CN111236419A - A new type of reinforced concrete structure beam-column joint and construction method - Google Patents

A new type of reinforced concrete structure beam-column joint and construction method Download PDF

Info

Publication number
CN111236419A
CN111236419A CN202010106685.3A CN202010106685A CN111236419A CN 111236419 A CN111236419 A CN 111236419A CN 202010106685 A CN202010106685 A CN 202010106685A CN 111236419 A CN111236419 A CN 111236419A
Authority
CN
China
Prior art keywords
column
core area
reinforced concrete
frame
equal
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010106685.3A
Other languages
Chinese (zh)
Inventor
陈国灿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Putian University
Original Assignee
Putian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Putian University filed Critical Putian University
Priority to CN202010106685.3A priority Critical patent/CN111236419A/en
Publication of CN111236419A publication Critical patent/CN111236419A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C5/00Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
    • E04C5/01Reinforcing elements of metal, e.g. with non-structural coatings
    • E04C5/06Reinforcing elements of metal, e.g. with non-structural coatings of high bending resistance, i.e. of essentially three-dimensional extent, e.g. lattice girders
    • E04C5/0636Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts
    • E04C5/064Three-dimensional reinforcing mats composed of reinforcing elements laying in two or more parallel planes and connected by separate reinforcing parts the reinforcing elements in each plane being formed by, or forming a, mat of longitunal and transverse bars

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

The invention provides a novel beam-column joint of a reinforced concrete structure, which comprises a beam-column joint core area and a reinforced concrete ring beam, wherein the reinforced concrete ring beam is arranged around the beam-column joint core area. The beam-column joint core area comprises a main reinforcement penetrating through the joint core area in the frame column, and stirrups, reinforcing stirrups, steel plate sleeves, concrete and the like in the core area, wherein the stirrups are bound outside the main reinforcement, and the steel plate sleeves sleeved outside the stirrups are supported on the reinforcement at the bottom of the frame beam penetrating through the core area; a steel plate belt is adopted to replace part of stirrups, the distance between the stirrups is reduced, the construction measures are perfected, and the like, a space with the diameter of about 200mm is vacated in the center of a node core area, so that an operation space is provided for binding and installing the steel bars; meanwhile, the vibrating rod is convenient to insert and pull out, so that the concrete can be vibrated tightly; be in node core region concrete in the closed region of steel sheet cover can pour simultaneously with the lower post, when can easily solving the post concrete strength and be higher than the beam slab, the difficult problem of pouring of core region concrete.

Description

一种新型钢筋混凝土结构梁柱节点及施工方法A new type of reinforced concrete structure beam-column joint and construction method

技术领域technical field

本发明涉及建筑结构工程技术领域,特别是一种新型钢筋混凝土结构梁柱节点及施工方法。The invention relates to the technical field of building structure engineering, in particular to a novel reinforced concrete structure beam-column joint and a construction method.

背景技术Background technique

建筑工程质量事关建筑的安全,与人民群众生命财产的安全、社会的和谐、安定与稳定等息息相关。因此,建设主管部门历来高度重视建筑工程质量管理。近几年随着建筑工程质量的监管力度的不断加大,建筑品质总体水平稳步提升,但是在我国房屋建造过程中,不少建筑质量通病仍缺乏有效的解决方法。The quality of construction projects is related to the safety of buildings, and is closely related to the safety of people's lives and property, social harmony, stability and stability. Therefore, the construction authorities have always attached great importance to the quality management of construction projects. In recent years, with the increasing supervision of construction quality, the overall level of construction quality has steadily improved. However, in the process of housing construction in my country, many common construction quality problems still lack effective solutions.

梁柱节点是钢筋混凝土框架结构的关键部位,是联系结构体系的枢纽,起着承上启下的作用。从受力的角度上考虑,梁柱节点核心区受力情况比较复杂,它既直接承受框架柱端传来的压力、剪力和弯矩,又要承受梁端剪力和弯矩。在地震反复作用时,核心混凝土处于剪压复杂应力状态,往往造成核心区出现交叉的裂缝及柱端压酥、剥落、钢筋压屈外鼓等。特别是角柱、边柱,由于扭转和偏心等因素的影响,受力更为复杂,比内框架柱更容易引起震害。历次震害表明,框架结构部分震害严重的部位多发生在受力最为复杂的梁柱节点,框架结构的破坏绝大部分是由于梁柱节点核心区混凝土强度不足和延性不够所致。因此梁柱节点是混凝土结构质量的薄弱环节,具有可靠质量的梁柱节点是确保结构体系安全服役的基本保证。The beam-column joint is the key part of the reinforced concrete frame structure, and it is the pivot linking the structural system, which plays a linking role. From the point of view of stress, the stress situation in the core area of beam-column joints is more complicated. It not only directly bears the pressure, shear force and bending moment from the column end of the frame, but also bears the shear force and bending moment of the beam end. During repeated earthquakes, the core concrete is in a state of complex shear-compression stress, which often results in crossed cracks in the core area, compression of column ends, spalling, and buckling of steel bars. In particular, corner columns and side columns, due to the influence of torsion and eccentricity, are subjected to more complex forces and are more likely to cause earthquake damage than inner frame columns. The previous earthquake damages show that the most serious parts of the frame structure occur in the beam-column joints with the most complex stress. Therefore, the beam-column joint is the weak link of the quality of the concrete structure, and the beam-column joint with reliable quality is the basic guarantee to ensure the safe service of the structural system.

调查分析表明,钢筋混凝土梁柱接头部位箍筋少放、漏放或不按设计间距要求放置、主筋弯锚不到位等现象特别普遍;节点内部混凝土不密实、空洞等情况也时有发生,这严重影响到结构的质量。The investigation and analysis show that the stirrups in the reinforced concrete beam-column joints are rarely placed, missing or not placed according to the design spacing requirements, and the main reinforcement bending anchors are not in place. seriously affect the quality of the structure.

对于钢筋混凝土结构梁柱节点施工中存在的问题,业界见怪不怪,业内认为,有关规范虽已有详细的规定,但由于梁柱节点区域钢筋众多,特别是中间柱的节点处钢筋密集:①在竖向,框架柱的纵向钢筋穿过节点核心区域;②在水平方向,纵向和横向框架梁的受力钢筋均穿过或锚固于框架柱的纵向钢筋内侧,呈井字形立体交叉;③此外还有绑扎于主筋上的横向箍筋等。For the problems existing in the construction of beam-column joints of reinforced concrete structures, the industry is not surprised. The industry believes that although the relevant specifications have detailed regulations, due to the large number of steel bars in the beam-column joint area, especially at the middle column joints, the steel bars are dense: ① In the vertical direction, the longitudinal steel bars of the frame columns pass through the core area of the node; ② In the horizontal direction, the stressed steel bars of the longitudinal and transverse frame beams pass through or are anchored to the inner side of the longitudinal steel bars of the frame columns, forming a three-dimensional cross in the shape of a zigzag; ③ In addition There are also transverse stirrups tied to the main reinforcement.

对以手工作业为主的操作人员来说,在狭小的空间中进行钢筋绑扎作业,要完成完全符合规范要求的钢筋工程,简直难于上青天。For operators who mainly work by hand, it is difficult to complete the reinforcement work that fully meets the requirements of the specification when performing reinforcement binding operations in a small space.

综上所述,钢筋混凝土结构梁柱节点区内钢筋纵横交错过于集中,是造成钢筋绑扎困难的主要原因,也是振动棒难以插入,混凝土震捣不到位,造成节点区内混凝土密实度不足,梁柱节点的施工质量难以得到保证的主要原因。In summary, the lack of vertical and horizontal cross-section of steel bars in the beam-column joint area of reinforced concrete structures is the main reason for the difficulty in binding steel bars. It is also difficult to insert the vibrating rod and the concrete is not vibrated in place, resulting in insufficient concrete density in the joint area, beams and beams. The main reason why the construction quality of column joints is difficult to be guaranteed.

另外,工程实际中经常遇到框架柱混凝土设计强度比梁板混凝土设计强度高两个等级及以上的情况。对此,《混凝土结构工程施工规范》GB50666和《混凝土结构工程施工质量验收规范》GB50204都有明确的规定,应在交界区域采取分隔措施。In addition, it is often encountered in engineering practice that the design strength of frame column concrete is two grades or more higher than the design strength of beam-slab concrete. In this regard, "Concrete Structure Engineering Construction Specification" GB50666 and "Concrete Structure Engineering Construction Quality Acceptance Specification" GB50204 both clearly stipulate that separation measures should be taken in the junction area.

目前工程上主要采用以下两种方法解决这个问题,第一,提高梁板混凝土强度等级,使梁柱混凝土强度等级差不高于5Mpa。之后经设计单位同意,采用与梁、板混凝土设计强度等级相同的混凝土进行浇筑。采用此方法,势必提高大幅度工程造价。At present, the following two methods are mainly used in the project to solve this problem. First, improve the strength level of beam-slab concrete, so that the difference between beam-column concrete strength level is not higher than 5Mpa. After that, with the approval of the design unit, the concrete with the same design strength grade as the beam and slab concrete is used for pouring. Using this method is bound to increase the project cost by a large margin.

第二,在距柱边500mm处,且不小于1/2框架梁高处,沿45度斜面从梁顶到梁底用钢丝网片将不同强度等级的混凝土隔开,先浇筑框架柱的混凝土。这在理论上是可行的,但实际工程中由于泵送的需要,商品混凝土的塌落度都比较大,一般为180~220mm,因此,实际工程中很难操作。Second, at a distance of 500mm from the edge of the column and not less than 1/2 the height of the frame beam, along the 45-degree slope from the top of the beam to the bottom of the beam, use steel mesh to separate the concrete of different strength grades, and pour the concrete of the frame column first. . This is feasible in theory, but due to the need of pumping in practical projects, the slump of commercial concrete is relatively large, generally 180-220mm, so it is difficult to operate in practical projects.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题,在于提供一种在核心区内钢筋布置相对分散,便于梁柱节点核心区内钢筋绑扎安装、振动棒插入以及混凝土震捣,施工质量可控等优点的新型钢筋混凝土结构梁柱节点。The technical problem to be solved by the present invention is to provide a new type of reinforced concrete with the advantages of relatively scattered reinforcement in the core area, convenient installation of reinforcement in the core area of beam-column joints, insertion of vibrating rods, vibration of concrete, and controllable construction quality. Structural beam-column connections.

本发明是这样实现的:一种新型钢筋混凝土结构梁柱节点,包括The present invention is realized in this way: a novel reinforced concrete structure beam-column joint, comprising:

框架梁和框架柱交接的梁柱节点核心区;所述梁柱节点核心区包括框架柱中穿过梁柱节点核心区的主筋、核心区内的箍筋、加强箍筋、焊接在一起的钢板套、混凝土;所述的箍筋绑扎在主筋外,钢板套套在箍筋外,钢板套还支于横穿核心区的框架梁底部的主筋之上;The beam-column node core area where the frame beam and the frame column are connected; the beam-column node core area includes the main reinforcement passing through the beam-column node core area in the frame column, the stirrups in the core area, the reinforcing stirrups, and the welded steel plates Cover, concrete; the stirrup is bound outside the main reinforcement, the steel plate sleeve is sleeved outside the stirrup, and the steel plate sleeve is also supported on the main reinforcement at the bottom of the frame beam that crosses the core area;

钢筋混凝土环梁,所述钢筋混凝土环梁环绕在所述梁柱节点核心区周围。A reinforced concrete ring beam, the reinforced concrete ring beam surrounds the core area of the beam-column joint.

进一步地,所述的钢筋混凝土环梁的混凝土强度与梁板相同,环梁的高度≥框架梁的高度+50mm;所述钢筋混凝土环梁的宽度≥框架梁的宽度,且应能满足框架梁主筋的锚固要求,框架梁主筋在环梁内的锚固按GB50010的规定执行。Further, the concrete strength of the described reinforced concrete ring beam is the same as the beam slab, and the height of the ring beam≥the height+50mm of the frame beam; the width of the reinforced concrete ring beam≥the width of the frame beam, and should be able to satisfy the frame beam The anchorage requirements of the main reinforcement, the anchorage of the main reinforcement of the frame beam in the ring beam shall be carried out according to the provisions of GB50010.

进一步地,钢筋混凝土环梁的主筋直径≥B16,间距≤200mm;当环梁腹板高度≥450mm时,在环梁两侧面沿高度设置纵向构造钢筋(腰筋),直径≥B14,每侧纵向构造钢筋的间距≤200mm,腰筋之间的拉筋间距≤200mm;主筋和腰筋均采用焊接接头。配置箍筋直径≥A8,间距≤100mm。Further, the diameter of the main bars of the reinforced concrete ring beam is greater than or equal to B16, and the spacing is less than or equal to 200mm; when the height of the web of the ring beam is greater than or equal to 450mm, longitudinal structural steel bars (waist bars) are arranged on both sides of the ring beam along the height, the diameter is greater than or equal to B14, and the longitudinal direction of each side is The spacing of structural steel bars is ≤200mm, and the spacing between tie bars between waist bars is less than or equal to 200mm; welded joints are used for main bars and waist bars. Configure stirrup diameter ≥ A8, spacing ≤ 100mm.

进一步地,在梁柱节点核心区内采取钢板套替代部分箍筋、适当缩小箍筋间距、优化节点核心区构造方案等措施,在箍筋肢距满足《建筑抗震设计规范》GB50011要求的前提下,箍筋避开核心区内中间部位安装,确保钢筋混凝土梁柱节点核心区截面内中间部位大约直径为200mm范围内没有钢筋、箍筋穿过,振动棒可以无障碍插入与拔出。Further, in the core area of beam-column joints, measures such as replacing some stirrups with steel plate sleeves, appropriately reducing the spacing of stirrups, and optimizing the structural plan of the core area of the joints are adopted. , The stirrups are installed away from the middle part of the core area to ensure that no steel bars and stirrups pass through the middle part of the cross section of the core area of the reinforced concrete beam-column joint with a diameter of about 200mm, and the vibrating rod can be inserted and pulled out without obstacles.

进一步地,所述钢板套由四块钢板焊接而成的,钢板套在全高范围内采用全焊透焊缝焊接;所述钢板套的高度=穿过核心区的框架梁底钢筋与穿过核心区的梁面钢筋之间的净距-10mm。Further, the steel plate sleeve is formed by welding four steel plates, and the steel plate sleeve is welded with full penetration welds within the full height range; The clear distance between the beam surface reinforcement in the area is -10mm.

进一步地,双向框架梁的角筋和位于第二排的梁侧钢筋横穿核心区,与钢筋混凝土环梁形成一个整体,增强核心区抵抗破坏的能力;对于边框节点,框架梁中位于第1~2排的梁侧钢筋穿过钢筋混凝土梁柱节点核心区后,锚固于另一侧的环梁内;而框架梁中位于第1~2排的非梁侧钢筋和第三排及以上的钢筋完全穿过同侧的钢筋混凝土环梁后弯折锚固,为振动棒的影响触及到每个角落提供便利。Further, the corner bars of the two-way frame beam and the beam side bars located in the second row cross the core area and form a whole with the reinforced concrete ring beam to enhance the ability of the core area to resist damage; After passing through the core area of the reinforced concrete beam-column joint, the beam-side reinforcement bars in the ~2 rows are anchored in the ring beam on the other side; while the non-beam-side reinforcement bars in the 1st-2nd row and the third row and above in the frame beams The steel bars are completely pierced through the reinforced concrete ring beam on the same side and then bent and anchored, which facilitates the impact of the vibrating rod to reach every corner.

进一步地,当柱截面改变时,下柱的主筋伸至钢板套顶部后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d;上柱的主筋伸至钢板套底部后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d,其中d为主筋的直径,laE为抗震时受拉钢筋的锚固长度。Further, when the cross section of the column is changed, the main reinforcement of the lower column extends to the top of the steel plate sleeve and then is bent and anchored in the ring beam on the same side. After extending to the bottom of the steel plate sleeve, it is bent and anchored in the ring beam on the same side. The total anchorage length is ≥1.2laE, and the anchorage length of the horizontal section is ≥12d, where d is the diameter of the main reinforcement, and laE is the anchorage length of the tensile reinforcement during earthquake resistance. .

进一步地,在顶层节点,下柱的主筋伸至钢板套顶部后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d。Further, at the top node, the main reinforcement of the lower column extends to the top of the steel plate sleeve and then is bent and anchored in the ring beam on the same side.

进一步地,所述梁柱节点核心区在与框架梁面及梁底对应的位置各焊接有直径≥B12的加强箍筋。Further, reinforcing stirrups with a diameter ≥ B12 are welded at positions corresponding to the beam surface and the bottom of the beam in the core area of the beam-column node.

进一步地,在框架柱内采取增大箍筋直径、适当缩小箍筋间距等措施,在箍筋肢距满足《建筑抗震设计规范》GB50011要求的前提下,箍筋避开核心区内中间约直径为200mm的部位安装,便于振动棒发挥作用。Further, measures such as increasing the diameter of the stirrups and appropriately reducing the spacing of the stirrups are taken in the frame column. On the premise that the distance between the stirrups meets the requirements of GB50011 of the Code for Seismic Design of Buildings, the stirrups should avoid the middle diameter of the core area. It is installed for the 200mm part, which is convenient for the vibrator to function.

若框架柱仍无法满足受剪承载力要求,框架柱内也可采取由钢板带焊接而成的钢板套替代部分箍筋。框架柱内的钢板套也是由四块钢板焊接而成的,框架柱内的钢板套在底层柱下端Hn/3范围内采用全焊透焊缝,在底层柱的上端Sc范围内采用全焊透焊缝,在中间部位可采用部分焊透焊缝;底层柱的钢板套的高度=二层框架梁底至基础顶面的距离-10mm。If the frame column still cannot meet the shear bearing capacity requirements, the steel plate sleeve welded by the steel strip can also be used to replace part of the stirrups in the frame column. The steel plate sleeve in the frame column is also welded by four steel plates. The steel plate sleeve in the frame column adopts full penetration weld within the range of H n /3 at the lower end of the bottom column, and adopts full penetration welding in the range of Sc at the upper end of the bottom column. For penetration welds, partial penetration welds can be used in the middle; the height of the steel plate sleeve of the bottom column = the distance from the bottom of the frame beam on the second floor to the top surface of the foundation -10mm.

框架柱内的钢板套在其它层的两端Sc范围内采用全焊透焊缝,而在中间部位可采用部分焊透焊缝,其中Sc≥hc,Sc≥Hn/6,且Sc≥500mm,hc为框架柱的截面长边尺寸,Hn为框架柱的净高;框架柱内的钢板套高度=上层框架梁底至下一层楼面的距离-10mm。The steel plate sleeves in the frame column shall adopt full penetration welds within the range of Sc at both ends of the other layers, and partial penetration welds can be used in the middle part, where Sc≥hc , Sc≥Hn /6, and Sc≥ 500mm, h c is the length of the cross section of the frame column, H n is the net height of the frame column; the height of the steel plate sleeve in the frame column = the distance from the bottom of the upper frame beam to the next floor -10mm.

本发明具有如下优点:The present invention has the following advantages:

(1)在梁柱节点核心区周边设置钢筋混凝土环梁,框架梁中的角筋和位于第二排的梁侧钢筋穿过核心区,与钢筋混凝土环梁形成一个整体,增强核心区抵抗破坏的能力;而框架梁中位于第1~2排的非梁侧钢筋和第三排及以上的钢筋完全穿过同侧的钢筋混凝土环梁后弯折锚固;在顶层节点将框架柱的主筋弯折至同侧的环梁中锚固,从而避免节点核心区内钢筋纵横交错的状况,为钢筋绑扎与安装提供必要的操作空间,为提高梁柱节点核心区内钢筋的绑扎质量提供了必要的保证。(1) Set up reinforced concrete ring beams around the core area of the beam-column joint. The corner bars in the frame beams and the beam side bars in the second row pass through the core area and form a whole with the reinforced concrete ring beams to enhance the resistance of the core area to damage. In the frame beam, the non-beam side steel bars located in the 1st to 2nd rows and the steel bars on the third row and above completely pass through the reinforced concrete ring beam on the same side and then bend and anchor; at the top node, the main bars of the frame column are bent. It is folded to the ring beam on the same side and anchored, so as to avoid the crisscrossing of steel bars in the core area of the node, provide necessary operating space for the binding and installation of steel bars, and provide the necessary guarantee for improving the binding quality of steel bars in the core area of beam-column joints .

(2)在梁柱节点核心区内采取由钢板带焊接而成的钢板套替代部分箍筋、适当缩小箍筋间距、优化节点核心区构造方案等措施,进一步改善节点核心区内钢筋密布的状况;在箍筋肢距满足《建筑抗震设计规范》GB50011要求的前提下,箍筋避开核心区内中间部位安装,确保钢筋混凝土梁柱节点核心区截面内中间部位大约直径为200mm范围内没有箍筋和主筋等穿过,便于振动棒的插入与拔出,确保振动棒的作用效应传递至核心区内每一处,使混凝土得到有效的震捣,及时排除混凝土中的气泡,可有效改善混凝土的密实度,提高混凝土的强度。(2) In the core area of beam-column joints, measures such as replacing part of the stirrups with steel plate sleeves welded by steel strips, appropriately reducing the spacing of stirrups, and optimizing the structural plan of the core area of the joint are further improved to further improve the dense distribution of steel bars in the core area of the joint. ; On the premise that the distance between the stirrups meets the requirements of GB50011 of "Code for Seismic Design of Buildings", the stirrups should be installed away from the middle part of the core area to ensure that the middle part of the section of the core area of the reinforced concrete beam-column joint is about 200mm in diameter. The rib and main rib pass through, which is convenient for the insertion and extraction of the vibrating rod, ensuring that the effect of the vibrating rod is transmitted to every part of the core area, so that the concrete can be effectively vibrated, and the air bubbles in the concrete can be eliminated in time, which can effectively improve the concrete. density and improve the strength of concrete.

(3)在便于施工的前提下,适当减小节点核心区内箍筋的间距,加上钢板套约束混凝土的效应,可大大增强核心区的变形能力,提高结构的抗震性能;核心区内的混凝土四周被钢板套约束住,可以避免高强混凝土在火灾紧急情况下高温爆裂的风险。(3) Under the premise of facilitating construction, appropriately reducing the spacing of stirrups in the core area of the node, coupled with the effect of confining the concrete by the steel plate sleeve, can greatly enhance the deformation capacity of the core area and improve the seismic performance of the structure; The concrete is restrained by steel plate sleeves around it, which can avoid the risk of high-strength concrete bursting at high temperature in case of fire emergency.

(4)所述的新型钢筋混凝土结构梁柱节点中,套在箍筋外的钢板套把梁柱节点核心区围住形成一个相对封闭的区域,可以把不同区域的混凝土分隔开来,即将核心区的混凝土和框架梁的混凝土隔开,因此采用新型的钢筋混凝土结构梁柱节点,可以轻而易举地解决框架节点核心区的混凝土强度高于梁板混凝土强度时的施工难题。(4) In the beam-column joint of the new reinforced concrete structure, the steel plate sleeves outside the stirrups enclose the core area of the beam-column joint to form a relatively closed area, which can separate the concrete in different areas. The concrete in the core area is separated from the concrete of the frame beam, so the new type of reinforced concrete beam-column joint can easily solve the construction problem when the strength of the concrete in the core area of the frame joint is higher than that of the beam-slab concrete.

(5)新型的钢筋混凝土结构梁柱节点的实施可为“强柱弱梁,更强节点”的设计理念得以实现提供必要的保障。(5) The implementation of the new reinforced concrete structure beam-column joint can provide the necessary guarantee for the realization of the design concept of "strong column, weak beam, stronger joint".

附图说明Description of drawings

下面参照附图结合实施例对本发明作进一步的说明。The present invention will be further described below with reference to the accompanying drawings and embodiments.

图1为本发明所述的新型钢筋混凝土框架结构示意图。FIG. 1 is a schematic diagram of the novel reinforced concrete frame structure according to the present invention.

其中,其中Sc≥hc,Sc≥Hn/6,且Sc≥500mm,hc为框架柱的截面长边尺寸,Hn为框架柱的净高;S为梁端箍筋加密区长度,抗震等级为一级时,梁端箍筋加密区长度S≥2.0hb(hb为梁高)且不小于500mm;抗震等级为二~四级时,梁端箍筋加密区长度S≥1.5hb(hb为框架梁高)且不小于500mm,H1,H2,Hw分别为第2层、第3层及屋面层的结构标高。Among them, Sc≥hc , Sc≥Hn /6, and Sc≥500mm , hc is the length of the cross-section of the frame column, Hn is the clear height of the frame column; S is the length of the beam end stirrup densification area, When the seismic grade is Grade 1, the length of the beam end stirrup densification area S ≥ 2.0hb (hb is the beam height) and not less than 500mm; when the seismic grade is 2 to 4, the beam end stirrup densified area length S ≥ 1.5hb ( hb is the frame beam height) and not less than 500mm, H1, H2, Hw are the structural elevations of the 2nd, 3rd and roof layers respectively.

图2为本发明所述的新型钢筋混凝土结构梁柱节点的平面图。FIG. 2 is a plan view of the beam-column joint of the novel reinforced concrete structure according to the present invention.

图3为本发明所述的新型钢筋混凝土结构梁柱节点的立面图。FIG. 3 is an elevation view of the beam-column joint of the novel reinforced concrete structure according to the present invention.

图4为框架梁主筋与钢筋混凝土核心区主筋在平面中的相对位置关系示意图。Figure 4 is a schematic diagram of the relative positional relationship between the main reinforcement of the frame beam and the main reinforcement of the reinforced concrete core area in a plane.

图5为图4中A-A截面示意图,也是钢板套与框架梁主筋在竖向相对位置关系示意图。FIG. 5 is a schematic diagram of the section A-A in FIG. 4 , and is also a schematic diagram of the vertical relative positional relationship between the steel plate sleeve and the main reinforcement of the frame beam.

图6为图5中B-B截面配筋示意图。FIG. 6 is a schematic diagram of reinforcement in section B-B in FIG. 5 .

其中,b为框架梁的宽度,hb为框架梁高。Among them, b is the width of the frame beam, and hb is the height of the frame beam.

图7为钢筋混凝土核心区截面配筋示意图1。Figure 7 is a schematic diagram 1 of the cross-section reinforcement in the reinforced concrete core area.

图8为钢筋混凝土核心区截面配筋示意图2。FIG. 8 is a schematic diagram 2 of the cross-section reinforcement in the reinforced concrete core area.

图9为钢筋混凝土核心区截面配筋示意图3。FIG. 9 is a schematic diagram 3 of the cross-section reinforcement in the reinforced concrete core area.

图10为图9中C-C截面中核心区的配筋示意图。FIG. 10 is a schematic diagram of the reinforcement arrangement in the core area in the C-C section in FIG. 9 .

图11为由钢板带焊接而成的钢板套32的构造示意图。FIG. 11 is a schematic structural diagram of a steel plate sleeve 32 formed by welding steel strips.

其中,焊缝标示中箭尾的索引号见国家标准图集15G909-1的附录A(余同)。Among them, the index number of the nock in the welding seam marking is shown in Appendix A of the National Standard Atlas 15G909-1 (the same as the rest).

图12为钢筋混凝土框架柱截面改变时框架柱主筋在节点核心区内的锚固构造示意图。Figure 12 is a schematic diagram of the anchorage structure of the main bars of the frame column in the core area of the node when the cross-section of the reinforced concrete frame column is changed.

其中d为钢筋的直径。where d is the diameter of the rebar.

图13为钢筋混凝土框架柱主筋在顶层边节点的锚固示意图。Figure 13 is a schematic diagram of the anchorage of the main bars of the reinforced concrete frame column at the top edge nodes.

其中d为钢筋的直径。where d is the diameter of the rebar.

图14为本发明所述的钢筋混凝土环梁的配筋示意图。FIG. 14 is a schematic diagram of the reinforcement configuration of the reinforced concrete ring beam according to the present invention.

其中bc为框架柱的宽度,hc为框架柱的截面高度。Where bc is the width of the frame column, hc is the section height of the frame column.

图15为本发明所述的钢筋混凝土环梁的主筋大样图。Fig. 15 is an enlarged view of the main reinforcement of the reinforced concrete ring beam according to the present invention.

图16为图14中位于节点核心区左侧的钢筋混凝土环梁的截面图。FIG. 16 is a cross-sectional view of the reinforced concrete ring beam located on the left side of the core region of the node in FIG. 14 .

图17为中间层角节点的钢筋混凝土环梁的配筋平面图。Fig. 17 is a plan view of reinforcement reinforcement of a reinforced concrete ring beam at a corner node of an intermediate floor.

其中bc为框架柱的宽度,hc为框架柱的截面高度。Where bc is the width of the frame column, hc is the section height of the frame column.

图18为中间层边节点的钢筋混凝土环梁的配筋平面图。Fig. 18 is a plan view of reinforcement reinforcement of a reinforced concrete ring beam at an edge node of an intermediate layer.

其中bc为框架柱的宽度,hc为框架柱的截面高度。Where bc is the width of the frame column, hc is the section height of the frame column.

图19为中间层钢筋混凝土框架梁主筋在边节点核心区的锚固示意图。Figure 19 is a schematic diagram of the anchorage of the main reinforcement of the intermediate layer reinforced concrete frame beam in the core area of the edge node.

图20为钢筋混凝土框架梁主筋在顶层边节点核心区的锚固示意图。Figure 20 is a schematic diagram of the anchorage of the main reinforcement of the reinforced concrete frame beam in the core area of the top edge node.

图21和22分别为钢筋混凝土框架梁截面高度不同时,框架梁主筋在节点核心区内的锚固构造示意图。Figures 21 and 22 are schematic diagrams of the anchoring structure of the main reinforcement of the frame beam in the core area of the node when the section height of the reinforced concrete frame beam is different.

其中HE为位于核心区两侧的框架梁底部主筋之间的高差,Bhu为环梁宽度。where HE is the height difference between the bottom main bars of the frame beams on both sides of the core area, and Bhu is the width of the ring beam.

图23为框架柱构造示意图,其中Sc为柱端加密区长度;Figure 23 is a schematic diagram of the frame column structure, wherein Sc is the length of the column end encryption zone;

图24~26为钢筋混凝土框架柱截面配筋示意图,其中bc和hc分别为框架柱的短边和长边尺寸。Figures 24 to 26 are schematic diagrams of cross-section reinforcement of reinforced concrete frame columns, where bc and hc are the dimensions of the short side and the long side of the frame column, respectively.

图27为钢板套42采用全焊透焊缝时的构造示意图。FIG. 27 is a schematic diagram of the structure of the steel plate sleeve 42 when a full penetration weld is used.

图28为钢板套42采用部分焊透焊缝时的构造示意图。FIG. 28 is a schematic diagram of the structure of the steel plate sleeve 42 when a partial penetration weld is used.

其中,焊缝标示中箭尾的索引号见国家标准图集15G909-1的附录A(余同)。Among them, the index number of the nock in the welding seam marking is shown in Appendix A of the National Standard Atlas 15G909-1 (the same as the rest).

附图标记说明:Description of reference numbers:

钢筋混凝土环梁1,主筋11,12,13,箍筋14,梁侧腰筋15,拉筋16,见图16;Reinforced concrete ring beam 1, main bars 11, 12, 13, stirrups 14, beam side waist bars 15, tie bars 16, see Figure 16;

框架梁2,底部角筋21,梁底第二排梁侧主筋22,底部其它主筋23,箍筋24,梁面角筋25,梁面第二排梁侧主筋26,梁面其它主筋27;腰筋28,拉筋29,见图4~6;Frame beam 2, bottom corner bars 21, the second row of beam side main bars at the bottom of the beam 22, other bottom main bars 23, stirrups 24, beam face corner bars 25, beam face second row beam side main bars 26, beam surface other main bars 27; Waist tendon 28, Lajin 29, see Figures 4-6;

梁柱节点核心区3,主筋31,下柱的主筋311,上柱的主筋312,核心区内的钢板套32,箍筋33,加强箍筋331,332,见图5、图8~12;The beam-column joint core area 3, the main reinforcement 31, the main reinforcement 311 of the lower column, the main reinforcement 312 of the upper column, the steel plate sleeve 32 in the core area, the stirrups 33, and the reinforcement stirrups 331, 332, see Figure 5, Figure 8-12;

框架柱4,主筋311,箍筋41,柱身钢板套42,见图23~28;;Frame column 4, main reinforcement 311, stirrup 41, column steel plate sleeve 42, see Figures 23 to 28;

基础5。Foundation 5.

具体实施方式Detailed ways

本发明的发明构思如下:The inventive concept of the present invention is as follows:

(1)在梁柱节点核心区周边设置钢筋混凝土环梁,把伸入核心区对振动棒的工作影响不大的框架梁侧主筋穿过核心区,与钢筋混凝土环梁形成一个整体,增强核心区抵抗破坏的能力;而把穿过或锚固于核心区内将妨碍振动棒插拔的梁柱钢筋锚固于同侧的钢筋混凝土环梁内,从而避免节点核心区内钢筋纵横交错的状况,为钢筋绑扎与安装提供必要的操作空间,为提高梁柱节点核心区内钢筋的绑扎质量提供了必要的保证。(1) Set up reinforced concrete ring beams around the core area of the beam-column joint, and pass the main bars on the side of the frame beams that extend into the core area and have little effect on the work of the vibrating rods through the core area to form a whole with the reinforced concrete ring beams to strengthen the core area. The ability to resist damage in the core area; and the beam-column steel bars that pass through or anchor in the core area, which will hinder the insertion and extraction of the vibrating rod, are anchored in the reinforced concrete ring beam on the same side, so as to avoid the criss-crossing condition of the steel bars in the core area of the node. The binding and installation of steel bars provides necessary operation space, and provides a necessary guarantee for improving the binding quality of steel bars in the core area of beam-column joints.

(2)在梁柱节点核心区内及框架柱内采取钢板套替代部分箍筋、并适当缩小核心区内箍筋的间距、优化钢筋布置方案等措施,进一步改善节点核心区内钢筋密布的状况;箍筋肢距满足《建筑抗震设计规范》GB50011要求的前提下,箍筋避开核心区内中间大约200mm部位安装,确保框架柱和钢筋混凝土梁柱节点核心区截面内中间部位大约直径为200mm范围内没有钢筋、箍筋穿过,便于振动棒的插入与拔出,确保振动棒的作用效应传递至核心区内每一处,使混凝土得到有效的震捣,及时排除混凝土中的气泡,可有效改善混凝土的密实度,提高混凝土的强度。(2) In the core area of beam-column joints and frame columns, steel plate sleeves are used to replace some stirrups, and the spacing of stirrups in the core area is appropriately reduced, and the reinforcement arrangement plan is optimized to further improve the dense distribution of reinforcement in the core area of the node. ; On the premise that the distance between the stirrups meets the requirements of GB50011 of the Code for Seismic Design of Buildings, the stirrups should be installed away from the middle part of the core area of about 200mm to ensure that the diameter of the middle part of the core area of the frame column and the reinforced concrete beam-column joint is about 200mm. There are no steel bars and stirrups passing through the range, which is convenient for the insertion and extraction of the vibrating rod, ensuring that the effect of the vibrating rod is transmitted to every part of the core area, so that the concrete can be effectively vibrated, and the air bubbles in the concrete can be eliminated in time. Effectively improve the compactness of concrete and increase the strength of concrete.

(3)在所述的新型钢筋混凝土结构梁柱节点中,梁柱节点核心区四周被焊接在一起的钢板套围住,钢板套把不同区域的混凝土分隔开来,即将核心区的混凝土和梁的混凝土隔开,可以与下柱同时浇筑混凝土,因此采用新型的钢筋混凝土结构梁柱节点,可有效解决地柱混凝土设计强度比梁板混凝土设计强度高两个等级及以上时梁柱节点核心区的混凝土的浇筑难题,确保节点核心区的混凝土强度等级与下柱的相同。(3) In the beam-column joint of the new reinforced concrete structure, the core area of the beam-column joint is surrounded by welded steel plate sleeves, and the steel plate sleeve separates the concrete in different areas, that is, the concrete in the core area and the The concrete of the beam is separated, and concrete can be poured at the same time as the lower column. Therefore, the use of a new type of reinforced concrete structure beam-column joint can effectively solve the core of the beam-column joint when the design strength of the ground-column concrete is two levels or more higher than the design strength of the beam-slab concrete. To solve the problem of concrete pouring in the area, ensure that the concrete strength grade in the core area of the node is the same as that of the lower column.

请参阅图1至图28所示。See Figures 1 through 28.

实施例:Example:

本发明的一种新型钢筋混凝土结构梁柱节点,包括A novel reinforced concrete structure beam-column joint of the present invention comprises:

(1)框架梁2和框架柱4交接的梁柱节点核心区3,如图1~11所示。所述梁柱节点核心区3包括框架柱4中穿过梁柱节点核心区3的主筋31、核心区内的混凝土及钢板套32和箍筋33,以及加强箍筋331,332,详见图5和图10所示;当柱截面改变时,还包括下柱的主筋311和上柱的主筋312,详见图12所示;所述箍筋33绑扎在主筋31,311之外,之后再在箍筋33外套入钢板套32,并支在双向框架梁2中穿过核心区的梁侧钢筋22之上,其中梁侧钢筋22位于框架梁底部第二排的梁侧边,并通过绑扎或通过短钢筋焊接固定在核心区的主筋上,详见图4和图5所示。(1) The core area 3 of the beam-column joint where the frame beam 2 and the frame column 4 meet, as shown in Figures 1-11. The core area 3 of the beam-column node includes the main reinforcement 31 passing through the core area 3 of the beam-column node in the frame column 4, the concrete and steel plate sleeves 32 and the stirrups 33 in the core area, and the reinforcement stirrups 331, 332, see Fig. 5 and As shown in Figure 10; when the column cross section is changed, it also includes the main reinforcement 311 of the lower column and the main reinforcement 312 of the upper column, as shown in Figure 12 for details; the stirrups 33 are bound outside the main reinforcement 31, 311, and then the stirrups The rib 33 is sheathed into the steel plate sleeve 32, and is supported on the beam side steel bar 22 passing through the core area in the two-way frame beam 2, wherein the beam side steel bar 22 is located at the beam side of the second row at the bottom of the frame beam, and is bound or passed through. The short steel bars are welded and fixed on the main bars in the core area, as shown in Figures 4 and 5 for details.

在具体一实施例中,核心区箍筋33间距≤100mm,在满足操作条件的情况下,间距尽可能小,一般取50~100mm;在梁柱节点核心区3中间附近箍筋33的肢距≥200mm,且应符合国家标准《建筑抗震设计规范》GB50011的规定;箍筋33可采用如图7~9等所示的形式,在核心区中间部位避免采用拉筋,以确保在梁柱节点核心区3的中心直径约为200mm范围内没有箍筋和主筋等穿过,如图7~9中虚线圆圈所示,便于振动棒的插入与拔出,确保核心区内每处混凝土均在振动作用有效半径之内,使混凝土得到有效的震捣,及时排除混凝土中的气泡,可有效改善混凝土的密实度,提高混凝土的强度。In a specific embodiment, the spacing between the stirrups 33 in the core area is less than or equal to 100 mm. Under the condition that the operating conditions are met, the spacing is as small as possible, generally 50 to 100 mm; ≥200mm, and should meet the requirements of the national standard "Code for Seismic Design of Buildings" GB50011; stirrups 33 can be in the form shown in Figures 7 to 9, and tie bars are avoided in the middle of the core area to ensure that the beam-column joints The center diameter of the core area 3 is about 200mm without stirrups and main bars passing through, as shown by the dotted circles in Figures 7 to 9, which is convenient for the insertion and extraction of the vibrating rod, and ensures that every concrete in the core area is vibrating. Within the effective radius of the action, the concrete can be effectively vibrated, and the air bubbles in the concrete can be removed in time, which can effectively improve the compactness of the concrete and increase the strength of the concrete.

核心区内的钢板套32是由四块钢板焊接而成的,其大样见图11所示;在钢板套全高范围内采用全焊透焊缝焊接,焊缝标示参照国家标准设计图集《钢结构连接施工图示》15G909-1执行,钢板套的高度=穿过核心区的框架梁底钢筋与穿过核心区的梁面钢筋之间的净距-10mm;其中t1和t2分别为两对边的钢板带厚度,钢板的强度、厚度及节点的受剪承载力计算应按现行国家标准《建筑结构荷载》GB50009、《混凝土结构设计规范》GB50010、《钢结构设计标准》GB50017、《钢管混凝土结构技术规范》GB50936、《高层建筑混凝土结构设计技术规程》JGJ3、《高层民用建筑钢结构技术规程》JGJ99和中国工程建设协会标准《矩形钢管混凝土节点技术规程》等的规定执行;抗震设计的框架结构尚应符合现行国家标准《建筑抗震设计规范》GB50011的规定执行。The steel plate sleeve 32 in the core area is welded by four steel plates, and its large sample is shown in Figure 11; the full-penetration weld is welded within the full height of the steel plate sleeve, and the welding seam is marked with reference to the National Standard Design Atlas " Steel structure connection construction diagram "15G909-1 implementation, the height of the steel plate sleeve = the clear distance between the bottom reinforcement of the frame beam passing through the core area and the beam surface reinforcement passing through the core area -10mm; where t 1 and t 2 are respectively is the thickness of the steel plate strip on the two opposite sides. The strength, thickness of the steel plate and the shear bearing capacity of the joint should be calculated according to the current national standard "Building Structure Load" GB50009, "Concrete Structure Design Code" GB50010, "Steel Structure Design Standard" GB50017, "Technical Specifications for Concrete-filled Steel Tubular Structures" GB50936, "Technical Specifications for Design of Concrete Structures of High-rise Buildings" JGJ3, "Technical Specifications for Steel Structures of High-rise Civil Buildings" JGJ99 and China Engineering Construction Association Standard "Technical Specifications for Rectangular Concrete-filled Steel Tube Joints" and other regulations; The designed frame structure should still comply with the current national standard "Code for Seismic Design of Buildings" GB50011.

在核心区内的主筋31或311外与框架梁底对应位置设置有加强箍筋331,在核心区的主筋31或312外与框架梁面对应位置设置有加强箍筋332,如图12所示。Reinforcing stirrups 331 are arranged outside the main bars 31 or 311 in the core area corresponding to the bottom of the frame beam, and reinforcing stirrups 332 are arranged outside the main bars 31 or 312 in the core area corresponding to the frame beam surface, as shown in FIG. 12 . Show.

当上下柱截面尺寸不同时,下柱的主筋311伸至钢板套顶后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d;上柱的主筋312伸至钢板套底部后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d,其中d为主筋的直径,laE为抗震时受拉钢筋的锚固长度,构造示意图见图12。When the cross-sectional dimensions of the upper and lower columns are different, the main reinforcement 311 of the lower column extends to the top of the steel plate sleeve and then bends and anchors it in the ring beam on the same side. 312 is extended to the bottom of the steel plate sleeve and then bent and anchored in the ring beam on the same side. The total anchorage length is greater than or equal to 1.2laE, and the anchorage length of the horizontal section is greater than or equal to 12d, where d is the diameter of the main reinforcement, and laE is the anchorage of the tensile reinforcement during earthquake The length and structure diagram are shown in Figure 12.

在顶层节点,下柱的主筋311伸至钢板套顶后弯折锚固于同侧的环梁内,其锚固总长度≥1.2laE,水平段的锚固长度≥12d,详见图13。At the top node, the main reinforcement 311 of the lower column extends to the top of the steel plate sleeve and then is bent and anchored in the ring beam on the same side. The total anchorage length is ≥1.2laE and the anchorage length of the horizontal section is ≥12d.

(2)钢筋混凝土环梁1,所述钢筋混凝土环梁1套设在所述梁柱节点核心区3外,如图14~18所示,在具体实施中,钢筋混凝土环梁1的强度等级与框架梁相同,与梁板一体浇筑成型。(2) Reinforced concrete ring beam 1, the reinforced concrete ring beam 1 is set outside the core area 3 of the beam-column joint, as shown in Figures 14-18, in the specific implementation, the strength grade of the reinforced concrete ring beam 1 The same as the frame beam, it is cast in one piece with the beam plate.

本发明所述的新型钢筋混凝土结构梁柱节点,在梁柱节点核心区3周边设置钢筋混凝土环梁1,将框架梁中的角筋21、25和位于第二排的梁侧钢筋22、26穿过核心区,与钢筋混凝土环梁形成一个整体,增强核心区抵抗破坏的能力;而其它纵向钢筋23、27、28则分散锚固于同侧的钢筋混凝土环梁内,避免节点核心区内钢筋纵横交错的状况,为钢筋绑扎与安装提供必要的操作空间,为提高梁柱节点核心区内钢筋的绑扎质量提供了必要的保证,可有效解决钢筋混凝土框架节点区施工质量难以保证的质量通病。In the beam-column joint of the novel reinforced concrete structure of the present invention, a reinforced concrete ring beam 1 is arranged around the core area 3 of the beam-column joint, and the corner bars 21 and 25 in the frame beam and the beam side bars 22 and 26 in the second row are connected. Passing through the core area, it forms a whole with the reinforced concrete ring beam, which enhances the ability of the core area to resist damage; while other longitudinal steel bars 23, 27, 28 are scattered and anchored in the reinforced concrete ring beam on the same side to avoid the reinforcement in the core area of the node. The criss-crossing situation provides necessary operating space for the binding and installation of steel bars, and provides a necessary guarantee for improving the binding quality of steel bars in the core area of beam-column joints, which can effectively solve the common quality problem that the construction quality of reinforced concrete frame node areas is difficult to guarantee.

在具体一实施例中,如图14~18所示,所述钢筋混凝土环梁1的高度≥框架梁2的高度+50mm;所述钢筋混凝土环梁1的宽度≥框架梁2的宽度,且应能满足框架梁2主筋的锚固要求,框架梁2主筋在钢筋混凝土环梁1内的锚固按GB50010的规定执行。In a specific embodiment, as shown in FIGS. 14-18 , the height of the reinforced concrete ring beam 1 ≥ the height of the frame beam 2 + 50 mm; the width of the reinforced concrete ring beam 1 ≥ the width of the frame beam 2 , and It should be able to meet the anchorage requirements of the main reinforcement of frame beam 2, and the anchorage of the main reinforcement of frame beam 2 in the reinforced concrete ring beam 1 shall be carried out according to the provisions of GB50010.

钢筋混凝土环梁1在上部设置封闭焊接主筋11,12,13,其面积不小于框架梁上部主筋的0.7倍,在下部设置封闭焊接主筋17~19,其面积不小于框架梁下部主筋的0.7倍;主筋13和19的长度=(bc+hc+50)*2,其中bc和hc分别为框架柱的短边和长边尺寸,如图14~15所示;主筋11(17),12(18)和13(19)之间的间距≤200mm;箍筋14直径≥A8mm,间距≤100mm,腰筋15的直径≥B14,相邻腰筋15之间的间距≤200mm,拉筋16之间的间距≤200mm,见图16。Reinforced concrete ring beam 1 is provided with closed welded main bars 11, 12, 13 in the upper part, and its area is not less than 0.7 times that of the upper main reinforcement of the frame beam, and closed welded main reinforcement bars 17-19 are set in the lower part, and its area is not less than 0.7 times of the lower main reinforcement of the frame beam ; The length of the main bars 13 and 19 = (bc+hc+50)*2, where bc and hc are the short and long sides of the frame column, respectively, as shown in Figures 14 to 15; the main bars 11 (17), 12 ( The distance between 18) and 13 (19) is less than or equal to 200mm; the diameter of stirrup 14 is greater than or equal to A8mm, the spacing is less than or equal to 100mm, the diameter of waist bar 15 is greater than or equal to B14, the spacing between adjacent waist bars 15 is less than or equal to 200mm, and the distance between ties 16 is less than or equal to 200mm. The spacing is less than or equal to 200mm, see Figure 16.

(3)框架梁2的截面尺寸、配筋等应符合相关规范的规定和设计文件的要求。框架梁主筋在核心区平面中的位置见图4,核心区内的钢板套与框架梁主筋在竖向相对位置见图5,钢筋混凝土框架梁2的截面配筋示意图见图6,其中b为框架梁的截面宽度,hb为截面高度。(3) The section size and reinforcement of the frame beam 2 shall comply with the provisions of the relevant codes and the requirements of the design documents. The position of the main reinforcement of the frame beam in the plane of the core area is shown in Figure 4, the vertical relative position of the steel plate sleeve and the main reinforcement of the frame beam in the core area is shown in Figure 5, and the schematic diagram of the cross-section reinforcement of the reinforced concrete frame beam 2 is shown in Figure 6, where b is The section width of the frame beam, hb is the section height.

框架梁在两端设置箍筋加密区,从环梁边开始,箍筋加密区长度为S,抗震等级为一级时,梁端箍筋加密区长度S≥2.0hb且不小于500mm;抗震等级为二~四级时,梁端箍筋加密区长度S≥1.5hb且不小于500mm,其中hb为框架梁高。The frame beam is provided with stirrup densification areas at both ends, starting from the edge of the ring beam, the length of the stirrup densification zone is S, and when the seismic grade is level 1, the length of the stirrup densification zone at the beam end is S≥2.0hb and not less than 500mm; the seismic grade When it is grade two to four, the length of the reinforced area of the stirrup at the beam end is S ≥ 1.5hb and not less than 500mm, where hb is the height of the frame beam.

钢筋混凝土框架梁2的底部角筋21和位于底部第二排的梁侧钢筋22从钢板套下贯通钢筋混凝土梁柱节点核心区3;其余的梁底钢筋23完全穿过同侧的环梁后弯折锚固,其锚固总长度≥laE,其中水平段的锚固长度≥0.4labE;钢筋混凝土框架梁2的梁面角筋25和第二排的梁侧钢筋26从钢板套上方穿过钢筋混凝土梁柱节点核心区3,其余的梁面钢筋27完全穿过同侧的环梁后弯折锚固,其锚固总长度≥laE,水平段的锚固长度≥0.4labE;其中laE为抗震时受拉钢筋的锚固长度,labE为主筋的受拉钢筋的基本锚固长度;详见图5所示。The bottom corner bars 21 of the reinforced concrete frame beam 2 and the beam side bars 22 located in the second row at the bottom penetrate through the core area 3 of the reinforced concrete beam-column joint from the steel plate cover; the rest of the beam bottom bars 23 completely pass through the ring beam on the same side Bending anchorage, the total anchorage length ≥laE, of which the anchorage length of the horizontal section is ≥0.4labE; the beam surface angle bars 25 of the reinforced concrete frame beam 2 and the beam side reinforcement bars 26 of the second row pass through the reinforced concrete beam from the top of the steel plate sleeve In the core area 3 of the column node, the rest of the beam surface steel bars 27 completely pass through the ring beam on the same side and then bend and anchor. The anchorage length, labE, is the basic anchorage length of the tensile reinforcement of the main reinforcement; see Figure 5 for details.

对于只有单侧框架梁的边节点,钢筋混凝土框架梁2的底部角筋21和底部第二排的梁侧钢筋22穿过钢筋混凝土梁柱节点核心区3延伸至另一侧的环梁边锚固,其锚固总长度≥laE,水平段的锚固长度≥0.4labE;如图19和图20所示,若锚固长度不足,可在主筋的末端两侧贴焊长度为钢筋直径3倍的锚筋;钢筋混凝土框架梁2的梁面角筋25和第二排的梁侧钢筋26从钢板套上跨过钢筋混凝土梁柱节点核心区3,完全穿过另一侧的环梁后弯折锚固,其锚固总长度≥laE,水平段的锚固长度≥0.4labE;其中laE为抗震时受拉钢筋的锚固长度,labE为主筋的受拉钢筋的基本锚固长度。For edge nodes with only one-sided frame beams, the bottom corner bars 21 of the reinforced concrete frame beam 2 and the beam side bars 22 of the second row at the bottom extend through the core area 3 of the reinforced concrete beam-column node to the ring beam edge anchoring on the other side. , the total anchorage length is greater than or equal to laE, and the anchorage length of the horizontal section is greater than or equal to 0.4labE; as shown in Figure 19 and Figure 20, if the anchorage length is insufficient, anchor bars with a length of 3 times the diameter of the steel bar can be welded on both sides of the end of the main bar; The beam face corner bars 25 of the reinforced concrete frame beam 2 and the beam side bars 26 of the second row are covered from the steel plate and cross the core area 3 of the reinforced concrete beam-column joint, and are bent and anchored after completely passing through the ring beam on the other side. The total anchorage length is greater than or equal to laE, and the anchorage length of the horizontal section is greater than or equal to 0.4labE; where laE is the anchorage length of the tensile reinforcement during earthquake resistance, and labE is the basic anchorage length of the tensioned reinforcement for the main reinforcement.

当位于核心区两侧的框架梁高度不同时,框架梁主筋在节点核心区内的锚固构造示意图见图21和图22;若HE/Bhu≤1/6,则高度大的梁底角筋21和第二排的梁侧钢筋22穿过核心区后向上弯折与另一侧的梁底主筋拉通;若HE/Bhu>1/6,则高度大的梁底角筋21和第二排的梁侧钢筋22穿过核心区和另一侧的环梁后弯折锚固于环梁内,其锚固总长度≥laE,水平段的锚固长度≥0.4labE;高度小的梁底角筋21和第二排的梁侧钢筋22则伸至钢板套边锚固于同侧的环梁内,锚固总长度≥laE,水平段的锚固长度≥0.4labE;其中laE为抗震时受拉钢筋的锚固长度,labE为主筋的受拉钢筋的基本锚固长度;HE是两侧主筋的位置高差,Bhu是环梁的宽度。When the heights of the frame beams located on both sides of the core area are different, the schematic diagrams of the anchorage structure of the main reinforcement of the frame beam in the node core area are shown in Figure 21 and Figure 22; And the beam side reinforcement 22 of the second row passes through the core area and then bends upward and connects with the main reinforcement at the bottom of the beam on the other side; if HE/Bhu>1/6, then the corner reinforcement 21 at the bottom of the beam with high height and the second row The beam side reinforcement 22 passes through the core area and the ring beam on the other side and is then bent and anchored in the ring beam. The total anchorage length is ≥laE, and the anchorage length of the horizontal section is ≥0.4labE; The beam side reinforcement bars 22 of the second row extend to the steel plate sleeve and anchor in the ring beam on the same side. The total anchorage length is greater than or equal to laE, and the anchorage length of the horizontal section is greater than or equal to 0.4labE. labE is the basic anchorage length of the tensile reinforcement of the main reinforcement; HE is the positional height difference of the main reinforcement on both sides, and Bhu is the width of the ring beam.

(4)相关构件(4) Related components

①为了便于振动棒的插入于拔出,在框架柱内采取增大箍筋直径、适当缩小箍筋间距等措施,在箍筋肢距满足《建筑抗震设计规范》GB50011要求的前提下,箍筋41避开核心区内中间约直径为200mm的部位安装,柱截面的箍筋可以采用如图24~26的形式。①In order to facilitate the insertion and extraction of the vibrating rod, measures such as increasing the diameter of the stirrups and appropriately reducing the spacing of the stirrups are taken in the frame column. 41 Avoid the middle part of the core area with a diameter of about 200mm and install it.

若采取以上措施后,框架柱仍无法满足受剪承载力要求,框架柱内也可采取由钢板带焊接而成的钢板套42替代部分箍筋。此时,框架柱内的钢板套42也是由四块钢板焊接而成的,其中t3和t4分别为两对边的钢板带厚度,钢板的强度、厚度及框架柱的受剪承载力计算应按现行国家标准《建筑结构荷载》GB50009、《混凝土结构设计规范》GB50010、《钢结构设计标准》GB50017、《钢管混凝土结构技术规范》GB50936、《高层建筑混凝土结构设计技术规程》JGJ3、《高层民用建筑钢结构技术规程》JGJ99和中国工程建设协会标准《矩形钢管混凝土节点技术规程》等的规定执行;抗震设计的框架结构尚应符合现行国家标准《建筑抗震设计规范》GB50011的规定执行;框架柱的受弯承载力计算时忽略钢板套的贡献,按现行的有关规定执行。If the frame column still cannot meet the shear bearing capacity requirements after taking the above measures, the steel plate sleeve 42 welded by the steel plate strip can also be used in the frame column to replace part of the stirrups. At this time, the steel plate sleeve 42 in the frame column is also welded by four steel plates, wherein t3 and t4 are the thickness of the steel plate strips on the two opposite sides, respectively. The strength and thickness of the steel plate and the shear bearing capacity of the frame column are calculated. The current national standards "Building Structural Load" GB50009, "Code for Design of Concrete Structures" GB50010, "Standards for Design of Steel Structures" GB50017, "Technical Specifications for Concrete-filled Steel Tubular Structures" GB50936, "Technical Specifications for Design of Concrete Structures for High-rise Buildings" JGJ3, "High-rise Buildings Concrete Structure Design Technical Specifications" The technical regulations for steel structures of civil buildings JGJ99 and the China Engineering Construction Association standard “Technical Regulations for Rectangular Steel Tube Concrete Joints” shall be implemented; the frame structure of seismic design shall still comply with the provisions of the current national standard “Code for Seismic Design of Buildings” GB50011; The contribution of the steel plate sleeve is ignored in the calculation of the flexural bearing capacity of the column, and it is implemented in accordance with the current relevant regulations.

钢板套42在底层柱下端Hn/3范围内采用全焊透焊缝,在底层柱的上端Sc范围内钢板套42采用全焊透焊缝,如图27所示,在中间部位可采用部分焊透焊缝,如图28所示;底层柱的钢板套42的高度=二层框架梁底至基础顶面的距离-10mm;The steel plate sleeve 42 adopts a full penetration weld within the range of H n /3 at the lower end of the bottom column, and the steel plate sleeve 42 adopts a full penetration weld within the range of the upper end Sc of the bottom column. The penetration weld is shown in Figure 28; the height of the steel plate sleeve 42 of the bottom column = the distance from the bottom of the frame beam on the second floor to the top surface of the foundation -10mm;

钢板套42在其它层的两端Sc范围内采用全焊透焊缝,而在中间部位可采用部分焊透焊缝,其中Sc≥hc,Sc≥Hn/6,且Sc≥500mm,hc为框架柱的截面长边尺寸,Hn为框架柱的净高;钢板套42高度=上层框架梁底至下一层楼面的距离-10mm。The steel plate sleeve 42 adopts full penetration welds in the range of Sc at both ends of the other layers, and can use partial penetration welds in the middle part, where Sc≥hc , Sc≥Hn /6, and Sc≥500mm, h c is the length of the cross-section of the frame column, H n is the net height of the frame column; the height of the steel plate sleeve 42 = the distance from the bottom of the upper frame beam to the next floor -10mm.

在钢板套42采用全焊透焊缝的柱端,设置箍筋加密区,箍筋间距≤100mm,在其它柱段,箍筋间距≤200mm,见图23。At the column end of the steel plate sleeve 42 where the full penetration weld is used, a stirrup densification area is set up, and the stirrup spacing is ≤100mm, and in other column sections, the stirrup spacing is ≤200mm, see Figure 23.

②基础,基础5按实际设计图纸进行施工。② Foundation, foundation 5 is constructed according to the actual design drawings.

所述的新型钢筋混凝土结构梁柱节点施工方法:Described new reinforced concrete structure beam-column joint construction method:

1)根据设计图纸的要求加工制作钢板带,并根据设计要求焊接成钢板套。1) According to the requirements of the design drawings, the steel strip is processed and made, and welded into a steel plate sleeve according to the design requirements.

2)加工制作环形主筋、框架梁钢筋、腰筋、框架柱钢筋和箍筋等。2) Process and manufacture annular main bars, frame beam bars, waist bars, frame column bars and stirrups, etc.

3)新型钢筋混凝土结构梁柱节点施工工艺流程:3) The construction process of the new reinforced concrete structure beam-column joint:

楼面轴线定位→在楼面画柱边线→焊接或绑扎框架柱的竖向受力筋31或311→在柱的主筋上画箍筋间距线→绑扎框架柱4的箍筋41→套入柱的钢板套42→绑扎梁柱节点核心区3的加强箍筋331→安装支撑,及框架柱、板、框架梁底及环梁的底部模板→套入框架梁箍筋24→穿框架梁2的底部受力筋→在框架柱4的主筋31或312上套入钢板套32→安装环梁的主筋、腰筋和箍筋→穿框架梁2的上部受力筋→安装核心区的箍筋33→套入核心区的钢板套32→安装核心区的加强箍筋322→绑扎框架梁2的箍筋→安装框架梁和环梁的侧向模板→利用溜槽浇筑框架柱4及梁柱节点核心区3的混凝土→浇筑框架梁板及环梁的混凝土。Floor axis positioning → draw the column edge line on the floor → weld or bind the vertical stress bar 31 or 311 of the frame column → draw the stirrup spacing line on the main bar of the column → bind the stirrup 41 of the frame column 4 → set it into the column The steel plate sleeve 42 → the reinforcing stirrups 331 in the core area 3 of the beam-column node binding → installation support, and the bottom formwork of the frame column, plate, frame beam bottom and ring beam → set into the frame beam stirrup 24 → wear the frame beam 2 Bottom reinforcement → insert the steel plate sleeve 32 on the main reinforcement 31 or 312 of the frame column 4 → install the main reinforcement, waist reinforcement and stirrups of the ring beam → wear the upper reinforcement reinforcement of the frame beam 2 → install the stirrup 33 in the core area → Set the steel plate sleeve 32 in the core area → Install the reinforcing stirrups 322 in the core area → Bind the stirrups of the frame beam 2 → Install the lateral formwork of the frame beam and the ring beam → Use the chute to cast the frame column 4 and the beam-column joint core area 3 Concrete → Concrete for frame beam slabs and ring beams.

本发明适用于现浇的钢筋混凝土框架结构体系和现浇的钢筋混凝土框剪结构体系中梁柱节点。The invention is suitable for the beam-column joints in the cast-in-place reinforced concrete frame structure system and the cast-in-place reinforced concrete frame-shear structure system.

虽然以上描述了本发明的具体实施方式,但是熟悉本技术领域的技术人员应当理解,我们所描述的具体的实施例只是说明性的,而不是用于对本发明的范围的限定,熟悉本领域的技术人员在依照本发明的精神所作的等效的修饰以及变化,都应当涵盖在本发明的权利要求所保护的范围内。Although the specific embodiments of the present invention have been described above, those skilled in the art should understand that the specific embodiments we describe are only illustrative, rather than used to limit the scope of the present invention. Equivalent modifications and changes made by a skilled person in accordance with the spirit of the present invention should be included within the scope of protection of the claims of the present invention.

Claims (8)

1. The utility model provides a novel reinforced concrete structure beam column node which characterized in that: comprises that
A beam-column joint core area at the joint of the frame beam and the frame column; the beam-column joint core area comprises a main rib penetrating through the beam-column joint core area in the frame column, and stirrups, reinforcing stirrups, a steel plate sleeve and concrete in the core area, wherein the stirrups are bound outside the main rib, the steel plate sleeve is sheathed outside the stirrups, and the steel plate sleeve is also supported on the main rib penetrating through the bottom of the frame beam in the core area;
the reinforced concrete ring beam surrounds the periphery of the beam column joint core area.
2. The novel beam-column joint of a reinforced concrete structure as claimed in claim 1, wherein: the concrete strength of the reinforced concrete ring beam is the same as that of the beam slab, and the height of the ring beam is more than or equal to the height of the frame beam plus 50 mm; the width of the reinforced concrete ring beam is larger than or equal to that of the frame beam, the anchoring requirement of the main reinforcement of the frame beam can be met, and the anchoring of the main reinforcement of the frame beam in the ring beam is executed according to the regulation of GB 50010.
3. The novel beam-column joint of a reinforced concrete structure as claimed in claim 2, wherein: the diameter of the main reinforcement of the reinforced concrete ring beam is more than or equal to B16, and the distance is less than or equal to 200 mm; the diameter of the stirrup is more than or equal to A8, and the distance is less than or equal to 100 mm; when the height of the web plate of the ring beam is more than or equal to 450mm, waist ribs are arranged along the height of two side surfaces of the ring beam, the diameter is more than or equal to B14, the distance between the waist ribs on each side is less than or equal to 200mm, and the space between the lacing wires between the waist ribs is less than or equal to 200 mm; the main rib and the waist rib are connected by welding.
4. The novel beam-column joint of a reinforced concrete structure as claimed in claim 1, wherein: the steel plate sleeve is formed by welding four steel plates, and full penetration welding seams are adopted for welding within the full height range of the steel plate sleeve; the height of the steel plate sleeve is equal to the clear distance between the frame beam bottom reinforcing steel bars passing through the core area and the beam surface reinforcing steel bars passing through the core area, and is-10 mm.
5. The novel reinforced concrete structure beam column node of claim 1, wherein: the angle bars in the frame beam and the beam side steel bars in the second row penetrate through the core area to form a whole with the reinforced concrete ring beam, so that the damage resistance of the core area is enhanced; the reinforcing steel bars on the non-beam side and the reinforcing steel bars on the third row and above in the 1 st-2 nd row in the frame beam completely penetrate through the reinforced concrete ring beam on the same side and then are bent and anchored; for the side frame node, after the beam side reinforcing steel bars located in the 1 st to 2 nd rows in the frame beam penetrate through the core area of the reinforced concrete beam-column node, the beam side reinforcing steel bars are anchored in the ring beam on the other side.
6. The novel reinforced concrete structure beam column node of claim 1, wherein: when the section sizes of the upper column and the lower column are different, the main ribs of the lower column extend to the top of the steel plate sleeve and then are bent and anchored in the ring beam on the same side, the anchoring total length is more than or equal to 1.2laE, and the anchoring length of the horizontal section is more than or equal to 12 d; the main reinforcement of the upper column extends to the bottom of the steel plate sleeve and then is bent and anchored in the ring beam on the same side, the anchoring total length is more than or equal to 1.2laE, the anchoring length of the horizontal section is more than or equal to 12d, wherein d is the diameter of the main reinforcement, and laE is the anchoring length of the tension reinforcement in earthquake resistance.
7. The novel reinforced concrete structure beam column node of claim 1, wherein: at the top node, the main rib of the lower column extends to the top of the steel plate sleeve and then is bent and anchored in the ring beam on the same side, the anchoring total length is more than or equal to 1.2laE, and the anchoring length of the horizontal section is more than or equal to 12 d.
8. The novel beam-column joint of a reinforced concrete structure as claimed in claim 1, wherein: and reinforcing stirrups with the diameter larger than or equal to B12mm are welded on the beam surface and the bottom of the frame beam in the beam-column joint core area.
CN202010106685.3A 2020-02-21 2020-02-21 A new type of reinforced concrete structure beam-column joint and construction method Pending CN111236419A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010106685.3A CN111236419A (en) 2020-02-21 2020-02-21 A new type of reinforced concrete structure beam-column joint and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010106685.3A CN111236419A (en) 2020-02-21 2020-02-21 A new type of reinforced concrete structure beam-column joint and construction method

Publications (1)

Publication Number Publication Date
CN111236419A true CN111236419A (en) 2020-06-05

Family

ID=70870469

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010106685.3A Pending CN111236419A (en) 2020-02-21 2020-02-21 A new type of reinforced concrete structure beam-column joint and construction method

Country Status (1)

Country Link
CN (1) CN111236419A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144910A (en) * 2020-10-30 2020-12-29 福州大学 Reinforced concrete frame node HDC wire winding reinforcement device and its construction method
CN112359967A (en) * 2020-12-04 2021-02-12 吉林建筑大学 Method for building concrete frame beam column joint by adopting integrated integral stirrups
CN113789975A (en) * 2021-10-21 2021-12-14 苏州达康建筑科技有限公司 Structure and method for reinforcing core area of concrete frame

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3867805A (en) * 1972-05-18 1975-02-25 Kajima Corp Method of forming joint construction of precast concrete columns and beams
JPH0524701U (en) * 1991-09-17 1993-03-30 前田建設工業株式会社 Beam-column joint structure of precast concrete structure
JPH07317149A (en) * 1994-05-24 1995-12-05 Takenaka Komuten Co Ltd Execution method of reinforced concrete column and beam frame
JP2010236217A (en) * 2009-03-31 2010-10-21 Neturen Co Ltd Structure and construction method for reinforcing column-beam joint portion of reinforced concrete construction
CN102864842A (en) * 2012-10-26 2013-01-09 上海中锦建设集团股份有限公司 Core anchoring barrel type node system of reinforced concrete frame structure and application of core anchoring barrel type node system
CN204781321U (en) * 2015-06-04 2015-11-18 扬州大学 Local reinforced concrete frame that adopts built -in square steel tube reinforcing
CN205153150U (en) * 2015-10-30 2016-04-13 华南理工大学 Frame beam column node reinforced structure
CN106545086A (en) * 2016-10-17 2017-03-29 华南理工大学 A kind of steel bar regeneration monolith bean column node and its construction method
CN107090909A (en) * 2017-06-19 2017-08-25 上海欧本钢结构有限公司 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN110273469A (en) * 2019-07-17 2019-09-24 金点石(北京)建筑设计咨询服务有限责任公司 Column beam connecting node, building frame construction and building body
CN212388730U (en) * 2020-02-21 2021-01-22 莆田学院 A new type of beam-column joint of reinforced concrete structure

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3867805A (en) * 1972-05-18 1975-02-25 Kajima Corp Method of forming joint construction of precast concrete columns and beams
JPH0524701U (en) * 1991-09-17 1993-03-30 前田建設工業株式会社 Beam-column joint structure of precast concrete structure
JPH07317149A (en) * 1994-05-24 1995-12-05 Takenaka Komuten Co Ltd Execution method of reinforced concrete column and beam frame
JP2010236217A (en) * 2009-03-31 2010-10-21 Neturen Co Ltd Structure and construction method for reinforcing column-beam joint portion of reinforced concrete construction
CN102864842A (en) * 2012-10-26 2013-01-09 上海中锦建设集团股份有限公司 Core anchoring barrel type node system of reinforced concrete frame structure and application of core anchoring barrel type node system
CN204781321U (en) * 2015-06-04 2015-11-18 扬州大学 Local reinforced concrete frame that adopts built -in square steel tube reinforcing
CN205153150U (en) * 2015-10-30 2016-04-13 华南理工大学 Frame beam column node reinforced structure
CN106545086A (en) * 2016-10-17 2017-03-29 华南理工大学 A kind of steel bar regeneration monolith bean column node and its construction method
CN107090909A (en) * 2017-06-19 2017-08-25 上海欧本钢结构有限公司 A kind of concrete frame bean column node steel pipe bundle reinforcing sleeve and its assembly method
CN110273469A (en) * 2019-07-17 2019-09-24 金点石(北京)建筑设计咨询服务有限责任公司 Column beam connecting node, building frame construction and building body
CN212388730U (en) * 2020-02-21 2021-01-22 莆田学院 A new type of beam-column joint of reinforced concrete structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄群贤;朱奇云;郭子雄;: "新型钢筋混凝土柱-钢梁混合框架节点研究综述", 建筑结构学报, no. 2, 30 December 2009 (2009-12-30), pages 154 - 158 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112144910A (en) * 2020-10-30 2020-12-29 福州大学 Reinforced concrete frame node HDC wire winding reinforcement device and its construction method
CN112359967A (en) * 2020-12-04 2021-02-12 吉林建筑大学 Method for building concrete frame beam column joint by adopting integrated integral stirrups
CN113789975A (en) * 2021-10-21 2021-12-14 苏州达康建筑科技有限公司 Structure and method for reinforcing core area of concrete frame
CN113789975B (en) * 2021-10-21 2022-08-05 苏州达康建筑科技有限公司 Structure and method for reinforcing core area of concrete frame

Similar Documents

Publication Publication Date Title
CN105569224B (en) Concrete filled steel tube edge constraint overlaps monoblock type shear wall and preparation and installation method
CN104328847B (en) A kind of construction method of interior bearing diagonal assembly concrete shear wall prefabricated components
CN107476476A (en) Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam
CN105804241A (en) Single-layer prefabricated assembly type reinforced concrete beam-column joint
CN105649203B (en) Precast prestressed concrete frame bean column node with U-shaped muscle and sleeve
CN208501878U (en) A kind of Self-resetting prefabrication and assembly construction frame structure interior joint
CN206667595U (en) A kind of concrete column of built-in four limbs lattice steel skeleton
CN108035438A (en) A kind of concrete assembled frame structure system of high-strength high ductility and connection method
CN111236419A (en) A new type of reinforced concrete structure beam-column joint and construction method
CN108797791B (en) A kind of assembly method of upper and lower self-heat conserving external wall and floor
CN109183983A (en) A kind of assembly method of upper and lower interior wall and floor
CN108775086A (en) The additional assembled integral beam-column node structure and construction method for being closed connection reinforcing bar
CN114592688B (en) Construction method of oblique reinforced concrete shear wall based on equivalent rod model
CN208105473U (en) A kind of assembly node of upper and lower self-heat conserving external wall and floor
CN108086528B (en) Prefabricated shear wall vertical steel plate connection structure, manufacturing and assembly method
CN114482400A (en) Superposed beam connected with prefabricated vertical component
CN212388730U (en) A new type of beam-column joint of reinforced concrete structure
CN106759885B (en) Cold formed steel structure house inner wall structural system
CN113250359A (en) Full precast concrete floor slab connection structure and design calculation method
CN208105474U (en) A kind of assembly node of upper and lower interior wall and floor
CN210597882U (en) Lattice type steel reinforced concrete combined column beam column node
CN106948495A (en) The prestressing force integral node and its construction method of steel core concrete column and beams of concrete
CN109356190B (en) Lattice column type pier concrete tower crane foundation and construction method thereof
CN217027742U (en) Superposed beam connected with prefabricated vertical component
CN205822448U (en) A kind of distinctiveness uses the precast frame bean column node of high performance material

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination