JP2790986B2 - Bridge pier construction method and construction method - Google Patents

Bridge pier construction method and construction method

Info

Publication number
JP2790986B2
JP2790986B2 JP7038259A JP3825995A JP2790986B2 JP 2790986 B2 JP2790986 B2 JP 2790986B2 JP 7038259 A JP7038259 A JP 7038259A JP 3825995 A JP3825995 A JP 3825995A JP 2790986 B2 JP2790986 B2 JP 2790986B2
Authority
JP
Japan
Prior art keywords
formwork
pier
construction
skeleton
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Lifetime
Application number
JP7038259A
Other languages
Japanese (ja)
Other versions
JPH08232212A (en
Inventor
紳一郎 熊谷
基文 斉藤
和道 佐々木
重美 福島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP7038259A priority Critical patent/JP2790986B2/en
Publication of JPH08232212A publication Critical patent/JPH08232212A/en
Application granted granted Critical
Publication of JP2790986B2 publication Critical patent/JP2790986B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Description

【発明の詳細な説明】DETAILED DESCRIPTION OF THE INVENTION

【0001】[0001]

【産業上の利用分野】この発明は中空の橋脚を複数の施
工区分に分割して構築する構築方法とその方法を実施す
るための施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a hollow bridge pier by dividing it into a plurality of construction sections and a construction method for implementing the method.

【0002】[0002]

【従来技術及び発明が解決しようとする課題】橋脚の施
工は一施工区間単位では主筋とそれを周囲から拘束する
せん断補強筋を配筋し、型枠を組み立ててコンクリート
を打設する、という要領で行われ、全体的には転用可能
な型枠を用い、型枠の組み立て,解体と盛り替えを繰り
返して上方へ移動する方法が一般的であるが、型枠の組
み立てと解体には手間と時間を要するため従来方法は能
率が悪い。特に橋脚の施工区間によって断面が変化する
場合には型枠の加工が必要になるため能率の低下は著し
い。また主筋は揚重機を用いることにより一施工区間分
まとめて吊り上げ、順次配筋することができるが、せん
断補強筋は単一の鉄筋として予め組み立てておくことが
できないためその配筋作業は一区間での施工遅延の原因
になっている。
2. Description of the Related Art In the construction of a bridge pier, a procedure of arranging a main reinforcing bar and a shear reinforcing bar for restraining the main reinforcing bar from the surroundings per unit of construction section, assembling a formwork, and placing concrete is performed. In general, a method is used in which a formwork that can be diverted is used, and the assembling, dismantling, and changing of the formwork are repeated and moved upward. However, assembling and dismantling the formwork is troublesome. The conventional method is inefficient because it requires time. In particular, when the cross section changes depending on the construction section of the pier, it is necessary to process the formwork, so the efficiency is significantly reduced. In addition, the main reinforcement can be lifted together for one construction section by using a lifting machine, and can be sequentially arranged.However, since the shear reinforcement cannot be pre-assembled as a single reinforcing bar, the reinforcement work is performed in one section. Is causing delays in construction.

【0003】高橋脚では型枠や鉄筋等の荷揚げにタワー
クレーンが使用されるが、タワークレーンは躯体上での
型枠と鉄筋の吊り込みにも使用されるため巻き上げ能力
が施工の進捗に影響し、その影響は橋脚高が大きくなる
程大きい。橋脚高の増加に伴い、風の影響も加わるため
稼働効率の低下を招き、稼働効率が低下すれば天候の影
響を受ける可能性が増すため施工の遅延につながる。
[0003] A tower crane is used for unloading a formwork or a reinforcing bar on a high pier, but the tower crane is also used for suspending a formwork and a reinforcing bar on a skeleton, so that a hoisting capacity affects the progress of construction. However, the effect is greater as the pier height increases. As the height of the piers increases, the effect of the wind also increases, resulting in a decrease in operating efficiency. If the operating efficiency decreases, the possibility of being affected by the weather increases, leading to a delay in construction.

【0004】この発明は上記背景を踏まえてなされたも
ので、施工の進捗を図る構築方法とそれを実施するため
の施工方法を提案するものである。
[0004] The present invention has been made in view of the above background, and proposes a construction method for progressing construction and a construction method for implementing the method.

【0005】[0005]

【課題を解決するための手段】本発明では型枠を埋設型
枠にし、型枠にせん断補強筋に相当する部材を一体化さ
せ、主筋を仮固定しておくことにより一施工区間におけ
る施工を単純化し、施工の進捗を図る。
According to the present invention, the construction in one construction section can be performed by using a mold as a buried mold, integrating a member corresponding to a shear reinforcing bar with the mold, and temporarily fixing a main bar. Simplify and progress construction.

【0006】型枠には橋脚の横断面上、内周側に配置さ
れる内型枠と外周側に配置される外型枠があり、内型枠
と外型枠は共に、片面に主筋を周囲から拘束する水平鋼
材が一体化した状態でプレキャストコンクリートで製作
される。水平鋼材は水平方向に配置される。主筋は水平
鋼材に包囲される側に鉛直方向に仮固定される。
[0006] The formwork includes an inner formwork arranged on the inner periphery side and an outer formwork arranged on the outer periphery side in the cross section of the pier. Both the inner formwork and the outer formwork have a main reinforcement on one side. It is made of precast concrete in a state in which horizontal steel materials constrained from the surroundings are integrated. The horizontal steel material is arranged in the horizontal direction. The main reinforcement is temporarily fixed in the vertical direction to the side surrounded by the horizontal steel material.

【0007】内型枠と外型枠は橋脚の横断面上、周方向
にそれぞれ隣接し、橋脚の躯体の厚さ方向に互いに対向
して施工済みの、橋脚の躯体上に組み立てられる。橋脚
の内周側と外周側で周方向に隣接する内型枠と外型枠の
各水平鋼材は互いに接続され、内型枠と外型枠の各主筋
は下方の施工済みの各主筋に接続される。その後、内型
枠と外型枠とで挟まれた空間内にコンクリートが打設さ
れて一施工区間の作業は終了する。コンクリートの硬化
後、更にその上方への内型枠と外型枠の組み立てからコ
ンクリートの打設までの作業が繰り返されて橋脚が完成
する。
[0007] The inner formwork and the outer formwork are adjacent to each other in the circumferential direction on the cross section of the pier, and are assembled on the pier body which has been constructed so as to face each other in the thickness direction of the pier body. The horizontal steel materials of the inner formwork and the outer formwork that are adjacent to each other in the circumferential direction on the inner and outer sides of the pier are connected to each other, and the main reinforcements of the inner formwork and the outer formwork are connected to the main reinforcements that have been constructed below. Is done. Thereafter, concrete is poured into the space sandwiched between the inner formwork and the outer formwork, and the work in one construction section is completed. After the concrete is hardened, the operations from assembling the inner formwork and the outer formwork further upward to placing the concrete are repeated to complete the pier.

【0008】内型枠と外型枠に予め水平鋼材が付属し、
主筋が仮固定されることにより個々の配筋作業が省略さ
れ、内型枠と外型枠がコンクリートの打設後にそのまま
橋脚の躯体の一部になることにより脱型と盛り替え、及
び再組み立ての手間も省略され、現場作業の省力化が図
られる。一施工区間における施工は内型枠と外型枠の組
み立てと主筋の接続、及びコンクリートの打設によって
完了するため施工の大幅な進捗が図られる。
[0008] A horizontal steel material is attached to the inner mold and the outer mold in advance,
Temporary fixation of the main reinforcement eliminates individual rebar arrangement work, and the inner and outer formwork become part of the pier body as it is after casting the concrete, so it can be removed, replaced, and reassembled. Labor is saved, and labor on site work is saved. The construction in one construction section is completed by assembling the inner formwork and the outer formwork, connecting the main reinforcement, and placing the concrete, so that the construction is greatly advanced.

【0009】施工は施工済みの、橋脚となる躯体の外周
に沿って昇降する昇降機に加え、頂部に揚重機を持つポ
ストと、ポストを支持する下部架台と、ポストに沿って
下部架台に対して昇降可能な上部架台からなる作業台を
用いて実施される。昇降機は躯体の外周側に高さ方向に
敷設された軌道に沿って昇降し、内型枠と外型枠を地上
から上部架台上まで搬送する。作業台は高さ方向に一定
距離だけ施工する毎に躯体の内部を利用して上昇し、上
部架台上まで荷揚げされた内型枠と外型枠の組み立てか
らコンクリート打設までの作業のために利用される。
[0009] In addition to the lift that moves up and down along the outer periphery of the skeleton that will be a bridge pier, the post has a lifting machine at the top, a lower gantry supporting the post, and a lower gantry along the post. The operation is performed using a worktable including an upper mount that can be moved up and down. The elevator moves up and down along a track laid in the height direction on the outer peripheral side of the skeleton, and transports the inner formwork and the outer formwork from the ground to the upper gantry. The workbench rises by using the inside of the skeleton every time a certain distance is constructed in the height direction, and for work from assembling the inner formwork and the outer formwork unloaded to the upper gantry to concrete casting Used.

【0010】作業台の一施工区間分の上昇は施工済みの
躯体の内面に作業台を支持させたまま、一施工区間の施
工が終了する毎に上部架台を上昇させて上方の躯体内面
に支持させた後、下部架台を上昇させて上部架台の下方
位置の躯体内面に支持させる、という要領で行われ、作
業台の上昇後、上部架台上まで荷揚げされている内型枠
と外型枠の組み立てが作業台のポストに付属した揚重機
によって行われる。
When the work table is raised for one construction section, the upper pedestal is raised every time the construction of one construction section is completed, while the work table is supported on the inner surface of the completed skeleton, and the work table is supported on the upper skeleton surface. After that, the lower gantry is raised and supported on the inner surface of the skeleton below the upper gantry, and after the workbench is raised, the inner and outer cranes unloaded to the upper gantry are lifted. Assembly is performed by a lifting machine attached to the workbench post.

【0011】内型枠と外型枠の荷揚げを昇降機が行い、
荷揚げされた内型枠と外型枠の組み立てを作業台の揚重
機が行い、それぞれの機能が分離することにより荷揚げ
作業と、躯体上での構築作業を並行して行うことが可能
となり、稼働効率と作業能率が向上し、工期の短縮化が
図られる。
An elevator lifts and unloads the inner and outer forms.
The unloading inner formwork and outer formwork are assembled by the lifting machine of the workbench, and their functions are separated so that the unloading work and the construction work on the skeleton can be performed in parallel. Efficiency and work efficiency are improved, and the construction period is shortened.

【0012】[0012]

【実施例】請求項1記載の発明は図1に示すように主筋
3を周囲から拘束するせん断補強筋に相当する水平鋼材
4が一体化し、主筋3が仮固定された内型枠1と外型枠
2を用いて中空の橋脚を完成させる構築方法である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIG. 1, a horizontal steel member 4 corresponding to a shear reinforcing bar for restraining a main bar 3 from the periphery is integrated with the inner form 1 to which the main bar 3 is temporarily fixed as shown in FIG. This is a construction method for completing a hollow pier using the formwork 2.

【0013】図2,図3に示すように内型枠1と外型枠
2は共にプレキャストコンクリートで製作され、現場で
打設されるコンクリート6と一体化して橋脚の一部の躯
体Kとなる。水平鋼材4は内型枠1と外型枠2の片面に
一体化し、その面にはコンクリート6との一体性を確保
するためのジベル5が突設される。主筋3は鉛直方向に
ジベル5に保持される形で内型枠1や外型枠2に仮固定
され、水平鋼材4は主筋3の内型枠1や外型枠2寄り
に、一部がプレキャストコンクリート中に埋設されて水
平方向に配置される。図2,図3の内型枠1,または外
型枠2の片側はプレキャストコンクリートの内部を示し
ている。
As shown in FIGS. 2 and 3, the inner mold 1 and the outer mold 2 are both made of precast concrete, and are integrated with the concrete 6 cast on site to form a part K of the pier. . The horizontal steel material 4 is integrated with one surface of the inner mold frame 1 and the outer mold frame 2, and a dowel 5 for ensuring integrity with the concrete 6 protrudes from the surface. The main reinforcement 3 is temporarily fixed to the inner formwork 1 and the outer formwork 2 while being held by the dowel 5 in the vertical direction, and the horizontal steel 4 is partially moved toward the inner formwork 1 and the outer formwork 2 of the main reinforcement 3. It is buried in precast concrete and placed horizontally. One side of the inner mold 1 or the outer mold 2 in FIGS. 2 and 3 shows the inside of the precast concrete.

【0014】内型枠1と外型枠2は図1,図2に示すよ
うに橋脚の横断面上、それぞれ内周側と外周側で周方向
に隣接して、躯体Kの厚さ方向には互いに対向して施工
済みの、橋脚の躯体K上に組み立てられる。対向する内
型枠1と外型枠2はコンクリート打設時の安定性確保の
ために対向する方向に架設される連結材7によって連結
される。内型枠1と外型枠2の各主筋3は下方に隣接す
る施工済みの、躯体Kとなった内型枠1と外型枠2の各
主筋3とカプラー8やその他の手段により接続され、周
方向に隣接する内型枠1,1と外型枠2,2の各水平鋼
材4,4は両者間に跨るプレート9等を介して互いに接
続される。上下に連続する主筋3,3の継手位置は図3
に示すように主筋3が並列する方向に例えば1本置きに
ずらされる。
As shown in FIGS. 1 and 2, the inner mold 1 and the outer mold 2 are circumferentially adjacent to each other on the inner circumferential side and the outer circumferential side on the cross section of the pier, respectively, in the thickness direction of the frame K. Are assembled on a bridge pier body K that has been installed facing each other. The opposing inner mold 1 and outer mold 2 are connected by a connecting member 7 installed in the opposing direction to ensure stability during concrete casting. The main reinforcements 3 of the inner formwork 1 and the outer formwork 2 are connected to the main reinforcements 3 of the inner formwork 1 and the outer formwork 2 which have been constructed adjacent to the lower side and have become the skeleton K by couplers 8 and other means. The horizontal steel members 4, 4 of the inner mold frames 1, 1 and the outer mold frames 2, 2, which are adjacent to each other in the circumferential direction, are connected to each other via a plate 9 or the like straddling therebetween. Fig. 3 shows the joint positions of the main bars 3
As shown in (1), for example, every other main bar 3 is shifted in the direction in which the main bars 3 are arranged in parallel.

【0015】内型枠1と外型枠2にはまた、図3,図4
に示すように内型枠1と外型枠2の運搬と組み立ての便
宜のための、及び2次コンクリート打設時の応力分担の
ための鉛直鋼材10が一体化する。鉛直鋼材10は水平鋼材
4の、対向する外型枠2や内型枠1側に配置され、内型
枠1と外型枠2は鉛直鋼材10と連結材7によってコンク
リート6の打設時に起立しながら対向した状態を維持す
る。また上下に隣接する施工区間のコンクリート6の打
ち継ぎ部分には両施工区間に跨る連結鋼材11が配置さ
れ、下側半分が下方の躯体K中に埋め込まれており、内
型枠1と外型枠2は鉛直鋼材10が連結鋼材11に接合され
ることにより設置時の躯体K上での安定性を確保する。
連結鋼材11の上側半分はコンクリート6の打設時にコン
クリート6中に埋め込まれる。
The inner mold 1 and the outer mold 2 are also shown in FIGS.
As shown in FIG. 7, a vertical steel material 10 is integrated for the convenience of transporting and assembling the inner mold frame 1 and the outer mold frame 2 and for sharing stress at the time of placing the secondary concrete. The vertical steel material 10 is disposed on the side of the outer steel frame 2 and the inner metal frame 1 facing the horizontal steel material 4, and the inner metal frame 1 and the outer metal frame 2 stand when the concrete 6 is poured by the vertical steel material 10 and the connecting member 7. While maintaining the facing state. In addition, a connecting steel member 11 straddling both construction sections is arranged at a joint portion of the concrete 6 in the construction section adjacent vertically, and the lower half is embedded in the lower frame K, and the inner form 1 and the outer mold are formed. The frame 2 secures stability on the skeleton K at the time of installation by joining the vertical steel material 10 to the connecting steel material 11.
The upper half of the connection steel 11 is embedded in the concrete 6 when the concrete 6 is poured.

【0016】橋脚の躯体Kの肉厚部分を示す図5〜図9
により一施工区間の施工手順を説明する。図5〜図9及
び図11〜図14は断面図になるが、便宜的に一部を立面図
として示す。
FIGS. 5 to 9 show the thick portions of the frame K of the pier.
The construction procedure of one construction section will be described. Although FIGS. 5 to 9 and FIGS. 11 to 14 are sectional views, some of them are shown as elevation views for convenience.

【0017】施工済みの躯体K上に、内型枠1と外型枠
2を上記要領で設置し(図5)、水平鋼材4,4を互い
に接続すると共に、対向する内型枠1と外型枠2を連結
材7によって連結する(図6)。続いて内型枠1と外型
枠2の各主筋3を躯体K上から突出している主筋3と互
いに接続した後(図7)、内型枠1と外型枠2とで挟ま
れた空間内にコンクリート6を打設する(図8)。コン
クリート6の硬化後、更に図5から図8までの手順を繰
り返して橋脚が構築される。図9に示すようにコンクリ
ート6の硬化によって躯体Kの一部となった内型枠1
の、橋脚の内周側には後述する作業台13の上部架台17や
下部架台16が載るブラケット12が突設される。
The inner frame 1 and the outer frame 2 are installed on the completed skeleton K in the above-described manner (FIG. 5), and the horizontal steel members 4, 4 are connected to each other, and the inner frame 1 and the outer frame are opposed to each other. The form 2 is connected by the connecting member 7 (FIG. 6). Subsequently, after connecting the main reinforcements 3 of the inner formwork 1 and the outer formwork 2 to the main reinforcements 3 protruding from the skeleton K (FIG. 7), a space sandwiched between the inner formwork 1 and the outer formwork 2. Concrete 6 is poured into the inside (FIG. 8). After the concrete 6 has hardened, the steps of FIGS. 5 to 8 are further repeated to construct the pier. As shown in FIG. 9, the inner formwork 1 which has become a part of the skeleton K by the hardening of the concrete 6.
On the inner peripheral side of the pier, a bracket 12 on which an upper pedestal 17 and a lower pedestal 16 of a worktable 13 to be described later are mounted protrudes.

【0018】請求項2記載の発明は施工済みの躯体Kの
外周に沿って昇降する昇降機24によって内型枠1と外型
枠2を荷揚げする一方、頂部に揚重機14を持つポスト15
と、ポスト15を支持する下部架台16と、ポスト15に沿っ
て下部架台16に対して昇降可能な上部架台17からなる作
業台13を一施工区間だけ施工する毎に橋脚の内部を利用
して上昇させる方法であり、請求項1記載の方法を実施
するために適用される施工方法である。
According to a second aspect of the present invention, the inner form 1 and the outer form 2 are unloaded by the lift 24 which moves up and down along the outer periphery of the completed frame K, while the post 15 having the hoist 14 at the top.
And using the inside of the pier each time a workbench 13 consisting of a lower gantry 16 supporting the post 15 and an upper gantry 17 that can move up and down with respect to the lower gantry 16 along the post 15 is constructed only for one construction section. This is a construction method applied to carry out the method according to claim 1.

【0019】作業台13のポスト15には上部架台17を引き
上げるリフトアップ装置18が設置され、リフトアップ装
置18と上部架台17間には双方に接続される引張材19が架
設される。同様に上部架台17には下部架台16を引き上げ
るリフトアップ装置20が設置され、リフトアップ装置20
と下部架台16間に引張材21が架設される。
The post 15 of the work table 13 is provided with a lift-up device 18 for lifting the upper pedestal 17, and a tension member 19 connected to both is installed between the lift-up device 18 and the upper pedestal 17. Similarly, a lift-up device 20 that lifts the lower mount 16 is installed on the upper mount 17, and the lift-up device 20
A tension member 21 is erected between the cradle and the lower gantry 16.

【0020】作業台13のポスト15の頂部上には橋脚の全
断面を覆う屋根22が架設され、屋根22の外周からは足場
23が懸垂する。作業台13上は屋根22によって天候の影響
を受けない環境下に置かれ、施工は雨天による中断を生
ずることなく遂行される。内型枠1と外型枠2の組み立
てと、主筋3と水平鋼材4の接続及びコンクリート6の
打設作業は上部架台17と足場23を利用して行われる。
A roof 22 covering the entire cross section of the pier is erected on the top of the post 15 of the workbench 13.
23 hangs up. The workbench 13 is placed in an environment unaffected by the weather by the roof 22, and the construction is performed without interruption due to rain. The assembling of the inner form 1 and the outer form 2, the connection of the main reinforcement 3 and the horizontal steel 4, and the placing of the concrete 6 are performed using the upper base 17 and the scaffold 23.

【0021】作業台13の上昇は上記した、施工済みの躯
体Kの内面側に突設されたブラケット12に作業台13の上
部架台17と下部架台16を支持させたまま(図10)、一施
工区間の施工が終了する毎に、作業台13の荷重を下部架
台16に負担させた状態で上部架台17を一施工区間分上昇
させ、上部架台17を上方の躯体Kの内面に突設されたブ
ラケット12に支持させた後(図11)、作業台13の荷重を
上部架台17に負担させた状態で下部架台16を上昇させて
上部架台17の下方位置の躯体Kの内面に支持させる(図
12)、という要領で行われる。作業台13の上昇毎に、請
求項1記載発明の内型枠1と外型枠2の組み立てからコ
ンクリート6の打設までの作業が行われる(図13)。
The work table 13 is raised while the upper frame 17 and the lower frame 16 of the work table 13 are supported by the brackets 12 protruding from the inner surface of the completed frame K (FIG. 10). Each time the construction of the construction section is completed, the upper gantry 17 is raised by one construction section while the load of the work table 13 is loaded on the lower gantry 16, and the upper gantry 17 is protruded from the inner surface of the upper frame K. After being supported by the bracket 12 (FIG. 11), the lower gantry 16 is raised with the load of the work table 13 being applied to the upper gantry 17, and is supported on the inner surface of the frame K below the upper gantry 17 ( Figure
12). Every time the work table 13 is raised, the work from assembling the inner formwork 1 and the outer formwork 2 according to the first aspect of the invention to placing concrete 6 is performed (FIG. 13).

【0022】昇降機24は図14に示すように躯体Kの外周
側に高さ方向に敷設された軌道25に沿って昇降可能に設
置され、内型枠1と外型枠2の上部架台17上への荷揚げ
を行う。上部架台17上に荷揚げされた内型枠1と外型枠
2は作業台13の揚重機14によって躯体K上に吊り込まれ
る。昇降機24と揚重機14の機能は独立するため両者は同
時に稼働できる。
As shown in FIG. 14, the elevator 24 is installed so as to be able to move up and down along a track 25 laid in the height direction on the outer peripheral side of the frame K, and is mounted on the upper frame 17 of the inner mold 1 and the outer mold 2. Unloading to. The inner form 1 and the outer form 2 unloaded on the upper gantry 17 are suspended on the frame K by the lifting machine 14 of the work table 13. Since the functions of the lift 24 and the hoist 14 are independent, both can operate simultaneously.

【0023】橋脚は請求項1記載発明と請求項2記載発
明を並行して実施することにより構築される。
The pier is constructed by carrying out the invention of claim 1 and the invention of claim 2 in parallel.

【0024】[0024]

【発明の効果】請求項1記載発明はせん断補強筋に相当
する水平鋼材を一体化し、主筋を仮固定したプレキャス
トコンクリート製の内型枠と外型枠を用い、両者の設置
と両者間へのコンクリートの打設を繰り返して橋脚を構
築する方法であるため、現場での配筋作業と、脱型及び
盛り替えが省略され、作業の省力化により施工の進捗を
図ることができる。
According to the first aspect of the present invention, a horizontal steel material corresponding to a shear reinforcing bar is integrated, and an inner and an outer frame made of precast concrete in which a main bar is temporarily fixed are used. Since the method is a method of constructing a bridge pier by repeatedly placing concrete, it is possible to omit the rebar arrangement work, the removal of the mold and the re-arrangement at the site, and to promote the construction by labor saving of the work.

【0025】請求項2記載発明は内型枠と外型枠の荷揚
げを昇降機が行い、荷揚げされた内型枠と外型枠の組み
立てを作業台の揚重機が行う方法であるため、荷揚げ作
業と躯体上での構築作業を並行して行うことが可能とな
り、稼働効率と作業能率が向上し、工期の短縮化が図ら
れる。
The second aspect of the present invention is a method in which the lifting and lowering of the inner formwork and the outer formwork are performed by the lift, and the lifting machine of the worktable performs the assembly of the unloaded inner formwork and the outer formwork. And the construction work on the skeleton can be performed in parallel, thereby improving the operation efficiency and work efficiency, and shortening the construction period.

【0026】特に請求項1記載発明と請求項2記載発明
を組み合わせて実施することにより施工進行上の無駄が
なくなるため施工進捗による工期短縮の効果は大きい。
In particular, by combining the invention of claim 1 and the invention of claim 2, there is no waste in the progress of construction, so that the effect of shortening the construction period by the progress of construction is great.

【図面の簡単な説明】[Brief description of the drawings]

【図1】橋脚の構築要領を示した斜視図である。FIG. 1 is a perspective view showing a construction procedure of a pier.

【図2】内型枠,または外型枠とその設置状況を示した
斜視図である。
FIG. 2 is a perspective view showing an inner mold frame or an outer mold frame and an installation state thereof.

【図3】内型枠,または外型枠を示した立面図である。FIG. 3 is an elevational view showing an inner formwork or an outer formwork.

【図4】図3の平面図である。FIG. 4 is a plan view of FIG. 3;

【図5】施工済みの躯体上への内型枠の設置時の様子を
示した立面図である。
FIG. 5 is an elevational view showing a state when the inner formwork is installed on the constructed skeleton.

【図6】内型枠と外型枠を連結し、水平鋼材を接続した
ときの様子を示した立面図である。
FIG. 6 is an elevational view showing a state where the inner mold and the outer mold are connected and a horizontal steel material is connected.

【図7】主筋を接続したときの様子を示した立面図であ
る。
FIG. 7 is an elevation view showing a state when main bars are connected.

【図8】コンクリートを打設したときの様子を示した立
面図である。
FIG. 8 is an elevational view showing a state when concrete is cast.

【図9】ブラケットを突設したときの様子を示した立面
図である。
FIG. 9 is an elevation view showing a state where a bracket is protruded.

【図10】コンクリートの打設が完了した時点の作業台
の様子を示した立面図である。
FIG. 10 is an elevational view showing the state of the workbench at the time when concrete placement has been completed.

【図11】上部架台を上昇させたときの様子を示した立
面図である。
FIG. 11 is an elevation view showing a state when the upper gantry is raised.

【図12】下部架台を上昇させたときの様子を示した立
面図である。
FIG. 12 is an elevational view showing a state when the lower gantry is raised.

【図13】作業台を上昇させた後のコンクリートの打設
が完了したときの様子を示した立面図である。
FIG. 13 is an elevational view showing a state in which concrete placement after raising the work table is completed.

【図14】昇降機と作業台の関係を示した立面図であ
る。
FIG. 14 is an elevational view showing the relationship between the elevator and the workbench.

【符号の説明】[Explanation of symbols]

1……内型枠、2……外型枠、3……主筋、4……水平
鋼材、5……ジベル、6……コンクリート、7……連結
材、8……カプラー、9……プレート、10……鉛直鋼
材、11……連結鋼材、12……ブラケット、13……作業
台、14……揚重機、15……ポスト、16……下部架台、17
……上部架台、18……リフトアップ装置、19……引張
材、20……リフトアップ装置、21……引張材、22……屋
根、23……足場、24……昇降機、25……軌道、K……躯
体。
1 ... inner mold, 2 ... outer mold, 3 ... main reinforcement, 4 ... horizontal steel, 5 ... dowel, 6 ... concrete, 7 ... connecting material, 8 ... coupler, 9 ... plate , 10… vertical steel, 11… connecting steel, 12… bracket, 13… working table, 14… lifting machine, 15… post, 16… lower pedestal, 17
…… Top stand, 18… lift device, 19 …… tension member, 20 …… lift device, 21 …… tension member, 22 …… roof, 23 …… scaffold, 24 …… elevator, 25 …… track , K ... The skeleton.

───────────────────────────────────────────────────── フロントページの続き (72)発明者 福島 重美 東京都新宿区荒木町13番地の4 住友建 設株式会社内 (56)参考文献 特開 平7−138914(JP,A) 特開 平5−280012(JP,A) 特開 平6−146218(JP,A) (58)調査した分野(Int.Cl.6,DB名) E01D 21/00 E01D 19/02────────────────────────────────────────────────── ─── Continuation of the front page (72) Inventor Shigemi Fukushima 13-4 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd. (56) References JP-A-7-138914 (JP, A) 5-280012 (JP, A) JP-A-6-146218 (JP, A) (58) Fields investigated (Int. Cl. 6 , DB name) E01D 21/00 E01D 19/02

Claims (2)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】 片面に、水平方向に主筋を周囲から拘束
する水平鋼材が一体化し、水平鋼材に包囲される側に鉛
直方向に主筋が仮固定されたプレキャストコンクリート
製の内型枠と外型枠を橋脚の横断面上、それぞれ内周側
と外周側で周方向に隣接させ、橋脚の躯体の厚さ方向に
互いに対向させて施工済みの、橋脚の躯体上に組み立
て、周方向に隣接する内型枠と外型枠の各水平鋼材を互
いに接続すると共に、内型枠と外型枠の各主筋を下方の
施工済みの各主筋に接続した後、内型枠と外型枠とで挟
まれた空間内にコンクリートを打設し、コンクリートの
硬化後、更にその上方への内型枠と外型枠の組み立てか
らコンクリートの打設までの手順を繰り返す橋脚の構築
方法。
1. A precast concrete inner mold and an outer mold having a horizontal steel material integrated on one side thereof for horizontally restraining a main reinforcement from the periphery and a main reinforcement temporarily fixed in a vertical direction on a side surrounded by the horizontal steel material. Assemble the frame on the pier's skeleton, which has been constructed so that the frames are circumferentially adjacent to each other on the inner and outer sides on the cross section of the pier, and opposed to each other in the thickness direction of the pier's skeleton. After connecting the horizontal steel materials of the inner formwork and the outer formwork to each other, and connecting the main reinforcements of the inner formwork and the outer formwork to the main reinforcements constructed below, sandwich the inner formwork and the outer formwork. A method of constructing a bridge pier in which concrete is poured into a closed space, and after the hardening of the concrete, the procedure from assembling the inner formwork and the outer formwork further up to placing the concrete is repeated.
【請求項2】 請求項1記載の方法を実施するための施
工方法であり、施工済みの、橋脚となる躯体の外周側に
高さ方向に敷設された軌道に沿って昇降する昇降機を用
いて請求項1に記載の内型枠と外型枠を地上から搬送す
る一方、頂部に揚重機を持つポストと、ポストを支持す
る下部架台と、ポストに沿って下部架台に対して昇降可
能な上部架台からなる作業台を施工済みの躯体の内面に
支持させたまま、一施工区間の施工が終了する毎に上部
架台を上昇させて上方の躯体内面に支持させた後、下部
架台を上昇させて上部架台の下方位置の躯体内面に支持
させる、という手順を繰り返して作業台を上昇させる橋
脚の施工方法。
2. A construction method for carrying out the method according to claim 1, wherein the construction is carried out by using an elevator that moves up and down along a track laid in the height direction on the outer peripheral side of a skeleton to be a pier. A post having a hoist at the top, a lower frame supporting the post, and an upper portion capable of moving up and down with respect to the lower frame along the post while conveying the inner frame and the outer frame according to claim 1 from the ground. With the work table consisting of the gantry supported on the inner surface of the constructed skeleton, the upper gantry is raised every time the construction of one construction section is completed and supported on the upper skeleton surface, and then the lower gantry is raised. A method of constructing a pier that raises the workbench by repeating the procedure of supporting it on the inner surface of the skeleton below the upper gantry.
JP7038259A 1995-02-27 1995-02-27 Bridge pier construction method and construction method Expired - Lifetime JP2790986B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7038259A JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7038259A JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Publications (2)

Publication Number Publication Date
JPH08232212A JPH08232212A (en) 1996-09-10
JP2790986B2 true JP2790986B2 (en) 1998-08-27

Family

ID=12520328

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7038259A Expired - Lifetime JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Country Status (1)

Country Link
JP (1) JP2790986B2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BG64524B1 (en) * 1997-09-23 2005-06-30 Pfizer Products Inc. Resorcinol derivatives
BG65146B1 (en) * 1999-03-22 2007-04-30 Pfizer Inc. Pharmaceutical composition for external application and use thereof as a skin lightening agent or for reducing of human pigmentation

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102304892B (en) * 2011-07-29 2013-06-12 清华大学 External energy-consumption self-resetting bridge pier stud structure system and realization method thereof
CN103510469B (en) * 2012-06-28 2015-06-10 中铁二十五局集团建筑安装工程有限公司 Construction method for manufacturing thin-walled hollow pier
CN103498436B (en) * 2013-10-18 2015-11-18 清华大学 A kind of interchangeable bridge pier anti-collision protective device and mounting method thereof
CN104846744B (en) * 2015-03-19 2017-01-11 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN105926449B (en) * 2016-05-04 2017-10-17 中国十九冶集团有限公司 The method for dismounting of Bridge High-pier overmolded template
CN106677069B (en) * 2016-12-28 2018-04-06 杭州江润科技有限公司 A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN107366230B (en) * 2017-07-19 2018-10-23 中国一冶集团有限公司 A kind of bridge pier column rollover board and construction method
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN107881902A (en) * 2017-10-16 2018-04-06 中国水利水电第四工程局有限公司 Concrete construction method and mirror surface concrete pier stud
CN109024251A (en) * 2018-10-10 2018-12-18 南京林业大学 A kind of prefabrication and assembly construction folded type reinforced concrete bridge pier structure
CN111021258B (en) * 2019-12-24 2021-07-13 广东省基础工程集团有限公司 Assembly type buttress pouring die carrier for bridge building
CN111593676A (en) * 2020-06-22 2020-08-28 中铁十八局集团有限公司 Construction method of thin-wall hollow pier
CN112627034A (en) * 2020-12-10 2021-04-09 上海宝冶集团有限公司 Synchronous construction method for turning over mold of high pier of bridge
CN113494051B (en) * 2021-08-09 2022-11-01 中铁大桥局集团有限公司 Construction method for block-by-block prefabricated installation of variable-section inclined tower steel reinforcement framework
CN113699877B (en) * 2021-10-09 2023-03-31 四川省交通勘察设计研究院有限公司 Steel-concrete composite structure pier suitable for high-intensity area and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3368483B2 (en) * 1993-11-11 2003-01-20 大成建設株式会社 Bridge pier construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BG64524B1 (en) * 1997-09-23 2005-06-30 Pfizer Products Inc. Resorcinol derivatives
BG65146B1 (en) * 1999-03-22 2007-04-30 Pfizer Inc. Pharmaceutical composition for external application and use thereof as a skin lightening agent or for reducing of human pigmentation

Also Published As

Publication number Publication date
JPH08232212A (en) 1996-09-10

Similar Documents

Publication Publication Date Title
JP2790986B2 (en) Bridge pier construction method and construction method
JP4252177B2 (en) Steel / concrete composite structure pier construction method
JP3013688B2 (en) Construction method of concrete structure
JPH0959932A (en) Construction method of column head of overhanging erection girder bridge
JP5003253B2 (en) RC beam construction method
CN114016417A (en) Top cover plate capping construction bottom template and method for oblique hollow pier
JPH0657710A (en) Construction of concrete main tower
JP3586121B2 (en) Mixed structure of reinforced concrete column and steel beam and its construction method
JP2731907B2 (en) Construction work method on sloping land
JP2812177B2 (en) Bridge pier construction method by slip form method
JPH0667511U (en) Electric automatic special support lifting device
JPH11323838A (en) Construction method of bridge
JP2000248632A (en) Floor climbing method of tower crane
JPH10131508A (en) Material transport device of temporarily set curing body
JPH05148817A (en) Construction of pc bridge
JP3690463B2 (en) Construction method of viaduct
JPH10102423A (en) Pca form and construction method of pier using the same pca form
JP2001193290A (en) Seismic isolation method for existing building
JPH0642184A (en) Construction of skeleton using half precast floor board
JPH0959924A (en) Slab form construction method
JP2761526B2 (en) How to build structures
JP2000257266A (en) Building skeleton constructing method
JPH0932295A (en) Construction method for concrete structure
JPS63312437A (en) Construction of underground structure
JPH1122106A (en) Composite bending principal member of concrete structure and constructing method of concrete structure by using composite bending principal member

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090612

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090612

Year of fee payment: 11

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100612

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100612

Year of fee payment: 12

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110612

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110612

Year of fee payment: 13

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120612

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120612

Year of fee payment: 14

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130612

Year of fee payment: 15

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term