a U shape and the upper part is open to the ground.

図14は、本発明の第二実施形態に係るシールド機10を用いたアンダーパス区間33の構築方法を示す図である。図14に示すように、下りアプローチ区間12を構築した後に、連続してアンダーパス区間33を構築する。ここで、シールド機10本体の勾配をアンダーパス区間33の所定の勾配、つまり工事桁8の勾配と同じにし、かつ、シールド機10による掘削断面の上面が、工事桁8の下面から支承6を配設するための所定の隙間分だけ下方の位置となるようにシールド機10を調整する。そして、シールド機10を掘進させ、工事桁8の真下を掘削して工事桁8の下面を露出させる。   FIG. 14 is a diagram illustrating a construction method of the underpass section 33 using the shield machine 10 according to the second embodiment of the present invention. As shown in FIG. 14, after constructing the downlink approach section 12, the underpass section 33 is constructed continuously. Here, the slope of the main body of the shield machine 10 is made the same as the predetermined slope of the underpass section 33, that is, the slope of the work beam 8, and the upper surface of the excavation cross section by the shield machine 10 extends from the lower surface of the work beam 8 to the support 6. The shield machine 10 is adjusted so as to be in a lower position by a predetermined gap for placement. And the shield machine 10 is dug, and the bottom of the work girder 8 is exposed by excavating the work beam 8 directly below.

図15は、本発明の第二実施形態に係るシールド機10が通過した後のアンダーパス区間33の横断方向断面図である。図15に示すように、シールド機10を工事桁8の真下に掘進させながら、後方にU型のセグメントを設置することによりU型構造物20を構築し、工事桁8を支承6を介してU型構造物20にて支持する。ここで、支承6は工事桁8及びU型構造物20に取り付けず、仮留め状態とする。   FIG. 15 is a cross-sectional view in the transverse direction of the underpass section 33 after the shield machine 10 according to the second embodiment of the present invention has passed. As shown in FIG. 15, a U-shaped structure 20 is constructed by installing a U-shaped segment on the rear side while digging the shield machine 10 directly below the work girder 8, and the work girder 8 is connected via the support 6. It is supported by a U-shaped structure 20. Here, the support 6 is not attached to the work girder 8 and the U-shaped structure 20 but is temporarily attached.

図16は、本発明の第二実施形態に係るシールド機10を用いた上りアプローチ区間14の構築方法を示す図である。図16に示すように、アンダーパス区間33を構築した後に、上りアプローチ区間14を構築する。ここで、第一実施形態と同様に、シールド機10本体の勾配を上りアプローチ区間14の所定の勾配と同じになるようにシールド機10を調整し、地上到達部16へ向けて所定の上り勾配で掘進する。シールド機10により上りアプローチ区間14を掘削しながら、上述した下りアプローチ区間12と同様に、セグメントを配設してU型構造物20を構築し、上方が地上に開放した状態の半地中部とする。   FIG. 16 is a diagram illustrating a construction method of the uplink approach section 14 using the shield machine 10 according to the second embodiment of the present invention. As shown in FIG. 16, after constructing the underpass section 33, the uplink approach section 14 is constructed. Here, similarly to the first embodiment, the shield machine 10 is adjusted so that the gradient of the shield machine 10 main body is the same as the predetermined gradient of the ascending approach section 14, and the predetermined ascending gradient toward the ground reaching unit 16. Dig in. While excavating the ascending approach section 14 with the shield machine 10, similarly to the descending approach section 12 described above, the U-shaped structure 20 is constructed by disposing the segments, and the upper half of the half ground is open to the ground. To do.

図17は、本発明の第二実施形態に係るアンダーパス区間33の横断方向断面図である。上りアプローチ区間14を構築した後に、図17に示すように、工事桁8、架台4、支持杭2を撤去し、本設桁9を設置し、パラペット22を取り付け、本設桁9を上床版、U型構造物20を壁・下床版とするアンダーパス区間33を構築する。ここで、支承6を第一実施形態と同様に、本設桁9及びU型構造物20に取り付ける。   FIG. 17 is a transverse sectional view of the underpass section 33 according to the second embodiment of the present invention. After constructing the ascending approach section 14, as shown in FIG. 17, the construction girder 8, the gantry 4 and the support pile 2 are removed, the main girder 9 is installed, the parapet 22 is attached, and the main girder 9 is installed on the upper floor slab. The underpass section 33 is constructed with the U-shaped structure 20 as a wall / lower floor slab. Here, the support 6 is attached to the main girder 9 and the U-shaped structure 20 as in the first embodiment.

図18は、本発明の第二実施形態に係る地下構造物の構築工法にて構築したトンネル31を示す図である。図18に示すように、トンネル31は、シールド機10により掘削され、U型構造物20を壁・下床版とする下りアプローチ区間12と、本設桁9を上床版、U型構造物20を壁・下床版とするアンダーパス区間33と、U型構造物20を壁・下床版とする上りアプローチ区間14とから構成される。また、第一実施形態と同様に近隣住民の利便性を図るために道路橋23をそれぞれ下りアプローチ区間12、上りアプローチ区間14の本設桁9近傍の上部に設置する。   FIG. 18 is a view showing the tunnel 31 constructed by the construction method of the underground structure according to the second embodiment of the present invention. As shown in FIG. 18, the tunnel 31 is excavated by the shield machine 10, and the down approach section 12 having the U-shaped structure 20 as the wall / lower floor slab, and the main girder 9 as the upper floor slab and the U-shaped structure 20. Is composed of an underpass section 33 having a wall / lower floor slab and an up approach section 14 having the U-shaped structure 20 as a wall / lower floor slab. Similarly to the first embodiment, the road bridge 23 is installed in the upper part of the down approach section 12 and the up approach section 14 near the main girder 9 for the convenience of the neighboring residents.

なお、本実施形態においては、上りアプローチ区間14を構築した後に、工事桁8、架台4等を撤去する方法について説明したが、これに限定されるものではなく、上りアプローチ区間14を構築しながら工事桁8、架台4等を撤去し、本設桁9を設置する方法を用いてもよい。   In the present embodiment, the method of removing the construction girder 8, the gantry 4 and the like after the ascending approach section 14 is constructed has been described. However, the present invention is not limited to this. A method of removing the construction girder 8 and the gantry 4 and installing the main girder 9 may be used.

本実施形態における地下構造物の構築工法にあっては、本設桁9をトンネル31の上床版として利用するために、土被りを最小限に抑えることができる。したがって、下り・上りアプローチ区間12、14の距離を短くすることができる。また、トンネル31の壁・下床版として利用するU型構造物20をシールド機10にて掘削しながら構築する。したがって、トンネル31の構築工期を飛躍的に短縮することができる。そして、シールド機10は地上発進して地上到達する。したがって、立坑の開削作業及び構築作業が不要となり、工期を短縮することができる。また、杭打ち機等による騒音・振動も発生しない。さらに、シールド機10にて下りアプローチ区間12、アンダーパス区間33、上りアプローチ区間14の順番に構築する。したがって、工事桁8の設置作業と下りアプローチ区間12の構築作業とを、工事桁8を撤去して本設桁9を設置する作業と上りアプローチ区間14の構築作業とを同時に施工することができるために、工期を短縮することができる。   In the construction method of the underground structure in the present embodiment, since the main girder 9 is used as the upper floor slab of the tunnel 31, the earth covering can be minimized. Therefore, the distance between the downlink / uplink approach sections 12 and 14 can be shortened. Further, the U-shaped structure 20 to be used as the wall / lower floor slab of the tunnel 31 is constructed while excavating with the shield machine 10. Therefore, the construction period of the tunnel 31 can be dramatically shortened. And the shield machine 10 starts on the ground and reaches the ground. Therefore, the shaft excavation work and construction work are not required, and the construction period can be shortened. In addition, no noise or vibration is generated by a pile driver. Further, the shield machine 10 is constructed in the order of the down approach section 12, the underpass section 33, and the up approach section 14. Therefore, the installation work of the construction girder 8 and the construction work of the down approach section 12 can be performed simultaneously with the work of removing the construction girder 8 and installing the main girder 9 and the construction work of the up approach section 14. Therefore, the construction period can be shortened.

なお、上述したすべての実施形態において、アンダーパス区間13、33及び下り・上りアプローチ区間12、14にU型のセグメントを設置することによりU型構造物20を構築する方法について説明したが、これに限定されるものではなく、例えば、(1)アンダーパス区間13、33にはU型構造物20を構築して工事兼本設桁5又は工事桁8若しくは本設桁9を支持し、下り・上りアプローチ区間12、14にはシールド機10の十分な推進力を得るために矩形のセグメントを設置して矩形構造物を構築し、地上への開放部分は矩形構造物への入口部分のみの状態とする方法、又は(1)において、下り及び上りアプローチ区間12、14の矩形構造物を構築した後に、この矩形構造物の地上露出部分を撤去して上方が地上に開放した状態とする方法、又は(2)アンダーパス区間13、33及び下り・上りアプローチ区間12、14に矩形のセグメントを設置することによりすべての区間を矩形構造物にて構築し、アンダーパス区間13、33の矩形構造物にて工事兼本設桁5又は工事桁8若しくは本設桁9を支持し、地上への開放部分は矩形構造物への入口部分のみの状態とする方法、又は(2)において、下り及び上りアプローチ区間12、14の矩形構造物を構築した後に、この矩形構造物の地上露出部分を撤去して上方が地上に開放した状態とする方法、又は(3)アンダーパス区間13、33には矩形構造物を構築して工事兼本設桁5又は工事桁8若しくは本設桁9を支持し、下り・上りアプローチ区間12、14にはU型構造物20を構築する方法、のいずれかを用いてもよい。   In all the embodiments described above, the method of constructing the U-shaped structure 20 by installing U-shaped segments in the underpass sections 13 and 33 and the down / upward approach sections 12 and 14 has been described. For example, (1) A U-shaped structure 20 is constructed in the underpass sections 13 and 33 to support the construction / main construction girder 5 or the construction girder 8 or the main girder 9, and to descend -In order to obtain sufficient propulsive force of the shield machine 10 in the ascending approach sections 12 and 14, a rectangular segment is constructed to construct a rectangular structure, and the open part to the ground is only the entrance part to the rectangular structure. In the method to make a state, or (1), after constructing the rectangular structure of the descending and ascending approach sections 12, 14, the ground exposed portion of the rectangular structure is removed and the upper part is opened to the ground. Or (2) by setting rectangular segments in the underpass sections 13 and 33 and the down / upward approach sections 12 and 14 to construct all sections with rectangular structures, A method of supporting the construction and permanent girder 5 or the construction girder 8 or the permanent girder 9 with 33 rectangular structures, and having only the entrance to the rectangular structure open to the ground, or (2) , After constructing the rectangular structure of the down and up approach sections 12 and 14, the ground exposed portion of the rectangular structure is removed and the upper part is opened to the ground, or (3) the underpass section 13 33, a method of constructing a rectangular structure to support the construction and permanent girder 5 or the construction girder 8 or the permanent girder 9, and constructing a U-shaped structure 20 in the down / upward approach sections 12 and 14, Noiz It may be used either.

また、上述したすべての実施形態において、架台4、支持杭2を撤去する方法について説明したが、これに限定されるものではなく、架台4、支持杭2は埋め殺しとしてもよい。   Moreover, in all embodiment mentioned above, although the method of removing the mount frame 4 and the support pile 2 was demonstrated, it is not limited to this, The mount frame 4 and the support pile 2 are good also as being killed.

さらに、上述したすべての実施形態において、軌道受式による工事兼本設桁5又は工事桁8若しくは本設桁9を用いる方法について説明したが、これに限定されるものではなく、例えば、枕木式、抱え込み式、槽状式等の他の方法による工事兼本設桁5又は工事桁8若しくは本設桁9を用いる方法でもよい。   Furthermore, in all the above-described embodiments, the method of using the construction and permanent girder 5 or the construction girder 8 or the permanent girder 9 by the track receiving type has been described. However, the present invention is not limited to this. Alternatively, a method using the construction and permanent girder 5 or the construction girder 8 or the permanent girder 9 by other methods such as a holding type and a tank type may be used.

本発明の第一実施形態に係る工事兼本設桁の設置状態を示す平面図である。It is a top view which shows the installation state of the construction and permanent installation girder which concerns on 1st embodiment of this invention. 図1のA−A’断面図である。It is A-A 'sectional drawing of FIG. 図1のB−B’断面図である。It is B-B 'sectional drawing of FIG. 本発明の第一実施形態に係るシールド機を用いた下りアプローチ区間の構築方法を示す図である。It is a figure which shows the construction method of the down approach area using the shield machine which concerns on 1st embodiment of this invention. 本発明の第一実施形態に係るシールド機を用いたアンダーパス区間の構築方法を示す図である。It is a figure which shows the construction method of the underpass area using the shield machine which concerns on 1st embodiment of this invention. 図5のC−C’矢視図である。FIG. 6 is a C-C ′ arrow view of FIG. 5. 本発明の第一実施形態に係るシールド機が通過した後のアンダーパス区間の横断方向断面図である。It is a transverse direction sectional view of the underpass section after the shield machine concerning a first embodiment of the present invention passes. 本発明の第一実施形態に係るシールド機を用いた上りアプローチ区間の構築方法を示す図である。It is a figure which shows the construction method of the up approach area using the shield machine which concerns on 1st embodiment of this invention. 本発明の第一実施形態に係るアンダーパス区間の断面図である。It is sectional drawing of the underpass area which concerns on 1st embodiment of this invention. 本発明の第一実施形態に係る地下構造物の構築工法にて構築したトンネルを示す図である。It is a figure which shows the tunnel constructed | assembled with the construction method of the underground structure which concerns on 1st embodiment of this invention. 本発明の第一実施形態に係る地下構造物の構築工法にて構築したトンネルとレールとの交差部を示す平面図である。It is a top view which shows the cross | intersection part of the tunnel and rail constructed | assembled with the construction method of the underground structure which concerns on 1st embodiment of this invention. 本発明の第二実施形態に係る工事桁の設置状態を示す断面図である。It is sectional drawing which shows the installation state of the construction girder which concerns on 2nd embodiment of this invention. 本発明の第二実施形態に係るシールド機を用いた下りアプローチ区間の構築方法を示す図である。It is a figure which shows the construction method of the downward approach area using the shield machine which concerns on 2nd embodiment of this invention. 本発明の第二実施形態に係るシールド機を用いたアンダーパス区間の構築方法を示す図である。It is a figure which shows the construction method of the underpass area using the shield machine which concerns on 2nd embodiment of this invention. 本発明の第二実施形態に係るシールド機が通過した後のアンダーパス区間の横断方向断面図である。It is a transverse direction sectional view of the underpass section after the shield machine concerning a second embodiment of the present invention passes. 本発明の第二実施形態に係るシールド機を用いた上りアプローチ区間の構築方法を示す図である。It is a figure which shows the construction method of the up approach area using the shield machine which concerns on 2nd embodiment of this invention. 本発明の第二実施形態に係るアンダーパス区間の横断方向断面図である。It is a transverse direction sectional view of an underpass section concerning a second embodiment of the present invention. 本発明の第二実施形態に係る地下構造物の構築工法にて構築したトンネルを示す図である。It is a figure which shows the tunnel constructed | assembled with the construction method of the underground structure which concerns on 2nd embodiment of this invention. 従来の全線開削工法の実施例を示す図である。It is a figure which shows the Example of the conventional full wire cutting method. 従来の部分開削工法の実施例を示す図である。It is a figure which shows the Example of the conventional partial cutting method.

符号の説明Explanation of symbols

1 レール 2 支持杭
4 架台 5 工事兼本設桁
5a 本設部 5b 仮設部
6 支承 6a 積層ゴム
6b 無収縮モルタル 8 工事桁
9 本設桁 10 シールド機
11 トンネル 12 下りアプローチ区間
13 アンダーパス区間 14 上りアプローチ区間
15 地上発進部 16 地上到達部
17 カッターヘッド 18 掘削室内
19 排土装置 20 U型構造物
22 パラペット 23 道路橋
31 トンネル 33 アンダーパス区間
100 地下構造物 101 支持杭
102 工事桁 103 土留め杭
104 地下構造物 105 パイプルーフ
106 作業空間
DESCRIPTION OF SYMBOLS 1 Rail 2 Support pile 4 Mount 5 Construction and permanent girder 5a Main part 5b Temporary part 6 Support 6a Laminated rubber 6b Non-shrink mortar 8 Construction girder 9 Main girder 10 Shield machine 11 Tunnel 12 Down approach section 13 Underpass section 14 Uphill approach section 15 Ground start section 16 Ground reach section 17 Cutter head 18 Excavation chamber 19 Earth removal device 20 U-shaped structure 22 Parapet 23 Road bridge 31 Tunnel 33 Underpass section 100 Underground structure 101 Support pile 102 Construction girder 103 Earth retaining Pile 104 Underground structure 105 Pipe roof 106 Work space

Claims (5)

既存の鉄道線路、道路等の車両軌道をアンダーパスするアンダーパス構造物を構築するための地下構造物の構築工法であって、
前記車両軌道を工事桁にて支持し、
シールド機にて前記車両軌道の下方にトンネルを掘削してセグメントを設置することによりトンネル部構造物を構築し、
前記工事桁を前記トンネル部構造物にて支持し、
前記工事桁を撤去し、本設桁を設置することにより前記アンダーパス構造物を構成することを特徴とする地下構造物の構築工法。
An underground structure construction method for constructing an underpass structure that underpasses a vehicle track such as an existing railway track or road,
Support the vehicle track with a construction girder,
By constructing a tunnel structure by excavating a tunnel below the vehicle track with a shield machine and installing a segment,
Support the construction girder with the tunnel structure,
A construction method for an underground structure, wherein the underpass structure is configured by removing the construction girder and installing a main girder.
既存の鉄道線路、道路等の車両軌道をアンダーパスするアンダーパス構造物を構築するための地下構造物の構築工法であって、
前記車両軌道を工事桁にて支持し、
シールド機を地上部から発進させて、所定の下り勾配を有する下りアプローチ区間を構築し、
前記下りアプローチ区間の終点部から、セグメントを設置することにより前記工事桁をトンネル部構造物にて支持するアンダーパス区間を構築し、
前記アンダーパス区間の終点部から、所定の上り勾配を有する上りアプローチ区間を構築し、
前記シールド機を地上に到達させ、
前記工事桁を撤去し、本設桁を設置することにより前記アンダーパス構造物を構成することを特徴とする地下構造物の構築工法。
An underground structure construction method for constructing an underpass structure that underpasses a vehicle track such as an existing railway track or road,
Support the vehicle track with a construction girder,
Start the shield machine from the ground, build a down approach section with a predetermined down slope,
By constructing an underpass section that supports the construction girder with a tunnel structure by installing a segment from the end point of the downward approach section,
From the end point of the underpass section, construct an up approach section having a predetermined up slope,
Let the shield machine reach the ground,
A construction method for an underground structure, wherein the underpass structure is configured by removing the construction girder and installing a main girder.
前記セグメントを略U型に設置することにより略U型の前記トンネル部構造物を構築し、前記本設桁を上床板、該略U型のトンネル部構造物を壁・下床板とする前記アンダーパス構造物を構成することを特徴とする請求項1又は2に記載の地下構造物の構築工法。   By constructing the substantially U-shaped tunnel part structure by installing the segments in a substantially U shape, the undersole is configured such that the main girder is an upper floor board and the substantially U-shaped tunnel part structure is a wall / lower floor board. The construction method of an underground structure according to claim 1 or 2, wherein a path structure is formed. 前記上りアプローチ区間及び前記下りアプローチ区間は、掘削部分が地上に開放された半地中部を備えることを特徴とする請求項2に記載の地下構造物の構築工法。   The construction method for an underground structure according to claim 2, wherein the ascending approach section and the descending approach section include a semi-ground part whose excavation part is open to the ground. 前記半地中部のセグメントは、環状又は矩形状に配置され、後に一部が撤去されて略U型に構築されることを特徴とする請求項4に記載の地下構造物の構築工法。   5. The construction method for an underground structure according to claim 4, wherein the semi-ground middle segment is arranged in an annular shape or a rectangular shape, and a part of the segment is removed later and is constructed in a substantially U shape.
JP2005176992A 2005-06-16 2005-06-16 Construction method for underground structures Expired - Fee Related JP5167578B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2005176992A JP5167578B2 (en) 2005-06-16 2005-06-16 Construction method for underground structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2005176992A JP5167578B2 (en) 2005-06-16 2005-06-16 Construction method for underground structures

Publications (2)

Publication Number Publication Date
JP2006348612A JP2006348612A (en) 2006-12-28
JP5167578B2 true JP5167578B2 (en) 2013-03-21

Family

ID=37644739

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2005176992A Expired - Fee Related JP5167578B2 (en) 2005-06-16 2005-06-16 Construction method for underground structures

Country Status (1)

Country Link
JP (1) JP5167578B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106285715B (en) * 2016-10-26 2018-06-08 中铁十一局集团城市轨道工程有限公司 Closely the construction method of first branch bored tunnel is worn in side to balancing earth-pressure shielding machine

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4148607B2 (en) * 1999-09-03 2008-09-10 東日本旅客鉄道株式会社 Construction method of underground structure using floor girder for construction girder
JP4136959B2 (en) * 2003-02-12 2008-08-20 鉄建建設株式会社 "How to build underground structures and installation girder"
JP4185401B2 (en) * 2003-05-23 2008-11-26 大成建設株式会社 Construction method of large section tunnel using divided box
JP4309219B2 (en) * 2003-09-30 2009-08-05 大成建設株式会社 Tunnel construction method
JP4233428B2 (en) * 2003-10-10 2009-03-04 株式会社大林組 Segment assembly equipment

Also Published As

Publication number Publication date
JP2006348612A (en) 2006-12-28

Similar Documents

Publication Publication Date Title
JP2008095293A (en) Method of constructing underground structure
JP2006322222A (en) Construction method of large-sectional tunnel
JP6186267B2 (en) How to build an underground tunnel
KR101206860B1 (en) Excavation tunnel constructing method using vertical side wall and arch ceiling
KR100898969B1 (en) Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof
JP3893056B2 (en) Construction method of underground structure
KR100784201B1 (en) Method for construction of tunnel
JP2002138561A (en) Structure and method for construction of box culvert
JP4888725B2 (en) Tunnel construction method
JP4104781B2 (en) Construction method of underground joint structure
JP5167578B2 (en) Construction method for underground structures
JP4303512B2 (en) Construction method of large section tunnel
JP2007126936A (en) Semisubterranean road and its construction method
JP5012149B2 (en) Ground support structure and ground support method
JP2005002671A (en) Underpinning method and viaduct
JP3910135B2 (en) Building construction method and beam member used therefor
JP4303511B2 (en) Construction method of large section tunnel
JP4705467B2 (en) Construction method of underground structure
JP2006257743A (en) Soil cement column wall, soil cement wall pile, soil cement structure, and foundation structure
JP6276300B2 (en) Open shield method
JP5073960B2 (en) Construction method of underground structure and underground structure
KR100443819B1 (en) Underway Tunneling Methods of arch typed Triangle Elementary pipe-roof
JP2006348472A (en) Width expanding construction method for existing underground tunnel
KR100833700B1 (en) Pipe roof structures
JP2006265827A (en) Construction method for underground penetration body, and steel-shell element therefor

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20080520

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20100405

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20110524

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20110721

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20120508

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20120703

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20120731

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20121022

A911 Transfer of reconsideration by examiner before appeal (zenchi)

Free format text: JAPANESE INTERMEDIATE CODE: A911

Effective date: 20121030

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20121127

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20121210

LAPS Cancellation because of no payment of annual fees