CN202466431U - Bridge specific model vase pier construction device - Google Patents
Bridge specific model vase pier construction device Download PDFInfo
- Publication number
- CN202466431U CN202466431U CN2012201129868U CN201220112986U CN202466431U CN 202466431 U CN202466431 U CN 202466431U CN 2012201129868 U CN2012201129868 U CN 2012201129868U CN 201220112986 U CN201220112986 U CN 201220112986U CN 202466431 U CN202466431 U CN 202466431U
- Authority
- CN
- China
- Prior art keywords
- vase
- pier
- steel
- bridge
- pier construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Bridges Or Land Bridges (AREA)
Abstract
The utility model relates to a bridge specific model vase pier construction device, which belongs to the technical field of building construction. The device comprises vase pier model splicing templates; steel horizontal frames with H-shaped sections are longitudinally distributed and fixed at intervals on the periphery of the splicing template; and steel studs which are distributed in the horizontal direction at intervals are fixedly connected between adjacent horizontal frames. After the device is combined on a top surface of a constructed bearing platform, a rigid whole body with a pouring cavity is formed, and the distance from one side to the ground can be conveniently adjusted through a jack supported between the bearing platform and H-shaped steel of the horizontal frame at the bottom, so that the perpendicularity can be effectively adjusted and controlled.
Description
Technical field
The utility model relates to a kind of Bridge Pier Construction device, and the special moulding vase of especially a kind of bridge pier construction equipment belongs to technical field of building construction.
Background technology
Along with urban construction is fast-developing, the overhead road of city bridge system becomes the important way that makes up multilevel traffic.The vase pier of existing bridge beautiful design enjoys so that the lines flow smoothly to be gazed at.Though be applied to the demand attractive in appearance that viaduct can satisfy special moulding; But because the special building form of construction work of overhead road of city bridge system; Adopt the method for tradition typing punching block support to be difficult to guarantee perpendicularity deviation, therefore need innovate the construction equipment of this type of bridge pier.
Summary of the invention
The purpose of the utility model is: through architecture advances, propose a kind of special moulding vase of the bridge pier construction equipment that can effectively regulate and control verticality.
In order to reach above purpose; The special moulding vase of the bridge of the utility model pier construction equipment has vase pier moulding assembled formwork; Said assembled formwork periphery is intervally arranged up and down and is fixed with the steel horizontal pane that the cross section is a H shape, is fixed with horizontal direction steel stud spaced apart between the adjacent level frame.
Like this; The construction equipment of the utility model is after combination on ten thousand the cushion cap end face of constructing; Constitute one and have the rigid unitary of building the shape chamber; By the jack of top between cushion cap and bottom level frame H shape steel etc., can regulate the road clearance of one of which side easily, thereby effectively regulate and control its verticality.
Description of drawings
Below in conjunction with accompanying drawing the utility model is further described.
Fig. 1 is the structural representation of an embodiment of the utility model.
The specific embodiment
Embodiment one
The special moulding vase of the bridge of present embodiment pier construction equipment basic structure shown in Fig. 1, be structured on the cushion cap 1 by around after assembled formwork 2 amalgamations, constitute the up big and down small vase pier moulding in cross section.Assembled formwork 2 peripheries are intervally arranged up and down and are fixed with the steel horizontal pane 3 that the cross section is a H shape.Be fixed with horizontal direction steel stud 4 spaced apart between the neighbouring horizontal pane, have the rigid unitary of building the shape chamber thereby make this device constitute one.For further agents enhance overall rigidity, also have drag-line 7 tensions of locking nut between the opposite side of horizontal pane 3 through two ends.The ascending changeover portion in corresponding vase pier cross section also is provided with between the neighbouring horizontal pane 3 with stud 4 is connected and is connected horizontal bar 9, plays the effect of further raising integral rigidity.Before the concreting; Can prop up the jack 4 between cushion cap end face and bottom level frame H shape steel by the top; And the cable wire 8 of tractive between top drag-line 7 terminations and bottom surface 6 anchor points; Finely tune the road clearance of vase pier moulding one side easily, (this gap can with the anti-spillage of stalloy filling) thus effectively regulate and control its verticality.
Facts have proved, adopt present embodiment device safety, efficient, cost economy, help to guarantee the construction quality of viaduct vase pier.Behind the casting complete, be easy to form removal, can not damage the smooth outer profile curve of vase pier.
Claims (3)
1. the special moulding vase of bridge pier construction equipment; Has vase pier moulding assembled formwork; It is characterized in that: said assembled formwork periphery is intervally arranged up and down and is fixed with the steel horizontal pane that the cross section is a H shape, is fixed with horizontal direction steel stud spaced apart between the adjacent level frame.
2. the special moulding vase of bridge according to claim 1 pier construction equipment is characterized in that: the cable pull that has locking nut between the opposite side of said horizontal pane through two ends.
3. the special moulding vase of bridge according to claim 2 pier construction equipment is characterized in that: the changeover portion in said vase pier cross section is provided with between the adjacent level frame with stud is connected and is connected horizontal bar.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201129868U CN202466431U (en) | 2012-03-22 | 2012-03-22 | Bridge specific model vase pier construction device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012201129868U CN202466431U (en) | 2012-03-22 | 2012-03-22 | Bridge specific model vase pier construction device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN202466431U true CN202466431U (en) | 2012-10-03 |
Family
ID=46914599
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012201129868U Expired - Fee Related CN202466431U (en) | 2012-03-22 | 2012-03-22 | Bridge specific model vase pier construction device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN202466431U (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103103930A (en) * | 2013-02-01 | 2013-05-15 | 北京交通大学 | Post-added pre-stress cable strengthening method |
CN104846744A (en) * | 2015-03-19 | 2015-08-19 | 南通大学 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
CN110593104A (en) * | 2019-09-12 | 2019-12-20 | 江苏永联精筑建设集团有限公司 | Manufacturing and construction process of vase type cable tower steel formwork |
CN111041985A (en) * | 2019-11-21 | 2020-04-21 | 江苏永联精筑建设集团有限公司 | Manufacturing and construction process of vase type cable tower steel formwork |
CN113279334A (en) * | 2021-05-19 | 2021-08-20 | 安徽省路港工程有限责任公司 | Construction method of one-step pouring molding system of double-column type vase pier steel template |
-
2012
- 2012-03-22 CN CN2012201129868U patent/CN202466431U/en not_active Expired - Fee Related
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103103930A (en) * | 2013-02-01 | 2013-05-15 | 北京交通大学 | Post-added pre-stress cable strengthening method |
CN103103930B (en) * | 2013-02-01 | 2016-06-08 | 北京交通大学 | Add preliminary tension drag-line after a kind of and add solid method |
CN104846744A (en) * | 2015-03-19 | 2015-08-19 | 南通大学 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
CN104846744B (en) * | 2015-03-19 | 2017-01-11 | 南通大学 | Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode |
CN110593104A (en) * | 2019-09-12 | 2019-12-20 | 江苏永联精筑建设集团有限公司 | Manufacturing and construction process of vase type cable tower steel formwork |
CN111041985A (en) * | 2019-11-21 | 2020-04-21 | 江苏永联精筑建设集团有限公司 | Manufacturing and construction process of vase type cable tower steel formwork |
CN113279334A (en) * | 2021-05-19 | 2021-08-20 | 安徽省路港工程有限责任公司 | Construction method of one-step pouring molding system of double-column type vase pier steel template |
CN113279334B (en) * | 2021-05-19 | 2022-09-27 | 安徽省路港工程有限责任公司 | Construction method of one-step pouring molding system of double-column type vase pier steel template |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN202466431U (en) | Bridge specific model vase pier construction device | |
CN102230313B (en) | Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof | |
CN108978471B (en) | Supporting device for increasing rigidity of cable-stayed bridge special-shaped cable tower and mounting method thereof | |
CN103306208A (en) | Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier | |
CN205501791U (en) | Two recessed arch integrated configurations of steel binder - entity jib - | |
CN204282187U (en) | A kind of novel Butterfly Arch Bridge | |
CN105113388A (en) | Formwork and bracket combining structure of vase pier of viaduct and application method | |
CN103255717A (en) | Method for constructing hit-preventing wall | |
CN107905114A (en) | A kind of construction method of large span Successive interference cancellation | |
CN109024298A (en) | Construction method of bent cap | |
CN201634998U (en) | Template of pier column of bridge | |
KR20130068158A (en) | Reinforced concrete arch bridge of girder type uniting with superstructure and substructure and its automatic construction method | |
CN102367653A (en) | Support structure for large-span continuous beam construction | |
CN105568788B (en) | Rail track traffic two-wire track girder is embraced in a kind of magnetic suspension | |
CN204982681U (en) | Steel bow member integral translation device | |
CN203248170U (en) | Lining trolley for secondary lining construction of pedestrian crosswalk | |
CN204098927U (en) | Cast anchor hole or switch hole independence lining trolley in tunnel | |
CN203334190U (en) | Thin-wall hollow pillar integral elevation model turning device | |
CN205276073U (en) | Two line track roof beams of rail formula track traffic are embraced in magnetic suspension | |
CN205012217U (en) | Overpass vase mound formwork support unites structure | |
CN211815595U (en) | Lower tower column tension and compression structure for cable tower | |
CN204151663U (en) | A kind of hybrid beam is without dorsal funciculus low-pylon cable-stayed bridge | |
CN211421171U (en) | Cast-in-place utility tunnel movable support platform truck formwork system | |
CN103195449A (en) | Large-span heavy-load open cut tunnel pre-stressed reinforced concrete lining structure | |
KR100614455B1 (en) | Extradosed Bridge and it's construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20121003 Termination date: 20140322 |