CN108316150A - The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam - Google Patents
The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam Download PDFInfo
- Publication number
- CN108316150A CN108316150A CN201810073072.7A CN201810073072A CN108316150A CN 108316150 A CN108316150 A CN 108316150A CN 201810073072 A CN201810073072 A CN 201810073072A CN 108316150 A CN108316150 A CN 108316150A
- Authority
- CN
- China
- Prior art keywords
- anchor beam
- steel anchor
- tower
- steel
- king
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 265
- 239000010959 steel Substances 0.000 title claims abstract description 265
- 238000010276 construction Methods 0.000 title claims abstract description 94
- 230000003014 reinforcing effect Effects 0.000 claims description 21
- 230000002787 reinforcement Effects 0.000 claims description 20
- 239000004567 concrete Substances 0.000 claims description 16
- 238000003466 welding Methods 0.000 claims description 15
- 238000005266 casting Methods 0.000 claims description 3
- 230000015271 coagulation Effects 0.000 claims 1
- 238000005345 coagulation Methods 0.000 claims 1
- 239000002689 soil Substances 0.000 claims 1
- 239000000463 material Substances 0.000 abstract description 9
- 238000009434 installation Methods 0.000 abstract description 7
- 239000002699 waste material Substances 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 4
- 230000001360 synchronised effect Effects 0.000 description 4
- 238000005516 engineering process Methods 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 238000004873 anchoring Methods 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000006835 compression Effects 0.000 description 1
- 238000007906 compression Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 239000003550 marker Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 239000003755 preservative agent Substances 0.000 description 1
- 230000002335 preservative effect Effects 0.000 description 1
- 239000011150 reinforced concrete Substances 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 230000007306 turnover Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D11/00—Suspension or cable-stayed bridges
- E01D11/04—Cable-stayed bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of Cable stayed Bridge Main Towers and the construction system and construction method of steel anchor beam, construction method to include the following steps:Step 1, pre-embedded steel slab is installed;Pre-embedded steel slab is arranged in the top surface of corbel;Step 2, king-post steel inner template is arranged between lower part joist top surface and top joist bottom surface;Step 3, the lower part of steel anchor beam falsework is mounted on existed building flat surface or completed steel anchor beam top plate, and steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework before king-tower merogenesis concreting;Step 4, the corresponding steel anchor beam of lower part joist and pre-embedded steel slab are welded to connect completion in place;Then steel anchor beam corresponding with top joist is installed, it is welded to connect with corresponding pre-embedded steel slab.Steel anchor beam installation is fused in tower column structure construction by construction method of the present invention, reduces the merogenesis construction times of king-post, is conducive to the inherent quality and presentation quality that control tower column structure, is more shortened construction period, reduce waste of material.
Description
Technical field
The invention belongs to CONSTRUCTION OF CABLE-STAYED BRIDGE technical fields, more particularly to the construction system of a kind of Cable stayed Bridge Main Tower and steel anchor beam
System and construction method.
Background technology
Cable-stayed bridge be it is a kind of by tower compression, drag-line tension, beam body by a kind of curved combined system bridge.The system can be effective
Building structure height is reduced, mitigates weight, save material.Modern cable-stayed bridge is with its good structural behaviour, larger leap energy
The architectural image of power, rational economic indicator and grace occupies an important position in modern bridge structure, due to modern structure
The progress of theory, Materials with High Strength, computer technology and construction method makes cable-stayed bridge be rapidly developed.
Cable stayed Bridge Main Tower is the anchored end of drag-line, and to ensure the rigidity at tensioning position, steel anchor beam is arranged in king-tower.Relatively
In using steel strand wires or increasing reinforcing bar come for increasing the rigidity of structure, setting steel anchor beam has that construction method is simple, shortens construction week
The features such as phase.According to the segmented construction requirement of king-post, king-post inner space, steel anchor beam structure and process characteristic, king-tower anchoring section
Each segment concrete wants one-time-concreting to complete, and requires king-post concrete structure with one-pass molding after formwork support arrangement, meet reinforcing bar binding,
Installation after steel plate installation, formwork support arrangement, the interim in place and concrete placings of steel anchor beam.
In steel anchor beam installation, to be the position installed according to steel anchor beam in king-post determine king-post merogenesis carrying out, such as
Fruit each steel anchor beam position is respectively provided with king-post merogenesis, causes king-post merogenesis more, to increase king-post main reinforcement connector, prestress steel
The number of turnover of twisted-wire contact and the inside and outside template of king-post has certain influence to the inherent quality of tower column structure and presentation quality.
If one king-post merogenesis of each two steel anchor beam correspondence can not since construction space is excessively narrow between each two joist simultaneously
The steel anchor beam of lower part is installed after the completion of concreting.
Invention content
The object of the present invention is to provide a kind of Cable stayed Bridge Main Tower and the construction systems and construction method of steel anchor beam, to solve to hold in the palm
Construction space is excessively narrow between beam, the problem of steel anchor beam of lower part can not be installed after the completion of concreting.
The technical solution that the present invention solves above-mentioned technical problem is as follows:A kind of construction system of Cable stayed Bridge Main Tower and steel anchor beam
System, which is characterized in that the Cable stayed Bridge Main Tower includes the first tower body and the second tower body, on first tower body and the second tower body between
Every being provided with the corresponding cable guard arm in position and armored concrete corbel;The Cable stayed Bridge Main Tower includes more than two king-towers point
Section;The king-tower merogenesis is equipped with upper and lower spaced top corbel and lower part corbel;Steel anchor beam is located in the first tower body and
On two tower bodies;The construction system includes:Pre-embedded steel slab, king-post steel inner template and steel anchor beam falsework;The pre-embedded steel slab
It is arranged in the top surface of corbel, pre-embedded steel slab passes through WELDING STUDS and corbel reinforcement welding;The king-post steel inner template is arranged in lower part
Between joist top surface and top joist bottom surface, it is welded and fixed using the main reinforcement of connection reinforcing bar and king-tower merogenesis;The steel anchor beam faces
When holder lower part be mounted on existed building flat surface or completed steel anchor beam top plate, the top surface of steel anchor beam falsework with
The pre-embedded steel slab installed on the joist top surface of lower part flushes;Steel anchor beam corresponding with lower part joist is installed to before concreting
On steel anchor beam falsework, steel anchor beam is welded to connect completion in place with pre-embedded steel slab after the cast of king-tower merogenesis concrete.
The construction system of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, further, the Cable stayed Bridge Main Tower by
Under it is supreme successively include the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel anchor beam
Include the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the 6th steel successively from the bottom to top
Anchor beam, the 7th steel anchor beam and the 8th steel anchor beam.
The technical solution that the present invention solves above-mentioned technical problem is as follows:A kind of construction party of Cable stayed Bridge Main Tower and steel anchor beam
Method, the construction method include the following steps:Step 1, pre-embedded steel slab is installed;The pre-embedded steel slab is arranged in the top surface of corbel,
After corbel reinforcement construction is completed and is checked and accepted, pre-embedded steel slab is passed through into WELDING STUDS and corbel reinforcement welding;Step 2, it props up and founds king-post
Steel inner template;King-post steel inner template is arranged between lower part joist top surface and top joist bottom surface, and king-post steel inner template is using company
The main reinforcement for connecing reinforcing bar and king-tower merogenesis is welded and fixed;Step 3, the lower part of steel anchor beam falsework is mounted on existed building flat surface
Or on completed steel anchor beam top plate, steel anchor beam corresponding with lower part joist is installed to steel before king-tower merogenesis concreting
On anchor beam falsework;Step 4, casting concrete after the completion of other reinforcing bars of king-tower merogenesis, template construction;By lower part joist pair
It is in place that the steel anchor beam and pre-embedded steel slab answered are welded to connect completion;Then corresponding with top joist steel anchor beam is installed, by its with it is right
The pre-embedded steel slab answered is welded to connect;Repeat the construction that step 1 completes Cable stayed Bridge Main Tower and steel anchor beam to step 4.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that the Cable stayed Bridge Main Tower packet
The first tower body and the second tower body are included, the corresponding cable guard arm in position and steel are arranged at intervals on first tower body and the second tower body
Reinforced concrete corbel;The Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;The king-tower merogenesis is equipped between the upper and lower every setting
The top corbel and lower part corbel set;Steel anchor beam is located on the first tower body and the second tower body.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that step 2 specifically includes, first
It carries out the in place of king-post cable guide pipe and fixes, then king-tower merogenesis reinforcement construction to lower beam restitope sets place, and it is laggard to check and accept completion
The construction of row king-post steel inner template.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that step 4 specifically includes, main
The inside and outside mould of tower merogenesis other parts template is all made of wooden model, is fixed using split bolt between inside and outside mould.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that in the construction for carrying out step 3
When, the top surface of steel anchor beam falsework is flushed with the pre-embedded steel slab installed on the joist top surface of lower part.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that the steel anchor beam props up temporarily
The rectangular top frame that frame is welded including the use of channel steel, and upper frame corner position standpipe connected vertically, and it is welded on adjacent standpipe
Between reinforced pipe.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that the Cable stayed Bridge Main Tower by
Under it is supreme successively include the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel anchor beam
Include the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the 6th steel successively from the bottom to top
Anchor beam, the 7th steel anchor beam and the 8th steel anchor beam.
The construction method of present invention Cable stayed Bridge Main Tower as described above and steel anchor beam, it is preferred that pacify on the first king-tower merogenesis
Fill the first steel anchor beam and the second steel anchor beam;Third steel anchor beam and the 4th steel anchor beam are installed on the second king-tower merogenesis;Third king-tower point
5th steel anchor beam and the 6th steel anchor beam are installed on section;7th steel anchor beam and the 8th steel anchor beam are installed on the 4th king-tower merogenesis.
The beneficial effects of the invention are as follows:
The above-mentioned construction method of the present invention is that steel anchor beam installation is fused in tower column structure construction, reduces the merogenesis of king-post
Construction times are not only more advantageous to the inherent quality and presentation quality of control tower column structure, more shorten construction period, subtract significantly
Waste of material is lacked.
Steel anchor beam is added in Cable stayed Bridge Main Tower, for increasing king-tower reinforcing bar or part increase transverse prestress,
Save construction period and material.After determining using steel anchor beam, steel anchor beam producer can proceed by the processing of steel anchor beam,
It synchronous with king-tower structure construction can carry out.And if if using part to increase reinforcing bar or prestressing force, due to king-tower reinforcing bar itself compared with
It is close, be used for laying increased reinforcing bar or prestress wire without space, very big inconvenience brought to construction, and very likely by
In reinforcing bar gap is smaller lead to concreting when can not vibration compacting, influence concrete quality, bring prodigious hidden danger of quality.
If increasing prestress wire, prestressed stretch-draw and mud jacking can cause the extension of entire Construction of Pylon duration, and
Have a significant impact to the presentation quality of king-tower.Artificial and material cost accordingly increases caused by therewith.In comparison, using steel
Anchor beam is not only constructed fairly simple convenience, and synchronous with king-tower structure construction can be carried out, and construction period is substantially reduced.
Description of the drawings
By being described in detail made by conjunction with the following drawings, above-mentioned and/or otherwise advantage of the invention will become
It becoming apparent from and is easier to understand, these attached drawings are only schematical, are not intended to limit the present invention, wherein:
Fig. 1 is a kind of Cable stayed Bridge Main Tower of embodiment and the construction method flow diagram of steel anchor beam;
Fig. 2 is that the Cable stayed Bridge Main Tower merogenesis of an embodiment of the present invention is intended to;
Fig. 3 is the second king-tower merogenesis and steel anchor beam arrangement schematic diagram of an embodiment of the present invention;
Fig. 4 is the joist and pre-embedded steel slab connection diagram of an embodiment of the present invention;
Fig. 5 is the steel anchor beam falsework front schematic view of an embodiment of the present invention;
Fig. 6 is the steel anchor beam falsework schematic top plan view of an embodiment of the present invention.
In attached drawing, parts list represented by the reference numerals are as follows:
1, the first tower body, the 2, second tower body, 3, cable guard arm, 4, armored concrete corbel, 5, steel anchor beam, 6, pre-embedded steel slab, 7,
WELDING STUDS, 8, steel anchor beam falsework, 9, king-post steel inner template, the 11, first king-tower merogenesis, the 12, second king-tower merogenesis, 13,
Three king-tower merogenesis, the 14, the 4th king-tower merogenesis, 41, lower part corbel, 42, top corbel, the 51, first steel anchor beam, the 52, second steel anchor
Beam, 53, third steel anchor beam, the 54, the 4th steel anchor beam, the 55, the 5th steel anchor beam, the 56, the 6th steel anchor beam, the 57, the 7th steel anchor beam, 58,
8th steel anchor beam, 81, upper frame, 82, standpipe, 83, reinforced pipe.
Specific implementation mode
Hereinafter, the Cable stayed Bridge Main Tower of the present invention and the construction system and construction method of steel anchor beam are described with reference to the accompanying drawings
Embodiment.
The embodiment recorded herein is the specific specific implementation mode of the present invention, for illustrating design of the invention,
It is explanatory and illustrative, should not be construed as the limitation to embodiment of the present invention and the scope of the invention.Except what is recorded herein
Outside embodiment, those skilled in the art can also based on the application claims and specification disclosure of that using aobvious and
The other technical solutions being clear to, these technical solutions include any obvious using making for the embodiment to recording herein
The technical solution of substitutions and modifications.
The attached drawing of this specification is schematic diagram, aids in illustrating the design of the present invention, it is schematically indicated the shape of each section
And its correlation.The structure of each component for the ease of clearly showing the embodiment of the present invention is note that, between each attached drawing
Do not drawn according to identical ratio.Identical reference marker is for indicating identical part.
Fig. 2-Fig. 6 shows the Cable stayed Bridge Main Tower of an embodiment of the present invention and the construction system of steel anchor beam, Cable stayed Bridge Main Tower
Including the first tower body 1 and the second tower body 2, corresponding 3 He of cable guard arm in position is arranged at intervals on the first tower body and the second tower body
Armored concrete corbel 4;Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;King-tower merogenesis be equipped with up and down it is spaced under
Portion's corbel 41 and top corbel 42;Steel anchor beam 5 is located in 2 on the first tower body 1 and the second tower body;
Construction system includes:Pre-embedded steel slab 6, king-post steel inner template 9 and steel anchor beam falsework 8;
As shown in figure 4, pre-embedded steel slab 6 is arranged in the top surface of corbel, pre-embedded steel slab 6 passes through WELDING STUDS 7 and corbel reinforcement welding;
In a kind of specific embodiment, the length dimension of pre-embedded steel slab 6 is smaller 20mm~60mm than the length dimension of joist top surface, pre-embedded steel slab
6 width dimensions are equal with the width dimensions of joist top surface;The length of WELDING STUDS 7 is 150mm~220mm;For example, WELDING STUDS is adopted
It is welded and is followed closely with 22 round ends of φ, long 200mm, spacing 200mm;
King-post steel inner template 9 is arranged between lower part joist top surface and top joist bottom surface, using connection reinforcing bar and king-tower merogenesis
Main reinforcement be welded and fixed;In a specific embodiment, king-post steel inner template 9 is the steel plate by preservative treatment, the thickness of steel plate
Degree is 10mm~20mm;The height of king-post steel inner template 9 is equal to the distance between lower part joist top surface and top joist bottom surface;
As shown in figure 3, the lower part of steel anchor beam falsework 8 is mounted on existed building flat surface or completed steel anchor beam top plate
On, the top surface of steel anchor beam falsework 8 is flushed with the pre-embedded steel slab 6 installed on the joist top surface of lower part;It will before concreting
Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework 8, and steel anchor beam waits for that king-tower merogenesis concrete pours with pre-embedded steel slab
It is in place that completion is welded to connect after note.
As shown in Fig. 2, Cable stayed Bridge Main Tower includes the first king-tower merogenesis 11, the second king-tower merogenesis 12, the successively from the bottom to top
Three king-tower merogenesis 13 and the 4th king-tower merogenesis 14, steel anchor beam from the bottom to top successively include the first steel anchor beam 51, the second steel anchor beam 52,
Third steel anchor beam 53, the 4th steel anchor beam 54, the 5th steel anchor beam 55, the 6th steel anchor beam 56, the 7th steel anchor beam 57 and the 8th steel anchor beam
58。
Fig. 1 shows the Cable stayed Bridge Main Tower of an embodiment of the present invention and the construction method of steel anchor beam, construction method include with
Lower step:
Step 1, pre-embedded steel slab 6 is installed;As shown in figure 4, pre-embedded steel slab 6 is arranged in the top surface of corbel, it is complete in corbel reinforcement construction
At and check and accept after, pre-embedded steel slab 6 is passed through into WELDING STUDS 7 and corbel reinforcement welding;
Step 2, it props up and founds king-post steel inner template 9;As shown in figure 3, the setting of king-post steel inner template 9 is held in the palm in lower part joist top surface and top
Between soffit, king-post steel inner template 9 is welded and fixed using the main reinforcement of connection reinforcing bar and king-tower merogenesis;Step 2 specifically includes, first
It carries out the in place of king-post cable guide pipe and fixes, then at king-tower merogenesis reinforcement construction to 41 position of lower part corbel, after the completion of examination
Carry out the construction of king-post steel inner template 9.Since it is desired that steel anchor beam corresponding with lower part joist is installed before concreting, installation
The construction that influence king-post inner template herein cannot be used traditional wooden model by steel anchor beam from the aspect of internal model bracing reinforcement afterwards
Construction;
Step 3, the lower part of steel anchor beam falsework 8 is mounted on existed building flat surface or completed 5 top plate of steel anchor beam,
Steel anchor beam corresponding with lower part joist 5 is installed on steel anchor beam falsework 8 before king-tower merogenesis concreting;Such as Fig. 5 and
Shown in Fig. 6, the rectangular top frame 81 that steel anchor beam falsework 8 is welded including the use of channel steel, with 81 corner position vertical connection of upper frame
Standpipe 82, and the reinforced pipe 83 that is welded between adjacent standpipe 82.It is influenced by king-tower merogenesis top joist, adjacent steel
Anchor beam cannot be installed simultaneously, it is necessary to be installed before concreting and respectively after pouring;
Step 4, casting concrete after the completion of other reinforcing bars of king-tower merogenesis, template construction;By the corresponding steel anchor beam of lower part joist 5
It is in place it to be welded to connect completion with pre-embedded steel slab 6;Then corresponding with top joist steel anchor beam 5 is installed, by its with it is corresponding pre-buried
Steel plate 6 is welded to connect;Step 4 specifically includes, and the inside and outside mould of king-tower merogenesis other parts template is all made of wooden model, between inside and outside mould
It is fixed using split bolt.
Repeat the construction that step 1 completes Cable stayed Bridge Main Tower and steel anchor beam 5 to step 4.
The above-mentioned construction method of the present invention is that steel anchor beam installation is fused in tower column structure construction, reduces king-post
Merogenesis construction times are not only more advantageous to the inherent quality and presentation quality of control tower column structure, more shorten construction period, greatly
Reduce waste of material greatly.
Steel anchor beam is added in Cable stayed Bridge Main Tower, for increasing king-tower reinforcing bar or part increase transverse prestress,
Save construction period and material.After determining using steel anchor beam, steel anchor beam producer can proceed by the processing of steel anchor beam,
It synchronous with king-tower structure construction can carry out.And if if using part to increase reinforcing bar or prestressing force, due to king-tower reinforcing bar itself compared with
It is close, be used for laying increased reinforcing bar or prestress wire without space, very big inconvenience brought to construction, and very likely by
In reinforcing bar gap is smaller lead to concreting when can not vibration compacting, influence concrete quality, bring prodigious hidden danger of quality.
If increasing prestress wire, prestressed stretch-draw and mud jacking can cause the extension of entire Construction of Pylon duration, and
Have a significant impact to the presentation quality of king-tower.Artificial and material cost accordingly increases caused by therewith.In comparison, using steel
Anchor beam is not only constructed fairly simple convenience, and synchronous with king-tower structure construction can be carried out, and construction period is substantially reduced.
In the construction method of a kind of preferred Cable stayed Bridge Main Tower and steel anchor beam, when carrying out the construction of step 3, steel anchor beam
The top surface of falsework 8 is flushed with the pre-embedded steel slab 6 installed on the joist top surface of lower part.As top of support is more slightly higher than pre-embedded steel slab
Words, will cause when carrying out king-tower concreting, and concrete is entered between steel anchor beam and pre-embedded steel slab, it is difficult to it clears up, from
And steel anchor beam elevation and cable guide pipe elevation is caused larger deviation occur.
Each technical characteristic of above-mentioned disclosure is not limited to disclosed and other feature combination, and those skilled in the art are also
Other combinations between each technical characteristic can be carried out according to the purpose of invention, be subject to realize the present invention purpose.
Claims (10)
1. the construction system of a kind of Cable stayed Bridge Main Tower and steel anchor beam, which is characterized in that the Cable stayed Bridge Main Tower includes the first tower body
With the second tower body, the corresponding cable guard arm in position and reinforced beam are arranged at intervals on first tower body and the second tower body
Support;The Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;The king-tower merogenesis is equipped with upper and lower spaced upper beam
Support and lower part corbel;Steel anchor beam is located on the first tower body and the second tower body;The construction system includes:Pre-embedded steel slab, king-post
Steel inner template and steel anchor beam falsework;The pre-embedded steel slab is arranged in the top surface of corbel, and pre-embedded steel slab passes through WELDING STUDS and beam
Hold in the palm reinforcement welding;The king-post steel inner template is arranged between lower part joist top surface and top joist bottom surface, using connection reinforcing bar
It is welded and fixed with the main reinforcement of king-tower merogenesis;The lower part of the steel anchor beam falsework is mounted on existed building flat surface or is completed
Steel anchor beam top plate on, the top surface of steel anchor beam falsework is flushed with the pre-embedded steel slab installed on the joist top surface of lower part;In coagulation
Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework by soil before pouring, and steel anchor beam waits for king-tower with pre-embedded steel slab
It is in place it to be welded to connect completion after the cast of merogenesis concrete.
2. the construction system of Cable stayed Bridge Main Tower according to claim 1 and steel anchor beam, which is characterized in that the cable-stayed bridge master
Tower includes the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel successively from the bottom to top
Anchor beam includes the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the successively from the bottom to top
Six steel anchor beams, the 7th steel anchor beam and the 8th steel anchor beam.
3. the construction method of a kind of Cable stayed Bridge Main Tower and steel anchor beam, which is characterized in that the construction method includes the following steps:Step
Rapid 1, pre-embedded steel slab is installed;The pre-embedded steel slab is arranged in the top surface of corbel, will be pre- after corbel reinforcement construction is completed and is checked and accepted
It buries steel plate and passes through WELDING STUDS and corbel reinforcement welding;Step 2, it props up and founds king-post steel inner template;King-post steel inner template is arranged in lower part
Between joist top surface and top joist bottom surface, king-post steel inner template is welded and fixed using the main reinforcement of connection reinforcing bar and king-tower merogenesis;
Step 3, the lower part of steel anchor beam falsework is mounted on existed building flat surface or completed steel anchor beam top plate, in king-tower point
Steel anchor beam corresponding with lower part joist is installed on steel anchor beam falsework before section concreting;Step 4, king-tower merogenesis
Casting concrete after the completion of other reinforcing bars, template construction;The corresponding steel anchor beam of lower part joist and pre-embedded steel slab have been welded to connect
At in place;Then steel anchor beam corresponding with top joist is installed, it is welded to connect with corresponding pre-embedded steel slab;Repeat step 1
The construction of Cable stayed Bridge Main Tower and steel anchor beam is completed to step 4.
4. the construction method of Cable stayed Bridge Main Tower according to claim 3 and steel anchor beam, which is characterized in that the cable-stayed bridge master
Tower includes the first tower body and the second tower body, and the corresponding cable guard arm in position is arranged at intervals on first tower body and the second tower body
With armored concrete corbel;The Cable stayed Bridge Main Tower includes more than two king-tower merogenesis;The king-tower merogenesis is equipped between the upper and lower
Every the top corbel and lower part corbel of setting;Steel anchor beam is located on the first tower body and the second tower body.
5. the construction method of Cable stayed Bridge Main Tower according to claim 4 and steel anchor beam, which is characterized in that step 2 is specifically wrapped
It includes, first carries out the in place of king-post cable guide pipe and fix, then king-tower merogenesis reinforcement construction to lower beam restitope sets place, checks and accepts and completes
The construction of king-post steel inner template is carried out afterwards.
6. the construction method of Cable stayed Bridge Main Tower according to claim 5 and steel anchor beam, which is characterized in that step 4 is specifically wrapped
It includes, the inside and outside mould of king-tower merogenesis other parts template is all made of wooden model, is fixed using split bolt between inside and outside mould.
7. the construction method of Cable stayed Bridge Main Tower according to claim 3 and steel anchor beam, which is characterized in that carrying out step 3
Construction when, the top surface of steel anchor beam falsework is flushed with the pre-embedded steel slab installed on the joist top surface of lower part.
8. according to the construction method of claim 3-7 any one of them Cable stayed Bridge Main Tower and steel anchor beam, which is characterized in that described
The rectangular top frame that steel anchor beam falsework is welded including the use of channel steel, with upper frame corner position standpipe connected vertically, and weldering
The reinforced pipe being connected between adjacent standpipe.
9. the construction method of Cable stayed Bridge Main Tower according to claim 8 and steel anchor beam, which is characterized in that the cable-stayed bridge master
Tower includes the first king-tower merogenesis, the second king-tower merogenesis, third king-tower merogenesis and the 4th king-tower merogenesis, the steel successively from the bottom to top
Anchor beam includes the first steel anchor beam, the second steel anchor beam, third steel anchor beam, the 4th steel anchor beam, the 5th steel anchor beam, the successively from the bottom to top
Six steel anchor beams, the 7th steel anchor beam and the 8th steel anchor beam.
10. the construction method of Cable stayed Bridge Main Tower according to claim 9 and steel anchor beam, which is characterized in that the first king-tower point
First steel anchor beam and the second steel anchor beam are installed on section;Third steel anchor beam and the 4th steel anchor beam are installed on the second king-tower merogenesis;Third
5th steel anchor beam and the 6th steel anchor beam are installed on king-tower merogenesis;7th steel anchor beam and the 8th steel anchor are installed on the 4th king-tower merogenesis
Beam.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810073072.7A CN108316150B (en) | 2018-01-25 | 2018-01-25 | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810073072.7A CN108316150B (en) | 2018-01-25 | 2018-01-25 | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge |
Publications (2)
Publication Number | Publication Date |
---|---|
CN108316150A true CN108316150A (en) | 2018-07-24 |
CN108316150B CN108316150B (en) | 2024-03-15 |
Family
ID=62887787
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810073072.7A Active CN108316150B (en) | 2018-01-25 | 2018-01-25 | Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN108316150B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629420A (en) * | 2019-01-08 | 2019-04-16 | 中铁大桥局集团有限公司 | A kind of king-tower transverse brace structure and its installation method |
CN110184898A (en) * | 2019-06-14 | 2019-08-30 | 中铁大桥局集团有限公司 | The steel skeleton segment of Cable stayed Bridge Main Tower anchorage zone and king-post construction method |
CN111005302A (en) * | 2019-12-30 | 2020-04-14 | 中交路桥华南工程有限公司 | Steel anchor beam mounting method |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4352220A (en) * | 1979-09-20 | 1982-10-05 | Polensky & Zollner | Method for the construction of a cable-stayed or rein-girth bridge |
JP2000080609A (en) * | 1998-09-08 | 2000-03-21 | Nakai Shoko Kk | Damping device for cable and protecting method of cable |
JP2007192011A (en) * | 2005-12-21 | 2007-08-02 | Jfe Koken Corp | Cable anchoring structure of structural body and cable tension adjusting method in cable anchoring structure |
CN101029472A (en) * | 2007-03-21 | 2007-09-05 | 浙江省舟山连岛工程建设指挥部 | Tower column of stayed-cable bridge and its construction |
US20120216357A1 (en) * | 2009-11-06 | 2012-08-30 | Dong-A University Research Foundation For Industry-Academy Cooperation | Constructing method of cable-stayed bridge and temporary cable therefor |
CN102864742A (en) * | 2012-09-05 | 2013-01-09 | 广东省公路勘察规划设计院股份有限公司 | Anchor device of first sliding and then fixing type combined steel anchor boxes of cable stayed bridge and construction method thereof |
CN203440753U (en) * | 2013-07-08 | 2014-02-19 | 中交第二公路工程局有限公司 | Multifunctional steel bar locating framework |
CN104480863A (en) * | 2014-12-12 | 2015-04-01 | 上海市基础工程集团有限公司 | Method for mounting and positioning steel anchor beams for constructing cable-stayed bridge main tower |
CN105970819A (en) * | 2016-05-31 | 2016-09-28 | 中铁大桥局集团第五工程有限公司 | Installation construction method for steel anchor beams |
CN207812307U (en) * | 2018-01-25 | 2018-09-04 | 北京城建道桥建设集团有限公司 | The construction system of Cable stayed Bridge Main Tower and steel anchor beam |
-
2018
- 2018-01-25 CN CN201810073072.7A patent/CN108316150B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4352220A (en) * | 1979-09-20 | 1982-10-05 | Polensky & Zollner | Method for the construction of a cable-stayed or rein-girth bridge |
JP2000080609A (en) * | 1998-09-08 | 2000-03-21 | Nakai Shoko Kk | Damping device for cable and protecting method of cable |
JP2007192011A (en) * | 2005-12-21 | 2007-08-02 | Jfe Koken Corp | Cable anchoring structure of structural body and cable tension adjusting method in cable anchoring structure |
CN101029472A (en) * | 2007-03-21 | 2007-09-05 | 浙江省舟山连岛工程建设指挥部 | Tower column of stayed-cable bridge and its construction |
US20120216357A1 (en) * | 2009-11-06 | 2012-08-30 | Dong-A University Research Foundation For Industry-Academy Cooperation | Constructing method of cable-stayed bridge and temporary cable therefor |
CN102864742A (en) * | 2012-09-05 | 2013-01-09 | 广东省公路勘察规划设计院股份有限公司 | Anchor device of first sliding and then fixing type combined steel anchor boxes of cable stayed bridge and construction method thereof |
CN203440753U (en) * | 2013-07-08 | 2014-02-19 | 中交第二公路工程局有限公司 | Multifunctional steel bar locating framework |
CN104480863A (en) * | 2014-12-12 | 2015-04-01 | 上海市基础工程集团有限公司 | Method for mounting and positioning steel anchor beams for constructing cable-stayed bridge main tower |
CN105970819A (en) * | 2016-05-31 | 2016-09-28 | 中铁大桥局集团第五工程有限公司 | Installation construction method for steel anchor beams |
CN207812307U (en) * | 2018-01-25 | 2018-09-04 | 北京城建道桥建设集团有限公司 | The construction system of Cable stayed Bridge Main Tower and steel anchor beam |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109629420A (en) * | 2019-01-08 | 2019-04-16 | 中铁大桥局集团有限公司 | A kind of king-tower transverse brace structure and its installation method |
CN110184898A (en) * | 2019-06-14 | 2019-08-30 | 中铁大桥局集团有限公司 | The steel skeleton segment of Cable stayed Bridge Main Tower anchorage zone and king-post construction method |
CN111005302A (en) * | 2019-12-30 | 2020-04-14 | 中交路桥华南工程有限公司 | Steel anchor beam mounting method |
CN111005302B (en) * | 2019-12-30 | 2021-07-30 | 中交路桥华南工程有限公司 | Steel anchor beam mounting method |
Also Published As
Publication number | Publication date |
---|---|
CN108316150B (en) | 2024-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105908864B (en) | Fill masonry and the construction method of frame-shear wall prevention Interface Crack structure | |
CN108035438A (en) | A kind of concrete assembled frame structure system of high-strength high ductility and connection method | |
CN106522561A (en) | Long-span concrete frame beam bonded prestressed post-cast strip inside stretching construction method | |
CN103850363B (en) | Prefabricated through hole assembly type reinforced concrete shear wall and construction method of prefabricated through hole assembly type reinforced concrete shear wall | |
WO2021023245A1 (en) | Pile slab-type soil retaining wall integral casting formwork structure and construction method therefor | |
CN108316150A (en) | The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam | |
CN111364364A (en) | Construction method for cast-in-place prestressed concrete continuous box girder | |
CN207812307U (en) | The construction system of Cable stayed Bridge Main Tower and steel anchor beam | |
CN103966953A (en) | Large-span concrete beam construction method based on unbonded steel strand prestress post-tensioning | |
CN104831639A (en) | Consolidation and release construction method for 0# blocks of ultra-wide non-uniform continuous beam | |
CN103938871B (en) | A kind of construction method adopting the steel core concrete column bonded prestress frame beam structure of reinforced concrete ring beam joint | |
CN103898876B (en) | Method for manufacturing reinforced concrete U-shaped aqueduct casting template without counter bolts | |
CN207919747U (en) | A kind of high-strength high concrete assembled frame structure system of ductility | |
CN205875457U (en) | Fill brickwork and prevent interface crack structure with frame shear force wall | |
CN102936953B (en) | Construction method of a bridging-arm stiffened steel structure template | |
CN204780635U (en) | Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures | |
CN111576620A (en) | Construction method for beam-column core area of stiffened concrete structure | |
CN111236419A (en) | Novel beam column joint of reinforced concrete structure and construction method | |
CN108775086A (en) | The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar | |
CN212388856U (en) | Cast-in-place clear water concrete batter post structure of prestressing force | |
CN104453013A (en) | Prefabricated wall component and fabricated reinforced concrete shear wall | |
CN204691068U (en) | A kind of overlength ring orientation prestress ring beam | |
CN113738102A (en) | Template building block for civil engineering and manufacturing method and using method thereof | |
CN206553938U (en) | Bridge pier integral formwork support one-shot forming structure | |
CN111119056A (en) | Construction method for steel-concrete combined section of inclined tower tip |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Meng Qingmin Inventor after: Li Hui Inventor after: Ji Jingtao Inventor after: Duan Jianglong Inventor after: Chang Litao Inventor after: Zhu Zhuokui Inventor before: Meng Qingmin Inventor before: Li Hui Inventor before: Ji Jingtao |
|
CB03 | Change of inventor or designer information | ||
GR01 | Patent grant | ||
GR01 | Patent grant |