JPH08232212A - Pier constructing method and execution method - Google Patents

Pier constructing method and execution method

Info

Publication number
JPH08232212A
JPH08232212A JP3825995A JP3825995A JPH08232212A JP H08232212 A JPH08232212 A JP H08232212A JP 3825995 A JP3825995 A JP 3825995A JP 3825995 A JP3825995 A JP 3825995A JP H08232212 A JPH08232212 A JP H08232212A
Authority
JP
Japan
Prior art keywords
pier
concrete
construction
mold
skeleton
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
JP3825995A
Other languages
Japanese (ja)
Other versions
JP2790986B2 (en
Inventor
Shinichiro Kumagai
紳一郎 熊谷
Motofumi Saito
基文 斉藤
Kazumichi Sasaki
和道 佐々木
Shigemi Fukushima
重美 福島
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sumitomo Construction Co Ltd
Original Assignee
Sumitomo Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sumitomo Construction Co Ltd filed Critical Sumitomo Construction Co Ltd
Priority to JP7038259A priority Critical patent/JP2790986B2/en
Publication of JPH08232212A publication Critical patent/JPH08232212A/en
Application granted granted Critical
Publication of JP2790986B2 publication Critical patent/JP2790986B2/en
Anticipated expiration legal-status Critical
Expired - Lifetime legal-status Critical Current

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

PURPOSE: To reduce the construction period by improving the efficiency of execution of a pier. CONSTITUTION: An inner mold 1 and an outer mold 2 made of pre-cast concrete where a horizontal steel to restrict a main reinforcement 3 is integrated with one side and the main reinforcement 3 is temporarily fixed are set adjacent to each other in the circumferential direction on the transverse section of the pier, and assembled on an executed skeleton K opposite to each other, and the respective main reinforcements 3 of the inner mold 1 and the outer mold 2 are connected to the respective executed main reinforcements at the lower position. Then, the concrete is placed in the space to be held by the inner mold 1 and the outer mold 2, and the concrete is solidified. The procedure of assembling the inner mold 1 and the outer mold 2 to the upper position of it and placing the concrete is further repeated.

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】この発明は中空の橋脚を複数の施
工区分に分割して構築する構築方法とその方法を実施す
るための施工方法に関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a construction method for constructing a hollow bridge pier by dividing it into a plurality of construction sections and a construction method for implementing the method.

【0002】[0002]

【従来技術及び発明が解決しようとする課題】橋脚の施
工は一施工区間単位では主筋とそれを周囲から拘束する
せん断補強筋を配筋し、型枠を組み立ててコンクリート
を打設する、という要領で行われ、全体的には転用可能
な型枠を用い、型枠の組み立て,解体と盛り替えを繰り
返して上方へ移動する方法が一般的であるが、型枠の組
み立てと解体には手間と時間を要するため従来方法は能
率が悪い。特に橋脚の施工区間によって断面が変化する
場合には型枠の加工が必要になるため能率の低下は著し
い。また主筋は揚重機を用いることにより一施工区間分
まとめて吊り上げ、順次配筋することができるが、せん
断補強筋は単一の鉄筋として予め組み立てておくことが
できないためその配筋作業は一区間での施工遅延の原因
になっている。
2. Description of the Related Art In the construction of a pier, a main pier and a shear reinforcing bar that constrains it from the surroundings are arranged in each construction section, and a form is assembled and concrete is placed. The general method is to use a reusable mold, and repeat the process of assembling, dismantling, and refilling the form, and moving it upward. However, it takes time and effort to assemble and dismantle the form. The conventional method is inefficient because it takes time. In particular, when the cross section changes depending on the construction section of the pier, it is necessary to process the formwork, resulting in a marked decrease in efficiency. Also, the main bar can be lifted together for one construction section by using a lifting machine and arranged sequentially, but since the shear reinforcement bar cannot be preassembled as a single reinforcing bar, the bar arrangement work is one section. It is a cause of delay in construction.

【0003】高橋脚では型枠や鉄筋等の荷揚げにタワー
クレーンが使用されるが、タワークレーンは躯体上での
型枠と鉄筋の吊り込みにも使用されるため巻き上げ能力
が施工の進捗に影響し、その影響は橋脚高が大きくなる
程大きい。橋脚高の増加に伴い、風の影響も加わるため
稼働効率の低下を招き、稼働効率が低下すれば天候の影
響を受ける可能性が増すため施工の遅延につながる。
At a high pier, a tower crane is used for unloading forms and reinforcing bars, but since the tower crane is also used for suspending the forms and reinforcing bars on the skeleton, the hoisting ability affects the progress of construction. However, the effect is greater as the pier height increases. As the bridge pier height increases, the effect of wind also causes a decrease in operating efficiency. If the operating efficiency decreases, the possibility of being affected by the weather increases, leading to a delay in construction.

【0004】この発明は上記背景を踏まえてなされたも
ので、施工の進捗を図る構築方法とそれを実施するため
の施工方法を提案するものである。
The present invention has been made in view of the above background, and proposes a construction method for promoting the progress of construction and a construction method for implementing the construction method.

【0005】[0005]

【課題を解決するための手段】本発明では型枠を埋設型
枠にし、型枠にせん断補強筋に相当する部材を一体化さ
せ、主筋を仮固定しておくことにより一施工区間におけ
る施工を単純化し、施工の進捗を図る。
According to the present invention, the formwork is an embedded formwork, a member corresponding to a shear reinforcing bar is integrated with the formwork, and the main bar is temporarily fixed so that construction in one construction section can be performed. Simplify the progress of construction.

【0006】型枠には橋脚の横断面上、内周側に配置さ
れる内型枠と外周側に配置される外型枠があり、内型枠
と外型枠は共に、片面に主筋を周囲から拘束する水平鋼
材が一体化した状態でプレキャストコンクリートで製作
される。水平鋼材は水平方向に配置される。主筋は水平
鋼材に包囲される側に鉛直方向に仮固定される。
The formwork has an inner formwork arranged on the inner peripheral side and an outer formwork arranged on the outer peripheral side in the cross section of the pier, and both the inner formwork and the outer formwork have a main bar on one side. It is made of precast concrete in a state where horizontal steel materials restrained from the surroundings are integrated. Horizontal steel products are arranged horizontally. The main bar is temporarily fixed in the vertical direction on the side surrounded by the horizontal steel material.

【0007】内型枠と外型枠は橋脚の横断面上、周方向
にそれぞれ隣接し、橋脚の躯体の厚さ方向に互いに対向
して施工済みの、橋脚の躯体上に組み立てられる。橋脚
の内周側と外周側で周方向に隣接する内型枠と外型枠の
各水平鋼材は互いに接続され、内型枠と外型枠の各主筋
は下方の施工済みの各主筋に接続される。その後、内型
枠と外型枠とで挟まれた空間内にコンクリートが打設さ
れて一施工区間の作業は終了する。コンクリートの硬化
後、更にその上方への内型枠と外型枠の組み立てからコ
ンクリートの打設までの作業が繰り返されて橋脚が完成
する。
The inner form frame and the outer form frame are adjacent to each other in the circumferential direction on the cross section of the pier, and are assembled on the already constructed pier frame so as to face each other in the thickness direction of the pier frame. Horizontal steel members of the inner and outer molds that are adjacent to each other in the circumferential direction on the inner and outer peripheries of the pier are connected to each other, and the main bars of the inner and outer molds are connected to the main bars that have been constructed below. To be done. After that, concrete is poured into the space sandwiched between the inner mold and the outer mold, and the work of one construction section is completed. After the concrete is hardened, the work from the assembly of the inner and outer molds above it to the placing of concrete is repeated to complete the pier.

【0008】内型枠と外型枠に予め水平鋼材が付属し、
主筋が仮固定されることにより個々の配筋作業が省略さ
れ、内型枠と外型枠がコンクリートの打設後にそのまま
橋脚の躯体の一部になることにより脱型と盛り替え、及
び再組み立ての手間も省略され、現場作業の省力化が図
られる。一施工区間における施工は内型枠と外型枠の組
み立てと主筋の接続、及びコンクリートの打設によって
完了するため施工の大幅な進捗が図られる。
Horizontal steel is attached to the inner and outer molds in advance,
Temporary fixing of the main bar eliminates the work of individual bar arrangement, and the inner and outer forms become part of the pier's skeleton as they are after the concrete has been cast, so that demolding and reassembling and reassembly are possible. The labor of is also omitted, and the labor in the field can be saved. Since the construction in one construction section is completed by assembling the inner and outer forms, connecting the main bars, and placing concrete, the construction progress can be made significantly.

【0009】施工は施工済みの、橋脚となる躯体の外周
に沿って昇降する昇降機に加え、頂部に揚重機を持つポ
ストと、ポストを支持する下部架台と、ポストに沿って
下部架台に対して昇降可能な上部架台からなる作業台を
用いて実施される。昇降機は躯体の外周側に高さ方向に
敷設された軌道に沿って昇降し、内型枠と外型枠を地上
から上部架台上まで搬送する。作業台は高さ方向に一定
距離だけ施工する毎に躯体の内部を利用して上昇し、上
部架台上まで荷揚げされた内型枠と外型枠の組み立てか
らコンクリート打設までの作業のために利用される。
For the construction, in addition to the elevator that has already been constructed and is moved up and down along the outer periphery of the pier body, a post with a lifting machine at the top, a lower mount for supporting the post, and a lower mount along the post It will be carried out using a workbench consisting of an upper platform that can be raised and lowered. The elevator moves up and down along a track laid in the height direction on the outer peripheral side of the skeleton, and conveys the inner mold and the outer mold from the ground to the upper pedestal. The workbench rises using the inside of the skeleton every time it is installed a certain distance in the height direction, and for work from assembling of the inner and outer formwork unloaded to the upper platform to concrete placement. Used.

【0010】作業台の一施工区間分の上昇は施工済みの
躯体の内面に作業台を支持させたまま、一施工区間の施
工が終了する毎に上部架台を上昇させて上方の躯体内面
に支持させた後、下部架台を上昇させて上部架台の下方
位置の躯体内面に支持させる、という要領で行われ、作
業台の上昇後、上部架台上まで荷揚げされている内型枠
と外型枠の組み立てが作業台のポストに付属した揚重機
によって行われる。
When the work table is raised by one construction section, the work platform is supported on the inner surface of the completed construction body, and the upper mount is raised every time the construction of one construction section is completed and the work platform is supported on the inner surface of the upper body. After that, the lower pedestal is raised to be supported on the inner surface of the body below the upper pedestal, and after the work platform is raised, the inner and outer molds that have been unloaded to the upper pedestal Assembly is done by a hoist attached to a workbench post.

【0011】内型枠と外型枠の荷揚げを昇降機が行い、
荷揚げされた内型枠と外型枠の組み立てを作業台の揚重
機が行い、それぞれの機能が分離することにより荷揚げ
作業と、躯体上での構築作業を並行して行うことが可能
となり、稼働効率と作業能率が向上し、工期の短縮化が
図られる。
The elevator unloads the inner and outer molds,
The hoisting machine on the workbench assembles the unloading inner and outer molds, and by separating the functions of each, it is possible to carry out the unloading work and the construction work on the skeleton in parallel. The efficiency and work efficiency are improved, and the construction period is shortened.

【0012】[0012]

【実施例】請求項1記載の発明は図1に示すように主筋
3を周囲から拘束するせん断補強筋に相当する水平鋼材
4が一体化し、主筋3が仮固定された内型枠1と外型枠
2を用いて中空の橋脚を完成させる構築方法である。
DETAILED DESCRIPTION OF THE PREFERRED EMBODIMENTS As shown in FIG. 1, the invention according to claim 1 integrates a horizontal steel material 4 corresponding to a shear reinforcing bar for restraining the main reinforcement 3 from the surroundings, and the main reinforcement 3 is temporarily fixed to the inner form 1 and the outside. It is a construction method for completing a hollow pier using the formwork 2.

【0013】図2,図3に示すように内型枠1と外型枠
2は共にプレキャストコンクリートで製作され、現場で
打設されるコンクリート6と一体化して橋脚の一部の躯
体Kとなる。水平鋼材4は内型枠1と外型枠2の片面に
一体化し、その面にはコンクリート6との一体性を確保
するためのジベル5が突設される。主筋3は鉛直方向に
ジベル5に保持される形で内型枠1や外型枠2に仮固定
され、水平鋼材4は主筋3の内型枠1や外型枠2寄り
に、一部がプレキャストコンクリート中に埋設されて水
平方向に配置される。図2,図3の内型枠1,または外
型枠2の片側はプレキャストコンクリートの内部を示し
ている。
As shown in FIGS. 2 and 3, both the inner mold 1 and the outer mold 2 are made of precast concrete and integrated with the concrete 6 cast on site to form a frame K of a part of the pier. . The horizontal steel material 4 is integrated with one surface of the inner mold 1 and the outer mold 2, and a jibber 5 is provided on the surface of the horizontal steel material 4 so as to ensure the integrity with the concrete 6. The main bars 3 are temporarily fixed to the inner mold 1 and the outer mold 2 while being held by the dowels 5 in the vertical direction, and the horizontal steel material 4 is partly near the inner mold 1 and the outer mold 2 of the main bar 3 and partly. It is embedded in precast concrete and placed horizontally. One side of the inner formwork 1 or the outer formwork 2 in FIGS. 2 and 3 shows the inside of the precast concrete.

【0014】内型枠1と外型枠2は図1,図2に示すよ
うに橋脚の横断面上、それぞれ内周側と外周側で周方向
に隣接して、躯体Kの厚さ方向には互いに対向して施工
済みの、橋脚の躯体K上に組み立てられる。対向する内
型枠1と外型枠2はコンクリート打設時の安定性確保の
ために対向する方向に架設される連結材7によって連結
される。内型枠1と外型枠2の各主筋3は下方に隣接す
る施工済みの、躯体Kとなった内型枠1と外型枠2の各
主筋3とカプラー8やその他の手段により接続され、周
方向に隣接する内型枠1,1と外型枠2,2の各水平鋼
材4,4は両者間に跨るプレート9等を介して互いに接
続される。上下に連続する主筋3,3の継手位置は図3
に示すように主筋3が並列する方向に例えば1本置きに
ずらされる。
As shown in FIGS. 1 and 2, the inner form 1 and the outer form 2 are circumferentially adjacent to each other on the inner peripheral side and the outer peripheral side in the transverse section of the pier, respectively, in the thickness direction of the frame K. Are assembled on the frame K of the pier, which has been installed facing each other. The inner mold 1 and the outer mold 2 which are opposed to each other are connected by a connecting member 7 which is installed in a direction opposite to each other in order to ensure stability when pouring concrete. Each main bar 3 of the inner mold 1 and the outer mold 2 is connected by a coupler 8 and other means with each main bar 3 of the inner mold 1 and the outer mold 2 which have been constructed and are adjacent to each other, and which have become the body K. The horizontal steel materials 4 and 4 of the inner molds 1 and 1 and the outer molds 2 and 2 which are adjacent to each other in the circumferential direction are connected to each other via a plate 9 or the like extending therebetween. The joint positions of the main bars 3 and 3 that continue vertically are shown in Fig. 3.
As shown in, the main bars 3 are displaced in the parallel direction, for example, every other one.

【0015】内型枠1と外型枠2にはまた、図3,図4
に示すように内型枠1と外型枠2の運搬と組み立ての便
宜のための、及び2次コンクリート打設時の応力分担の
ための鉛直鋼材10が一体化する。鉛直鋼材10は水平鋼材
4の、対向する外型枠2や内型枠1側に配置され、内型
枠1と外型枠2は鉛直鋼材10と連結材7によってコンク
リート6の打設時に起立しながら対向した状態を維持す
る。また上下に隣接する施工区間のコンクリート6の打
ち継ぎ部分には両施工区間に跨る連結鋼材11が配置さ
れ、下側半分が下方の躯体K中に埋め込まれており、内
型枠1と外型枠2は鉛直鋼材10が連結鋼材11に接合され
ることにより設置時の躯体K上での安定性を確保する。
連結鋼材11の上側半分はコンクリート6の打設時にコン
クリート6中に埋め込まれる。
The inner mold 1 and the outer mold 2 are also shown in FIGS.
As shown in FIG. 1, the vertical steel material 10 is integrated for the convenience of transportation and assembly of the inner mold 1 and the outer mold 2, and for the stress sharing during the placement of the secondary concrete. The vertical steel material 10 is arranged on the side of the horizontal steel material 4 facing the outer formwork 2 or the inner formwork 1 side, and the inner formwork 1 and the outer formwork 2 are erected by the vertical steel material 10 and the connecting material 7 when the concrete 6 is poured. While facing each other. In addition, a connecting steel material 11 extending over both construction sections is arranged at the jointing portion of the concrete 6 in the construction sections that are vertically adjacent to each other, and the lower half is embedded in the lower frame K, and the inner mold 1 and the outer mold are formed. The frame 2 secures the stability on the frame K at the time of installation by joining the vertical steel material 10 to the connecting steel material 11.
The upper half of the connecting steel material 11 is embedded in the concrete 6 when the concrete 6 is poured.

【0016】橋脚の躯体Kの肉厚部分を示す図5〜図9
により一施工区間の施工手順を説明する。図5〜図9及
び図11〜図14は断面図になるが、便宜的に一部を立面図
として示す。
5 to 9 showing the thick portion of the skeleton K of the pier
The construction procedure for one construction section will be described below. Although FIGS. 5 to 9 and FIGS. 11 to 14 are sectional views, some of them are shown in an elevational view for convenience.

【0017】施工済みの躯体K上に、内型枠1と外型枠
2を上記要領で設置し(図5)、水平鋼材4,4を互い
に接続すると共に、対向する内型枠1と外型枠2を連結
材7によって連結する(図6)。続いて内型枠1と外型
枠2の各主筋3を躯体K上から突出している主筋3と互
いに接続した後(図7)、内型枠1と外型枠2とで挟ま
れた空間内にコンクリート6を打設する(図8)。コン
クリート6の硬化後、更に図5から図8までの手順を繰
り返して橋脚が構築される。図9に示すようにコンクリ
ート6の硬化によって躯体Kの一部となった内型枠1
の、橋脚の内周側には後述する作業台13の上部架台17や
下部架台16が載るブラケット12が突設される。
The inner mold 1 and the outer mold 2 are installed on the constructed frame K in the above-described manner (FIG. 5), the horizontal steel members 4 and 4 are connected to each other, and the inner mold 1 and the outer mold which face each other are connected. The formwork 2 is connected by the connecting material 7 (FIG. 6). Subsequently, after connecting each main bar 3 of the inner mold 1 and the outer mold 2 to the main bar 3 protruding from the skeleton K (FIG. 7), the space sandwiched between the inner mold 1 and the outer mold 2 Concrete 6 is placed inside (Fig. 8). After the concrete 6 is hardened, the procedure from FIG. 5 to FIG. 8 is further repeated to build the pier. As shown in FIG. 9, the inner formwork 1 which became a part of the skeleton K by hardening the concrete 6
On the inner circumference side of the pier, a bracket 12 on which an upper mount 17 and a lower mount 16 of a work platform 13 to be described later are placed is projected.

【0018】請求項2記載の発明は施工済みの躯体Kの
外周に沿って昇降する昇降機24によって内型枠1と外型
枠2を荷揚げする一方、頂部に揚重機14を持つポスト15
と、ポスト15を支持する下部架台16と、ポスト15に沿っ
て下部架台16に対して昇降可能な上部架台17からなる作
業台13を一施工区間だけ施工する毎に橋脚の内部を利用
して上昇させる方法であり、請求項1記載の方法を実施
するために適用される施工方法である。
According to the second aspect of the present invention, the inner mold 1 and the outer mold 2 are unloaded by the elevator 24 that moves up and down along the outer periphery of the constructed frame K, while the post 15 having the lifting machine 14 at the top is unloaded.
And the lower pedestal 16 that supports the post 15 and the work platform 13 that includes the upper pedestal 17 that can move up and down with respect to the lower pedestal 16 along the post 15 every time the construction section is constructed by using the inside of the pier. It is a method of raising, and is a construction method applied for implementing the method of claim 1.

【0019】作業台13のポスト15には上部架台17を引き
上げるリフトアップ装置18が設置され、リフトアップ装
置18と上部架台17間には双方に接続される引張材19が架
設される。同様に上部架台17には下部架台16を引き上げ
るリフトアップ装置20が設置され、リフトアップ装置20
と下部架台16間に引張材21が架設される。
A lift-up device 18 for lifting the upper mount 17 is installed on the post 15 of the workbench 13, and a tension member 19 connected between the lift-up device 18 and the upper mount 17 is installed between the lift-up device 18 and the upper mount 17. Similarly, a lift-up device 20 for lifting the lower mount 16 is installed on the upper mount 17, and the lift-up device 20
The tension member 21 is installed between the lower frame 16 and the lower frame 16.

【0020】作業台13のポスト15の頂部上には橋脚の全
断面を覆う屋根22が架設され、屋根22の外周からは足場
23が懸垂する。作業台13上は屋根22によって天候の影響
を受けない環境下に置かれ、施工は雨天による中断を生
ずることなく遂行される。内型枠1と外型枠2の組み立
てと、主筋3と水平鋼材4の接続及びコンクリート6の
打設作業は上部架台17と足場23を利用して行われる。
A roof 22 covering the entire cross section of the pier is installed on the top of the post 15 of the work table 13, and a scaffolding is provided from the outer periphery of the roof 22.
23 hangs. The workbench 13 is placed under the environment not affected by the weather by the roof 22, and the construction is performed without interruption due to rain. The upper frame 17 and the scaffolding 23 are used for assembling the inner form 1 and the outer form 2, connecting the main bar 3 and the horizontal steel material 4, and placing concrete 6.

【0021】作業台13の上昇は上記した、施工済みの躯
体Kの内面側に突設されたブラケット12に作業台13の上
部架台17と下部架台16を支持させたまま(図10)、一施
工区間の施工が終了する毎に、作業台13の荷重を下部架
台16に負担させた状態で上部架台17を一施工区間分上昇
させ、上部架台17を上方の躯体Kの内面に突設されたブ
ラケット12に支持させた後(図11)、作業台13の荷重を
上部架台17に負担させた状態で下部架台16を上昇させて
上部架台17の下方位置の躯体Kの内面に支持させる(図
12)、という要領で行われる。作業台13の上昇毎に、請
求項1記載発明の内型枠1と外型枠2の組み立てからコ
ンクリート6の打設までの作業が行われる(図13)。
The workbench 13 is lifted while the upper mount 17 and the lower mount 16 of the workbench 13 are supported by the bracket 12 projecting on the inner surface side of the already constructed frame K (FIG. 10). Each time the construction of the construction section is completed, the upper pedestal 17 is raised by one construction section while the load of the workbench 13 is being borne on the lower pedestal 16, and the upper pedestal 17 is projected on the inner surface of the upper skeleton K. After being supported by the bracket 12 (FIG. 11), the lower pedestal 16 is raised while the load of the workbench 13 is being loaded on the upper pedestal 17 and is supported on the inner surface of the skeleton K below the upper pedestal 17 ( Figure
12), and so on. Every time the workbench 13 is raised, the work from the assembling of the inner mold 1 and the outer mold 2 according to the first aspect of the invention to the placing of the concrete 6 is performed (FIG. 13).

【0022】昇降機24は図14に示すように躯体Kの外周
側に高さ方向に敷設された軌道25に沿って昇降可能に設
置され、内型枠1と外型枠2の上部架台17上への荷揚げ
を行う。上部架台17上に荷揚げされた内型枠1と外型枠
2は作業台13の揚重機14によって躯体K上に吊り込まれ
る。昇降機24と揚重機14の機能は独立するため両者は同
時に稼働できる。
As shown in FIG. 14, the elevator 24 is installed so as to be able to ascend and descend along a track 25 laid in the height direction on the outer peripheral side of the skeleton K, and on the upper mount 17 of the inner mold 1 and the outer mold 2. Unload to. The inner formwork 1 and the outer formwork 2 unloaded on the upper mount 17 are suspended on the skeleton K by the lifting machine 14 of the workbench 13. Since the functions of the elevator 24 and the lifting machine 14 are independent, both can operate at the same time.

【0023】橋脚は請求項1記載発明と請求項2記載発
明を並行して実施することにより構築される。
The pier is constructed by carrying out the invention according to claim 1 and the invention according to claim 2 in parallel.

【0024】[0024]

【発明の効果】請求項1記載発明はせん断補強筋に相当
する水平鋼材を一体化し、主筋を仮固定したプレキャス
トコンクリート製の内型枠と外型枠を用い、両者の設置
と両者間へのコンクリートの打設を繰り返して橋脚を構
築する方法であるため、現場での配筋作業と、脱型及び
盛り替えが省略され、作業の省力化により施工の進捗を
図ることができる。
According to the first aspect of the present invention, a horizontal steel material corresponding to a shear reinforcing bar is integrated, and an inner mold and an outer mold made of precast concrete in which the main bar is temporarily fixed are used. Since it is a method of constructing bridge piers by repeatedly placing concrete, it does not require on-site reinforcement work, demolding and refilling, and the progress of construction can be promoted by labor saving.

【0025】請求項2記載発明は内型枠と外型枠の荷揚
げを昇降機が行い、荷揚げされた内型枠と外型枠の組み
立てを作業台の揚重機が行う方法であるため、荷揚げ作
業と躯体上での構築作業を並行して行うことが可能とな
り、稼働効率と作業能率が向上し、工期の短縮化が図ら
れる。
According to the second aspect of the present invention, since the elevator unloads the inner mold and the outer mold and the hoisting machine of the workbench assembles the unloaded inner mold and the outer mold, the unloading work is performed. And construction work on the frame can be done in parallel, improving operating efficiency and work efficiency, and shortening the construction period.

【0026】特に請求項1記載発明と請求項2記載発明
を組み合わせて実施することにより施工進行上の無駄が
なくなるため施工進捗による工期短縮の効果は大きい。
In particular, by carrying out the invention of claim 1 and the invention of claim 2 in combination, there is no waste in the construction process, so that the construction period can be greatly shortened by the construction progress.

【図面の簡単な説明】[Brief description of drawings]

【図1】橋脚の構築要領を示した斜視図である。FIG. 1 is a perspective view showing a construction procedure of a pier.

【図2】内型枠,または外型枠とその設置状況を示した
斜視図である。
FIG. 2 is a perspective view showing an inner mold or an outer mold and its installation state.

【図3】内型枠,または外型枠を示した立面図である。FIG. 3 is an elevation view showing an inner mold or an outer mold.

【図4】図3の平面図である。FIG. 4 is a plan view of FIG. 3;

【図5】施工済みの躯体上への内型枠の設置時の様子を
示した立面図である。
FIG. 5 is an elevational view showing a state in which the inner formwork is installed on the constructed body.

【図6】内型枠と外型枠を連結し、水平鋼材を接続した
ときの様子を示した立面図である。
FIG. 6 is an elevational view showing a state in which a horizontal steel material is connected by connecting an inner mold and an outer mold.

【図7】主筋を接続したときの様子を示した立面図であ
る。
FIG. 7 is an elevational view showing a state in which main bars are connected.

【図8】コンクリートを打設したときの様子を示した立
面図である。
FIG. 8 is an elevation view showing a state where concrete is poured.

【図9】ブラケットを突設したときの様子を示した立面
図である。
FIG. 9 is an elevational view showing a state in which a bracket is projected.

【図10】コンクリートの打設が完了した時点の作業台
の様子を示した立面図である。
FIG. 10 is an elevational view showing a state of the workbench at the time when pouring of concrete is completed.

【図11】上部架台を上昇させたときの様子を示した立
面図である。
FIG. 11 is an elevational view showing a state when the upper mount is raised.

【図12】下部架台を上昇させたときの様子を示した立
面図である。
FIG. 12 is an elevational view showing a state when the lower mount is raised.

【図13】作業台を上昇させた後のコンクリートの打設
が完了したときの様子を示した立面図である。
FIG. 13 is an elevational view showing a state when the placing of concrete is completed after the workbench is raised.

【図14】昇降機と作業台の関係を示した立面図であ
る。
FIG. 14 is an elevation view showing the relationship between the elevator and the workbench.

【符号の説明】[Explanation of symbols]

1……内型枠、2……外型枠、3……主筋、4……水平
鋼材、5……ジベル、6……コンクリート、7……連結
材、8……カプラー、9……プレート、10……鉛直鋼
材、11……連結鋼材、12……ブラケット、13……作業
台、14……揚重機、15……ポスト、16……下部架台、17
……上部架台、18……リフトアップ装置、19……引張
材、20……リフトアップ装置、21……引張材、22……屋
根、23……足場、24……昇降機、25……軌道、K……躯
体。
1 ... Inner form, 2 ... Outer form, 3 ... Main bar, 4 ... Horizontal steel, 5 ... Givel, 6 ... Concrete, 7 ... Connecting material, 8 ... Coupler, 9 ... Plate , 10 …… vertical steel, 11 …… connected steel, 12 …… bracket, 13 …… workbench, 14 …… lifter, 15 …… post, 16 …… bottom mount, 17
...... Upper pedestal, 18 ...... Lift up device, 19 ...... Tensile material, 20 ...... Lift up device, 21 ...... Tensile material, 22 ...... Roof, 23 ...... Scaffolding, 24 ...... Elevator, 25 ...... Track , K ... body.

フロントページの続き (72)発明者 福島 重美 東京都新宿区荒木町13番地の4 住友建設 株式会社内Front page continuation (72) Inventor Shigemi Fukushima 13 13 Arakicho, Shinjuku-ku, Tokyo Sumitomo Construction Co., Ltd.

Claims (2)

【特許請求の範囲】[Claims] 【請求項1】 片面に、水平方向に主筋を周囲から拘束
する水平鋼材が一体化し、水平鋼材に包囲される側に鉛
直方向に主筋が仮固定されたプレキャストコンクリート
製の内型枠と外型枠を橋脚の横断面上、それぞれ内周側
と外周側で周方向に隣接させ、橋脚の躯体の厚さ方向に
互いに対向させて施工済みの、橋脚の躯体上に組み立
て、周方向に隣接する内型枠と外型枠の各水平鋼材を互
いに接続すると共に、内型枠と外型枠の各主筋を下方の
施工済みの各主筋に接続した後、内型枠と外型枠とで挟
まれた空間内にコンクリートを打設し、コンクリートの
硬化後、更にその上方への内型枠と外型枠の組み立てか
らコンクリートの打設までの手順を繰り返す橋脚の構築
方法。
1. An inner mold and an outer mold made of precast concrete in which a horizontal steel member for horizontally restraining the main bar from the surroundings is integrally formed on one surface, and the main bar is temporarily fixed to the side surrounded by the horizontal steel member in the vertical direction. On the cross-section of the pier, the frames are circumferentially adjacent to each other on the inner and outer circumference sides, and are assembled on the pier's skeleton that has already been constructed by facing each other in the thickness direction of the pier's skeleton and adjacent to each other in the circumferential direction. After connecting the horizontal steel members of the inner and outer molds to each other and connecting the main bars of the inner and outer molds to the main bars that have been constructed below, sandwich them between the inner and outer molds. A method of constructing a pier, in which concrete is placed in a closed space, and after the concrete is hardened, the steps from assembling the inner and outer molds above it to placing the concrete are repeated.
【請求項2】 請求項1記載の方法を実施するための施
工方法であり、施工済みの、橋脚となる躯体の外周側に
高さ方向に敷設された軌道に沿って昇降する昇降機を用
いて請求項1に記載の内型枠と外型枠を地上から搬送す
る一方、頂部に揚重機を持つポストと、ポストを支持す
る下部架台と、ポストに沿って下部架台に対して昇降可
能な上部架台からなる作業台を施工済みの躯体の内面に
支持させたまま、一施工区間の施工が終了する毎に上部
架台を上昇させて上方の躯体内面に支持させた後、下部
架台を上昇させて上部架台の下方位置の躯体内面に支持
させる、という手順を繰り返して作業台を上昇させる橋
脚の施工方法。
2. A construction method for carrying out the method according to claim 1, which uses an elevator which is elevated and lowered along a track laid in the height direction on the outer peripheral side of a pier frame that has been constructed. A post having a lifting machine at the top, a lower mount for supporting the post, and an upper part that can be moved up and down along the post with respect to the lower mount while transporting the inner formwork and the outer formwork according to claim 1 from the ground. While the work table consisting of the gantry is supported on the inner surface of the already constructed skeleton, the upper pedestal is raised every time the construction of one construction section is completed and is supported on the inner skeleton of the upper skeleton, and then the lower pedestal is raised. A pier construction method in which the work platform is raised by repeating the procedure of supporting it on the inner surface of the body below the upper frame.
JP7038259A 1995-02-27 1995-02-27 Bridge pier construction method and construction method Expired - Lifetime JP2790986B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP7038259A JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP7038259A JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Publications (2)

Publication Number Publication Date
JPH08232212A true JPH08232212A (en) 1996-09-10
JP2790986B2 JP2790986B2 (en) 1998-08-27

Family

ID=12520328

Family Applications (1)

Application Number Title Priority Date Filing Date
JP7038259A Expired - Lifetime JP2790986B2 (en) 1995-02-27 1995-02-27 Bridge pier construction method and construction method

Country Status (1)

Country Link
JP (1) JP2790986B2 (en)

Cited By (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102304892A (en) * 2011-07-29 2012-01-04 清华大学 External energy-consumption self-resetting bridge pier stud structure system and realization method thereof
CN103498436A (en) * 2013-10-18 2014-01-08 清华大学 Replaceable bridge pier anti-collision protective device and mounting method thereof
CN103510469A (en) * 2012-06-28 2014-01-15 中铁二十五局集团建筑安装工程有限公司 Construction method for manufacturing thin-walled hollow pier
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN105926449A (en) * 2016-05-04 2016-09-07 中国十九冶集团有限公司 Method for disassembling turnover formwork of high pier of bridge
CN106677069A (en) * 2016-12-28 2017-05-17 杭州江润科技有限公司 Construction method for overall formwork one-time forming structure of pier
CN107366230A (en) * 2017-07-19 2017-11-21 中国冶集团有限公司 A kind of bridge pier column rollover board and construction method
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN107881902A (en) * 2017-10-16 2018-04-06 中国水利水电第四工程局有限公司 Concrete construction method and mirror surface concrete pier stud
CN109024251A (en) * 2018-10-10 2018-12-18 南京林业大学 A kind of prefabrication and assembly construction folded type reinforced concrete bridge pier structure
CN111021258A (en) * 2019-12-24 2020-04-17 张玲 Assembly type buttress pouring die carrier for bridge building
CN111593676A (en) * 2020-06-22 2020-08-28 中铁十八局集团有限公司 Construction method of thin-wall hollow pier
CN112627034A (en) * 2020-12-10 2021-04-09 上海宝冶集团有限公司 Synchronous construction method for turning over mold of high pier of bridge
CN113494051A (en) * 2021-08-09 2021-10-12 中铁大桥局集团有限公司 Construction method for block-by-block prefabricated installation of variable-section inclined tower steel reinforcement framework
CN113699877A (en) * 2021-10-09 2021-11-26 四川省交通勘察设计研究院有限公司 Steel-concrete composite structure pier suitable for high-intensity area and construction method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
BR9803596A (en) * 1997-09-23 2000-04-25 Pfizer Prod Inc Derivatives of resorcinol.
HN2000000033A (en) * 1999-03-22 2001-02-02 Pfizer Prod Inc RESORCINOL COMPOSITION

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138914A (en) * 1993-11-11 1995-05-30 Taisei Corp Bridge pier construction method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07138914A (en) * 1993-11-11 1995-05-30 Taisei Corp Bridge pier construction method

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102304892A (en) * 2011-07-29 2012-01-04 清华大学 External energy-consumption self-resetting bridge pier stud structure system and realization method thereof
CN103510469A (en) * 2012-06-28 2014-01-15 中铁二十五局集团建筑安装工程有限公司 Construction method for manufacturing thin-walled hollow pier
CN103498436A (en) * 2013-10-18 2014-01-08 清华大学 Replaceable bridge pier anti-collision protective device and mounting method thereof
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN104846744B (en) * 2015-03-19 2017-01-11 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN105926449A (en) * 2016-05-04 2016-09-07 中国十九冶集团有限公司 Method for disassembling turnover formwork of high pier of bridge
CN106677069B (en) * 2016-12-28 2018-04-06 杭州江润科技有限公司 A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN106677069A (en) * 2016-12-28 2017-05-17 杭州江润科技有限公司 Construction method for overall formwork one-time forming structure of pier
CN107366230A (en) * 2017-07-19 2017-11-21 中国冶集团有限公司 A kind of bridge pier column rollover board and construction method
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN107881902A (en) * 2017-10-16 2018-04-06 中国水利水电第四工程局有限公司 Concrete construction method and mirror surface concrete pier stud
CN109024251A (en) * 2018-10-10 2018-12-18 南京林业大学 A kind of prefabrication and assembly construction folded type reinforced concrete bridge pier structure
CN111021258A (en) * 2019-12-24 2020-04-17 张玲 Assembly type buttress pouring die carrier for bridge building
CN111021258B (en) * 2019-12-24 2021-07-13 广东省基础工程集团有限公司 Assembly type buttress pouring die carrier for bridge building
CN111593676A (en) * 2020-06-22 2020-08-28 中铁十八局集团有限公司 Construction method of thin-wall hollow pier
CN112627034A (en) * 2020-12-10 2021-04-09 上海宝冶集团有限公司 Synchronous construction method for turning over mold of high pier of bridge
CN113494051A (en) * 2021-08-09 2021-10-12 中铁大桥局集团有限公司 Construction method for block-by-block prefabricated installation of variable-section inclined tower steel reinforcement framework
CN113699877A (en) * 2021-10-09 2021-11-26 四川省交通勘察设计研究院有限公司 Steel-concrete composite structure pier suitable for high-intensity area and construction method thereof

Also Published As

Publication number Publication date
JP2790986B2 (en) 1998-08-27

Similar Documents

Publication Publication Date Title
JPH08232212A (en) Pier constructing method and execution method
JP4252177B2 (en) Steel / concrete composite structure pier construction method
CN110409900B (en) Hybrid connection prefabricated prestressed concrete circular storage silo structure
JPH11181725A (en) Method for constructing horizontal beam of main tower made of concrete
CN106032705A (en) Integrated casting molding construction method of reinforced concrete floor system
JPH09310405A (en) Reinforced concrete column and precast form
JPH08134848A (en) Execution method of steel pipe-concrete composite structure pier
JP4136049B2 (en) Concrete pier construction method
CN210421568U (en) Assembled beam and plate structure
JPH07300817A (en) Concrete filled steel pipe truss bridge pier and its construction method
CA2114263A1 (en) Method of post-tensioning steel/concrete truss before installation
CN109610707A (en) A design and rapid construction method for flush assembly of prefabricated steel beams and floor slabs
JPH10102423A (en) Pca form and construction method of pier using the same pca form
JP2009299346A (en) Construction method of building
JP2000045229A (en) Constructing method of bridge
CN210288825U (en) Assembled and cast-in-situ combined beam plate structure
JPH0978532A (en) Work execution method for concrete bridge pier
JPH11343734A (en) Construct method for concrete structure
JPH0833032B2 (en) Construction method of building frame
JPH11172964A (en) Tower-shaped structure construction method
JPH0667511U (en) Electric automatic special support lifting device
JPH11323838A (en) Construction method of bridge
JPH03125755A (en) Constructing method for cylindrical multistoried structure
JP2731907B2 (en) Construction work method on sloping land
JPH0932295A (en) Construction method for concrete structure

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090612

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090612

Year of fee payment: 11

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100612

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100612

Year of fee payment: 12

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110612

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110612

Year of fee payment: 13

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120612

Year of fee payment: 14

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120612

Year of fee payment: 14

FPAY Renewal fee payment (prs date is renewal date of database)

Free format text: PAYMENT UNTIL: 20130612

Year of fee payment: 15

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

EXPY Cancellation because of completion of term