JP2004308225A - Work method and overhead bypass road - Google Patents

Work method and overhead bypass road Download PDF

Info

Publication number
JP2004308225A
JP2004308225A JP2003102507A JP2003102507A JP2004308225A JP 2004308225 A JP2004308225 A JP 2004308225A JP 2003102507 A JP2003102507 A JP 2003102507A JP 2003102507 A JP2003102507 A JP 2003102507A JP 2004308225 A JP2004308225 A JP 2004308225A
Authority
JP
Japan
Prior art keywords
elevated
detour
construction
bridge
section
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP2003102507A
Other languages
Japanese (ja)
Other versions
JP4263935B2 (en
Inventor
Yasuo Nishida
泰夫 西田
Mitsuhiko Ota
光彦 太田
Yoshio Koizumi
儀生 小泉
Nobuaki Kobayashi
信明 小林
Kazuyoshi Kasakura
和義 笠倉
Yukio Yoshikawa
幸夫 吉川
Shingo Hisamatsu
新吾 久松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Hirose and Co Ltd
Original Assignee
Taisei Corp
Hirose and Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp, Hirose and Co Ltd filed Critical Taisei Corp
Priority to JP2003102507A priority Critical patent/JP4263935B2/en
Publication of JP2004308225A publication Critical patent/JP2004308225A/en
Application granted granted Critical
Publication of JP4263935B2 publication Critical patent/JP4263935B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

<P>PROBLEM TO BE SOLVED: To provide a work method for performing temporary work and regular work without performing large traffic regulation to a vehicle passing through an existing traffic road; and to propose an overhead bypass road for largely restraining the traffic regulation at temporary work in the work method using an overhead traffic road. <P>SOLUTION: After continuously arranging a plurality of bridge girders 11 and 21 in the air of a work section R3 arranged in the road R1, the bridge beam 21 is lowered, and communicated with the road R1. After automobiles S are bypassed on the plurality of bridge girders 11 and 21, the regular work is performed in the work section R3. After becoming passable through the work section R3, the lowered bridge girders 21 is lifted, and the automobiles S are passed through the work section R3. <P>COPYRIGHT: (C)2005,JPO&NCIPI

Description

【0001】
【発明の属する技術分野】
本発明は、既設交通路で工事を行う際の工事方法および高架式迂回路に関する。
【0002】
【従来の技術】
道路や鉄道などの既設交通路を補修する場合や既設交通路下に地中構造物を構築する場合など、既設交通路で工事を行う場合には、工事に必要なスペースを確保するとともに、工事に伴う交通渋滞を避けるために、当該工事区間を通行する車両等を迂回させる必要がある。
【0003】
ところが、建物が密集した都市部などでは、迂回路用の用地を確保することが非常に困難な状況にある。このような問題を打開する方策の一つとして、既設交通路上に仮設の高架橋(以下、「高架式迂回路」という)を構築し、当該高架式迂回路に車両等を迂回させたうえで、本工事を行う工事方法が知られている(例えば、特許文献1参照)。
【0004】
【特許文献1】
特開平5−247913号公報(図1)
【0005】
【発明が解決しようとする課題】
ところが、高架式迂回路を構築あるいは解体する仮設工事に長期間を要してしまうことが少なくない。つまり、高架式迂回路により本工事中の交通渋滞等を大幅に緩和することができるが、その一方で、仮設工事に伴う交通渋滞が発生してしまう。
【0006】
特に、既設交通路から高架部へ至るアプローチ部を構築あるいは解体している間は、建築限界等の問題から当該アプローチ部の下方に車両等を通行させることができないため、大幅な交通規制を余儀なくされてしまう。
【0007】
そこで、本発明は、高架式交通路を用いた工事方法であって、既設交通路を通行する車両等に大幅な交通規制を実施することなく仮設工事および本工事を行うことができる工事方法を提供することを課題とし、さらには、仮設工事中の交通規制を大幅に抑制することができる高架式迂回路を提案することを課題とする。
【0008】
【課題を解決するための手段】
このような課題を解決するために、請求項1に記載された発明は、既設交通路に設けられた工事区間上に高架式迂回路を構築し、当該高架式迂回路上に交通を迂回させたうえで、前記工事区間で本工事を行い、前記工事区間が通行可能となった後に、前記高架式迂回路の一部または総てを上昇させて前記高架式迂回路下の建築限界を確保することを特徴とする工事方法である。
【0009】
かかる工事方法によると、車両や人等の交通(以下、車両等という)が往行する既設交通路において工事を行う場合に、既設交通路を通行する車両等に大幅な交通規制を実施することなく本工事を行うことができる。そして、本工事が進捗して当該工事区間が通行可能な状態となった段階で、高架式迂回路の一部または総てを上昇させて当該高架式迂回路下の建築限界を確保することで、高架式迂回路の解体を待たずに直ちに当該工事区間に車両等を通行させることが可能となり、その結果、高架式迂回路の解体作業に伴う交通規制を大幅に抑制することができる。
【0010】
請求項2に記載された発明は、既設交通路に設けられた工事区間の上空に複数の橋桁の一部または総てを連設する仮設工事工程と、前記複数の橋桁を設置して前記既設交通路と連通し、前記複数の橋桁上に交通を迂回させる橋桁設置工程と、前記工事区間で本工事を行う本工事工程と、前記工事区間が通行可能となった後に、設置した前記橋桁を上昇させる橋桁上昇工程とを含むことを特徴とする工事方法である。
【0011】
かかる工事方法は、既設交通路に設けられた工事区間の上空に複数の橋桁を連設した後に、前記複数の橋桁を設置して前記既設交通路と連通し、前記複数の橋桁上に車両等を迂回させたうえで、前記工事区間で本工事を行い、前記工事区間が通行可能となった後に、設置した前記橋桁を上昇させ、前記工事区間に車両等を通行させるものであり、この工事方法によると、車両等が往行する既設交通路において工事を行う場合に、既設交通路を通行する車両等に大幅な交通規制を実施することなく仮設工事および本工事を行うことができる。すなわち、高架式迂回路を構成する複数の橋桁の総てを工事区間の上空に構築できるので、当該高架式迂回路の供用を開始する直前までその下方に車両等を通行させることもできる。そして、複数の橋桁が高架式迂回路として機能するようにそれらの一部または総てを所定の位置に設置すれば直ちに高架式迂回路(複数の橋桁)上に車両等を通行させることができ、さらに、本工事が進捗して当該工事区間が通行可能な状態となった段階で、これらを上昇させれば、高架式迂回路の解体を待たずに直ちに当該工事区間に車両等を通行させることができる。
【0012】
請求項3に記載された発明は、請求項2に記載の工事方法であって、前記仮設工事工程は、前記既設交通路に左右一対の擁壁を構築することを含み、前記橋桁設置工程は、前記擁壁間を盛土して前記橋桁と前記既設交通路とを擦り付けることを含み、前記橋桁上昇工程は、前記擁壁間の盛土を撤去することを含むことを特徴とする。
【0013】
かかる工事方法は、予め既設交通路に構築しておいた左右一対の擁壁間を盛土することにより、降下させた橋桁と既設交通路とを擦り付けるものである。このようにすると、既設交通路を通行する車両等に対する交通規制をより一層削減することができる。なお、擁壁は、現場打ち、プレキャストのどちらであってもよく、重力式擁壁、L型擁壁、逆T擁壁などのほか、地中連続壁や橋脚列の山留であっても差し支えない。また、この擁壁を本体構造物として利用しても差し支えない。
【0014】
請求項4に記載された発明は、既設交通路に設けられた工事区間の交通を迂回させるための高架式迂回路であって、工事区間の上空に構築されるアプローチ部を有し、当該アプローチ部は、前記工事区間の上空に連設された複数の橋桁からなり、当該複数の橋桁は、それぞれ前記工事区間に構築された橋脚に昇降可能に支持されていることを特徴とする。
【0015】
かかる高架式迂回路は、工事区間の上空に多径間に亘って構築されたアプローチ部を降下させて既設交通路と連通させると、工事区間を迂回する迂回路となる。すなわち、当該高架式迂回路の供用を開始する直前までアプローチ部の下方に車両等を通行させることもでき、アプローチ部全体を降下させれば直ちに高架式迂回路に車両等を通行させることができる。また、本工事が進捗して当該工事区間が通行可能な状態となった段階で、アプローチ部を上昇させれば、高架式迂回路の解体を待たずに直ちに当該工事区間に車両等を通行させることができる。すなわち、車両等が往行する既設交通路において工事を行う場合に、既設交通路を通行する車両等に大幅な交通規制を実施することなく仮設工事および本工事を行うことができる。なお、アプローチ部を構成する複数の橋桁は、所定の勾配で傾斜させた状態で連設されたものであってもよく、あるいは、水平に連設されたものであってもよい。複数の橋桁を水平に連設した場合には、各橋桁を所定の勾配に傾斜させつつ降下させ、水平に戻しつつ上昇させることになる。
【0016】
請求項5に記載された発明は、請求項4に記載の高架式迂回路であって、前記各橋桁は、その両端のそれぞれが昇降可能に支持されていることを特徴とする。
【0017】
かかる高架式迂回路によると、橋桁の両端のそれぞれが昇降可能に支持されているので、橋桁の勾配を調節することができる。すなわち、橋桁を昇降させる際に、その一端の昇降量と他端の昇降量とに差をつければ容易に橋桁の勾配を調節することができる。例えば、水平に架設された橋桁を所定の勾配で傾斜させつつ降下させることができる。
【0018】
請求項6に記載された発明は、請求項5に記載の高架式迂回路であって、隣り合う前記橋桁の端部同士が伸縮自在な連結器により連結されていることを特徴とする。
【0019】
かかる高架式迂回路によると、連結器により隣り合う橋桁の端部間の離隔距離を適切な状態に保つことができるので、多径間に亘るアプローチ部全体を一括して昇降させることができる。
【0020】
請求項7に記載された発明は、請求項4乃至請求項6のいずれか一項に記載の高架式迂回路であって、前記各橋脚の上端に昇降装置が設けられており、前記各橋桁は、前記昇降装置に吊り下げられていることを特徴とする。
【0021】
かかる高架式迂回路によると、橋脚に設けられた昇降装置を適宜操作することで、橋桁を昇降させることができる。すなわち、橋桁を昇降させる際に、ホイールクレーンやジャッキを搭載した特殊車両を準備する必要がない。
【0022】
請求項8に記載された発明は、請求項4乃至請求項7のいずれか一項に記載の高架式迂回路であって、前記各橋脚に、降下させた状態の前記橋桁を支持する支持部が設けてあることを特徴とする。
【0023】
かかる高架式迂回路によると、各橋脚の所定の位置に予め支持部が設けられているので、降下時において橋桁の位置決めが容易になる。
【0024】
請求項9に記載された発明は、請求項4乃至請求項8のいずれか一項に記載の高架式迂回路であって、前記各橋脚は、橋軸直角方向に所定の間隔をあけて配置された左右一対の支柱からなることを特徴とする。
【0025】
かかる高架式迂回路によると、左右一対の支柱を橋脚としたので、高架式迂回路の工事期間中など、一般の車両が工事区間(高架式迂回路の下方)を通行する場合に、当該橋脚により交通の流れが阻害されることがない。
【0026】
請求項10に記載の高架式迂回路は、請求項4乃至請求項9のいずれか一項に記載の高架式迂回路前記アプローチ部と前記既設交通路とを連通させる摺付部をさらに有し、当該摺付部は、前記工事区間に配置された左右一対の擁壁を備えていることを特徴とする。
【0027】
かかる高架式迂回路によると、擁壁間を盛土することにより、当該アプローチ部と既設交通路とを容易に摺り付けることができる。なお、擁壁は、現場打ち、プレキャストのどちらであってもよく、重力式擁壁、L型擁壁、逆T擁壁などのほか、地中連続壁や橋脚列の山留であっても差し支えない。また、この擁壁を本体構造物として利用しても差し支えない。
【0028】
【発明の実施の形態】
以下、本発明の実施の形態を添付した図面を参照して詳細に説明する。
【0029】
本発明に係る工事方法は、図1に示すように、道路R1に設けられた工事区間R3の上空に高架式迂回路Uを構築した後に、この高架式迂回路Uの一部を降下させて道路R1と連通し(図6参照)、高架式迂回路U上に自動車Sを迂回させたうえで、工事区間R3で本工事を行い、工事区間R3が通行可能となった後に、この高架式迂回路Uの降下させた部分を上昇させ(図8参照)、工事区間R3に自動車Sを通行させるものである。
【0030】
なお、本実施形態では、図10(a)(b)に示すように、平面交差する道路R1,R2の一方を地下化する場合であって、道路R1に設けた工事区間R3において断面略矩形形状を呈するボックスカルバート70および断面略U字形状を呈する掘割構造物80を構築する工事(本工事)を行う場合を例示するが、既設交通路の種類(道路、鉄道など)、交通の種類(自動車、電車、人など)や本工事の種類は、これに限定されることがないのはいうまでもない。
【0031】
[高架式迂回路]
まず、高架式迂回路Uについて説明する。高架式迂回路Uは、図1に示すように、工事区間R3の上空に構築される高架部10およびアプローチ部20と、道路R1に構築される摺付部30とを備えている。なお、アプローチ部20および摺付部30は、高架部10の橋軸方向の両側に配置される。
【0032】
(高架部)
高架部10は、図1に示すように、工事区間R3の上空に連設された複数の橋桁11(以下、「固定橋桁11」という)を備えている。なお、固定橋桁11の設置高さは、工事期間中に変化することはない。
【0033】
固定橋桁11には、本実施形態では、交差点R4を跨ぐ長スパンのものと、その橋軸方向の両側に配置された短スパンのものとがある。長スパンの固定橋桁11は、交差点R4を挟んで対向する第一橋脚40,40間に架設されており、短スパンの固定橋桁11は、第一橋脚40と第二橋脚50との間、あるいは、第二橋脚50と第三橋脚60との間に架設されている。なお、固定橋桁11およびその橋脚40,50の構造形式、材質等は特に制限されるものではなく、施工条件等に合わせて適宜なものを選定することができる。
【0034】
第一橋脚40および第二橋脚50は、本実施形態では、おおよそ同一の構成であるので、以下では、第一橋脚40について説明する。第一橋脚40は、図2(a)に示すように、橋軸直角方向に所定の間隔をあけて配置された左右一対の支柱41,41と、これらを連結する横材41bとからなる。
【0035】
支柱41は、図1に示すように、橋軸方向に所定の間隔をあけて連設した複数の支持杭41aからなる柱列を複数の横材41cで一体にしたものである。支持杭41aは、図2(a)に示すように、ボックスカルバート70の床付面よりもさらに下方にある支持層まで打ち込まれている。
【0036】
(アプローチ部)
アプローチ部20は、図1に示すように、工事区間R3の上空に略水平に連設された複数(本実施形態では四つ)の橋桁21(以下、「可動橋桁21」という)を備えている。
【0037】
可動橋桁21は、図3に示すように、橋軸方向に隣り合う第三橋脚60,60に昇降可能に架設されている。本実施形態では、図4に示すように、一対の受桁22,22と、この受桁22,22間に架設された左右一対のトラス架構23,23と、このトラス架構23,23同士を連結する複数の横桁24と、横桁24上に覆設される複数の覆工板25とから構成されている。また、図5(a)に示すように、トラス架構23と受桁22との間は、ピン沓23aと上下方向に伸縮自在な可動沓23bとが橋軸方向に並んで介設されている。ここで、ピン沓23aは、供用時に可動沓に変更可能な構成であってもよい。
【0038】
受桁22は、図5(c)に示すように、本実施形態では、一対のH鋼22a,22aを複数の連結材22bで連結してなる梁部22Aと、この梁部22Aの端部に突設されたガイド部22Bとを備えており、梁部22Aの両端部には、ピン沓23aおよび可動沓23bが固定されている。また、図5(b)に示すように、ガイド部22Bには、吊具22c,22cが固定されており、吊具22c,22cには、第三橋脚60の上端に設けられた昇降装置62(図5(a)参照)から垂下する線状部材62aの下端が接続されている。すなわち、可動橋桁21は、受桁22,22を介して昇降装置62に吊り下げられていることになる。
【0039】
なお、可動橋桁21の構造形式や材質等は、図示のものに限定されることはなく、施工条件や荷重条件などに応じて適宜なものを選定することができる。
【0040】
第三橋脚60は、図2(b)に示すように、工事区間R3において橋軸直角方向に所定の間隔をあけて配置された左右一対の支柱61,61からなり、その上端は、可動橋桁21の上方に位置している。
【0041】
支柱61は、図3に示すように、橋軸方向に所定の間隔をあけて連設された四つの柱材61aからなる柱列の上端を横材61dで連結したものである。なお、図1に示すように、摺付部30との境界に位置する第三橋脚60の支柱61’は、二つの柱材61aからなる。
【0042】
柱材61aは、図3に示すように、地中連続壁91(図2(b)参照)を構成する芯材91aに立設固定されている。なお、芯材91aは、支持層まで貫入させておくものとする。また、図2(b)に示すように、柱材61aには、上昇させた状態の可動橋桁21の受桁22が載置される仮受部61cと、降下させた状態の可動橋桁21の受桁22が載置される支持部61bとが設けてある。なお、仮受部61cは、可動橋桁21が仮受部61cに載置されているときに、可動橋桁21の下方に建築限界を確保することができるような高さに設置される。また、可動橋桁21が仮受部61cあるいは支持部61bに支持されているときは、結果として受桁22と左右一対の支柱61,61(柱材61a,61a)とによりラーメン構造が形成されることになる。
【0043】
また、図5(c)に示すように、隣り合う柱材61a,61aの橋軸方向の間隔は、受桁22のガイド部22Bよりも大きい。すなわち、ガイド部22Bは、隣り合う柱材61a,61a間を上下に移動可能である。
【0044】
なお、地中連続壁91(図2(b)参照)が構築されない区間では、支持杭61e(図1参照)を打ち込み、この支持杭61eの上端に柱材61aを立設固定する。
【0045】
また、図3に示すように、四つの柱材61aの上端を連結する横材61dには、昇降装置62,62が固定されている。
【0046】
昇降装置62は、受桁22のガイド部22B(図5(c)参照)の真上に位置している。すなわち、一の受桁22に対して二つの昇降装置62が配置されることになる。また、昇降装置62からワイヤーや鋼棒など線状部材62aが垂下しており、その下端が受桁22の吊具22c(図5(a)(b)参照)に接続されている。そして、四つの昇降装置62を適宜操作すると可動橋桁21が昇降することになり、さらに、一の可動橋桁21において、その一方の受桁22の昇降量と他方の受桁22の昇降量とに差をつけると、可動橋桁21が傾斜することになる。
【0047】
また、図5(a)に示すように、隣り合う可動橋桁21,21の受桁22,22同士が伸縮自在な連結器26により連結されている。連結器26には、例えば、ジャッキを用いることができる。
【0048】
(摺付部)
摺付部30は、図1に示すように、アプローチ部20と道路R1との間に設けられており、図2(c)に示すように、工事区間R3に配置された左右一対の擁壁31,31を備えている。そして、アプローチ部20を降下させる直前もしくは降下させた直後に擁壁31,31間を盛土することにより、降下させたアプローチ部20と道路R1とが擦り付けられることになる。
【0049】
擁壁31は、図2(c)に示すように、本実施形態では、逆T型であり、その高欄部の土留31aのみが地上に突出し、その他の部位は、地中に埋設されている。なお、最終的には、擁壁31,31間は、掘り下げられることになる。また、擁壁31の構造形式等は、図示のものに限定されることはなく、施工条件に合わせて適宜変更してもよい。
【0050】
[工事方法]
次に、高架式迂回路Uを利用した工事方法について説明する。この工事方法は、図6に示すように、道路R1に設けられた工事区間R3上に高架式迂回路Uを構築し、この高架式迂回路U上に自動車Sを迂回させたうえで、工事区間Rで本工事を行い、工事区間R3が通行可能となった後に、高架式迂回路Uの一部または総てを上昇させて高架式迂回路U下の建築限界を確保するものである(図8参照)。すなわち、高架式迂回路Uを構成する複数の橋桁(固定橋桁11および可動橋桁21)の総てを工事区間R3の上空に連設しておき、その後、これらが高架式迂回路Uとして機能するようにその一部の橋桁(アプローチ部20の可動橋桁21)を所定の位置に設置して(降下させて)道路R1と連通し、これら複数の橋桁11,21上に自動車Sを迂回させたうえで、工事区間R3で本工事を行い、工事区間R3が通行可能となった後に、設置した(降下させた)可動橋桁21を上昇させて高架式迂回路U下の建築限界を確保するものである。以下、各工程を詳細に説明する。
【0051】
(仮設工事工程)
まず、図2(a)(b)に示すように、ボックスカルバート70および掘割構造物80を構築する際の土留となる土留壁90を構築する。なお、土留壁90の構造・形式は、土質条件等に合わせて適宜変更しても差し支えない。本実施形態の土留壁90には、ソイルミキシングウォール(SMW)工法により構築された地中連続壁91(図2(a)(b)参照)と、鋼矢板工法により構築された鋼矢板92(図2(c)参照)とがある。本実施形態では、掘削深さが比較的大きい区間に地中連続壁91を構築し(図2(a)(b)参照)、掘削深さが比較的浅い区間に鋼矢板92を構築する(図2(c)参照)。
【0052】
次に、図1に示すように、工事区間R3の所定の位置で支持杭41aを複数本打ち込んで第一橋脚40を構築するとともに、支持杭51aを複数本打ち込んで第二橋脚50を構築する。また、地中連続壁91(図2(b)参照)が構築された区間にあっては、局所的に長くした地中連続壁91の芯材91aの上端に柱材61aを立設固定し、鋼矢板92(図2(c)参照)が構築された区間にあっては、支持杭61eを複数本打ち込んだうえで、その支持杭の上端に柱材61aを立設固定し、さらに、複数の柱材61aの上端を横材61dで連結するとともに、横材61dの上面に昇降装置62,62を固定して第三橋脚60を構築する。
【0053】
ここで、図2(a)に示すように、第一橋脚40は、橋軸直角方向に所定の間隔をあけて立設された左右一対の支柱41,41により構成されているので、この支柱41,41間に自動車Sを通行させることが可能であり、当該空間を右折車線等に利用することもできる。すなわち、第一橋脚40を構築しても、交通の流れが阻害されることがない。第二橋脚50および第三橋脚60についても同様である。
【0054】
続いて、図1に示すように、第一橋脚40、第二橋脚50および第三橋脚60に固定橋桁11および可動橋桁21を架設して高架部10およびアプローチ部20を構築する。すなわち、道路R1に設けられた工事区間R3の上空に複数の橋桁11,21を連設して高架部10およびアプローチ部20を構築する。
【0055】
固定橋桁11および可動橋桁21は、クローラクレーンやジャッキを装備した重機等を用いて架設することができるが、可動橋桁21については、第三橋脚60の上端に設けられた昇降装置62を利用して架設してもよい。
【0056】
このとき、高架部10では、高架式迂回路Uの縦断線形に沿って固定橋桁11を架設し、アプローチ部20では、建築限界を確保することができる高さに可動橋桁21を水平に架設する。
【0057】
ここで、可動橋桁21は、図2(b)に示すように、支柱61に設けた仮受部61cに載置されるが、かかる状態のときは、可動橋桁21の下方に建築限界が確保されるので、可動橋桁21の下方に自動車Sを通行させることができる。
【0058】
また、図2(c)に示すように、アプローチ部20と摺付部30との境界付近(図1参照)を先行的に掘り下げて擁壁31を構築し、その後、再び地表面まで埋め戻しておく。
【0059】
(橋桁設置工程)
次に、図6に示すように、複数の橋桁11,21のうち、アプローチ部20の可動橋桁21を一括して降下(傾斜)させるとともに、擁壁31,31(図7(c)参照)間を盛土して、アプローチ部20と道路R1とを連通し、高架式迂回路U上(複数の橋桁11,21上)に自動車Sを迂回させる。
【0060】
すなわち、図3に示すように、第三橋脚60に設けられた仮受部61c(図2(b)参照)を撤去したうえで、隣り合う可動橋桁21,21間の離隔距離を連結器26で調節しつつ、第三橋脚60に設けられた昇降装置62を操作して、多径間に亘る複数の可動橋桁21を一括して降下(傾斜)させる。より詳細には、隣り合う可動橋桁21,21の離隔距離を連結器26で所定の範囲内に納まるように適宜調節しつつ、各可動橋桁21において、その摺付部30側の端部(受桁22)の降下速度を高架部10側の端部(受桁22)の降下速度よりも大きくする。このとき、受桁22の両端が吊り下げられているので、安定した状態で可動橋桁21を降下させることができる。
【0061】
また、第三橋脚60には、図7(b)に示すように、降下させた状態の可動橋桁21の受桁22が載置される支持部61bが設けられているので、可動橋桁21の位置決めは、非常に容易である。しかも、結果として受桁22と左右一対の支柱61,61(柱材61a,61a)とによりラーメン構造が形成されることになるので、力学的にも優れている。
【0062】
また、第三橋脚60に設けた昇降装置62で可動橋桁21を降下させる構成であるので、ホイールクレーンやジャッキを搭載した特殊車両を準備する必要がない。
【0063】
なお、図7(c)に示すように、アプローチ部20と道路R1とは、可動橋桁21を降下させる直前もしくは降下させた直後に擁壁31,31の高欄部の土留31a,31a間を盛土することにより摺り付けられる。擁壁31は、本体構造物である掘割構造物80の摺付端部の擁壁に接続された土留であるため、その設置作業を簡易かつ安価に行うことが可能である。すなわち、作業の容易化および迅速化を図ることが可能であり、結果として道路R1を通行する自動車Sに対する交通規制をより一層削減することができる。
【0064】
(本工事工程)
続いて、工事区間R3で本工事を行う。本実施形態では、図7(a)に示すように、地中連続壁91,91間を所定の深さまで掘り下げつつ第一橋脚40の支柱41,41同士を横材41bで補強し、高架部10の下方においてボックスカルバート70を構築する。また、図7(b)に示すように、アプローチ部20の下方において、地中連続壁91,91間に切梁93を設置しつつ所定の深さまで掘り下げて掘割構造物80を構築する。
【0065】
このとき、高架式迂回路U下を作業スペースとして利用することができるので、作業効率がよい。
【0066】
その後、図9(a)に示すように、ボックスカルバート70の上面に受梁41dを設け、この受梁41dに第一橋脚40を受け替えたうえで、ボックスカルバート70内を貫通する支持杭41aおよび横材41b(図7(a)参照)を撤去して、ボックスカルバート70内を自動車Sが通行可能な状態にし、同様に、図9(b)に示すように、掘割構造物80内にある切梁93等(図7(b)参照)を撤去して、掘割構造物80内を自動車Sが通行可能な状態にする。すなわち、工事区間R3を通行可能な状態にする。
【0067】
(橋桁昇降工程)
工事区間R3が通行可能となったら、図8に示すように、降下させた可動橋桁21を上昇させるとともに、図9(c)に示すように、擁壁31,31の高欄部の土留31a,31a間の盛土を撤去し、さらに、擁壁31,31間を掘り下げて、工事区間R3に自動車Sを通行させる。
【0068】
可動橋桁21を上昇させるには、隣り合う可動橋桁21,21間の離隔距離を連結器26(図3参照)で調節しつつ、第三橋脚60に設けられた昇降装置62を適宜操作して、各可動橋桁21を水平に戻しつつ上方に移動させればよい。
【0069】
その後、図10(a)に示すように、高架式迂回路Uを撤去すると、交差点R4の立体交差化(道路R1の地下化)が完了する。
【0070】
このように、本実施形態に係る工事方法によると、自動車Sが往行する道路R1において工事を行う場合に、道路R1を通行する自動車Sに大幅な交通規制を実施することなく仮設工事および本工事を行うことができる。
【0071】
すなわち、この工事方法によると、図1に示すように、工事区間R3を迂回させるための高架式迂回路Uを構成する複数の橋桁11,21の総てを工事区間R3の上空に構築するので、図2(a)(b)に示すように、高架式迂回路Uの供用を開始する直前まで高架部10およびアプローチ部20の下方に自動車Sを通行させることができる。そして、図7(b)に示すように、可動橋桁21を降下させれば直ちに高架式迂回路Uに車両等を通行させることができ、さらに、本工事が進捗して工事区間R3(図8参照)が通行可能な状態となった段階で、これらを上昇させれば、図9(a)(b)(c)に示すように、高架式迂回路Uの解体を待たずに直ちに工事区間R3に自動車Sを通行させることができる。言い換えれば、工事を行う道路R1の幅員が狭く、平面的な迂回路では、十分な交通量を確保することが困難な場合であっても、工事区間R3に高架式迂回路Uを構築することで、工事区間R3の全区間に渡って必要な車線を確保することが可能となり、その結果、工事に伴う渋滞を大幅に抑制することが可能となる。
【0072】
また、施工者にとっても、十分な作業スペースを確保することが可能となるため、作業効率の向上を図ることができ、その結果、工期の短縮、工事費の削減を図ることが可能となる。
【0073】
なお、前記した実施形態では、複数の可動橋桁21の総てを同一高さにおいて水平に連設した場合を例示したが、これに限定されることはなく、例えば、図示は省略するが、予め所定の勾配で傾斜させた状態で連設してもよい。この場合には、各可動橋桁において昇降速度を変化させる必要がないので、施工管理が容易になる。
【0074】
また、前記した実施形態では、隣り合う可動橋桁21,21間に連結器26を配置したが、連結器26を省略してもよい。この場合、図示は省略するが、複数の可動橋桁のそれぞれを別個独立に昇降させることができる。
【0075】
また、前記した実施形態では、高架式迂回路Uのうち、アプローチ部20のみを昇降可能に構成したが、高架部10が昇降可能に構成されていても勿論よい。例えば、本工事が河川堤防の嵩上げに伴う鉄道軌条のレベルアップである場合など、本工事が完了したときに高架式迂回路Uの全体に亘ってその下方に建築限界が確保できない場合には、アプローチ部20のみならず高架部10をも上昇させて高架式迂回路U下の建築限界を確保することで、高架式迂回路Uの解体を待たずに直ちに工事区間に車両等を通行させることが可能となり、その結果、高架式迂回路Uの解体作業に伴う交通規制を大幅に抑制することができる。
【0076】
また、前記した実施形態では、高架部10のみならずアプローチ部20をも工事区間R3の上空に構築しておき、高架式迂回路U上へ自動車Sを迂回させる直前にアプローチ部20を降下させる工事方法を例示したが、これに限定されることはなく、例えば、高架式迂回路Uのうち、高架部10のみを工事区間R3の上空に構築しておき、高架式迂回路U上へ自動車Sを迂回させる直前にアプローチ部20を構成する可動橋桁21を急速施工により所定の勾配で架設して、道路R1と高架部10とを連通させても差し支えない。すなわち、高架式迂回路Uを構成する複数の橋桁(固定橋桁11および可動橋桁21)のうち、その一部の橋桁(高架部10の固定橋桁11)を工事区間R3の上空に連設しておき、その後、残りの橋桁(アプローチ部20の可動橋桁21)を所定の位置に急速施工により設置して道路R1と連通し、これら複数の橋桁11,21上に自動車Sを迂回させてもよい。
【0077】
また、図11に示すように、地中構造物100,110を併設する場合には、地中構造物100の上方に高架式迂回路U’を構築し、前記した工事方法により地中構造物100を構築した後に、高架式迂回路U’を地中構造物110の上空に移設し、同じく前記した工事方法により地中構造物110を構築すればよい。なお、地中構造物100,110を同時に構築しても差し支えなく、さらには、高架式迂回路U’,U’を併設しても差し支えない。
【0078】
以上では、本発明に係る高架式迂回路および工事方法を、道路R1を地下化する場合を例に詳細に説明したが、既設交通路で行う他の工事に適用することも勿論できる。例えば、詳細な説明は省略するが、既設道路の拡幅、補修、復旧工事を行う場合、老朽化した跨線橋や高架橋の架替工事を行う場合、鉄道の連続高架化工事を行う場合など様々な工事に本発明に係る高架式迂回路および工事方法を適用することができる。
【0079】
【発明の効果】
本発明に係る工事方法によると、既設交通路を通行する車両等に大幅な交通規制を実施することなく仮設工事および本工事を行うことができる。
【0080】
また、本発明に係る高架式迂回路によると、仮設工事および本工事中の交通規制を大幅に抑制することができる。さらに、施工者にとっても、広大な作業スペースを確保することができるので、工期短縮、施工費の削減を図ることができる。
【図面の簡単な説明】
【図1】本発明に係る工事方法および高架式迂回路を示す側面図である。
【図2】(a)は図1のX1−X1断面図、(b)は図1のX2−X2断面図、(c)は図1のX3−X3断面図である。
【図3】アプローチ部の橋桁を示す拡大側面図である。
【図4】アプローチ部の橋桁を示す拡大上面図である。
【図5】(a)は橋桁の端部を示す拡大側面図、(b)はアプローチ部の橋桁を示す端面図であって図4のY1−Y1矢視図、(c)は(b)のZ1−Z1矢視図である。
【図6】本発明に係る工事方法を説明する側面図であって、図1に続く工程を示す図である。
【図7】(a)は図6のX1−X1断面図、(b)は図6のX2−X2断面図、(c)は図6のX3−X3断面図である。
【図8】本発明に係る工事方法を説明する側面図であって、図6に続く工程を示す図である。
【図9】(a)は図8のX1−X1断面図、(b)は図8のX2−X2断面図、(c)は図8のX3−X3断面図である。
【図10】(a)は本発明に係る工事方法を説明する側面図であって、図8に続く工程を示す図、(b)は(a)の上面図である。
【図11】本発明に係る高架式迂回路の変形例を示す断面図である。
【符号の説明】
10 高架部
11 固定橋桁
20 アプローチ部
21 可動橋桁
22 受桁
26 連結器
30 摺付部
31 擁壁
31a 土留
40 第一橋脚
50 第二橋脚
60 第三橋脚
61 支柱
61a 柱材
61b 支持部
61c 仮受部
62 昇降装置
70 ボックスカルバート
80 掘割構造物
90 土留壁
R1,R2 道路
R3 工事区間
R4 交差点
S 自動車
U 高架式迂回路
[0001]
TECHNICAL FIELD OF THE INVENTION
The present invention relates to a construction method and an elevated detour when performing construction on an existing traffic route.
[0002]
[Prior art]
When performing construction on existing traffic routes, such as when repairing existing traffic routes such as roads and railways, or when constructing underground structures under existing traffic routes, secure the space necessary for construction and In order to avoid traffic congestion due to the above, it is necessary to detour vehicles and the like passing through the construction section.
[0003]
However, in an urban area where buildings are densely located, it is very difficult to secure a site for a detour. As one of the measures to solve such problems, a temporary viaduct (hereinafter referred to as “elevated detour”) is built on the existing traffic route, and vehicles and the like are detoured to the elevated detour, A construction method for performing this construction is known (for example, see Patent Document 1).
[0004]
[Patent Document 1]
JP-A-5-247913 (FIG. 1)
[0005]
[Problems to be solved by the invention]
However, it often takes a long time to construct or dismantle an elevated detour. That is, traffic congestion and the like during the main construction can be greatly reduced by the elevated detour, but on the other hand, traffic congestion due to temporary construction occurs.
[0006]
In particular, while constructing or disassembling the approach section from the existing traffic route to the elevated section, vehicles cannot be allowed to pass under the approach section due to problems such as building limits, so it is necessary to greatly restrict traffic. Will be done.
[0007]
Accordingly, the present invention provides a construction method using an elevated traffic route, which is capable of performing a temporary construction and a main construction without implementing a significant traffic regulation on vehicles or the like passing through an existing traffic route. It is another object of the present invention to provide an elevated detour that can significantly suppress traffic regulation during temporary construction.
[0008]
[Means for Solving the Problems]
In order to solve such a problem, the invention described in claim 1 constructs an elevated detour on a construction section provided on an existing traffic route and diverts traffic on the elevated detour. Above, the main construction is performed in the construction section, and after the construction section is allowed to pass, a part or all of the elevated detour is raised to secure a building limit under the elevated detour. It is a construction method characterized by the following.
[0009]
According to this construction method, when carrying out construction on an existing traffic route where traffic of vehicles, people, etc. (hereinafter referred to as vehicles, etc.) goes, significant traffic regulations will be imposed on vehicles, etc. that pass through the existing traffic route. Without the need for this work. Then, when this construction progresses and the construction section is in a passable state, by raising a part or all of the elevated detour to secure the building limit under the elevated detour In addition, it becomes possible to immediately pass vehicles and the like through the construction section without waiting for dismantling of the elevated detour, and as a result, it is possible to significantly suppress traffic regulation accompanying dismantling work of the elevated detour.
[0010]
The invention described in claim 2 is a temporary construction step in which a part or all of a plurality of bridge girders are continuously installed above a construction section provided on an existing traffic route, and the plurality of bridge girders are installed and the existing bridge girders are installed. A bridge girder installation step of communicating with a traffic route and detouring traffic on the plurality of bridge girders, a main construction step of performing main construction work in the construction section, and the bridge girder installed after the construction section becomes traversable. And a bridge girder raising step for raising the bridge girder.
[0011]
Such a construction method includes, after a plurality of bridge girders are continuously installed above a construction section provided on an existing traffic route, installing the plurality of bridge girders and communicating with the existing traffic route, and providing a vehicle or the like on the plurality of bridge girders. After the detour, the main work is performed in the construction section, and after the construction section becomes traversable, the installed bridge girder is raised to allow vehicles and the like to pass through the construction section. According to the method, when construction is performed on an existing traffic route on which vehicles and the like go, temporary construction and main construction can be performed without significantly restricting traffic on vehicles and the like passing on the existing traffic route. That is, since all of the plurality of bridge girders constituting the elevated detour can be constructed above the construction section, vehicles and the like can pass under the elevated detour just before the service is started. If some or all of the bridge girders are installed at predetermined positions so as to function as an elevated detour, vehicles and the like can be immediately passed on the elevated detour (a plurality of bridge girders). Further, when the work is progressed and the construction section is in a passable state, if these are raised, vehicles and the like are immediately passed through the construction section without waiting for dismantling of the elevated detour. be able to.
[0012]
The invention described in claim 3 is the construction method according to claim 2, wherein the temporary construction step includes constructing a pair of left and right retaining walls on the existing traffic route, and the bridge girder installation step includes: And embedding the space between the retaining walls to rub the bridge girder against the existing traffic path, and the bridge girder raising step includes removing the embankment between the retaining walls.
[0013]
In this construction method, the bridge girder that has been lowered and the existing traffic route are rubbed by embankment between a pair of left and right retaining walls that have been constructed in the existing traffic route in advance. In this way, traffic regulations on vehicles and the like passing through existing traffic routes can be further reduced. The retaining wall may be cast-in-place or precast, and may be a gravity retaining wall, an L-shaped retaining wall, an inverted T retaining wall, or the like, or an underground continuous wall or a pier row pier. No problem. Also, this retaining wall may be used as a main body structure.
[0014]
The invention described in claim 4 is an elevated type detour for diverting traffic in a construction section provided on an existing traffic route, comprising an approach portion constructed above the construction section, and the approach concerned. The part is composed of a plurality of bridge girders continuously connected in the sky of the construction section, and the plurality of bridge girders are supported by piers constructed in the construction section so as to be able to move up and down.
[0015]
Such an elevated detour becomes a detour that bypasses the construction section when the approach section constructed over multiple spans is lowered over the construction section to communicate with the existing traffic path. That is, a vehicle or the like can be passed under the approach section until immediately before the service of the elevated detour starts, and the vehicle or the like can be immediately passed through the elevated detour if the entire approach section is lowered. . In addition, when the construction section progresses and the construction section is in a passable state, if the approach section is raised, vehicles and the like are allowed to pass through the construction section immediately without waiting for dismantling of the elevated detour. be able to. That is, in the case where construction is performed on an existing traffic route on which vehicles and the like travel, the temporary construction and the main construction can be performed without significantly restricting traffic on vehicles and the like passing on the existing traffic route. Note that the plurality of bridge girders constituting the approach portion may be connected continuously in a state of being inclined at a predetermined gradient, or may be connected horizontally. When a plurality of bridge girders are installed horizontally, each bridge girder is lowered while being inclined at a predetermined gradient, and is raised while returning to horizontal.
[0016]
The invention described in claim 5 is the elevated detour according to claim 4, wherein each of the bridge girders is supported at both ends thereof so as to be able to go up and down.
[0017]
According to such an elevated detour, since both ends of the bridge girder are supported so as to be able to move up and down, the inclination of the bridge girder can be adjusted. That is, when raising and lowering the bridge girder, the gradient of the bridge girder can be easily adjusted by making a difference between the lifting amount at one end and the lifting amount at the other end. For example, a bridge girder that is horizontally laid can be lowered while being inclined at a predetermined gradient.
[0018]
According to a sixth aspect of the present invention, there is provided the elevated detour according to the fifth aspect, wherein ends of the adjacent bridge girders are connected by a telescopic coupler.
[0019]
According to such an elevated detour, the distance between the ends of the adjacent bridge girders can be kept in an appropriate state by the coupler, so that the entire approach portion extending over multiple spans can be moved up and down in a lump.
[0020]
The invention described in claim 7 is the elevated detour according to any one of claims 4 to 6, wherein an elevating device is provided at an upper end of each pier, and each of the bridge girders is provided. Is suspended from the lifting device.
[0021]
According to the elevated detour, the bridge girder can be raised and lowered by appropriately operating the lifting device provided on the pier. That is, when raising and lowering the bridge girder, there is no need to prepare a special vehicle equipped with a wheel crane or jack.
[0022]
The invention described in claim 8 is the elevated detour according to any one of claims 4 to 7, wherein each of the piers supports the bridge girder in a lowered state. Is provided.
[0023]
According to such an elevated detour, since the support portion is provided in advance at a predetermined position of each pier, the positioning of the bridge girder at the time of descent becomes easy.
[0024]
The invention described in claim 9 is the elevated detour according to any one of claims 4 to 8, wherein the piers are arranged at predetermined intervals in a direction perpendicular to the bridge axis. It consists of a pair of left and right supports.
[0025]
According to this elevated detour, a pair of right and left pillars are used as piers. Therefore, when a general vehicle passes through a construction section (below the elevated detour), such as during the construction of the elevated detour, the pier is used. Traffic flow is not hindered.
[0026]
An elevated detour according to a tenth aspect further includes a sliding portion that allows the approach part and the existing traffic path to communicate with each other according to any one of the fourth to ninth aspects. The sliding portion includes a pair of left and right retaining walls arranged in the construction section.
[0027]
According to such an elevated detour, by embankment between the retaining walls, the approach portion and the existing traffic path can be easily rubbed. The retaining wall may be cast-in-place or precast, and may be a gravity retaining wall, an L-shaped retaining wall, an inverted T retaining wall, or the like, or an underground continuous wall or a pier row pier. No problem. Also, this retaining wall may be used as a main body structure.
[0028]
BEST MODE FOR CARRYING OUT THE INVENTION
Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings.
[0029]
In the construction method according to the present invention, as shown in FIG. 1, after constructing an elevated detour U above a construction section R3 provided on a road R1, a part of the elevated detour U is lowered. After communicating with the road R1 (see FIG. 6) and diverting the automobile S on the elevated detour U, the main construction is performed in the construction section R3. The lowered portion of the detour U is raised (see FIG. 8) to allow the vehicle S to pass through the construction section R3.
[0030]
In the present embodiment, as shown in FIGS. 10A and 10B, one of the roads R1 and R2 that intersect with each other is made underground, and a substantially rectangular section is provided in a construction section R3 provided on the road R1. An example of performing construction (main construction) for constructing a box culvert 70 having a shape and a digging structure 80 having a substantially U-shaped cross section will be exemplified. Needless to say, the type of construction and the type of construction work are not limited to these.
[0031]
[Elevated detour]
First, the elevated detour U will be described. As shown in FIG. 1, the elevated detour U includes an elevated section 10 and an approach section 20 constructed above the construction section R3, and a sliding section 30 constructed on the road R1. The approach portion 20 and the sliding portion 30 are arranged on both sides of the elevated portion 10 in the bridge axis direction.
[0032]
(Elevated section)
As shown in FIG. 1, the elevated portion 10 includes a plurality of bridge girders 11 (hereinafter, referred to as “fixed bridge girders 11”) that are continuously provided above the construction section R3. The installation height of the fixed bridge girder 11 does not change during the construction period.
[0033]
In this embodiment, the fixed bridge girder 11 has a long span spanning the intersection R4 and a short span girder arranged on both sides in the bridge axis direction. The long span fixed bridge girder 11 is erected between the first piers 40 and 40 facing each other across the intersection R4, and the short span fixed bridge girder 11 is provided between the first pier 40 and the second pier 50, or , Between the second pier 50 and the third pier 60. The structure type, material and the like of the fixed bridge girder 11 and its piers 40 and 50 are not particularly limited, and an appropriate one can be selected according to construction conditions and the like.
[0034]
In the present embodiment, the first pier 40 and the second pier 50 have substantially the same configuration, and therefore, the first pier 40 will be described below. As shown in FIG. 2A, the first pier 40 includes a pair of right and left columns 41, 41 arranged at predetermined intervals in a direction perpendicular to the bridge axis, and a horizontal member 41b connecting these columns.
[0035]
As shown in FIG. 1, the support column 41 is formed by integrally integrating a column array including a plurality of support piles 41 a arranged at predetermined intervals in a bridge axis direction with a plurality of cross members 41 c. As shown in FIG. 2A, the support pile 41a is driven into a support layer further below the floor surface of the box culvert 70.
[0036]
(Approach part)
As shown in FIG. 1, the approach section 20 includes a plurality (four in the present embodiment) of bridge girders 21 (hereinafter, referred to as “movable bridge girders 21”) that are connected substantially horizontally over the construction section R3. I have.
[0037]
As shown in FIG. 3, the movable bridge girder 21 is installed on third piers 60 adjacent to each other in the bridge axis direction so as to be able to move up and down. In this embodiment, as shown in FIG. 4, a pair of receiving girders 22, a pair of left and right truss frames 23, 23 laid between the receiving girders 22, 22 and the truss frames 23, 23 are connected to each other. It is composed of a plurality of cross beams 24 to be connected and a plurality of lining plates 25 provided on the cross beams 24. As shown in FIG. 5 (a), a pin shoe 23a and a movable shoe 23b which is vertically expandable and contractible are interposed between the truss frame 23 and the receiving girder 22 in the bridge axis direction. . Here, the pin shoe 23a may be configured to be changeable to a movable shoe during operation.
[0038]
As shown in FIG. 5C, in the present embodiment, the receiving girder 22 includes a beam 22A formed by connecting a pair of H steels 22a, 22a with a plurality of connecting members 22b, and an end of the beam 22A. , And a pin shoe 23a and a movable shoe 23b are fixed to both ends of the beam 22A. Further, as shown in FIG. 5 (b), hoists 22c, 22c are fixed to the guide portion 22B, and the hoisting devices 22c, 22c have lifting devices 62 provided at the upper end of the third pier 60. The lower end of the linear member 62a hanging down from (see FIG. 5A) is connected. That is, the movable bridge girder 21 is suspended by the lifting device 62 via the receiving girder 22.
[0039]
In addition, the structure type, the material, and the like of the movable bridge girder 21 are not limited to those shown in the drawings, and an appropriate one can be selected according to construction conditions, load conditions, and the like.
[0040]
As shown in FIG. 2 (b), the third pier 60 is composed of a pair of right and left columns 61, 61 arranged at predetermined intervals in the direction perpendicular to the bridge axis in the construction section R3. 21 is located above.
[0041]
As shown in FIG. 3, the support column 61 is formed by connecting the upper ends of a row of four column members 61a continuously provided at a predetermined interval in the bridge axis direction with a horizontal member 61d. In addition, as shown in FIG. 1, the column 61 ′ of the third pier 60 located at the boundary with the sliding portion 30 is composed of two column members 61 a.
[0042]
As shown in FIG. 3, the column member 61a is erected and fixed to a core member 91a constituting an underground continuous wall 91 (see FIG. 2B). In addition, the core material 91a shall penetrate to the support layer. Further, as shown in FIG. 2B, the column member 61a is provided with a temporary receiving portion 61c on which the receiving girder 22 of the movable bridge girder 21 in the raised state is placed, and a movable bridge girder 21 in the lowered state. And a supporting portion 61b on which the receiving beam 22 is placed. The temporary receiving part 61c is installed at a height below the movable bridge girder 21 so that a building limit can be secured when the movable bridge girder 21 is placed on the temporary receiving part 61c. Further, when the movable bridge girder 21 is supported by the temporary receiving portion 61c or the supporting portion 61b, as a result, a ramen structure is formed by the receiving girder 22 and the pair of left and right columns 61, 61 (column members 61a, 61a). Will be.
[0043]
Further, as shown in FIG. 5C, the interval between the adjacent column members 61 a in the bridge axis direction is larger than the guide portion 22 B of the girder 22. That is, the guide portion 22B can move up and down between the adjacent column members 61a.
[0044]
In a section where the underground continuous wall 91 (see FIG. 2B) is not constructed, the support pile 61e (see FIG. 1) is driven in, and the column member 61a is erected and fixed to the upper end of the support pile 61e.
[0045]
Further, as shown in FIG. 3, lifting devices 62, 62 are fixed to a horizontal member 61d connecting the upper ends of the four column members 61a.
[0046]
The elevating device 62 is located directly above the guide portion 22B of the receiving beam 22 (see FIG. 5C). That is, two lifting devices 62 are arranged for one receiving beam 22. A linear member 62a such as a wire or a steel rod hangs from the elevating device 62, and the lower end thereof is connected to the hanging tool 22c of the receiving beam 22 (see FIGS. 5A and 5B). When the four lifting devices 62 are appropriately operated, the movable bridge girder 21 moves up and down. Further, in one movable bridge girder 21, the lifting amount of one receiving girder 22 and the lifting amount of the other receiving girder 22 are reduced. If the difference is made, the movable bridge girder 21 will be inclined.
[0047]
Further, as shown in FIG. 5A, the receiving girders 22, 22 of the adjacent movable bridge girders 21, 21 are connected to each other by a telescopic coupler 26. For example, a jack can be used for the coupler 26.
[0048]
(Sliding part)
The sliding part 30 is provided between the approach part 20 and the road R1, as shown in FIG. 1, and as shown in FIG. 2C, a pair of left and right retaining walls arranged in the construction section R3. 31, 31 are provided. By embankment between the retaining walls 31 immediately before or immediately after the approach portion 20 is lowered, the approach portion 20 that has been lowered and the road R1 are rubbed.
[0049]
As shown in FIG. 2 (c), the retaining wall 31 is an inverted T type in this embodiment, and only the earth retaining portion 31a in the high section protrudes above the ground, and other portions are buried underground. . Finally, the space between the retaining walls 31 is dug down. Further, the structure type and the like of the retaining wall 31 are not limited to those shown in the drawings, and may be appropriately changed in accordance with construction conditions.
[0050]
[Construction method]
Next, a construction method using the elevated detour U will be described. In this construction method, as shown in FIG. 6, an elevated detour U is constructed on a construction section R3 provided on a road R1, and a vehicle S is detoured on the elevated detour U. After the main construction is performed in the section R and the construction section R3 becomes passable, a part or all of the elevated detour U is raised to secure a building limit under the elevated detour U ( See FIG. 8). That is, all of the plurality of bridge girders (the fixed bridge girder 11 and the movable bridge girder 21) constituting the elevated detour U are connected continuously above the construction section R3, and thereafter, these function as the elevated detour U. Thus, a part of the bridge girder (the movable bridge girder 21 of the approach portion 20) is installed at a predetermined position (to be lowered), communicates with the road R1, and the vehicle S is detoured on the plurality of bridge girder 11, 21. Above, the main construction is performed in the construction section R3, and after the construction section R3 becomes traversable, the movable bridge girder 21 that has been installed (dropped) is raised to secure the building limit under the elevated detour U. It is. Hereinafter, each step will be described in detail.
[0051]
(Temporary construction process)
First, as shown in FIGS. 2A and 2B, a retaining wall 90 serving as a retaining wall when constructing the box culvert 70 and the excavated structure 80 is constructed. The structure and form of the retaining wall 90 may be changed as appropriate in accordance with soil conditions and the like. The earth retaining wall 90 of the present embodiment includes an underground continuous wall 91 (see FIGS. 2A and 2B) constructed by a soil mixing wall (SMW) method, and a steel sheet pile 92 constructed by a steel sheet pile method. FIG. 2C). In the present embodiment, the underground continuous wall 91 is constructed in a section where the excavation depth is relatively large (see FIGS. 2A and 2B), and a steel sheet pile 92 is constructed in a section where the excavation depth is relatively shallow (see FIG. 2A). FIG. 2 (c)).
[0052]
Next, as shown in FIG. 1, a plurality of support piles 41a are driven at predetermined positions in the construction section R3 to construct the first pier 40, and a plurality of support piles 51a are driven to construct the second pier 50. . Further, in the section where the underground continuous wall 91 (see FIG. 2B) is constructed, the column member 61a is erected and fixed on the upper end of the core member 91a of the locally elongated underground continuous wall 91, In the section where the steel sheet pile 92 (see FIG. 2 (c)) is constructed, a plurality of support piles 61e are driven, and a column member 61a is erected and fixed to the upper end of the support pile. The third bridge pier 60 is constructed by connecting the upper ends of the column members 61a with the cross members 61d and fixing the lifting devices 62, 62 on the upper surface of the cross members 61d.
[0053]
Here, as shown in FIG. 2A, the first pier 40 is constituted by a pair of right and left columns 41, 41 erected at predetermined intervals in the direction perpendicular to the bridge axis. The vehicle S can be passed between 41 and 41, and the space can be used for a right turn lane or the like. That is, even if the first pier 40 is constructed, the flow of traffic is not obstructed. The same applies to the second pier 50 and the third pier 60.
[0054]
Subsequently, as shown in FIG. 1, the fixed bridge girder 11 and the movable bridge girder 21 are erected on the first pier 40, the second pier 50, and the third pier 60 to construct the elevated portion 10 and the approach portion 20. That is, a plurality of bridge girders 11 and 21 are continuously provided above the construction section R3 provided on the road R1 to construct the elevated section 10 and the approach section 20.
[0055]
The fixed bridge girder 11 and the movable bridge girder 21 can be erected using a heavy machine equipped with a crawler crane or a jack, but the movable bridge girder 21 uses a lifting device 62 provided at the upper end of the third pier 60. May be erected.
[0056]
At this time, the fixed bridge girder 11 is erected along the vertical line of the elevated detour U in the elevated portion 10, and the movable bridge girder 21 is erected horizontally at a height where the building limit can be secured in the approach portion 20. .
[0057]
Here, as shown in FIG. 2B, the movable bridge girder 21 is placed on the temporary receiving portion 61c provided on the support column 61. In such a state, the building limit is secured below the movable bridge girder 21. Therefore, the vehicle S can pass under the movable bridge girder 21.
[0058]
In addition, as shown in FIG. 2C, the vicinity of the boundary between the approach portion 20 and the sliding portion 30 (see FIG. 1) is dug down in advance to construct a retaining wall 31, and then backfilled to the ground surface again. Keep it.
[0059]
(Bridge girder installation process)
Next, as shown in FIG. 6, the movable bridge girder 21 of the approach portion 20 is lowered (inclined) in a lump among the plurality of bridge girders 11 and 21, and the retaining walls 31 and 31 (see FIG. 7C). The embankment is filled, the approach portion 20 is connected to the road R1, and the vehicle S is detoured on the elevated detour U (on the plurality of bridge girders 11, 21).
[0060]
That is, as shown in FIG. 3, after removing the temporary receiving portion 61c (see FIG. 2B) provided on the third pier 60, the separation distance between the adjacent movable bridge girders 21 and 21 is determined by the coupler 26. By operating the lifting / lowering device 62 provided on the third pier 60, the plurality of movable bridge girders 21 spanning multiple diameters are lowered (inclined) at a time while adjusting the distance. More specifically, while appropriately adjusting the separation distance between the adjacent movable bridge girders 21 and 21 so as to be within a predetermined range by the coupler 26, the end (receiving portion) of each movable bridge girder 21 on the sliding portion 30 side is adjusted. The descending speed of the girder 22) is made higher than the descending speed of the end (the receiving girder 22) on the elevated portion 10 side. At this time, since both ends of the receiving girder 22 are suspended, the movable bridge girder 21 can be lowered in a stable state.
[0061]
As shown in FIG. 7B, the third pier 60 is provided with a support portion 61b on which the receiving girder 22 of the movable bridge girder 21 in a lowered state is provided. Positioning is very easy. Moreover, as a result, a ramen structure is formed by the receiving girder 22 and the pair of left and right columns 61, 61 (column members 61a, 61a), so that it is excellent in mechanical properties.
[0062]
Further, since the movable bridge girder 21 is lowered by the elevating device 62 provided on the third pier 60, there is no need to prepare a special vehicle equipped with a wheel crane or jack.
[0063]
As shown in FIG. 7 (c), the approach portion 20 and the road R1 are filled between the earth retaining portions 31a, 31a of the railing portion of the retaining walls 31, 31 immediately before or immediately after the movable bridge girder 21 is lowered. It is rubbed by doing. Since the retaining wall 31 is a sill connected to the retaining wall at the sliding end of the excavated structure 80 as the main body structure, the installation work can be performed easily and inexpensively. That is, it is possible to facilitate and speed up the work, and as a result, it is possible to further reduce the traffic regulation on the automobile S passing on the road R1.
[0064]
(Main construction process)
Subsequently, main construction is performed in the construction section R3. In this embodiment, as shown in FIG. 7A, the columns 41, 41 of the first pier 40 are reinforced with cross members 41b while digging down between the underground continuous walls 91, 91 to a predetermined depth, and Build a box culvert 70 below 10. Further, as shown in FIG. 7B, a digging structure 80 is constructed by digging down to a predetermined depth below the approach portion 20 while installing a cutting beam 93 between the underground continuous walls 91, 91.
[0065]
At this time, the work space under the elevated detour U can be used as a work space, and work efficiency is high.
[0066]
Thereafter, as shown in FIG. 9A, a receiving beam 41d is provided on the upper surface of the box culvert 70, and after replacing the first pier 40 with the receiving beam 41d, the support pile 41a penetrating through the inside of the box culvert 70 is provided. And the cross member 41b (see FIG. 7 (a)) is removed so that the car S can pass through the inside of the box culvert 70, and similarly, as shown in FIG. A certain beam 93 or the like (see FIG. 7B) is removed, and the inside of the digging structure 80 is set in a state where the automobile S can pass. That is, a state is established in which the vehicle can pass through the construction section R3.
[0067]
(Bridge girder elevating process)
When the construction section R3 becomes passable, the lowered movable bridge girder 21 is raised as shown in FIG. 8, and as shown in FIG. The embankment between 31a is removed, and the retaining wall 31, 31 is dug down to allow the vehicle S to pass through the construction section R3.
[0068]
In order to raise the movable bridge girder 21, the lifting device 62 provided on the third pier 60 is appropriately operated while adjusting the distance between the adjacent movable bridge girder 21 and 21 with the coupler 26 (see FIG. 3). What is necessary is just to move each movable bridge girder 21 upward while returning it horizontally.
[0069]
Thereafter, as shown in FIG. 10 (a), when the elevated detour U is removed, the intersection R4 is completed at the intersection (underground road R1).
[0070]
As described above, according to the construction method according to the present embodiment, when the construction is performed on the road R1 on which the car S travels, the temporary construction and the construction work can be performed without significantly restricting the traffic on the car S passing on the road R1. Can perform construction.
[0071]
That is, according to this construction method, as shown in FIG. 1, all of the plurality of bridge girders 11 and 21 constituting the elevated detour U for bypassing the construction section R3 are constructed above the construction section R3. As shown in FIGS. 2A and 2B, the vehicle S can pass under the elevated portion 10 and the approach portion 20 until immediately before the service of the elevated detour U is started. Then, as shown in FIG. 7 (b), when the movable bridge girder 21 is lowered, the vehicle or the like can immediately pass through the elevated detour U, and furthermore, when the construction is progressing, the construction section R3 (FIG. 8) 9 (a), 9 (b) and 9 (c), immediately after the elevated detour U is dismantled without waiting for disassembly, as shown in FIGS. The vehicle S can be passed through R3. In other words, even if the width of the road R1 on which the construction is performed is narrow and it is difficult to secure a sufficient traffic volume with a planar detour, it is necessary to construct the elevated detour U in the construction section R3. Thus, it is possible to secure necessary lanes over the whole section of the construction section R3, and as a result, it is possible to significantly suppress traffic congestion due to construction.
[0072]
Also, since a sufficient work space can be secured for the builder, work efficiency can be improved, and as a result, it is possible to shorten the construction period and reduce the construction cost.
[0073]
Note that, in the above-described embodiment, the case where all of the plurality of movable bridge girders 21 are horizontally connected at the same height is exemplified. However, the present invention is not limited to this. They may be provided continuously in a state of being inclined at a predetermined gradient. In this case, since it is not necessary to change the elevating speed at each movable bridge girder, construction management is facilitated.
[0074]
In the above-described embodiment, the coupler 26 is disposed between the adjacent movable bridge girders 21 and 21, but the coupler 26 may be omitted. In this case, although not shown, each of the plurality of movable bridge girders can be independently raised and lowered.
[0075]
In the above-described embodiment, only the approach section 20 of the elevated detour U is configured to be able to move up and down. However, the elevated section 10 may be configured to be able to move up and down. For example, in the case where the construction is to improve the level of the railway rails due to raising the river embankment, and when the construction is completed, if the building limit cannot be secured below the entire elevated detour U, By raising not only the approach section 20 but also the elevated section 10 to secure the building limit under the elevated detour U, vehicles and the like can immediately pass through the construction section without waiting for the demolition of the elevated detour U. As a result, traffic regulation accompanying the dismantling work of the elevated detour U can be greatly suppressed.
[0076]
In the above-described embodiment, not only the elevated section 10 but also the approach section 20 is constructed above the construction section R3, and the approach section 20 is lowered immediately before the vehicle S is detoured on the elevated detour U. Although the construction method has been exemplified, the invention is not limited thereto. For example, in the elevated detour U, only the elevated portion 10 is constructed above the construction section R3, and the vehicle is placed on the elevated detour U. Immediately before detouring S, the movable bridge girder 21 constituting the approach portion 20 may be erected at a predetermined gradient by rapid construction, and the road R1 and the elevated portion 10 may be communicated. That is, of a plurality of bridge girders (fixed bridge girder 11 and movable bridge girder 21) constituting the elevated detour U, a part of the bridge girder (fixed bridge girder 11 of the elevated portion 10) is continuously provided above the construction section R3. After that, the remaining bridge girder (the movable bridge girder 21 of the approach portion 20) may be installed at a predetermined position by rapid construction to communicate with the road R1, and the vehicle S may be detoured on the plurality of bridge girder 11, 21. .
[0077]
In addition, as shown in FIG. 11, when the underground structures 100 and 110 are installed side by side, an elevated detour U ′ is constructed above the underground structure 100, and the underground structure is constructed by the above-described construction method. After constructing the underground structure 100, the elevated detour U ′ may be relocated above the underground structure 110, and the underground structure 110 may be constructed in the same manner as described above. The underground structures 100 and 110 may be constructed at the same time, and the elevated detours U 'and U' may be provided together.
[0078]
In the above, the elevated detour and the construction method according to the present invention have been described in detail by taking the case where the road R1 is underground as an example. However, it is needless to say that the elevated detour and the construction method can be applied to other construction performed on an existing traffic route. For example, although detailed explanations are omitted, various works such as widening, repairing, and rehabilitation work on existing roads, replacing old bridges and viaducts, and continuously elevating railways In addition, the elevated detour and the construction method according to the present invention can be applied.
[0079]
【The invention's effect】
ADVANTAGE OF THE INVENTION According to the construction method concerning this invention, temporary construction and main construction can be performed, without implementing a large traffic regulation with respect to the vehicle etc. which pass through an existing traffic route.
[0080]
Further, according to the elevated detour according to the present invention, traffic regulation during temporary construction and main construction can be significantly suppressed. Furthermore, a large work space can be secured for the builder, so that the construction period can be shortened and the construction cost can be reduced.
[Brief description of the drawings]
FIG. 1 is a side view showing a construction method and an elevated detour according to the present invention.
2A is a cross-sectional view taken along line X1-X1 in FIG. 1, FIG. 2B is a cross-sectional view taken along X2-X2 in FIG. 1, and FIG. 2C is a cross-sectional view taken along X3-X3 in FIG.
FIG. 3 is an enlarged side view showing a bridge girder of an approach portion.
FIG. 4 is an enlarged top view showing a bridge girder of an approach portion.
5A is an enlarged side view showing an end of a bridge girder, FIG. 5B is an end view showing a bridge girder of an approach part, and is a view taken in the direction of arrows Y1-Y1 in FIG. 4, and FIG. FIG. 3 is a view taken along arrow Z1-Z1 of FIG.
FIG. 6 is a side view for explaining the construction method according to the present invention, showing a step following FIG. 1;
7A is a sectional view taken along line X1-X1 of FIG. 6, FIG. 7B is a sectional view taken along line X2-X2 of FIG. 6, and FIG. 7C is a sectional view taken along line X3-X3 of FIG.
FIG. 8 is a side view for explaining the construction method according to the present invention, showing a step following FIG. 6;
9A is a sectional view taken along line X1-X1 of FIG. 8, FIG. 9B is a sectional view taken along line X2-X2 of FIG. 8, and FIG. 9C is a sectional view taken along line X3-X3 of FIG.
10A is a side view for explaining the construction method according to the present invention, showing a step following FIG. 8, and FIG. 10B is a top view of FIG.
FIG. 11 is a cross-sectional view showing a modified example of the elevated detour according to the present invention.
[Explanation of symbols]
10 elevated section
11 Fixed bridge girder
20 Approach Department
21 movable bridge girder
22 Receiving digits
26 coupler
30 Sliding part
31 Retaining Wall
31a Dome
40 First Pier
50 Second Pier
60 Third Pier
61 prop
61a pillar
61b support
61c Temporary receiving section
62 Lifting device
70 box culvert
80 Drilling structure
90 Earth retaining wall
R1, R2 road
R3 construction section
R4 intersection
S car
U elevated detour

Claims (10)

既設交通路に設けられた工事区間上に高架式迂回路を構築し、当該高架式迂回路上に交通を迂回させたうえで、前記工事区間で本工事を行い、前記工事区間が通行可能となった後に、前記高架式迂回路の一部または総てを上昇させて前記高架式迂回路下の建築限界を確保することを特徴とする工事方法。After constructing an elevated detour on the construction section provided on the existing traffic route, detouring the traffic on the elevated detour, performing the main work in the construction section, and the construction section becomes traversable After that, a part or all of the elevated detour is raised to secure a building limit under the elevated detour. 既設交通路に設けられた工事区間の上空に複数の橋桁の一部または総てを連設する仮設工事工程と、
前記複数の橋桁を設置して前記既設交通路と連通し、前記複数の橋桁上に交通を迂回させる橋桁設置工程と、
前記工事区間で本工事を行う本工事工程と、
前記工事区間が通行可能となった後に、設置した前記橋桁を上昇させる橋桁上昇工程とを含むことを特徴とする工事方法。
A temporary construction process in which a part or all of a plurality of bridge girders are continuously installed above the construction section provided on the existing traffic route;
A bridge girder installation step of installing the plurality of bridge girders, communicating with the existing traffic path, and bypassing traffic on the plurality of bridge girders;
A main construction process for performing the main construction in the construction section,
A bridge girder raising step of raising the installed bridge girder after the construction section has become traversable.
前記仮設工事工程は、前記既設交通路に左右一対の擁壁を構築することを含み、
前記橋桁設置工程は、前記擁壁間を盛土して前記橋桁と前記既設交通路とを擦り付けることを含み、
前記橋桁上昇工程は、前記擁壁間の盛土を撤去することを含むことを特徴とする請求項2に記載の工事方法。
The temporary construction process includes constructing a pair of left and right retaining walls on the existing traffic route,
The bridge girder installation step includes embankment between the retaining walls and rubbing the bridge girder with the existing traffic path,
The construction method according to claim 2, wherein the bridge girder raising step includes removing an embankment between the retaining walls.
既設交通路に設けられた工事区間の交通を迂回させるための高架式迂回路であって、
工事区間の上空に構築されるアプローチ部を有し、
当該アプローチ部は、前記工事区間の上空に連設された複数の橋桁からなり、
当該複数の橋桁は、それぞれ前記工事区間に構築された橋脚に昇降可能に支持されていることを特徴とする高架式迂回路。
An elevated detour for diverting traffic in a construction section provided on an existing traffic route,
It has an approach section built above the construction section,
The approach section is composed of a plurality of bridge girders continuously arranged above the construction section,
The elevated detour, wherein the plurality of bridge girders are supported by piers constructed in the construction section so as to be able to move up and down.
前記各橋桁は、その両端のそれぞれが昇降可能に支持されていることを特徴とする請求項4に記載の高架式迂回路。The elevated detour according to claim 4, wherein each of the bridge girders is supported at both ends thereof so as to be able to move up and down. 隣り合う前記橋桁の端部同士が伸縮自在な連結器により連結されていることを特徴とする請求項5に記載の高架式迂回路。The elevated detour according to claim 5, wherein the ends of the adjacent bridge girders are connected by a telescopic coupler. 前記各橋脚の上端は、前記各橋桁の上方に位置しており、
前記各橋桁は、前記各橋脚の上端に設けられた昇降装置に吊り下げられていることを特徴とする請求項4乃至請求項6のいずれか一項に記載の高架式迂回路。
The upper end of each pier is located above each of the bridge girders,
The elevated detour according to any one of claims 4 to 6, wherein each of the bridge girders is suspended by an elevating device provided at an upper end of each of the piers.
前記各橋脚に、降下させた状態の前記橋桁を支持する支持部が設けてあることを特徴とする請求項4乃至請求項7のいずれか一項に記載の高架式迂回路。The elevated detour according to any one of claims 4 to 7, wherein each of the piers is provided with a support portion that supports the bridge girder in a lowered state. 前記各橋脚は、橋軸直角方向に所定の間隔をあけて配置された左右一対の支柱からなることを特徴とする請求項4乃至請求項8のいずれか一項に記載の高架式迂回路。The elevated detour according to any one of claims 4 to 8, wherein each of the piers comprises a pair of right and left columns arranged at predetermined intervals in a direction perpendicular to the bridge axis. 前記アプローチ部と前記既設交通路とを連通させる摺付部をさらに有し、
当該摺付部は、前記工事区間に配置された左右一対の擁壁を備えていることを特徴とする請求項4乃至請求項9のいずれか一項に記載の高架式迂回路。
Further comprising a sliding portion for communicating the approach portion and the existing traffic route,
The elevated detour according to any one of claims 4 to 9, wherein the sliding portion includes a pair of left and right retaining walls disposed in the construction section.
JP2003102507A 2003-04-07 2003-04-07 Construction method and elevated detour Expired - Fee Related JP4263935B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2003102507A JP4263935B2 (en) 2003-04-07 2003-04-07 Construction method and elevated detour

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2003102507A JP4263935B2 (en) 2003-04-07 2003-04-07 Construction method and elevated detour

Publications (2)

Publication Number Publication Date
JP2004308225A true JP2004308225A (en) 2004-11-04
JP4263935B2 JP4263935B2 (en) 2009-05-13

Family

ID=33465917

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2003102507A Expired - Fee Related JP4263935B2 (en) 2003-04-07 2003-04-07 Construction method and elevated detour

Country Status (1)

Country Link
JP (1) JP4263935B2 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104420418A (en) * 2013-09-02 2015-03-18 国家电网公司 Construction method of tower pile foundation engineering trestle
CN107841953A (en) * 2017-11-30 2018-03-27 中铁二十局集团第工程有限公司 Across the cast-in-place section construction support in high-altitude obliquely-intersected beams abrupt slope side and construction method
JP2018071218A (en) * 2016-10-31 2018-05-10 鹿島建設株式会社 Temporary construction bridge and floor slab replacement method
CN112112049A (en) * 2020-10-16 2020-12-22 中铁西安勘察设计研究院有限责任公司 Construction method for replacing existing railway roadbed with railway simply-supported T-beam bridge
JP6981716B1 (en) * 2020-08-15 2021-12-17 哲矢 森田 Bypass road between two adjacent railroad crossings and how to use it

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104420418A (en) * 2013-09-02 2015-03-18 国家电网公司 Construction method of tower pile foundation engineering trestle
CN104420418B (en) * 2013-09-02 2017-01-04 国家电网公司 Tower pile foundation engineering trestle construction method
JP2018071218A (en) * 2016-10-31 2018-05-10 鹿島建設株式会社 Temporary construction bridge and floor slab replacement method
CN107841953A (en) * 2017-11-30 2018-03-27 中铁二十局集团第工程有限公司 Across the cast-in-place section construction support in high-altitude obliquely-intersected beams abrupt slope side and construction method
CN107841953B (en) * 2017-11-30 2024-02-27 中铁二十局集团第一工程有限公司 High-altitude oblique crossing Liang Doupo side span cast-in-situ section construction support and construction method
JP6981716B1 (en) * 2020-08-15 2021-12-17 哲矢 森田 Bypass road between two adjacent railroad crossings and how to use it
JP2022033068A (en) * 2020-08-15 2022-02-28 哲矢 森田 Bypass road between two adjacent railroad crossings and utilization method thereof
CN112112049A (en) * 2020-10-16 2020-12-22 中铁西安勘察设计研究院有限责任公司 Construction method for replacing existing railway roadbed with railway simply-supported T-beam bridge

Also Published As

Publication number Publication date
JP4263935B2 (en) 2009-05-13

Similar Documents

Publication Publication Date Title
KR101344063B1 (en) The construction method of steel-concrete underpass
KR100949601B1 (en) Method for broadening width of existing bridge without Temporary road
JPH08253946A (en) Reverse placing method for concrete of underground structure under road
JP3586864B2 (en) Underground structure construction method and elevated traffic path
JP4671912B2 (en) Bridge replacement method
KR101040731B1 (en) Movable temporary structure for constructing composite covering arch structure
JP4406577B2 (en) Digging road
JP4263935B2 (en) Construction method and elevated detour
JP2017218727A (en) Temporary driveway having a lifting column and movable in tunnel, and road construction method using temporary driveway
JP2004332357A (en) Method for constructing elevated type traffic route and elevated type traffic route
KR100605495B1 (en) Trenchless method of underground passage and structure thereof
JP2005146695A (en) Viaduct structure and method of constructing the same
JP3380301B2 (en) Viaduct construction method
JP4280208B2 (en) Viaduct replacement method
JP2005090108A (en) Erection method of bridge
JP3940587B2 (en) Construction method of divided bridge type traffic route
JP2004278230A (en) Method of constructing grade separation of roads, and pier connection structure
JP4233025B2 (en) How to construct a three-dimensional intersection
JP3619515B2 (en) Split-bridge type traffic road and method for constructing split-bridge type traffic road
JP3682247B2 (en) Construction method of elevated traffic route
CN109629443B (en) Cast-in-place channel beam three-point pushing system crossing existing road and construction method
JP3380302B2 (en) Viaduct construction method
JP2003193405A (en) Grade separation and its constructing method
RU89124U1 (en) DEVICE FOR ESTABLISHING A TUNNEL OF A SMALL LOCATION UNDER THE ROAD SECTION
JP3616587B2 (en) Construction method of elevated traffic route

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20060116

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20080401

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20080520

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20080704

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20090203

A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20090213

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120220

Year of fee payment: 3

R150 Certificate of patent or registration of utility model

Free format text: JAPANESE INTERMEDIATE CODE: R150

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120220

Year of fee payment: 3

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130220

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130220

Year of fee payment: 4

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20140220

Year of fee payment: 5

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

LAPS Cancellation because of no payment of annual fees