CN207812307U - The construction system of Cable stayed Bridge Main Tower and steel anchor beam - Google Patents

The construction system of Cable stayed Bridge Main Tower and steel anchor beam Download PDF

Info

Publication number
CN207812307U
CN207812307U CN201820128371.1U CN201820128371U CN207812307U CN 207812307 U CN207812307 U CN 207812307U CN 201820128371 U CN201820128371 U CN 201820128371U CN 207812307 U CN207812307 U CN 207812307U
Authority
CN
China
Prior art keywords
anchor beam
steel
tower
king
steel anchor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn - After Issue
Application number
CN201820128371.1U
Other languages
Chinese (zh)
Inventor
孟庆敏
李辉
吉静涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban Construction Road & Bridge Group Co Ltd
Original Assignee
Beijing Urban Construction Road & Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban Construction Road & Bridge Group Co Ltd filed Critical Beijing Urban Construction Road & Bridge Group Co Ltd
Priority to CN201820128371.1U priority Critical patent/CN207812307U/en
Application granted granted Critical
Publication of CN207812307U publication Critical patent/CN207812307U/en
Withdrawn - After Issue legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model discloses a kind of Cable stayed Bridge Main Tower and the construction system of steel anchor beam, the construction system includes:Pre-embedded steel slab, king-post steel inner template and steel anchor beam falsework;Pre-embedded steel slab is arranged in the top surface of corbel, and pre-embedded steel slab passes through WELDING STUDS and corbel reinforcement welding;King-post steel inner template is arranged between lower part joist top surface and top joist bottom surface, is welded and fixed using the main reinforcement of connection reinforcing bar and king-tower merogenesis;The lower part of steel anchor beam falsework is mounted on existed building flat surface or completed steel anchor beam top plate, and top surface is flushed with pre-embedded steel slab;Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework before concreting, steel anchor beam is welded to connect completion in place with pre-embedded steel slab after the cast of king-tower merogenesis concrete.Steel anchor beam installation is fused in king-tower structure construction by the utility model construction system, reduces the merogenesis construction times of king-tower, is not only contributed to the quality of control king-tower structure, is more shortened construction period, reduce waste of material.

Description

The construction system of Cable stayed Bridge Main Tower and steel anchor beam
Technical field
The utility model belongs to CONSTRUCTION OF CABLE-STAYED BRIDGE equipment technical field, more particularly to a kind of Cable stayed Bridge Main Tower and steel anchor beam Construction system.
Background technology
Cable-stayed bridge be it is a kind of by tower compression, drag-line tension, beam body by a kind of curved combined system bridge.The system can be effective Building structure height is reduced, mitigates weight, save material.Modern cable-stayed bridge is with its good structural behaviour, larger leap energy The architectural image of power, rational economic indicator and grace occupies an important position in modern bridge structure, due to modern structure The progress of theory, Materials with High Strength, computer technology and construction method makes cable-stayed bridge be rapidly developed.
Cable stayed Bridge Main Tower is the anchored end of drag-line, and to ensure the rigidity at tensioning position, steel anchor beam is arranged in king-tower.Relatively In using steel strand wires or increasing reinforcing bar come for increasing the rigidity of structure, setting steel anchor beam has that construction method is simple, shortens construction week The features such as phase.According to the segmented construction requirement of king-post, king-post inner space, steel anchor beam structure and process characteristic, king-tower anchoring section Each segment concrete wants one-time-concreting to complete, and requires king-post concrete structure with one-pass molding after formwork support arrangement, meet reinforcing bar binding, Installation after steel plate installation, formwork support arrangement, the interim in place and concrete placings of steel anchor beam.
In steel anchor beam installation, to be the position installed according to steel anchor beam in king-post determine king-post merogenesis carrying out, such as Fruit each steel anchor beam position is respectively provided with king-post merogenesis, causes king-post merogenesis more, to increase king-post main reinforcement connector, prestress steel The number of turnover of twisted-wire contact and the inside and outside template of king-post has certain influence to the inherent quality of tower column structure and presentation quality. If one king-post merogenesis of each two steel anchor beam correspondence can not since construction space is excessively narrow between each two joist simultaneously The steel anchor beam of lower part is installed after the completion of concreting.
Utility model content
The purpose of this utility model is to provide the construction system of a kind of Cable stayed Bridge Main Tower and steel anchor beam.
The technical solution that the utility model solves above-mentioned technical problem is as follows:A kind of construction of Cable stayed Bridge Main Tower and steel anchor beam System, the Cable stayed Bridge Main Tower include the first tower body and the second tower body, are arranged at intervals on first tower body and the second tower body The corresponding cable guard arm in position and armored concrete corbel;The Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;It is described King-tower merogenesis is equipped with upper and lower spaced top corbel and lower part corbel;Steel anchor beam is located at the first tower body and the second tower body On;The construction system includes:Pre-embedded steel slab, king-post steel inner template and steel anchor beam falsework;The pre-embedded steel slab setting exists The top surface of corbel, pre-embedded steel slab pass through WELDING STUDS and corbel reinforcement welding;The king-post steel inner template is arranged on lower part joist top Between face and top joist bottom surface, it is welded and fixed using the main reinforcement of connection reinforcing bar and king-tower merogenesis;The steel anchor beam falsework Lower part be mounted on existed building flat surface or completed steel anchor beam top plate, top surface and the lower part of steel anchor beam falsework are held in the palm The pre-embedded steel slab installed on top surface of the beam flushes;Steel anchor beam corresponding with lower part joist is installed to steel anchor beam before concreting On falsework, steel anchor beam is welded to connect completion in place with pre-embedded steel slab after the cast of king-tower merogenesis.
The construction system of the utility model Cable stayed Bridge Main Tower as described above and steel anchor beam, further, the cable-stayed bridge master Tower includes the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel successively from the bottom to top Anchor beam includes the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the successively from the bottom to top Six steel anchor beams, the 7th steel anchor beam and the 8th steel anchor beam.
The construction system of the utility model Cable stayed Bridge Main Tower as described above and steel anchor beam, further, the steel anchor beam face When the rectangular top frame that is welded including the use of channel steel of holder, and upper frame corner position standpipe connected vertically, and being welded on adjacent Reinforced pipe between standpipe.
The construction system of the utility model Cable stayed Bridge Main Tower as described above and steel anchor beam, further, the pre-embedded steel slab Length dimension it is smaller 20mm~60mm than the length dimension of joist top surface, the width of the width dimensions and joist top surface of pre-embedded steel slab It is equal sized;The length of WELDING STUDS is 150mm~220mm.
The construction system of the utility model Cable stayed Bridge Main Tower as described above and steel anchor beam, further, in the king-post steel Template is the steel plate by preservative treatment, and the thickness of steel plate is 10mm~20mm;The height of king-post steel inner template is held in the palm equal to lower part The distance between top surface of the beam and top joist bottom surface.
The utility model construction system, which can be realized, is fused to steel anchor beam installation in king-tower structure construction, reduces The merogenesis construction times of king-tower are not only more advantageous to the inherent quality and presentation quality of control king-tower structure, more shorten construction Period greatly reduces waste of material.
Description of the drawings
By being described in detail made by conjunction with the following drawings, the above-mentioned and/or otherwise advantage of the utility model will It becoming more apparent upon and is easier to understand, these attached drawings are only schematical, are not intended to limit the utility model, wherein:
Fig. 1 is the construction method flow diagram of Cable stayed Bridge Main Tower and steel anchor beam;
Fig. 2 is that a kind of Cable stayed Bridge Main Tower merogenesis of embodiment of the utility model is intended to;
Fig. 3 is the second king-tower merogenesis and steel anchor beam arrangement schematic diagram of a kind of embodiment of the utility model;
Fig. 4 is the joist and pre-embedded steel slab connection diagram of a kind of embodiment of the utility model;
Fig. 5 is a kind of steel anchor beam falsework front schematic view of embodiment of the utility model;
Fig. 6 is a kind of steel anchor beam falsework schematic top plan view of embodiment of the utility model.
In attached drawing, parts list represented by the reference numerals are as follows:
1, the first tower body, the 2, second tower body, 3, cable guard arm, 4, armored concrete corbel, 5, steel anchor beam, 6, pre-buried steel Plate, 7, WELDING STUDS, 8, steel anchor beam falsework, 9, king-post steel inner template, the 11, first king-tower merogenesis, the 12, second king-tower merogenesis, 13, third king-tower merogenesis, the 14, the 4th king-tower merogenesis, 41, lower part corbel, 42, top corbel, the 51, first steel anchor beam, 52, second Steel anchor beam, 53, third steel anchor beam, the 54, the 4th steel anchor beam, the 55, the 5th steel anchor beam, the 56, the 6th steel anchor beam, the 57, the 7th steel anchor beam, 58, the 8th steel anchor beam, 81, upper frame, 82, standpipe, 83, reinforced pipe.
Specific implementation mode
Hereinafter, the implementation of the Cable stayed Bridge Main Tower of the utility model and the construction system of steel anchor beam is described with reference to the accompanying drawings Example.
The embodiment recorded herein is the specific specific implementation mode of the utility model, for illustrating the utility model Design, is explanatory and illustrative, should not be construed as the limit to the utility model embodiment and the scope of the utility model System.In addition to the embodiment recorded herein, those skilled in the art can also be based on the application claims and specification institute is public For the content opened using obvious other technical solutions, these technical solutions include doing using the embodiment to recording herein Go out the technical solution of any obvious substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the utility model, it is schematically indicated each section Shape and its correlation.It note that the structure of each component for the ease of clearly showing the utility model embodiment, respectively It is not drawn according to identical ratio between attached drawing.Identical reference marker is for indicating identical part.
Fig. 2-Fig. 6 shows a kind of Cable stayed Bridge Main Tower of embodiment of the utility model and the construction system of steel anchor beam, cable-stayed bridge King-tower includes the first tower body 1 and the second tower body 2, and the corresponding cable guard arm in position is arranged at intervals on the first tower body and the second tower body 3 and armored concrete corbel 4;Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;King-tower merogenesis is equipped between the upper and lower every setting Lower part corbel 41 and top corbel 42;Steel anchor beam 5 is located at 2 on the first tower body 1 and the second tower body;
Construction system includes:Pre-embedded steel slab 6, king-post steel inner template 9 and steel anchor beam falsework 8;
As shown in figure 4, pre-embedded steel slab 6 is arranged in the top surface of corbel, pre-embedded steel slab 6 passes through WELDING STUDS 7 and corbel steel bar welding It connects;In a specific embodiment, the length dimension of pre-embedded steel slab 6 is smaller 20mm~60mm than the length dimension of joist top surface, in advance The width dimensions for burying steel plate 6 are equal with the width dimensions of joist top surface;The length of WELDING STUDS 7 is 150mm~220mm;For example, cutting Power nail is using 22 round ends of φ weldering nail, long 200mm, spacing 200mm;
King-post steel inner template 9 is arranged between lower part joist top surface and top joist bottom surface, using connection reinforcing bar and king-tower The main reinforcement of merogenesis is welded and fixed;In a specific embodiment, king-post steel inner template 9 is the steel plate by preservative treatment, steel plate Thickness be 10mm~20mm;The height of king-post steel inner template 9 be equal between lower part joist top surface and top joist bottom surface away from From;
As shown in figure 3, the lower part of steel anchor beam falsework 8 is mounted on existed building flat surface or completed steel anchor beam top On plate, the top surface of steel anchor beam falsework 8 is flushed with the pre-embedded steel slab 6 installed on the joist top surface of lower part;Before concreting Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework 8, steel anchor beam waits for king-tower merogenesis concrete with pre-embedded steel slab It is in place that completion is welded to connect after cast.
As shown in Fig. 2, Cable stayed Bridge Main Tower includes the first king-tower merogenesis 11, the second king-tower merogenesis 12, the successively from the bottom to top Three king-tower merogenesis 13 and the 4th king-tower merogenesis 14, steel anchor beam from the bottom to top successively include the first steel anchor beam 51, the second steel anchor beam 52, Third steel anchor beam 53, the 4th steel anchor beam 54, the 5th steel anchor beam 55, the 6th steel anchor beam 56, the 7th steel anchor beam 57 and the 8th steel anchor beam 58。
Since the second king-tower merogenesis includes third steel anchor beam and the 4th steel anchor beam, between each two corbel, construction space is excessively Narrow and steel anchor beam is close on the inside of the second king-tower merogenesis, it is impossible to row installation again after fractionation.Carrying out steel anchor beam installation in king-tower When construction, if determining king-post merogenesis according to the position of steel anchor beam installation, cause king-post merogenesis more, to increase king-post master The number of turnover of muscle connector, prestress steel twist wire terminal and the inside and outside template of king-post, inherent quality to king-post tower column structure and Presentation quality has certain influence.
Below in conjunction with the method that Fig. 1 and Fig. 2 illustrate to construct using above-described embodiment construction system, step 1, installation the Pre-embedded steel slab on two king-tower merogenesis lower part joists, pre-embedded steel slab pass through WELDING STUDS and corbel reinforcement welding;Step 2, by second King-tower merogenesis top joist influences, and third steel anchor beam, the 4th steel anchor beam cannot be installed simultaneously, before concreting and need to pour It installs respectively afterwards.The steel anchor beam installed before concreting will influence the construction of king-tower internal model herein after installation, be supported from internal model From the aspect of reinforcing, traditional wooden model cannot be used to construct, therefore the part between third steel anchor beam, the 4th steel anchor beam uses tower Column steel inner template.It is noted that the normal inside and outside mould of king-tower situation template is all made of wooden model, fixed with split bolt;Step 3, by Concreting is not carried out also in the corresponding lower part joist of third steel anchor beam, therefore third steel anchor beam needs to utilize steel anchor beam interim Holder is fixed temporarily.Then remaining king-tower reinforcing bar, template and concrete construction are carried out successively, wait for that concrete strength reaches To the 4th steel anchor beam of installation when design strength, and remove the steel anchor beam falsework below third steel anchor beam.The utility model is applied Work system, which can be realized, is fused to steel anchor beam installation in king-tower structure construction, reduces the merogenesis construction times of king-tower, It is not only more advantageous to the inherent quality and presentation quality of control king-tower structure, construction period is more shortened, greatly reduces material Waste.
In a kind of Cable stayed Bridge Main Tower of specific embodiment and the construction system of steel anchor beam, as shown in Figure 5 and Figure 6, steel anchor The rectangular top frame 81 that beam falsework 8 is welded including the use of channel steel, with upper frame corner position standpipe 82 connected vertically, and weldering The reinforced pipe 83 being connected between adjacent standpipe 82.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to the purpose for realizing the utility model.

Claims (5)

1. the construction system of a kind of Cable stayed Bridge Main Tower and steel anchor beam, which is characterized in that the Cable stayed Bridge Main Tower includes the first tower body With the second tower body, the corresponding cable guard arm in position and reinforced beam are arranged at intervals on first tower body and the second tower body Support;The Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;The king-tower merogenesis is equipped with upper and lower spaced upper beam Support and lower part corbel;Steel anchor beam is located on the first tower body and the second tower body;The construction system includes:Pre-embedded steel slab, king-post Steel inner template and steel anchor beam falsework;The pre-embedded steel slab is arranged in the top surface of corbel, and pre-embedded steel slab passes through WELDING STUDS and beam Hold in the palm reinforcement welding;The king-post steel inner template is arranged between lower part joist top surface and top joist bottom surface, using connection reinforcing bar It is welded and fixed with the main reinforcement of king-tower merogenesis;The lower part of the steel anchor beam falsework is mounted on existed building flat surface or is completed Steel anchor beam top plate on, the top surface of steel anchor beam falsework is flushed with the pre-embedded steel slab installed on the joist top surface of lower part;In coagulation Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework by soil before pouring, and steel anchor beam waits for king-tower with pre-embedded steel slab It is in place it to be welded to connect completion after the cast of merogenesis concrete.
2. the construction system of Cable stayed Bridge Main Tower according to claim 1 and steel anchor beam, which is characterized in that the cable-stayed bridge master Tower includes the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel successively from the bottom to top Anchor beam includes the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the successively from the bottom to top Six steel anchor beams, the 7th steel anchor beam and the 8th steel anchor beam.
3. the construction system of Cable stayed Bridge Main Tower according to claim 1 and steel anchor beam, which is characterized in that the steel anchor beam faces When the rectangular top frame that is welded including the use of channel steel of holder, and upper frame corner position standpipe connected vertically, and being welded on adjacent Reinforced pipe between standpipe.
4. the construction system of Cable stayed Bridge Main Tower according to claim 1 and steel anchor beam, which is characterized in that the pre-embedded steel slab Length dimension it is smaller 20mm~60mm than the length dimension of joist top surface, the width of the width dimensions and joist top surface of pre-embedded steel slab It is equal sized;The length of WELDING STUDS is 150mm~220mm.
5. the construction system of Cable stayed Bridge Main Tower according to claim 1 and steel anchor beam, which is characterized in that in the king-post steel Template is the steel plate by preservative treatment, and the thickness of steel plate is 10mm~20mm;The height of king-post steel inner template is held in the palm equal to lower part The distance between top surface of the beam and top joist bottom surface.
CN201820128371.1U 2018-01-25 2018-01-25 The construction system of Cable stayed Bridge Main Tower and steel anchor beam Withdrawn - After Issue CN207812307U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820128371.1U CN207812307U (en) 2018-01-25 2018-01-25 The construction system of Cable stayed Bridge Main Tower and steel anchor beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820128371.1U CN207812307U (en) 2018-01-25 2018-01-25 The construction system of Cable stayed Bridge Main Tower and steel anchor beam

Publications (1)

Publication Number Publication Date
CN207812307U true CN207812307U (en) 2018-09-04

Family

ID=63325232

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820128371.1U Withdrawn - After Issue CN207812307U (en) 2018-01-25 2018-01-25 The construction system of Cable stayed Bridge Main Tower and steel anchor beam

Country Status (1)

Country Link
CN (1) CN207812307U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316150A (en) * 2018-01-25 2018-07-24 北京城建道桥建设集团有限公司 The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN109930488A (en) * 2019-03-06 2019-06-25 安徽省公路桥梁工程有限公司 The construction method of oblique cord tower constructing structure system
CN111519546A (en) * 2020-05-26 2020-08-11 武船重型工程股份有限公司 Three-dimensional application engineering frame of steel anchor beam

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108316150A (en) * 2018-01-25 2018-07-24 北京城建道桥建设集团有限公司 The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN108316150B (en) * 2018-01-25 2024-03-15 北京城建道桥建设集团有限公司 Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
CN109930488A (en) * 2019-03-06 2019-06-25 安徽省公路桥梁工程有限公司 The construction method of oblique cord tower constructing structure system
CN111519546A (en) * 2020-05-26 2020-08-11 武船重型工程股份有限公司 Three-dimensional application engineering frame of steel anchor beam

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN102146658B (en) Locally uncombined suspension bridge steel-concrete combined bridge deck system and construction method of combined bridge deck system
CN105569224A (en) Concrete-filled steel tube edge restraint overlapping integrated shear wall and preparing and installation methods thereof
CN108035438A (en) A kind of concrete assembled frame structure system of high-strength high ductility and connection method
CN207812307U (en) The construction system of Cable stayed Bridge Main Tower and steel anchor beam
CN108104284B (en) Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method
CN109469349A (en) A kind of floor strengthening reconstruction method for adding reinforced concrete secondary beam
CN111677327A (en) Prestressed brace reinforced concrete beam structure
CN207919746U (en) A kind of prefabricated node of high-strength high concrete assembled frame of ductility
CN107130715A (en) Teeth groove is poured after a kind of to be linked and packed the construction method of formula building roof system
CN111364364A (en) Construction method for cast-in-place prestressed concrete continuous box girder
CN206174120U (en) Prefabricated constructional column and structure thereof
CN105649248B (en) Prefabricated PC concrete core slab and Cast-in-situ Beam integral construction method
CN108316150A (en) The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN209227836U (en) Prefabricated concrete structure wall-column all steel is keyed structure
CN110644662A (en) Prefabricated flat slab composite slab based on stress and splitting method thereof
KR101358878B1 (en) Reinforcement member and girder using the same
CN207919747U (en) A kind of high-strength high concrete assembled frame structure system of ductility
CN112376400B (en) Wet joint structure of precast concrete beam and construction process thereof
CN102936953B (en) Construction method of a bridging-arm stiffened steel structure template
KR101028372B1 (en) Construction for connection of the truss assembled deck plates
CN212388856U (en) Cast-in-place clear water concrete batter post structure of prestressing force
CN214061940U (en) Precast concrete assembled structure with rib mold structure
CN105926820A (en) Construction method for prefabricated beam steel bearing plate resistance net piece combination floor
KR20120008667A (en) Beam construction method using deckplate end-reinforcing member

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
AV01 Patent right actively abandoned

Granted publication date: 20180904

Effective date of abandoning: 20240315

AV01 Patent right actively abandoned

Granted publication date: 20180904

Effective date of abandoning: 20240315

AV01 Patent right actively abandoned
AV01 Patent right actively abandoned