CN106677069B - A kind of construction method of bridge pier integral formwork support one-shot forming structure - Google Patents

A kind of construction method of bridge pier integral formwork support one-shot forming structure Download PDF

Info

Publication number
CN106677069B
CN106677069B CN201611233074.5A CN201611233074A CN106677069B CN 106677069 B CN106677069 B CN 106677069B CN 201611233074 A CN201611233074 A CN 201611233074A CN 106677069 B CN106677069 B CN 106677069B
Authority
CN
China
Prior art keywords
pier stud
template
binder
construction
pier
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201611233074.5A
Other languages
Chinese (zh)
Other versions
CN106677069A (en
Inventor
王新泉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Road and bridge engineering Group Co.,Ltd of Jiangxi Province
Original Assignee
Hangzhou Jiangrun Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Jiangrun Technology Co Ltd filed Critical Hangzhou Jiangrun Technology Co Ltd
Priority to CN201611233074.5A priority Critical patent/CN106677069B/en
Publication of CN106677069A publication Critical patent/CN106677069A/en
Application granted granted Critical
Publication of CN106677069B publication Critical patent/CN106677069B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The present invention relates to a kind of construction method of bridge pier integral formwork support one-shot forming structure, comprise the following steps:1) cushion cap face handle, 2) pier stud construction cripple set up, 3) reinforcing bar system peace, 4) model sheetinstallat, 5) concreting, 6) form removable, health, 7) binder prestressed stretch-draw mud jacking.The present invention has the advantages that environment-friendly, easy for construction, cheap.

Description

A kind of construction method of bridge pier integral formwork support one-shot forming structure
Technical field
The present invention relates to a kind of one-time formed construction method of bridge pier integral formwork support.
Background technology
At present, domestic overpass two-columned pier pier stud construction generally uses H type twin columns, and mostly curve variable cross-section loudspeaker Mouth bridge-type, and binder span is larger, pier stud binder is relatively conventional using prestressing force form, the queen post highly more than 10 meters The construction of H types pier stud is more using segmentation casting method, and secondary formwork is difficult and leaves obvious segmentation and connects stubble, if primary concreting outward appearance into Type effect is undesirable;And in concreting, leakiness of disposably vibrating, at bridge pier variable cross-section with binder connecting portion steel Muscle is closeer, and bell mouth shape anchor notch and binder prestressing force corrugated conduit gather with reinforcing bar, such as primary concreting, variable cross-section horn mouth Standing beneath section is difficult vibration compacting.
In summary, existing two-columned pier low construction efficiency is not high, and construction quality is difficult to ensure that, exists substantial amounts of Open defect.In consideration of it, need the bridge pier integral formwork support one-shot forming knot for inventing that a kind of efficiency of construction is high, quality is secure badly at present Structure and construction method.Constructed using the method, easy for construction and construction quality is high, has certain economic technology benefit.
The content of the invention
It is an object of the invention to provide the bridge pier integral formwork support one-shot forming knot that a kind of efficiency of construction is high, quality is secure The construction method of structure, make every effort to bridge pier one piece pouring molding, optimized construction procedure, improve construction efficiency, lift engineering construction Quality.
The purpose of the present invention is achieved through the following technical solutions:A kind of bridge pier integral formwork support one-shot forming structure is applied Work method, its main construction procedure are as follows:
1) cushion cap face is handled:According to the pier stud sideline of surveying and locating, using manually to Construction Joint face scope progress dabbing Until exposing coarse aggregate, while the cement mortar on pier stud embedded bar top layer is cleared up, and rinsed well with high pressure clear water.Flushing finishes Pier stud embedded bar is adjusted afterwards, ensures that reinforcing bar is straight, complies with design requirement.
2) pier stud construction cripple is set up:Pier shaft surrounding sets up double-pole scaffold, and double-pole scaffold surrounds pier stud four Week closes and set up.Scaffold basis is fallen within cushion cap and firm ground, by montant, whippletree, adjustable bolt, flitch, adjustable Jacking composition is saved, scaffold sets Crossing brace in its four sides by code requirement, and scaffold is set up according to fastener type pin hand Frame regulation enforcement, surrounding and horizontal direction are respectively provided with safety guard net, and set up lower channel for above and below workmen;Construction surface Platform springboard, workbench are set.
3) reinforcement fabrication and installation:The reinforcing bar of different construction parts stores classifiedly in reinforcement yard, and is numbered, pier Post cage bar, stirrup and binder matrix tablet start to install after making shaping.Pre-buried bridge pier cage bar during bearing platform construction, and use and face When support, carry out pier stud reinforcing bar colligation, be attached when pre-buried for pier stud cage bar spreading using straight screw sleeve.First colligation pier Then column tie-bar lifts binder framework of steel reinforcement piece, matrix tablet and pier stud cage bar are welded shape by welder's welding to binder bottom position It is integral, matrix tablet all colligation residue stirrup, construction muscle and encryption reinforcing bar after the completion of welding are treated, pre-buried PVC sleeve pipes simultaneously wear Prestressing force bellows, prestressing force corrugated conduit use coordinate setting in advance, weld well word hoop or fixed using U-shaped card, such as Steel-bar and stress technique corrugated conduit position conflicts, then follows cage bar and avoid prestressing force corrugated conduit, cuts stirrup, adjustment cage bar less, Cut off the principle recovered in time afterwards.Reinforcement installation one-shot forming, firm stable after entirety is formed, binder reinforcing bar bottom is without in advance Supporting module.
4) model sheetinstallat:Using set shaped steel formwork, including standard paragraphs template, loudspeaker mouth template, binder bed die, side form group Into, formed by panel, flange, cross rib, perpendicular rib, draw-bar seat, arc reinforcement, channel-section steel, R plates, by processed in factory customization and Into prestressed anchor notch position stays in advance to be set, and wherein horn mouth should carry out preassembling with binder linkage section template, it is ensured that construct Matched moulds zero deflection, internal corner part connection are accurate in journey.Template is first polished, is derusted, brushes releasing agent;Then in cushion cap top surface Release template outer edge, Rational choice regulating block, standard knot carry out standard section section spelling, by the masonry mortar on cushion cap or Brick mold, as bottom adjusting template.Regulation steel form in bottom is first installed, further according to pier stud height selection standard section and regulating block Integral assembling, and highly divide the assembled integral big-size formwork in four sides to be lifted by single pier stud, finally by corner to pull bar Reinforced.Fill variable cross-section section loudspeaker mouth template;Set up total sub-semigroup, installation variable cross-section horn mouth and binder connecting portion Template, it is fixed with bottom vertical section template, then install binder end template, be attached, reinforce with bridge pier horn mouth, simultaneously Bowl buckle scaffold jacking is adjusted, installs horn mouth side template.Attached vibrator is uniformly laid in template.
5) concreting:Mould, one-time continuous cast are entered using automobile pump concrete.
6) form removable, health:After pier stud concreting, watering maintenance was proceeded by every 2 hours or so.Mould Plate removes the artificial progress with truck crane, classifies after form removable and is under lock and key, and goes to next pier stud construction week.Form removable After the completion of, pier stud, binder are integrally wrapped up using plastic sheeting immediately, carry out fencing lawn.
7) binder prestressed stretch-draw mud jacking:When concrete strength reaches 90% and age is not less than 7 days, it can carry out pre- Prestress steel strand lashing, and tensioning.
The beneficial effects of the invention are as follows:
(1) disposably by the colligation of bridge pier reinforcing bar and model sheetinstallat in place, and primary concreting concrete can reduce process ring Section, reduce labor intensity, accelerating construction progress.
(2) compared with being segmented pouring construction, it can effectively avoid that joint part concrete leakiness, seam be obvious, segmentation concrete color Phenomena such as difference is larger, it is ensured that Surface Quality of Concrete meets design requirement.
(3) one-time-concreting technique is used, secondary formwork difficulty can be reduced, avoids the secondary reinforcement installation of bridge pier binder, template Install and pollution of the concreting to bottom finished product.
(4) accurately it is connected by being accurately positioned prestressing force corrugated conduit, anchor notch being reserved with template, post-stressed muscle Laying increase the span of binder, local pressure is uneven (pier stud eccentric compression) at curved section horn mouth moulding, applies pre- Stress enhances the resistance of bridge pier.
Brief description of the drawings
Fig. 1 is a kind of bridge pier integral formwork support one-shot forming agent structure schematic diagram of the present invention;
Fig. 2 is standard paragraphs template schematic diagram;
Fig. 3 is loudspeaker mouth template schematic diagram;
Fig. 4 is construction flow chart of the present invention.
Description of reference numerals:1- panels, 2- platform springboards, 3- lower channels, 4- workbenches, 5- flanges, 6- cross ribs, 7- Perpendicular rib, 8- tapping pipes, the pre-buried bellowss of 9-, 10-PVC sleeve pipes, 11- montants, 12- cross bars, 13- Crossing braces, 14- can adjust spiral shell Bolt, 15- flitches, 16- can adjust jacking, and 17- is to pull bar, 18- draw-bar seats, 19- arc reinforcements, 20- channel-section steels, 21-R plates, 22- Attached vibrator.
Embodiment
The present invention is described further with reference to embodiment.The explanation of following embodiments is only intended to help and understands this Invention.It should be pointed out that for those skilled in the art, under the premise without departing from the principles of the invention, also Some improvement and modification can be carried out to the present invention, these are improved and modification also falls into the protection domain of the claims in the present invention It is interior.
Reinforcing bar colligation, welding technique requirement, large-scale steel form concatenation construction technique, binder post stretching are pre- in present embodiment Stress tension technology etc. repeats no more, and emphasis illustrates the implementation of bridge pier integral formwork support one-shot forming structure installation of the present invention Mode.
Fig. 1 is a kind of bridge pier integral formwork support one-shot forming agent structure schematic diagram of the present invention;Fig. 2 is the signal of standard paragraphs template Figure;Fig. 3 is loudspeaker mouth template schematic diagram;
Bridge pier integral formwork support one-shot forming structure shown in reference picture 1-3, by operating platform, set shaped steel formwork, scaffold System, built-in fitting etc. form.
Operating platform is by platform springboard 2, lower channel 3, the grade of workbench 4 composition.
Set shaped steel formwork is made up of standard paragraphs template and horn mouth template, by panel 1, flange 5, cross rib 6, perpendicular rib 7, drawing Pole socket 18, arc reinforcement 19, channel-section steel 20, R plates 21 form, attached vibrator 22.
Scaffold system is by montant 11, cross bar 12, Crossing brace 13, adjustable bolt 14, flitch 15, adjustable jacking 16 etc. Composition.
Built-in fitting includes tapping pipe 8, pre-buried bellows 9, PVC sleeve pipes 10 etc..
As shown in figure 4, bridge pier integral formwork support one-shot forming structure construction step is as follows:
1) cushion cap face is handled:According to the pier stud sideline of surveying and locating, using manually to Construction Joint face scope progress dabbing Until exposing coarse aggregate, while the cement mortar on pier stud embedded bar top layer is cleared up, and rinsed well with high pressure clear water.
2) pier stud construction cripple is set up:Pier shaft surrounding is set up double using Φ 48mm × 3.0mm design of coupler scaffold Arrange scaffold.Double-pole scaffold is set up around pier stud surrounding closure, and vertically and horizontally spacing is 90 × 90cm, cross bar step pitch 120cm.Pin Hand cradle basis is fallen within cushion cap and firm ground, and scaffold sets Crossing brace, scaffold in its four sides by code requirement Set up according to design of coupler scaffold regulation enforcement, surrounding and horizontal direction are respectively provided with safety guard net, and set up lower platform Above and below workmen.
3) reinforcing bar system is pacified:The reinforcing bar of different construction parts stores classifiedly in reinforcement yard, and is numbered, pier stud master Muscle, stirrup and binder matrix tablet start to install after making shaping.Then first colligation pier stud stirrup lifts to binder bottom position Matrix tablet and pier stud cage bar are welded to form entirety by binder framework of steel reinforcement piece, welder's welding, treat matrix tablet all after the completion of welding Colligation residue stirrup, construction muscle and encryption reinforcing bar, and prestressing force corrugated conduit is worn, prestressing force corrugated conduit uses coordinate in advance Positioning, weld well word hoop or fixed using U-shaped card.
4) model sheetinstallat:Using set shaped steel formwork, formed by processing customization in factory, especially horn mouth curved section line style stream Freely, accurately, prestressed anchor notch position stays in advance to be set, and wherein horn mouth should be carried out pre- with binder linkage section template for graceful, control It is assembled, it is ensured that matched moulds zero deflection, internal corner part connection are accurate in work progress.Bridge abutment moulding plate mainly by regulating block (10cm, 30cm, 50cm, 100cm), standard knot, horn mouth variable cross-section curved section template, binder bed die, side form composition.There is foot after assembling Enough rigidity, strength and stability.Template polishing, derusting, brush releasing agent;First install bottom regulation steel form (30cm or 50cm), further according to pier stud height selection standard section and regulating block integral assembling, and highly to divide by single pier stud four sides to be assembled into whole Body big-size formwork is lifted, and is reinforced finally by corner Screw arbor with nut at both-ends.Fill variable cross-section section loudspeaker mouth template;Set up bowl buckle Formula scaffold, installation variable cross-section horn mouth and binder connecting portion template, make it be fixed with bottom vertical section template, then install and be Beam bottom mother plate, it is attached, reinforces with bridge pier horn mouth, while adjust jacking, installs horn mouth side template.Prestressed anchor groove position Loudspeaker mouth template is put finally to install.
5) concreting:Mould, one-time continuous cast are entered using automobile pump concrete.Pier shaft concrete uses laminated pouring, Every layer of thickness control is in 30~50cm.Pier top reinforced mesh mesh 10cm × 10cm, in construction to automotive pump conveying tube end Spreading vertical tube, a diameter of 80mm of hard tube, material are metal iron pipe, and length 3m can be according to live actual height spreading or dismounting.
6) form removable, health:Draw is produced to prevent in concrete that moisture evaporation is too fast, and ensures hydrated cementitious mistake Journey is smoothed out, and after pier stud concreting, watering maintenance was proceeded by every 2 hours or so.When concrete strength reaches Pier Formwork is removed to 2.5MPa, binder bed die should can bear it from gravity and other possible superimposed loads in concrete strength Shi Fangke is removed.After the completion of form removable, pier stud, binder are integrally wrapped up using plastic sheeting immediately, carry out fencing lawn, is supported The shield phase is not less than 7 days.
7) binder prestressed stretch-draw mud jacking:When concrete strength reaches 90% and age is not less than 7 days, prestressing force is carried out Steel stranded wire penetrating adapter, and tensioning.Prestress wire lashing uses high speed strand pulling machine.Before tensioning clear up anchor cushion block on cement mortar and Iron rust, and itself and ripple pore central perpendicularity are checked, if any deviation, with wedge-shaped steel cushion block.One end uses the big jack of 100t, The other end uses the per share tensioning 5t respectively of small jack, then big jack one-end tension.

Claims (1)

1. a kind of construction method of bridge pier integral formwork support one-shot forming structure, it is characterised in that comprise the following steps:
1) cushion cap face is handled:According to the pier stud sideline of surveying and locating, dabbing is carried out to Construction Joint face scope until exposing thick bone Material, while the cement mortar on pier stud embedded bar top layer is cleared up, and rinsed well with high pressure clear water;It is pre-buried to pier stud after flushing Reinforcing bar is adjusted, and is ensured that reinforcing bar is straight, is complied with design requirement;
2) pier stud construction cripple is set up:Pier shaft surrounding sets up double-pole scaffold, and double-pole scaffold closes around pier stud surrounding Conjunction is set up;Scaffold basis is fallen within cushion cap and firm ground, by montant (11), whippletree (12), adjustable bolt (14), wood Side (15) and adjustable jacking (16) form, scaffold its four sides by code requirement setting Crossing brace (13), surrounding and Horizontal direction is respectively provided with safety guard net, and sets up lower channel (3) for above and below workmen;Construction surface sets platform springboard And workbench (4) (2);
3) reinforcement fabrication and installation:Pier stud cage bar, stirrup and binder matrix tablet start to install after making shaping;The bearing platform construction phase Between pre-buried bridge pier cage bar, and use temporary support, carry out pier stud reinforcing bar colligation, straight spiral shell is used for pier stud cage bar spreading when pre-buried Line sleeve is attached;Then first colligation pier stud stirrup lifts binder framework of steel reinforcement piece, welder's welding will to binder bottom position Matrix tablet welds to form entirety with pier stud cage bar, treats colligation residue stirrup, construction muscle and encryption after the completion of matrix tablet whole welding Reinforcing bar, pre-buried PVC sleeve pipes (10) simultaneously wear prestressing force bellows (9), and prestressing force corrugated conduit uses coordinate setting in advance, welding Well word hoop is fixed using U-shaped card, when steel-bar and stress technique corrugated conduit position conflicts, then follows cage bar and avoids and in advance should Power corrugated conduit, stirrup, adjustment cage bar are cut less, cuts off the principle recovered in time afterwards;Reinforcement installation one-shot forming, after forming entirety Firm stable, binder reinforcing bar bottom is without leading supporting module;
4) model sheetinstallat:Using set shaped steel formwork, including standard paragraphs template, loudspeaker mouth template, binder bed die and side form, by face Plate (1), flange (5), cross rib (6), perpendicular rib (7), draw-bar seat (18), arc reinforcement (19), channel-section steel (20) and R plates (21) group Into prestressed anchor notch position stays in advance to be set, and wherein horn mouth should carry out preassembling with binder linkage section template, it is ensured that construct Matched moulds zero deflection, internal corner part connection are accurate in journey;Template is first polished, is derusted, brushes releasing agent;Then in cushion cap top surface Release template outer edge, Rational choice regulating block, standard knot carry out standard section section spelling, by the masonry mortar on cushion cap or Brick mold, as bottom adjusting template;Regulation steel form in bottom is first installed, further according to pier stud height selection standard section and regulating block Integral assembling, and highly divide the assembled integral big-size formwork in four sides to be lifted by single pier stud, finally by corner to pull bar (17) reinforced;Fill variable cross-section section loudspeaker mouth template;Total sub-semigroup is set up, installation variable cross-section horn mouth is connected with binder Position template, it is fixed with bottom vertical section template, then install binder end template, be attached, reinforce with bridge pier horn mouth, Bowl buckle scaffold jacking is adjusted simultaneously, installs horn mouth side template;Attached vibrator (22) is uniformly laid in template;
5) concreting:Mould, one-time continuous cast are entered using automobile pump concrete;
6) form removable, health:After pier stud concreting, watering maintenance was proceeded by every 2 hours;Form removable by Truck crane coordinates artificial progress, classifies after form removable and is under lock and key, and goes to next pier stud construction week;After the completion of form removable, Pier stud, binder are integrally wrapped up using plastic sheeting immediately, carry out fencing lawn;
7) binder prestressed stretch-draw mud jacking:When concrete strength reaches 90% and age is not less than 7 days, prestressing force can be carried out Steel stranded wire penetrating adapter, and tensioning.
CN201611233074.5A 2016-12-28 2016-12-28 A kind of construction method of bridge pier integral formwork support one-shot forming structure Active CN106677069B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201611233074.5A CN106677069B (en) 2016-12-28 2016-12-28 A kind of construction method of bridge pier integral formwork support one-shot forming structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201611233074.5A CN106677069B (en) 2016-12-28 2016-12-28 A kind of construction method of bridge pier integral formwork support one-shot forming structure

Publications (2)

Publication Number Publication Date
CN106677069A CN106677069A (en) 2017-05-17
CN106677069B true CN106677069B (en) 2018-04-06

Family

ID=58873051

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201611233074.5A Active CN106677069B (en) 2016-12-28 2016-12-28 A kind of construction method of bridge pier integral formwork support one-shot forming structure

Country Status (1)

Country Link
CN (1) CN106677069B (en)

Families Citing this family (23)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN109235261B (en) * 2018-10-31 2024-07-02 广东省交通规划设计研究院集团股份有限公司 Bridge tower construction device and bridge tower construction method
CN110091124B (en) * 2019-04-08 2021-12-24 湖北时瑞达重型工程机械有限公司 Curved surface part construction process of bridge vase-shaped pier column mold
CN110216791B (en) * 2019-05-18 2020-09-11 陕西建工第五建设集团有限公司 Positioning method for integral straight anchor of reinforcement cage and steel formwork
CN110172915A (en) * 2019-05-20 2019-08-27 中交路桥华东工程有限公司 A kind of high tower shaped form crossbeam Joint Re-bar Construction
CN110158548A (en) * 2019-06-11 2019-08-23 许昌水利建筑工程有限公司 A kind of sluice steel form and its arrangement and method for construction
CN110396937A (en) * 2019-08-06 2019-11-01 中铁二十三局集团第三工程有限公司 The asynchronous construction of hollow thin-walled high pier binder pier beam
CN110512524A (en) * 2019-08-16 2019-11-29 中交一公局第五工程有限公司 A kind of bridge pier column safe construction method
CN110593558A (en) * 2019-09-26 2019-12-20 常州市市政建设工程有限公司 Large-scale steel mold without pull rod for vase-type pier stud and construction process of large-scale steel mold
CN110578300A (en) * 2019-09-26 2019-12-17 常州市市政建设工程有限公司 Large-volume concrete pouring process for special-shaped bridge pier column
CN110700101B (en) * 2019-10-12 2024-06-18 中建八局第二建设有限公司 Spliced template for pier pouring and construction method thereof
CN110778116B (en) * 2019-10-30 2021-07-09 中国建筑第八工程局有限公司 Construction method of complex curved surface giant concrete beam tube structure
CN111455858A (en) * 2020-04-23 2020-07-28 安徽省路港工程有限责任公司 Integral pouring construction method for column pier
CN111593652A (en) * 2020-06-16 2020-08-28 吴秋敏 Bridge construction supporting foundation construction process
CN112144412A (en) * 2020-09-25 2020-12-29 四川交投建设工程股份有限公司 Construction method of prefabricated assembled intercolumnar tie beam
CN113279334B (en) * 2021-05-19 2022-09-27 安徽省路港工程有限责任公司 Construction method of one-step pouring molding system of double-column type vase pier steel template
CN113417215A (en) * 2021-07-06 2021-09-21 中铁二十局集团第六工程有限公司 Bridge construction method
CN114045750B (en) * 2021-11-10 2023-11-28 中冶交通建设集团有限公司 Construction method of high pier column tie beam
CN114561873B (en) * 2022-03-16 2023-08-08 杭州萧山交通建设管理有限公司 Bridge high pier construction method
CN114790690A (en) * 2022-04-13 2022-07-26 中铁二十三局集团第三工程有限公司 Synchronous construction method for tie beam and pier body in hydraulic creeping formwork high pier
CN115110423A (en) * 2022-06-24 2022-09-27 保利长大工程有限公司 Rectangular pier construction process
CN115305826B (en) * 2022-08-31 2024-06-04 中冶(上海)钢结构科技有限公司 Rapid pre-assembly method for large-span high-precision flange connection bridge
CN115306136B (en) * 2022-10-12 2022-12-16 上海建工一建集团有限公司 Inclined wall eversion climbing type steel platform construction device and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06264410A (en) * 1992-10-08 1994-09-20 Keihan Concrete Kogyo Kk Prefabrication method of bridge pier and bridge pier concrete block
JPH08232212A (en) * 1995-02-27 1996-09-10 Sumitomo Constr Co Ltd Pier constructing method and execution method
KR20090041189A (en) * 2007-10-23 2009-04-28 삼성물산 주식회사 Pier and the construction method for the same
CN101446073A (en) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 Reinforced concrete pier stud with capping beam or irregular Y-shaped reinforced concrete pier stud once-forming construction method
CN201738229U (en) * 2010-05-18 2011-02-09 中国一冶集团有限公司 Template for method of one-step molding construction of vase-shaped columnar pier for urban viaduct
CN102011368A (en) * 2010-11-10 2011-04-13 中国一冶集团有限公司 One-time molding construction method for vase-shaped columnar pier of viaduct
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN104929047A (en) * 2015-06-09 2015-09-23 沈阳市政集团有限公司 V-shaped pier outer support construction method

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06264410A (en) * 1992-10-08 1994-09-20 Keihan Concrete Kogyo Kk Prefabrication method of bridge pier and bridge pier concrete block
JPH08232212A (en) * 1995-02-27 1996-09-10 Sumitomo Constr Co Ltd Pier constructing method and execution method
KR20090041189A (en) * 2007-10-23 2009-04-28 삼성물산 주식회사 Pier and the construction method for the same
CN101446073A (en) * 2008-12-19 2009-06-03 上海市第五建筑有限公司 Reinforced concrete pier stud with capping beam or irregular Y-shaped reinforced concrete pier stud once-forming construction method
CN201738229U (en) * 2010-05-18 2011-02-09 中国一冶集团有限公司 Template for method of one-step molding construction of vase-shaped columnar pier for urban viaduct
CN102011368A (en) * 2010-11-10 2011-04-13 中国一冶集团有限公司 One-time molding construction method for vase-shaped columnar pier of viaduct
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN104929047A (en) * 2015-06-09 2015-09-23 沈阳市政集团有限公司 V-shaped pier outer support construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
桥梁系梁及其墩台身施工技术探讨;郭振枝;《科技与企业》;20140822(第16期);第218页 *

Also Published As

Publication number Publication date
CN106677069A (en) 2017-05-17

Similar Documents

Publication Publication Date Title
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN207143755U (en) A kind of adjustable bracket for No. 0 block of bridge pier
CN202359506U (en) Double hoop supporting system for pier column capping beam
CN108385980A (en) Deformation joint shear wall set shaped steel formwork installs unidirectional fastening screw construction method
CN105863253A (en) Integral formwork-supporting type asynchronous casting stairwell wall column formwork supporting system and construction method
CN206267422U (en) A kind of assembly concrete superposed column
CN108678218A (en) Assembly concrete shear wall and its method of construction based on multipurpose thin-wall steel tube
CN105908864A (en) Interface crack preventing structure for filling brickwork and framework shear wall and construction method
CN102251481B (en) Railway pier layered construction method and construction device
CN104963289A (en) Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud
CN106346596A (en) Precast stair template matching system
CN206174120U (en) Prefabricated constructional column and structure thereof
CN105128131A (en) Method for manufacturing prestressed hollow slab beam through polystyrene foam
CN105804395A (en) Staircase one-step continuous casting forming construction method based on integral shaped formwork
CN110625786B (en) Concrete slab construction method based on steel bar welding net and cement pressure plate
CN109895239B (en) Fabricated concrete stair slow platform beam slab and construction method thereof
CN205894681U (en) Closed staircase template
CN206553938U (en) Bridge pier integral formwork support one-shot forming structure
CN110080299A (en) A kind of shallow embedding mountain tunnel open-cut engineering method
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN113373815A (en) Construction method for on-site wet joint of prefabricated bent cap
CN104947853A (en) Built-in stand type cast-in-place reinforced concrete pillar and construction method
CN102767378B (en) Double-column type tunnel portal method for bent frame construction tunnel
KR101120588B1 (en) Vertical joint frame for improving monolithic concrete
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Zhao Ronggao

Inventor after: Zhang Zhonghui

Inventor after: Xiong Juan

Inventor after: Li Ming

Inventor after: Zeng Yunfeng

Inventor after: Chen Shichao

Inventor before: Wang Xinquan

TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20180412

Address after: 330002 1352 Jinggangshan Avenue, Xihu District, Nanchang, Jiangxi.

Patentee after: Road and bridge engineering Group Co.,Ltd of Jiangxi Province

Address before: 310015 Hangzhou Wanda Commercial Center, Zhejiang, building 3, unit 1901, room 3

Patentee before: Hangzhou Jiang Run Science and Technology Ltd.