CN108755441A - Variable cross-section high pier overmolded structure and construction method - Google Patents

Variable cross-section high pier overmolded structure and construction method Download PDF

Info

Publication number
CN108755441A
CN108755441A CN201810892487.7A CN201810892487A CN108755441A CN 108755441 A CN108755441 A CN 108755441A CN 201810892487 A CN201810892487 A CN 201810892487A CN 108755441 A CN108755441 A CN 108755441A
Authority
CN
China
Prior art keywords
section
concrete
stiff skeleton
exterior sheathing
pier shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201810892487.7A
Other languages
Chinese (zh)
Other versions
CN108755441B (en
Inventor
谢瑜军
杨力
徐炳
陈柯
张继业
叶玲玲
朱义福
张可琪
周勤
周一勤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Communication Engineering Construction Group Co Ltd
Original Assignee
Ningbo Communication Engineering Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Communication Engineering Construction Group Co Ltd filed Critical Ningbo Communication Engineering Construction Group Co Ltd
Priority to CN201810892487.7A priority Critical patent/CN108755441B/en
Publication of CN108755441A publication Critical patent/CN108755441A/en
Application granted granted Critical
Publication of CN108755441B publication Critical patent/CN108755441B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a kind of variable cross-section high pier overmolded structure and construction methods, are related to field of bridge construction, structure includes foundation platform, multistage inner template system, multistage exterior sheathing system, stiff skeleton etc., and is had the characteristics that:One, the pre-buried stiff skeleton of variable cross-section high pier is calculated by multigroup formula, it is contemplated that it ensure that the enough intensity of stiff skeleton, rigidity by the biggest impact of vibrating head when wind-force and casting concrete, it is ensured that safety;Two, it is to be oriented to stiff skeleton, scale is arranged in more back cord both ends horizontal top surfaces, is set to control outer vertical framework top surface installation fixing position to play the role of being accurately positioned variable cross-section slope ratio;Three, adjusting bolt is set, outer vertical framework position is adjusted flexibly, improves the precision of variable cross-section pier shaft cast-in-situ template slope ratio;Therefore, it can preferably improve the quality of variable cross-section high pier and ensure construction safety, there is resource-effective, degree of progress speed, the effect of energy-saving and emission-reduction, economic benefit and social benefit are notable.

Description

Variable cross-section high pier overmolded structure and construction method
Technical field
The present invention relates to a kind of field of bridge construction, in particular to variable cross-section high pier overmolded structures and construction method.
Background technology
Across great rivers, zanjon valley bridge high pier generally using having holder and erection without scaffolding, in recent years without Holder over-form construction technique is using more.Over-form construction is generally made of 2~4 sections of templates of every section of m of height 2m~3, is poured After pushing up section concrete, most bottom section template is turned into top section, to push up section template as support, the cast-in-place epimere pier shaft of epimere template is installed Concrete, cycle alternation turn over a liter construction.When pier shaft main reinforcement spreading, length is generally 3~4 times of one section of height, and stability is poor, Before not binding molding, the stiff skeleton of pier shaft will be embedded in as object of reference stationary positioned.Such as variable cross-section pier shaft, due to slope ratio Rate very little, construction is accurate more difficult to control, and every section of subtle deviation will form the larger cumulative errors of high pier, influence high pier Stress and good appearance.Therefore, the pre-buried stiff skeleton of variable cross-section high pier must have enough intensity, rigidity and precision, And variable cross-section pier shaft cast-in-situ template slope ratio precision adjusts flexible and convenient template system, to avoid stiff skeleton unstability, It collapses mould accident and influences the construction quality of high pier.
Invention content
The technical problem to be solved by the present invention lies in overcoming the defects of the prior art and provide a kind of adjustment of precision flexibly, Safety guarantee, reliable in quality, energy-saving and environment-friendly variable cross-section high pier overmolded structure and construction method.
The technical problem of the present invention is achieved through the following technical solutions:
The multistage of inside and outside suit is arranged on the foundation platform for a kind of variable cross-section high pier overmolded structure, including foundation platform Inner template system and multistage exterior sheathing system are equipped with stiff skeleton between multistage inner template system and multistage exterior sheathing system, The stiff skeleton, which is embedded in foundation platform by lower end and gradually extends upwardly at the top of pier shaft, makees guiding stationary positioned, passes through strength Property skeleton guide location and installation pier shaft reinforcing bar;The multistage exterior sheathing system and multistage inner template system is circulated up friendship paragraph by paragraph For overmolded casting concrete and form bridge pier shaft.
The stiff skeleton is made of shaped steel and the upper and lower tie-rod intersected in length and breadth, the shaped steel bottom of first section stiff skeleton Portion is embedded in foundation platform top, extends the height of 4~5 times of every section of exterior sheathing systems thereon, and as object of reference stationary positioned Pier shaft reinforcing bar and exterior sheathing system, inner template system.
The stiff skeleton, top section areWhen number section concreting, stiff skeleton stress mechanical model is:Exterior sheathing System and inner template system fromNumber section overmolded is extremelyNumber section casting concrete, every section of height are, it is assumed thatNumber section concrete Design strength is had reached,Number section concrete is solidifying not up to design strength requirement,Number section is high to stiff skeleton top Degree is, wind-engaging force effect, wind load intensity is, stiff skeleton withIt is elastic connection below number section concrete;Stiffness bone Frame existsIn number section concretePlace,Locate free beam on elastic foundation,The elasticity resisting coefficient of number section concrete is, Elastic resistance meets Wen Keer (Winkler) it is assumed that displacement at stiff skeleton any pointWith the drag for acting on the pointIt is directly proportional and unrelated with the drag for acting on other each points, i.e.,, stiff skeleton bending stiffness is Number section concrete is liquid,Stiff skeleton in number sectionLocating horizontal pressure force intensity isLocate horizontal pressure force Intensity is, in formulaFor the force density of concrete,For swashing for casting concrete vibrating head It shakes addition speed, concrete vibration bar is simple harmonic oscillation;When number section concreting, the exciting extra order of concrete vibration bar It moves and speed, the deflection curve equation of stiff skeleton horizontal pressure force intensity and stiff skeleton and stiff skeleton stress is by following formula It calculates:
Formula one,
Formula two,
Solve the differential equation, obtain
It enables, obtain
Solve the differential equation, obtain
Solve the differential equation, obtain
In above equation,Totally 10 undetermined constants, due toThere are continuous strips at place Part and boundary condition:
It is more than simultaneous that 10 yuan of linear function groups, obtain
Formula three,
In formula one, formula two and formula three, each symbolic significance is as follows:
--- multistage exterior sheathing system, the height of every section of multistage inner template system, i.e., the height of every section casting concrete,
--- multistage exterior sheathing system, the height of multistage inner template system uppermost top of concrete to stiff skeleton top,
--- every section of casting concrete height of over-form constructionVariable cross-section transverse horizontal in receive distance,For variable cross-section height The slope ratio of bridge pier,
--- the rigidity of unit width stiff skeleton,
--- concrete vibration bar simple harmonic oscillation displacement function,
--- concrete vibration bar simple harmonic oscillation velocity function,
--- concrete vibration bar simple harmonic oscillation speed maximum value,
--- multistage exterior sheathing system, multistage inner template system uppermost top of concrete areIt sentences up to stiff skeleton Top isThe unit width wind load intensity that place is received,
--- multistage exterior sheathing system, top unit width when multistage inner template system uppermost concrete is considered as liquid Horizontal loading intensity is exciting additional levels load intensity caused by casting concrete vibrating head,
--- multistage exterior sheathing system, bottom unit width when multistage inner template system uppermost concrete is considered as liquid Horizontal loading intensity, the horizontal lotus of the exciting additional levels load intensity caused by casting concrete vibrating head and liquid concrete Intensity superposition is carried,,
--- the force density of unit width concrete,
--- the exciting addition speed of casting concrete vibrating head,
--- the angular frequency of casting concrete vibrating head,
--- the time of vibration of casting concrete vibrating head,
--- the peak swing of casting concrete vibrating head,
--- the elasticity resisting coefficient of section concrete is poured,
--- stiff skeletonNumber section concrete isSection concrete stress line of deflection ordinate,
--- stiff skeletonNumber section concrete isDuan Shouli line of deflection ordinates,
--- stiff skeletonDuan Shouli line of deflection ordinates,
--- stiff skeletonSection abscissa,
--- unit width stiff skeleton existsUnit width elastic resistance in number section concrete,,
--- coefficient,,
--- unit width stiff skeletonIn number sectionThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeleton allows moment of flexure,
--- unit width stiff skeletonThe amount of deflection at place,
--- unit width stiff skeletonThe amount of deflection at place,
--- unit width stiff skeletonThe allowable deflection at place,
--- unit width stiff skeletonThe allowable deflection at place,
--- undetermined coefficient;
--- stiff skeleton is in wind-force and pours corresponding under section concrete horizontal pressure force acts on The i.e. corresponding amount of deflection point of horizontal displacement or position.
The multistage exterior sheathing system and multistage inner template system is steel, every section of exterior sheathing system and every section of internal model The height of plate system is 2m~3m;The bridge pier shaft is the casting concrete between outer template system and inner template system And the empty stomach pier shaft formed.
Every section of exterior sheathing system is enclosed by vertical framework outside cross form outside two panels, two panels and is formed jointly The shape of pier shaft is equipped with more back cords, more longitudinal ties and Duo Gen for fixed form in every section of exterior sheathing system A pair of of adjusting bolt is respectively arranged in the top both sides of cross-tie, every section of outer vertical framework, and adjusts the plane position of outer vertical framework Set the variable cross-section slope ratio for being allowed to meet pier shaft.
It is respectively equipped with more bolts at the top and bottom of every section of exterior sheathing system, and is mutually interconnected through the more bolts Connect upper and lower adjacent epimere exterior sheathing system and hypomere exterior sheathing system;It is respectively provided with steel on the outside of every section of exterior sheathing system Matter workbench, the diagonal brace for supporting steel workbench and the railing on the outside of steel workbench top surface.
Scale is arranged in the both ends horizontal top surface of the more back cords, and controls outer vertical framework top surface installation fixing position and set.
Every section of inner template system encloses the shape of pier shaft empty stomach, and lateral by more longitudinal ties and Duo Gen Pull rod is fixed.
It is respectively equipped with more bolts at the top and bottom of every section of inner template system, and is mutually interconnected through the more bolts Connect upper and lower adjacent epimere inner template system and hypomere inner template system.
A kind of construction method of variable cross-section high pier overmolded structure, mainly includes the following steps:
Step 1: designing and producing variable cross-section high pier overmolded structure
1. according to variable cross-section high pier design drawing, the size of stiff skeleton and template is drafted;
2. by formula one, formula two and three tentative calculation stiff skeleton of formula and exterior sheathing system stress, corresponding size is determined;
3. making stiff skeleton and exterior sheathing system, inner template system;
4. factory makes pier shaft reinforcing bar;
Step 2: pre-buried stiff skeleton
When cushion cap reinforcing bar is bound, first section stiff skeleton bottom is embedded in foundation platform top, extends outside 4~5 times every section thereon The height of template system, measuring accuracy meet the requirements;
Step 3: 3 sections of pier shaft concrete on construction foundation platform
1. connecting cushion cap embedded bar, 3 sections of pier shaft reinforcing bars that binding factory makes;
2. 1 extra template system of first section pier shaft concrete and steel workbench on installation foundation cushion cap;
3. pouring first section i.e. 1 number section pier shaft concrete on foundation platform;
5. installing No. 2 inner template systems, exterior sheathing system and steel workbench after 1 number section pier shaft concrete final set, pass through tune Save the variable cross-section slope ratio that pier shaft is accurately positioned in adjusting bolt;
6. pouring 2 number section pier shaft concrete;
7. installing No. 3 inner template systems, exterior sheathing system and steel workbench after 2 number section pier shaft concrete final set;
8. pouring 3 number section pier shaft concrete;
Step 4: 4 number section pier shaft concrete of construction
1. removing 1 number section exterior sheathing system and steel workbench after 3 number section pier shaft concrete final set;
2. No. 4 inner template systems are fixed in installation;
3. the outer cross form and steel workbench of 4 extra template systems are fixed in installation, 4 extra vertical frameworks are tentatively fixed;
4. the variable cross-section slope ratio of pier shaft is accurately positioned by adjusting adjusting bolt;
5. more than 3 number section of spreading every section of 3~4 times of exterior sheathing system length pier shaft reinforcing bars;
6. pouring 4 number section pier shaft concrete;
Step 5: 5 number section pier shaft concrete of construction
1. removing 2 number section exterior sheathing systems and steel workbench after 4 number section pier shaft concrete final set;
2. welding spreading stiff skeleton, extend the height of 4~5 times of every section of exterior sheathing systems thereon;
3. No. 5 inner template systems are fixed in installation;
4. the outer cross form and steel workbench of 5 extra template systems are fixed in installation, 5 extra vertical frameworks are tentatively fixed;
5. the variable cross-section slope ratio of pier shaft is accurately positioned by adjusting adjusting bolt;
6. pouring 5 number section pier shaft concrete;
And so on, it, will be one section most beneath after the completion of the continuous 3 sections of exterior sheathing systems of pier shaft and inner template system inner concrete pour Exterior sheathing system, inner template system and steel workbench are removed, then are installed in above most the preceding paragraph, piecewise upward overmolded The pier shaft concrete of each number section of constructing is until complete entire high pier, stiff skeleton and pier shaft reinforcing bar also corresponding piecewise spreading;It applies Exterior sheathing system, inner template system, steel workbench, stiff skeleton, pier shaft reinforcing bar and concreting are adopted during work It is lifted and is transported with tower crane, construction personnel is realized by elevator or safety climbing ladder;Reinforce construction monitoring, it is ensured that high pier is flat The slope ratio precision and stiff skeleton, reinforcing bar and concrete quality of face position and variable cross-section meet the requirements.
Compared with prior art, a kind of variable cross-section high pier overmolded structure of major design of the present invention and construction method, should Method has the characteristics that:One, it is designed by formula one, formula two and formula three and calculates the pre-buried stiffness bone of variable cross-section high pier Frame, calculation formula consider high pier stiff skeleton by the biggest impact of vibrating head when wind-force and casting concrete, ensure that strength Property skeleton enough intensity, rigidity, to avoid stiff skeleton unstability, collapse mould accident, it is ensured that safety;Two, it is with stiff skeleton It is oriented to, scale is arranged in more back cord both ends horizontal top surfaces, is set to control outer vertical framework top surface installation fixing position to play standard Determine the effect of position variable cross-section slope ratio;Three, adjusting bolt is set, outer vertical framework position is adjusted flexibly, improves variable cross-section pier The precision of body cast-in-situ template slope ratio;Through the above structure and corresponding operating method is combined, can more preferably improve variable cross-section high bridge The quality of pier and ensure construction safety, resource-effective, degree of progress speed also has the effect of energy-saving and emission-reduction, economic benefit and society Remarkable benefit.
Description of the drawings
Fig. 1 is the schematic view of facade structure of the present invention.
Fig. 2 is the left view of Fig. 1.
Fig. 3 is the vertical view of Fig. 1.
Fig. 4 is the schematic view of facade structure of overmolded structure.
Fig. 5 is the vertical view of Fig. 4.
Fig. 6 is the Force Calculation schema of stiff skeleton.
Specific implementation mode
It will again elaborate to the embodiment of the present invention by above-mentioned attached drawing below.
As shown in Fig. 1 ~ Fig. 6,1. foundation platforms, 2. pier shafts, 21. concrete, 22. empty stomaches, 3. stiff skeletons, 31. shaped steel, 32. tie-rod, 4. pier shaft reinforcing bars, 5. exterior sheathing systems, 51. outer cross forms, 52. outer vertical frameworks, 53. back cords, 54. longitudinal drawings Bar, 55. cross-ties, 56. adjusting bolts, 57. bolts, 6. inner template systems, 7. steel workbenches, 71. railings, 72. are tiltedly Support.
Variable cross-section high pier overmolded structure and construction method are related to concrete high pier in bridge and apply as shown in Fig. 1 ~ Fig. 3 Work field, structure is mainly by structures such as foundation platform 1, multistage inner template system 6, multistage exterior sheathing system 5 and stiff skeletons 3 At.
Wherein, multistage exterior sheathing system 5 and 6 system of multistage inner template are steel, are mounted in the form of inner and outer sleeves fill On foundation platform 1, and it to be used for the high pier of cast-in-situ bridge, the height of every section of exterior sheathing system 5 and every section of inner template system 6 is 2m~3m.
Every section of exterior sheathing system 5 is enclosed jointly by vertical framework 52 outside cross form outside two panels 51, two panels And the shape of pier shaft 2 is formed, it is horizontal that more back cords 53, more longitudinal ties 54 and Duo Gen are equipped in every section of exterior sheathing system 5 To pull rod 55, play the role of fixed form, the top both sides of every section of outer vertical framework 52 are respectively arranged a pair of of adjusting bolt 56, use It is allowed to meet the variable cross-section slope ratio of pier shaft 2 in the plan-position for adjusting outer vertical framework 52;The both ends horizontal of more back cords 53 Scale is arranged in top surface, is set for controlling 52 top surface installation fixing position of outer vertical framework, and variable cross-section slope ratio is accurately positioned to play Effect.
The top and bottom of every section of exterior sheathing system 5 are respectively equipped with more bolts 57, and through the more bolt phases Connect fixed and its upper and lower adjacent epimere exterior sheathing system and hypomere exterior sheathing system;Every section of exterior sheathing system 5 Outside is respectively provided with steel workbench 7, the diagonal brace 72 of bearing steel workbench 7 and on the outside of 7 top surface of steel workbench Railing 71.
Every section of inner template system 6 encloses the shape of 2 empty stomach 22 of pier shaft, and the present embodiment is to enclose rectangular sky The shape of abdomen pier shaft is also fixed by more longitudinal ties 54 and Duo Gen cross-ties 55.In every section of inner template system 6 Top and bottom are also respectively equipped with more bolts 57, and are interconnected and fixed and its upper and lower adjacent epimere through the more bolts Inner template system and hypomere inner template system.
The stiff skeleton 3 is arranged between multistage inner template system 6 and multistage exterior sheathing system 5, the stiff skeleton 3 It is made of shaped steel 31 and the upper and lower tie-rod 32 intersected in length and breadth, 31 bottom of shaped steel of first section stiff skeleton 3 is embedded in foundation platform 1 top extends the height of 4~5 times of every section of exterior sheathing systems 6 thereon, i.e., gradually extends upwardly to 2 top of pier shaft and make guiding fixation Positioning guides location and installation pier shaft reinforcing bar 4 by stiff skeleton 3.
Meanwhile pier shaft reinforcing bar 4 being installed on stiff skeleton 3, then by multistage exterior sheathing system 5 and multistage inner template system 6 It is circulated up alternately overmolded casting concrete 21 paragraph by paragraph, is formed bridge pier shaft 2;Therefore, the bridge pier shaft it is practical be exactly Casting concrete 21 between exterior sheathing system 5 and inner template system 6 and formed empty stomach pier shaft.
The stiff skeleton 3, top section areWhen number section concreting, 3 stress mechanical model of stiff skeleton is:External mold Plate system 5 and inner template system 6 fromNumber section overmolded is extremelyNumber section casting concrete 21, every section of height are, it is assumed thatNumber section Concrete has reached design strength,Number section concrete is solidifying not up to design strength requirement,Number section is to stiff skeleton 3 Tip height is, wind-engaging force effect, wind load intensity is, stiff skeleton 3 with21 or less number section concrete is that elasticity connects It connects;Stiff skeleton 3 existsIn number section concretePlace,Locate free beam on elastic foundation,The elastic resistance of number section concrete Coefficient is, elastic resistance meets Wen Keer (Winkler) it is assumed that displacement at stiff skeleton any pointWith act on the point DragIt is directly proportional and unrelated with the drag for acting on other each points, i.e.,, stiff skeleton bending stiffness isNumber section concrete is liquid,Stiff skeleton in number sectionLocating horizontal pressure force intensity isLocate water The flat intensity of pressure is, in formulaFor the force density of concrete,It is vibrated for casting concrete The exciting addition speed of stick, concrete vibration bar are simple harmonic oscillation;When number section concreting, the exciting of concrete vibration bar Additional displacement and speed, the deflection curve equation of 3 horizontal pressure force intensity of stiff skeleton and stiff skeleton and stiff skeleton stress by Following formula calculates:
Formula one,
Formula two,
Solve the differential equation, obtain
It enables, obtain
Solve the differential equation, obtain
Solve the differential equation, obtain
In above equation,Totally 10 undetermined constants, due toThere are continuous strips at place Part and boundary condition:
It is more than simultaneous that 10 yuan of linear function groups, obtain
Formula three,
In formula one, formula two and formula three, each symbolic significance is as follows:
--- multistage exterior sheathing system 5, the height of every section of multistage inner template system 6, i.e., the height of every section casting concrete 21 Degree,
--- the height that multistage exterior sheathing system 5,6 uppermost concrete of multistage inner template system, 21 top surface are pushed up to stiff skeleton 3 Degree,
--- 21 height of every section of casting concrete of over-form constructionVariable cross-section transverse horizontal in receive distance,For variable cross-section The slope ratio of high pier,
--- the rigidity of unit width stiff skeleton 3,
--- concrete vibration bar simple harmonic oscillation displacement function,
--- concrete vibration bar simple harmonic oscillation velocity function,
--- concrete vibration bar simple harmonic oscillation speed maximum value,
--- multistage exterior sheathing system 5,6 uppermost concrete of multistage inner template system, 21 top surface areIt sentences up to stiffness The top of skeleton 3 isThe unit width wind load intensity that place is received,
--- multistage exterior sheathing system 5, top unit when 6 uppermost concrete 21 of multistage inner template system is considered as liquid Width levels load intensity is exciting additional levels load intensity caused by casting concrete vibrating head,
--- multistage exterior sheathing system 5, bottom unit when 6 uppermost concrete 21 of multistage inner template system is considered as liquid Width levels load intensity, the water of exciting additional levels load intensity and liquid concrete caused by casting concrete vibrating head Flat load intensity superposition,,
--- the force density of unit width concrete 21,
--- the exciting addition speed of casting concrete vibrating head,
--- the angular frequency of casting concrete vibrating head,
--- the time of vibration of casting concrete vibrating head,
--- the peak swing of casting concrete vibrating head,
--- the elasticity resisting coefficient of section concrete is poured,
--- stiff skeletonNumber section concrete isSection concrete stress line of deflection ordinate,
--- stiff skeletonNumber section concrete isDuan Shouli line of deflection ordinates,
--- stiff skeletonDuan Shouli line of deflection ordinates,
--- stiff skeletonSection abscissa,
--- unit width stiff skeleton 3 existsUnit width elastic resistance in number section concrete 21,,
--- coefficient,,
--- unit width stiff skeletonIn number sectionThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeleton 3 allows moment of flexure,
--- unit width stiff skeletonThe amount of deflection at place,
--- unit width stiff skeletonThe amount of deflection at place,
--- unit width stiff skeletonThe allowable deflection at place,
--- unit width stiff skeletonThe allowable deflection at place,
--- undetermined coefficient;
--- stiff skeleton is in wind-force and pours corresponding under section concrete horizontal pressure force acts on The i.e. corresponding amount of deflection point of horizontal displacement or position.
In addition, the construction method of variable cross-section high pier overmolded structure, mainly includes the following steps:
Step 1: designing and producing variable cross-section high pier overmolded structure
1. according to variable cross-section high pier design drawing, the size of stiff skeleton 3 and template is drafted;
2. by formula one, formula two and three tentative calculation stiff skeleton 3 of formula and 5 stress of exterior sheathing system, corresponding size is determined;
3. making stiff skeleton 3 and exterior sheathing system 5, inner template system 6;
4. factory makes pier shaft reinforcing bar 4;
Step 2: pre-buried stiff skeleton
When cushion cap reinforcing bar is bound, 3 bottom of first section stiff skeleton is embedded in 1 top of foundation platform, extends 4~5 times every section thereon The height of exterior sheathing system 5, measuring accuracy meet the requirements;
Step 3: 3 sections of pier shaft concrete on construction foundation platform
1. connecting cushion cap embedded bar, 3 sections of pier shaft reinforcing bars 4 that binding factory makes;
2. 1 extra template system of first section pier shaft concrete and steel workbench 7 on installation foundation cushion cap 1;
3. pouring first section i.e. 1 number section pier shaft concrete on foundation platform 1;
5. installing No. 2 inner template systems 6, exterior sheathing system 5 and steel workbench 7 after 1 number section pier shaft concrete, 21 final set, lead to Overregulate the variable cross-section slope ratio that pier shaft is accurately positioned in adjusting bolt 56;
6. pouring 2 number section pier shaft concrete;
7. installing No. 3 inner template systems 5, exterior sheathing system 6 and steel workbench 7 after 2 number section pier shaft concrete final set;
8. pouring 3 number section pier shaft concrete;
Step 4: 4 number section pier shaft concrete of construction
1. removing 1 number section exterior sheathing system 5 and steel workbench 7 after 3 number section pier shaft concrete, 21 final set;
2. No. 4 inner template systems 6 are fixed in installation;
3. the outer cross form 51 and steel workbench 7 of 4 extra template systems 5 are fixed in installation, 4 extra longitudinal direction moulds are tentatively fixed Plate 52;
4. the variable cross-section slope ratio of pier shaft 2 is accurately positioned by adjusting adjusting bolt 56;
5. more than 3 number section of spreading every section of 3~4 times of exterior sheathing system length pier shaft reinforcing bars;
6. pouring 4 number section pier shaft concrete 21;
Step 5: 5 number section pier shaft concrete of construction
1. removing 2 number section exterior sheathing systems 5 and steel workbench 7 after 4 number section pier shaft concrete, 21 final set;
2. welding spreading stiff skeleton 3, extend the height of 4~5 times of every section of exterior sheathing systems thereon;
3. No. 5 inner template systems 6 are fixed in installation;
4. the outer cross form 51 and steel workbench 7 of 5 extra template systems are fixed in installation, 5 extra longitudinal direction moulds are tentatively fixed Plate 52;
5. the variable cross-section slope ratio of pier shaft 2 is accurately positioned by adjusting adjusting bolt 56;
6. pouring 5 number section pier shaft concrete 21;
And so on, it, will most bottom after the completion of 2 continuous 3 sections of exterior sheathing systems 5 of pier shaft and 6 inner concrete 21 of inner template system pour Next section of exterior sheathing system 5, inner template system 6 and steel workbench are removed, then are installed in above most the preceding paragraph, paragraph by paragraph The pier shaft concrete of upward each number section of over-form construction until complete entire high pier, stiff skeleton 3 and pier shaft reinforcing bar also accordingly by Section spreading;Work progress China and foreign countries template system 5, inner template system 6, steel workbench 7, stiff skeleton 3,4 and of pier shaft reinforcing bar Concrete 21, which pours, to be all made of tower crane lifting and transports, and construction personnel is realized by elevator or safety climbing ladder;Reinforce construction Monitoring, it is ensured that the slope ratio precision and stiff skeleton, reinforcing bar and concrete quality of high pier plan-position and variable cross-section meet It is required that.
It is of the present invention that examples are only for illustrating the present invention and not for limiting the scope of the present invention.It should additionally manage Solution, after reading the content taught by the present invention, those skilled in the art can make various modifications or changes to the present invention, this In a little equivalent forms are also fallen within the scope of the appended claims of the present application.

Claims (10)

1. a kind of variable cross-section high pier overmolded structure, including foundation platform(1), it is characterised in that it is arranged on the foundation platform The multistage inner template system of inside and outside suit(6)With multistage exterior sheathing system(7), in multistage inner template system(6)With multistage external mold Plate system(5)Between be equipped with stiff skeleton(3), which is embedded in foundation platform by lower end(1)And gradually prolong upwards Extend to pier shaft(2)Guiding stationary positioned is made at top, passes through stiff skeleton(3)Guide location and installation pier shaft reinforcing bar(4);Described is more Section exterior sheathing system(5)With multistage inner template system(6)It is circulated up alternately overmolded casting concrete paragraph by paragraph(21)And form bridge Beam pier shaft.
2. variable cross-section high pier overmolded structure according to claim 1, it is characterised in that the stiff skeleton(3)Be by Shaped steel(31)The tie-rod intersected in length and breadth above and below(32)Composition, first section stiff skeleton(3)Shaped steel(31)Bottom is embedded in basis Cushion cap(1)Top extends 4~5 times of every section of exterior sheathing systems thereon(5)Height, and as object of reference stationary positioned pier shaft steel Muscle(4)With exterior sheathing system(5), inner template system(6).
3. variable cross-section high pier overmolded structure according to claim 1, it is characterised in that the stiff skeleton(3), top Section beWhen number section concreting, stiff skeleton(3)Stress mechanical model is:Exterior sheathing system(5)With inner template system(6) FromNumber section overmolded is extremelyNumber section casting concrete(21), every section of height is, it is assumed thatIt is strong that number section concrete has reached design Degree,Number section concrete is solidifying not up to design strength requirement,Number section is to stiff skeleton(3)Tip height is, by Wind-force acts on, and wind load intensity is, stiff skeleton(3)WithNumber section concrete(21)It is elastic connection below;Stiff skeleton (3)?In number section concretePlace,Locate free beam on elastic foundation,The elasticity resisting coefficient of number section concrete is, Elastic resistance meets Wen Keer (Winkler) it is assumed that displacement at stiff skeleton any pointWith the drag for acting on the pointIt is directly proportional and unrelated with the drag for acting on other each points, i.e.,, stiff skeleton bending stiffness isNumber section concrete is liquid,Stiff skeleton in number sectionLocating horizontal pressure force intensity isThe horizontal pressure in place Power intensity is, in formulaFor the force density of concrete,For casting concrete vibrating head Exciting addition speed, concrete vibration bar are simple harmonic oscillation;When number section concreting, the exciting of concrete vibration bar is additional Displacement and speed, stiff skeleton(3)The deflection curve equation and stiff skeleton stress of horizontal pressure force intensity and stiff skeleton by with Lower formula calculates:
Formula one,
Formula two,
Solve the differential equation, obtain
It enables, obtain
Solve the differential equation, obtain
Solve the differential equation, obtain
In above equation,Totally 10 undetermined constants, due toThere are continuous strips at place Part and boundary condition:
It is more than simultaneous that 10 yuan of linear function groups, obtain
Formula three,
In formula one, formula two and formula three, each symbolic significance is as follows:
--- multistage exterior sheathing system(5), multistage inner template system(6)Every section of height, i.e. every section of casting concrete(21) Height,
--- multistage exterior sheathing system(5), multistage inner template system(6)Uppermost concrete(21)Top surface is to stiff skeleton (3)The height on top,
--- every section of casting concrete of over-form construction(21)HighlyVariable cross-section transverse horizontal in receive distance,For variable cross-section The slope ratio of high pier,
--- unit width stiff skeleton(3)Rigidity,
--- concrete vibration bar simple harmonic oscillation displacement function,
--- concrete vibration bar simple harmonic oscillation velocity function,
--- concrete vibration bar simple harmonic oscillation speed maximum value,
--- multistage exterior sheathing system(5), multistage inner template system(6)Uppermost concrete(21)Top surface isSentence up to Stiff skeleton(3)Top isThe unit width wind load intensity that place is received,
--- multistage exterior sheathing system(5), multistage inner template system(6)Uppermost concrete(21)It is considered as top when liquid Unit width horizontal loading intensity is exciting additional levels load intensity caused by casting concrete vibrating head,
--- multistage exterior sheathing system(5), multistage inner template system(6)Uppermost concrete(21)It is considered as bottom when liquid Unit width horizontal loading intensity, exciting additional levels load intensity and liquid concrete caused by casting concrete vibrating head Horizontal loading intensity superposition,,
--- unit width concrete(21)Force density,
--- the exciting addition speed of casting concrete vibrating head,
--- the angular frequency of casting concrete vibrating head,
--- the time of vibration of casting concrete vibrating head,
--- the peak swing of casting concrete vibrating head,
--- the elasticity resisting coefficient of section concrete is poured,
--- stiff skeleton(3)Number section concrete isSection concrete stress line of deflection ordinate,
--- stiff skeleton(3)Number section concrete isDuan Shouli line of deflection ordinates,
--- stiff skeleton(3)Duan Shouli line of deflection ordinates,
--- stiff skeleton(3)Section abscissa,
--- unit width stiff skeleton(3)?Number section concrete(21)In unit width elastic resistance,,
--- coefficient,,
--- unit width stiff skeletonIn number sectionThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeletonThe moment of flexure that place is received,
--- unit width stiff skeleton(3)Allow moment of flexure,
--- unit width stiff skeleton(3)The amount of deflection at place,
--- unit width stiff skeleton(3)The amount of deflection at place,
--- unit width stiff skeleton(3)The allowable deflection at place,
--- unit width stiff skeleton(3)The allowable deflection at place,
--- undetermined coefficient;
--- stiff skeleton is in wind-force and pours corresponding under section concrete horizontal pressure force acts on's The i.e. corresponding amount of deflection point of horizontal displacement or position.
4. variable cross-section high pier overmolded structure according to claim 1, it is characterised in that the multistage exterior sheathing system (5)With multistage inner template system(6)It is steel, every section of exterior sheathing system(5)With every section of inner template system(6)Height be 2m~3m;The bridge pier shaft(2)It is in outer template system(5)With inner template system(6)Between casting concrete(21)And The empty stomach pier shaft of formation.
5. variable cross-section high pier overmolded structure according to claim 4, it is characterised in that every section of exterior sheathing system (5)It is by cross form outside two panels(51), the outer vertical framework of two panels(52)It encloses jointly and forms pier shaft(2)Shape, Every section of exterior sheathing system(5)Inside it is equipped with the more back cords for fixed form(53), more longitudinal ties(54)With more cross To pull rod(55), every section of outer vertical framework(52)Top both sides a pair of of adjusting bolt is respectively set(56), and adjust outer longitudinal mould Plate(52)Plan-position be allowed to meet pier shaft(2)Variable cross-section slope ratio.
6. variable cross-section high pier overmolded structure according to claim 5, it is characterised in that every section of exterior sheathing system (5)Top and bottom be respectively equipped with more bolts(57), and it is connected with each other upper and lower adjacent epimere external mold through the more bolts Plate system and hypomere exterior sheathing system;Every section of exterior sheathing system(5)Outside is respectively provided with steel workbench(7), bearing The diagonal brace of steel workbench(72)With the railing on the outside of steel workbench top surface(71).
7. variable cross-section high pier overmolded structure according to claim 5, it is characterised in that the more back cords(53)Two It holds horizontal top surface that scale is set, and controls outer vertical framework(52)Top surface installation fixing position is set.
8. variable cross-section high pier overmolded structure according to claim 4, it is characterised in that every section of inner template system (5)The shape of pier shaft empty stomach is enclosed, and by more longitudinal ties(54)With more cross-ties(55)It is fixed.
9. variable cross-section high pier overmolded structure according to claim 8, it is characterised in that every section of inner template system (5)Top and bottom be respectively equipped with more bolts(57), and it is connected with each other upper and lower adjacent epimere internal model through the more bolts Plate system and hypomere inner template system.
10. a kind of construction method of variable cross-section high pier overmolded structure according to claim 3, it is characterised in that this method Mainly include the following steps:
Step 1: designing and producing variable cross-section high pier overmolded structure
1. according to variable cross-section high pier design drawing, stiff skeleton is drafted(3)With the size of template;
2. passing through three tentative calculation stiff skeleton of formula one, formula two and formula(3)With exterior sheathing system(5)Stress determines corresponding Size;
3. making stiff skeleton(3)With exterior sheathing system(5), inner template system(6);
4. factory makes pier shaft reinforcing bar(4);
Step 2: pre-buried stiff skeleton
When cushion cap reinforcing bar is bound, first section stiff skeleton(3)Bottom is embedded in foundation platform(1)Top extends 4~5 times thereon Every section of exterior sheathing system(5)Height, measuring accuracy meets the requirements;
Step 3: 3 sections of pier shaft concrete on construction foundation platform
1. connecting cushion cap embedded bar, 3 sections of pier shaft reinforcing bars that binding factory makes;
2. installation foundation cushion cap(1)Upper 1 extra template system of first section pier shaft concrete(5)With steel workbench(7);
3. pouring foundation platform(1)Upper first section i.e. 1 number section pier shaft concrete(21);
5. 1 number section pier shaft concrete(21)No. 2 inner template systems, exterior sheathing system and steel workbench are installed after final set(7), By adjusting adjusting bolt(56)Pier shaft is accurately positioned(2)Variable cross-section slope ratio;
6. pouring 2 number section pier shaft concrete;
7. installing No. 3 inner template systems after 2 number section pier shaft concrete final set(5), exterior sheathing system(6)With steel workbench (7);
8. pouring 3 number section pier shaft concrete(21);
Step 4: 4 number section pier shaft concrete of construction
1. 3 number section pier shaft concrete(21)1 number section exterior sheathing system is removed after final set(5)With steel workbench(7);
2. No. 4 inner template systems are fixed in installation(6);
3. 4 extra template systems are fixed in installation(5)Outer cross form(51)With steel workbench(7), tentatively fix 4 extras Vertical framework(52);
4. by adjusting adjusting bolt(56)Pier shaft is accurately positioned(2)Variable cross-section slope ratio;
5. more than 3 number section of spreading every section of 3~4 times of exterior sheathing system length pier shaft reinforcing bars;
6. pouring 4 number section pier shaft concrete(21);
Step 5: 5 number section pier shaft concrete of construction
1. waiting for 4 number section pier shaft concrete(21)2 number section exterior sheathing systems are removed after final set(5)With steel workbench(7);
2. welding spreading stiff skeleton(3), extend 4~5 times of every section of exterior sheathing systems thereon(5)Height;
3. No. 5 inner template systems are fixed in installation(6);
4. 5 extra template systems are fixed in installation(5)Outer cross form(51)With steel workbench(7), tentatively fix 5 extras Vertical framework(52);
5. by adjusting adjusting bolt(56)Pier shaft is accurately positioned(2)Variable cross-section slope ratio;
6. pouring 5 number section pier shaft concrete(21);
And so on, pier shaft(2)Continuous 3 sections of exterior sheathing systems(5)With inner template system(6)Inner concrete(21)Pour completion It afterwards, will most beneath one section of exterior sheathing system(5), inner template system(6)It removes, then is installed in most upper with steel workbench One section above, and the pier shaft concrete of each number section of upward over-form construction is until complete entire high pier, stiff skeleton paragraph by paragraph(3)And pier Body reinforcing bar also corresponding piecewise spreading;Work progress China and foreign countries template system(5), inner template system(6), steel workbench(7), strength Property skeleton(3), pier shaft reinforcing bar(4)And concrete(21)It pours and is all made of tower crane lifting and transports, construction personnel is by lifting electricity Ladder or safety climbing ladder are realized;Reinforce construction monitoring, it is ensured that the slope ratio precision and stiffness of high pier plan-position and variable cross-section Skeleton, reinforcing bar and concrete quality meet the requirements.
CN201810892487.7A 2018-08-07 2018-08-07 Variable-section high pier turning structure and construction method Active CN108755441B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810892487.7A CN108755441B (en) 2018-08-07 2018-08-07 Variable-section high pier turning structure and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810892487.7A CN108755441B (en) 2018-08-07 2018-08-07 Variable-section high pier turning structure and construction method

Publications (2)

Publication Number Publication Date
CN108755441A true CN108755441A (en) 2018-11-06
CN108755441B CN108755441B (en) 2024-03-26

Family

ID=63969257

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810892487.7A Active CN108755441B (en) 2018-08-07 2018-08-07 Variable-section high pier turning structure and construction method

Country Status (1)

Country Link
CN (1) CN108755441B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110016867A (en) * 2019-04-16 2019-07-16 中国铁建大桥工程局集团有限公司 A kind of high pier group overmolded cross construction method of variable cross-section
CN110748162A (en) * 2019-10-30 2020-02-04 中国铁建重工集团股份有限公司 Turnover device and turnover method of turnover device
CN111797449A (en) * 2020-05-28 2020-10-20 广西交科集团有限公司 Method for judging reasonable height of layered pouring concrete beam
CN115110423A (en) * 2022-06-24 2022-09-27 保利长大工程有限公司 Rectangular pier construction process
CN116702303A (en) * 2023-08-08 2023-09-05 合肥工业大学 Bridge pier skeleton curve analysis method, system and storage medium

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11256515A (en) * 1998-03-13 1999-09-21 Mitsubishi Heavy Ind Ltd Anchoring method for steel bridge pier
CN103306208A (en) * 2013-07-05 2013-09-18 中南大学 Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN103469735A (en) * 2013-09-26 2013-12-25 中南大学 Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN105887685A (en) * 2016-04-18 2016-08-24 中铁港航局集团有限公司 Railway high pier body template and scaffold integrated turnover formwork segmental construction method
CN208857703U (en) * 2018-08-07 2019-05-14 宁波交通工程建设集团有限公司 Variable cross-section high pier overmolded structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH11256515A (en) * 1998-03-13 1999-09-21 Mitsubishi Heavy Ind Ltd Anchoring method for steel bridge pier
CN103306208A (en) * 2013-07-05 2013-09-18 中南大学 Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN103469735A (en) * 2013-09-26 2013-12-25 中南大学 Method for mounting curve ultrahigh hollow column plate type pier top solid section template
CN104846744A (en) * 2015-03-19 2015-08-19 南通大学 Construction method for pouring and forming urban viaduct curve type pier stud in one-off mode
CN105887685A (en) * 2016-04-18 2016-08-24 中铁港航局集团有限公司 Railway high pier body template and scaffold integrated turnover formwork segmental construction method
CN208857703U (en) * 2018-08-07 2019-05-14 宁波交通工程建设集团有限公司 Variable cross-section high pier overmolded structure

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110016867A (en) * 2019-04-16 2019-07-16 中国铁建大桥工程局集团有限公司 A kind of high pier group overmolded cross construction method of variable cross-section
CN110748162A (en) * 2019-10-30 2020-02-04 中国铁建重工集团股份有限公司 Turnover device and turnover method of turnover device
CN110748162B (en) * 2019-10-30 2021-12-07 中国铁建重工集团股份有限公司 Turnover device and turnover method of turnover device
CN111797449A (en) * 2020-05-28 2020-10-20 广西交科集团有限公司 Method for judging reasonable height of layered pouring concrete beam
CN111797449B (en) * 2020-05-28 2021-11-02 广西交科集团有限公司 Method for judging reasonable height of layered pouring concrete beam
CN115110423A (en) * 2022-06-24 2022-09-27 保利长大工程有限公司 Rectangular pier construction process
CN116702303A (en) * 2023-08-08 2023-09-05 合肥工业大学 Bridge pier skeleton curve analysis method, system and storage medium
CN116702303B (en) * 2023-08-08 2023-09-29 合肥工业大学 Bridge pier skeleton curve analysis method, system and storage medium

Also Published As

Publication number Publication date
CN108755441B (en) 2024-03-26

Similar Documents

Publication Publication Date Title
CN108755441A (en) Variable cross-section high pier overmolded structure and construction method
CN105908777B (en) A kind of pipe gallery sliding mould and its application method
CN108004928B (en) A kind of asymmetric rigid frame-continuous girder construction technology
CN104389313B (en) The positioning and plumbing device of Two bors d's oeuveres type i iron lattice column and positioning and plumbing method thereof
CN105568870B (en) For the triangle hanging basket method cantilever device and its construction method of cross-line bridge construction
CN208857703U (en) Variable cross-section high pier overmolded structure
CN107905124B (en) A kind of symmetrical expression rigid frame-continuous girder construction technology
CN102230313A (en) Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof
CN113293694B (en) Turnover formwork frame structure for efficient pier body construction and construction process
CN103290784A (en) Arched beam combination bridge lifting construction method
CN107806019A (en) Large-span suspension bridge gate Sarasota construction method
CN109779114A (en) A kind of monoblock type folding plate combined beam
CN109098092A (en) A kind of hundred misso tower line type control of H-type and rapid constructing method
CN111455837B (en) Thin-wall hollow pier pouring connection structure and construction method thereof
CN105113539B (en) Combined multi-functional diaphram wall Core Walls Structure and its construction method in a kind of contrary sequence method
CN211472143U (en) Pier steel form
CN114717954B (en) Ultra-high concrete tower column construction method based on three-dimensional space coordinate positioning
CN205653708U (en) Work platform that inclined plane climbed follows
CN114717968A (en) Construction method for main tower of cable-stayed bridge
CN202401753U (en) Sliding die device
CN104358213A (en) Support-free and opposite pull rod combination construction method for concrete triangular rigid frame in consideration of restraint action of inclined legs
CN113605684A (en) Vortex screw lifting elevator shaft creeping formwork system and operation method thereof
CN106522569B (en) Glomeration builds prefabricated construction flooring combined type leveling unit and its leveling method
CN107326812A (en) No. 1 plate installation and positioning structure and operating method in No. 0 block of Wavelike steel webplate bridge
CN107513943A (en) A kind of continuous beam closure section traveling formwork structure and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant