CN104846744A - Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode - Google Patents
Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode Download PDFInfo
- Publication number
- CN104846744A CN104846744A CN201510120099.3A CN201510120099A CN104846744A CN 104846744 A CN104846744 A CN 104846744A CN 201510120099 A CN201510120099 A CN 201510120099A CN 104846744 A CN104846744 A CN 104846744A
- Authority
- CN
- China
- Prior art keywords
- pier
- concrete
- template
- formwork
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D19/00—Structural or constructional details of bridges
- E01D19/02—Piers; Abutments ; Protecting same against drifting ice
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D2101/00—Material constitution of bridges
- E01D2101/20—Concrete, stone or stone-like material
- E01D2101/24—Concrete
- E01D2101/26—Concrete reinforced
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明公开了一种城市高架曲线式墩柱一次浇筑成型施工方法,其中,施工步骤如下:第一步,墩柱预埋主筋定位;第二步,墩身与承台结合部位凿毛;第三步,测量放样;第四步,脚手架搭设;第五步,钢筋加工与安装;第六步,模板加工、安装;第七步,混凝土浇筑;第八步,模板拆除、养生 ;第九步,脚手架拆除;本发明提供的一种城市高架曲线式墩柱一次浇筑成型施工方法,具有施工快捷,结构合理,经济实惠等特点,广泛适用于城市高墩桥梁,尤其是城市高墩景观桥梁。
The invention discloses a construction method for one-time pouring and molding of urban elevated curved pier columns, wherein the construction steps are as follows: first step, pre-embedded main reinforcement positioning of pier columns; The third step is to measure and set out; the fourth step is to set up scaffolding; the fifth step is to process and install steel bars; the sixth step is to process and install formwork; the seventh step is to pour concrete; the eighth step is to remove formwork and maintain health; the ninth step , Scaffold removal; The invention provides a construction method of one-time pouring and forming of urban elevated curved pier columns, which has the characteristics of fast construction, reasonable structure, economic benefits, etc., and is widely applicable to urban high-pier bridges, especially urban high-pier landscape bridges.
Description
技术领域 technical field
本发明涉及一种高架桥施工方法,具体涉及一种城市高架曲线式墩柱一次浇筑成型施工方法。 The invention relates to a construction method of a viaduct, in particular to a construction method of one-time casting and forming of curved pier columns of an urban viaduct.
背景技术 Background technique
随着经济及城市交通的迅猛发展,高架桥中的桥梁逐渐要求“景观化”,桥梁景观对于城市或区域形象的塑造也越来越被人们所关注,并要与城市或区域形象的塑造相匹配。 With the rapid development of economy and urban traffic, the bridges in viaducts gradually require "landscape", and the shaping of the image of the city or region by the bridge landscape is also more and more concerned by people, and it must match the shaping of the image of the city or region .
墩与梁相比,更接近人的视点,墩柱的形状、体量、表面处理及附属物等都形成了景观要素,是美学设计的重点。 Compared with beams, piers are closer to people's point of view. The shape, volume, surface treatment and appendages of pier columns all form landscape elements and are the focus of aesthetic design.
近年来桥墩也从早期的圆柱墩向纤细、美观的轻型桥墩发展,特别是曲线式墩柱在国内被广泛的应用。 In recent years, bridge piers have also developed from early cylindrical piers to slender and beautiful light-weight piers, especially curved piers are widely used in China.
曲线式墩柱适用性强、造型美观,避免了传统施工方法的缺陷,技术上先进、可靠、适用,经济上合理,取得了显著的经济和社会效益。 The curved piers have strong applicability and beautiful appearance, avoid the defects of traditional construction methods, are technologically advanced, reliable, applicable, and economically reasonable, and have achieved significant economic and social benefits.
但构造复杂:钢筋外倾且稠密、空间定位较困难、模板外倾且模内操作空间小、墩顶预埋件多。 However, the structure is complex: the steel bars are inclined and dense, the space positioning is difficult, the formwork is outwardly inclined and the operation space in the mold is small, and there are many embedded parts on the top of the pier.
传统的施工方法为墩身主筋现场逐根接长,水平箍筋逐层绑扎,墩身标准段、曲线段模板分次安装,混凝土分次浇筑,施工周期长,易产生错台、色差、冷缝、保护层合格率低等外观及质量缺陷。 The traditional construction method is that the main reinforcement of the pier body is lengthened one by one on site, the horizontal stirrups are bound layer by layer, the formwork of the standard section and the curved section of the pier body are installed in stages, and the concrete is poured in stages. Appearance and quality defects such as joints and low pass rate of protective layer.
针对这些缺陷,本发明提出了一种城市高架曲线式墩柱一次浇筑成型施工方法。 Aiming at these defects, the present invention proposes a construction method for one-time pouring and forming of urban elevated curved pier columns.
发明内容 Contents of the invention
本发明所要解决的技术问题是提供一种城市高架曲线式墩柱一次浇筑成型施工方法,墩柱适用性强、造型美观,避免了传统施工方法的缺陷。 The technical problem to be solved by the present invention is to provide a construction method for one-time pouring of urban elevated curved pier columns. The pier columns have strong applicability and beautiful appearance, and avoid the defects of traditional construction methods.
本发明提供的一种城市高架曲线式墩柱一次浇筑成型施工方法,施工步骤如下:第一步,墩柱预埋主筋定位:预埋主筋,承台钢筋焊接牢固,绑扎箍筋形成劲性骨架;第二步,墩身与承台结合部位凿毛:承台混凝土强度达到2.5MPa后,对墩身预埋钢筋内侧承台顶面混凝土进行凿毛,凿至砼面有石子外露为止,并冲洗干净;第三步,测量放样;采用全站仪在承台顶面放设墩柱纵、横轴线和柱模内外平面轮廓线,墨斗弹出连线,测量出墩底四周标高,作为钢筋绑扎、安装和立模基准;第四步,脚手架搭设;墩身四周采用Φ48mm×3.5mm碗扣支架或扣件式钢管搭设双排脚手架作为墩身钢筋安装、模板安拆及混凝土浇筑时工作平台;脚手架四周闭合,基础落于承台及处理硬化好的地基上,内外侧利用钢管及扣件按规范要求设置斜杆或剪刀撑,脚手架内侧与外模之间预留模板安装、拆距除间距,作业层、通道宽度范围内脚手板铺满铺稳,外围平台栏杆比最上层作业层高1.2m; 第五步,钢筋加工与安装;1)主筋丝头加工:墩身主筋(≥Φ25mm)采用滚扎直螺纹套筒连接;2)半成品加工:半成品采用分类加工,针对变截面段主筋及箍筋采取逐根编号下料加工、分类堆放;3)墩身钢筋骨架加工:墩柱钢筋骨架在钢筋加工车间采用平地整体胎模长线法整体制作,采用型钢设置固定曲线段+长度可调的标准段墩身钢筋骨架长线胎模,根据墩身主筋布置,胎模采用可调节支撑型钢架;第六步,模板加工、安装;模板安装前根据墩身的高度配置好模板并编号,整体预先拼装,完成模板拼缝、错台、平整度调整;预拼合格的模板达到板面局部不平≤1.0mm,相邻两板表面高低差≤1.0mm,拼缝≤1.0mm,模板整体表面平整度≤3.0mm,并在试拼合格的模板背肋后采用油漆作调整标记; 预拼验收合格的模板拆分成块,磨光机反复打磨至金属亮色,采用统一的脱模剂,在模板表面均匀涂抹,略风干,并采用塑料薄膜覆盖防尘;第七步,混凝土浇筑;曲线式墩柱墩身与系梁混凝土整体浇筑成型,墩身混凝土振捣密实,在墩顶系梁伸入墩柱的上下层主筋处预留混凝土浇筑串筒安拆,振捣人员上下通道,断开的钢筋采用滚轧直螺纹套筒连接,上下层及相邻钢筋接头错开不小于35d的距离; 振捣人员经墩顶预留人孔及爬梯至钢筋内部,接串筒浇筑混凝土,串筒采用方木、钢管成井字形支撑在模板上口,底口距离砼顶面不超过2.0米,混凝土采用汽车吊提升料斗,串筒下料,按水平30cm分层,相邻墩柱轮流浇筑,单根墩柱四周及中间部位预先设置多台振捣棒振捣,浇筑上层时插入式振捣器伸入到下层5~10cm,混凝土强度达到2.5MPa后,完成墩顶支座垫石混凝土人工凿毛;第八步,模板拆除、养生 ;吊车配合人工完成模板的拆除,拆除的模板分类堆放,集中清理、刷好脱模剂备下次使用;常温下模板拆除后立即洒水养护,采用塑料薄膜及透明胶带紧密缠裹覆盖,保持薄膜覆盖严密,使构件表面始终处于湿润状态; 第九步,脚手架拆除;模板拆除后拆除操作架,脚手架拆除前,对脚手架作全面检查,清除全部剩余材料,器具及杂物,拆除时划出安全区,设置警示标志。 The present invention provides a construction method for one-time pouring and forming of urban elevated curved pier columns. The construction steps are as follows: the first step, the pre-embedded main reinforcement of the pier column is positioned: the pre-embedded main reinforcement, the steel reinforcement of the cap is welded firmly, and the hoops are bound to form a rigid skeleton ; The second step is to chisel the joint part of the pier body and the cap: after the concrete strength of the cap reaches 2.5MPa, the concrete on the top surface of the cap inside the pre-embedded steel bar of the pier body is chiseled until stones are exposed on the concrete surface, and then Rinse clean; the third step is to measure and stake out; use a total station to set the vertical and horizontal axes of the pier column and the inner and outer plane contour lines of the column mold on the top surface of the platform, and the ink fountain will pop up the connection line to measure the elevation around the bottom of the pier and use it as a reinforcement binding , installation and formwork reference; the fourth step, scaffold erection; around the pier body, use Φ48mm×3.5mm bowl buckle bracket or fastener type steel pipe to set up double-row scaffolding as a working platform for pier body reinforcement installation, formwork installation and dismantling, and concrete pouring; The surroundings of the scaffolding are closed, and the foundation is placed on the bearing platform and the treated and hardened foundation. Steel pipes and fasteners are used on the inner and outer sides to set inclined bars or scissors braces according to the requirements of the specifications. The distance between the inner side of the scaffolding and the outer formwork is reserved for formwork installation, demolition and distance removal. , the working layer and the scaffolding within the width of the channel are fully paved and stable, and the railings on the peripheral platform are 1.2m higher than the uppermost working layer; Step 5, steel bar processing and installation; 1) Main steel wire head processing: main steel bar of pier body (≥Φ25mm) Connected by rolling straight thread sleeves; 2) Processing of semi-finished products: Semi-finished products are processed by classification, and the main reinforcement and stirrup of the variable section section are processed by numbering and stacked one by one; 3) Reinforcement skeleton processing of pier body: pier column reinforcement skeleton In the steel bar processing workshop, the long-line tire mold of the whole tire mold on the flat ground is used as a whole, and the fixed curve section is set by the section steel + the long-line tire mold of the steel bar skeleton of the standard section pier body with adjustable length. According to the layout of the main reinforcement of the pier body, the tire mold adopts an adjustable supporting steel frame. ;The sixth step is formwork processing and installation; before formwork installation, formwork is configured and numbered according to the height of the pier body, and the whole is pre-assembled to complete the formwork seam, wrong platform, and flatness adjustment; the pre-assembled qualified formwork reaches the local unevenness of the plate surface ≤1.0mm, the height difference between two adjacent boards is ≤1.0mm, the seam is ≤1.0mm, the overall surface flatness of the formwork is ≤3.0mm, and the paint is used as an adjustment mark after the back rib of the formwork that has passed the trial assembly; the pre-assembled acceptance is qualified The formwork is split into pieces, and the polishing machine is repeatedly polished to a bright metal color, and a uniform release agent is used to spread evenly on the surface of the formwork, slightly air-dried, and covered with a plastic film to prevent dust; the seventh step is concrete pouring; curved pier The column pier body and the tie beam concrete are integrally poured into shape, the concrete of the pier body is vibrated and compacted, and the concrete pouring string tube is reserved at the main reinforcement of the upper and lower floors where the tie beam on the top of the pier extends into the pier column, and the upper and lower passages for vibrator personnel are disconnected. The steel bars are connected by rolling straight thread sleeves, and the upper and lower layers and the adjacent steel bar joints are staggered at a distance of not less than 35d; Wooden and steel pipes are supported in a well shape on the upper opening of the formwork, and the bottom opening is no more than 2.0 meters away from the top surface of the concrete. The concrete is hoisted by a truck crane and unloaded in series. Layers are layered according to the horizontal 30cm, and adjacent pier columns are poured in turn. For construction, multiple vibrating rods are pre-installed around and in the middle of a single pier column to vibrate. When pouring the upper layer, the plug-in vibrator extends into the lower layer by 5-10cm. After the concrete strength reaches 2.5MPa, the pier top support is completed. The concrete is manually chiseled; the eighth step is to remove the formwork and maintain its health; the crane cooperates with the manual to complete the dismantling of the formwork. Use plastic film and scotch tape to tightly wrap and cover to keep the film tightly covered so that the surface of the component is always in a wet state; the ninth step is to remove the scaffolding; For the remaining materials, utensils and sundries, draw a safe area and set up warning signs when dismantling.
第一步中,对长期外露钢筋涂刷防锈水泥浆,主筋连接丝头旋入机械套筒或保护帽,整体包裹进行防锈保护。 In the first step, the long-term exposed steel bars are painted with anti-rust cement slurry, and the connecting wire ends of the main bars are screwed into mechanical sleeves or protective caps, and the whole package is protected against rust.
第六步中,模板采用吊车配合人工调整的方式进行逐块安装,底节模板通过承台预埋筋固定,模板拼装时按预拼编号顺序及标记调整到位,拼缝间采用双面胶粘贴并打磨齐平,保护层垫块与模板垂直密贴,每节段模板拼装好后检查模板的中心偏位和垂直度,紧固连接配件,模板安装完成,垂直度及中心位置检测合格后,模板顶用缆风绳配紧张器将钢模板四边呈八字形固定牢固。 In the sixth step, the formwork is installed piece by piece by means of a crane and manual adjustment. The bottom section formwork is fixed by the pre-embedded reinforcement of the cap. When the formwork is assembled, it is adjusted in place according to the sequence of pre-assembled numbers and marks. Paste and polish flush, the protective layer pads are vertically attached to the formwork, check the center deviation and verticality of the formwork after each section of the formwork is assembled, fasten the connection accessories, the formwork installation is completed, and the verticality and center position after passing the test On the top of the formwork, use cable wind ropes with tensioners to fix the four sides of the steel formwork in a figure-eight shape.
第七步中,混凝土浇筑完成后对墩顶进行一次收浆,控制表面平整度,待混凝土要初凝还未初凝时进行二次收浆,模板拆除前,墩身及系梁顶部混凝土收光后利用土工布对顶面混凝土进行覆盖蓄水养生。 In the seventh step, after the concrete pouring is completed, the grouting is performed on the top of the pier to control the flatness of the surface, and the second grouting is performed when the concrete is about to set and has not yet set. Before the formwork is removed, the concrete on the pier body and the top of the tie beam is collected After light, use geotextiles to cover the top concrete to store water and maintain health.
第八步中,高温季节,墩顶设置滴灌桶接带孔水管缠绕墩身覆膜滴淋进行养护,冬季施工,塑料薄膜缠裹后加设加厚双层土工布缠裹保温养护,并在支架内侧增加帆布覆盖,进行加热养护,确保混凝土在浇筑后的头7天不低于10℃。 In the eighth step, in the high temperature season, a drip irrigation bucket is installed on the top of the pier to connect the perforated water pipe to wrap the pier body with film and drip for maintenance. In winter construction, after the plastic film is wrapped, a thick double-layer geotextile is added to wrap it for heat preservation and maintenance. The inner side of the bracket is covered with canvas and heated for curing to ensure that the concrete is not lower than 10°C in the first 7 days after pouring.
本发明相对于现有技术具有如下有益效果:本发明提供的一种城市高架曲线式墩柱一次浇筑成型施工方法:1、质量显著提高,墩身钢筋加工、平地整体胎模长线法整体制作采取工厂标准化作业,便于质量控制与验收,现场分节拼装成整体,确保了墩身钢筋安装精度;墩身模板采用大面定型钢模板,采取体外对拉加固自稳体系,一次性拼装成整体,有利于模板拼缝、错台检查及平面位置、垂直度控制,提高了墩柱成品外观质量与几何尺寸精度,实现了成品墩身无拉杆孔;模板涂刷统一的优质脱模剂,墩柱混凝土一次性连续浇筑,确保了拆模后成品墩身无施工接缝,混凝土色泽一致。 Compared with the prior art, the present invention has the following beneficial effects: A construction method for one-time pouring and molding of urban elevated curved pier columns provided by the present invention: 1. The quality is significantly improved, and the pier body steel bar processing and the overall production of flat tire mold long-line method are adopted The standardized operation of the factory is convenient for quality control and acceptance. The site is assembled into a whole in sections to ensure the installation accuracy of the steel bars of the pier body; It is beneficial to formwork seam joints, stagger inspection, and plane position and verticality control, which improves the appearance quality and geometric accuracy of the finished pier column, and realizes that there is no tie rod hole in the finished pier body; the formwork is coated with uniform high-quality release agent, and the pier column Concrete is poured continuously at one time, which ensures that the finished pier has no construction joints after the formwork is removed, and the color of the concrete is consistent.
2、施工安全、风险小,钢筋场内加工、现场装配式安装较常规现场加工受外界影响因素少;取消了传统模板二次安装、支撑、拆除工序,提高了施工安全性。 2. The construction is safe and the risk is small. Compared with conventional on-site processing, the on-site processing and on-site assembly installation of steel bars are less affected by external factors; the secondary installation, support, and dismantling procedures of traditional formwork are cancelled, which improves construction safety.
3、工期、进度方面,墩柱钢筋骨架在场内胎模法批量制作,与承台施工平行作业,现场钢筋骨架装配式安装,墩柱模板一次性快速安装、混凝土一次性快速连续浇筑,与常规的钢筋现场散绑,钢筋、模板分两次安装,混凝土分两次浇筑相比,单座墩柱施工周期可缩短4~5天。 3. In terms of construction period and progress, the steel skeleton of the pier column is mass-produced on-site by tire mold method, and it works in parallel with the construction of the platform cap. The steel bars are loosely tied on site, the steel bars and formwork are installed in two times, and the concrete is poured in two times. Compared with the construction period of a single pier column, the construction period can be shortened by 4 to 5 days.
4、节约成本、经济效益方面,本发明提高了模板、钢管支架周转材料的使用率;减少了钢筋加工材料浪费,提高了工效,取消了常规施工二次接缝处理、脚手架作业平台搭设拆除、模板安装拆除人员、起重吊装设备的投入,实现了工序有效转换,加快了进度,减少了项目管理费用支出。 4. In terms of cost saving and economic benefits, the present invention improves the utilization rate of templates and steel pipe support turnover materials; reduces the waste of steel bar processing materials, improves work efficiency, and cancels the secondary joint treatment of conventional construction, the erection and removal of scaffolding operation platforms, The investment in formwork installation and dismantling personnel and lifting and hoisting equipment has realized the effective conversion of the process, accelerated the progress, and reduced the project management expenses.
附图说明 Description of drawings
图1为本发明的施工工艺流程图。 Fig. 1 is a construction process flow chart of the present invention.
具体实施方式 Detailed ways
下面结合附图和实施例对本发明作进一步的描述。 The present invention will be further described below in conjunction with the accompanying drawings and embodiments.
本发明提供的施工方法具有施工快捷,结构合理,经济实惠等特点,广泛适用于城市高墩桥梁,尤其是城市高墩景观桥梁。 The construction method provided by the invention has the characteristics of fast construction, reasonable structure, economic benefits, etc., and is widely applicable to urban high-pier bridges, especially urban high-pier landscape bridges.
本发明提供的施工方法的工艺原理为:墩身四周搭设钢管脚手架作为墩身钢筋骨架安装、模板安拆及混凝土浇筑作业平台,墩身钢筋骨架在工厂采用平地胎模法整体制作,现场分节安装成整体,墩身模板采用墩身曲线形式的定型钢模板分节拼装,整体一次支立,从而实现了墩身、柱间系梁混凝土一次连续浇筑成型。 The technological principle of the construction method provided by the present invention is as follows: steel pipe scaffolding is erected around the pier body as a working platform for installation of the pier body reinforcement skeleton, formwork installation and dismantling, and concrete pouring. Installed as a whole, the formwork of the pier body is assembled in sections using shaped steel formwork in the form of a pier body curve.
本发明的操作方案为:一、墩柱预埋主筋定位预埋主筋与承台钢筋焊接牢固,绑扎足够数量的箍筋形成劲性骨架,以防承台混凝土浇筑、振捣时预埋钢筋变形、移位,对长期外露钢筋涂刷防锈水泥浆,主筋连接丝头旋入机械套筒或保护帽,整体包裹进行防锈保护。 The operation plan of the present invention is: 1. The pre-embedded main reinforcement of the pier column is positioned and welded firmly with the reinforcement of the cap, and a sufficient number of stirrups are bound to form a rigid skeleton to prevent the deformation of the pre-embedded reinforcement during concrete pouring and vibration of the cap , shifting, apply rust-proof grout to the long-term exposed steel bars, screw the main bar connecting wire head into the mechanical sleeve or protective cap, and wrap the whole body for anti-rust protection.
二、墩身与承台结合部位凿毛承台混凝土强度达到2.5MPa后,对墩身预埋钢筋内侧承台顶面混凝土进行凿毛,凿至砼面有较多石子外露(新鲜砼)为止,并冲洗干净。 2. After the concrete strength of the chiseled cap at the junction of the pier body and the cap reaches 2.5 MPa, the concrete on the top surface of the cap inside the pre-embedded steel bar of the pier body shall be chiseled until more stones are exposed on the concrete surface (fresh concrete), and Rinse well.
三、测量放样 采用全站仪在承台顶面放设墩柱纵、横轴线和柱模内外平面轮廓线,墨斗弹出连线,测量出墩底四周标高,作为钢筋绑扎、安装和立模基准。 3. Measurement and setting out Use the total station to place the vertical and horizontal axes of the pier column and the contour lines of the inner and outer planes of the column formwork on the top of the platform, and the ink fountain will pop up the connection line to measure the elevation around the bottom of the pier, which will be used as the benchmark for steel bar binding, installation and formwork erection .
四、脚手架搭设墩身四周采用Φ48mm×3.5mm碗扣支架或扣件式钢管搭设双排脚手架作为墩身钢筋安装、模板安拆及混凝土浇筑时工作平台。 4. Scaffold erection Around the pier body, use Φ48mm×3.5mm bowl buckle bracket or fastener type steel pipe to set up double-row scaffolding as a working platform for pier body reinforcement installation, formwork installation and dismantling, and concrete pouring.
脚手架四周闭合,基础落于承台及处理硬化好的地基上,内外侧利用钢管及扣件按规范要求设置斜杆或剪刀撑,确保支架的整体稳定性。 The surroundings of the scaffolding are closed, and the foundation is placed on the platform cap and the treated hardened foundation. Steel pipes and fasteners are used on the inside and outside to set up inclined rods or scissors braces according to the specifications to ensure the overall stability of the scaffold.
脚手架内侧与外模之间预留模板安装、拆距除间距,作业层、通道宽度范围内脚手板铺满铺稳,外围平台栏杆比最上层作业层高1.2m。 Between the inner side of the scaffold and the outer formwork, formwork installation, demolition distance and distance are reserved, the scaffolding boards are fully paved within the working layer and the width of the channel, and the railings on the peripheral platform are 1.2m higher than the uppermost working layer.
五、钢筋加工与安装现场设立钢筋加工区,专门用于钢筋堆放与加工。 5. Steel bar processing and installation A steel bar processing area is set up on site, which is specially used for steel bar stacking and processing.
1、主筋丝头加工:墩身主筋(≥Φ25mm)采用滚扎直螺纹套筒连接,现场设置丝头加工作业平台,实现了钢筋下料、丝头加工、打磨、成品堆放、验收流水化作业。 1. Thread head processing of main reinforcement: The main reinforcement of the pier body (≥Φ25mm) is connected by a rolling straight thread sleeve, and a wire head processing operation platform is set up on site, realizing the streamlined operation of steel bar blanking, wire head processing, grinding, finished product stacking, and acceptance inspection .
2、半成品加工:半成品采用分类加工,针对变截面段主筋及箍筋因各部位尺寸不等,采取逐根编号下料加工、分类堆放。 2. Processing of semi-finished products: Semi-finished products are processed by classification. For the main reinforcement and stirrup of the variable cross-section section due to the different sizes of each part, it is processed and stacked by numbering one by one.
3、墩身钢筋骨架加工:为了保证现场墩身钢筋安装的精度及安装效率,有效解决曲线段主筋及箍筋各个方向及尺寸不等的技术难题,墩柱钢筋骨架在钢筋加工车间采用平地整体胎模长线法整体制作。 3. Processing of pier body steel bar skeleton: In order to ensure the accuracy and installation efficiency of the on-site pier body steel bar installation, and effectively solve the technical problems of different directions and sizes of the main bars and stirrups in the curved section, the pier column steel bar frame is made of flat ground in the steel bar processing workshop. The overall production of the tire mold by the long-line method.
因曲线墩柱墩身曲线段尺寸固定,现场采用型钢设置固定曲线段+长度可调的标准段墩身钢筋骨架长线胎模,根据墩身主筋布置,胎模采用可调节支撑型钢架,以适应于不同截面钢筋骨架制作及便于吊装移位。 Due to the fixed size of the curve section of the pier body, the section steel is used to set the fixed curve section + the long-line tire mold of the standard pier body reinforcement skeleton with adjustable length. It is suitable for the production of steel skeletons with different cross-sections and is convenient for lifting and shifting.
以南通市区高架引桥矩形佛手柱式墩为例,墩柱高度方向由变化的直线段+4m曲线段,直线段截面尺寸(横桥向×顺桥向)为1.6×2.0m,中墩曲线段顶端截面尺寸为2.3×2.0m,边墩曲线段顶端截面尺寸为2.3×2.5m,现场在平地上放样胎模中心线与墩身直、曲段截面轴线重合,采用[12.6槽钢按墩身直线段间隔1.5m、曲线段间隔1m设置胎膜台座(相邻台座之间采用型钢连接,以确保整体刚度),考虑到墩身曲线段截面渐变,曲线段台座一侧设置宽度可调节∟100×10的角钢与台座铰接、另一侧按墩身线形设置∟100×10的角钢与台座固结,最上层主筋支撑架设置高度可调节∟50×5的角钢与宽度可调的∟100×10的角钢铰接,同时曲线段胎架支撑型钢高度也随之渐变,胎膜两侧∟100×10角钢侧面按主筋间距焊接用于固定主筋可抽拔定位筋的定位螺母,完成4m固定曲线段+变化的直线段墩身骨架长线胎模的制作,此台架可适用于不同高度中墩、边墩钢筋骨架的制作。 Taking the rectangular bergamot-style pier of the viaduct approach bridge in Nantong City as an example, the height direction of the pier column is changed from a straight line section to a 4m curved section. The cross-sectional size of the top of the section is 2.3×2.0m, and the cross-sectional size of the top of the curved section of the side pier is 2.3×2.5m. The center line of the staked tire mold coincides with the axis of the straight and curved section of the pier body on the flat ground, and [12.6 channel steel is used to press the pier Membrane pedestals are set at intervals of 1.5m between straight sections and 1m between curved sections (adjacent pedestals are connected by section steel to ensure the overall rigidity). Considering the gradual change of the cross-section of the curved section of the pier body, the width of the pedestal on one side of the curved section can be adjusted∟ The 100×10 angle steel is hinged with the pedestal, and the other side is set according to the line of the pier body. The ∟100×10 angle steel is consolidated with the pedestal. The ×10 angle steel is hinged, and at the same time, the height of the tire frame supporting steel in the curve section is also gradually changed. The sides of the ∟100×10 angle steel on both sides of the membrane are welded according to the distance between the main ribs. The positioning nuts used to fix the main ribs and the pull-out positioning ribs are used to complete the 4m fixed curve. The production of long-line tire molds for segmental + variable straight segment pier body skeletons, this bench is suitable for the production of steel skeletons for middle piers and side piers of different heights.
墩身钢筋骨架采用分节制作,整体绑扎,首先安装可调节∟100×10与∟50×5角钢,50×5角钢与另一侧固接∟100×10角钢采用定位销连接,两侧∟100×10角钢安装主筋支撑筋,形成整体胎膜,在胎模型钢及支撑筋上按标识放置主筋,墩身主筋采用滚扎直螺纹套筒连接,同一断面的钢筋接头数量不超过断面钢筋数量的50%,相邻钢筋接头错开不小于35d的距离,曲线段各根主筋需严格按照设计位置摆放,精确调整曲线段主筋朝向并用锁母锁紧,然后分别在每节主筋顶、中及尾端上共焊接三道加劲箍筋(直径同主筋),加劲箍筋与主筋逐根点焊牢固,以保证成品钢筋骨架起吊刚度、骨架拆分及现场安装时套筒的对接精度,按照加劲筋成型法的施工流程,最后绑扎墩身箍筋,箍筋绑扎紧贴主筋,上下层网格对齐,层间距精确,制作完成钢筋骨架。 The reinforced skeleton of the pier body is made in sections and bound as a whole. Firstly, the adjustable ∟100×10 and ∟50×5 angle steels are installed, and the 50×5 angle steels are fixed to the other side. 100×10 angle steel is installed with the main reinforcement support reinforcement to form an integral membrane. Place the main reinforcement on the tire model steel and the support reinforcement according to the logo. The main reinforcement of the pier body is connected by a rolling straight thread sleeve. The number of reinforcement joints at the same section does not exceed the number of section reinforcement The joints of adjacent steel bars are staggered at a distance of not less than 35d. The main bars in the curved section must be placed in strict accordance with the design position. The orientation of the main bars in the curved section should be precisely adjusted and locked with lock nuts. A total of three stiffening stirrups (with the same diameter as the main reinforcement) are welded on the tail end, and the stiffening stirrups and the main reinforcement are spot-welded firmly one by one to ensure the lifting stiffness of the finished steel skeleton, the separation of the skeleton and the butt joint accuracy of the sleeve during on-site installation. The construction process of the reinforcement forming method is to bind the stirrups of the pier body at the end, and the stirrups are bound closely to the main reinforcement, the grids of the upper and lower layers are aligned, and the spacing between layers is accurate, and the steel skeleton is completed.
墩身钢筋骨架匹配制作完成后,在相邻两节钢筋骨架对应的钢筋上用油漆做出连接标记,进行节段编号,在分节钢筋骨架加劲箍筋处设置起吊环,确保钢筋骨架在吊装时的刚度,避免发生扭曲变形,完成两侧墩身主筋支撑的抽拔,解除一侧可活动∟100×10、∟50×5角钢与另一侧∟100×10角钢的连接,以便于分节钢筋骨架拆分起吊移位,分节钢筋骨架起吊移位至规定地点规范存放。 After the steel frame matching of the pier body is completed, paint the connection marks on the corresponding steel bars of the two adjacent steel bar frames, number the segments, and set lifting rings at the stiffening stirrups of the segmental steel bar frames to ensure that the steel bar frames can be hoisted properly. To avoid twisting and deformation, complete the drawing of the main reinforcement support of the pier body on both sides, and release the connection between the movable ∟100×10, ∟50×5 angle steel on one side and the ∟100×10 angle steel on the other side, so as to facilitate the distribution The section steel frame is disassembled, hoisted and moved, and the section steel frame is hoisted and moved to the specified place for standard storage.
钢筋骨架安装:检验合格的钢筋骨架,按前场安装顺序,采用平板运输车分节运至现场,平板运输车设置同胎膜间距相同的钢筋骨架支撑台座,以防止钢筋骨架堆放、运输时变形。 Steel frame installation: The steel frame that passes the inspection shall be transported to the site in sections according to the installation sequence of the front field, and the flat transport vehicle shall be equipped with a steel frame supporting platform with the same spacing as the tire film to prevent the steel frame from being deformed during stacking and transportation .
由吊车采用“二点起吊”的方法分节安装,吊装吊顶设置钢丝绳扁担梁与加劲箍筋吊点连接,以保证钢筋骨架垂直度,人工配合钢筋骨架准确就位。 The crane adopts the method of "two-point lifting" to install in sections, and the hoisting ceiling is set to connect the steel wire rope shoulder beam with the stiffening hoisting point to ensure the verticality of the steel frame, and the manual coordination of the steel frame is accurate.
墩柱主筋采用带锁母的滚扎直螺纹套筒与节段钢筋骨架和承台预埋标识记号的主筋对号入座,逐个连接,采用扳手将套筒和待接长钢筋连接拧紧,再将接长钢筋与套筒采用锁母锁紧,并采用力矩扳手对连接质量进行检验。 The main reinforcement of the pier column adopts a rolling straight thread sleeve with a lock nut, and the segmental reinforcement skeleton and the main reinforcement of the pre-embedded identification mark of the cap are seated in alignment, and are connected one by one. The steel bar and the sleeve are locked with a lock nut, and the connection quality is checked with a torque wrench.
为保证墩身钢筋骨架平面位置、垂直度,将墩身平面位置放样于承台上,通过掉锤测量,高度上每2-4m在脚手架上利用钢管搭设一道主筋安装外形框架形成劲性骨架对已安装钢筋骨架进行校核、保护。 In order to ensure the plane position and verticality of the steel reinforcement skeleton of the pier body, the plane position of the pier body is set out on the cap platform, and measured by dropping the hammer, a main reinforcement is erected on the scaffold every 2-4m in height using steel pipes to install the outer frame to form a rigid skeleton pair A reinforced skeleton has been installed for verification and protection.
逐节钢筋骨架安装完成后,在墩身钢筋骨架侧面绑扎与设计要求钢筋净保护层厚度相匹配的并与墩身混凝土同标号、同色泽、呈梅花型的混凝土保护层垫块。 After the installation of the section-by-section reinforcement skeleton is completed, a plum blossom-shaped concrete protection layer pad that matches the net protective layer thickness of the steel reinforcement required by the design and has the same label and color as the pier body concrete is bound on the side of the pier body reinforcement skeleton.
曲线段两侧墩身柱端设上系梁,先进行上系梁底模安装,再完成上系梁钢筋安装。 The upper tie beams are installed at the ends of the pier body columns on both sides of the curved section, and the bottom formwork of the upper tie beams is installed first, and then the reinforcement of the upper tie beams is installed.
墩柱钢筋安装后,如不能及时进行模板安装,四周应设置揽风绳进行固定并用彩条布进行包裹防污、防锈。 After the pier column reinforcement is installed, if the formwork cannot be installed in time, wind ropes should be set around to fix it and wrapped with colored strips to prevent dirt and rust.
六、模板加工、安装模板安装前根据墩身的高度配置好模板并编号,整体预先拼装,完成模板拼缝、错台、平整度调整。 6. Formwork processing and installation Before the formwork is installed, the formwork is configured and numbered according to the height of the pier body, and the whole is pre-assembled to complete the formwork seam, staggered platform, and flatness adjustment.
预拼合格的模板应达到板面局部不平≤1.0mm,相邻两板表面高低差≤1.0mm,拼缝≤1.0mm,模板整体表面平整度≤3.0mm,并在试拼合格的模板背肋后采用油漆作调整标记。 The pre-assembled qualified formwork should meet the local unevenness of the board surface ≤ 1.0mm, the height difference between the adjacent two boards ≤ 1.0mm, the seam ≤ 1.0mm, the overall surface flatness of the formwork ≤ 3.0mm, and the back rib of the qualified formwork in the trial assembly Finally, use paint as an adjustment mark.
预拼验收合格的模板拆分成块,磨光机反复打磨至金属亮色,采用统一的脱模剂,在模板表面均匀涂抹,略风干,并采用塑料薄膜覆盖防尘,防止二次污染,确保混凝土表面的镜面感。 The pre-assembled and accepted templates are split into pieces, and the polishing machine is repeatedly polished to a bright metal color. A uniform release agent is used to spread evenly on the surface of the template, and it is slightly air-dried, and covered with a plastic film to prevent dust and prevent secondary pollution. Mirror finish on concrete surface.
模板采用吊车配合人工调整的方式进行逐块安装,底节模板通过承台预埋筋固定,模板拼装时按预拼编号顺序及标记调整到位,拼缝间采用双面胶粘贴并打磨齐平,达到接缝严密,无错台,保护层垫块与模板垂直密贴,无破损,每节段模板拼装好后检查模板的中心偏位和垂直度,紧固连接配件,保证模板有足够的强度和刚度,合格后拼装下一节模板。 The formwork is installed piece by piece by means of a crane and manual adjustment. The bottom section formwork is fixed by the pre-embedded reinforcement of the cap. When the formwork is assembled, it is adjusted in place according to the pre-assembled numbering sequence and marks. The joints are pasted with double-sided adhesive and polished to be flush , to achieve tight joints, no wrong platform, and the protective layer pads are vertically attached to the formwork without damage. After the formwork of each section is assembled, check the center deviation and verticality of the formwork, and fasten the connecting parts to ensure that the formwork has sufficient space. Strength and rigidity, assemble the template for the next section after passing the test.
模板安装完成,垂直度及中心位置检测合格后,模板顶用缆风绳配紧张器将钢模板四边呈“八”字形固定牢固。 After the formwork is installed and the verticality and center position are tested to be qualified, the four sides of the steel formwork are fixed firmly in the shape of an "eight" with a cable wind rope and a tensioner on the top of the formwork.
七、混凝土浇筑曲线式墩柱墩身与系梁混凝土整体浇筑成型,因墩身钢筋密集,墩顶支座垫石钢筋网片及预埋件较多,混凝土浇筑与振捣一直是其施工难点,为确保混凝土顺利入模,墩身混凝土振捣密实,在墩顶系梁伸入墩柱的上下层主筋处预留混凝土浇筑串筒安拆,振捣人员上下通道,断开的钢筋采用滚轧直螺纹套筒连接,上下层及相邻钢筋接头错开不小于35d的距离。 7. Concrete pouring Curved pier column pier body and tie beam concrete are integrally poured into shape. Due to the dense steel reinforcement of the pier body, there are many steel mesh pieces and pre-embedded parts for the pier top support pad stone, concrete pouring and vibration have always been difficult in its construction. , in order to ensure that the concrete enters the mold smoothly, the concrete of the pier body is vibrated and compacted, and the concrete pouring string tube is reserved at the main reinforcement of the upper and lower layers of the pier top tie beam extending into the pier column for installation and disassembly. Rolled straight thread sleeve connection, the upper and lower layers and adjacent steel bar joints are staggered by a distance of not less than 35d.
振捣人员经墩顶预留人孔及爬梯至钢筋内部,接串筒浇筑混凝土,串筒采用方木、钢管成井字形支撑在模板上口,底口距离砼顶面不超过2.0米,混凝土采用汽车吊提升料斗,串筒下料,按水平30cm分层,相邻墩柱轮流浇筑,考虑到模内钢筋密集,振捣棒移位不便,单根墩柱四周及中间部位预先设置多台振捣棒振捣,一方面有利于振捣人员振捣,另一方面加快了混凝土振捣进度,避免混凝土浇筑时间长易形成冷缝,减轻了振捣人员劳动强度,振捣作业遵循“先外后内、快插慢拔、不过不欠”的原则,浇筑上层时插入式振捣器伸入到下层5-10cm,以保证全面振捣密实,应防止模板受振动器影响而发生变形或碰撞模板、钢筋、预埋件等,发现钢筋被踩踏或支撑件移位时,及时修正,严禁作业人员在钢筋上随意走动。 The vibrator goes through the reserved manhole and ladder at the top of the pier to the inside of the steel bar, and pours the concrete with the string tube. The car crane lifts the hopper, and the material is discharged in series. The layers are layered according to the horizontal 30cm, and the adjacent piers are poured in turn. Considering the dense steel bars in the mold and the inconvenience of the displacement of the vibrator, multiple vibrators are pre-installed around and in the middle of a single pier. On the one hand, it is beneficial to the vibration of the vibrator, and on the other hand, it speeds up the concrete vibration progress, avoids the formation of cold joints due to the long time of concrete pouring, and reduces the labor intensity of the vibrator. The vibrating operation follows the "first outside The principle of "back inside, fast insertion and slow extraction, but not less", when pouring the upper layer, the plug-in vibrator extends 5-10cm into the lower layer to ensure comprehensive vibration and compactness, and the formwork should be prevented from being deformed or collided by the vibrator Formwork, steel bars, embedded parts, etc., when it is found that the steel bars are trampled or the support parts are displaced, they should be corrected in time, and it is strictly forbidden for workers to walk around on the steel bars.
混凝土浇筑完成后及时对墩顶进行一次收浆,控制表面平整度,待混凝土要初凝还未初凝时进行二次收浆,防止混凝土表面出现裂纹。 After the concrete pouring is completed, the grouting on the top of the pier shall be carried out in time to control the surface flatness, and the grouting shall be carried out a second time when the concrete is about to set initially, so as to prevent cracks on the concrete surface.
模板拆除前,墩身及系梁顶部混凝土收光后立即利用土工布对顶面混凝土进行覆盖蓄水养生。 Before the formwork is removed, the concrete on the top of the pier body and the tie beam is immediately covered with geotextiles to store water and maintain its health.
混凝土强度达到2.5MPa后,完成墩顶支座垫石混凝土人工凿毛。 After the concrete strength reaches 2.5MPa, the pier top support pad stone concrete is artificially chiseled.
八、模板拆除、养生 吊车配合人工完成模板的拆除,拆除的模板分类堆放,集中清理、刷好脱模剂备下次使用。 8. Formwork removal and health preservation The crane cooperates with the manual to complete the removal of the formwork, and the dismantled formwork is sorted and piled up, cleaned up centrally, and the release agent is brushed for the next use.
常温下模板拆除后立即洒水养护,及时采用塑料薄膜及透明胶带紧密缠裹覆盖,保持薄膜覆盖严密,使构件表面始终处于湿润状态。 Immediately after the formwork is removed at room temperature, sprinkle water for maintenance, and wrap it tightly with plastic film and transparent tape in time to keep the film tightly covered so that the surface of the component is always in a wet state.
高温季节,墩顶设置滴灌桶接带孔水管缠绕墩身覆膜滴淋进行养护。 In the high temperature season, drip irrigation barrels are installed on the top of the pier to connect the perforated water pipes to wrap the pier body with film-covered dripping for maintenance.
冬季施工,塑料薄膜缠裹后加设加厚双层土工布缠裹保温养护,并在支架内侧增加帆布覆盖,进行加热养护,确保混凝土在浇筑后的头7天不低于10℃。 For winter construction, after wrapping with plastic film, add thick double-layer geotextile wrapping for heat preservation and maintenance, and add canvas covering inside the support for heating and curing to ensure that the concrete is not lower than 10°C in the first 7 days after pouring.
九、脚手架拆除模板拆除后即可拆除操作架,脚手架拆除前,对脚手架作全面检查,清除全部剩余材料,器具及杂物;拆除时划出安全区,设置警示标志,派专人看管;拆除的构配件应分类堆放,以便于运输、维护和保管。 9. The operation frame can be removed after the removal of the scaffolding template. Before the removal of the scaffolding, a comprehensive inspection of the scaffolding is carried out to remove all remaining materials, utensils and sundries; a safe area is drawn during the removal, warning signs are set, and special personnel are assigned to take care of it; Components should be classified and stacked to facilitate transportation, maintenance and storage.
本施工方案的效益分析:(一)经济效益分析1.墩身钢筋加工与现场承台施工采用平行施工,有效地实现了工序转化,提高了墩身施工的连续性和均衡性。 Benefit analysis of this construction scheme: (1) Economic benefit analysis 1. The processing of the pier body reinforcement and the construction of the on-site cap platform are carried out in parallel, which effectively realizes the transformation of the process and improves the continuity and balance of the pier body construction.
2.墩身钢筋下料、加工、整体制作采用工厂标准化作业,便于质量控制与验收,有效地提高工效、机械使用率,减少了原材料的资源浪费。 2. The blanking, processing and overall production of pier body steel bars adopt factory standardized operations, which is convenient for quality control and acceptance, effectively improves work efficiency and machine utilization rate, and reduces waste of raw material resources.
3.墩柱主筋采用直螺纹套筒机械连接,根据起吊能力,现场墩身钢筋骨架可预先分节接长,采用装配式整体安装,保证了安装质量,安装效率,减少或取消钢筋安装平台的搭设,较传统的墩身钢筋安装,现场采用钢管逐层搭设作业平台,主筋采用采用吊车配合逐根焊接接长、分层箍筋绑扎、加固工艺相比较,施工难度降低、劳动强度减轻,起重吊车使用时间大量减少,工期成倍缩短。 3. The main reinforcement of the pier column is mechanically connected with a straight thread sleeve. According to the lifting capacity, the steel skeleton of the pier body on site can be lengthened in advance in sections, and the assembly-type overall installation is adopted to ensure the installation quality and efficiency, and reduce or cancel the erection of the reinforcement installation platform. Compared with the traditional pier body steel bar installation, steel pipes are used to erect the work platform layer by layer on site, and the main bars are welded and lengthened one by one by a crane, layered stirrups are tied, and compared with the reinforcement process, the construction difficulty is reduced and the labor intensity is reduced. The use time is greatly reduced, and the construction period is doubled.
4.墩身模板优化了拼装、加固方式,提高了模板安装的精度与安装效率,墩身混凝土一次浇筑,减少了常规工程施工中二次混凝土接缝处理、钢筋梳理接长、脚手架作业平台搭设拆除、模板二次安装、支撑、拆除工序,提高了模板、钢管支架周转材料的使用率,减少了人员、起重设备、材料的投入。 4. The formwork of the pier body optimizes the assembly and reinforcement methods, which improves the accuracy and efficiency of formwork installation. The concrete of the pier body is poured at one time, which reduces the secondary concrete joint treatment, steel bar combing and lengthening, scaffolding operation platform erection and dismantling in conventional engineering construction. The secondary installation, support and dismantling process of the formwork improves the utilization rate of the turnover materials of the formwork and steel pipe support, and reduces the investment of personnel, lifting equipment and materials.
5.本发明在保证质量的前提下,有效节约工期、减少了材料浪费,提高了工效、降低了施工、管理成本,具有良好的经济效益。 5. On the premise of ensuring the quality, the invention can effectively save the construction period, reduce material waste, improve work efficiency, reduce construction and management costs, and have good economic benefits.
以单座墩柱(双柱)施工为例,较常规施工工艺相比,平均节约人工15个工日,25T汽车吊3个台班,缩短工期4-5天,提高了模板、墩身双排脚手架钢管支架周转材料的使用率,劳务、机械成本降低约8000元/座,加上工期节省带来的效益,经济效益显著。 Taking the construction of a single pier column (double column) as an example, compared with the conventional construction technology, it saves an average of 15 man-days of labor, 3 shifts of 25T truck cranes, shortens the construction period by 4-5 days, and improves the double-sided construction of formwork and pier body. The utilization rate of scaffolding steel pipe support turnover materials, labor and mechanical costs are reduced by about 8,000 yuan/seat, plus the benefits brought about by saving the construction period, the economic benefits are significant.
(二)社会效益分析曲线式墩柱较多应用于城市及区域形象要求高的项目,此类项目大多工期紧,对质量、安全、文明施工要求高,本发明在有效提升质量的前提下,提高了工业化施工程度,受环境制约因素少,施工安全风险小,在提高工效、缩短工期、节约成本以及安全文明施工方面取得了突破,具有良好的社会效益。 (2) Analysis of social benefits Curved piers are mostly used in projects with high urban and regional image requirements. Most of these projects have tight construction schedules and high requirements for quality, safety, and civilized construction. The present invention effectively improves the quality. It has improved the degree of industrialized construction, has few environmental constraints, and has low construction safety risks. It has made breakthroughs in improving work efficiency, shortening construction period, saving costs, and safe and civilized construction, which has good social benefits.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510120099.3A CN104846744B (en) | 2015-03-19 | 2015-03-19 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510120099.3A CN104846744B (en) | 2015-03-19 | 2015-03-19 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104846744A true CN104846744A (en) | 2015-08-19 |
CN104846744B CN104846744B (en) | 2017-01-11 |
Family
ID=53846703
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510120099.3A Expired - Fee Related CN104846744B (en) | 2015-03-19 | 2015-03-19 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104846744B (en) |
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677069A (en) * | 2016-12-28 | 2017-05-17 | 杭州江润科技有限公司 | Construction method for overall formwork one-time forming structure of pier |
CN107761548A (en) * | 2017-09-14 | 2018-03-06 | 中铁十九局集团第二工程有限公司 | Slope-changing hollow high pier reverse formwork construction method for passenger special line |
CN108699851A (en) * | 2018-03-30 | 2018-10-23 | 深圳市君盈建筑科技有限公司 | The prefabricated system of processing of reinforcing bar |
CN108755441A (en) * | 2018-08-07 | 2018-11-06 | 宁波交通工程建设集团有限公司 | Variable cross-section high pier overmolded structure and construction method |
CN108867398A (en) * | 2018-08-14 | 2018-11-23 | 魏浩峰 | A kind of construction method of bridge construction super-small space double limb pier stud |
CN108943375A (en) * | 2018-07-10 | 2018-12-07 | 中铁十局集团第二工程有限公司 | A kind of framework of steel reinforcement installation method |
CN109914801A (en) * | 2019-03-26 | 2019-06-21 | 南通大学 | A construction method of vertical whole body hanging board for external facade |
CN110512524A (en) * | 2019-08-16 | 2019-11-29 | 中交一公局第五工程有限公司 | A kind of bridge pier column safe construction method |
CN110593558A (en) * | 2019-09-26 | 2019-12-20 | 常州市市政建设工程有限公司 | Large-scale steel mold without pull rod for vase-type pier stud and construction process of large-scale steel mold |
CN110805206A (en) * | 2019-11-20 | 2020-02-18 | 上海宝冶建筑工程有限公司 | Stirrup construction method and device for arc-shaped shear wall hidden column |
CN111074754A (en) * | 2020-01-06 | 2020-04-28 | 中铁六局集团有限公司 | Construction method of fair-faced concrete for pier column and pier column |
CN111321673A (en) * | 2020-03-23 | 2020-06-23 | 五冶集团上海有限公司 | Bridge cylindrical pier template, assembling method and construction method of bridge cylindrical pier |
CN111677189A (en) * | 2020-06-12 | 2020-09-18 | 中电建南方建设投资有限公司 | Upright post construction method |
CN112229383A (en) * | 2020-09-29 | 2021-01-15 | 上海铁大建设工程质量检测有限公司 | Observation pier |
CN112482239A (en) * | 2020-12-17 | 2021-03-12 | 张家港保税区金港建设工程质量检测有限公司 | Double-amplitude four-cable-plane cable-stayed bridge of single-blade hyperboloid single-column tower and construction method thereof |
CN113417215A (en) * | 2021-07-06 | 2021-09-21 | 中铁二十局集团第六工程有限公司 | Bridge construction method |
CN113494052A (en) * | 2021-07-06 | 2021-10-12 | 中铁二十局集团第六工程有限公司 | Construction method of solid pier column |
CN113979683A (en) * | 2021-12-08 | 2022-01-28 | 中国华西企业股份有限公司 | Fair-faced concrete and pier forming construction method |
CN115387241A (en) * | 2022-09-30 | 2022-11-25 | 中铁九局集团第一建设有限公司 | Construction Method of Small Radius Curve Cast-in-situ Continuous Box Girder |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08232212A (en) * | 1995-02-27 | 1996-09-10 | Sumitomo Constr Co Ltd | Pier constructing method and execution method |
CN101761028A (en) * | 2010-01-13 | 2010-06-30 | 湖南大学 | Hyperbolic bridge pier and hyperbolic bridge pier and tower |
CN202466431U (en) * | 2012-03-22 | 2012-10-03 | 深圳市兴班建筑工程有限公司 | Bridge specific model vase pier construction device |
CN103410101A (en) * | 2013-08-23 | 2013-11-27 | 中南大学 | Tower crane conversion method for construction of parabola-shaped ultrahigh pier |
-
2015
- 2015-03-19 CN CN201510120099.3A patent/CN104846744B/en not_active Expired - Fee Related
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08232212A (en) * | 1995-02-27 | 1996-09-10 | Sumitomo Constr Co Ltd | Pier constructing method and execution method |
CN101761028A (en) * | 2010-01-13 | 2010-06-30 | 湖南大学 | Hyperbolic bridge pier and hyperbolic bridge pier and tower |
CN202466431U (en) * | 2012-03-22 | 2012-10-03 | 深圳市兴班建筑工程有限公司 | Bridge specific model vase pier construction device |
CN103410101A (en) * | 2013-08-23 | 2013-11-27 | 中南大学 | Tower crane conversion method for construction of parabola-shaped ultrahigh pier |
Non-Patent Citations (1)
Title |
---|
尹传斌等: "城市高架桥花瓶形柱式桥墩一次成型施工技术", 《工业建筑》 * |
Cited By (24)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106677069B (en) * | 2016-12-28 | 2018-04-06 | 杭州江润科技有限公司 | A kind of construction method of bridge pier integral formwork support one-shot forming structure |
CN106677069A (en) * | 2016-12-28 | 2017-05-17 | 杭州江润科技有限公司 | Construction method for overall formwork one-time forming structure of pier |
CN107761548A (en) * | 2017-09-14 | 2018-03-06 | 中铁十九局集团第二工程有限公司 | Slope-changing hollow high pier reverse formwork construction method for passenger special line |
CN108699851A (en) * | 2018-03-30 | 2018-10-23 | 深圳市君盈建筑科技有限公司 | The prefabricated system of processing of reinforcing bar |
CN108943375A (en) * | 2018-07-10 | 2018-12-07 | 中铁十局集团第二工程有限公司 | A kind of framework of steel reinforcement installation method |
CN108755441A (en) * | 2018-08-07 | 2018-11-06 | 宁波交通工程建设集团有限公司 | Variable cross-section high pier overmolded structure and construction method |
CN108755441B (en) * | 2018-08-07 | 2024-03-26 | 宁波交通工程建设集团有限公司 | Variable-section high pier turning structure and construction method |
CN108867398B (en) * | 2018-08-14 | 2021-02-02 | 桂林建安建设集团有限公司 | Construction method of bridge construction ultra-small-space double-limb pier stud |
CN108867398A (en) * | 2018-08-14 | 2018-11-23 | 魏浩峰 | A kind of construction method of bridge construction super-small space double limb pier stud |
CN109914801A (en) * | 2019-03-26 | 2019-06-21 | 南通大学 | A construction method of vertical whole body hanging board for external facade |
CN110512524A (en) * | 2019-08-16 | 2019-11-29 | 中交一公局第五工程有限公司 | A kind of bridge pier column safe construction method |
CN110593558A (en) * | 2019-09-26 | 2019-12-20 | 常州市市政建设工程有限公司 | Large-scale steel mold without pull rod for vase-type pier stud and construction process of large-scale steel mold |
CN110805206B (en) * | 2019-11-20 | 2021-09-17 | 上海宝冶建筑工程有限公司 | Stirrup construction method and device for arc-shaped shear wall hidden column |
CN110805206A (en) * | 2019-11-20 | 2020-02-18 | 上海宝冶建筑工程有限公司 | Stirrup construction method and device for arc-shaped shear wall hidden column |
CN111074754B (en) * | 2020-01-06 | 2021-06-29 | 中铁六局集团有限公司 | Construction method of fair-faced concrete for pier column and pier column |
CN111074754A (en) * | 2020-01-06 | 2020-04-28 | 中铁六局集团有限公司 | Construction method of fair-faced concrete for pier column and pier column |
CN111321673A (en) * | 2020-03-23 | 2020-06-23 | 五冶集团上海有限公司 | Bridge cylindrical pier template, assembling method and construction method of bridge cylindrical pier |
CN111677189A (en) * | 2020-06-12 | 2020-09-18 | 中电建南方建设投资有限公司 | Upright post construction method |
CN112229383A (en) * | 2020-09-29 | 2021-01-15 | 上海铁大建设工程质量检测有限公司 | Observation pier |
CN112482239A (en) * | 2020-12-17 | 2021-03-12 | 张家港保税区金港建设工程质量检测有限公司 | Double-amplitude four-cable-plane cable-stayed bridge of single-blade hyperboloid single-column tower and construction method thereof |
CN113417215A (en) * | 2021-07-06 | 2021-09-21 | 中铁二十局集团第六工程有限公司 | Bridge construction method |
CN113494052A (en) * | 2021-07-06 | 2021-10-12 | 中铁二十局集团第六工程有限公司 | Construction method of solid pier column |
CN113979683A (en) * | 2021-12-08 | 2022-01-28 | 中国华西企业股份有限公司 | Fair-faced concrete and pier forming construction method |
CN115387241A (en) * | 2022-09-30 | 2022-11-25 | 中铁九局集团第一建设有限公司 | Construction Method of Small Radius Curve Cast-in-situ Continuous Box Girder |
Also Published As
Publication number | Publication date |
---|---|
CN104846744B (en) | 2017-01-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104846744B (en) | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode | |
CN102747677B (en) | Bridge and construction method thereof | |
CN111946124B (en) | Method for manufacturing silo with vertical shaft structure by using section bar combined frame for silo | |
CN102505708B (en) | Construction method of tunnel at oversized cross section open cut area in track traffic | |
CN109706846B (en) | High and narrow bridge capping beam through steel bar construction method for slope foundation | |
CN110184941B (en) | Bridge main tower construction method | |
CN111287095A (en) | Special construction method for main beam of lower-towing super-large bridge | |
CN105755954B (en) | A kind of construction technology of intercommunication clear-water concrete anticollision barrier | |
CN107882321A (en) | Diameter Silo slding form operation engineering method | |
CN108638324A (en) | A kind of construction method of prefabricated case beam | |
CN103410320B (en) | The tower silo flexibility platform bitubular connects sliding construction method | |
CN104372890A (en) | Construction method of bare concrete prefabricated box beam with complicated structure | |
CN109747037A (en) | A kind of elder generation's post-tensioned prestressing combines the U-shaped beam prefabricated construction technology of large span of construction | |
CN108330835A (en) | The construction method of setting bracket | |
CN104963289A (en) | Integral one-time pouring construction method of large-volume concrete for special-shaped pier stud | |
CN103233424A (en) | Hanging-basket-method support-free anti-collision wall construction method, construction hanging basket and template for construction | |
CN110512524A (en) | A kind of bridge pier column safe construction method | |
CN104894954A (en) | Overall mounting and constructing method of pier stud reinforcing steel bars of urban bridge | |
CN108394016A (en) | Prefabricated case beam factorial construction management method | |
CN103590603A (en) | Large-span multi-curvature thin shell reinforced concrete structure construction method | |
CN103774561A (en) | Streamline operation construction method of precast small box girders for highway in assembling mode | |
CN106703407A (en) | Construction method of double-layered shape steel supporting rack of cantilever beam plate | |
CN112211113A (en) | Cast-in-place construction method for large-span diamond-shaped bent cap of high pier | |
CN110093852A (en) | Shaped form bridge pier Construction technology of fair-faced concrete | |
CN115030064A (en) | A kind of construction method of moving beam for reconstruction of high-speed railway elevated station |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
EXSB | Decision made by sipo to initiate substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
CB03 | Change of inventor or designer information |
Inventor after: Cao Hui Inventor after: Shi Yang Inventor after: Li Yuantao Inventor after: Hao Yi Inventor after: Li Jun Inventor after: Chen Chang Inventor after: Fan Peng Inventor after: Shen Qiangru Inventor after: Cheng Jun Inventor after: Yu Mingcong Inventor after: Dong Jinjun Inventor after: Yuan Yunguang Inventor before: Cao Hui Inventor before: Shen Qiangru Inventor before: Cheng Jun |
|
COR | Change of bibliographic data | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20170111 Termination date: 20180319 |