CN206553938U - Bridge pier integral formwork support one-shot forming structure - Google Patents

Bridge pier integral formwork support one-shot forming structure Download PDF

Info

Publication number
CN206553938U
CN206553938U CN201621452913.8U CN201621452913U CN206553938U CN 206553938 U CN206553938 U CN 206553938U CN 201621452913 U CN201621452913 U CN 201621452913U CN 206553938 U CN206553938 U CN 206553938U
Authority
CN
China
Prior art keywords
template
bridge pier
horn mouth
built
shot forming
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201621452913.8U
Other languages
Chinese (zh)
Inventor
顾侃
周润翔
周焕星
王鸯
骆兴荣
郝伟
李锦�
方珊婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Institute Of Communications Planning And Design & Research
Original Assignee
Hangzhou Institute Of Communications Planning And Design & Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Institute Of Communications Planning And Design & Research filed Critical Hangzhou Institute Of Communications Planning And Design & Research
Priority to CN201621452913.8U priority Critical patent/CN206553938U/en
Application granted granted Critical
Publication of CN206553938U publication Critical patent/CN206553938U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model is related to bridge pier integral formwork support one-shot forming structure, is mainly made up of operating platform, set shaped steel formwork, scaffold system and built-in fitting;Operating platform is mainly made up of platform springboard, lower channel and workbench;Set shaped steel formwork is made up of standard paragraphs template and horn mouth template, and standard paragraphs template and horn mouth template composition are constituted by panel, flange, cross rib, perpendicular rib, draw-bar seat, arc reinforcement, channel-section steel, R plates and attached vibrator;Scaffold system is main to be made up of montant, cross bar, Crossing brace, adjustable bolt, flitch, adjustable jacking;Built-in fitting includes tapping pipe, pre-buried bellows and PVC sleeve pipes.The utility model has the advantages that environment-friendly, easy construction, cheap.

Description

Bridge pier integral formwork support one-shot forming structure
Technical field
The utility model is related to a kind of bridge pier integral formwork support one-shot forming structure.
Background technology
At present, domestic overpass two-columned pier pier stud construction generally uses H type twin columns, and mostly curve variable cross-section loudspeaker Mouth bridge-type, and binder span is larger, pier stud binder is relatively conventional using prestressing force form, the queen post highly more than 10 meters The construction of H types pier stud is more using segmentation casting method, and secondary formwork is difficult and leaves substantially segmentation and connects stubble, if primary concreting outward appearance into Type effect is undesirable;And in concreting, leakiness of disposably vibrating, with binder connecting portion steel at bridge pier variable cross-section Muscle is closeer, and bell mouth shape anchor notch and binder prestress pipe gather with reinforcing bar, such as primary concreting, below variable cross-section horn mouth Vertical section is difficult vibration compacting.
In summary, existing two-columned pier low construction efficiency is not high, and construction quality is difficult to ensure that, is existed substantial amounts of Open defect.In consideration of it, need badly at present a kind of efficiency of construction of utility model is high, quality is secure bridge pier integral formwork support once into Type structure.
Utility model content
The purpose of this utility model be to provide a kind of efficiency of construction is high, quality is secure bridge pier integral formwork support once into Type structure, makes every effort to bridge pier one piece and pours shaping, optimized construction procedure improves construction efficiency, lifts engineering construction quality.
The purpose of this utility model is achieved through the following technical solutions:Bridge pier integral formwork support one-shot forming structure, it is main To be made up of operating platform, set shaped steel formwork, scaffold system and built-in fitting;Operating platform is main by platform springboard, lead to up and down Road and workbench composition;Set shaped steel formwork is made up of standard paragraphs template and horn mouth template, standard paragraphs template and loudspeaker mouth mold Plate composition is constituted by panel, flange, cross rib, perpendicular rib, draw-bar seat, arc reinforcement, channel-section steel, R plates and attached vibrator;Pin Hand cradle system is main to be made up of montant, cross bar, Crossing brace, adjustable bolt, flitch, adjustable jacking;Built-in fitting includes sluicing Pipe, pre-buried bellows and PVC sleeve pipes.
The beneficial effects of the utility model are:
(1) it is disposable by the colligation of bridge pier reinforcing bar and model sheetinstallat in place, and primary concreting concrete can reduce process ring Section, reduces labor intensity, accelerating construction progress.
(2) be segmented pouring construction compared with, can be prevented effectively from joint part concrete leakiness, seam substantially, segmentation concrete color The difference phenomenon such as larger, it is ensured that Surface Quality of Concrete meets design requirement.
(3) one-time-concreting technique is used, secondary formwork difficulty can be reduced, it is to avoid the secondary reinforcement installation of bridge pier binder, template Install and pollution of the concreting to bottom finished product.
(4) accurately it is connected by being accurately positioned prestressing force corrugated conduit, anchor notch being reserved with template, post-stressed muscle Laying to increase local pressure at the span of binder, curved section horn mouth moulding uneven (pier stud eccentric compression), apply pre- Stress enhances the resistance of bridge pier.
Brief description of the drawings
Fig. 1 is a kind of bridge pier integral formwork support one-shot forming agent structure schematic diagram of the utility model;
Fig. 2 is standard paragraphs template front view;
Fig. 3 is standard paragraphs template upward view;
Fig. 4 is standard paragraphs template top view;
Fig. 5 is loudspeaker mouth template front view;
Fig. 6 is loudspeaker mouth template side view;
Fig. 7 is loudspeaker mouth template upward view;
Fig. 8 is loudspeaker mouth template top view;
Fig. 9 is the utility model construction flow chart.
Description of reference numerals:1- panels, 2- platform springboards, 3- lower channels, 4- workbenches, 5- flanges, 6- cross ribs, 7- Perpendicular rib, 8- tapping pipes, the pre-buried bellowss of 9-, 10-PVC sleeve pipes, 11- montants, 12- cross bars, 13- Crossing braces, 14- can adjust spiral shell Bolt, 15- flitches, 16- can adjust jacking, and 17- is to pull bar, 18- draw-bar seats, 19- arc reinforcements, 20- channel-section steels, 21-R plates, 22- attached vibrators.
Embodiment
The utility model is described further with reference to embodiment.The explanation of following embodiments is only intended to help and managed Solve the utility model.It should be pointed out that for those skilled in the art, not departing from the utility model principle On the premise of, some improvement and modification can also be carried out to the utility model, these are improved and modification also falls into the utility model In scope of the claims.
Reinforcing bar colligation, welding technique requirement in present embodiment, large-scale steel form concatenation construction technique, binder post stretching are pre- Stress tension technology etc. is repeated no more, and emphasis illustrates what the bridge pier integral formwork support one-shot forming structure that the utility model is related to was installed Embodiment.
Fig. 1 is a kind of bridge pier integral formwork support one-shot forming agent structure schematic diagram of the utility model;Fig. 2 to Fig. 4 is standard Section template schematic diagram;Fig. 5 to Fig. 8 is loudspeaker mouth template schematic diagram;
Bridge pier integral formwork support one-shot forming structure shown in reference picture 1-8, by operating platform, set shaped steel formwork, scaffold System, the composition such as built-in fitting.
Operating platform is by platform springboard 2, lower channel 3, the grade of workbench 4 composition.
Set shaped steel formwork is made up of standard paragraphs template and horn mouth template, by panel 1, flange 5, cross rib 6, perpendicular rib 7, drawing Pole socket 18, arc reinforcement 19, channel-section steel 20, R plates 21 are constituted, attached vibrator 22.
Scaffold system is by montant 11, cross bar 12, Crossing brace 13, adjustable bolt 14, flitch 15, adjustable jacking 16 Deng composition.
Built-in fitting includes tapping pipe 8, pre-buried bellows 9, PVC sleeve pipes 10 etc..
As shown in figure 9, bridge pier integral formwork support one-shot forming structure construction step is as follows:
1) cushion cap face is handled:According to the pier stud sideline of surveying and locating, using manually to Construction Joint face scope progress dabbing Until exposing coarse aggregate, while clearing up the cement mortar on pier stud embedded bar top layer, and rinsed well with high pressure clear water.
2) pier stud construction cripple is set up:Pier shaft surrounding is set up double using Φ 48mm × 3.0mm design of coupler scaffold Arrange scaffold.Double-pole scaffold is set up around pier stud surrounding closure, and vertically and horizontally spacing is 90 × 90cm, cross bar step pitch 120cm.Pin Hand cradle basis fall within cushion cap and firm ground on, scaffold its four sides by code requirement set Crossing brace, scaffold Set up according to design of coupler scaffold regulation enforcement, surrounding and horizontal direction are respectively provided with safety guard net, and set up lower platform Above and below workmen.
3) reinforcing bar system is pacified:The reinforcing bar of different construction parts is stored classifiedly in reinforcement yard, and is numbered, pier stud master Muscle, stirrup and binder matrix tablet make to be started to install after shaping.Then first colligation pier stud stirrup lifts to binder bottom position Matrix tablet and pier stud cage bar are welded to form entirety by binder framework of steel reinforcement piece, welder's welding, treat matrix tablet all after the completion of welding Colligation residue stirrup, construction muscle and encryption reinforcing bar, and prestressing force corrugated conduit is worn, prestressing force bellows is in advance using coordinate Positioning, welding well word hoop or fixed using U-shaped card.
4) model sheetinstallat:Using set shaped steel formwork, formed by processing customization in factory, especially horn mouth curved section line style stream Freely, graceful, control is accurate, and prestressed anchor notch position is stayed in advance to be set, and wherein horn mouth should carry out pre- with binder linkage section template It is assembled, it is ensured that matched moulds zero deflection, internal corner part connection are accurate in work progress.Bridge abutment moulding plate it is main by regulating block (10cm, 30cm, 50cm, 100cm), standard knot, horn mouth variable cross-section curved section template, binder bed die, side form composition.Have after assembling Enough rigidity, strength and stability.Template polishing, derusting, brushing releasing agent;First install bottom regulation steel form (30cm or 50cm), further according to pier stud height selection standard section and regulating block integral assembling, and highly to divide by single pier stud four sides to be assembled into whole Body big-size formwork is lifted, and is reinforced finally by corner Screw arbor with nut at both-ends.Fill variable cross-section section loudspeaker mouth template;Set up bowl button Formula scaffold, installs variable cross-section horn mouth and binder connecting portion template, it is fixed with bottom vertical section template, then installs and be Beam bottom mother plate, is attached with bridge pier horn mouth, reinforces, while adjusting jacking, installs horn mouth side template.Prestressed anchor groove position Loudspeaker mouth template is put finally to install.
5) concreting:Mould, one-time continuous cast are entered using automobile pump concrete.Pier shaft concrete uses laminated pouring, Every layer of thickness control is in 30~50cm.Pier top reinforced mesh mesh 10cm × 10cm, in construction to automotive pump conveying tube end Spreading vertical tube, a diameter of 80mm of hard tube, material is metal iron pipe, and length is 3m, can be according to live actual height spreading or dismounting.
6) form removable, health:Draw is produced to prevent in concrete that moisture evaporation is too fast, and ensures hydrated cementitious mistake Journey is smoothed out, after pier stud concreting is finished, and watering maintenance was proceeded by every 2 hours or so.When concrete strength reaches Pier Formwork is removed to 2.5MPa, binder bed die should can bear it from gravity and other possible superposition lotuses in concrete strength It can be removed during load.After the completion of form removable, pier stud, binder are integrally wrapped up using plastic sheeting immediately, fencing lawn is carried out, Curing period, is not less than 7 days.
7) binder prestressed stretch-draw mud jacking:When concrete strength reaches 90% and age is not less than 7 days, prestressing force is carried out Steel stranded wire penetrating adapter, and tensioning.Prestress wire lashing uses high speed strand pulling machine.Before tensioning clear up anchor cushion block on cement mortar and Iron rust, and itself and ripple pore central perpendicularity are checked, if any deviation, with wedge-shaped steel cushion block.One end uses the big jack of 100t, The other end uses the per share tensioning 5t respectively of small jack, then big jack one-end tension.

Claims (1)

1. a kind of bridge pier integral formwork support one-shot forming structure, it is characterised in that:Mainly by operating platform, set shaped steel formwork, pin hand Frame system and built-in fitting composition;Operating platform is mainly made up of platform springboard (2), lower channel (3) and workbench (4);It is fixed Steel form is made up of standard paragraphs template and horn mouth template, and standard paragraphs template and horn mouth template composition are by panel (1), method Blue (5), cross rib (6), perpendicular rib (7), draw-bar seat (18), arc reinforcement (19), channel-section steel (20), R plates (21) and adhesion type vibrate Device (22) is constituted;Scaffold system is main by montant (11), cross bar (12), Crossing brace (13), adjustable bolt (14), flitch (15) it, can adjust jacking (16) composition;Built-in fitting includes tapping pipe (8), pre-buried bellows (9) and PVC sleeve pipes (10).
CN201621452913.8U 2016-12-28 2016-12-28 Bridge pier integral formwork support one-shot forming structure Active CN206553938U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621452913.8U CN206553938U (en) 2016-12-28 2016-12-28 Bridge pier integral formwork support one-shot forming structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621452913.8U CN206553938U (en) 2016-12-28 2016-12-28 Bridge pier integral formwork support one-shot forming structure

Publications (1)

Publication Number Publication Date
CN206553938U true CN206553938U (en) 2017-10-13

Family

ID=60359536

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621452913.8U Active CN206553938U (en) 2016-12-28 2016-12-28 Bridge pier integral formwork support one-shot forming structure

Country Status (1)

Country Link
CN (1) CN206553938U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279334A (en) * 2021-05-19 2021-08-20 安徽省路港工程有限责任公司 Construction method of one-step pouring molding system of double-column type vase pier steel template

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113279334A (en) * 2021-05-19 2021-08-20 安徽省路港工程有限责任公司 Construction method of one-step pouring molding system of double-column type vase pier steel template
CN113279334B (en) * 2021-05-19 2022-09-27 安徽省路港工程有限责任公司 Construction method of one-step pouring molding system of double-column type vase pier steel template

Similar Documents

Publication Publication Date Title
CN106677069B (en) A kind of construction method of bridge pier integral formwork support one-shot forming structure
CN207143755U (en) A kind of adjustable bracket for No. 0 block of bridge pier
CN202359506U (en) Double hoop supporting system for pier column capping beam
CN107119574A (en) A kind of Cantilever Construction Method of arch rib bridge girder
CN206267422U (en) A kind of assembly concrete superposed column
CN102251481B (en) Railway pier layered construction method and construction device
CN105908864A (en) Interface crack preventing structure for filling brickwork and framework shear wall and construction method
CN107419802A (en) A kind of Precast Concrete Frame and construction method
CN110512524A (en) A kind of bridge pier column safe construction method
CN206174120U (en) Prefabricated constructional column and structure thereof
CN211007659U (en) Device for controlling forming of embedded steel plate in concrete column on column surface
CN108678218A (en) Assembly concrete shear wall and its method of construction based on multipurpose thin-wall steel tube
CN106346596A (en) Precast stair template matching system
CN105128131A (en) Method for manufacturing prestressed hollow slab beam through polystyrene foam
CN105804395A (en) Staircase one-step continuous casting forming construction method based on integral shaped formwork
CN206917087U (en) A kind of prefabricated assembling type reinforced concrete framework open tubular column and its making mould
CN113389379A (en) Construction method of post-cast strip floor with independent support
CN102409848A (en) Construction molding methods for light-weight ribbed floorslab and light-weight ribbed floor
CN206553938U (en) Bridge pier integral formwork support one-shot forming structure
CN108316150A (en) The construction system and construction method of Cable stayed Bridge Main Tower and steel anchor beam
CN107217790A (en) A kind of prefabricated assembling type reinforced concrete framework open tubular column and its construction method
CN114277672B (en) Large-span prestressed concrete bent cap structure and construction method thereof
CN110080299A (en) A kind of shallow embedding mountain tunnel open-cut engineering method
CN206448272U (en) Roadbed side slope arched framework one-time-shaped mould
CN213952981U (en) Steel pipe supporting base of stair platform

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant