CN111074754A - Pier column bare concrete construction method and pier column - Google Patents

Pier column bare concrete construction method and pier column Download PDF

Info

Publication number
CN111074754A
CN111074754A CN202010010527.8A CN202010010527A CN111074754A CN 111074754 A CN111074754 A CN 111074754A CN 202010010527 A CN202010010527 A CN 202010010527A CN 111074754 A CN111074754 A CN 111074754A
Authority
CN
China
Prior art keywords
concrete
mold cavity
partition plate
fair
poured
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010010527.8A
Other languages
Chinese (zh)
Other versions
CN111074754B (en
Inventor
张玉奇
付建国
王玉飞
张晓东
揭振兴
郭慧栋
王程
杜泽鸿
张慧波
杨军
邓理想
马永丽
戴公强
白鹏鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Sixth Group Co Ltd
Traffic Engineering Branch of China Railway Sixth Group Co Ltd
Original Assignee
China Railway Sixth Group Co Ltd
Traffic Engineering Branch of China Railway Sixth Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Sixth Group Co Ltd, Traffic Engineering Branch of China Railway Sixth Group Co Ltd filed Critical China Railway Sixth Group Co Ltd
Priority to CN202010010527.8A priority Critical patent/CN111074754B/en
Publication of CN111074754A publication Critical patent/CN111074754A/en
Application granted granted Critical
Publication of CN111074754B publication Critical patent/CN111074754B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a pier stud fair-faced concrete construction method and a pier stud, and belongs to the field of pier stud construction. The pier stud fair-faced concrete construction method comprises the following steps: erecting embedded steel bars, and erecting a steel bar framework at the position of the pier stud; installing templates, namely assembling the templates on the periphery of the steel reinforcement framework to form a mold cavity; pouring concrete, namely pouring first concrete and second concrete in the mold cavity at the same time, wherein the first concrete is poured on the edge part of the mold cavity close to the inner wall of the template, the second concrete is poured on the middle part inside the mold cavity, the first concrete and the second concrete are respectively fair-faced concrete, and the water cement ratio of the first concrete is greater than that of the second concrete; vibrating concrete, namely vibrating the first concrete and the second concrete poured in the die cavity respectively; removing the template, namely removing the template after the concrete in the mold cavity is cured; and (5) concrete curing. The pier column manufactured by the pier column fair-faced concrete construction method is higher in strength and better in surface quality.

Description

Pier column bare concrete construction method and pier column
Technical Field
The invention belongs to the technical field of pier stud construction, and particularly relates to a pier stud fair-faced concrete construction method and a pier stud.
Background
The bare concrete is the concrete which is formed by one-step pouring, does not have any external decoration and directly adopts the natural color of cast-in-place concrete as a decorative surface. The urban subway overhead pier has high requirement on the strength of the pier, the clear water concrete pier is manufactured by taking the strength and the surface quality into consideration, the traditional pier construction method is adopted for construction, the strength requirement of the pier can be guaranteed, but the surface of the pier is easy to have defects, and the surface requirement of the clear water concrete is difficult to achieve.
Disclosure of Invention
The invention aims to provide a pier stud fair-faced concrete construction method and a pier stud, and aims to solve the technical problem that although the strength requirement of the pier stud can be ensured by a traditional pier stud construction method in the prior art, the surface of the pier stud is difficult to meet the surface requirement of fair-faced concrete.
In order to achieve the purpose, the technical scheme adopted by the invention is to provide a pier stud fair-faced concrete construction method, which comprises the following steps:
erecting embedded steel bars, and erecting a steel bar framework at the position of the pier stud;
installing templates, namely assembling the templates on the periphery of the steel reinforcement framework to form a mold cavity;
pouring concrete, namely pouring first concrete and second concrete in the die cavity simultaneously, wherein the first concrete is poured on the edge part of the die cavity close to the inner wall of the template, the second concrete is poured on the middle part inside the die cavity, the first concrete and the second concrete are respectively fair-faced concrete, and the water cement ratio of the first concrete is greater than that of the second concrete;
vibrating the concrete, namely vibrating the first concrete and the second concrete poured in the die cavity respectively;
removing the template, namely removing the template after the concrete in the mold cavity is cured;
and (5) concrete curing.
As another embodiment of the present application, during said concrete casting, a partition plate is placed inside said mould cavity to divide said mould cavity into a middle portion and an annular edge portion;
removing said divider plate from the concrete poured in the mold cavity after said first concrete and said second concrete are poured and prior to said concrete being vibrated.
As another embodiment of the present application, the partition plate includes a first annular partition plate and a second annular partition plate, and an inscribed circle diameter of the first annular partition plate is smaller than an inscribed circle diameter of the second annular partition plate;
during said concrete casting, placing a divider plate within said mold cavity to divide said mold cavity into a central portion and an annular rim portion, comprising:
placing the first annular partition plate in the mold cavity, dividing the mold cavity into a middle part and an annular edge part, pouring first concrete on the edge part of the mold cavity, and pouring second concrete on the middle part of the mold cavity;
and taking the first annular partition plate out of the poured concrete, putting the second annular partition plate on the first concrete poured in the mold cavity, dividing the mold cavity into a middle part and an annular edge part, continuously pouring the first concrete on the edge part of the mold cavity, and continuously pouring the second concrete on the middle part of the mold cavity.
As another embodiment of the present application, in the concrete vibrating process, the second concrete in the mold cavity is vibrated first, and then the first concrete in the mold cavity is vibrated.
As another embodiment of the present application, when vibrating the second concrete in the mold cavity, a vibrating rod is vertically inserted from top to bottom to vibrate;
when the first concrete in the die cavity is vibrated, a vibrating rod is adopted to vibrate from top to bottom and from the first concrete to the second concrete in an inclined insertion mode.
As another embodiment of the present application, the partition plate includes a first annular partition plate and a second annular partition plate, and an inscribed circle diameter of the first annular partition plate is smaller than an inscribed circle diameter of the second annular partition plate;
during said concrete casting, placing a divider plate within said mold cavity to divide said mold cavity into a central portion and an annular rim portion, comprising:
placing the second annular partition plate in the mold cavity to divide the mold cavity into a middle part and an annular edge part, and then pouring first concrete on the edge part of the mold cavity and pouring second concrete on the middle part of the mold cavity;
and taking the second annular clapboard out of the poured concrete, putting the first annular clapboard on the second concrete poured in the mold cavity, continuously pouring the first concrete at the edge part of the mold cavity, and continuously pouring the second concrete at the middle part of the mold cavity.
As another embodiment of the present application, in the concrete vibrating process, the first concrete in the mold cavity is vibrated first, and then the second concrete in the mold cavity is vibrated.
As another embodiment of the present application, when vibrating the first concrete in the mold cavity, a vibrating rod is vertically inserted from top to bottom to vibrate;
when the second concrete in the die cavity is vibrated, a vibrating rod is adopted to vibrate from top to bottom and to insert the second concrete into the first concrete in an inclined manner.
As another embodiment of the present application, the first concrete and the second concrete are the same in the kinds and mixing ratios of cement, coarse aggregate, fine aggregate, admixture and admixture.
The pier stud fair-faced concrete construction method provided by the embodiment of the invention has the beneficial effects that: compared with the prior art, the pier stud fair-faced concrete construction method provided by the embodiment of the invention has the advantages that the first concrete with larger water cement ratio is poured at the edge part of the die cavity, so that the first concrete has stronger fluidity, and the first concrete can form a high-quality surface. And the water cement ratio of the second concrete is smaller, so that the strength of the pier is ensured.
The invention adopts another technical scheme that the pier column is manufactured by adopting any one of the pier column fair-faced concrete construction methods.
The pier column provided by the embodiment of the invention has the beneficial effects that: compared with the prior art, the pier stud of the embodiment of the invention has higher strength and better surface quality by adopting the method.
Drawings
In order to more clearly illustrate the technical solutions in the embodiments of the present invention, the drawings needed to be used in the embodiments or the prior art descriptions will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments of the present invention, and it is obvious for those skilled in the art to obtain other drawings based on these drawings without inventive exercise.
Fig. 1 is a flow chart of a pier stud fair-faced concrete construction method according to an embodiment of the invention;
FIG. 2 is a schematic construction structure diagram of the pier stud fair-faced concrete construction method provided by the embodiment of the invention;
FIG. 3 is a top view of FIG. 2;
fig. 4 is a schematic view of a construction structure constructed by using the pier stud fair-faced concrete construction method according to another embodiment of the present invention.
Wherein, in the figures, the respective reference numerals:
1-template; 2-a first annular partition; 3-first concrete; 4-second concrete; 5-second annular partition.
Detailed Description
In order to make the technical problems, technical solutions and advantageous effects to be solved by the present invention more clearly apparent, the present invention is further described in detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Referring to fig. 1 to 4 together, a method for constructing bare concrete for a pier stud according to an embodiment of the present invention will now be described. A pier stud fair-faced concrete construction method comprises the following steps:
s100, erecting embedded steel bars, and erecting a steel bar framework at the position of a pier stud;
step S200, installing a template 1, and assembling the template 1 on the periphery of the steel reinforcement framework to form a mold cavity;
step S300, pouring concrete, namely pouring first concrete 3 and second concrete 4 in the mold cavity at the same time, wherein the first concrete 3 is poured at the edge part of the mold cavity close to the inner wall of the template 1, the second concrete 4 is poured at the middle part inside the mold cavity, the first concrete 3 and the second concrete 4 are respectively fair-faced concrete, and the water cement ratio of the first concrete 3 is greater than that of the second concrete 4;
step S400, vibrating concrete, namely vibrating the first concrete 3 and the second concrete 4 poured in the die cavity respectively;
step S500, the template 1 is removed, and the template 1 is removed after the concrete in the cavity of the template is cured;
and S600, curing the concrete.
Compared with the prior art, the pier stud fair-faced concrete construction method provided by the embodiment of the invention has the advantages that the first concrete 3 with larger water cement ratio is poured at the edge part of the die cavity, so that the first concrete 3 has stronger fluidity, and the first concrete 3 can form a high-quality surface. And the water cement of the second concrete 4 is smaller, so that the strength of the pier is ensured.
In this embodiment, in the step S100 of erecting the embedded steel bars, the steel bars in the transverse direction and the longitudinal direction are bound into the steel bar framework according to the three-dimensional shape of the pier stud to be manufactured, and the steel bar framework cannot protrude out of the surface of the pier stud.
In the step S200 of installing the formwork 1, the formwork 1 must be pre-assembled, inspected, checked for acceptance, checked for joints, flatness, slab staggering, positioning pins, anchoring, etc., before being used in a construction site, so as to ensure the surface quality of the pier stud. The surface of the template 1 is brushed with template 1 paint as a release agent. After the template 1 is painted once, the template 1 can be poured and used for three times, and then the template 1 is needed to be painted again.
In the concrete casting in step S300, the first concrete 3 is selected from portland cement (portland cement having a compressive strength of 42.5 MPa) having a strength grade of P · O42.5 or more. The cement is preferably made by the same manufacturer, the same variety, the same batch and the same strength grade. The aggregate of the first concrete 3 is non-alkali active aggregate. The coarse aggregate has good continuous gradation, uniform and clean color, the mud content is less than 0.7 percent, the mud block content is less than 0.3 percent, and the needle-shaped particles are less than or equal to 10 percent. The fine aggregate is river sand with good continuous gradation, the fineness modulus is 2.3-2.9, the mud content is less than or equal to 1.0%, and the mud block content is less than or equal to 0.5%. Coarse and fine aggregates are required to be stored in separate bins, each batch of aggregates are detected, and the aggregates are put into the bins after meeting the requirements, so that special bin supply is realized, the aggregates are ensured to meet the requirements, and the color and luster are consistent. The admixture of the first concrete 3 is harmless to concrete and reinforcing steel bars, the mixture has good workability, and the admixtures used in the same project are from the same manufacturer and the same variety. The admixture selects I-grade fly ash, the mixing amount is determined through tests, and the quality and the application technology meet the current national standard and the regulations related to environmental protection. The commercial concrete station of the first concrete 3 needs to be provided with an independent cement tank for storage, and can only be used at the clear water concrete structure part, each batch of tank-entering cement is subjected to index detection before entering the tank, and the tank-entering cement is stored after meeting the requirements until the batch of cement is used up, and the cement is detected again, so that the stable quality of the cement in the construction process is ensured. The requirements of the second concrete 4 for cement, aggregate, admixtures may be the same as the first concrete 3.
The first concrete 3 can be prepared from 400kg/m3 of a cementing material, 0.41 of water-cement ratio, 16% of single-doped fly ash, 42% of sand content, 5-20 mm of broken stone continuous gradation and 10-20 mm of large stone: small stone (5-10 mm) ═ 3: 1, adopting a Subot polycarboxylic acid high-performance water reducing agent as an additive, designing slump (160 +/-20) mm, adjusting according to actual conditions during construction, selecting an optimal concrete mixing ratio, and pumping concrete.
The water-cement ratio of the second concrete 4 is slightly smaller than that of the first concrete 3, for example, the cement material is 400kg/m3, the water-cement ratio is 0.36, the single-doped fly ash is 16%, the sand content is 42%, the broken stone is 5-20 mm continuous gradation, and the large stone (10-20 mm): small stone (5-10 mm) ═ 3: 1, adopting a Subot polycarboxylic acid high-performance water reducing agent as an additive, designing slump (160 +/-20) mm, adjusting according to actual conditions during construction, selecting an optimal concrete mixing ratio, and pumping concrete. The water cement ratio of the first concrete 3 and the second concrete 4 is determined according to actual conditions, and the difference between the water cement ratio of the first concrete 3 and the water cement ratio of the second concrete 4 is not suitable to be too large.
Specifically, the first concrete cement: mineral powder: fly ash: large stones: small stones: sand: water: 280 parts of admixture: 60: 60: 782: 260: 754: 161: 3.2. and concrete cement in the second concrete: mineral powder: fly ash: large stones: small stones: sand: water: additive 314: 67: 67: 782: 260: 754: 161: 3.6.
in the concrete pouring of step S300, temperature measuring lines may be buried inside and on the surface of the first concrete 3 and the second concrete 4, and the temperature measuring lines are arranged at three different heights, i.e., upper, middle and lower. The ambient temperature and humidity were measured every 30min and a record was formed. And measuring the surface temperature of the concrete after the form is removed, wherein each surface is not less than 5 points. And measuring the concrete mold-entering temperature at not less than 10 points.
In the concrete vibrating step S400, the first concrete 3 and the second concrete 4 in the mold cavity may be vibrated in a conventional vibrating manner. The steps of dismantling the formwork 1 of the step S500 and curing the concrete of the step S600 may be the same as the conventional pier construction process.
Referring to fig. 2 to 4, as an embodiment of the method for constructing bare concrete for a pier stud according to the present invention, in the step S300 of pouring concrete, a partition plate is placed in a mold cavity to partition the mold cavity into a middle portion and an annular edge portion;
after the first concrete 3 and the second concrete 4 are cast and before the concrete is vibrated, the partition plate is taken out of the concrete cast in the mold cavity.
In this embodiment, the annular shape of the divider plate is similar to the cross-sectional profile of the pier, with dimensions less than the cross-sectional profile of the pier. For example, the cross-sectional profile of the pier is generally rectangular and the corresponding divider plate is generally rectangular and annular, the length of the divider plate being less than the length of the cross-sectional profile of the pier and the width of the divider plate being less than the width of the cross-sectional profile of the pier.
In this embodiment, the partition plate is placed in the mold cavity to divide the mold cavity into a middle portion and an annular edge portion, and the partition plate may be placed in the middle of the mold cavity so that the edge portion of the mold cavity is in an annular shape surrounding the periphery of the middle portion. When pouring, a plurality of concrete pumps can be adopted to respectively pour concrete to different positions of the edge part of the die cavity.
After the first concrete 3 and the second concrete 4 are poured and before the concrete is vibrated, the partition plate is taken out from the poured concrete in the mold cavity, so that the influence of the partition plate on vibration can be avoided.
Referring to fig. 2 and 3, as an embodiment of the method for constructing dry concrete for a pier stud according to the present invention, the partition plate includes a first annular partition plate 2 and a second annular partition plate 5, and the diameter of the inscribed circle of the first annular partition plate 2 is smaller than the diameter of the inscribed circle of the second annular partition plate 5.
In the concrete casting process of step S300, placing a partition plate in the mold cavity to divide the mold cavity into a middle portion and an annular edge portion, including:
placing a first annular clapboard 2 in a mold cavity, dividing the mold cavity into a middle part and an annular edge part, pouring first concrete 3 on the edge part of the mold cavity, and pouring second concrete 4 on the middle part of the mold cavity;
the first annular partition 2 is removed from the poured concrete, the second annular partition 5 is placed over the first concrete 3 poured in the mould cavity, the mould cavity is divided into a middle part and an annular edge part, the first concrete 3 continues to be poured in the edge part of the mould cavity, and the second concrete 4 continues to be poured in the middle part of the mould cavity.
In this embodiment, a plurality of partition plates having different inscribed circle diameters may be used, and the shape of each partition plate is the same.
The first annular partition plate 2 may be placed in the lower portion of the mold cavity to divide the mold cavity into an edge portion and a middle portion, and then the first concrete 3 and the second concrete 4 may be poured separately. After the lower part of the mold cavity is poured, the first annular partition plate 2 is taken out, then the second annular partition plate 5 is placed on the first concrete 3 poured in the mold cavity, the mold cavity is divided into an edge part and a middle part by the partition plate again, and then the first concrete 3 and the second concrete 4 are continuously poured on the poured concrete, so that the thickness of the first concrete 3 in the mold cavity is gradually increased from bottom to top, and the problem that the surface quality of the pier column is influenced because the second concrete 4 on the upper part of the mold cavity flows onto the inner wall of the mold plate 1 after the two partition plates are taken out is avoided to the greatest extent.
Referring to fig. 2 and 3, as a specific embodiment of the method for constructing bare concrete for a pier stud according to the present invention, in the step S400 of vibrating the concrete, the second concrete 4 in the mold cavity is vibrated first, and then the first concrete 3 in the mold cavity is vibrated. By the method, the second concrete 4 on the upper part of the die cavity can be prevented from flowing onto the inner wall of the die plate 1, and the surface quality of the pier stud is prevented from being influenced.
In the embodiment, the concrete is poured and tamped in layers, 12 high-frequency vibrating rods with the thickness of 50mm are adopted to sink to the bottom in advance, the vibrating operation of 'fast inserting and slow pulling' is unified, the distance between an inserting point and the inner wall of the formwork 1 is kept at 10cm, the distance between action points is 30-45 cm, the vibrating rods are lifted by about 30cm each time, the condition that the lower-layer concrete surface is not pulled by 10cm is suitable, the corresponding positions of the vibrating rods can be marked by significant objects such as double faced adhesive tapes in advance, and the vibrating time is about 25-35 s each time. The vibration time is controlled, and the points of the first concrete 3 towards the outside from the middle second concrete 4 are distributed. In order to facilitate the vibration of the concrete of the pier body, the reinforcing mesh at the top of the pier column can be placed when the concrete is poured to the position near the top of the pier column. The height of each pouring is not more than 30cm, the concrete is required to be vibrated uniformly, the leakage vibration and the over vibration are not required, the deep insertion and the light lifting are realized, the fast insertion and the slow pulling are realized, the vibration time is properly controlled, and more than 10cm of each layer needs to be inserted for connection.
Referring to fig. 2 and 3, as a specific embodiment of the method for constructing bare concrete for a pier stud according to the present invention, when vibrating the second concrete 4 in the mold cavity, a vibrating rod is vertically inserted from top to bottom to vibrate;
when the first concrete 3 in the die cavity is vibrated, the vibrating rod is adopted to vibrate from top to bottom and from the first concrete 3 to the oblique insertion of the second concrete 4. By adopting the method, the junction of the first concrete 3 and the second concrete 4 can form certain mixing, the overlarge difference between the two is avoided, the stress is generated, and the two are prevented from being separated.
In this embodiment, when the first concrete 3 in the mold cavity is vibrated, the included angle between the vibrating rod and the vertical direction is 5 degrees to 10 degrees.
Referring to fig. 4, as an embodiment of the method for constructing dry concrete for a pier stud according to the present invention, the partition plate includes a first annular partition plate 2 and a second annular partition plate 5, and the diameter of the inscribed circle of the first annular partition plate 2 is smaller than the diameter of the inscribed circle of the second annular partition plate 5.
In the concrete casting process of step S300, placing a partition plate in the mold cavity to divide the mold cavity into a middle portion and an annular edge portion, including:
placing a second annular clapboard 5 in the mold cavity to divide the mold cavity into a middle part and an annular edge part, then pouring first concrete 3 on the edge part of the mold cavity, and pouring second concrete 4 on the middle part of the mold cavity;
the second annular partition 5 is removed from the poured concrete, the first annular partition 2 is then placed over the second concrete 4 poured in the mould cavity, the first concrete 3 continues to be poured in the edge portion of the mould cavity and the second concrete 4 continues to be poured in the middle portion of the mould cavity.
In this embodiment, a plurality of partition plates having different inscribed circle diameters may be used, and the shape of each partition plate is the same.
It is possible to place a second annular partition 5 in the lower part of the mold cavity to divide the mold cavity into an edge part and a middle part and then to pour the first concrete 3 and the second concrete 4, respectively. After the lower part of the mold cavity is poured, the second annular partition plate 5 is taken out, the first annular partition plate 2 is placed on the first concrete 3 poured in the mold cavity, the mold cavity is divided into the edge part and the middle part by the partition plate again, and then the first concrete 3 and the second concrete 4 are continuously poured on the poured concrete, so that the thickness of the first concrete 3 in the mold cavity is gradually reduced from bottom to top, and the problem that the surface quality of the pier column is influenced because the second concrete 4 at the lower part of the mold cavity flows onto the inner wall of the mold plate 1 after the two partition plates are taken out is avoided to the greatest extent.
Referring to fig. 4, as a specific embodiment of the method for constructing bare concrete for a pier stud according to the present invention, in the step S400 of vibrating the concrete, the first concrete 3 in the mold cavity is vibrated first, and then the second concrete 4 in the mold cavity is vibrated. This kind of mode can avoid the second concrete 4 of die cavity lower part to flow on 1 inner wall of template, influence the surface quality of pier stud.
In this embodiment, in the concrete is poured and tamped in layers, 12 high-frequency vibrating rods with the diameter of 50mm are adopted to sink to the bottom in advance, the vibrating rods are uniformly 'quickly inserted and slowly pulled out', the distance between an insertion point and the inner wall of the formwork 1 is kept at 10cm, the distance between action points is 30-45 cm, the vibrating rods are lifted by about 30cm each time, preferably 10cm of the lower concrete surface is not pulled out, the concrete can be marked by significant objects such as double-sided adhesive tapes at corresponding positions of the vibrating rods in advance, and the vibrating time is about 25-35 s each time. The time of each vibration is controlled, and the points of the second concrete 4 facing the outside from the middle first concrete 3 are distributed. In order to facilitate the vibration of the concrete of the pier body, the reinforcing mesh at the top of the pier column can be placed when the concrete is poured to the position near the top of the pier column. The height of each pouring is not more than 30cm, the concrete is required to be vibrated uniformly, the leakage vibration and the over vibration are not required, the deep insertion and the light lifting are realized, the fast insertion and the slow pulling are realized, the vibration time is properly controlled, and more than 10cm of each layer needs to be inserted for connection.
Referring to fig. 4, as a specific embodiment of the method for constructing bare concrete for a pier stud according to the present invention, when vibrating the first concrete 3 in the mold cavity, a vibrating rod is vertically inserted from top to bottom to vibrate;
when the second concrete 4 in the die cavity is vibrated, the vibrating rod is adopted to vibrate from top to bottom and from the second concrete 4 to the oblique insertion of the first concrete 3. By adopting the method, the junction of the first concrete 3 and the second concrete 4 can form certain mixing, the overlarge difference between the two is avoided, the stress is generated, and the two are prevented from being separated.
In this embodiment, when the second concrete 4 in the mold cavity is vibrated, the included angle between the vibrating rod and the vertical direction is 5 degrees to 10 degrees.
Referring to fig. 2 to 4, as an embodiment of the method for constructing bare concrete for a pier stud according to the present invention, the first concrete 3 and the second concrete 4 have the same kind and mixing ratio of cement, coarse aggregate, fine aggregate, admixture, and admixture. The first concrete 3 and the second concrete 4 have basically the same components except different cement-water ratios, and the difference between the first concrete and the second concrete is not too large.
In this embodiment, the cement of the first concrete 3 and the cement of the second concrete 4 are products of the same manufacturer, the same variety, the same batch, and the same strength grade. The coarse aggregate and the fine aggregate adopted by the first concrete 3 and the second concrete 4 are the same, and the same product in the same production place is adopted.
The embodiment of the invention also provides the pier stud, which is manufactured by adopting any one of the pier stud fair-faced concrete construction methods.
Compared with the prior art, the pier stud of the embodiment of the invention has higher strength and better surface quality by adopting the method.
The present invention is not limited to the above preferred embodiments, and any modifications, equivalent substitutions and improvements made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (10)

1. The pier stud fair-faced concrete construction method is characterized by comprising the following steps:
erecting embedded steel bars, and erecting a steel bar framework at the position of the pier stud;
installing templates, namely assembling the templates on the periphery of the steel reinforcement framework to form a mold cavity;
pouring concrete, namely pouring first concrete and second concrete in the die cavity simultaneously, wherein the first concrete is poured on the edge part of the die cavity close to the inner wall of the template, the second concrete is poured on the middle part inside the die cavity, the first concrete and the second concrete are respectively fair-faced concrete, and the water cement ratio of the first concrete is greater than that of the second concrete;
vibrating the concrete, namely vibrating the first concrete and the second concrete poured in the die cavity respectively;
removing the template, namely removing the template after the concrete in the mold cavity is cured;
and (5) concrete curing.
2. The pier fair-faced concrete construction method according to claim 1, wherein a partition plate is placed in the cavity to divide the cavity into a middle portion and an annular edge portion during the concrete pouring process;
removing said divider plate from the concrete poured in the mold cavity after said first concrete and said second concrete are poured and prior to said concrete being vibrated.
3. The pier column fair-faced concrete construction method according to claim 2, wherein the partition plate comprises a first annular partition plate and a second annular partition plate, and the diameter of an inscribed circle of the first annular partition plate is smaller than that of the inscribed circle of the second annular partition plate;
during said concrete casting, placing a divider plate within said mold cavity to divide said mold cavity into a central portion and an annular rim portion, comprising:
placing the first annular partition plate in the mold cavity, dividing the mold cavity into a middle part and an annular edge part, pouring first concrete on the edge part of the mold cavity, and pouring second concrete on the middle part of the mold cavity;
and taking the first annular partition plate out of the poured concrete, putting the second annular partition plate on the first concrete poured in the mold cavity, dividing the mold cavity into a middle part and an annular edge part, continuously pouring the first concrete on the edge part of the mold cavity, and continuously pouring the second concrete on the middle part of the mold cavity.
4. The pier stud fair-faced concrete construction method according to claim 3, wherein in the concrete vibrating process, the second concrete in the mold cavity is vibrated first, and then the first concrete in the mold cavity is vibrated.
5. The pier fair-faced concrete construction method according to claim 4, wherein when the second concrete in the mold cavity is vibrated, a vibrating rod is vertically inserted from top to bottom to vibrate;
when the first concrete in the die cavity is vibrated, a vibrating rod is adopted to vibrate from top to bottom and from the first concrete to the second concrete in an inclined insertion mode.
6. The pier column fair-faced concrete construction method according to claim 2, wherein the partition plate comprises a first annular partition plate and a second annular partition plate, and the diameter of an inscribed circle of the first annular partition plate is smaller than that of the inscribed circle of the second annular partition plate;
during said concrete casting, placing a divider plate within said mold cavity to divide said mold cavity into a central portion and an annular rim portion, comprising:
placing the second annular partition plate in the mold cavity to divide the mold cavity into a middle part and an annular edge part, and then pouring first concrete on the edge part of the mold cavity and pouring second concrete on the middle part of the mold cavity;
and taking the second annular clapboard out of the poured concrete, putting the first annular clapboard on the second concrete poured in the mold cavity, continuously pouring the first concrete at the edge part of the mold cavity, and continuously pouring the second concrete at the middle part of the mold cavity.
7. The pier stud fair-faced concrete construction method according to claim 6, wherein in the concrete vibrating process, the first concrete in the mold cavity is vibrated first, and then the second concrete in the mold cavity is vibrated.
8. The pier fair-faced concrete construction method according to claim 7, wherein when vibrating the first concrete in the mold cavity, a vibrating rod is vertically inserted from top to bottom for vibrating;
when the second concrete in the die cavity is vibrated, a vibrating rod is adopted to vibrate from top to bottom and to insert the second concrete into the first concrete in an inclined manner.
9. The pier stud fair-faced concrete construction method according to any one of claims 1 to 8, wherein the kinds and the mixing ratios of the cement, the coarse aggregate, the fine aggregate, the admixture and the admixture of the first concrete and the second concrete are the same.
10. The pier stud, characterized in that, adopt the pier stud fair-faced concrete construction method of any claim 1 to 9 to make.
CN202010010527.8A 2020-01-06 2020-01-06 Pier column bare concrete construction method and pier column Active CN111074754B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010010527.8A CN111074754B (en) 2020-01-06 2020-01-06 Pier column bare concrete construction method and pier column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010010527.8A CN111074754B (en) 2020-01-06 2020-01-06 Pier column bare concrete construction method and pier column

Publications (2)

Publication Number Publication Date
CN111074754A true CN111074754A (en) 2020-04-28
CN111074754B CN111074754B (en) 2021-06-29

Family

ID=70322225

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010010527.8A Active CN111074754B (en) 2020-01-06 2020-01-06 Pier column bare concrete construction method and pier column

Country Status (1)

Country Link
CN (1) CN111074754B (en)

Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010013803A (en) * 2008-07-01 2010-01-21 Tokura Construction Co Ltd Concrete curing system
JP2010265734A (en) * 2009-05-18 2010-11-25 Goei Seisakusho:Kk Re-repairing method for fair faced concrete finish face
US8936411B1 (en) * 2013-09-12 2015-01-20 Lithocrete, Inc. Architectural concrete
JP2015140597A (en) * 2014-01-29 2015-08-03 前田建設工業株式会社 Construction method for concrete structure
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
JP2016156248A (en) * 2015-02-26 2016-09-01 鹿島建設株式会社 Concrete structure construction method and concrete structure
CN107060340A (en) * 2017-03-20 2017-08-18 郑州航空工业管理学院 A kind of construction technology of Machine-made Sand clear-water concrete
US20170275893A1 (en) * 2013-08-20 2017-09-28 Shaw & Sons, Inc. Architectural concrete and method of forming the same
CN107447646A (en) * 2017-06-28 2017-12-08 扬州大学 A kind of steel continuous fiber composite reinforcing ECC concrete combined column/bridge pier and preparation method thereof
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN107881902A (en) * 2017-10-16 2018-04-06 中国水利水电第四工程局有限公司 Concrete construction method and mirror surface concrete pier stud
CN108424088A (en) * 2018-06-01 2018-08-21 成都交投建筑工业化有限公司 Self-compaction clear-water concrete and its construction method for bridge prefabrication pier stud
JP2018159205A (en) * 2017-03-22 2018-10-11 株式会社奥村組 Sprayed mortar for reinforcement
CN108999094A (en) * 2018-10-17 2018-12-14 中铁六局集团广州工程有限公司 Bridge pier conservation layer and bridge pier pier shaft insured's cloth conserve engineering method
CN110093852A (en) * 2019-05-15 2019-08-06 平煤神马建工集团有限公司 Shaped form bridge pier Construction technology of fair-faced concrete
CN110107089A (en) * 2019-05-15 2019-08-09 平煤神马建工集团有限公司 Municipal works clear-water concrete casting construction method
CN110107085A (en) * 2019-05-10 2019-08-09 中铁六局集团有限公司 Superelevation fair-faced concrete column construction method
CN209509496U (en) * 2019-01-12 2019-10-18 中国建筑第二工程局有限公司 Construction template for manufacturing seamless clear water concrete decorative column
CN110424268A (en) * 2019-07-30 2019-11-08 中铁上海工程局集团有限公司 A kind of main bridge hollow pier structure construction technique

Patent Citations (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010013803A (en) * 2008-07-01 2010-01-21 Tokura Construction Co Ltd Concrete curing system
JP2010265734A (en) * 2009-05-18 2010-11-25 Goei Seisakusho:Kk Re-repairing method for fair faced concrete finish face
US20170275893A1 (en) * 2013-08-20 2017-09-28 Shaw & Sons, Inc. Architectural concrete and method of forming the same
US8936411B1 (en) * 2013-09-12 2015-01-20 Lithocrete, Inc. Architectural concrete
JP2015140597A (en) * 2014-01-29 2015-08-03 前田建設工業株式会社 Construction method for concrete structure
JP2016156248A (en) * 2015-02-26 2016-09-01 鹿島建設株式会社 Concrete structure construction method and concrete structure
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN107060340A (en) * 2017-03-20 2017-08-18 郑州航空工业管理学院 A kind of construction technology of Machine-made Sand clear-water concrete
JP2018159205A (en) * 2017-03-22 2018-10-11 株式会社奥村組 Sprayed mortar for reinforcement
CN107447646A (en) * 2017-06-28 2017-12-08 扬州大学 A kind of steel continuous fiber composite reinforcing ECC concrete combined column/bridge pier and preparation method thereof
CN107700358A (en) * 2017-09-18 2018-02-16 王卫星 The construction method of track traffic pier stud
CN107881902A (en) * 2017-10-16 2018-04-06 中国水利水电第四工程局有限公司 Concrete construction method and mirror surface concrete pier stud
CN108424088A (en) * 2018-06-01 2018-08-21 成都交投建筑工业化有限公司 Self-compaction clear-water concrete and its construction method for bridge prefabrication pier stud
CN108999094A (en) * 2018-10-17 2018-12-14 中铁六局集团广州工程有限公司 Bridge pier conservation layer and bridge pier pier shaft insured's cloth conserve engineering method
CN209509496U (en) * 2019-01-12 2019-10-18 中国建筑第二工程局有限公司 Construction template for manufacturing seamless clear water concrete decorative column
CN110107085A (en) * 2019-05-10 2019-08-09 中铁六局集团有限公司 Superelevation fair-faced concrete column construction method
CN110093852A (en) * 2019-05-15 2019-08-06 平煤神马建工集团有限公司 Shaped form bridge pier Construction technology of fair-faced concrete
CN110107089A (en) * 2019-05-15 2019-08-09 平煤神马建工集团有限公司 Municipal works clear-water concrete casting construction method
CN110424268A (en) * 2019-07-30 2019-11-08 中铁上海工程局集团有限公司 A kind of main bridge hollow pier structure construction technique

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
付建国等: "常州地铁2号线高架区间清水混凝土墩柱施工技术探究", 《混凝土》 *

Also Published As

Publication number Publication date
CN111074754B (en) 2021-06-29

Similar Documents

Publication Publication Date Title
CN107326810B (en) The reserved grout hole connection method of precast assembly bridge pier
CN104499498B (en) A kind of construction method of mass concrete building
CN111962724A (en) Wall crack control method
CN107759170A (en) A kind of prefabricated hollow stair of light ceramsite concrete and preparation method
CN108414304A (en) A kind of mold and method made for coupled shear-flow test joint samples
CN111074754B (en) Pier column bare concrete construction method and pier column
CN105064500A (en) Balcony beam slab inner side filling wall body and main body structure integral casting construction method
CN111516096A (en) Precast column concrete pouring method in fabricated building
US11679528B2 (en) Solid waste large-mixing-amount concrete prefabricated laminated slab and preparation method thereof
CN206308899U (en) A kind of prefabricated band is floatd window wallboard
CN215630069U (en) Waterproof integrated prefabricated component for independent basement foundation
CN210507502U (en) Prefabricated assembled concrete slab bed structure
CN209456964U (en) A kind of anti-crack concrete panel
CN107268755A (en) A kind of construction method of inlet for stom water
CN209759947U (en) Assembled concrete pavement slab and pavement that permeates water
CN108409264B (en) Preparation method of L-shaped prefabricated terrazzo decorative hanging plate
CN109877946B (en) Resin layer for ceramic high-pressure grouting and manufacturing method of high-pressure grouting mold
CN203924896U (en) A kind of iron skill enclosure wall
CN1116486C (en) In-situ deposited porous reinforced concrete roof and its construction process
CN215671157U (en) Prefabricated construction of control floor thickness
CN102161581B (en) Light wall material produced on site
CN110761561A (en) Construction process of special concrete for compensating crack resistance
CN109385977A (en) A kind of anti-crack concrete panel and its construction method
CN204571286U (en) Cast-in-place bracket column concrete construction formwork
CN109732771A (en) A kind of production technology and products thereof of precast bridge plate

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant